Document 11422005

advertisement
Published by:
RSSB
© Copyright 2015
Rail Safety and Standards Board Limited
RIS-1710-PLT
This document contains one or more pages which contain colour.
Issue One: December 2015
Rail Industry Standard
RIS
Rail Industry Standard for Engineering Certification of Railborne Plant
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Issue record
Issue
Date
Comments
One
December 2015
Original document
Requirements for assessment process
for railborne plant, amended from
previously published Engineering
Acceptance in RIS-1530-PLT.
Superseded or replaced documents
The following Rail Industry Standard is superseded or replaced, either in whole or in part
as indicated:
RIS-1530-PLT issue five Rail Industry Standard
for Engineering Acceptance of On-Track Plant
and Associated Equipment
Part 3
05 December 2015
RIS-1530-PLT issue five Rail Industry Standard for Engineering Acceptance of On-Track
Plant and Associated Equipment, ceases to be in force and is withdrawn as of
05 December 2015.
Supply
The authoritative version of this document is available at www.rssb.co.uk/railway-groupstandards. Enquiries on this document can be forwarded to enquirydesk@rssb.co.uk.
Page 2 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Contents
Section
Description
Part 1
1.1
1.2
1.3
1.4
1.5
1.6
Introduction
Purpose of this document
Application of this document
Health and safety responsibilities
The structure of this document
Copyright
Approval and authorisation of this document
4
4
4
4
4
4
4
Part 2
2.1
2.2
2.3
Document Specific Information
Scope of this document
Relevant legislation
Definitions
5
5
5
6
Part 3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
Engineering Conformance
How engineering conformance relates to product acceptance
General requirement for engineering assessment process
Engineering Conformance Certificate
Assessment process
Limitations on the Engineering Conformance Certificate
Requirements for Engineering Conformance Certificate
Vehicle number for OTP and OTM
Modifications
Innovative solutions
Accreditation of PABs
8
8
10
10
12
15
15
16
17
18
19
Appendices
Appendix A Engineering Conformance Certificate for OTM
20
References
23
Figures
Figure 1
Figure 2
RSSB
Page
Plant approval process
Example of date label
8
12
Page 3 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Part 1
Introduction
1.1
Purpose of this document
1.1.1
This document is a standard on the engineering certification process for items of railborne
plant, for members of RSSB to use if they so choose.
1.1.2
This document provides a voluntary standard on engineering assessment of railborne plant
and associated equipment for use on any rail network, for the rail industry to use.
1.2
Application of this document
1.2.1
A member of RSSB may choose to adopt all or part of this document through internal
procedures or contract conditions. Where this is the case the member of RSSB will specify
the nature and extent of application.
1.2.2
Compliance requirements and dates have not been specified since these will be the
subject of internal procedures or contract conditions.
1.3
Health and safety responsibilities
1.3.1
Users of documents published by RSSB are reminded of the need to consider their own
responsibilities to ensure health and safety at work and their own duties under health and
safety legislation. RSSB does not warrant that compliance with all or any documents
published by RSSB is sufficient in itself to ensure safe systems of work or operation or to
satisfy such responsibilities or duties.
1.4
The structure of this document
1.4.1
This document is set out as a series of requirements, in some cases followed by relevant
guidance. The guidance is indicated by prefixing the paragraph number with the letter ‘G’.
1.5
Copyright
1.5.1
Copyright in the Railway Group documents is owned by Rail Safety and Standards Board
Limited. All rights are hereby reserved. No Railway Group document (in whole or in part)
may be reproduced, stored in a retrieval system, or transmitted, in any form or means,
without the prior written permission of Rail Safety and Standards Board Limited, or as
expressly permitted by law.
1.5.2
RSSB members are granted copyright licence in accordance with the Constitution
Agreement relating to Rail Safety and Standards Board Limited.
1.5.3
In circumstances where Rail Safety and Standards Board Limited has granted a particular
person or organisation permission to copy extracts from Railway Group documents, Rail
Safety and Standards Board Limited accepts no responsibility for, nor any liability in
connection with, the use of such extracts, or any claims arising therefrom. This disclaimer
applies to all forms of media in which extracts from Railway Group documents may be
reproduced.
1.6
Approval and authorisation of this document
1.6.1
The content of this document was approved by PLT Standards Committee on 15 October
2015.
1.6.2
This document was authorised by RSSB on 28 October 2015.
Page 4 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Part 2
Document Specific Information
2.1
Scope of this document
2.1.1
This document applies to all On-track Plant (OTP) and trolleys that are in use, or to be
used, on GB railway.
2.1.2
This document applies to all On-track Machines (OTM) in travelling and working modes
and to OTM in running mode for use on railways which are not in scope of the
Interoperability Directive.
2.1.3
G 2.1.2.1
Railway infrastructure not part of the Interoperability Directive is declared by
the Department for Transport in GB and by the Member State in other
European countries.
G 2.1.2.2
Assessment of new OTM in running mode and modifications for existing
OTM in running mode will be carried out in accordance with the
requirements of the Interoperability Directive and associated TSIs and the
Safety Management System of the railway undertaking concerned.
