Deviations Register RGS Number GIRT7016 RGS Issue Number Five RGS Title Interface between Station Platforms, Track and Trains Certificate Number 16-030-DEV Title Southall Station Platform 3 Canopy support columns. GKRT0075 Four Lineside Signal Spacing and Speed Signage 16-029-DEV Braking distance for PSR on the Down Slow 3.2.3.3 a) line at Woking Junction. GKRT0077 One Ground Frames and Shunters' Releases 16-028-DEV Severn Beach single line working system including SERC ground frame connection not including track circuit detection indications at the control point. 2.2.1.4 GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 16-026-DEV Signal Buzzer Functionality and Texture. B8.4.2 GMRT2466 Three Railway Wheelsets 16-025-DEV Axle Standards. 2.1.1 Current Deviations Register as at 09 May 2016 RGS Clause 6.5.2 Scope Southall Station Platform 3 canopy - the existing canopy columns (4Nos) are the only element affected by this work; the canopy does provide Mechanical and Electrical routes, but these are not impacted and are not considered as part of this deviation. Southall platform 3 view towards country, columns 3 and 4Southall platform 3 view towards London, columns 1 and 2 Woking Junction down slow line on the BML1 Line. Nature and Degree As part of the Crossrail surface works, the Down Relief track is slewed, this encroaches into the existing non-compliance area on platform 3, further reducing the distance between the canopy supporting columns and the platform edge. The track slew is to be undertaken in May 2016; however, the new compliant canopy will not be in place until December 2017. A temporary deviation is sought until the existing canopy is removed and replaced with a permanent compliant canopy which, as per current programme, is December 2017. The planned track slew of the Down Relief cannot be achieved without narrowing Platform 3 at the country end with a maximum reduction of 171 mm. The reduction in platform width at the other column positions is shown in the following table. Table showing existing existing and proposed dimensions between the columns and platform edge The greatest narrowing distance is recorded at the country end of Platform 3, between the last canopy support column 4, and platform edge is 171 mm (Image 2). The amount of narrowing decreases gradually towards the London end, down to 113 mm. The temporary deviation will provide sufficient time to To provide the PSWI at compliant position incurs excessive alteration to the interlocking (SSI), which is at its capacity limit. Risk Assessment/Safety Justification Applicant Organisation A Health and Safety risk assessment has Network Rail been conducted in collaboration with the stakeholders in order to identify mitigation measures to address the temporary deviation. The temporary deviation will take effect from 01/05/2016 and remain in place until 12/01/2018. Certificate Issue Date 31/03/2016 Certificate End Date 12/01/2018 Lead SC Infrastructure Lead SC Approval Date N/A Deviation Status Current Network Rail 14/04/2016 N/A Control Command and Signalling 17/03/2016 Current Network Rail 14/04/2016 N/A Control Command and Signalling 17/03/2016 Current Bombardier Transportation on behalf of, MTR Corporation (Crossrail) Ltd 04/05/2016 N/A Rolling Stock 11/03/2016 Current This combination of standards has recently Bombardier Transportation on been used for other FLEXX Eco projects behalf of, MTR Corporation such as ICx in Germany and C30 metro for (Crossrail) Ltd Stockholm. Similar standards were applied to Class 172 and Class 22x units, which also had FLEXX Eco bogies. However, standard BS8535 was not published at the time of authorisation for these units. BS8535 explicitly addresses inboard bearing bogies and references EN 13261, which shows it is intended to be used as part of the EN suite of wheelset standards. 11/04/2016 N/A Rolling Stock 11/03/2016 Current At the time of commissioning the signalling system at Woking (circa 1997), there was a speed reduction from 90 mph to 60 mph for routes towards Basingstoke on the BML1 line (due to track curvature across the junction). Following the Woking Junction remodelling circa 2008, excessive side wear has been noticed on 2234 points across the junction, so a 40 mph TSR was imposed to prolong the life of the points and keep them safe and reliable. The TSR has been in service since 2008. The speed shown on the PSWI at 1188 m will be changed from 60 to 40 mph, on the basis that the vast majority of trains conform to Table C braking and that anything else will not or is not permitted to exceed 75 mph and would brake within 1188 m, which is inside the Appendix X braking distance of 1307 m. It should also be noted that the Appendix X braking rates are historic and do not reflect the reality of current rolling stock. The proposal is to convert the current TSR to a 40 mph PSR but retain the current PSWI signage board location which is currently placed at Table C braking distances and not for Table A and B. The Existing PSWI for 60 mph is currently at 1188 m from the PSR. A Compliant PSWI for 40 mph would need to be at 1307 m from ELR AMB - Severn Beach single line In order to to comply with the requirement, The new and revised controls will be working system from Hallen Marsh Jn to costs and risks of the significant alterations designed such that track circuit failure Severn Beach Station, including SERC to line side circuits, interlocking and the cannot result in an inadvertent release of ground frame connection. Controlled by the panel in St Andrews Signal Box (SB) for the interlocking. A robust train exit sequence is St Andrews Signal Box panel. provision of three track circuits are too high. proposed for the new shut in arrangement, which will include the requirement for the local operator to manually confirm that the train has cleared the main line complete with tail light and the signaller to confirm to the operator that all signalling has returned to normal before the operator may leave. Remote Condition Monitoring (RCM) facilities will be available to monitor track circuit performance as required. The interlocking will prevent section signals from clearing unless track circuits are clear. Provision is being made for the implementation of remote condition monitoring for the new track circuits. Medium-voltage Direct Current (MVDC) track circuits, with track feed relays, to be utilised for improved reliability of train detection. This deviation applies to all Class 345 units. The Class 345 signal buzzer is not textured The proposed functionality is suitable for the and does not comply with the functionality operation of Class 345 units. The majority of specified in the standard. It is not the operation will be driver-only operation, considered appropriate to provide a textured and so the signal bell will not be required. button for the signal buzzer, because the When the units are operated with a guard, adjacent 'doors close' pushbutton is also the only remote place the guard can close textured. The other highlighted parts of the the doors from is the rear cab. Therefore, clause are not complied with to enable a both cabs will be occupied and it is simpler design of circuit. The Locomotives appropriate to sound the buzzer in both and Passenger Rolling Stock (LOC and cabs. There is no scenario when the buzzer PAS) Technical Specifications for would be used with only one cab occupied. Interoperability (TSI) places no requirements Linking the buzzer functionality with the on signal bell functionality. bodyside door status is not considered necessary, since bodyside doors are already interlocked with traction. If the buzzer is sounded too early during platform duties, the driver will not be able to leave the station. A number of similar deviations have been raised for Turbostar and Electrostar units (14/087/DEV, 12/126/DEV, 08/113/DGN, 09/046/DGN) owing to inconsistency between GMRT2473, the Rule Book, and the operation of these units in service. The operator (MTR Crossrail) has been engaged throughout the design review process with the design of the cab and the operation of the train by the driver and guard, and is satisfied with the proposed design. The deviation will apply to all Class 345 The implementation of the Technical units. All vehicle types will have FLEXX Eco Specifications for Interoperability (TSIs) bogies. mandated through a series of European Union Directives has resulted in a review of all requirements mandated in Railway Group Standards. Page 1 Deviations Register RGS Number GMRT2100 RGS Issue Number Five RGS Title Requirements for Rail Vehicle Structures Certificate Number 16-024-DEV Title Fire Extinguisher Position RGS Clause 6.7.6.3 GMRT2044 Four Braking System Requirements and Performance for Multiple Units 16-023-DEV Emergency Brake Application Deterrent. 5.4.2 GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 16-022-DEV Loss of Door Interlock Response. B7.6 The deviation will apply to all all new vehicle The Class 345 door interlock is linked with designs. the traction system (as required by the Locomotives and Passenger Technical Specifications for Interoperability ( LOC and PAS TSI), Clause 4. 2. 5. 5. 7) and is not linked with braking control. Therefore, opening a bodyside door would not cause an emergency brake application. The bodyside door design selected for the Class 345 means that a link with the emergency brake is no longer necessary, as explained in section 8 - 'Demonstrate that what you are proposing to do instead is reasonable'. GMRT2185 Two Train Safety Systems 16-021-DEV Isolation Switch Design B5.1, B5.3 This deviation will apply to all Class 345 units. The Class 345 will have simple isolation switches which do not require a key for operation of the switch itself and do not have a visible seal or similar. The switches can be reset by the driver. The benefits of this solution are that, unlike some previous designs, the isolation switches do not require the driver s key to move the switches to 'isolated'. This means that the driver s cab does not require de-activating / re-activating to isolate a system (which can take several minutes), and so the process of responding to a fault is quicker. The isolation switches can be re-set by the driver, which removes the risk that the driver inadvertently isolates the wrong system and then is unable to resolve the situation. GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 16-018-DEV Roll-over Cant Deficiency. 2.4.1.1 The deviation will apply to all Class 345 units. The units will be delivered as 7-car and 9-car formations, but all units will ultimately be 9-car formations and the same design. All vehicle types are considered as part of this deviation. The Class 345 unit has been designed to minimise mass while achieving a high passenger capacity. To achieve this, the unit has in-board bearing bogies, and open saloons with longitudinal seating in most areas. This means that the unit has a relatively high centre of gravity in under exceptional payload conditions, and so does not comply with the 21° cant deficiency requirement. GMRT2461 One Sanding Equipment Fitted to Multiple Units and On-Track Machines 16-017-DEV Sanding positions. 9.1 and9.3.1 The deviation will apply to all Class 345 units. The deviation applies equally to both seven-car and nine-car formations. Crossrail units will be nine-car fixed formations (with some units initially operating as seven-car units). The Crossrail technical specification required sanding at multiple locations. This requirement aligns with Bombardier s experience with London Underground (LUL) S-Stock that a single sanding position will be insufficient to effectively apply sand for a long unit. Current Deviations Register as at 09 May 2016 Scope Nature and Degree The deviation will apply to all Class 345 units. The units will be delivered as sevencar and nine-car formations, but all units will ultimately be nine-car formations and the same design. The fire extinguisher is stored in a cupboard that is present in both formations. The deviation will apply to all Class 345 The Class 345 units do not include the units. function to latch the emergency brake until the low-speed signal is detected. Therefore, an emergency brake application can be cancelled before the unit has come to a stop. While it is technically possible to achieve this function, it was not considered necessary. Removing this function simplifies the brake control functionality. Risk Assessment/Safety Justification The cupboard installation will mean that even if the fire extinguisher comes out of its restraints, it will still be constrained by the cupboard door. This design reduces the risk to passengers compared to a low-level, open installation. Applicant Organisation Bombardier Transportation on behalf of, MTR Corporation (Crossrail) Ltd Certificate Issue Date 04/05/2016 Certificate End Date N/A Lead SC Rolling Stock Lead SC Approval Date 11/03/2016 Deviation Status Current Guidance notes for Clause 2. 2. 2. 1 of the new draft of GMRT2045, which will replace GMRT2044, gives an explanation of the source of the requirement. It states that the requirement was written to reduce the risk of mechanical failure of bogie or friction braking equipment due to the higher forces from emergency braking for which it was not designed. The requirement is now only applicable to 'ex-BR' units. This is not applicable to new-build units, where brake equipment is designed to withstand the forces associated with emergency braking. The Locomotives and Passenger (LOC and PAS) Technical Specification for Interoperability (TSI) does not specify this function and envisages that an emergency brake command could be cancelled (see clause 4. 2. 4. 4. 1 (4)). The Class 345 bodyside doors differ from those on previous multiple units in that it is not possible to open the door in any way while the unit is in motion. (For example, when the egress device is activated on Electrostar vehicles, the doors unlock and then are held closed by the door motors until sufficient time has passed for the train to come to a stop. ) On the Class 345, activating the egress device triggers a latched switch but further movement of the egress device is limited by a physical bolt. The bodyside doors are not unlocked and do not move. The traction interlock is not broken. The switch in the egress handle informs the driver that the handle has been activated via the Trains Control and Management System (TCMS). The driver is told which door is affected on the Human Machine Interface (HMI) screen. The driver can use this information and the status of the door interlock to determine the next safe place for the unit to stop - in the Central Operating Section, this will normally be the next station. When the train has slowed to less than 1 km/h, the bolt in the egress handle will release, and the egress handle can be fully moved. Only at this stage will the door unlock. This means that the Rule Book Module TW5 contains the instructions for isolation of safety systems. The driver must stop, if not already stopped, and contact the signaller to receive instructions. There is no operational scenario where the driver should isolate systems while the train is moving. Although isolating a system while the train is moving is technically possible, it would require the driver to leave the driving position, unlock the isolation switch panel, and isolate the system while facing away from the direction of travel. The Class 345 design includes monitoring of switches by the Train Diagnostic System, which is clearly visible to the driver. This is considered to be sufficient deterrent to the driver miss-using the isolation switches. The Train Diagnostic System and the Train Data Recorder both log use of the isolation switches so it can clearly be determined if and when a system has been isolated. The operator (MTR Crossrail) has been engaged throughout the design review process with the design of the cab and the operation of the train by the driver, and is satisfied with the proposed design. The 21° limit has been subject to a number of deviations: 14/048/DEV Class 700 (Thameslink)14/126/DEV Mk. 3 Galley cars15/047/DEV Class 465/9 TOSL car15/067/DEV Class 321 trailer vehicle. Through these deviations, it has been established that a lower cant deficiency limit is acceptable. As with the vehicles quoted above, the lowest value for the Class 345 unit occurs on an intermediate vehicle, which has less sensitivity to roll-over due to cross winds. There have been a number of recent deviations for sanding where units comply with the objectives of GMRT2461, but do not comply with the precise requirements of the standard. In particular, deviation 15-061DEV permits each unit within a multiple unit consist to sand if that unit detects wheel slide. The new draft version of GMRT2461 recognises that current requirements are too restrictive, and requirements for sanding position and rate have been removed in favour of a more general requirement to not affect track circuits. The sanding system for Class 345 is being developed to achieve the required impact on adhesion while minimising the amount of sand deposited (lower sand usage reduces maintenance costs as well as minimising the risks of affecting track circuits). The current sanding strategy (at the end of the design phase) is a maximum sanding rate of 1. 5 kg/min at each sander, which is equal to the 3 kg/min rate applied by Electrostar units. The unit will be capable of sanding at double this rate, but it is not anticipated that this will be required. The sanding rate will be managed to ensure compliance with 7. 5 g/m laying rate in GMRT2461 Clause 9. 3. 1 is maintained. If it is found that this is not Bombardier Transportation on behalf of, MTR Corporation (Crossrail) Ltd 04/05/2016 N/A Rolling Stock 11/03/2016 Current Bombardier Transportation on behalf of, MTR Corporation (Crossrail) Ltd 04/05/2016 N/A Rolling Stock 11/03/2016 Current Bombardier Transportation on behalf of, MTR Corporation (Crossrail) Ltd 04/05/2016 N/A Rolling Stock 11/03/2016 Current Bombardier Transportation, on 01/04/2016 behalf of, MTR Corporation (Crossrail) Ltd N/A Rolling Stock N/A Current Bombardier Transportation on behalf of, MTR Corporation (Crossrail) Ltd N/A Rolling Stock 11/03/2016 Current 11/04/2016 Page 2 Deviations Register RGS Number GMRT2472 RGS Issue Number Two RGS Title Certificate Number Requirements for Data Recorders on Trains 16-016-DEV Title West Coast Railway Class 37 European Train Control System (ETCS) Fitment Data Recorders. RGS Clause 3.1.1.5, 3.1.3.1 Scope The deviation applies to two Class 37 locomotives (37668 and 37669) that are being fitted with the Hitachi on-board subsystem to provide ETCS functionality (baseline 2. 3. 0d). GMRT2472 Two Requirements for Data Recorders on Trains 16-015-DEV Class 387 Issue 2. Compliance to GMRT2472 All clauses. The scope of this deviation is for all Class 387 vehicles whose application for authorisation is based on conformity to Type UKTYPE/51/2015/0012 (Class 387 proxy Type reference). The deviation is applicable for all routes over which the Class 387 vehicles will operate. GMRT2131 One Audibility and Visibility of Trains. 16-014-DEV Class 387 Issue 1. Compliance to GMRT2131 All clauses GIRT7016 Five Interface between Station Platforms, Track and Trains 16-012-DEV Waterloo Station Platforms 1 - 6 Platform cross fall. 11.1.3 GIRT7016 Five Interface between Station Platforms, Track and Trains 16-010-DEV Waterloo Station, Platforms 3 to 6 Reduced Platform Widths at Country Ends. 7.3.1 (c) and 7.4.1 Current Deviations Register as at 09 May 2016 Nature and Degree The application design for the project was completed in early 2015, and an Engineering Acceptance Certificate for 37668 was issued in August 2015 to allow dynamic testing. This was against Issue 1 of GMRT2472. The design for 37669 is identical, but fitment has been delayed. This means that the compliance date for issue 2 of GMRT2472 has now passed. The proposed On Train Monitoring Recorder (OTMR) and Juridical Recording Unit (JRU) are fully compliant with Issue 1, but do not meet certain specific requirements of Issue 2. Full compliance would require modifications to the existing design and installation, which would introduce further delay and cost with minimal benefit. Risk Assessment/Safety Justification Applicant Organisation The proposed protection parameters are West Coast Railway slightly less extreme than those specified in Issue 2. However, they still provide a very high level of protection in the event of an emergency, and are in line with the existing installations on a large number of vehicles, which can be considered to be reference systems in Common Safety Method (CSM) terms. The possible impact on data survivability in the event of an accident is small, and has no direct safety consequences. The proposed orange colour is easily recognisable and identical to a large number of existing data recorders. There is no impact on the ability to identify and locate this item. Certificate Issue Date 01/04/2016 Certificate End Date N/A Lead SC Rolling Stock Lead SC Approval Date 11/03/2016 Deviation Status Current Compared to GMRT2472 Issue 1, the requirements of GMRT2472 Issue 2 specify new and more demanding survivability requirements for the Crash-Proof Memory, additional data to be recorded, more onerous recording performance requirements (I. e. faster speed to record data), new reliability figures, and new requirements related to both maintainability and data retrieval. These new requirements cannot be met by the current Class 387 OnTrain Data Recorder (OTDR). Therefore, to achieve full compliance with GMRT2472 Issue 2, a new OTDR will need to be fitted to the Class 387 vehicles. Bombardier has been working with the supplier HaslerRail to develop a GMRT2472 Issue 2 compliant solution for the fully TSI-compliant Class 345 Crossrail design. This solution is not electrically compatible with the Class 387 design because of the introduction of a new electronic interface with the Trains Control and Management System (TCMS). In addition, the OTDR unit has larger physical dimensions and higher mass because of the significant difference in the level of protection of the data required, so that the new OTDR unit does not physically fit in the existing space envelope. To implement the The scope of this deviation is for all Class Visibility The differences between 387 vehicles whose application for GMRT2483 Issue 1 and GMRT2131 Issue 1 authorisation is based on conformity to Type are significant; GMRT2131 Issue 1 specifies UKTYPE/51/2015/0012 (Class 387 proxy different requirements for the dimensions of Type reference). The deviation is applicable the lights, beam intensity and beam pattern, for all routes over which the Class 387 introduces new dimming control functionality vehicles will operate. and different measurement criteria etc. Therefore, a design solution that could meet both standards is not achievable. Bombardier has been working with the supplier Translec to develop a GMRT2131 compliant solution for the fully TSI-compliant Class 345 Crossrail design; it is expected to reach design finalisation by March 2016. This new Translec design solution does not fit within the Class 387 head/tail/marker light space envelope and has a different control unit to achieve the newly specified dimming functionality. To implement the solution in the Class 387 vehicles will require a new bracket mounting arrangement, modification to the wiring schematics and redesign of the GRP front end. The Class 387 design has been in production continuously since May 2014; the production of the next 'batch' of Class 387 vehicles which require authorisation (as conforming to Type) will commence in March 2016. However, modifying the Class 387 design to Waterloo Station Platforms 1 - 6 Waterloo Station Platforms 1 - 4 are being extended and Platforms 5 - 6 are being altered in order to facilitate a new track layout. Whilst platform extensions will have compliant falls those areas of associated platform which will require re surfacing will not have compliant falls Provision of compliant falls is not practicable due to cost and programme considerations. The design proposes to retain the existing platform construction, where the track alignment allows this and the platform edge positions to be adjusted to compliant offsets to the new track alignment. The crossfalls shall be improved as far as reasonably practicable in doing so. Note that Platform 7-8 is not considered within the scope of this derogation as the modifications to this platform only comprise re-positioning of platform edge copers as opposed to complete platform reconstruction works. It is considered that there is no negative impact from complying with GMRT2472 Issue 1 instead of GMRT2472 Issue 2. The revised GMRT2472 Issue 2 requires the recording of additional data and a greater level of protection capability for data survivability. The OTDR only records and stores data that can be analysed in the event of an incident; the recording of additional information does not by itself improve the safety of the vehicles. This is reflected in GMRT2472 Issue 2 itself, since it does not mandate to bring existing rail vehicles into compliance. The revised requirements in GMRT2472 Issue 2 do not have an effect on the ability of the unit to meet the essential requirement that trains must be fitted with a recording device. The Class 387 design is now almost life-expired because of the June 2017 transition phase for introducing nonTechnical Specification for Interoperability (TSI) compliant rolling stock. Therefore, this application is for a limited number of units only. In order to comply with the requirements of GMRT2472 Issue 2 would require fitting a proportionally small number of trains with a different Data Recorder to that used across a fleet of several hundred trains. This would necessitate a separate It is considered that there is no negative impact from complying with GMRT2483 Issue 1 and GMRT2484 Issue 2 instead of GMRT2131 Issue 1. With respect to audibility, the requirements in GMRT2484 Issue 2 and GMRT2131 Issue 1 are equivalent - as stated in the relative impact assessment - and therefore there is no difference in complying with GMRT2484 Issue 2 instead of GMRT2131 Issue 1. With respect to visibility, the additional Class 387 units (which conform to the authorised Class 387 Type design) are fully compliant with GMRT2483 Issue 1. As stated by impact assessment 15 IA22, GMRT2483 Issue 1 reflects the existing UK operating conditions. Therefore, modifying existing designs to achieve compliance with GMRT2131 Issue 1 instead of GMRT2483 Issue 1 will not improve the safety of the railway system. This is reflected in GMRT2131 Issue 1 itself, since it does not mandate to bring existing rail vehicles into compliance. Continued compliance with GMRT2483 Issue 1 and GMRT2484 Issue 2 will avoid any design incompatibility among the Class 387 fleet, with significant benefits to the Operators in terms of operational and maintenance costs. In addition, the Class 387 design is now There is no worsening of the current situation. 