ENGINEERING TECHNICAL FIELD NOTES TECHNICAL DATA RETRIEVAL INFORMATION PROFESSIONAL REPORTS MANAGEMENT DEVELOPMENT SYSTEM L 10 Stabilization of the 3 Notes Field Underwater Repair NUMBER 1 Bridge Footing Foundation 1 Bridge Footing Washington Office News FOREST SERVICE ýxFS US SFR-4 U.S. MARCH 1978 DEPARTMENT OF AGRICULTURE U4S FIELD NOTES ENGINEERING Volume Information contained in this Number 10 3 been developed for guidance of employees has respon-sibility of the United cooperating for The the that text in interpretation or names use does not in this States by other than publication an constitute its of Agriculture is official Department contractors and its assumes no its own employees. for the information and endorsement or approval of Agriculture to the exclusion suitable. publication or policy except engineers and engineering by Service Department of this information by the United or service be construed intended use The firm or corporation must not not of Agriculture-Forest and State agencies. may be the publication Department of the reader. Such product of others The Federal of trade use convenience of any States as FSM exclusively the represents recommended references. personal opinions or approved of the respective procedures Because of the type of material technicians should read each issue FOREST SERVICE DEPARTMENT OF AGRICULTURE Washington D.C. 20013 in however for engineers. U.S. mandatory author and instructions the publication this publication all is UNDERWATER REPAIR OF BRIDGE Lyle Lallwn Structural Engineer FOOTING Duane Yager Structural Engineer Region 1 The Bungalow Idaho. Bridge spans the North Fork of the Clearwater River in northern is located approximately 75 air miles 121 km west of Missoula It Montana on Clearwater National Forest which Office at Orofino Idaho. the Supervisors is managed through the The bridge consists of a 39-foot 11.89-meter simple span and a 80.5-foot and 80-foot 24.5 34.1 and 23.4 meter 112-foot three-span continuous The superstructure is composed of a concrete deck 28 feet 8.5 unit. meters wide supported by constant-depth riveted steel plate girders on continuous unit and by steel wide-flange beams on the simple span. The substructure is composed of two-column concrete end bents founded on and piers consisting of solid reinforced concrete shafts spread footings with reinforced concrete footing resting on plain concrete seals. the Pier No. is located 2 meter continuous 6.9 meters high on 9 x 32 9 x 35 x x 4 2.7 2.7 x foot foot 5 between the 80.5-foot 24.5 meter and concrete pier shaft The reinforced spans. x 28 feet 8.5 meters x 9.8 10.7 x x x 3.5 in a westerly direction the river flows approximately 5 to 12 feet 1.5 to 3.7 meters of the footing seal. and northern edges site is 22.5 1.1 meters meter reinforced footing meter plain concrete seal. 1.2 1.5 feet 112-foot 34.1 feet and rests sitting on At this a with normal water depth of the respective southern along Visual observation by Forest Service Engineering personnel during the indicated the possibility of scour problems around Pier No. summer of 1974 2 of the bridge. Scour around and under pier footings has long been a In this case the Region 1 Transportation worldwide problem for engineers. Structures Group was contacted Engineering personnel with scuba diving the footing and severe scour was noted under the gear were sent to inspect footing seal. The underwater inspection revealed scour depths of 2 to 2.5 feet 0.61 to 0.76 meters along the eastern end of the plain concrete seal. Along most of the 35-foot 10.7 meter length the northern edge of the seal had scour which varied from 2 to 3 feet 0.61 to 0.91 meters deep and extended as The western end was undermined far as 5 feet 1.5 meters under the seal. from 0 seal showed to 2 feet 0 to 0.61 little or no meters deep. scour. 