The clauses in this document contain requirements that relate to, and could be mandated
by any infrastructure manager to be complied with by, the following industry parties:
a)
Manufacturers of railborne plant.
b)
Plant assessment bodies (PABs).
c)
Asset Managers of railborne plant.
d)
Operators of railborne plant.
e)
Maintainers of railborne plant.
2.2
Relevant legislation
2.2.1
Compliance with legislation is a statutory requirement and outside the scope of this
standard. However, for information, regulations of particular relevance to this standard are:
RSSB
a)
Supply of Machinery (Safety) Regulations 2008 – as amended by the Supply of
Machinery (Safety) (Amendment) Regulations 2011.
b)
Provision and Use of Work Equipment Regulations1998.
c)
Railways (Interoperability) Regulations 2011.
d)
All other relevant legislation such as Lifting Operations and Lifting Equipment
Regulations 1998.
Page 5 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
2.3
Definitions
Asset Manager
For the purposes of this document the steward of an item of railborne plant is the entity that
controls the use of the item of railborne plant.
Demountable Machine
Formerly known as Rail Mounted Maintenance Machine (RMMM) and is a railborne plant
that can travel on rail under its own power system. Such railborne plant are not allowed to
run, work, travel or operate outside possessions. Rail in this definition refers to permanent
rails intended for use by normal rail vehicles.
Engineering assessment
The process whereby conformance of railborne plant to the mandatory requirements is
confirmed and certificated.
Engineering Conformance Certificate (ECC)
For the purpose of this document, a certificate issued by a Plant assessment body
confirming conformance of the design and construction of railborne plant and associated
equipment, and its maintenance plan, with all relevant mandatory requirements of the
standards set out in 3.1.4.
Instruction handbook
Text, drawing and pictorial information for an individual railborne plant as a controlled
document. It is permissible for this to be one or more volumes, with or without
supplements, appendices, loose sheets (test results etc).
Maintenance instruction
The document which details the standard of maintenance required for railborne plant and
associated equipment.
Manufacturer
The company assembles the complete item of railborne plant or associated equipment, or
converts a host vehicle to run on railway lines. This is the entity which completes the CE
marking.
On-track Machine (OTM)
Any rail-mounted machine meeting the requirements of GM/RT2400 and permitted to be
moved, either self-propelled or in train formation, outside a possession.
On-track Plant (OTP)
Collective term for RRV, Demountable Machine and their trailers.
Plant assessment body (PAB)
For the purpose of this document, a plant assessment body (PAB) is a body with authority
to issue Engineering Conformance Certificates for railborne plant and associated
equipment.
Railborne plant
On-track machines, on-track plant and manually propelled trolleys.
Rolling Stock Library
The national central database of rail vehicle design and operational data, which is
maintained by the Network Rail’s authorised agent.
Running mode
Railborne plant is considered to be in running mode when its suspension allows movement
along the track, all parts stowed with everything within the applicable gauge, and the
machine interrelates with the signalling and control systems for normal railway traffic.
Page 6 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Road-rail vehicle (RRV)
A road-rail vehicle (RRV) is one that can travel on the ground and also travel on rail by
virtue of a rail wheel guidance system under its own power system. Such vehicles are not
allowed to run, work, travel or operate on rail outside possessions.
Trailer
A non-self-propelled, rail-mounted railborne plant capable of being towed or propelled by a
machine (this includes attachments with two or more rail wheels).
Travelling mode
Railborne plant is considered to be in travelling mode when its suspension allows
movement along the track, all moveable parts stowed with everything within the applicable
gauge, the machine does not require to interact with the signalling and control systems (in
this condition there is no need to ensure operation of signalling systems or for cab based
signalling equipment).
Trolley
A manually propelled, rail-mounted device supported simultaneously on both running rails,
as shown in RIS-1530-PLT.
Working mode
Railborne plant is considered to be in working mode when it is used to perform any of its
permitted design tasks, as soon as an item of railborne plant is unstowed it is in working
mode.
RSSB
Page 7 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Part 3
Engineering Conformance
3.1
How engineering conformance relates to product acceptance
3.1.1
Railborne plant shall, in the first instance, be accepted onto the railway using a three point
process of conformity with statutory requirements, engineering conformance and product
acceptance. Subsequently each time the item of railborne plant is used it shall be assessed
for suitability for the intended application. This process is set out in Figure 1.
1. STATUTORY REQUIREMENTS
SUPPLIER
ASSURANCE
Industry uses
manufacturers of
known ability and
quality
a)
Manufacturer carries out self certification to the
Machinery Directive.
b)
OTM’s in running mode assessed by NoBo for
compliance to TSIs, DeBo for compliance to
NNTRs and AB for CSM(RAE) report.
2. ENGINEERING CONFORMANCE
All railborne plant assessed for compliance to agreed
GB Industry Standards by PAB
3. PRODUCT ACCEPTANCE
Initial product acceptance of first of class by each
infrastructure manager.
RULES &
ASSESSMENTS
Industry uses plant
to agreed rules
and localised
assessment to suit
Figure 1
3.1.2
USE OF PLANT
Each time an item of railborne plant is planned to be
used, it is assessed by the user to confirm it is capable
of delivering the safe work plan proposed.