27/04/2016 N/A Rolling Stock 11/03/2016 Current Bombardier Transportation, on 27/04/2016 behalf of, Great Western Railway, Porterbrook Leasing N/A Rolling Stock 11/03/2016 Current Network Rail 15/04/2016 N/A Infrastructure 02/03/2016 Current Waterloo Station, Platforms 3 to 6 Reduced Platform Widths at Country Ends. This programme of work increases capacity Network Rail at Waterloo Station and other outlying stations helping to relieve passenger congestion and improving passenger comfort. Whilst the proposed platform lengthening will introduce non-compliant widths, the proposal has been assessed to bring significant benefits to passenger capacity and congestion relief for the current and future operation of the station. We strongly believe this to be a reasonable approach and the scheme is supported by our stakeholders. 15/04/2016 N/A Infrastructure 02/03/2016 Current Wessex Capacity Programme is extending and altering platforms at Waterloo Station in order to improve overall capacity into Waterloo Station. It is not practicable to provide compliant platform widths, particularly as some platforms are already non-compliant to the requirements of the standard. Platforms 3 - 6 will have noncompliant widths at their country ends. Platforms 3 and 4 are to be extended to accommodate ten-car class 458 trains. To accommodate the required changes in track layout platforms 5 and 6 will be shortened and a large portion will be rebuilt. A number of pinch points exist on the approach route to Waterloo Station which limit the geometry of the track the main pinch point being the bridge structure to Westminster Road Bridge. The track layout is also limited by operational requirements such as achieving 18 trains per hour during peak operations. Bombardier Transportation, Great Western Railway, Porterbrook Leasing Page 3 Deviations Register RGS Number GIRT7016 RGS Issue Number Five RGS Title Interface between Station Platforms, Track and Trains Certificate Number 16-009-DEV Title Maryland Station, Platform 1, 2 and 3, Restricted Platform Width. RGS Clause 6.2.2 b) Scope For the 3. 90 m length of the platform 2/3 lift, on both the platform 2 and 3 sides of the lifts. For a 3. 88 m length of platform 1 eastwards from the corner of the new lift shaft. GKRT0045 Four Lineside Signals, Indicators and Layout of Signals 16-003-DEV Bristol signal B25, situated to the East of Bedminster Station on the MLN1 at 119M 2Ch. 5.1.2.4 Bristol signal B25, situated to the East of Bedminster Station on the MLN1 at 119M 2Ch. GKRT0044 Three Permissive Working 16-002-DEV Doncaster Station Area Capacity Enhancements - Provision of Signalling Controls for Permissive Working. 3.2.1c, 3.2.2 GERT8000-TW5 Six Preparation and movement of trains. Defective or isolated vehicles and on-train equipment 16-001-DEV Emergency bypass switch (EBS) requirement for competent person. 11.2 Current Deviations Register as at 09 May 2016 Nature and Degree The minimum practical width of a new lift shaft structure, together with the existing constraints arising from the platform layout and adjacent structures (the platform 1 retaining wall) are such that platform widths of 2. 5 m or greater cannot be achieved alongside the new lifts. The new lifts are proposed so as to provide improved access to the platforms for passengers of reduced mobility, including the disabled, who would be unable to use the stairs, or who could only use the stairs with difficulty. The internal width of the lift cars is set to achieve compliance with the requirements of the Department for Transport (DfT) "Design Standards for Accessible Railway Stations". Bristol signal B25 (BL2166 by new WMSR numbering system) is currently mounted on a two track cantilever with B27 (BL2168): both are 4 aspect signals. B25 is applicable to the Up Relief, for an Up direction move and B27 is applicable to the Up Main, also in the Up direction. B27 has Junction Indicators at positions 4 and 5, but B25 is now mounted on the upright column of the structure and is provided with Alphanumeric Route Indicators in place of the former Junction Indicators at positions 4, 5 and 6. The linespeed on the approach to B25 is 40 mph, but there is a 25 mph Permanent Speed Restriction at the toes of 769B points which applies to all routes available from B25. B25 has four recorded Category A Signals Passed at Danger (SPADs) in recent years (22/12/1993, 04/07/2003, 02/07/2006 and 27/12/2011). Three of the SPADs have been recorded as being due to 'reading wrong signal' [B27]. The SPAD investigation recommended the relocation of the signal onto a straight post in order to reduce the possibility of any crossreading with B27. It is not possible to site B25 provided with Junction Indicators on a straight post due to the limited space available between the Up Relief and the This deviation is specifically associated to Not all the controls specified within signals reading into Doncaster Station GKRT0044 (3. 2. 1c and 3. 2. 2) are platform 1 (D279) from the South. It is currently provided for Doncaster area. specific to permissive routes from signals Drivers within the area are aware of the D269, D1465, D1467 and D1471. current arrangements, and application of these controls would create unnecessary interlocking works and limited safety benefit for the Doncaster Station area enhancements scheme. Whilst the controls stipulated within Sections 3. 2. 1 and 3. 2. 2 are achievable in the detailed wiring design, provision of these controls would result in the following: The introduction of conflicting controls in the Doncaster interlocking, which could result in an unsafe arrangement. The signaller at Doncaster will retain the ability to signal trains from other signals for the purposes of attaching and detaching, utilising the existing controls provided by the Westpac circuitry without the inclusion of the requirements listed above. The introduction of a potentially confusing operational arrangement to the signaller and driver where the controls would differ for similar signalled moves. The introduction of novel and complex free-wired circuitry in the Doncaster interlocking including the requirement for additional new free wired relays. The introduction of additional All Great Western Routes, provided the If it is necessary to operate the EBS on a distance is specified within the Defective On- train in service and it is formed of more than Train Equipment (DOTE) plan. one unit, unless it is possible to move all the passengers into the front unit, it is necessary to detrain the passengers at the first suitable station. This then means that the train would be required to enter service as Empty Coaching Stock (ECS) from that station. Clause 11. 2 requires that, if a train on which the EBS has been operated is to enter service as ECS to travel to a maintenance depot, and it is formed of more than one unit, a guard or competent person has to travel in the rear unit. If the train was being worked driver only, it is unlikely that there will be anyone immediately available to act as a competent person. In such situations, it takes about an hour for a competent person to reach the train. At most locations, this means that the line in one direction is blocked for that entire time as the train is not permitted to make any movement until a competent person is provided. This delay is in addition to that already incurred by the defect that resulted in the requirement to operate the EBS. An incident of this type on the Great Western network on 09/11/2015 caused c1400 minutes of delay, 21 cancellations and caused significant crowd Risk Assessment/Safety Justification The original scope of the Crossrail project would have left seven stations that are to be served by Crossrail trains without step free access to the platforms, one of which is Maryland station. This station was reconstructed in the 1940s with a new four track layout, and with a new station building and new access steps to the four platforms. That reconstruction resulted in platform widths of less than 2. 5 m on platforms 1, 2 and 3 at locations adjacent to the stairs that provide access from the station structure above. The platforms are located in a cutting bounded by retaining walls, with the wall to the rear of platform 1 being a reinforced concrete structure. The attached drawing MMD-336583-C-SK-MYL-0005 provides key dimensions for the current layout. Following feasibility and option selection studies, a preferred scheme for the provision of lifts to provide step free access to all platforms was selected. The layout of the proposed lifts for platforms 1, 2 and 3 is shown on the attached drawing MMD336583-C-SK-MYL-0005 and 0006 The lift to serve platform 4 will be located in existing platform buildings, and does not affect the clear width of platform 4. The proposed lift structure on platform 1 will replace an N/A Applicant Organisation Mott MacDonald on behalf of, Rail for London Certificate Issue Date 23/03/2016 Certificate End Date N/A Lead SC Infrastructure Lead SC Approval Date 02/03/2016 Deviation Status Current Network Rail 07/03/2016 31/12/2017 Control Command and Signalling 18/02/2016 Current 07/03/2016 N/A Control Command and Signalling 18/02/2016 Current 01/03/2016 31/12/2018 Traffic Operation and Management 02/02/2016 Current The implementation of the projects proposal Network Rail will affect the below by: The safety of the railway system We are proposing to implement a proven, tried and tested method of permissive working that is consistent with the existing approach within that specific area. The compatibility of the railway system now and in the future The project approach is to provide a consistent compatible method of permissive working for the existing railway system/operation. It is envisaged that this would simplify future alterations/upgrades. Costs and service performance, including reliability and availability by delivering the same functionality as existing is the most costeffective method for the project to deliver the works. If it became a requirement to achieve full compliance to the standard, the increased complexity of the physical works and the conflicting approach with providing the additional controls could have a negative impact on the service provided. Reference should be made to Risk Assessment Ref. 139058/SIG/RA/001 that was carried out to form the projects opinion. The risk assessment method to be adopted is qualitative, with expert judgement being the primary method for assessing the risks The risk of operating a train formed of more Great Western Railway than one unit with the EBS raised is that, if the train becomes divided, no brake application is automatically made on the front portion and the driver is likely to be unaware that a division has taken place. The brakes will automatically apply on the rear portion. No changes are intended to be made to the existing arrangements for detraining passengers, if it is necessary to operate the EBS on a train in passenger service. Consequently, the risk of passengers travelling in the rear portion of a divided train are unchanged. The revised arrangements are only intended to be applied on lines signalled by TCB so, in the event of a train division, the rear portion will be protected by the signalling system. Clause 11. 2 already requires the signaller to be told that the train is travelling with the EBS operated. The revised arrangements should avoid some of the present significant delays that result when it becomes necessary to operate the EBS on a driveronly passenger train formed of more than one unit. Page 4 Deviations Register RGS Number GCRT5021 RGS Issue Number Four RGS Title Track System Requirements Certificate Number 15-136-DEV Title Windsor branch siding track gradient. RGS Clause 2.8.2.1 GIRT7016 Five Interface between Station Platforms, Track and Trains 15-135-DEV City Thameslink Station, Platforms 1 and Platform 2Reduced headroom to CIS screens. 8.1.1 GIRT7016 Five Interface between Station Platforms, Track and Trains 15-134-DEV. Ealing Broadway Station - Island Platform 2 and 3 mid-platform fencing. 6.2.2 (a) GERT8000-S5 Six Passing a signal at danger or an end of authority (EoA) without a movement authority (MA) 15-133-DEV High Output Track Renewals System (TRS) 1.1 Protection Zone Trials Current Deviations Register as at 09 May 2016 Scope The Slough Side of Bath Road Overbridge at 18m 1705yds (CH1040550). ELR - WIN Mileage - 18m 1460yds to 18m 1705yds Nature and Degree As part of the route funded relock/recontrol, Crossrail West Outer are amending the existing track layout on the Windsor Branch near Slough station. A key component of these works is removing the existing connection between the East Loop and the Windsor Branch (328a/b pts) and converting the East Loop into a cripple siding which will terminate on the Slough Side of Bath Road Overbridge at 18m 1705yds (CH1040550). The existing East Loop falls at an average of 1 in 158 towards Windsor (away from the main line) over the 215 m in front of the proposed buffer position. Following the proposed track renewal works the Cripple siding will fall at an average of 1 in 161. 527 from the newly installed 8313 pts to the new buffer. The specification for the proposed works requires the Windsor Branch to be lowered under Bath Road Overbridge sufficiently that the resultant clearances provide for future electrification. This fixed point at 18m 1740yds along with the existing Switches and Crossings (SandC) at 18m 1340yds severely restrict the ability to make any meaningful difference to the vertical alignment of the East Loop meaning compliance cannot be achieved. Standard states that sidings should not be steeper City Thameslink, Platforms 1 and Platform 2 At City Thameslink Station, the Thameslink Design Type: Infotec TR Series TFT Programme shall be installing six number displays TR32P. lRefer to attached schedule banks of Customer Information System (CIS) which shows the proposed CIS Display displays on both platforms (platforms 1 and offsets. 2), each bank consisting of four number 32" Thin Film Transistor (TFT) displays. The N423 CIS enhancements project has a requirement to show enhanced train service information appropriate for a 24 trains per hour (tph) timetable; to meet this requirement the project need to replace the existing Infotec P2014 displays as these can only display details of the next four trains at each platform which is appropriate for the current lower frequency train service but not for 24 tph. The project is proposing to install 32" TFT displays which will be able to show details of the next eight trains at each platform to meet the requirements to show enhanced train service information for a 24 tph train service. The CIS displays will also show a train pictogram to show where to wait and train facilities so that, for example, PRMs can board the train in the correct location reducing dwell time. A signal sighting review has confirmed that the placement of the six number banks of TFT displays on Platforms 1 and 2 has no impact to the current operational railway. The Ealing Broadway Station - Island Platform 2 This deviation will allow a retractable barrier and 3. to be fitted on the island platform between the up main line and the down relief line at Ealing Broadway. A current station building is situated in middle of the island platform which prevents the fence being placed 3000 mm from the line. The fence will be noncompliant for a short length adjacent to the waiting room, with a minimum clearance of 2800 mm. The line Speeds are: Up Main Platform 2 - 125 mph Down Relief Platform 3 - 90 mph. A retractable fence will be between the bottom of the staircase and the current waiting room in the middle of the platform but this retracts into a nonoperational area and the 'do not pass this point' sign will be moved to ensure this. Not installing the fence is severely negating the potential benefit of the current fencing already installed at the London end of Ealing Broadway as it still allows free access to the main lines at the point at which members of the public access the platform. Given the location of Ealing Broadway within the rail network and the volume of services in the area which are affected by fatalities at the station, the consequences of not fencing the whole length of the island platform will see the problem continue to cause severe issues The temporary deviation will be used to 1) Rule Book Module S5 - Section 1. 1 This carry out trials nationally on all routes on clause lists the occasions when a Signal can Network Rail infrastructure. The trials will be passed at danger or an end of authority be restricted to non-DC electrified areas with (EOA) to be passed without a movement single and double track lines in track circuit authority (MA). A temporary deviation is block areas that do not have axle counters, required to add an TRS Protection Zone to level crossings or ground frames. the list in sub clause 9 to allow an On-Track Machine (OTM) to pass a signal at danger towards a High Output TRS Protection Zone. The trials will be controlled and managed to a strict and risk assessed methodology by the TRS Services project. Each location will have their own trial team that will run the day to day trialling whilst reporting into the main project team. With supplementary protection in place, the OTM is fully protected from coming into contact with other traffic on that line. Risk Assessment/Safety Justification Applicant Organisation The risk assessment supporting this Network Rail application has identified the following controls and mitigation: The facility will only be used for turnback moves, when the trains will be occupied by drivers, or for temporary stabling of failed units so will be used infrequently. The installed buffer stop has been risk assessed in line with GCRT5033 and has been specified according to the rolling stock that will be located in the siding and will have countdown markers and a red 'stop' light. Stabled, crippled trains will be located close to the buffer stop so momentum towards the buffer stop will be reduced. The fall within the siding is away from the connection with the branch through line and is therefore away from operational traffic. Alignment of the siding is parallel to the branch line I. e. not towards the running lines Bridge structure sits beyond extended wing walls which retain a heavily vegetated embankment; any train run through would impact this feature and not the bridge structure itself - as indicated in the buffer stop risk assessment. Certificate Issue Date 15/02/2016 Certificate End Date N/A Lead SC Infrastructure Lead SC Approval Date 05/01/2016 Deviation Status Current The proposed headroom clearances of 2300 Network Rail mm would not cause any safety issues related to train movements, alighting between train and platform or public safety at this station. A signal sighting review has confirmed that the placement of the six number banks of TFT displays on Platforms 1 and 2 has no impact to the current operational railway. 27/01/2016 N/A Infrastructure 05/01/2016 Current The Island platform is between the down Network Rail relief line and the up main line. The up main platform is 125 mph through the station and is only used during perturbation or planned engineering works. There have been 13 fatal incidents in the last 5 years, a majority involving the person stepping onto the line from a mainline platform. The flow of pedestrians in peak hours prevents the usual style of mid-platform fence being used as it needs to be retractable to allow passengers to flow around the building when passengers numbers are high. The fence will be retracted and gate opened on any occasion when the main line platform is in use and the platform is monitored by a security guard as well as the station staff. 27/01/2016 31/08/2018 Infrastructure 05/01/2016 Current Once the trials have been successfully Network Rail completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames, with final trials being looked at for axle counter areas and including DC electrified areas. Whilst the TRS Protection Zone is in place and there is a requirement to have a ZKL Track Circuit Operating Device (TCOD) in place when the TRS Protection Zone is granted and therefore the signal protecting will be held at danger, this request is to allow additional OTM's to be allowed into the TRS Protection Zone and authority for the Signaller to grant the movement in accordance with the conditions in S5. The application will support the trial of the TRS Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation). The Safe and Efficient Access Safety Case The SEA risk assessment The SEA detailed procedure The HO protection form The SEA trial record sheet The various SEA briefing 12/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current Page 5 Deviations Register RGS Number GERT8000-OTM RGS Issue Number Seven RGS Title Working of on-track machines (OTM) GERT8000-HB12 Five Duties of the engineering supervisor (ES) or 15-131-DEV safe work leader (SWL) in a possession High Output Track Renewals System (TRS) 3, 10 Protection Zone Trials. GERT8000-HB7 Five General duties of a controller of site safety (COSS) 15-130-DEV High Output Track Renewals System (TRS) 4.4 Protection Zone Trials. GERT8000-TW7 Six Wrong-direction movements 15-129-DEV High Output Track Renewals System (TRS) 1.1, 1.2 Protection Zone Trials. Current Deviations Register as at 09 May 2016 Certificate Number 15-132-DEV Title RGS Clause High Output Track Renewals System (TRS) 4.1, 4.2 Protection Zone Trials. Scope The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. Nature and Degree Clause 4. 1 stipulates that the work will not require wrong direction movements (except as described for the rail grinding train), the on-track machine (High Output TRS and OnTrack Machine (OTM)) that will be trialled as part of the TRS Protection Zone procedure (Tampers) need to make at least 2-3 wrong direction movements as part of their normal method of operation. The clause also stipulates that a machine may so work if signalled as an Engineering train requiring to stop in section, but not on a Track Circuit Block (TCB) lines or where intermediate block signals are provided. Clause 4. 