1 The remaining south side of the Three alternatives were considered Repair of Pier No. 2 at estimated cost an Replacement of Pier No. at 2 an of $90000 estimated cost of $200000 and environ-mental Complete bridge replacement at an estimated cost The first the $400000. alternative was chosen because it would result in less quicker repair even though all repair work had to be done under water and there was more risk involved. impact to of pier less cost and A contract was advertised for sandblasting and painting portions of the as well as repairing the pier footing and was awarded to superstructure William Cummings of Orofino Idaho. Forest Service personnel involved were J.M. White Contracting Officer Neal Flowers Contracting Officers and Representative The section of the Lyle Lallum Inspector. contract called for construction of footing repair a perimeter from 3 to 5 feet 0.91 to seal. of the existing The contractor loose material from within the boundaries of for eleva-tion con-struction access 1.52 dikes and a cofferdam with meters outside the perimeter was then required to pump the the cofferdam to bedrock and fill in that space with concrete to an Because of the fisheries in even with the top of the existing seal. the river stream turbidity at a point 150 feet downstream from the site was limited to an increase of 20 Jackson Turbidity Units and the work had to be performed between July 15 and September 15 1976. the contractor proposed to perform the pier repair In lieu of a cofferdam work through an alternate solution employing bagged grout which he called The work was to be bagpipe groutainer forms that proposal was accepted. main office is in Turzillo whose a subcontractor Corporation performed by Ohio. Brecksville method of repair though unknown to Region 1 engineering personnel had been used successfully by the subcontractor on similar contracts in the The bagpipe groutainer forms are bags cut and sewn Midwest and Canada. A small hole is left in one at the site. from a roll of cotton-like fabric The to fill it with grout. end of each bag where a nozzle is inserted in much the and filled with to form a in grout wall are placed layers bags This same way that a mason uses stones to form Standard Methods a wall. joint for the Examination of Water and Wastewater the American Water American Public Health Association publication Latest and the Water Pollution Control Federation. Works Association of the edition. 2 The proposed method required two divers for underwater work and a dryland crew consisting of two diver helpers and three laborers plus a foreman and a superintendent. A barge was used to store the divers equipment and as a work platform for the divers helpers fig. 1. The work consisted of Excavation Placement loose material from of of the The pumping of Figure bagged the 1. grout cavity under around and under the footing and the footing seal Barge used as work platform full of grout. for divers. The excavating consisted of removing all loose material.from the streambed in the area under the footing seal and within the proposed perimeter of the bagged grout fig 2. Material up to 6 inches 15 cm in diameter was removed by using airlifts handled by the divers. Airlifts are metal tubes from 4 10 to inches to 25 in diameter that move varying 10 cm material by compressed air forced through them creating a suction at the The clear granular nature of the material involved made it possible bottom. to deposit this material in the riverbed without exceeding the contract turbidity requirements. Material larger than 6 inches 15 cm was either moved by hand or by a backhoe operating from the bridge deck. The backhoe 3 Existing Concrete Seal Bedrock Groutainer bags Bagged _ý Grout - 1 ELEVATION Pumped Grout Leveling Course Groutainer bags Bagged Grout Typ. ji Pumped Grout Leveling Course Typ. Bagged Grout / o Footing Bearing Area Existing Concrete ý\ Seal PLAN Figure 2. Plan for excavation. 4 - - 1 used cables attached to the area. boom to pull log debris away from the footing The groutainer bags were placed on the bedrock and filled with grout. Depending on the roughness of the bedrock surface bag lengths varied from 3 to 20 feet 0.9 to 5.1 meters. A horizontal plane was formed by the bottom layer of bags upon which more layers of groutainer bags could be In areas where scour readily placed. were the largest it was depths necessary to place three groutainer bags side by side on the bedrock in order to establish a base wide enough for the gravity wall form. layers were stepped in until only one bag was required when the top of the wall was reached. The bottom layer of groutainer bags was doweled 18 inches 45.7 cm into bedrock with reinforcing bar dowels at 2 feet The second 0.61 meter centers. and third layers were doweled at 3 feet 0.91 meter centers into next lower layers. Additional layers were doweled at 4 feet 1.2 meter centers into next lower layer. Succeed-ing 6 addition repairing the scour area under the existing seal a nose on pier footing was constructed that began at the corners of the existing seal and extended about 12 feet 3.66 meters upstream from the