Plant approval process
Authorisation of new OTMs (or where a significant engineering change is taking place)
come within the scope of the Railways (Interoperability) Regulations (as amended) 2011,
(which transpose the Railway Interoperability Directive 2008/57/EC into UK law) when
intended for running on mainline railway. Machines in running mode on other than mainline
railway and all machines in travelling and working modes shall comply with 3.1.3.
Page 8 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
3.1.3
3.1.4
3.1.5
3.1.6
Statutory requirements are outside the scope of this standard. It is recognised that
compliance with the statutory requirements forms an important element of the product
assessment and railborne plant shall be declared compliant with the Machinery Directive
(as enacted by the Supply Of Machines (Safety) Regulations in GB). To claim presumption
of conformity to the machinery directive the manufacturer or supplier shall use the following
European Standard:
a)
On-track Machine – BS EN 14033-3:2009+A1:2011.
b)
Road-rail vehicle – BS EN 15746-2:2010 + A1:2011.
c)
Demountable Machine – BS EN 15955-2:2013.
d)
Trailers – BS EN 15954-2:2013.
e)
Trolleys – BS EN 13977:2011.
Engineering conformance is the subject of this standard and is explained more fully in
section 3.2 onwards. It is the assessment of the machine against the technical
requirements given in a specific nominated standard as shown:
a)
RIS-1530-PLT for the assessment of RRV, demountable machines, trailers and
associated equipment and trolleys.
b)
RIS-1702-PLT for the assessment of OTM in 'travelling' and 'working' modes.
Product Acceptance is the responsibility of each Infrastructure Manager (IM) who will have
their own standard to describe the process, it typically includes:
a)
Confirmation of the requirement for this type of plant.
b)
A check that an Engineering Conformance Certificate (ECC) for compliance to a
defined RIS exists.
c)
Safety justification and compatibility for potential for use on the infrastructure.
d)
The arrangements to ensure competent people and suitable facilities and
maintenance arrangements.
e)
Industrial relations agreement.
Use of Plant is responsibility of each user, to ensure safe use of plant and protect people,
infrastructure and railway operations, it typically comprises:
a)
Confirmation of ability to be used safely in this location.
b)
Confirmation that permitted use includes the job planned and capability of plant to
complete task.
c)
Confirmation of a valid ECC.
d)
Confirmation that arrangements exist for duration of use (whether one shift or several
years) – including emergency arrangements.
G 3.1.6.1
3.1.7
RSSB
Further guidance and requirements for the safe use of railborne plant is
shown in RIS-1700-PLT.
All plant requires the approval of the infrastructure manager for the operational use of the
plant and its known attachments on the managed infrastructure. The approval relates to
the type, safety and quality of work of the plant in its intended use and the effect on the
infrastructure.
Page 9 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
G 3.1.7.1
G 3.1.7.2
It is advisable before commencing design and build of the first in class of any
item of plant to engage early with one or more infrastructure manager to
assess the likelihood of the plant being required. Enquiries concerning the
application of the formal product acceptance process requirements will
normally receive a written response for the first in class to state one of the
following:
a)
The plant or concept is not required by the infrastructure manager.
b)
Formal product acceptance request will not be required because plant
type already accepted.
c)
Formal product acceptance request will be required.
All subsequent plant of identical design and construction will assume product
acceptance by the original acceptance for the first in class.
3.1.8
Where the item of plant is confirmed as being suitable, and full formal product acceptance
request is not considered to be required, written notification to this effect will be given by
the infrastructure manager. The requirement not to have full formal product acceptance
does not mean that the plant does not need full Engineering Conformance Assessment set
out in this document and the relevant technical standards (see 3.2), all railborne plant shall
have Engineering Conformance Assessment and a formal Engineering Conformance
Certificate issued.
3.2
General requirement for engineering assessment process
3.2.1
Each item of railborne plant shall have an Engineering Conformance Certificate. It shall be
obtained from a Plant Assessment Body (PAB).
3.2.2
The plant Asset Manager or manufacturer shall provide evidence to the PAB,
demonstrating conformance of the design, construction and maintenance instructions of
the item of plant or engineering change with all relevant mandatory requirements of the
specific technical requirements document, as set out in 3.1.4.
3.2.3
If an item of plant does not comply with a requirement(s) of the nominated technical
standard set out in 3.1.4, the Asset Manager or manufacturer is permitted to seek a
deviation by writing to the infrastructure manager that mandates this document stating
which requirement(s) cannot be met, why it is impracticable to do so and the alternative
means by which performance is achieved. The Plant Standards Committee may be used to
discuss the application for general observation and comment. Details of any deviations
shall be forwarded to the PAB for it to consider during the engineering assessment
process. The PAB shall record details of deviations on the Engineering Conformance
Certificate.
3.3
Engineering Conformance Certificate
3.3.1
An Engineering Conformance Certificate confirms conformance of the design, construction
and maintenance plan with all relevant mandatory requirements of the nominated technical
requirements standard set out in 3.1.4. An Engineering Conformance Certificate shall be
required for a new item of railborne plant, or for any engineering change of a previously
accepted item of railborne plant in any area covered by the mandatory requirements of the
technical requirements standard set out in 3.1.4.