2 stipulates that the driver must tell the signaller that the OTM will be working outside of a possession as part of the trials of the TRS Protection Zone procedure there is not requirement for the driver to do this as the signaller will be made aware by the published Weekly Operating Notice (WON) notice and the On Train Manager. So a temporary deviation is sought to allow trials of the TRS Protection Zone procedure on track circuit block lines and to allow the OTM to make wrong direction movements as required. The trials will be controlled and managed to a strict and risk assessed methodology by the TRS Services project. The temporary deviation will be used to The project requires the addition of the TRS carry out trials nationally on all routes on Protection Zone as trials to take reason why Network Rail infrastructure. The trials will a line should be considered to be blocked to be restricted to non-DC electrified areas with allow place to evaluate the procedure. single and double track lines in track circuit These trials will be controlled and managed block areas that do not have axle counters, to a strict and risk assessed methodology by level crossings or ground frames. the TRS Services project. Each location will have their own trial team that will run the day to day trialling whilst reporting into the main project team. . With supplementary protection in place the On-Track Machine (OTM) is fully protected from coming into contact with other traffic on that line. The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. This clause documents the ten occasions when a signaller may authorise the driver to make wrong direction movement for which a signal is not provided. A temporary deviation is required to allow wrong direction movements to be authorised as part of this proposed method of work as none of the ten existing circumstances apply. The trials will be controlled and managed to a strict and risk assessed methodology by the TRS Services project. Each location will have their own trial team that will run the day to day trialling whilst reporting into the main project team. With supplementary protection in place, the OTM is fully protected from coming into contact with other traffic on that line. Risk Assessment/Safety Justification Applicant Organisation Once the trials have been successfully Network Rail completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames, with final trials being looked at for axle counter areas and including DC electrified areas. The application will support the trial of the TRS Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation). The Safe and Efficient Access Safety Case The SEA risk assessment The SEA detailed procedure The HO protection form The SEA trial record sheet The various SEA briefing documents. Certificate Issue Date 12/02/2016 Certificate End Date 31/12/2017 Lead SC Traffic Operation and Management Lead SC Approval Date 15/12/2015 Deviation Status Current To allow trials of the TRS Protection Zone Network Rail procedure to go ahead a deviation is required against clauses 3 and 10 to allow a ES/SWL to be identified within TRS Protection Zone and for them to be used to setup a safe system of work. Once the trials have been successfully completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames. With final trials being looked at for axle counter areas and including DC electrified areas. The deviation will support the trial of the TRS Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation) . The Safe and Efficient Access Safety Case The SEA risk assessment The SEA detailed procedure The HO protection form The SEA trial record sheet The various SEA briefing documents. 12/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current Once the trials have been successfully Network Rail completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames. With final trials being looked at for axle counter areas and including DC electrified areas The application will support the continuing trial of the TRS Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation). The Safe and Efficient Access Safety Case The SEA risk assessment The SEA detailed procedure The HO protection form The SEA trial record sheet The various SEA briefing documents. 12/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current So the temporary deviation is to allow trials Network Rail of the TRS Protection Zone procedure by allowing the On-Track Machine (OTM) authorised to make wrong direction movements for which no signal is provided as required, as well as asking for the OnTrain Manager to be added to the list of people who can authorise the OTM driver to make a wrong direction movement. Once the trials have been successfully completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames, with final trials being looked at for axle counter areas and including DC electrified areas. The application will support the operation of Multiple on-track machines working on a line not under possession, the method of operation can be found in the application and will support the trial of the TRS Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation). The Safe and Efficient Access Safety Case The SEA risk 12/02/2016 31/12/2017 Traffic Operation and Managementy 15/12/2015 Current Page 6 Deviations Register RGS Number GERT8000-TW5 RGS Issue Number Six RGS Title Preparation and movement of trains. Defective or isolated vehicles and on-train equipment Certificate Number 15-128-DEV Title RGS Clause High Output Track Renewals System (TRS) 4.4, 4.5, 22.2, 22.3 Protection Zone Trials. Scope The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. Nature and Degree A temporary deviation is required to allow Automatic Warning System (AWS) to be isolated on an OTM when the OTM is in working mode on a line not under a T3 possession. These clauses relate to train borne defective/isolated Automatic Warning System and Track Circuit Actuators. These clauses instruct the driver that the signaller must be informed immediately of defective/isolated equipment and that further movement must not be made until authorised. The clauses go on to document what action must be taken before the train can proceed. The project requests that the On-Track Machine (OTM) driver does not need to comply with these clauses as part of the High Output TRS Protection Zone trials. The trials will be controlled and managed to a strict and risk assessed methodology by the TRS Services project. Each location will have their own trial team that will run the day to day trialling whilst reporting into the main project team. With supplementary protection in place, the OTM is fully protected from coming into contact with other traffic on that line. GERT8000-TW1 Ten Preparation and movement of trains 15-127-DEV High Output Track Renewals System (TRS) 46 Protection Zone Trials. The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. This clause documents that the driver of a train can ask the signaller to stop trains on any adjacent line which would otherwise put the driver's personal safety in danger. The occasions that are listed for doing this include when an On-Track Machine (OTM) driver requires to check working equipment is correctly positioned before or after an OTM carries out work. The 'Safe and Efficient Access' project believes that the person setting up the safe systems of work at the site should be the Safe Works Leader (SWL) / Engineering Supervisor (ES). These trials will be controlled and managed to a strict and risk assessed methodology by the TRS Services project. Each location will have their own trial team that will run the day to day trialling whilst reporting into the main project team. The project believes that only having one person setting up safe systems of work for the TRS Protection Zone procedure will remove the possibility of confusion and incident by restricting the communications to the signaller and the On Train Manager only. GERT8000-TS1 Ten General signalling regulations 15-126-DEV High Output Track Renewals System (TRS) 13.2.1 Protection Zone Trials. GERT8000-TS11 Two Failure of, or work on, signalling equipment - 15-125-DEV signallers' regulations Current Deviations Register as at 09 May 2016 High Output Track Renewals System (TRS) 1.5 Protection Zone Trials. Risk Assessment/Safety Justification Applicant Organisation Once the trials have been successfully Network Rail completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames, with final trials being looked at for axle counter areas and including DC electrified areas. Going trials on London North Eastern (LNE) and Anglia which will continue but will include all routes within Network Rail. The application will support the trial of the TRS Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation). The Safe and Efficient Access Safety Case The SEA risk assessment The SEA detailed procedure The HO protection form The SEA trial record sheet The various SEA briefing documents. The temporary deviation is required to allow Network Rail the SWL/ ES to take the block on behalf of the OTM driver as part of the trials of the Track Renewals System (TRS) Protection Zone procedure. Once the trials have been successfully completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames, with final trials being looked at for axle counter areas and including DC electrified areas. The application will support the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe Efficient Access detailed procedure. The procedure has been designed around one person being in charge of setting up all safe systems of work (SSoW) for all staff working within the TRS Protection Zone. The present clause allows only the driver to get the block of an adjacent line. The alteration of the clause would remove the requirement for the driver to take a line blockage of the adjacent line and increase the likelihood of the block being granted in an efficient manner - co-ordinated with other work. The project aim is to improve track worker safety by removing the need for possession Rule Book Module TS1 - Clause 13. 2. 1: This temporary deviation is required to allow Network Rail This clause allows a SWL/COSS /PC to the SWL / ES to block line with a Protection block the line for staff to work on a line Zone without using any other formal blocked to all movements expect those blockages as laid down in 13. 2 of TS1. The recognised to work within the Line Blockage, deviation is required to allow an SWL or ES A temporary deviation is sought to enable to request a line to be blocked to create a the SWL / Engineering Supervisor (ES) to protection zone for an TRS to work, with the formally protect both the TRS train and staff TRS standing at an agreed location, and for on a line. This would allow just the ES/SWL a tamper to enter the blocked line to set up safe systems of work in the most subsequently. The arrangements to be efficient manner at the site, therefore applied, including documentation would be removing possible confusion. as set out in the documentation issued for the trials of the arrangements. The Protection Zone would, during the trial, become a recognised way of blocking the line in conjunction with all other deviations associated with this application. Once the trials have been successfully completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames. With final trials being looked at for axle counter areas and including DC electrified areas. The deviation will support the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe Efficient Access detailed procedure. The procedure has been designed around The temporary deviation will be used to This clause relates to signalling equipment Normally, an RT3187 form is completed Network Rail carry out trials nationally on all routes on being disconnected and, when a form when any signalling equipment is Network Rail infrastructure. The trials will RT3187 should be used, the project disconnected outside of a Line Blockage or be restricted to non-DC electrified areas with requests that the RT3187 form is not used T3 Possession, or if it affects the normal single and double track lines in track circuit during the TRS Protection Zone for the passage of trains or needs the signaller's block areas that do not have axle counters, disconnection of any equipment wholly cooperation, or will affect the normal level crossings or ground frames. within the Protection Zone which is outside operation of the equipment. Whilst the TRS of a Line Blockage or T3 Possession. If the Protection Zone is in place, some equipment disconnection continues past the TRS may be disconnected on the line affected Protection Zone, then TS11 would need to and will be reconnected prior to the TRS be complied with. Protection Zone being given up. The deviation will support the trial of the TRS Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation). The Safe and Efficient Access Safety Case The SEA risk assessment The SEA detailed procedure The HO protection form The SEA trial record sheet The various SEA briefing documents. Certificate Issue Date 12/02/2016 Certificate End Date 31/12/2017 Lead SC Traffic Operation and Management Lead SC Approval Date 15/12/2015 Deviation Status Current 12/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current 11/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current 12/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current Page 7 Deviations Register RGS Number GERT8000-S5 RGS Issue Number Six RGS Title Passing a signal at danger or an end of authority (EoA) without a movement authority (MA) Certificate Number 15-124-DEV Title RGS Clause High Output Ballast Cleaner Protection Zone 1.1 Trials. Scope The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. GERT8000-OTM Seven Working of on-track machines (OTM) 15-123-DEV High Output Ballast Cleaner Protection Zone 4.1, 4.2 Trials. The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. GERT8000-HB12 Five Duties of the engineering supervisor (ES) or 15-122-DEV safe work leader (SWL) in a possession High Output Ballast Cleaner Protection Zone 3, 10 Trials. GERT8000-HB7 Five General duties of a controller of site safety (COSS) High Output Ballast Cleaner Protection Zone 4.4 Trials. Current Deviations Register as at 09 May 2016 15-121-DEV Nature and Degree Requirement 1. 1 relates to the occasions when signals can be passed at danger or an end of authority (EOA) to be passed without a movement authority (MA). A temporary deviation is required to add an High Output Ballast Cleaner (HOBC) Protection Zone to the list in sub clause 9 to allow a On-Track Machine (OTM) to pass a signal at danger towards a HOBC Protection Zone. These trials will be controlled and managed to a strict and risk assessed methodology by the HOBC Services project. Each location will have there own trial team that will run the day to day trialling whilst reporting into the main project team. With supplementary protection in place the OTM is fully protected from coming into contact with other traffic on that line. Clause 4. 1 stipulates that the work will not require wrong direction movements (except as described for the rail grinding train), the on-track machine (High Output Ballast Cleaner (HOBC) and On-Track Machine (OTM)) that will be trialled as part of the HOBC Protection Zone procedure (Tampers) need to make at least 2-3 wrong direction movements as part of their normal method of operation. The clause also stipulates that a machine may so work if signalled as an Engineering train requiring to stop in section, but not on a Track Circuit Block (TCB) lines or where intermediate block signals are provided. Clause 4. 2 stipulates that the driver must tell the signaller that the OTM will be working outside of a possession as part of the trials of the HOBC Protection Zone procedure there is not requirement for the driver to do this as the signaller will be made aware by the published Weekly Operating Notice (WON) and the On-Train Manager. The trials will be controlled and managed to a strict and risk assessed methodology by the HOBC Services project. Each location will have their own trial team that will run the day to day trialling whilst reporting into the main project team. With supplementary The temporary deviation will be used to The project requires the addition of the carry out trials nationally on all routes on HOBC Protection Zone as reason why a line Network Rail infrastructure. The trials will should be considered to be blocked to allow be restricted to non-DC electrified areas with trials to take place to evaluate the single and double track lines in track circuit procedure. The trials will be controlled and block areas that do not have axle counters, managed to a strict and risk assessed level crossings or ground frames. methodology by the HOBC Services project. Each location will have their own trial team that will run the day to day trialling whilst reporting into the main project team. With supplementary protection in place, the OTM is fully protected from coming into contact with other traffic on that line. The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines circuit block areas that do not have axle counters, level crossings or ground frames. Rule Book Handbook 7 - Clause 4. 4: This clause lists the occasions when a COSS may use a blocked line to set up a safe system of work. A temporary deviation is required to introduce the HOBC Protection Zone procedure into the list as none of the existing circumstances apply. This clause details that the COSS may use a blocked line as part of the safe system of work but then lays down guidelines on when a line may be considered to be blocked. The COSS must only consider a line to be blocked if at least one of the following applies: The COSS has blocked the line or lines concerned as shown in Handbook 8. The line or lines concerned have been blocked by a PC and the COSS has agreed a safe system of work with that PC as shown in Handbook 8. The COSS's site of work is within an Engineering Supervisor (ES)'s or Safe Work Leader (SWL)'s work site and the COSS has agreed a safe system of work with that ES, as shown in Handbook 9. The COSS's site of work is within a siding and the COSS has agreed a safe system of work with that Person in Charge of Sidings (PICOS), as shown in Handbook 9. The project requires the addition of the High Output Ballast Cleaner (HOBC) Protection Risk Assessment/Safety Justification Applicant Organisation The application is sought to carry out initial Network Rail trials that will be limited to single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames in non-DC electrified areas. Once these trials have been successfully completed the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames. With final trials being looked at for axle counter areas and including DC electrified areas. Whilst the HOBC Protection Zone is in place and there is a requirement to have a ZKL Track Circuit Operating Device (TCOD) in place when the HOBC Protection Zone is granted and therefore the signal protecting will be held at danger, this request is to allow additional OTMs into the HOBC Protection Zone and authority for the Signaller to grant the movement in accordance with the conditions in S5. The application will support the trial of the HOBC Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a Once the trials have been successfully Network Rail completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames. With final trials being looked at for axle counter areas and including DC electrified areas. The application will support the trial of the HOBC Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation): The Safe and Efficient Access Safety Case. The SEA risk assessment. The SEA detailed procedure. The HO protection form. The SEA trial record sheet. The various SEA briefing documents. Certificate Issue Date 09/02/2016 Certificate End Date 31/12/2017 Lead SC Traffic Operation and Management Lead SC Approval Date 15/12/2015 Deviation Status Current 12/02/2016 12/12/2017 Traffic Operation and Management 15/12/2015 Current To allow trials of the HOBC Protection Zone Network Rail procedure to go ahead a non compliance is required against clauses 3 and 10 to allow a ES / SWL to be identified within HOBC Protection Zone and for them to be used to setup a safe system of work. Once these trials have been successfully completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames, with final trials being looked at for axle counter areas and including DC electrified areas. The application will support the trial of the HOBC Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation): The Safe and Efficient Access Safety Case. The SEA risk assessment. The SEA detailed procedure. The HO protection form. The SEA trial record sheet. The various SEA briefing documents. 09/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current Once these trials have been successfully Network Rail completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames, with final trials being looked at for axle counter areas and including DC electrified areas. The application will support the continuing trial of the HOBC Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation): The Safe and Efficient Access Safety Case. The SEA risk assessment. The SEA detailed procedure. The HO protection form. The SEA trial record sheet. The various SEA briefing documents. 09/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current Page 8 Deviations Register RGS Number GERT8000-TW7 RGS Issue Number Six RGS Title Wrong-direction movements Certificate Number 15-120-DEV Title RGS Clause High Output Ballast Cleaner Protection Zone 1.1, 1.2 Trials. GERT8000-TW5 Six Preparation and movement of trains. Defective or isolated vehicles and on-train equipment 15-119-DEV High Output Ballast Cleaner Protection Zone 4.4, 4.5, 22.2, 22.3 Trials. GERT8000-TW1 Ten Preparation and movement of trains 15-118-DEV High Output Ballast Cleaner (HOBC) Protection Zone Trials. GERT8000-TS1 Ten General signalling regulations 15-117-DEV High Output Ballast Cleaner Protection Zone 13.2.1 Trials. Current Deviations Register as at 09 May 2016 46 Scope The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. Nature and Degree This clause documents the ten occasions when a Signaller may authorise the driver to make wrong direction movement for which a signal is not provided. A temporary deviation is required to allow wrong direction movements to be authorised as part of this proposed method of work as none of the ten existing circumstances apply. The trials will be controlled and managed to a strict and risk assessed methodology by the High Output Ballast Cleaner (HOBC) Services project. Each location will have their own trial team that will run the day to day trialling whilst reporting into the main project team. With supplementary protection in place the On-Track Machine (OTM) is fully protected from coming into contact with other traffic on that line. A temporary deviation is required to allow Automatic Warning System (AWS) to be isolated on an On-Track Machine (OTM) when the OTM is in working mode on a line not under a T3 possession. These clauses relate to train borne defective / isolated Automatic Warning System and Track Circuit Actuators. These clauses instruct the Driver that the Signaller must be informed immediately of defective/isolated equipment and that further movement must not be made until authorised. The clauses go on to document what action must be taken before the train can proceed. The project requests that the On-Track Machine (OTM) driver does not need to comply with these clauses as part of the High Output Ballast Cleaner (HOBC) Protection Zone trials The trials will be controlled and managed to a strict and risk assessed methodology by the HOBC Services project. Each location will have there own trial team that will run the day to day trialling whilst reporting into the main project team. With supplementary protection in place, the OTM is fully protected from coming into contact with other traffic on that line. The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. The trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. Clause 46 specifies that the driver of a train can ask the signaller to stop trains on any adjacent line which would otherwise put the driver's personal safety in danger. The occasions that are listed for doing this include when an On-Track Machine (OTM) driver requires to check working equipment is correctly positioned before or after an OTM carries out work. The 'Safe and Efficient Access' project believes that the person setting up the safe systems of work at the site should be the Safe Works Leader / Engineering Supervisor. The trials will be controlled and managed to a strict and risk assessed methodology by the HOBC Services project. Each location will have their own trial team that will run the day-today trialling whilst reporting into the main project team. The project believes that only having one person setting up safe systems of work for the HOBC Protection Zone procedure will remove the possibility of confusion and incident by restricting the communications to the signaller and the On Train Manager only. Risk Assessment/Safety Justification Applicant Organisation A temporary deviation is to allow trials of the Network Rail HOBC Protection Zone procedure by allowing the OTM authorised to make wrong direction movements for which no signal is provided as required, as well as allowing for the On-Train Manager to be added to the list of people who can authorise the OTM driver to make a wrong direction movement. Once the trials have been successfully completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames, with final trials being looked at for axle counter areas and including DC electrified areas. The application will support the operation of Multiple on-track machines working on a line not under possession, the method of operation can be found in the application and will support the trial of the HOBC Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation): The Safe and Efficient Access Safety Case. The SEA risk assessment. The SEA detailed procedure. Once the trials have been successfully Network Rail completed the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames. With final trials being looked at for axle counter areas and including DC electrified areas. The application will support the trial of the HOBC Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe and Efficient Access - a proposal (presentation). The Safe and Efficient Access Safety Case The SEA risk assessment. The SEA detailed procedure. The HO protection form. The SEA trial record sheet. The various SEA briefing documents. The temporary deviation is required to allow Network Rail the SWL / ES to take the block on behalf of the OTM driver as part of the trials of the HOBC Protection Zone procedure. Once these trials have been successfully completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames. With final trials being looked at for axle counter areas and including DC electrified areas. The application will support the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe Efficient Access detailed procedure. The procedure has been designed around one person being in charge of setting up all Safe Systems of Work (SSoW) for all staff working within the HOBC Protection Zone. The present clause allows only the driver to get the block of an adjacent line. The alteration of the clause would remove the requirement for the driver to take a line blockage of the adjacent line and increase the likelihood of the block being granted in an efficient manner - co-ordinated with other work. The project aim is to improve track worker safety by removing the need for This clause allows a Safe Work Leader The temporary deviation is required to allow Network Rail (SWL) / Controller of Site Safety (COSS) / an SWL or ES to request a line to be Protection Controller (PC) to block the line blocked to create a protection zone for a for staff to work on a line blocked to all high output ballast cleaner (HOBC) to work, movements expect those recognised to work with the HOBC standing at an agreed within the Line Blockage. A temporary location, and for a tamper to enter the deviation is sought to enable the SWL / blocked line subsequently without using any Controller of Site Safety (ES) to formally other formal blockages as laid down in 13. 