seal to reduce flow turbulence in the footing area during future high-water periods. In to the The size the of the cavity possibility of resulting from the excavation caused concern about to excessive loss of collapsing it was decided to divide the bearing area under the footing. Therefore Each part was excavated cavity into six parts. a bag wall built and the and full of grout before proceeding to the next part bags cavity pumped as each layer of bags was completed. The top layer of bags was fig. form so as to a between the wall and concrete sill. placed lip existing were inserted into the silled the wall before the last Pipes cavity through of was The used to allow the water layer bags placed. pipes were trapped to escape as the cavity formed the wall and bottom of sill by existing was filled with grout fig. 4. the pier shifting due or 3 The grout was composed of cement sand and an additive called Interaid which acted as a pumping lubricant. The grout was mixed by an air-operated mixer in 6 cubic-foot 0.17 cubic meter batches absolute volume and 1-1/2-inch 3.8 diameter hoses to the area. cm footing pumped through ft. The mix consisted of 3 II 7 cu. design bags Type cement fig. 5. consis-tently kilo-pascals 0.2 meter of sand 2 pounds 10 ounces 1.2 kg Test cubes taken from gallons 60.6 liters of water. cubic showed compressive strengths in excess of 3500 of the psi Interaid and 1.6 grout 24131 practi-cal for 7-day and 7000 psi 48263 kilopascals for 28-day tests. contract time involved in the footing repair was 25 working days. Engineering personnel engaged in this project agreed that it was a of A cost savings and efficient method of repairing scoured footings. for the 7 of the contract repair about original price footing percent It is thought portion of the contract was realized by using this method. The total 5 further savings could have been realized had the designers known procedure prior to writing and advertising the contract. There was only one bid received on this project from a local contractor not The actual underwater work was experienced in this type of work. that about a this subcon-tracted. One Figure 3. Zayer of grout bags and grout was pumped into this portion of the area under the footing. The advantages as of using the groutainer method in lieu of a cofferdam were by divers follows. The condition of all of the There was less The method The scour of the the foundation could be checked during repair operation. environmental damage caused by sedimentation. was more economical. area could pier be repaired in parts shifting. 6 reducing the possibility Pipe Pumped Grout Bagged Grout Bagged Grout Bedrock Bedrock Pumped Grout PHASE PHASE I 11 Groutainer 4 Existing Concrete Seal Bedrock Pumped Grout TYPICAL CROSS SECTION Figure 4. Placement of bags to form a Zip between wall and existing concrete sill. 7 bags Bagged Grout Typ. the Figure 5. Grout mixers and pump 8 operated by an air compressor. STABILIZATION OF THE FOUNDATION FOR BRIDGE FOOTING Duane Yager Structural Engineer Region 1 The Sun located River Bridge 24 miles 39 1965 after .fee 2.4 is a three-span prestress concrete girder bridge km west of Augusta Montana. The bridge was built flood in the area. The original footing was placed 8 major below the a m in ground line. of 1975 before high water the footing of Pier No. 1 was partially undermined. Emergency repairs were made to protect the footing during spring runoff but a near record runoff occurred in June. The riprap placed around the footing was eroded with scouring The pier settled about 1 inch 2.5 cm on the upstream beneath the footing. 2 inches end and over 5 cm on the downstream end. This differential in the columns settlement caused cracks and a bearing assembly breakage corner of the cap to break off. The amount of movement could not be tolerated in a bridge designed as a simple span structure. In the found spring to be experi-ence en-larging The objective was to stabilize the pier in its existing and to position and cap. Based on previous repair the bearing assemblies columns with grouting it was decided to stabilize the pier by pumping grout into the native foundation material forming a consolidated mass 20 feet wide by 39 the feet long by 10 feet deep existing concrete footing. 6.1 x 11.9 x 3.0 meters and A contract for the repairs was awarded to LeeTurzello Contracting Co. and The area is subject work began on December 15. to severe winter weather in to -35F conditions temperatures can vary between 50F. Enclosures Fig. 1 24 hours and 50 mph 80 kmh winds are not uncommon. 