Page 10 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
3.3.2
3.3.3
3.3.4
G 3.3.1.1
Note that the PAB assesses plant against the requirements of the technical
requirements standard only. The PAB process does not check the item of
plant against any statutory or legislative requirements. Issue of an
Engineering Conformance Certificate does not confer or imply that plant is
safe in all respects, nor that its performance meets the requirements of the
supply specification.
G 3.3.1.2
The manufacturer and / or supplier will need to perform a wider assessment
in order that foreseeable risks arising from the design, conversion and
intended operation, including foreseeable failure modes, and reasonably
foreseeable misuse, have been identified, assessed and mitigated at the
design stage. This will help the manufacturers and suppliers of OTP to meet
health and safety requirements. A legal framework is provided via the
Supply of Machinery (Safety) Regulations 2008 – as amended by the Supply
of Machinery (Safety) (Amendment) Regulations 2011.
For OTP, the initial Engineering Conformance Certificate shall be dated for a maximum life
of seven years, at which time it is permissible for the OTP to be re-accepted to the
applicable documents current at the time of re-certification.
G 3.3.2.1
When OTP receives an Engineering Conformance Certificate for the first
time, the certificate is given a life of up to seven years, starting from the date
of first assessment.
G 3.3.2.2
OTM and trolleys are permitted to be given an ECC without time limit. OTM
do not need to have time limit for their basic design which is based on more
onerous structural requirements and have a longer service life expectancy.
The standard OTM is based on a far longer design history.
Engineering Conformance Certificates issued as a result of re-assessment of the whole
item of OTP to current documents shall be dated for a maximum life of seven years from
the date of re-assessment.
G 3.3.3.1
When an item of OTP already has an Engineering Conformance Certificate
and is re-submitted for full assessment against the current version of this
document, then the Engineering Conformance Certificate that is issued as a
result of the assessment is normally given a life of seven years irrespective
of the age of any of the vehicle’s constituent parts.
G 3.3.3.2
In order for railborne plant to remain as certificated OTP after expiry of its
existing certificate, the whole railborne plant will need to be re-certificated to
the full requirements of the current version of RIS-1530-PLT at that time.
Where an OTP Asset Manager does not renew an expired Engineering Conformance
Certificate the OTP Asset Manager shall inform the Network Rail, Asset Information that
the railborne plant is no longer in use.
G 3.3.4.1
RSSB
Network Rail, Asset Information are informed because they are acting as the
national database for all railborne plant.
Page 11 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
3.3.5
A new Engineering Conformance Certificate issued as a result of any modification to the
OTP shall have the same expiry date as the previously accepted OTP unless the whole
OTP has been re-assessed to the current document.
G 3.3.5.1
The OTP Asset Manager, when submitting an item of OTP for reassessment due to a modification during the life of an existing Engineering
Conformance Certificate, has a choice to make. They can:
a)
Have the whole OTP assessed against the current issue of RIS-1530PLT and have a new Engineering Conformance Certificate valid for
seven years.
Or
b)
3.3.6
Have only the modification assessed against the section of RIS -1530PLT applicable to the modification and receive a new Engineering
Conformance Certificate with the same expiry date as the original
certificate.
All OTP shall have the date of expiry of the current Engineering Conformance Certificate
displayed on the OTP. This shall be positioned next to the vehicle number stating 'ECC
expiry date dd/mm/yyyy'.
G 3.3.6.1
The Asset Manager should check that all their OTP have this label fitted. An
example of the label is shown in Figure 2. The material for the label should
be a self-adhesive label laminated with anti-graffiti surface. The information
should be black on a yellow background, in Helvetica medium font.
75 mm
200 mm
Figure 2
Engineering Conformance Certificate
Expiry Date
dd / mm / yyyy
Example of date label
3.4
Assessment process
3.4.1
Engineering assessment process
3.4.1.1
The PAB shall assess the railborne plant for compliance with the relevant technical
standard, see 3.1.4, and when satisfied that the railborne plant is compliant shall issue an
Engineering Conformance Certificate.
G 3.4.1.1.1
Engineering assessment consists of a review of the design and construction
of a railborne plant to check its compliance with the mandatory requirements
and a review of the maintenance plan for OTP to confirm that if followed it
would enable continued compliance throughout its operational life.
Page 12 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
G 3.4.1.1.2
3.4.1.2
The certificate set out in Appendix A is an example of the required format for
OTMs, an example of the certificate for OTP and trolleys is given in
RIS-1530-PLT. However it is expected that the information shown should be
in the same order on the actual certificate produced and using the specified
wording shown in the examples as far as practicable (so that the necessary
information can easily be found and understood when required).
An Engineering Conformance Certificate shall be signed only by an authorised signatory
employed by the PAB with the appropriate scope of recognition.
The issue of all certificates shall be formally recorded by the PAB. Three copies of each
certificate that each carries an original signature and official stamp of the organisation (or
equivalent secure system) shall be issued and distributed, by the PAB, as follows:
3.4.1.3
a)
Railborne plant Asset Manager copy.
b)
PAB copy.
c)
Network Rail Asset Information.