2 protect both the Controller of Site Safety of TS1. The arrangements to be applied, (HOBC) train and staff on a line. This would including documentation would be as set out allow just the ES / SWL to set up safe in the documentation issued for the trials of systems of work in the most efficient manner the arrangements. The Protection Zone at the site, therefore removing possible would during the trial become a recognised confusion. way of blocking the line in conjunction with all other temporary deviations associated with this application. Once these trials have been successfully completed, the project will be looking to increase the scope of the trials to include multiple line complexities and level crossings and ground frames. With final trials being looked at for axle counter areas and including DC electrified areas. The application will support the operation of multiple on-track machines working on a line not under possession, the method of operation can be found in the Safe Efficient Access detailed procedure. The procedure has been designed around the SWL or ES being in charge of setting up all Safe Certificate Issue Date 15/02/2016 Certificate End Date 31/12/2017 Lead SC Traffic Operation and Management Lead SC Approval Date 15/12/2015 Deviation Status Current 12/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current 09/02/2016 31/12/2017 Traffic Operation and Management 15/12/2015 Current 09/02/2016 31/12/2017 Traffic Operations and Management 15/12/2015 Current Page 9 Deviations Register RGS Number GERT8000-TS11 RGS Issue Number Two RGS Title Certificate Number Failure of, or work on, signalling equipment - 15-116-DEV signallers' regulations Title RGS Clause High Output Ballast Cleaner Protection Zone 1.5 Trials. Scope The temporary deviation will be used to carry out trials nationally on all routes on Network Rail infrastructure. Trials will be restricted to non-DC electrified areas with single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames. Nature and Degree This clause relates to signalling equipment being disconnected and when a form RT3187 should be used. The project requests that the RT3187 form is not used during the High Output Ballast Cleaner (HOBC) Protection Zone for the disconnection of any equipment wholly within the HOBC Protection Zone which is outside of a Line Blockage or T3 Possession. If the disconnection continues past the HOBC Protection Zone, then TS11 would need to be complied with. Risk Assessment/Safety Justification Applicant Organisation Normally, an RT3187 form is completed Network Rail when any signalling equipment is disconnected outside of a Line Blockage or T3 Possession or if affects the normal passage of trains or needs the signallers cooperation or will affect the normal operation of the equipment. Whilst the HOBC Protection Zone is in place, some equipment may be disconnected on the line affected and will be reconnected prior to the HOBC Protection Zone being given up. The application will support the trial of the HOBC Protection Zone procedure. Network Rail would like to trial a new form of Protection Zone of the line that allows the operation of multiple on-track machines working on a line not under possession. The method of operation can be found in the Safe and Efficient Access - a proposal (presentation). The Safe and Efficient Access Safety Case The SEA risk assessment The SEA detailed procedure The HO protection form The SEA trial record sheet The various SEA briefing documents. Certificate Issue Date 12/02/2016 Certificate End Date 31/12/2017 Lead SC Traffic Operation and Management Lead SC Approval Date 15/12/2015 Deviation Status Current GIRT7033 Three Lineside Operational Safety Signs 15-115-DEV Flexible Train Arrival Point (FTAP) Trial Extension. 2.1.1 National - All routes. Current Group Standard requirements mean that all trains about to enter a possession have to be authorised to pass a signal at danger. Further authorisation and control is required to bring trains to a stand within the possession to the exact work site. This process requires unproductive time (typically 20 minutes or more) during the possession, which is at odds with the requirement for Network Rail to become more efficient at delivering work generally. The current requirements therefore mean the High Output trains are not being used to best advantage. It is estimated that this process would allow Network Rail 10-20 minutes additional production time on every High Output shift. This could equate to an estimated 50,000 Pounds Sterling increase in production in every shift. The following risks have been identified: As the possession would not be granted until the train is at the FTAP, other train may approach the signage. The risk is if the train overshoots the FTAP. Threats relating to this have been assessed and mitigated. (see FTAP Proposal documentation). From the bow-tie risk assessment, FTAP will not be applied 'near' a level crossing that has not been closed or brought under local control. 'Near' means: from at least 200 m before the striking in point on the approach to a level crossing. to at least 200 m plus the length of train beyond the striking out point after a level crossing. 14/04/2016 31/12/2017 Control Command and Signalling 24/11/2015 Current GERT8075 Two AWS and TPWS Interface Requirements 15-114-DEV Transition between European Train Control System (ETCS) mode SN (class B system Automatic Warning System / Train Protection and Warning System (AWS/TPWS)) and other ETCS modes . 2.2.4.11, 3.2.3.7, 3.2.4.4, 4.2.5.1, 4.2.5.2, 4.2.5.3, 4.2.5.4, 4.2.5.5, 4.2.5.6, 4.2.5.7, 4.2.5.8 Thameslink Class 700 units. N/A Control Command and Signalling 26/11/2015 Current Three Railway Wheelsets 15-113-DEV Trial of Economic Tyre Turning (ETT) on Class 390 Wheelsets with P12 Profiles 4.4.1 Up to five-off Class 390/0 and 390/1 trainsets in the number range 01 to 57. Brake demand less than 59 seconds the behaviour of the train meets the stated intent of the 59 second requirement. It is therefore considered that there is no safety impact of this non-compliance. Putting the train into shunt (SH) mode via the DMI and then deactivating shunt mode - This scenario will not be possible when the Class 700 enters service in the UK. Siemens have inhibited the selection of shunt mode on the ETCS DMI when ETCS operates in Level NTC. Consequently, the driver will not be able to select level SH under any circumstances. Setting the national value of the maximum speed attainable in SH mode to zero from Thameslink provides additional protection to prevent a train moving in this state. It is considered that there is no safety implication from this. Putting the train into another Level, I. e. Level 2 and then back into Level NTC Drivers have not been told during their training of this phenomenon. The risk of a driver identifying this by chance as a means of circumnavigating the 59 second timeout following a TPWS brake demand is very low. If a driver had an intricate understanding of the system and used this as a method of bypassing the timeout, it would be considered a deliberate violation of Findings from the RSSB T641 Research Project and recent work by the University of Huddersfield show that the use of a ETT thin flange wheel profile: Does not compromise safety against derailment (T641 report); Has no significant detrimental effect on vehicle dynamic performance (T641 report); Has no significant impact on rail damage and wear (T641 report and IRR report 110/81);An economic benefit exists (IRR report 110/81). On the basis of the above findings, it is considered that the trial will have no impact on the safety of the railway system or compatibility of the trial trainsets with the West Coast Main Line infrastructure. Undertaking of the trial will require an additional cost, related to monitoring the inservice performance of the ETT P12 wheel profiles and the undertaking of a Ride Quality assessment. However, provided that the trial is successful, then it will further support the introduction of ETT wheel profiles, which will produce the industry benefits identified in Section 10. 21/01/2016 GMRT2466 Testing of the class 700 fleet has revealed a number of scenarios in which it is possible to: have a TPWS or AWS triggered brake application which lasts for less than 59 seconds reset a TPWS or AWS triggered brake application by means other than those specified in the standard. These circumstances arise due to the interface requirements between the ETCS and Class B systems specified in the Command Control and Signalling Technical Specifications for Interoperability (CCS TSI). The train implements baseline 3. 3. 0. When the train transitions from ETCS mode SN to another ETCS mode, the TSI requires that the Class B system is reset. Three scenarios have been identified where this is possible. Putting the train into shunt mode (SH) in level NTC;Selecting another ETCS level, then reselecting level NTC;Deactivating the cab and reactivating the cab using the master switch. To comply with the RGS requirement, the CCS TSI (2012/88/EU and 2012/696/EU), Annex A, Table A2, line 4 would need to be modified, see Union of Signalling Industry (UNISIG) Subset-026, chapter 4. 6. 2. The hazard analyses for ETCS modes performed by UNISIG and European Railway Agency The impact of complying with the current RGS requirement is that it limits the useful life of wheel pans. This is because, at each turn the full wheel profile, including a 'full thickness' flange must be recreated. As the wheel pan approaches its scrapping diameter, it is not always possible to recreate the full flange thickness of the wheel profile without reducing the wheel below its last turning diameter. Therefore, at this point, whilst the wheel pans still have usable life remaining, it is necessary for them to be removed and scrapped. This imposes avoidable costs on the industry: In replacing wheels which have some useable life remaining (unavailability of vehicles, unplanned wheelset replacement when wheel pick up damage near the end of their life etc. ). A study by the University of Huddersfield Institute of Railway Research (IRR report 110/81 issue 1) has suggested that saving of between £880K and £5. 1M may be realisable across the GB passenger fleet if RGS permitted Economic Tyre Turning (ETT) at the end of a wheels life; In early replacement of wheelsets at heavy overhaul when they have significant remaining life. ETT could be one of a range of measures that allow maintainers to extend 01/01/2017 Rolling Stock 04/12/2015 Current Current Deviations Register as at 09 May 2016 Govia Thameslink Railway Limited West Coast Trains Ltd (trading 07/01/2016 as Virgin Trains) Page 10 Deviations Register RGS Number GKRT0045 RGS Issue Number Four RGS Title Lineside Signals, Indicators and Layout of Signals GMRT2400 Five Engineering Design of On-track Machines in 15-109-DEV Running Mode Addition of drain at the base of the fuel tank. 2.4.1.1 GCRT5212 One Requirements for Defining and Maintaining Clearances 15-108-DEV Lower Sector Structure Gauge - Raised Check Rails for Tram-Train. GIRT7016 Five Interface between Station Platforms, Track and Trains 15-105-DEV Charing Cross Station - Platforms 1-6 (uncovered sections only). GERT8073 Three Requirements for the Application of Standard Vehicle Gauges 15-104-DEV Clarification of the expression 'is included in 3.1.2.3 the Rolling Stock Library' in clause 3.1.2.3 of GERT8073 Issue 3 Current Deviations Register as at 09 May 2016 Certificate Number 15-111-DEV Title Location: Abbotswood Junction - signal BA 3658. RGS Clause 5.2.3.1 Scope Junction signal BA 3658, ELR: BAG2, Abbotswood Junction. Mileage: 69 miles. Nature and Degree The only practicable and compliant solution is to provide an approach release from red control on BA3658 (the replacement for G59), but this is considered operationally restrictive and a worsening of the current arrangement that train drivers are accustomed to. It may also create a Signal Passed at Danger (SPAD) risk due to driver anticipation. Risk Assessment/Safety Justification Applicant Organisation As part of the Bromsgrove Corridor Network Rail Resignalling project, there is a requirement to renew the signalling between Barnt Green and Ashchurch. Abbotswood junction is currently a 30 mph turnout on a 90 mph section of line. The existing three-aspect junction signal G59 has a single flashing yellow in rear and operations have requested that this is retained as part of the resignalling to ensure that delays are not introduced by a more restrictive approach control. The non-compliance is not considered to be particularly severe and has precedents on the network where existing non-compliant arrangements have been perpetuated at Operations and Train Operating Companies (TOCs) request. The signalling arrangement provides adequate clear and unambiguous routing information for the driver at the earliest opportunity so that he can control the speed of the train safely. The Train Protection and Warning System (TPWS) fitment for BA3658 is fully effective to 6%g. Flashing yellow aspect sequence reduced the likelihood of a SPAD due to non-provision of approach release from red the signal will normally be off when the diverging route is set rather than at red. There is only 10 mph difference between This deviation is for the following vehicle: The second sentence of the above clause Plasser and Theurer have a large number of Plasser UK Ltd TOPS Number: DR74002 EVN: 99 70 9128 mandates 'All openings in the fuel tank shall machines already certificated for operation 002-1. be above the maximum fuel level'. Without on Network Rail Infrastructure (compliant a drain plug fitted to the fuel tank, there with earlier issues of GMRT2400) and fitted would not be the facility to routinely remove with drains at the base of the fuel tank. any condensation build-up. Due to the There have been no problems with this weather conditions in the United Kingdom arrangement. and the working routines in which On-Track Machines are operated throughout the winter months, fuel tanks are highly susceptible to condensation contamination. The machine's fuel tank will quite often be manually re-filled from a barrel, which carries a high risk of water contamination. There is a necessity to drain the water from the tank to reduce the risk of damage to the fuel system. Certificate Issue Date 13/01/2016 Certificate End Date N/A Lead SC Control Command and Signalling Lead SC Approval Date 26/11/2015 Deviation Status Current 07/01/2016 N/A Rolling Stock 04/12/2015 Current G2, G4.1 2m61ch (Tinsley Chord turn out) to 5m59ch (Parkgate turn out), approximately 3 miles. This includes 9 point ends: Tinsley North Junction 2m61chNew turnout 305 pts Tinsley East: 2m79ch2 x existing turnouts 302 and 301B ptsRotherham: 4m40chExisting crossover 4301 A+BExisting turnout 4300 ptsParkgate turnout: 5m59chNew crossover 4002 A+BNew turnout 4000 pts. Not interoperable. 11.1.4 Charing Cross Station - Platforms 1-6 (uncovered sections only) ELR: XTD. Mileage from 0m 4ch to the country ramp ends. Charing Cross station has six existing platforms, which are split approximately at 0m 4ch) between a covered and uncovered sections. It is not possibly to comply with the gauge requirements and achieve a technically compatible solution. Tram-Train vehicles which have wheels compatible with highway based tram-type track, have a narrower flange, and are not compatible with standard railway check rails. An alternative design of check rail has been developed to interact with the Tram Train wheels at a higher point. This is needed to maintain their checking function whilst maintaining the flangeway clearance for conventional rolling stock wheels. To achieve a check rail design which will perform its function, it must exceed the standard lower sector structure gauge. See RGS deviation and associated documents attached for risk justification argument. See RGS deviation and associated Network Rail documents attached for risk assessment. The clearance is affected and changes from standard clearance to special reduced clearance. The SandC tamper would be capable of operating over the raised check rail, including in tamping mode. 18/12/2015 N/A Infrastructure 11/11/2015 Current Charing Cross station has six existing platforms, which are split (approximately at 0m 4ch) between a covered and uncovered area. The platform in the uncovered area is supported by a steel trestle structure which rests on a trapezoidal steel trough deck. It is understood that the current bridge deck and platforms were installed in the early 1970s. The deck and trestle legs are exhibiting severe corrosion in places. An interim solution comprising a temporary lightweight proprietary `Titan' metalwork structure between the existing platform and steel bridge deck, to provide additional support to the platforms has been installed since December 2013 and maintained since. The original temporary deviation (reference number 13/235/DEV) to allow this installation to proceed was approved in December 2013 with the current temporary deviation (reference number 14/074/DEV) expiring in January 2016. The deviation was originally approved with the proviso that a firm programme to reinstate compliant platforms would be achieved; however, RAM Sponsor personnel changes, access restrictions and project development, design and delivery costs have prohibited works to progress. The scope of this deviation The scope of the deviation is to clarify how Historically, the Carkind descriptors used in Clause 3. 1. 2. 3 can be applied, particularly the Rolling Stock Library to describe in light of changes in the wagon TSI. different vehicle types do not necessarily reliably describe particular vehicle designs. One wagon Carkind descriptor can, for instance, include vehicles with different bogie types or different physical attributes. Similarly, wagons that may have very similar characteristics from a gauging point of view may have been allocated different Carkinds. Furthermore, due to Technical Specification for Interoperability (TSI) and other changing standards requirements, new wagons are likely to differ in detail and Carkind from their similar predecessors when, from a gauging perspective, their physical characteristics may be essentially identical or substantively similar to vehicles that have been in successful operational service for many years. In this situation, the expression `is included in The Rolling Stock Library in R2' is considered to be inadequately precise to avoid the possibility of misinterpretation of its intent with a likely consequential requirement for unintended overly onerous design and acceptance processes and unnecessary contract risk. A local risk assessment has been jointly Network Rail undertaken by Infrastructure Project and Managed Stations to evaluate the possible risks associated with deviation from Clause 11. 1. 4 and to consider possible additional controls to mitigate those risks. The output from further risk assessment will follow following stakeholder HAZID / HAZOP meeting scheduled 23/10/2015. The risks are considered Tolerable. This will be subject to records of events arising since the original deviation was imposed and the findings of the proposed HAZID / HAZOP scheduled by the SE MFF delivery project with Asset team, station management and Train Operating Company (TOC) stakeholder representatives initially for 23/10/2015. The station is a terminal station with the linespeed adjacent to these platforms being 10-15 mph controlled by Train Protection Warning System (TPWS). 09/12/2015 01/12/2018 Infrastructure 11/11/2015 Current It is considered that clarification of the intent Private Wagon Federation of Clause 3. 1. 2. 3: will have no deleterious effect on the safety of the railway system, environmental protection or health. It effectively carries forward the requirement of Clause 2. 1. 2. 2 of the superseded RGS GERT8073 Issue 2. Many thousands of wagons have been accepted for operation under this process with no known detrimental safety consequences. Will not affect the compatibility of the railway system now or in the future. Will avoid the risk of increased unnecessary costs arising from unintended overly onerous design and acceptance processes and the introduction of a new and unnecessary contract risk. 07/01/2016 N/A Rolling Stock 04/12/2015 Current Page 11 Deviations Register RGS Number GIRT7016 RGS Issue Number Five RGS Title Interface between Station Platforms, Track and Trains Certificate Number 15-103-DEV Title Finsbury Park Station - Platform 5/6 particularly Platform 6 side. RGS Clause 6.2.2 Scope Finsbury Park Station is located on the East Coast Mainline at ECM1 @ 02mi 0902yd. The station - orientated north to south - is located in a triangle formed by the local highways: Stroud Green to the north, running northwest-southeast; Station Place to east, running north to south; and Seven Sisters to the south, running southwestnortheast. The station is accessed from street level and is constructed on a series of brick viaducts, with the Network Rail platforms located approximately 6 m above street level. The crown of the LUL running tunnels are approximately 2 m below street level are buried within the London clay strata, with the crowns the lower band of the made ground. Finsbury Park consists of 8no platforms, formed by 4no island platforms (from east to west - Platforms 1/2, 3/4, 5/6, 7/8), with a redundant platform, known as the Milkdock, to the west of the site. This derogation relates only to Platform 5/6 - particularly Platform 6 side. GIRT7016 Five Interface between Station Platforms, Track and Trains 15-099-DEV Leicester station.- Headroom on Platforms. 