10C -37C were built to protect the workers and this precaution was justified of the work. all the conditions described occurred during conduct as 1.9 cm steel pipes vertically The first operation was to drive 3/4-inch outside of the existing footings. The pipes were 3 feet at about 0.91 5 feet 0.91 to centers and were driven 3 to placed on 4-foot 1.2 material. these 1.52 into the native Grout was pumped through pipes the top This procedure sealed until it surfaced see Figures 2 3 and 4. steel used to the and A star drill was core through grout casing area. The steel pipes were then driven inside the was driven in the holes. m m m 9 Figure 1 Figure Enclosure built for men to work. 2 Grout pump 10 and water heater. Figure Pumping 3. grout through r 3/4-inch steel f ýyav. f S. 1F 5a ýý 1. ýý pipes. % t . tt Figure 4. Grout was pumped until it came 11 to surface. m pres-sure casing to a depth of 10 feet 3.05 and grout was pumped to complete the consolidation of a mass 20 x 39 x 10 feet 6.1 x 11.9 x 3.0 in width About 80 cubic length and depth. yards 61.2 cubic meters of grout were used. the final pumping operations Special care was necessary during directly under the existing footing because a small amount of grout could have raised the entire pier. The grout mixture pumped into the 0 to 1 bag Interaid bags cement 2 3 cu. native material was as follows 0-0.085 cu ft. 2 12 gallons 45.4 The amount of sand used varied the native material. m lb 5 liters depending oz meters 1.05 kg sand water on the amount of fines present in dis-tance The last step of the repairs was to encase the existing footing of the pier with concrete. The original contract specified standard cast-in-place reinforced concrete. Because of the freezing temperature and the long to any concrete plant the contractor requested and was allowed to use Preplaced Aggregate Concrete PAC Fig. 5. PAC consists of preplacing to 1-1/2-inch 1.3 to 3.8 coarse aggregate of 1/2shown in Figure as and then sand-cement into the to form concrete 6 pumping grout aggregate The of the made from 7. PAC Fig. compressive strength cylinders ranged cm 5200 between psi to 5590 psi 35852 to 38541 kilopascals at 28 days. One problem with PAC is that the forms must be watertight or the grout and will not fill all the voids. starts at the bottom Pumping proceeds to the top Fig. 8. It took 12 hours to pump grout to form 48 cubic yards The top of PAC was finished by striking the top 36.7 cu. meters of PAC. found when surface similar to cast-in-place concrete. few voids were Very consoli-dating the were stripped. forms the project was $50000 but the results achieved by native material with pumped grout and using PAC to enlarge the footing will provide a satisfactory and long-lasting product Fig. 9. The cost of the pier 12 Figure Reinforcing steel 5. placed foz PAC footing. Sul La tlxuýý 3 L 6t tai ýý Eý ý Figure 6. tr six a ý v Placing 1 coarse aggregate in 13 the footing. Figure Figure 8. 7. Pumping grout into the coarse aggregate. Final pumping of grout to eliminate air pockets. 14 Figure 9 Finished product. 15 WASHINGTON OFFICE NEWS TECHNOLOGICAL IMPROVEMENTS Heyward T. Taylor Assistant Director con-cise REGIONAL PARTICIPATION IN EDT PROGRAM The program development work it well underway for the FY 1979 EDT effort. As in most years there are more proposals than there are dollars available to fund them. This makes the final selection rather complex. A good thorough problem definition is the first step toward selection of The proposals submitted by the Regions this year were projects funding. in to Not only were they generally outstanding regard problem definition. well written but there were many more proposals to be considered. but for Currently there are 10 projects being funded which are a direct result of Of course there proposals submitted by the Regions. are many problems which went from field personnel to Centers or to the Washington Office to be included as part of the overall program. The 10 proposals referred to were submitted as a direct result of Regional EDT effort. They were initiated at the District or Forest level and sent through the Regional EDT Board. Through this same route a number of local or Regional problems have been identified and approved for work as Regional EDT projects. Dis-tricts. 