G 3.4.1.2.1
A copy of the ECC is sent to Network Rail, irrespective which infrastructure
the plant is intended to be used on, because Network Rail have agreed to
host the national plant database. As a minimum this database holds only the
existence of the plant and the type, any other information supplied is at the
discretion of the infrastructure manager concerned.
G 3.4.1.2.2
OTM intended for use on Network Rail managed infrastructure in running
mode will additionally need to have conformance to engineering
requirements communicated to the Rolling Stock Library.
An Engineering Conformance Certificate shall be issued for either:
a)
An individual item of railborne plant.
Or
b)
A group of identical items of railborne plant. The Engineering Conformance
Certificate shall list the vehicle number of each railborne plant covered by the
certificate.
G 3.4.1.3.1
3.4.1.4
RSSB
For guidance on what constitutes an identical item of railborne plant see
G.3.4.2.1.3.
A new Engineering Conformance Certificate shall be issued in the following circumstances:
a)
Following successful assessment of an item of new railborne plant.
b)
At change of the Asset Manager of the railborne plant. The new Asset Manager is
responsible for obtaining a new Engineering Conformance Certificate.
c)
Following assessment of the relevant clauses when change of engineering state (see
3.8), including amendment to maintenance plans (except as shown in 3.4.2.5).
d)
Following successful assessment at life expiry of the previous certificate.
Page 13 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
3.4.1.5
At the re-issue of an Engineering Conformance Certificate, the previous limitations shall be
transferred to the new certificate unless a modification has removed the reason for the
limitation.
G 3.4.1.5.1
Information on the previous certificate may be included in the supplementary
/ additional information section of the certificate.
3.4.2
Requirements for assessment process
3.4.2.1
The assessment process, carried out by a PAB, shall include the following for the railborne
plant:
a)
An assessment of the first in class for all aspects of design, construction, testing and
condition of the railborne plant that could have an influence on its compliance with this
document.
b)
Where required to comply with the standards as set out in 3.1.4, testing of the
railborne plant under operational conditions in running, travelling and working modes
as necessary.
G 3.4.2.1.1
The first in class railborne plant is given a more rigorous assessment than
subsequent identical railborne plant. The first in class is assessed for all
aspects of its operation and construction in accordance with this document
against the relevant technical standard set out in 3.1.4.
G 3.4.2.1.2
All subsequent identical railborne plant need to be checked for conformity
against the first in class railborne plant and for the mandatory tests that
every new railborne plant requires. These tests are set out in the relevant
technical standard set out in 3.1.4. Further guidance is given throughout the
relevant technical standards for the different testing requirements between
the first in class railborne plant and subsequent railborne plant.
G 3.4.2.1.3
Identical railborne plant are those of exactly the same design. To be
identical the railborne plant must use the same manufacturer and model type
of all sub-components. The dimensions of major components must be the
same to within the tolerances on the engineering drawings. The wheel loads
of each wheel in tare and fully laden conditions should not vary by more than
5% between first in class and subsequent railborne plant for each wheel.
The tare weight of the whole railborne plant should not vary by more than
2%. Software version numbers of all control, braking and safety features
should be assessed to check the software core functionality is the same as
the approved / certified first in class railborne plant.
3.4.2.2
An assessment of the documented maintenance instructions for the railborne plant shall be
carried out to confirm that the requirements of the relevant technical standard set out in
3.1.4 are met.
3.4.2.3
The PAB shall issue an Engineering Conformance Certificate for the railborne plant when it
is satisfied that the railborne plant complies with all of the mandatory requirements of the
relevant technical standard set out in 3.1.4. The current issue number of the approved
maintenance plan shall be shown on the Engineering Conformance Certificate.
3.4.2.4
Where an Engineering Conformance Certificate is issued for subsequent identical railborne
plant the Engineering Conformance Certificate for the first in class railborne plant shall be
referenced.
Page 14 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
G 3.4.2.4.1
3.4.2.5
Revision of a maintenance plan does not necessitate reissue of the Engineering
Conformance Certificate provided that the railborne plant Asset Manager possesses a
letter from one of the bodies listed in 3.8.1.1, which verifies that the amendments to the
maintenance plan do not affect the railborne plant’s compliance with the relevant technical
standard set out in 3.1.4.
G 3.4.2.5.1
3.4.2.6
For subsequent identical railborne plant, the Engineering Conformance
Certificate does not require the design aspects to be reviewed separately for
each railborne plant, but recognises the first in class certificate and any
special limitations identified therein as evidence of conformance of those
aspects within its scope.
When the railborne plant(s) is subsequently re-certificated, if a revised
approved maintenance plan is in use, the reference on the new Engineering
Conformance Certificate should be updated.
For modifications, as described in section 3.8, where the same modification is being
applied across different types of railborne plant it is permissible to use the same process
described in 3.4.2.1 such that the first railborne plant modified has the design, construction
and testing and subsequent railborne plant are checked for conformance to the original
modification. The assessment and process used needs to be rigorous enough to identify
where there could be issues in transferring a modification to other machines and
consequently flag the need for further appropriate assessment. Where the Engineering
Conformance Certificate is issued for subsequent identical modifications the Engineering
Conformance Certificate for the first railborne plant modified shall be referenced in addition
to reference to the Engineering Conformance Certificate for the first in class railborne plant
if applicable.