8.1 Leicester station: Platform 1, Qty 3 x CIS displays; LEI-NTI-001,002 and 003 (2405mm to underside);Platform 2, Qty 3 x CIS displays; LEI-NTI-004,005 and 006 (2335mm to underside);Platform 3, Qty 3 x CIS displays; LEI-NTI-007,008 and 009 (2310mm to underside). GIRT7033 Three Lineside Signs 15-098-DEV Proposed new sign dimensions control the risks for the line MRDs, applicable to the Thameslink core area. 2.2.1.1 GKRT0045 Four Lineside Signals, Indicators and Layout of Signals 15-097-DEV Swindon Area Signalling Renewal: Swindon 5.2.3.1 Station Flashing Aspect Sequences (Down Direction). The proposed variation will be applicable to the Swindon Area Signalling Renewal (SASR): Swindon Station Flashing Aspect Sequences (Down Direction). At the eastern approach to Swindon Station, flashing yellow aspect sequences from the Down Main SW1155 signal to Platform 1 SW1209 signal. Scheme Plan No. 11-GW-009/02 Version A. 6 "Swindon Station Area" refers. GERT8075 Two AWS and TPWS Interface Requirements 15-095-DEV Non-compliance with Clause 4.2.2.1 b) of GERT8075. This deviation applies to the AWS Audible Indicator Unit, part no. 062/016116, when fitted to Thameslink Class 700 units and subclasses. Current Deviations Register as at 09 May 2016 4.2.2.1 b) Nature and Degree The platform at the proposed site of the new passenger lift, is supported off made ground retained by brick viaduct structures running along the east and west boundaries of the station. The made ground is circa 8-9 m in depth (from platform level), where the strata is then formed from London clay. Within the fill, immediately below the site of the passenger lift, are buried LUL crosspassageways constructed from either brickwork or cast segmental lining. Immediately to the east of the proposed lift is a north-south running passageway known as the Connect Equipment Room (CER), therefore constraining the proposed lift location from being designed further centrally within the platform. Risk Assessment/Safety Justification Applicant Organisation Based on the conservative approach as Network Rail discussed above, the project has identified the following mitigations and risk-reduction mechanisms and therefore feels that the derogation is a sound and sensible approach: The linespeed of the Down Slow 1 is 35/55 mph, and trains passing on this line all stop for Platform 7. Direct through trains are very seldom. Therefore, passengers should not congregate towards the edge of Platform 6. Platform 6 side is not used by the train operator, Govia Thameslink Railway (GTR), and therefore after consultation with the operator, the reduction of the platform edge clearance is agreeable. The derogation to reduce the platform edge clearance to proposed 2183 mm, minimum 2100 mm would only be for a total length of proposed 3900 mm, maximum 4000 mm. . The total passenger usage of the combined island Platform 5/6 is very low. Platform 5 side is used, but a maximum of 3no trains arrive and depart from this platform every hour, therefore actual usage and footfall of the platform is very low. The effective minimum platform edge clearance from the proposed lift shaft to Platform 5 side shall be 6890 mm, therefore an oversized clearance on the used-side of the The height of the platform canopies is too Network Rail low to achieve the 2500 mm minimum height. Certificate Issue Date 09/12/2015 Certificate End Date N/A Lead SC Infrastructure Lead SC Approval Date 11/11/2015 Deviation Status Current 09/12/2015 N/A Infrastructure 11/11/2015 Current The proposed new sign dimensions control Network Rail the risks for the line Minimum Reading Distances (MRDs) required. BS EN 16494: 2015 permits variation in size for the European Train Control System (ETCS) Block Marker (AB08) and other European Rail Traffic Management System (ERTMS) signs. This standard states: "In the case of low line speeds and/or structure gauge constraints, it is permissible to use signs within the scope of this standard with height and width less than 500 mm, provided that the dimensions are proportionally the same as in Table 3. Where these signs are used, readability shall be optimized. " Off-site trials have been conducted and from these it has been concluded that the smaller signs are fit for purpose. The risk arising from their smaller size is negligible. Two reports for the off-site trials are attached with the application. Signal Sighting assessment has taken place, and the visibility of these signs will be briefed and included in driver training packs (as part of route learning). The results of the assessment in the form a report. Sample sign sighting forms and the report are attached with the application. 14/04/2016 N/A Control Command and Signalling 29/10/2015 Current Junction method 2 Flashing Yellow Aspect Sequence requires that, for a permissible speed approaching the diverging junction in the range 80 mph - 125 mph, the permissible speed at the point of divergence should be 40 mph or greater. Compliance to the RGS requirement would restrict the approach to Platform 1 to MAR at SW1175 signal, with performance impact on the planned timetable services and the approach would be inconsistent with the existing arrangements to Platform 3 from SW1155; this would result in a less drivable layout from train operator's perspective. The permissible speed at the point of divergence (30 mph) is 10 mph below the limit required by the standard. The WMSR Signalling Compliance Approach "Principle of Re-lock and Re-control" applies (CCMS Reference 10455124). Additionally, the signals concerned enjoy good sighting of their cautionary aspects and the permissible speed profile decreases on approach to the station. The Advance Warning Indicator (AWI) for the divergence previously sighted at braking distance is to be repositioned at the first caution signal. At Swindon Station, a flashing yellow aspect Network Rail sequence from the Down Main into Platform 3 has existed for many years; it has the property that the permissible speed approaching the diverging junction is 40/85 mph and the permissible speed at the point of divergence is 30 mph. The alternative provision to additionally provide MAY-FA for approach to Platform 1 allows greater efficiency in the use of Swindon Station. Although the MAY-FA facility to Platform 3 was provided at a time when most Down Trains serving Swindon used Platform 3 (or less commonly Platform 1) it is understood that the Train Operating Companies (TOCs) would like to see the present feature retained, notably for train services from London to Cheltenham. All the Swindon area signals relocked by the SASR project are predicted to be replaced with an ERTMS L2 system in the future. 18/12/2015 N/A Control Command and Signalling 29/10/2015 Current As part of the approval process to demonstrate compliance with GERT8075, sound tests were performed on a Thameslink Class 700 unit. The test included on-train measurements of the ambient noise and the warning- and clear tones. The measured ambient noise according to TSI Noise was 74. 7 dB(A). at 100 mph. During testing with the Automatic Warning System (AWS) Audible Indicator Unit, part no. 062/015822, it was found that it was not possible to meet the requirement for the AWS caution horn and the AWS clear bell to be 10dB(A) above ambient. Safety relevant acoustical information from Govia Thameslink Railway AWS can be clearly heard by the driver and also considers the health and safety aspects of drivers hearing abilities. This applies to the AWS caution horn being 6 dB(A) above ambient noise level and only to appear occasionally, and the AWS 'clear' bell also being 6 dB(A) above ambient noise level and to appear very often. The sounds on the train were also evaluated under real conditions in the cab by the operator and trade union representatives. Both parties described the signals as clearly distinguishable. The subjective impression was that the signals were already very loud. 18/12/2015 N/A Control Command and Signalling N/A Current The height of the platform canopies is too low to permit the required 2500 mm clearance to underside. Smaller displays would affect the readability of the information. Low severity - the displays are 'like for like' replacements of existing displays in their current locations utilising the existing brackets. The existing displays have been in place for 15 years with no incidents. The proposed variation will be applicable to It is impracticable to use the signs with the the Thameslink core (tunnel) area only with dimensions prescribed in the Railway Group limited clearances. The non-standard Standard within the core Thameslink route dimensions of the signs proposed: AB02, due to limited clearances in the tunnel. It is AB03, AB07, AC11. Specific detail on the not practicable to achieve compliance as it geographic scope is contained in the would require extensive civil engineering document "Supporting Information" attached works to provide the necessary additional to the application. This deviation applies clearance within the core (tunnel) area. only to the Thameslink 'core' (tunnel) area with limited clearances and when supported by a signal sighting committee assessment. . Page 12 Deviations Register RGS Number GMRT2149 RGS Issue Number Three RGS Title Requirements for Defining and Maintaining the Size of Railway Vehicle Certificate Number 15-094-DEV Title Sheffield Tram-Train Lower Sector Gauge Clearance. RGS Clause B6.2 Scope This application relates to a total of seven three-car tram-train Electric Multiple Units (EMUs) for operation between Sheffield Meadowhall South and a new turn-back platform at Parkgate via Rotherham Central. Unit numbers: 399201 - 399207. Vehicle numbers: 99001 - 99007;99101 99107;99201 - 99207. Nature and Degree General background information on the Tram Train Project is given in Appendix A. The tram-train vehicles are of a low-floor design aimed at achieving level access at tram stops on the tramway, and at dedicated low platforms on the mainline railway. The low floor height and associated compact design of the vehicle bogies results in areas of limited clearance in the lower sector. Complying with the RGS requirements would require a substantial re-design of the existing vehicle bogie, and may not be technically feasible. The resulting limited clearances are the subject of this deviation application. GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 15-090-DEV Class 185 six-car over-length station operations. B12.1 and B12.2.2. Liverpool South Parkway and Widnes Stations. GERT8000-TW5 Six Preparation and movement of trains Defective or isolated vehicles and on train equipment 15-089-DEV Class 185 six-car over-length station operations. 6.1 Class 185 six-car over-length operations at: Liverpool South Parkway Station; Warrington Central Station; Widnes Station; Any other station on routes where the use of the facility is occasional and/or limited to stations with low numbers of passengers boarding and alighting [I. e. meeting the requirements of B12. 1 of 08/059/NC]. GKRT0192 Two Level Crossing Interface Requirements 15-084-DEV Hardstaffs User Work Crossings (UWC), non-provision of level crossing position indicators on East Midlands Control Centre (EMCC) Mansfield Workstation. 2.9.3.1 b) The deviation applies to Hardstaffs User Worked Crossing (ELR RAC 133m 9ch) and the control point Mansfield Workstation, EMCC. It is not intended to provide an identifying mark for the level crossing on the control point Visual Display Unit (VDU) screen when telephones are commissioned there for use by the Authorised User. GMRT2473 is also subject to a noncompliance pending standards change: 08/059/NC "Revisions to requirements related to power-operated external doors" authorised on 29/05/2008. This noncompliance already permits the use of a manual Selective Door Opening (SDO) system "on routes where the use of the facility is occasional and/or limited to stations with low numbers of passengers boarding and alighting. " 08/059/NC therefore covers most of the Transpennine Express over-length operations, but arguably not all. Six-car Class 185s stop over-length at Liverpool South Parkway and Widnes during the peak periods at times when the passenger demand necessitates a six-car train; this cannot then reasonably be considered low numbers of passengers and, depending on interpretation, is not occasional either. Complying in the short term could therefore involve either: Reducing the train length from six cars to three. Demand is such that the service would be so heavily loaded that passengers would be left behind at stations. This would increase the risk of staff, contractor and passenger assaults and the likelihood of incidents at the platform/train interface. It Compliance in the medium to long term will be as detailed in Section 9 above - Method of elimination. None of those options can be achieved in the short term. Complying in the short term could therefore involve either: Reducing the train length from six cars to three. Demand is such that the service would be so heavily loaded that passengers would be left behind at stations. This would increase the risk of staff, contractor and passenger assaults and the likelihood of incidents at the platform/train interface. Vulnerable passengers would be particularly at risk. It would also prevent the train crew from being able to readily walk through the train, increasing the potential consequences if, for example, a passenger was taken ill on the train or a train evacuation was required. Retaining the train length as six cars but removing all over-length calls. Almost all of these stops are a passenger service requirement of the franchise. Running two separate three-car trains instead of one sixcar train. Even if additional train crew resources could be provided, it is highly unlikely that an additional path would be available. The TransPennine Express franchise operates on already congested routes through busy hubs including Leeds, The Operations Risk Advisor and the Route Level Crossing Manager are providing an enhancement at Hardstaffs User Worked Crossing through the provision of telephones. The project scope did not include the requirement to update the signallers VDU control system and it is proposed that the required update is undertaken as part of a future project. The cost of updating the Westcad screens to show Hardstaffs UWC is 50,000 Pounds Sterling, considerably more than the project could afford and to undertake the change. In becoming compliant, the level crossing telephones would not be commissioned, which continues the residual risk that users of the crossing miscommunicate their location to the signaller, and the signaller therefore may authorise a crossing in an unsafe situation leading to potential collision between a train and a road vehicle. Current Deviations Register as at 09 May 2016 Risk Assessment/Safety Justification The proposed alternative provisions have the potential to result in insufficient clearances between the tram-vehicles and the infrastructure on the proposed operating route. In order to establish that sufficient clearance exists over the route to be operated by tram-train, an absolute gauging methodology has been adopted and Network Rail has commissioned Balfour Beatty to undertake a Clear Route assessment of the tram-train vehicles and the proposed route. The Clear Route assessment was made using a Vampire model created by the University of Huddersfield dynamics team, reference: Vampire Model 20140604-TT-NR-EL6. tareVampire Model 20140604-TT-NR-EL6Deflated. The relevant co-ordinates from the Vampire model have been input into the Clear Route model and run over the proposed route. No infrastructure infringements have been identified for the limited route over which the tram-train vehicles will operate. It should be noted that the proposed tram-train operation has no diversionary routes, and the request for deviation is limited to the route defined in Signalling Scheme 12_ne_0047 Version 9. 1. Clearance tests and dynamic testing will The current manual SDO Method of Work has worked successfully since April 2014. Customer information is provided, although it is noted that most customers on the peak hour trains in question are regular customers. The risk is further reduced on morning peak trains as most passengers at both stations are boarding rather than alighting. An analysis of the method of work at these stations shows that trains have called over length at Liverpool South Parkway in excess of 1800 occasions per year, and at Widnes approximately 260 occasions per year. This is a total of well over 2000 occasions per year at these two stations. In the sixteen month period between 01/04/2014 and 01/08/2015, only one irregularity has been reported, which resulted in the doors being released but did not result in any injury, and that incident was on an unplanned strengthening move arranged by control on the day as opposed to a planned operation. This data supports the view that, considering the low likelihood of an incident and the most likely severity, the overall risk is low in line with our internal Risk Assessment standard. A review of the over length working Method of Work and Risk Assessment was undertaken involving The proposed alternative provisions will permit the continued operation of six-car trains over-length at several stations across the current First TransPennine Express (FTPE) network, using a manual SDO system. The manual SDO system involves the conductor manually locking passenger doors out of use at the rear of the train, along with suitable customer information. GM/RT2473 is subject to a non-compliance pending standards change: 08/059/NC "Revisions to requirements related to poweroperated external doors" authorised on 29/05/2008. This non-compliance already permits the use of a manual SDO system "on routes where the use of the facility is occasional and/or limited to stations with low numbers of passengers boarding and alighting. "As the Class 185 Method of Work involves the conductor manually locking individual doors out of use at the rear of the train (as opposed to, for example, manually operating a system from a cab), the view of the Traffic Operation and Management Standards Committee (TOM SC) previously is that a deviation to TW5 is also needed. Class 185 units comply with the requirements of GM/RT2473 relating to the external Emergency Access Device (EEAD) Safety of the rail user and information provided to the user by the signaller when they communicate by the phone is increased due to the positive identity of the level crossing on the workstation telephone concentrator, provision of a laminated diagram of the crossing positioned next to the workstation position, a Special Box Instruction detailing the procedure and signals leading up to the level crossing, plus local training and briefing. There will be a residual risk that signallers will incorrectly identify the positions of the trains despite the information provided off of the workstation screens, but this risk is considered tolerable. Applicant Organisation Stagecoach Supertram Certificate Issue Date 14/12/2015 Certificate End Date N/A Lead SC Rolling Stock Lead SC Approval Date 30/10/2015 Deviation Status Current First/Keolis Transpennine Ltd 07/01/2016 (trading as First Transpennine Express) 19/05/2018 Rolling Stock 04/12/2015 Current First/Keolis Transpennine Ltd 20/11/2015 (trading as First Transpennine Express) 19/05/2018 Traffic Operations and Management 20/10/2015 Current Network Rail 27/10/2016 Control Command and Signalling 01/10/2015 Current 02/11/2015 Page 13 Deviations Register RGS Number GKRT0192 RGS Issue Number Two RGS Title Level Crossing Interface Requirements Certificate Number 15-082-DEV Title Non-compliance of Signals DM3, DM11 position relative to Downham Market Level Crossing. RGS Clause 2.1.1.3 Scope DM3 and DM11 protecting Downham Market Station Level Crossing. ELR BGK 86 miles 4 ch. GMRT2044 Four Braking System Requirements and Performance for Multiple Units 15-079-DEV Deterrent feature of the emergency brake. 5.4.2 GMRT2044 Four Braking System Requirements and Performance for Multiple Units 15-076-DEV Class 700 Enhanced Emergency Brake Rate. Hitachi Class 800/801/ 802 vehicles, to be used on Great Western and East Coast services. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Class 700 'Thameslink EMU' and all its subclasses. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GKRT0045 Four Lineside Signals, Indicators and Layout of Signals 15-074-DEV Non-provision of approach controls on ER6 signal at Rochester. GCRT5212 One Requirements for Defining and Maintaining Clearances 15-071-DEV Amendment to deviation 14/174/DEV against GC/RT5212 Issue 1 for trialling of platform gap fillers on Heathrow Central Terminal Area (CTA) Platforms 1 and 2, Terminal 4 (T4) Platforms 1 and 2 and Terminal 5 (T5) Platforms 3 and 4. Current Deviations Register as at 09 May 2016 Nature and Degree Signal DM3: Signal DM3 cannot be moved due to the limited length of the Up Platform with the crossover at the far end which cannot be moved. A timer delaying the aspect on signal DM3 already exists. The estimated £550k cost of relocating the Signal is disproportionate to the limited safety benefits realised. Signal DM11: The estimated £550k cost of relocating the Signal is disproportionate to the limited safety benefits realised. Trains may be delayed and drivers may be less willing to commence an emergency brake application until they are sure that such an application is required. Currently, no deterrent is fitted to the High Speed Train (HST) 125 fleets. 5.4.1 Class 700 is equipped with an emergency braking system of high integrity. The importance of the emergency brake system is to being failsafe and stopping the train safely within the shortest possible distance. To achieve this aim, the Class 700 emergency braking system uses the adhesion coefficient in the best possible way as set out within Technical Specification for Interoperability Locomotives and Passenger Rolling Stock (TSI Loc and Pas) 2011/291/EU. TSI Loc and Pas therefore defines adhesion coefficient limits, which are considered best practice. That Class 700 has a high integrity emergency brake system is also confirmed by the measured stopping distance curves (Figures 8. 7-28 - EB at tare load, 8. 7-38 - EB at full load and 8. 7-48 EB at crush load of Extract of Test report EN2 A6Z00037908793 000 -) complying to curve B3 of Figure 3 in GM/RT 2044 Issue 4. Regards Appendix A of this standard curve B3 is considered as the maximum desirable retardation in order to reduce the possibility of wheelslide. Regards full service braking the aim is considered to best possibly meet curve A3 of Figure 3 of the standard in order to meet the stopping distances required by signal spacing margins. A3 defines the 5.2.2.1 Deviation applies to ER6 signal at Rochester As part of the East Kent Resignalling Phase only. 2 (EKR2) Project, the Rochester area is to be extensively remodelled to facilitate the replacement of the existing station with a new one approximately 500 m nearer to London. The remodelling is to be delivered in stages and, as part of one of these, it was necessary to relocate ER6 signal 170 m in rear of its previous position in order to allow for future relocation of one of the sets of points which it reads over (60 points for access to the Down Siding). ER6 signal at Rochester is a three-aspect junction signal on the Down Main with the following routes: A(S) - into Down Siding,B(M) - into Down Platform Loop - via a 15mph divergence,C(M) - along Down Main 30mph line speed. As the existing difference in line speeds between the B(M) and C(M) routes is 15 mph, achieving compliance with the requirements of GK/RT0045 would require one of the following options to be implemented: Increase permissible speed of divergence over 67 points into the Down Platform Loop to 20 mph or greater (to achieve compliant Junction Method 1: Unrestricted Aspect Sequence). Reduce permissible line speed on the Down Main to 25 mph (to achieve C2.1, Table 2 - Categorisation of clearances Deviation 14/174/DEV was granted to allow Clause C2 Table 2 provides definition of for absolute gauging. G4.1 - Alterations the trialling of platform gap fillers on CTA normal/reduced/special reduced clearances other than to permit the passage of larger Platforms 1 and 2 until the 15/01/2017. The in the lower sector. Clause G4. 1 states that rail vehicles. amendment that is being sought under the alterations to infrastructure should not cause current submission is to Deviation reduction of clearances from one category to 14/174/DEV. It seeks to bring all HEx a more severe (smaller clearance) category. platform gap filler trials, the ones ongoing on The current platforms clearances comply T5 Platform 4 and those proposed at CTA, with the RGS requirements. In every as well as the newly proposed trials for T4 platform (including T5 Platform 4 before Platforms 1 and 2 and T3 Platform 5, under June 2014), there have been instances of 14/174/DEV with a synchronised finish date passengers, especially those with a small of all trials in January 2017. "Supporting foot size, stepping between the platform and Document 1" attached to this deviation the Class 332 and Class 360/2 step plate amendment gives further details. The and getting their foot/leg trapped. impact of the gap filler installation is to reduce nominal clearance between vehicles and the infrastructure from normal clearance to 25 mm-50 mm (I. e. reduced clearance). The gap filler is, however, flexible and effective clearance remains greater than this nominal value. The clearance rules of GC/RT5212 Issue 1, however, do not recognise the possibility of such flexible components, and deviation is therefore necessary. The trial will be conducted up till 31/01/2017 to allow for sufficient trial time and data gathering to demonstrate that the gap filler achieves a safety benefit and the installation is robust under the operating Risk Assessment/Safety Justification Signal DM3: The SPAD risk at DM3 was assessed to be relatively high, the main causes being: o The short safe overrun distance (14. 