3 8 and 9 have been particularly active in this regard in the Regions 1 5 last few years. Proposals have been solicited from the Forests and All these proposals have been reviewed at an annual Regional Board meeting and some have ultimately been approved as Service-wide projects. consider-ation. all proposals regardless of their sources cannot be funded. one that comes to the Washington Office is put into a standard However format placed in the proposal book Blue Book and given equal Sometimes it may take a year or two for a proposal to reach high to be included in the funded priority program. enough Unfortunately each We We encourage all Regions to continue active participation in this program. need to surface problems and needs of the resource managers at the field level. Washington Office EDT Board meets to review activities of the program status as well as to take up necessary business topics. of the EDT program we met In order to give this group a better perspective last year at the Equipment Development Center in San Dimas California. Continuing this concept this year we are meeting at the Center in Missoula Annually the Centers and 16 Montana April 11-13. This provides an opportunity for all attendees to facilities inspect ongoing work and interface directly with the respective Center employees. At this meeting we will be discussing project status at each Center and reviewing on-the-ground work that is underway at visit the MEDC. 17 CONSULTATION AND STANDARDS Walter E. Furen Assistant Director ROADS AND SYNTHETIC FABRICS material for use in road Synthetic fabrics have become a very important construction. A significant opportunity exists to use these fabrics because and compare they function as an efficient filter provide tensile strength Substantial favorably with graded aggregate filters from a cost standpoint. reductions of siltation at a reasonable cost may be achieved by the use of synthetic fabrics in a variety of drainage and streamside installations. Forest Service Engineering personnel and others were recently asked questions in an attempt to determine the state-of-the-art of fabric Forest Service applications 1. 2. these use on How.extensive is the Forest Service use of synthetic fabrics Who is doing the engineering work on Forest Service fabric projects 3. 4. What What The answers to technical information is available on the subject research and development work is presently underway these questions indicated that 1. All regions have some experience in design and using synthetic fabrics. 2. Woven construction fabrics used for filtration in underdrains is the most Many have been installed during the last common application. 2 3. 4. 5. or 3 years. Fabrics have been installed or planned on Forest projects in six Regions. for subgrade restraint Fabrics have been installed or planned on Forest projects in four Regions. for material separation Fabrics have been and strengthening projects in four installed or planned for lagoon liners earth soil retention on log bridge decks on Forest Regions. 18 6. The design of underdrain and 7. systems are Regional Office materials or design sections fabric applications. nearly all other synthetic FHWA The Federal Highway Administration package on the use of synthetic fabrics package will contain 1. 2. 3. 4. is divided between Forests Regional Offices. in is preparing an for highway Highway Focus May 1977 Vol. 9 is devoted entirely to synthetic involved No. 1 implementation The construction. FHWA publication which fabrics. Guidelines for Use of Fabrics in Construction and Maintenance R-6. of Low-Volume Roads USDA Forest Service Synthesis of nationwide fabric-related used by several roadbuilding agencies. specifications presently Current information concerning the activities of the FHWA and the the American Society for Testing Materials American Association of State Highway and Transportation Officials AASHTO relative to this subject. The package ASTM should be distributed in early spring 1978. The FHWA is also considering the production of an instructional would portray the state-of-the-art of synthetic fabric use. movie which synthe-tic Literature Available Vis-cher A substantial number of articles have been written on the subject of A list of the pertinent ones for Forest fabrics for road construction. Service Engineers is shown below Use W. of Synthetic Fabrics on Muskeg Subgrades in Road Construction .22-pag paper plus USDA Forest Service R-10 November 1975. design examples. Highway Focus US Dept Transp FHWA May 1977 Vol. articles on the use and specifications of synthetic 9 No. 1. Eight fabrics. of Fabrics in Construction and Maintenance of Tow-Volume Forest Service R-6 and J. Mohney USDA Roads J. Steward R. Williamson U.S. Department of June 1977. This will also be available through and state-of-the-art Comprehensive Implementation Division. Guidelines for Use Trans-portation design guide. lg The Use of Fabrics in Forest Service Road Construction A. Pelzner and Forest Service October 1977. 