G 3.4.2.6.1
For modifications to be considered the same they should consist of identical,
or very similar, modification instructions; and where connections are being
made to electrical, pneumatic or hydraulic circuits the same number of
connections of each type should be made across the fleet. The testing
regime following the modification should be identical, with the same pass or
fail requirements.
G 3.4.2.6.2
The Engineering Conformance Certificate should be clearly marked with the
certificate number of the first in class railborne plant (as set out in 3.4.2.4)
and also the certificate number for the first of type of the modification.
3.5
Limitations on the Engineering Conformance Certificate
3.5.1
Where the safe use of the railborne plant is assured only with limitations in place, then the
Engineering Conformance Certificate shall show the limitations within which the operation
of the railborne plant shall be restricted.
3.5.2
Appendix A shows an example of the required format of the Engineering Conformance
Certificate for an OTM and example certificates for OTP and trolleys are shown in
RIS_1530-PLT. The information, including any limitations, shall be in the same order on
the actual certificate produced and using the specified wording shown where possible (so
that the necessary information can easily be found and understood when required).
3.6
Requirements for Engineering Conformance Certificate
3.6.1
In addition to the requirements of 3.4 and 3.5, the Engineering Conformance Certificate
shall contain the following information:
RSSB
Page 15 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
a)
The date of issue and date of expiry.
b)
The particular mode, including any specified attachments for which the assessment is
being agreed.
c)
A unique identity number (as set out in 3.7).
d)
Manufacturer's serial number.
e)
The standard and issue number of the relevant technical standard set out in 3.1.4 to
which the railborne plant has been assessed.
f)
Gross vehicle weight.
g)
Tare weight, where appropriate.
h)
Additional requirements as set out throughout the relevant technical standard set out
in 3.1.4.
i)
The railborne plant Asset Manager.
j)
All applicable deviations issued by any body which mandates this standard.
k)
Limitations, as required by 3.5.
l)
Serial number of the duty charts for each load lifting point, where appropriate.
m) Where infrastructure managers are already known to have granted product
acceptance these shall be shown.
n)
Various options available in the technical standard set out in 3.1.4 defined for the
railborne plant (for example; gauge, axle weight, movement limiting device type etc).
3.7
Vehicle number for OTP and OTM
3.7.1
As part of the assessment process each OTP and OTM shall be given a unique identity
number. This number shall be allocated by Network Rail, and displayed on both sides of
the railborne plant. The number shall additionally be displayed on the data panels.
G 3.7.1.1
Network Rail, irrespective which infrastructure the OTP or OTM is intended
to be used on, have agreed to host the national plant database and hence
will allocate the unique vehicle number.
G 3.7.1.2
OTMs may already have a unique identity number from another member
state. This will always be used with the machine in running mode. Network
Rail (in conjunction with the infrastructure manager concerned if different)
will decide the use of the machine in travelling and working modes for
allocating the number.
3.7.2
The unique identity number on the railborne plant sides shall be readable from the ground
and at a distance of at least 5 m from the railborne plant. Where it is not practicable to
meet this requirement then the number shall be legible, as large as practicable and in a
prominent position.
3.7.3
Where it is not reasonably practicable to display the number on both sides of the railborne
plant, it is permissible to provide identification elsewhere on the railborne plant which shall
still be clearly visible as set out in 3.7.2.
Page 16 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
G 3.7.3.1
3.7.4
The number may be provided on adhesive label or painted directly onto the
railborne plant. The number should be of a contrasting colour to the
background to which it is applied, to provide ease of visibility (a typical font
used is sans-serif).
Data panels shall be attached to each side of the railborne plant following full assessment
of the railborne plant to the relevant technical standard set out in 3.1.4. The data on each
panel shall be legible at a distance of 2 m from the side of the railborne plant.
G 3.7.4.1
The data panels, (details set out in the relevant technical standards), can be
reformatted where there are constraints on the railborne plant size, the entire
data panel needs to be visible simultaneously.
3.8
Modifications
3.8.1
Modifications to all railborne plant
3.8.1.1
Except as set out in 3.8.2, modifications to previously accepted railborne plant shall be
re-certificated by a PAB or assessed by a competent engineer that re-certification is not
necessary. A competent engineer is one of:
a)
An accredited signatory of a PAB.
b)
A professional head of rail vehicle engineering of a railway undertaking operating
on-track machines.
c)
Network Rail, Professional Head of Plant Engineering.
d)
London Underground, Relevant Head of Technical Discipline.
G 3.8.1.1.1
A modification is anything affecting compliance with the relevant technical
standard set out in 3.1.4, including the maintenance requirements. Normally
a modification will require skilled intervention and is not already described in
the instruction handbook.
G 3.8.1.1.2
For OTP, in the majority of cases the Asset Manager of the railborne plant is
not the holder of a safety management system, therefore it is recommended
that advice be sought from the PAB or the relevant professional head as
shown in 3.8.1.1.
G 3.8.1.1.3
The decision whether a modification requires re-certification is based on
whether the change is significant.