5m). o The short standback distance (less than 10m for passenger trains). o Trains normally approaching the crossing before the sequence has initiated and the crossing receiving high use by the public. Therefore, in the event of a SPAD, it is likely that the road and footway over the crossing would be occupied. The high risk was despite the existing SPAD controls, which include: o Signal DM3 is approach controlled from the previous signal DM2 (when DM3 is at danger). o The previous signal (DM2) is protected with both TSS and Overspeed Sensor System (OSS). o Signal DM3 is protected by TPWS TSS. Providing SPAD prediction was found to be the most cost-effective solution of those examined and therefore most effective at mitigating the risk. The cost of the option is approximately £100k. Signal DM11: The SPAD risk at DM11 was assessed to be low, the reasons for this are: o The signal is only normally approached once per day during normal operation and very rarely during degraded operations, where the signal could be approached with a shunt move at low speed. No foreseen impact on this point. TSI requirement has been defined in order to meet the essential requirement 2. 4. 1 (Rolling Stock/Safety) and 2. 4. 3 (Technical compatibility) of the Interoperability Directive (2008/57/EC). There are no impacts on the risks that are addressed by Clause 5. 4. 1. The risks are identified as: Wheel slide by provision of too much brake force leading to exceeding the adhesion limits. Wheel slide then would be resulting in longer stopping distances and damage to wheel and also damage to rail which is less likely. => Risk is controlled by complying with TSI Loc and Pas 2011/291/EU and the adhesion limits defined within this standard and meeting braking curve B3 of GM/RT2044 Issue 4 Figure 3. => Risk is further mitigated by the provision of a highly reliable Wheel slide protection system. Providing to less additional brake force, not enabling the driver to react on misjudgement or in case of emergency appropriately. => Risk is controlled by providing at least 15% enhancement on the brake performance. Applicant Organisation Network Rail Certificate Issue Date 02/11/2015 Certificate End Date N/A Lead SC Control Command and Signalling Lead SC Approval Date 01/10/2015 Deviation Status Current Hitachi Rail Europe Ltd 16/10/2015 N/A Rolling Stock 01/10/2015 Current Govia Thameslink Railway 16/10/2015 N/A Rolling Stock 01/10/2015 Current The permissible speed differential is 15 mph which is only 5 mph greater than GK/RT0045 permits and the maximum line speed is only 30 mph. The sighting of the new position of ER6 signal is constrained by the viaduct over the River Medway on the approach to the signal and the signal has been assessed as being visible for 158 m on approach which exceeds the minimum reading distance by 30%. The Automatic Warning System (AWS) magnet for the signal has been positioned at the point at which the signal becomes visible. It is considered that the driver shall have sufficient time to comprehend the signal indication to enable him to control the speed of the train appropriately. As ER6 B(M) will only ever clear to a yellow aspect, the driver will always receive an AWS warning when taking the diverging route which should also assist in controlling the speed. Dialogue with Southeastern has identified that, with an unrestricted approach to ER6, it would be expected that a train would approach the signal at the full line speed of 30 mph. The signal is 657 m from the divergence and the gradient profile between these two points is level (for 7 m), then falls at 1 in 167 for 463 m before rising at 1 in 180 to the divergence. The impacts of the proposed gap filler have been more fully detailed in the supporting documents attached. In summary, the gap filler trial is expected to: Improve passenger safety on T4 Platforms 1 and 2 and T5 Platforms 3 (in addition to T5 Platform 4 and CTA Platforms 1 and 2 as already covered in other deviations). Maintain acceptable train / platform clearances, as demonstrated in the trials ongoing on Heathrow T5 Platform 4, whilst not affecting technical compatibility of the railway system through the reduction in normal clearance arrangements. The gap fillers can be removed if railway requirements change in the future, or if the trial proves to be unsuccessful. Have no effect on service performance. Have no direct impact on environment. Supporting documentation attached to this report discusses the details including the risk assessment. Network Rail 02/11/2015 01/08/2016 Control Command and Signalling 01/10/2015 Current Heathrow Airport Limited on behalf of, Heathrow Express Limited 16/10/2015 31/01/2017 Infrastructure 09/09/2015 Current Page 14 Deviations Register RGS Number GKRT0075 RGS Issue Number Three RGS Title Lineside Signal Spacing and Speed Signage Certificate Number 15-070-DEV Title Shenfield, Down Main line deceleration distance to diverging points. RGS Clause 3.2.3.3, 3.2.3.4 Scope Position of Advance Warning Indicator (AWI) in relation to 2255A points, Down Main, ELR LTN at 19 miles 11 chains. GKRT0045 Four Lineside Signals, Indicators and Layout of Signals 15-069-DEV Swansea - PT3158 Differential in permissible speed exceeds the requirements for approach-release-free (MAF) junction signalling. 5.2.2 The deviation applies to PT3158 signal at Swansea Loop East Junction, controlled from Wales Railway Operating Centre (ROC). GIRT7016 Five Interface between Station Platforms, Track and Trains 15-068-DEV New waiting shelter(s), clearance to platform 6.2.2 b) edge(s). This deviation from RGS relates to horizontal clearance between the platform edge(s) and proposed new waiting shelter at the station listed below: Trefforest Estate, TRE CAM 09m 53ch. Office of Rail and Road (ORR) Passenger Figures 227,933. Arriva Trains Wales / Network Rail is proposing to replace the existing waiting shelter. Site constraints do not allow for the installation of the new proposed shelters to achieve the RGS. GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 15-067-DEV Class 321 reduction in trailer vehicle rollover angle to 18.0 degrees. 2.4.1.1 b) All Class 321 trailer vehicles that have completed their mid-life refurbishment. GMRT2130 Four Vehicle Fire, Safety and Evacuation 15-066-DEV Class 387 - Compliance to GM/RT2130 Issue 4. All clauses. Current Deviations Register as at 09 May 2016 Nature and Degree Provision of the AWI at the distance prescribed by Appendix X of GK/RT0075 or positioning the AWI at the next available position 180 m on approach to the flashing double yellow signal was discounted by the Signal Sighting Committee because it would dissociate the warning indicator from the flashing aspect indicated to the driver. Appendix X of GK/RT0075 uses the worst case braking (Appendix A) which is not reflective of the majority of trains that will be using this route and 86 m at 75 mph is equivalent to only approximately 2. 5 seconds of running time, which would have only a small impact on the overall deceleration profile. The deficiency represents only approximately 6% of the calculated AWI positioning distance. Risk Assessment/Safety Justification Applicant Organisation Existing signal spacing is deficient to Network Rail GK/RT/0075 and is mitigated by application of controls, essentially a YY-YY-Y-R aspect sequence. The proposed flashing aspect sequence of FYY-FY-(Y+Pos 1) and provision of AWI positioned at the FYY signal does not provide deceleration distance in accordance with Table X of GK/RT/0075. The driver will be alerted on the approach to the AWI as the train passes over the shared Automatic Warning System (AWS) magnet which is located 180 m on the approach. As the AWI has an Achievable Reading Distance of 161 m (please refer to the AWI Sighting Form), this distance more than compensates for the deficiency of 86 m in the required distance between the AWI and the diverging route speed indicator as the driver would, most likely, commence braking once the AWI becomes visible instead of when it is reached. The difference between the permissible All trains will be starting from rest at Network Rail speeds of the straight ahead and diverging Swansea station. The Permanent Speed routes through and immediately beyond the Restriction (PSR) across the station throat is junction is 10 mph or less. Compliance is 20 mph. This steps up to 40 mph 267 m on possible. However, in discussion with Train approach to PT3158. By this time, the signal Operating Company (TOC) / Freight is in view. Considering the reading distance Operating Company (FOC) driver and the lack of time to accelerate, it was representatives and Network Rail schemes considered unnecessary to apply Main experts during scheme plan development, it Aspect Red (MAR) as this would condition was considered desirable to perpetuate the drivers to anticipate the aspect stepping up current arrangements of free aspect, given on approach as it would be unusual for this the specific geography of the site with all signal to be at red. This arrangement is trains starting from rest. consistent with the equivalent existing signal PT281 for which no Signals Passed at Danger (SPADs) are recorded. Certificate Issue Date 07/10/2015 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 03/09/2015 Deviation Status Current 07/10/2015 N/A CCS 03/09/2015 Current The existing waiting shelter at the named station is within 2500 mm of the platform edge(s). The existing shelter is 1. 82 m (upside) from the platform edge and 2. 08 m (downside) from the platform edge. The existing shelter is 1. 62 m in width, measured from the outside of each post and excluding any overhang from the roof. The proposed new shelter is 1. 60 m in width, measured from the outside of each post and excluding any overhang from the roof; the overhang of the roof is 0. 20 m to both sides measured 2. 50 m above platform level. The overhang of the proposed roof is not allowed for in the calculation of the setback from the platform edge as it achieves RGS No. GI/RT7016 Clause 8. 1. 1 b) issue five, Platform Headroom. The new style shelter is a product in the Arriva Trains Wales latest range of high quality vandal resistant waiting shelters. The shelters offer no visible fixings, seating, high efficiency internal LED lighting system, concealed drainage and modular glazing. The existing shelter, which has reduced horizontal offsets from the edge of platform(s) at 1. 82 m on the Up and 2. 08 m on the down has been in place for a number of years and no operational issues with regards to their proximity to the platform edge has come to light. The existing shelter has no internal lighting or Close Circuit Television (CCTV) provision and a mix of solid window or missing panels. Cross-sections illustrating the existing and proposed arrangement for distances from the edge of the platform are shown below. 11/12/2015 N/A Infrastructure 11/11/2015 Current The reduction in roll-over angle would ESG Ltd permit the introduction of air conditioning and PRM refurbishment. Provision of the full reduction of 3 degrees (from 21 to 18 degrees) would enable the suspension to be optimised to minimise any reduction in ride comfort as a result of these modifications. There is no desire to reduce the roll-over angle below the 18 degrees which is considered to have been proven to be safe. 12/08/2015 31/12/2016 RST N/A Current It is considered that there is no negative Bombardier Transportation impact from complying with GM/RT2130 Issue 3 and the SRT TSI instead of GM/RT2130 Issue 4. An assessment of the differences between GM/RT2130 Issue 3 and Issue 4, with respect to any safety benefits and technical compatibility of the railway system, is documented in Bombardier report 3EER400019-0846_B. Within this report, the implications of applying the revised requirements of GM/RT2130 Issue 4 to the Class 387 design is also discussed; the level of assessment involved is extensive and does not introduce any safety benefits or have any effect on the ability of the vehicles to meet the essential requirements. The Office of Rail and Road (ORR) previously issued a letter accepting the use of the superseded Issue 3 of GM/RT2130 for the authorisation of the original Class 387/1 vehicles (base design), on the basis of the justifications presented within Bombardier report 3EER4000190846_B. The base design for the vehicles within the scope of this application has been authorised as compliant to the requirements of the SRT TSI (4 minutes running capability) and the requirements of GM/RT2130 Issue 3, as supported by 18/09/2015 N/A RST 28/08/2015 Current Vehicles shall be designed with mass distribution and suspension characteristics which ensure the capability to run round smooth curves at constant speed, without rolling over, at not less than 21ø cant deficiency. Currently, the design for the Eversholt Class 321 fleet mid-life refurbishment is nearing completion. This will bring the unit into line with Persons with Reduced Mobility (PRM) requirements, provide additional passenger standee room by opening up the vestibules and introduce air conditioning units above the vestibules to improve passenger comfort (along with several other smaller changes as documented in the attached System Requirements Specification, TS-140129-007 Issue L). As part of the work, the impact on vehicle dynamics has been assessed and documented in the attached Interfleet report (ITLR-T35919-001). As may be seen in the report, the air conditioning and refurbishment add mass in the tare condition. The placement of the air conditioning units in the roof above the vestibules also increases the vertical C of G. On top of this, the additional mass of increased numbers of standees compounds the issue. The increase in mass and vertical · 27 four-car Class 387/2 Electric Multiple The vehicles within the scope of this Units (EMUs) (units 387201 to 387227) · 8 application were identified as options for four-car Class 387/1 EMUs (units 387130 to additional vehicles on the contract for the 387137). All these units are an option for supply of Class 387/1 vehicles (recently additional vehicles on the original Class authorised to be placed into service in June 387/1 contract (units 387101 - 387129). This 2015), which have now been exercised. The deviation is for projects requiring contract for the authorised Class 387/1 authorisation for placing in service under the vehicles was signed in July 2013, prior to the Railways (Interoperability) Regulations 2011. GM/RT2130 Issue 4 application date. As additional vehicles to the Class 387/1 contract, the vehicles within the scope of this application are of a carry-over design. The production of these additional vehicles has commenced. The applications for authorisation of the vehicles will be predicated on conformity with the authorised Class 387/1 type, under Regulation 9 of the Railways (Interoperability) Regulations 2011. To demonstrate compliance with GM/RT2130 Issue 4 would require a significant assessment of the established Electrostar design. The timescales involved with demonstrating compliance will place the delivery of both projects at risk, and result in significant additional costs. Page 15 Deviations Register RGS Number GERT8000-TW1 RGS Issue Number Nine RGS Title Preparation and movement of trains Certificate Number 15-065-DEV Title RGS Clause Operation of Network Rail Infrastructure 4.4 Maintenance Unit (IMU) train with Ultrasonic Test Unit (UTU) brakes isolated. Scope The deviation is sought against Clause 4. 4 to permit UTU trains consisted with ultrasonic test cars in their formation to run with brakes isolated. Specifically, the deviation applies to five test cars numbered as follows: 62384, 62287, 999606, 999602 and 999605. These vehicles are operated throughout the UK rail network. There are, at the present time, five UTU trains in service, each containing one of the above numbered vehicles. Notable features of the ultrasonic test cars are: · The test cars have one unbraked bogie; · They are equipped with a full set of emergency equipment; · They are equipped with six wheels scotches. UTU test cars are certificated to run in any formation, but must not be the rear vehicle at any time. The requirement to meet the reduced speed requirements above must still be complied with (table as specified in GE/RT8000/TW1 Issue 9, Clause 4. 4). The maximum authorised speed of UTU trains is 75 mph. When testing, the UTU train will run at maximum speed of 30 mph. Nature and Degree Compliance with the RGS standard leads to problems with wheelflats on the test cars, particularly in the potentially low adhesion periods. The non-availability of the test cars puts the UTU testing plan in jeopardy, leading to potential railhead damage and the potential for rail non-compliance issues. Risk Assessment/Safety Justification Applicant Organisation The impact of the alternative provision will Colas Rail Ltd be to ensure that the UTU testing plan is maintained as planned, vehicle availability is maintained, vehicle maintenance costs are reduced through reduced wheelset damage, resulting in a benefit to the operational railway nationally. Safety issues have been addressed by ensuring that the required brake force for the consisted train is available at all times, introducing additional vehicles into the consist if required and also compliance with the reduction in train speed above 35 mph, 10 mph reduction in speed up to and including 75 mph. The revised working arrangements will be subject to a traincrew briefing. The issued train list will reflect the fact that there is an unbraked UTU test car in formation. Certificate Issue Date 10/08/2015 Certificate End Date N/A Lead SC TOM Lead SC Approval Date N/A Deviation Status Current GKRT0045 Four Lineside Signals, Indicators and Layout of Signals 15-064-DEV Flashing aspects for K531 signal at Potters Bar. 5.2.3.1 and Table 2 Signal K531, control by Kings Cross PSB. The route is from the Down Fast to Down Slow lines through points 2182 crossover reverse to the south of Potters Bar station. Compliance would either require an increase in crossover speed to a minimum of 40 mph, or retaining the approach release from red of K531. The current control causes trains proceeding from the Fast to Slow line to decelerate with K531 at red before releasing the aspect to proceed over 2182 crossover. It is not currently possible to change the line speed over the junction to 40 mph (from 30 mph) which would allow the flashing aspect from 115 mph to 40 mph which would be compliant with the clause because this would require relaying the junction. Network Rail 03/09/2015 N/A CCS 06/08/2015 Current GKRT0192 Two Level Crossing Interface Requirements 15-062-DEV Positioning of Signal T645 at 22.3 m from Plumpton level crossing. 2.1.1.3 Positioning of Signal T645 at 22. 3 m from Plumpton level crossing. Complying with requirements of GK/RT0192 Section 2. 1. 13(a) will require repositioning of Signal T645 that will result in reduction of the platform length. This will also require signal sighting of the repositioned signal, review of inter-signal spacings, platform extension on London end of Platform 2 or provision of Selective Door Operations (SDOs). As signal T645 has no Signal Passed at Danger (SPAD) history and repositioning of signal will involve expenditure of approximately œ400K in the remedial works, this option is not economically justifiable. Complying with the requirements of GK/RT0192 section 2. 1. 1. 3(b) will require holding Signal T643 at 'ON' until the level crossing is closed to road traffic. This restriction on Signal T643 will result in increased downtime of Plumpton level crossing barriers, causing unwanted disruption to road traffic that is likely to trigger misuse and trespass of the level crossing when the barriers are down for a long time. Network Rail 03/09/2015 N/A CCS 06/08/2015 Current GMRT2461 One Sanding Equipment Fitted to Multiple Units and on- track Machines 15-061-DEV Automatic sanding on trailing units with automatic detection of low adhesion (using Wheel Slide Protection (WSP)). 6.2, 9.1, 9.3.1 All multiple units with automatic sanders, where the means of detection of low adhesion is from a wheel slide detection, whether running alone, or in multiple. NB: this is intended to include all units with automatic sanders, where the means of detection of low adhesion is from a wheel slide detection, that are operating as trailing units even if the leading unit is a tread braked unit with manual sanders or a unit with no sanders fitted. The deviation requests enhanced performance, which is non-compliant with the standard as written, but consistent with the objectives of the standard. Signal K531 has only one diverging route on to the Down Slow line and therefore the risk of misreading the routing information is reduced when receiving a flashing aspect sequence and reduces the Signal Passed at Danger (SPAD) risk from anticipation. The crossing line speed is 30 mph which is under the requirement minimum line speed of 40 mph for flashing aspect controls from the approaching line speed 115 mph. In order to manage the over-speed risk at the junction, a permissible speed warning indicator and associated Automatic Warning System (AWS) for the diverging speed will be provided on approach to the signal displaying the flashing yellow aspect, which will remind drivers of the junction speed. There is a perceived risk with the existing layout that trains will accelerate towards the crossover after the signal clears as the crossover is 700 m from K531. The flashing aspect sequence will reduce the current requirement for drivers to accelerate towards the crossover after receiving a delayed aspect release on the junction signal. An existing deficiency has been found during the signal sighting assessment, which will be resolved with the provision of a new, right hand mounted K531. Signal T645 has no Signal Passed at Danger (SPAD) history, and provision of Stowmarket control as part of the project will further enhance the safety of level crossing users. As such, the severity/degree of the proposed variation has been considered as low as per the risk assessment report. A risk assessment has been carried out to identify the risks and find out additional protection required. Following actions will be taken to comply with the recommendations of the risk assessment report and provide additional protection, if required: Monitoring of post-commissioning frequency of Signal T645 being worked in manual mode and frequency of activation of Stowmarket control shall be implemented as per recommendations of risk assessment report. Observation of post-commissioning behaviour of crossing users with respect to level crossing closure warnings, and Stowmarket control warnings shall be recorded as per recommendations of risk assessment report. Initiation of lowering of the level crossing barriers, along with activation of Stowmarket controls, will be implemented if found to be necessary as a result of risk assessment of the observations in items above. Sand will be permitted to be dispensed on trailing units during any brake application (service or emergency) when the leading vehicle of that unit automatically the presence of low adhesion (Clause 6. 