33-page presentation for the AASHTO meeting at Atlantic City N.J. This paper is basically a distillation of the above Guideline paper. It will be published by AASHTO. J. Steward USDA Nonwoven Fabric Is Finding Increased Use in Stabilizing Logging Forest Industries November 1977 Vol. 104 No. 12. article on fabric use for subgrade restraint. Blackman. Research and Roads Ted 4-page Development Work There is extensive activity underway by road agencies fabric manufacturers and the academic community to answer some of the questions about fabrics. Some of these activities are 1. FHWA has develop a research contract with Oregon State University characteristics and specifications. strength 2. ASTM Committee D-18 and D-13 are working to develop specifications for various highway uses. 3. Corps 4. Several Forest Service Regions have trail-use projects some are instrumented and are being monitored. of Engineers Waterways revised specifications. Synthetic fabrics provide structural problems. tests to and Experiment Station is working on a promising new option for forest road underway drainage and Forest Service Engineers are involved in numerous and varied synthetic projects and are assuming a leadership role in this new technology. fabric Divi-sion MORE ON REINFORCED EARTH The July 1977 edition of the Journal of the GeotechnicaZ Engineering walls. Engineers who ASCE carries two papers on Reinforced Earth are involved in design or construction of RE will find them informative and The references are interesting. RE Jerry C. and Raymond Vol. Reinforced Earth Wall. Chang Jerry C. and Raymond Vol. Reinforced Earth Wall. Chang A. Forsyth. 103 A. No. GT7 Forsyth. 103 No. GT7 20 Design and Field Behavior of 677-692. Proc. Paper 13034 p. Finite Element Proc. Analysis of Paper 13035 p. 711-724. DEVELOPMENT REMOTE-SENSING PALLET OF A SYSTEM Frederick P. HIGH-ALTITUDE FOR FORESTRY APPLICATIONS Weber Manager Forestry Applications Program high-altitude The Nationwide Forestry Applications NFA Program scientists B. Johnson Space Center Houston Texas are working with the Systems Division to develop a Universal Pallet System for the aircraft Fig. 1 for use on forestry reconnaissance at Lyndon Experiment the NASA WB57F applications studies. During the last 18 months the NFA Program has participated in cooperative remote sensing technology assistance projects in Regions 1 6 and 10 with and the Geometronics the Methods Applications Group FIDM Davis California has been oriented The focus of these studies WO. Development Unit toward. phototechnology development applied to timber management inventory and Our objective has been to determine the forest pest management problems. effectiveness of utilizing various formats of high resolution 85-120 cost E L/mm reconnaissance photography on select applications problems. The remotely-sensed data collected--primarily photography--have been obtained with the Lockheed U-2 aircraft flying from the NASA-Ames Research Center at and the General Dynamics WB57F deployed California Moffett Field Sunnyvale Both from the NASA-Johnson Space Center at Ellington AFB Houston Texas. The U-2 is feet AMSL. aircraft are capable of sustained flight at 65000 aloft at a time generally restricted to carrying one remote-sensing system the Actron HR732 e.g. the ITEK KA80A optical bar panoramic camera or This generally has caused large-format camera but not both simultaneously. for the problems in developing an objective experimental design phototech-nology development studies. For has a large payload for carrying experimental systems aloft. in be carried of 3-foot and 6-foot can pallets example various combinations total a of 15 feet. Theoretically the bomb bay area up to a total length is attainable. gross weight pallet capability of 5000 pounds The WB57F high-altitude con-currently The NFA Program has indicated our support to NASA in developing a reconnaissance capability for the WB57F which can explore a number of technology assessment and development opportunities. requirements are specified as follows