3.8.1.2
The decision that formal re-certification is not required shall be documented and signed by
the competent engineer who made the decision. The railborne plant Asset Manager shall
keep a copy of this written confirmation on file and retain an auditable record of all work
undertaken and approved.
3.8.1.3
The PAB shall assess any modification and consider whether any limitations need to be
added to, amended or removed from the Engineering Conformance Certificate to achieve
compliance with the relevant technical standard set out in 3.1.4.
G 3.8.1.3.1
RSSB
This clause is applicable when any Engineering Conformance Certificate is
re-issued, for example for a change of Asset Manager or change of
identification number.
Page 17 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
3.8.1.4
For OTP, the Asset Manager shall provide to all Infrastructure Managers who are known to
have granted Product Acceptance the item of OTP, details of all modifications undertaken
to a railborne plant, including details of work undertaken, and a copy of either, the
competent engineer’s assessment, or a new Engineering Conformance Certificate that has
been issued.
3.8.2
Modifications to mobile elevating work platforms
3.8.2.1
The railborne plant Asset Manager shall have any modification to a mobile elevating work
platform (MEWP) assessed by a PAB, manufacturer or a Notified Body (NoBo), for the
potential to affect the compliance with BS EN 280:2001 or later.
3.8.2.2
Where the modification will affect the compliance with BS EN 280:2001 or later, an
assessment shall be made and where compliant, a certificate of conformance to BS EN
280:2001 or later, shall be issued covering the modification.
G 3.8.2.2.1
The requirements of 3.8.2.1 and 3.8.2.2 are that all modifications to railborne
plant that include MEWP functionality are assessed by a PAB, manufacturer
or NoBo. The professional head of rail vehicle engineering of a railway
undertaking does not have the discretion as to whether or not a modification
requires re-assessment for compliance to BS EN 280:2001.
G 3.8.2.2.2
Following the decision about compliance with BS EN 280:2001 the next
decision is about compliance to the relevant technical standard set out in
3.1.4, as set out in 3.8.1.1.
G 3.8.2.2.3
The assessment of compliance to BS EN 280 is carried out by a NoBo (as
stated in Machinery Directive).
3.9
Innovative solutions
3.9.1
Any innovation proposed for plant or its component parts, where the innovative solution is
not covered, or not adequately covered, by the relevant technical standard set out in 3.1.4
shall be assessed by a PAB for its suitability against a comparable national or international
standard recognised by the European Union. The standard(s) against which the innovation
is assessed shall be shown on the Engineering Conformance Certificate.
3.9.2
Where innovative features on plant are not covered by the requirements of the relevant
technical standard set out in 3.1.4s, the PAB’s assessment shall be for compliance with an
appropriate UK or EU standard. If there is no appropriate standard, the Asset Manager
shall convene an expert group including the manufacturer, an infrastructure manager,
RSSB and a PAB to determine if the innovation is acceptable.
G 3.9.2.1
All railborne plant, or major components / modules for railborne plant that
have not previously been assessed should be assessed for compliance with
the relevant technical standard set out in 3.1.4 and an Engineering
Conformance Certificate issued. Any new railborne plant, or more likely a
system or component for a railborne plant, which is not currently covered by
the relevant technical standard, should be assessed for railway safety and
its effect on other railborne plant and the infrastructure.
G 3.9.2.2
Components for a railborne plant are those that are significant in their effect
and are a fundamental change from those components previously assessed.
For example a different style of wiper blade for a windscreen wiper does not
come into this category, but a new proposed rotary centrifugal screen is
covered by this clause.
Page 18 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
3.10
Accreditation of PABs
3.10.1
Only PABs accredited by UKAS (the United Kingdom Accreditation Service) shall be used
to assess plant.
3.10.2
UKAS shall accredit PABs using the UKAS processes, as used for accreditation of DeBos
(Designated Body) but accompanied by a recognised GB plant expert. The accreditation of
the PAB shall include review of the internal PAB process for verifying competence of
nominated signatories.
G 3.10.2.1
3.10.3
RSSB
Recognised GB plant expert will normally be provided by RSSB.
The list, and contact details, of current accredited PABs shall be displayed on RSSB
website.
Page 19 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Appendix A Engineering Conformance Certificate for OTM
PAB Logo
On-track Machine
Engineering Conformance Certificate
Name of Plant Assessment Body
Accreditation Code
Delta Rail
ER
Vehicle Class / Description :
[Manufacturer name] Tamper [model]
Vehicle Operator
:
[Operator name]
Issue Date
:
xxth August 2015
Expiry Date (if any)
:
xxth August 2016
Vehicle Numbers
DR 73906
FIRST IN CLASS * (Delete as appropriate)
Certificate Number of First in Class * ER / 0798 / 06
Authorised by :
Official Stamp
Signatory Name
Reason for issue and Scope of Work
Guidance note :
First item - to reference last full certification assessment standard.
Then detail scope of work for this certificate including clearly the issue number of
GM/RT2400 and/or RIS-1702-PLT and what has been assessed.