1 already permits sanding on the leading unit for any brake application when the presence of low adhesion is automatically detected). As such, trailing units will only dispense sand if they detect the presence of low adhesion using their own local wheel slide protection system and have sufficient sand available. The likelihood of sanding on trailing units occurring is lower, as the sanding by the leading unit will condition the railhead and so the trailing units are likely to experience wheel slide to a lesser extent. This functionality has been developed to increase the safety of the railway in conditions of extremely poor rail head adhesion or where the sanding system on the leading unit does not function correctly (due to a fault or having run out of sand), having a positive impact on overall system performance. The amount of sand deposited and the number of axles following the deposition point will be the same as if the units were separate trains following each other. Therefore, it is considered that there Association of Train Operating 05/10/2015 Companies (ATOC) N/A RST 28/08/2015 Current Current Deviations Register as at 09 May 2016 Page 16 Deviations Register RGS Number GMRT2461 RGS Issue Number One RGS Title Sanding Equipment Fitted to Multiple Units and on- track Machines Certificate Number 15-060-DEV Title Sanding on trailing units with manual sanders. RGS Clause 9.1, 9.3.1 Scope All multiple units with manual sanders. Nature and Degree The deviation requests enhanced performance, which is non-compliant with the standard as written, but consistent with the objectives of the standard. Risk Assessment/Safety Justification Applicant Organisation Certificate Issue Date Sand will be permitted to be dispensed on Association of Train Operating 18/09/2015 trailing tread braked units when sanding is Companies (ATOC) initiated by the driver on the leading unit and automatically during an emergency brake application. This functionality has been developed to increase the safety of the railway in conditions of extremely poor rail head adhesion or where the sanding system on the leading unit does not function correctly (due to a fault or having run out of sand), having a positive impact on overall system performance. The amount of sand deposited and the number of axles following the deposition point will be the same as if the units were separate trains following each other. Therefore, it is considered that there is no negative impact in terms of contamination of the railhead, the associated monitoring regime will be used to confirm this on the routes over which these trains will operate. The RSSB T1046 research project suggests that the improvements in adhesion achieved would give safety and operational benefits that significantly outweigh any possible reduction in the ability of track circuits to detect trains. Certificate End Date N/A Lead SC RST Lead SC Approval Date 28/08/2015 Deviation Status Current GKRT0045 Five Lineside Signals, Indicators and Layout of Signals 15-059-DEV Henwick signals HK22. 5.1.2.4 Henwick signal HK22. Compliance with the standard is considered to present a potentially more confusing indication to train drivers on this route who are familiar with the current semaphore arrangements. GMRT2149 Three Requirements for Defining and Maintaining the Size of Railway Vehicle 15-058-DEV Class 700 (Thameslink EMU) Pantograph Sway. B10.1 Class 700 'Thameslink EMU' and all its subclasses. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Class 700 fully complies with sub-clause a). Class 700 fully complies with sub-clause b) for a wind speed up to 26 m/s and cant deficiency of 150 mm or wind speeds up to 35 m/s and cant deficiency of 65 mm. Class 700 does not fulfil the area of 26 m/s to 35 m/s at cant deficiency of 150 mm and maximum speed. GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 15-057-DEV Sheffield Tram-Train Door Control (Issue 2). B5.3 B6.1 B7.5.2, B 7.5.3, B 7.5.4 B7.6, B11.4 B7.10 B10.1 B11.2, B11.3, B11.5 This application relates to a total of seven three-car tram-train Electric Multiple Units (EMUs). Unit numbers: · 399201 - 399207. Vehicle numbers: · 99001 - 99007; · 99101 99107; · 99201 - 99207. GKRT0075 Three Lineside Signal Spacing and Speed Signage 15-056-DEV Down Cannon Street line country side of 3.3.1.4 a) London Bridge High Level. Non-provision of Permissible Speed Warning Indicator (PSWI) and associated Automatic Warning System (AWS) for existing 60 to 40 Permanent Speed Restriction (PSR). The proposed approach maintains consistency with current aspects for through trains and makes it more obvious to trains routed into the turnback. This approach has been adopted on the advice of professional railway and train operators. An assessment of the risk arising from this non-compliance has been provided separately. This configuration will mitigate against the risk of the route indicator failing and a main proceed aspect along being displayed (suggesting the through route) with the route actually set for the dead-end turnback road. The proposed arrangements are envisaged to build upon the existing driver knowledge for this area. As part of the Henwick turnback scheme, existing motor worked semaphore signals HK22 and HK23 are to be provided with a Site Instruction (SI) to allow trains to be routed into the turnback road. For trains passing HK23, both routes have a linespeed of 40 mph at the point of divergence, although the turnout route subsequently drops to 15 mph for the entrance into the turnback road. Trains passing HK22 continue at a linespeed of 40 mph, which reduced to 15 mph for both routes at the point of divergence. To avoid confusion for drivers and make it clearer that The deviation has no impact on the train design as the train is designed in its safest way. The changed approach considers the basics of the new draft standard as laid out in T942. The report T942 is the basis for GM/RT2173 on panto sway; we've worked to the same principles and the same goal but being a bit more conservative. We've also assessed the 35 m/s curves from the report which are not incorporated in GM/RT2173. Regarding Figure E. 2 of the new draft standard, we have an additional safety margin as we meet the pantograph sway requirement +190 mm at cant deficiency 150 mm and 160 kph not only for maximum wind speed of 22 m/s but also for 26 m/s. Discussions have been held with the Notified Body (NoBo), and they confirm that the methodology in T942 (which they also considered to be valid) has been correctly applied by Siemens. The door arrangement is provided in accordance with EN14752: 2005, which is a recognised standard widely accepted across Europe to control the risks associated with passenger doors. See Appendix for more details. There is currently an existing 40 PSR on the Down Cannon Street line on approach to the Old Spa Road station just prior to the 2M3/4 mile post. It is understood that this PSR has been in place for over 40 years due to track alignment reasons. The speed on approach to the 40 PSR is 60 mph. The 60 PSR begins approximately 900 m on approach. Prior to the 60 PSR, the line speed is 20 mph through London Bridge station. As part of Thameslink Stage HL05, the existing very old and unclear 60 PSR boards outside the station are being replaced and moved on to the nearest gantry to aid sighting. In addition to this L121 signal which is two signal sections in rear of the 40 PSR on the affected Down Cannon Street line is also being relocated on to the next gantry. It should be noted that, ultimately, this stage does not change the existing speed profile. There is no existing PSWI or AWS for this existing 60 to 40 mph speed reduction. The addition of a PSWI and associated AWS within two short signal sections will provide an unnecessary cab task and distraction over such a well-known speed profile. There is also no realistic position to place a PSWI board or AWS from a sighting perspective. The stage scheme has been Current Deviations Register as at 09 May 2016 The tram-train vehicles are being built to an existing design that complies with European standards. Replacement of the door system with an RGS-compliant system would require significant re-engineering of the vehicle design. Down Cannon Street line country side of The provision of PSWI and associated London Bridge High Level. Non-Provision of suppressed permanent AWS inductor would permissible speed warning indicator and be required in a complex area of track. associated AWS for existing 60 to 40 PSR. Train Operating Companies (TOCs) have expressed concern at this provision and feel this would import risk of confusion to driver task demands. The speed profile for nonfreight trains remains unchanged from today and has been like this for over 40 years. The relevant TOCs (South Eastern and Govia Thameslink Railway (GTR)) have been contacted about the proposal and have confirmed that they would object to a change to the existing PSR arrangements on the Down Cannon Street line on the basis that it would likely lead to driver confusion. Risks associated with PSWI non-provision are minimal. Network Rail operations and the TOCs have been informed of the proposal to not provide an additional PSWI board and fully support this on the basis that it would likely increase the risk of driver distraction and therefore increase the risk of a signal misread. Network Rail 03/09/2015 N/A CCS 06/08/2015 Current Govia Thameslink Railway Limited 18/09/2015 N/A Rolling Stock 28/08/2015 Current Stagecoach Supertram 02/09/2015 N/A RST 24/07/2015 Current Network Rail 29/07/2015 23/12/2017 CCS 09/07/2015 Current Page 17 Deviations Register RGS Number GMRT2400 RGS Issue Number Five RGS Title Certificate Number Engineering Design of On-track Machines in 15-055-DEV Running Mode Title RGS Clause Automatic reset of air release parking brake 2.3.2.3 actuator. GIRT7016 Five Interface between Station Platforms, Track and Trains Borders Rail Project - ELR: SBO, Galashiels 2.1.2 Platform. GMRT2472 Two Requirements for Data Recorders on Trains 15-051-DEV Sheffield Tram-Train Data Recorder, Issue 1. 2.1.1 GMRT2045 Three Braking Principles for Rail Vehicles 15-050-DEV Sheffield Tram-Train Braking Principles, Issue 3. 7.2.3, 7.4.3 GERT8075 One AWS andTPWS Interface Requirements 15-049-DEV Fitment of Train Protection Warning System 6.2.1.1, 6.2.1.2, 6.2.1.3 (TWPS) to control units compliant with GE/RT8030 Issue 2 to Virgin Trains (West Coast) Fleets. GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 15-047-DEV Class 465/9 Trailer Open Standard Lavatory 2.4.1.1 b) (TOSL) reduction in roll-over angle to 19.3 degrees. Current Deviations Register as at 09 May 2016 15-052-DEV Scope Nature and Degree The deviation application applies to seven This clause references BS EN 14033-1: vehicles of six different types (as detailed 2011, Clause 9. 2. 5. 2. BS EN 14033-1: below) that are to be used for erection of 2011 Clause 9. 2. 5. 2 states: "Any spring Overhead Line Electrification (OLE) apply air release parking brake actuator equipment (other than the masts). These shall be provided with a mechanical release, vehicles are existing vehicles that have been accessible from the outside. It shall be manufactured by SVI S. p. A in Citt… di possible to operate such a release from a Castello, Italy, a company dedicated to the convenient position with consideration of the manufacture of on-track plant, and are: risk of contact with an electrified rail of the Traction Unit RT 250: Self-propelled and infrastructure. The parking brake actuators hauling vehicle with cab and crane; EVN No: shall reset automatically by filling with 99 70 9231 001-7. Wagon with four compressed air. The parking brake tensioning drums CG002A; unpowered, and actuators shall still be capable of manual semi-permanently connect to the: EVN No: release even when the full service brake is 99 70 9231 002-5. Wagon with four applied. The vehicles were designed and hydraulic drums CG002B; also unpowered; fitted with WABCO "Trainstop" parking currently fitted with a crane that will be brakes which do not have an automatic reset removed. EVN No: 99 70 9231 003-3. option after the parking brake has been Elevated self-propelled platform PT 500; self- released. The parking brakes are of an propelled mobile elevated working platform automatic spring-applied type. These with wire-positioning arm. EVN No: 99 70 parking brakes are released (if required) by 9231 004-1. Elevated self-propelled using a screw fixture on the end on the platform RSM 9; self-propelled mobile cylinder, and can only be reset by manually elevated working platform; two in the screwing the release fixture in the reverse consist. EVN Nos: 99 70 9231 005-8 and direction. The vehicles were designed to be 99 70 9231 006-6. APV 250; self-propelled fitted with the existing braking system, and and hauling vehicle with mobile elevated to fit an alternative brake would involve an working platform and measuring underframe re-design and modification, pantograph. EVN No: 99 70 9231 007-4. including structural changes to the Borders Rail Project - ELR: SBO, There is a requirement within the standard Galashiels Platform. that station platforms shall not be located on horizontal curves with radii less than 1000 m unless the particular geographical characteristics of the potential sites and the characteristics of the railway infrastructure at the proposed location of the platform do not provide a reasonable opportunity for achieving this. In October 2014, Transport Scotland requested that the project was to construct the future passive provision for nine-car trains as part of the current works. This resulted in a non-compliance of 70 m at the southern end of the 215 m long platform. The 70 m starts at the south end of the platform on a 632 m radius, which then transitions to a straight platform over a 35 m length. The introduction of a reduced horizontal radii curve through the station will not have an impact on the operational and safe running of the railway. A sketch of the proposed track alignment is enclosed. Network Rail and ScotRail have jointly agreed that the risks associated with the proposed deviation from GI/RT7016 are tolerable: they do not warrant any additional measures to be introduced to allow safe train dispatch as the conductor has full visibility of all doors. This application relates to a total of seven Activation of the emergency egress device is three-car tram-train Electric Multiple Units recorded on the On Train Monitoring (EMUs). Unit numbers: · 399201 - 399207. Recorder (OTMR). Activation of the Vehicle numbers: · 99001 - 99007; · 99101 - passenger communication system is 99107; · 99201 - 99207. proposed not to be recorded on the OTMR. This application relates to a total of seven Operation of the passenger communication three-car tram-train Electric Multiple Units device does not initiate a brake application. (EMUs). Unit numbers: · 399201 - 399207. The tram-train is fitted with different brake Vehicle numbers: · 99001 - 99007; · 99101 - operating modes compared to mainline 99107; · 99201 - 99207. vehicles. Risk Assessment/Safety Justification Applicant Organisation The impact of the alternative provision is a SGS CORREL Rail Ltd negligible risk. The parking brake will only be manually wound off in an emergency recovery situation by specialised staff. In these specialised and very rare occasions, it will be necessary for the recovery staff to manually remove the mechanical device used to wind-off the parking brake when parking the vehicles after they have been recovered. This is documented in the recovery procedures they will be following and poses no greater risk in that situation than a vehicle with a manual handbrake that needs to wound on. The same deviation has been given to Plasser (reference 15/002/DEV). Certificate Issue Date 02/09/2015 Certificate End Date N/A Lead SC RST Lead SC Approval Date 24/07/2015 Deviation Status Current The proposed station is to be located in Network Rail Galashiels town centre and is to be constructed adjacent to the new transport bus interchange being constructed by the local authority. This is in accordance with the requirements of the legislation on which the project is based (I. e. the Waverley Railway (Scotland) Act 2006). The Act provides powers for the compulsory purchase of land, as identified within it, for the sole purpose of constructing of the railway. The horizontal alignment follows the former track solum and the associated land available (I. e. limit of deviation) as defined in the Waverley Act and does not offer any credible alternatives to the horizontal radius proposed. The alignment is further constrained by an existing retaining wall on the East side of the track and a public road on the west side of the railway line. Additionally the alignment is further constrained by the existing overbridge 011/101A which is located just south of the proposed station. This structure is to be retained. The proximity of the existing overbridge at the south end of the station, the track being located on the solum of the original alignment, the station being located between an existing retaining wall and a The recorded images from the on-board Stagecoach Supertram CCTV will be available for post-incident investigation. 10/08/2015 N/A INS 08/07/2015 Current 02/09/2015 N/A RST 24/07/2015 Current The driver is responsible to apply the brake Stagecoach Supertram 19/08/2015 following the activation of the passenger communication device. Separate brake systems are capable of providing the equivalent of an emergency brake application. · 390/0 and 390/1 trainsets in the number Fit the latest train-borne equipment It is considered that, due to the benefits West Coast Trains Ltd (trading 29/07/2015 range 01 to 57; · 221 trainsets in the number compliant with GE/RT8075 Issue 2, in identified in Section 11 - Proposed as Virgin Trains) range 221101 to 221118 and 221142 to accordance with GE/RT8075 Issue 1, to the alternative provisions, the alternative 221144. fleets of trainsets operated by Virgin Trains provisions improve the safety of the railway (Class 221 'Super Voyager' and Class 390 system whilst retaining compatibility with the 'Pendolino) would require: Additional cab current TPWS Driver Machine Interface wiring from the control unit to the Driver (DMI) and bogie mounted AWS / TPWS Machine Interface (DMI). Revisions to the equipment. Virgin Trains consider that the cab desk layout, to accommodate the larger safety benefits outweigh the costs of the new 'footprint' of the Mk4 DMI. Modification or control units, without any detriment to TPWS replacement of the existing On-Train reliability and availability. There are no Monitoring Recorder (OTMR), to impacts of the alternative provisions with the accommodate the different OTMR interface drivers, with minimal impact for the vehicle that the Mk4 unit provides. Revisions to the maintainers, which are based upon the OTMR data analysis software to revision of parts numbers in vehicle accommodate the Mk4's serial channel maintenance documentation. The above OTMR interface. These requirements are comments are supported by the successful onerous (in terms of cost and trainset trial of TPWS Mk3 control units to five-off downtime) in comparison to the benefits that Class 390 cab vehicles, since 2010. Virgin the fitment of the equipment conforming to Trains considered the safety benefits GE/RT8075 Issue 2 provides, thus it is realised during the remaining life of the considered that there is not a 'reasonable franchise, outweigh the cost of the control opportunity' (Clause 6. 2. 1. 3 of GE/RT8075 base unit without any detriment to Issue 1) to modify the vehicles and related dependability and reliability. software to accommodate the equipment conforming to GE/RT8075 Issue 2. N/A RST 24/07/2015 Current N/A Control Command and Signalling 09/07/2015 Current All Class 465/9 TOSL vehicles that have Vehicles shall be designed with mass completed their PRM interior refurbishment. distribution and suspension characteristics which ensure the capability to run round smooth curves at constant speed, without rolling over, at not less than 21ø cant deficiency. Currently, the vehicles have started a refurbishment programme to bring the vehicles into line with the latest Persons of Reduced Mobility (PRM) requirements. The effect of this interior change on the TOSL vehicle is to create additional standing room in the crush condition when wheelchairs are not present. The additional standees increase the mass and raise the vertical centre of gravity which, in turn, has increased the sway and roll-over angle of the vehicle. A comparative gauging exercise has been undertaken demonstrating the minimum full unloading (roll-over) angles in Table 2. 4 of the attached Mott MacDonald report - Dynamic evaluation of 465/9 PRM modifications. As may be seen, the vehicle meets the standard requirements (>21 degrees) in tare but fails in crush. The existing "Reference" vehicle fails with an inflated roll-over angle of 19. 63 degrees and deflated roll-over angle of 20. 69 degrees. The modified vehicle fails with angles of 19. 27 and 20. 40 respectively (the N/A RST N/A Current Reduction in the roll-over angle from 21 to 19. 3 degrees would enable the TOSL vehicles to continue to operate post PRM modification without significant re-design of their suspension. ESG Ltd 28/05/2015 Page 18 Deviations Register RGS Number GKRT0045 RGS Issue Number Four RGS Title Lineside Signals, Indicators and Layout of Signals Certificate Number 15-046-DEV Title Bromsgrove Signals: BA3603 (FYY), BA3609 (FY+FYY), BA3611 (MAY+FY), BA3617 (MAY), BA7631, BA7619, BA9621 and BA7623. RGS Clause 5.5.1 d) Scope ELR: BAG2;Location: BromsgroveMilage: 52½ to 56½ miles;Signals: BA3603 (FYY), BA3609 (FY+FYY), BA3611 (MAY+FY), BA3617 (MAY), BA7631, BA7619, BA9621 and BA7623. Nature and Degree Compliance to RGS would prohibit the use of a flashing aspect approach for services into the Down Bromsgrove loop, or the flashing aspect sequences for diverging routes to platforms 1, 2 or 3. Both of these options have significant performance impact. Due to the severe gradient of the Lickey incline, it is felt that the application of Main Aspect Red (MAR) controls increases driver expectancy of signal to clear in this gradient area. GKRT0075 Three Lineside Signal Spacing and Speed Signage 15-045-DEV Bromsgrove Signals: BA3609, BA3611, BA3617 and BA3633. Appendix A - Section A1 ELR: BAG2; Location: Bromsgrove; Mileage: 52« to 56« miles; Signals: BA3609, BA3611, BA3617 and BA3633. Signalling Braking Distance Data for all Trains' has a number of tables that provide train braking data for various gradients. On 'Composite table for all trains' the steepest falling gradient that data is provided for is 1 in 50. A note is provided below the graph that states 'For gradients greater than 1 in 50 falling - seek derogation'. Situated between Blackwell and Bromsgrove is the steepest main line railway in the country Lickey Incline - which has a gradient of 1 in 38 and is approximately 2 miles long. The non-compliance is due to this geographical feature. It would cost about œ150,000,000 to change the Lickey Incline and regrade it into an area addressed in the requirements. Conversely, for signals to be positioned descending down this gradient, there is no braking data provided in GK/RT0075 for all trains, therefore it is not possible to comply with the requirements. GERT8402 One ERTMS/ETCS DMI National Requirements 15-044-DEV WCR Class 37 ETCS DMI speed display. 2.2.1 The deviation applies to two Class 37 locomotives listed below that are being fitted with the Hitachi on-board subsystem to provide ETCS functionality (baseline 2. 3. 0d). · Vehicle 37668, · Vehicle 37669. The trains are owned and operated by West Coast Railways. They will be used for operation on the Cambrian Line (in ETCS Level 2) and elsewhere on Network Rail controlled infrastructure (in ETCS Level 0). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GMRT2400 Five Engineering Design of On-track Machines in 15-043-DEV Running Mode Emergency Brake Override 2.3.1.1 GMRT2130 Four Vehicle Fire, Safety and Evacuation 15-039-DEV Sheffield Tram-Train Fire Safety and Evacuation Performance. GMRT2100 Five Requirements for Rail Vehicle Structures 15-038-DEV Sheffield Tram-Train Structural Performance Part 2 - All clauses; Part 3 - 3.3.2 and (Issue 3). 3.3.3.1; Part 4 - All clauses; Part 5 - 5.3.1.4, 5.3.2, 5.3.3 and 5.3.4; Clause 5.4.2 Part 6 6.1.2, 6.2.4, 6.9.1.2, 6.5 and 6.6; Part 7 - All clauses, plus Clauses 5.2.3 and 9.2 for aerodynamics. Part 2 - All clauses. Part 4 - All clauses. Part This application relates to a total of seven 5 - 5.1.1 d). Part - 6.3.3.Part 7 - 7.1.6, 7.1.8 three-car tram-train EMUs: Unit numbers: and 7.1.9. 