Our Forest Service sensor 21 RB57Fo 22 NASA 1a Figure Always Flown - 5 Panoramic Camera film format 24-30 inch focal length lens system 9O FOV and 200 L/mm or better resolving stereo-convergent 1.61 power of T.O.C. mode - and focal or mission dependent Large Format Camera lens 1.61 system and 100 9 x 9 x L/mm 18 format 24-inch focal length or better resolving power of T.O.C. target. Frame Metric Camera length lens - 5 Camera 5. x frame format 24-30 length lens system and 150-200 L/mm or better resolving power of T.O.C. 1.61 target. Frame Reconnaissance inch - Some applications require require stereo-mono mode. target. some 9 format 6-inch system mission dependent or 12-inch focal AMPS with six high resolution Multispectral Camera System camera stations on 70mm - spectrally calibrated-format. Ideally our choice for film loading would be CS-l S0242 CS-2 S0131 CS-3 2443 Selectively CS-4 CS-5 CS-6 3414 no 3414 w/25A filter w/12 filter 3414 filter Flown - Landsat C - Landsat D multispectral - Synthetic Aperture Imaging Radar dual polarized X or C-band SLAR multispectral scanner scanner RS18 modified NSOOIMS APQ 102b-modified An example of how the WB57F forestry pallet could be applied is given in the This NFA Program case of the current Northern California Test Project. cooperative technology assistance project with R-5 MAG and GDU deals with the assessment of drought impact on current mortality rate of trees in While the specific technical objectives are many and Northern California. varied the overall goal is to determine the comparative efficiencies of several remote sensing approaches in a quasi-production environment for addressing several complex FIDM problems related to pest surveys and implementation of Pest Management action. A high priority objective is to answer questions related to the total efficiency of utilizing optical bar camera technology versus a somewhat more conventional large Answers obtained in the Northern California Test format camera technology. evalu-ations 23 Project will be considered in specifying applied this coming summer for statewide remote sensing in Montana surveys the technology to be South Dakota. and current target is to have the WB57F pallet completed with installation Apollo pan camera for applications testing on the Tongass National Forest this summer. The primary mission requirement is to test imaging radar for topographic mapping on Prince of Wales Island but we Our of the OB high-resolution also plan to deploy the high-resolution panoramic camera the KA96A frame reconnaissance camera and the Landsat C multispectral scanner. A progress report of WB57F forestry pallet issues. 24 project will be given in later TO READERS OF FIELD NOTES INVITATION Every reader a is author potential you would of an article for Field Notes. If we you have news item or a accu-rate short article publication Material Field in to share with like Service engineers to send you invite it for Notes. to submitted the Office Washington for be reviewed should publication by the Washing-ton respective short articles Office and white Notes is list ask number Each items are preferred. to 7113. The length of pages typewritten several submitted to the material All be should illustrations all FSM sentences drawings original or and Forest Manager your Office sent to your Office directly Service retirees. or the office. Regional If to are Information Copies of back issues Regional all you are not Station currently and on the Coordinator to increase also available from the Office. Region questions short timely technically current Service-wide engineers several is photos. Forests of copies Washington or news information distributed from the Washington Area Headquarters the to from the be typed double-spaced should black mailing interest submitted may vary however Field to see that and of informative material glossy Office Regional has an Information and material for Coordinator The publication. whom to Coordinators R-1 Melvin R-4 Ted Wood R-2 Royal M. Ryser R-5 Jim R-3 Juan R-6 Kjell R-8 Bob Bowers Coordinators Dittmer Gomez should direct questions field McCoy Bakke concerning personnel submit both should are R-9 Fred Hintsala R-10 F. WO format editing W. Baxandall Al Colley publishing dates and other problems to USDA Forest Engineering Service Staff Attn Gordon P.O. Box 2417 Washington Telephone L. D.C. Rm. 1108 RP-E Rome or Rita E. Wright 20013 Area Code 703-235-8198 U.S. GOVERNMENT PRINTING OFFICE 1978 0-261-474/FS