Customer Copy
Certificate Number : ER/0999/15
Page 1 of 3
Page 20 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Deviations associated with this certificate (if none state “NONE”)
None
Previous Certificate Number (if none state “NONE”): ER/0131/07
Maintenance Plan Details
Maintenance Plan Title
:
Maintenance Plan Number :
Vehicle data
Route availability
Issue No :
(laden)
:
Maximum speed (running)
:
Applicable gauge (running)
:
Applicable brake curve
:
Minimum curve radius
:
Other mandatory data for RSL
:
Date :
(tare) :
(travelling) :
(working) :
Limitations of Use
1.
The vehicle shall not work on light rail systems.
2.
Vehicle must not be travelled on:
Track cants greater than *** mm.
Track gradients greater than 1 in **
Curve less than xx m.
For reverse movements the vehicle shall be controlled by ground staff.
3.
4.
During reverse movements of the vehicle is to proceed at walking speed under the control of ground
staff until the superstructure can be slewed to face direction of travel.
5.
The vehicle may only operate with the access adjacent to a cess or a line closed to all train movements
or the documented safe system of work must take account of adequate safe clearances to adjacent
lines.
6.
Not permitted in live conductor rail areas
7.
Not permitted to work under live OLE
8.
Vehicle is not permitted to tow or propel any other vehicle.
9.
Crane on vehicle must only be used with stabilisers deployed.
Certificate Number: ER/0999/15
Page 2 of 3
RSSB
Page 21 of 23
RIS-1710-PLT Issue One December 2015
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
Supplementary Information
(Optional – minimum requirements where applicable)
1.
Manufacturer serial / chassis number
2.
Maximum travelling cant
– 200mm
3.
Maximum working cant
– 100mm
4.
Maximum gradient
– 1 in 25
5.
Potential vertical load applied either side of rail head - xxx kgs
6.
Maximum vehicle tail swing – xxmm
7.
Maximum speeds (travel and working) on rail not to exceed:
** mph plain line
** mph switches and crossings
** mph raised check/guard rails
** mph with raised and manned platform
** mph when travelling with load on crane
** mph Towing/propelling
** mph emergency recovery
8.
The vehicle is approved to carry xx persons seated in the driver's cab and xx passengers
(seated/standing) in (a trailer/the load area).
9.
Demountable modules - None specific wording - words to reflect vehicle specifics
10. Vehicle incapable of moving along the track when disconnected from the towing vehicle.
11. Height of underside of rotating superstructure above rail level - xx mm
12. Attachments for use without RCI - None specific wording - words to reflect vehicle specifics
13. Attachments for use on specific vehicles - None specific wording - words to reflect vehicle specifics
14. Where an attachment is known to have a significant adverse affect on stability the RCI shall always be
in ‘Lift Mode’ when using the attachment
15. Attachments for Raising Lowering personnel - None specific wording - words to reflect vehicle specifics
16. Load lifting point located at xxxxxxxx, rated capacity xx tonnes SWL .
17. RCI information :
Manufacturer
Model
Software version
Duty chart reference, issue number and date
Certificate Number : ER/0999/15
Page 3 of 3
Page 22 of 23
RIS-1710-PLT Issue One December 2015
RSSB
Uncontrolled When Printed
Document comes into force and supersedes Part 3 of
RIS-1530-PLT Iss 5 on 05/12/2015
Rail Industry Standard for Engineering Certification of Railborne
Plant
References
The Catalogue of Railway Group Standards give the current issue number and status of
documents published by RSSB. This information is also available from
www.rgsonline.co.uk.
RGSC 01
RGSC 02
Railway Group Standards Code
Standards Manual
Documents referenced in the text
Railway Group Standards
GM/RT2400
Engineering Design of On-track Machines in Running Mode
RSSB documents
RIS-1530-PLT
Rail Industry Standard for Technical Requirements for On-track
Plant their Associated Equipment and Trolleys
RIS-1700-PLT
Rail Industry Standard for Safe Use of Plant for Infrastructure Work
RIS-1702-PLT
Rail Industry Standard for the Design of On-track Machines in
Working and Travelling Modes
Other References
Supply of Machinery (Safety) Regulations 2008 – as amended by
the Supply of Machinery (Safety) (Amendment) Regulations 2011
Provision and Use of Work Equipment Regulations1998Control of
Vibration at Work Regulations: 2005
Lifting Operations and Lifting Equipment Regulations: 1998
Road Machines (Construction and Use) Regulations: 1986
BS EN 280:2001
Mobile Elevating Work Platforms – Design Calculations – Stability
Criteria – Construction – Safety – Examinations and Tests
BS EN 13977:2011
Railway applications. Track. Safety requirements for portable
machines and trolleys for construction and maintenance
BS EN 14033-3:2009+A1:2011
Railway applications. Track. Railbound construction and
maintenance machines. General safety requirements
BS EN 15746-2:2010+A1:2011
Railway applications — Track — Road-rail machines and their
associated equipment — Part 2: General safety requirements
BS EN 15954-2:2013 Railway applications. Track. Trailers and associated equipment.
General safety requirements
BS EN 15955-2:2013 Railway applications. Track. Demountable machines and
associated equipment. General safety requirements
RSSB
Page 23 of 23
RIS-1710-PLT Issue One December 2015
Download