399201 - 399207; Vehicle numbers: 99001 99007,99101 - 99107, 99201 - 99207. This application relates to a total of seven three-car tram-train Electric Multiple Units (EMUs) for operation between Meadowhall South (on the Sheffield tramway), Rotherham Central and a new turn-back platform at Parkgate. Unit numbers: 399201 - 399207. Vehicle numbers: 99001 99007;99101 - 99107;99201 - 99207. Current Deviations Register as at 09 May 2016 Risk Assessment/Safety Justification The main risk with this proposal is that a train driver gets confused as to which flashing yellow aspect sequence applies to which junction. The worst case scenario is that a driver thinks he is set for the loop when he is in fact set for a route into one of the platforms. The risk is that the driver misjudges his speed and takes the closer junction too fast. Another risk is that the driver loses his bearings in fog or at night time and get confused as to which junction the flashing yellows are set for. Mitigations for the risk are: The provision of Preliminary Routing Indicators (PRIs) for the first flashing sequence only. The PRIs provide early route information as to which platform the driver will be signalled into. The PRIs will indicate forward arrows for a route set onto the Loop Permanent Speed Warning Indicators (PSWIs) are provided for each turnout. The Automatic Warning System (AWS) will be suppressed for routes which do not apply for that sign. The turnout speed onto the loop is 50 mph and the turnout speed into the station is 40 mph only a 10 mph difference. A train taking the 40 mph turnout at 50 mph will not derail. PSWI with AWS are provided to enforce the turnout speeds. There are geographic The overrun risk, layout design and Train Protection and Warning System (TPWS) provision at the bottom of the incline has taken into account the severe falling gradient. Options that have been developed for the new Bromsgrove Station track layout have taken into account the need to avoid conflicting train moves at the bottom of the incline. Another factor is that, as a result of the electrification and new station increased passenger traffic will use the incline, including three additional trains per hour which will be turning back at Bromsgrove once the electrification is commissioned. It is considered that, even with the provision of Overhead Line Electrification (OLE) masts, the signal sighting will be very good down the incline. As a result of an incident several years ago, special controls are in place on the incline. Today, G10 signal provides the first caution when G16 is at red. In the proposed re-signalling, the provision of fouraspect signalling achieves the same result in that the first caution will be at the summit of the incline. Also, the use of four-aspect signalling gives the driver a clearer message about the status of the line ahead than the previous Main Aspect Red (MAR) control. Existing signal G16 has been The chosen solution must provide technical compatibility with the existing Cambrian infrastructure, as well as achieving the necessary level of safety. The proposed implementation will mean that the two fitted vehicles behave in an identical manner to the 24 Class 158s and three Class 97/3s fitted by Ansaldo that are currently operating on the Cambrian. From a CSM RA perspective, the Ansaldo implementation is considered to be a reference system since it is already successfully implemented in equivalent vehicles operating over the relevant infrastructure. The proposed implementation is compatible with the existing Cambrian and off-Cambrian trackside, as already demonstrated by trials of a test locomotive (97301) fitted with the proposed software. The proposed implementation is compatible with the National Onboard Subsystem Requirements Specification which forms the requirements specification for future ETCS fitment. There is no impact on costs, service performance, reliability or availability. The only identified issue is the behaviour of the vehicles if they enter an ETCS-fitted trackside area other than the Cambrian, and this trackside uses mph in Level 2. This is already an issue for It is considered that there is no increased risk by adopting the proposed alternate provisions. Applicant Organisation Network Rail Certificate Issue Date 02/11/2015 Certificate End Date N/A Lead SC Control Command and Signalling Lead SC Approval Date 01/10/2015 Deviation Status Current Network Rail 25/06/2015 N/A CCS 11/06/2015 Current Hitachi Rail Europe 10/07/2015 N/A CCS 11/06/2015 Current Plasser UK 23/07/2015 N/A RST 19/06/2015 Current See appendix A Issue 2. Stagecoach Supertram 18/12/2015 N/A Rolling Stock N/A Current The tram-trains are being built to an existing The tram-train is similar to designs of tram- Stagecoach Supertram design that is based on compliance with trains vehicles in Germany. More details are European standards, in particular EN 12663- provided in Appendix A. 1, EN 15227, EN 13749, EN 15152 and EN 14752. 16/10/2015 N/A Rolling Stock 22/05/2015 Current The Cambrian ETCS trackside was implemented before the production of GE/RT8402, and the trackside is not compatible with the requirements of GE/RT8402. Development work would be required on the trackside to allow a train that is compliant with GE/RT8402 to operate as expected. At present, a train leaving the Cambrian will retain its NID_C value, and hence will continue to display speed in km/h in Level 0. This is not the required outcome since the train is now displaying km/h on the DMI but all lineside signage is in mph. Modifications to the trackside would be required to send a new NID_C value to the train (by RBC and balise) as it left the Cambrian. Modifications to the existing support and maintenance procedures would also be required so that existing Cambrian national values balises used for maintenance purposes are removed from use and replaced with balises with a suitable alternative NID_C set of national values for use off of the Cambrian. The Hitachi onboard software was developed and tested, based on the specification used for existing ETCS-fitted Class 97/3 locomotives operating on the Cambrian Line. This development work pre-dated the issue of Plasser and Theurer on track machines The final paragraph of BS EN 14033-1: 2011 authorised to self-propel outside Clause 9. 2. 7 mandates "An override device possessions. The following machines will for the emergency brake for use by the not have a driver's override for the driver shall be provided where there is the emergency brake fitted: DR Number EVN possibility of the emergency brake being DR74002 99 70 9128002-1 DR77909 99 70 applied remotely from the driving cab. " To 9125909-0 DR77010 99 70 9125010-7 comply with this paragraph would require DR73120 99 70 9123120-6 DR73121 99 70 the development of an override system 9123121-4 DR73122 99 70 9123122-2 This capable of achieving the required deviation is for a project requiring functionality without any reduction in safety authorisation for placing in service under the or reliability. Apart from the driving cab, the Railways (Interoperability) Regulations 2011. only other location on an on-track machine where personnel are authorised to be present during running is the rear cab. There is direct communication between the rear cab and the operable driving cab. In the exceptionally unlikely event of the need to apply the emergency brake from the rear cab, any personnel present in the rear cab will be trained On-track Machine (OTM) staff who will be able to explain to the driver why they have done so and reset the emergency brake button if requested by the driver. See appendix A Issue 2. Page 19 Deviations Register RGS Number GMRT2132 RGS Issue Number One RGS Title On-board Energy Metering for Billing Purposes Certificate Number 15-036-DEV Title Sheffield Tram-Train Energy Metering. RGS Clause All clauses. GMRT2044 Four Braking System Requirements and Performance for Multiple Units 15-035-DEV Sheffield Tram-Train Braking Performance. 5.4.1 and 5.4.2, 7.1.2 and 7.1.3. GCRT5021 Five Track System Requirements 15-034-DEV Wembley Turnback Siding - gradient. 2.8.2.1 GIRT7016 Five Interface between Station Platforms, Track and Trains 15-033-DEV Wembley Stadium Station - position of Driver Operation Only (DOO) Mirrors. 6.5.3 and 8.1.1 GIRT7016 Five Interface between Station Platforms, Track and Trains 15-031-DEV South Ruislip station, Platform 3 - position of 6.5.3 and 8.1.1 Driver Operation Only (DOO) Mirror. Current Deviations Register as at 09 May 2016 Scope This application relates to a total of seven three-car tram-train EMUs to be operated on the line from the junction between the Sheffield Tramway system and Network Rail, and on the line to Rotherham and Parkgate. Unit numbers: · 399201 399207. Vehicle numbers: · 99001 - 99007; · 99101 - 99107; · 99201 - 99207. This application relates to a total of seven three-car Tram Train EMUs. Unit numbers: · 399201 - 399207. Vehicle numbers: · 99001 - 99007, · 99101 - 99107, · 99201 99207. · Name: Wembley Turnback Siding; · ELR: NAJ1; · Mileage: 4m70ch; · OS Ref: TQ189 853. Wembley Stadium Station - position of Driver Operation Only (DOO) Mirrors. South Ruislip station, Platform 3 - DOO Mirror. Nature and Degree GM/RT2132 was published to close an open point in the Conventional Rail Conventional Rail Locomotives and Passenger Technical Specification for Interoperability (CR Loc and Pas TSI) 2011. Subsequently, the TSI has been reissued and this references EN 50463: 2012. Risk Assessment/Safety Justification Applicant Organisation The limited number of units operating from a Stagecoach Supertram single maintenance location enables a manual download as an alternative to the provision of a wireless network. Certificate Issue Date 03/07/2015 Certificate End Date N/A Lead SC RST Lead SC Approval Date 22/05/2015 Deviation Status Current See appendix. See appendix. 15/06/2015 N/A RST 22/05/2015 Current In September 2015, Chiltern Railways will begin to operate nine-car trainsets as a part of the High Level Output Specification (HLOS) remit to provide access for 1000 extra passengers during the peak commuter hours into / out of London Marylebone Station. Chiltern Railways have identified that Wembley turnback will require lengthening to enable nine-car trainsets to leave Wembley depot and return to London in the contra-peak to enable operational readiness for the PM peak. Wembley turnback, which is currently only long enough for eight-car trainsets, is located between the up and down main lines and has a gradient of 1 in 90 which does not comply to 1 in 500 as specified in GC/RT5021. The length of extension required is 40 m. Please refer to Appendix A of the Wembley GRIP 3 report (70008452WSP-REP-MD-002) for further details of the proposed track layout. To comply with the requirement, the existing turnback track would have to be completely removed. The level of the turnback would have to drop lower than that of both the Up and Down main (approximately 2. 5 m lower). A contiguous bored pile wall would need to be installed along both sides with a reinforced It is not deemed appropriate to achieve compliance by moving the mirror because this would result in: Compromising the position of the mirrors, increasing the risk of the driver being unable to identify passengers fouling the Platform Train Interface when departing from the station; Increasing the likelihood of the driver adjusting their operating position to optimise the view of the Platform Train Interface. This introduces a hazard to the Driver, resulting in possible occupational health issues; Disproportionate costs associated with the construction of compliant supporting structures. Medium - No health and safety issues have been reported relating to the position of the existing mirror. The design solution proposes extension of Network Rail the existing siding by 40 m at the current 1 in 90 gradient; please refer to Appendix A of the Wembley GRIP 3 report (70008452WSP-REP-MD-002) for further details of the proposed track layout. This proposal has the following benefits over a compliant solution: · Simpler design solution; · Greatly reduced number of possessions, meaning less disruption to passengers and significantly reduced schedule 4 costs; · No impact on Up / Down main track support zone; · Minimal performance issues as existing turnback siding could remain operational during the majority of construction works. The cost estimate for this solution is œ200k (GRIP 3). 20/07/2015 N/A INS 13/05/2015 Current Project Ref. 143467 - Chiltern Railways Network Rail and London Midland/London Overground DOO Mirrors Renewal/Recovery. This deviation is requested for a like for like renewal on a Driver Only Operation Mirror (DOO) which forms part of a larger scheme for the renewal of 30 mirrors on the Chiltern line. These mirrors are now nearing the end of life as most of them were installed before 1994. The existing mirrors, and proposed new mirrors in the same position, are less than the required 2000 mm from the platform edge required by the standard. The existing mirrors are located as follows: · P1 5 Car - 2120 mm from the platform edge and the bottom of the mirror is 2280 mm from the surface of the platform; · P2 4 Car - 1750 mm from the platform edge and the bottom of the mirror is 2030 mm from the surface of the platform; · P2 8 Car - 720 mm from the platform edge and the bottom of the mirror is 1720 mm from the surface of the platform. The project has conducted a review of the existing DOO mirrors. For those found non-compliant, representatives from the Train Operating Company (TOC), Network Rail and design contractor conducted a site visit. This visit concluded that the mirror could not be moved to a Project Ref. 143467 - Chiltern Railways Network Rail and London Midland/London Overground DOO Mirrors Renewal/Recovery. This deviation is requested for a like for like renewal on a Driver Only Operation Mirror (DOO) which forms part of a larger scheme for the renewal of 30 mirrors on the Chiltern line. These mirrors are now nearing the end of life as most of them were installed before 1994. The existing mirror, and proposed new mirror in the same position, is less than the required 2000 mm from the platform edge required by the standard. The existing mirror is located as follows: · P3 three-car: 2165 mm from the platform edge and the bottom of the mirror is 2040 mm from the surface of the platform. The project has conducted a review of the existing DOO mirrors. For those found non-compliant, representatives from the Train Operating Company (TOC), Network Rail and design contractor conducted a site visit. This visit concluded that the mirror could not be moved to a compliant position without impacting on the driver's image of the train and associated safety aspects of operation. As a result, it is proposed that the mirror is renewed in the current position. The proposal is to: Renew the mirror on a 'like 10/07/2015 N/A INS 13/05/2015 Current 15/06/2015 N/A INS 13/05/2015 Current It is not deemed appropriate to achieve compliance by moving the mirror because this would result in: Compromising the position of the mirrors, increasing the risk of the driver being unable to identify passengers fouling the Platform Train Interface when departing from the station; Increasing the likelihood of the driver adjusting their operating position to optimise the view of the Platform Train Interface. This introduces a hazard to the driver, resulting in possible occupational health issues; Disproportionate costs associated with the construction of compliant supporting structures. Platform 3, three-car mirror View of the rear of the three-car train is limited due to the waiting room building protruding into the platform. Option of moving three-car stop further up the platform was considered however the car stop would extend just short of the EOP mirror and would also mean passengers have an extended walk down the platform which would result in the TOC receiving customer complaints. Medium - No health and safety issues have been reported relating to the position of the existing mirror. Moving the mirrors could compromise the position of the mirror, increasing the risk of Stagecoach Supertram Page 20 Deviations Register RGS Number GIRT7016 RGS Issue Number Five RGS Title Interface between Station Platforms, Track and Trains Certificate Number 15-030-DEV Title Great Missenden Platform 1 - position of Driver Operation Only (DOO) Mirror. RGS Clause 8.1.1 Scope Great Missenden Platform 1 - position of Driver Operation Only (DOO) Mirror. Nature and Degree It is not deemed appropriate to achieve compliance by moving the mirror because this would result in: Compromising the position of the mirrors, increasing the risk of the Driver being unable to identify passengers fouling the Platform Train Interface when departing from the station. Increasing the likelihood of the driver adjusting their operating position to optimise the view of the Platform Train Interface. This introduces a hazard to the driver, resulting in possible occupational health issues. Disproportionate costs associated with the construction of compliant supporting structures. Medium - No health and safety issues have been reported relating to the position of the existing mirror. GIRT7016 Five Interface between Station Platforms, Track and Trains 15-029-DEV Gerrards Cross Platform 1 - position of Driver Operation Only (DOO) Mirrors. 6.5.3 and 8.1.1 Gerrards Cross Platform 1 - position of Driver Operation Only (DOO) Mirrors. It is not deemed appropriate to achieve compliance by moving the mirror because this would result in: Compromising the position of the mirrors, increasing the risk of the driver being unable to identify passengers fouling the Platform Train Interface when departing from the station. Increasing the likelihood of the driver adjusting their operating position to optimise the view of the Platform Train Interface. This introduces a hazard to the driver, resulting in possible occupational health issues. Disproportionate costs associated with the construction of compliant supporting structures. GIRT7016 Five Interface between Station Platforms, Track and Trains 15-028-DEV Denham station platform 2 four-car stop position of Driver Only Operation (DOO) mirror. 8.1.1 Denham station platform 2 four-car stop position of DOO mirror. It is not deemed appropriate to achieve compliance by moving the mirror because this would result in: Compromising the position of the mirrors, increasing the risk of the driver being unable to identify passengers fouling the Platform Train Interface when departing from the station. Increasing the likelihood of the driver adjusting their operating position to optimise the view of the Platform Train Interface. This introduces a hazard to the driver, resulting in possible occupational health issues. Disproportionate costs associated with the construction of compliant supporting structures. GIRT7016 Five Interface between Station Platforms, Track and Trains 15-027-DEV Aylesbury Station Platform 2 and Platform 3 - 6.5.3 and 8.1.1 Driver Operation Only (DOO) Mirrors. Current Deviations Register as at 09 May 2016 Aylesbury Station Platform 2 and Platform 3 - It is not deemed appropriate to achieve Driver Operation Only (DOO) Mirrors. compliance by moving the mirror because this would result in: Compromising the position of the mirrors, increasing the risk of the Driver being unable to identify passengers fouling the platform / train interface when departing from the station. Increasing the likelihood of the driver adjusting their operating position to optimise the view of the platform / train interface. This introduces a hazard to the driver, resulting in possible occupational health issues. Disproportionate costs associated with the construction of compliant supporting structures. Risk Assessment/Safety Justification This deviation is requested for a like for like renewal on a Driver Only Operation Mirror (DOO) which forms part of a larger scheme for the renewal of 30 mirrors on the Chiltern line. These mirrors are now nearing the end of life as most of them were installed before 1994. The existing mirrors, and proposed new mirrors in the same position, are less than the required 2500 mm from the platform surface required by the standard. The existing mirror is located as follows: P1 4 Car - 2250 mm from the platform edge and the bottom of the mirror is 2110 mm from the surface of the platform. The project has conducted a review of the existing DOO mirrors. For those found non-compliant, representatives from the Train Operating Company (TOC), Network Rail and design contractor conducted a site visit. This visit concluded that the mirror could not be moved to a compliant position without impacting on the driver's image of the train and associated safety aspects of operation. As a result, it is proposed that the mirrors are renewed in their current positions. The proposal is to: Renew the mirror on a 'like for like' basis; Re-use existing supporting structure. This would result in: No changes to the drivers' current working practice; Medium - No health and safety issues have been reported relating to the position of the existing mirrors. Moving the mirrors could compromise the position of the mirror, increasing the risk of the driver being unable to identify passengers fouling the Platform Train Interface when departing from the station. Project Ref. 143467 - Chiltern Railways and London Midland/London Overground Driver Only Operation Mirror (DOO) Mirrors Renewal/Recovery. This deviation is requested for a like for like renewal on a DOO which forms part of a larger scheme for the renewal of 30 mirrors on the Chiltern line. These mirrors are now nearing the end of life as most of them were installed before 1994. The existing mirrors, and proposed new mirrors in the same position, are less than the required 2000 mm from the platform edge and the required 2500 mm above the platform surface required by the standard. The existing mirrors are located as follows: · P1 4 Car North - 1620 mm from the platform edge and the bottom of the mirror is 1930 mm from the surface of the platform; · P1 4 Car South - 2373 mm from the platform edge and the bottom of the mirror is 1480 mm from the surface of the platform. The project Medium - No health and safety issues have been reported relating to the position of the existing mirror. Moving the mirrors could compromise the position of the mirror, increasing the risk of the driver being unable to identify passengers fouling the Platform Train Interface when departing from the station. Project Ref. 143467 - Chiltern Railways and London Midland/London Overground DOO mirrors renewal/recovery. This deviation is requested for a like for like renewal on a DOO Mirror which forms part of a larger scheme for the renewal of 30 mirrors on the Chiltern line. These mirrors are now nearing the end of life as most of them were installed before 1994. The existing mirrors, and proposed new mirrors in the same position, are less than the required 2500 mm above the platform surface required by the standard. The existing mirror is located as follows: 2150 mm from the platform edge and the bottom of the mirror is 2180 mm from the surface of the platform. The project has conducted a review of the existing DOO mirrors. For those found non-compliant, representatives from the Train Operating Company (TOC), Network Rail and design contractor conducted a site visit. This visit concluded Medium - no health and safety issues have been reported relating to the position of the existing mirror. Moving the mirrors could compromise the position of the mirror, increasing the risk of the driver being unable to identified passengers fouling the platform / train interface when departing from the station. Project Ref. 143467 - Chiltern Railways and London Midland/London Overground Driver Only Operation (DOO) mirrors renewal / recovery. This deviation is requested for a like for like renewal on a DOO which forms part of a larger scheme for the renewal of 30 mirrors on the Chiltern line. These mirrors are now nearing the end of life as most of them were installed before 1994. The existing mirrors, and proposed new mirrors in the same position, are less than the 2000 mm required by the standard. The existing mirrors are located as follows: · P2 4/2 Car - 1715 mm from the platform edge and the bottom of the mirror is 1655 mm from the surface of the platform; · P2 5/6 Car - 1810 mm from the platform edge and the bottom of the mirror is 1660 mm from the surface of the platform; · P3 S Car 1900 mm from the platform edge and the bottom of the mirror is 1345 mm from the surface of the platform. The project has Applicant Organisation Network Rail Certificate Issue Date 10/07/2015 Certificate End Date N/A Lead SC INS Lead SC Approval Date 13/05/2015 Deviation Status Current Network Rail 10/07/2015 N/A INS 13/05/2015 Current Network Rail 05/06/2015 N/A INS 13/05/2015 Current Network Rail 10/07/2015 N/A INS 13/05/2015 Current Page 21 Deviations Register RGS Number GIRT7016 RGS Issue Number Five RGS Title Interface between Station Platforms, Track and Trains Certificate Number 15-026-DEV Title Borders Rail Project - ELR: SBO, Stow Platform Curvature. RGS Clause 2.1.2 Scope Borders Rail Project - ELR: SBO, Stow Platform Curvature. GIRT7016 Five Interface between Station Platforms, Track and Trains 15-025-DEV Borders Project - ELR : SBO, Stow Up Platform (Southbound) - reduced platform width at existing building. 7.2 Borders Project - ELR : SBO, Stow Up Platform (Southbound) reduced platform width at existing building. GIRT7016 Five Interface between Station Platforms, Track and Trains 15-024-DEV Borders Rail Project - ELR : SBO, Gorebridge Platform Curvature. 2.1 Borders Rail Project - ELR: SBO, Gorebridge Platform Curvature. GKRT0045 Four Lineside Signals, Indicators and Layout of Signals 15-022-DEV PN177 signal non-provision of flashing double yellow. 5.2.3.4 PN177 signal only. Between Preston from Lancaster. Approaching Oxheys Up Passenger Loop. Current Deviations Register as at 09 May 2016 Nature and Degree The proposed station is to be located on the site of the original Stow station. The deviation relates to the full length of both the up and down platforms. The up platform (southbound) is to be constructed on a 780 m radius and the down platform (northbound) on a 777 m radius. This is in accordance with the requirements of the legislation on which the project is based (I. e. The Waverley Railway (Scotland) Act 2006). The Act provides powers for the compulsory purchase of land, as identified within it, for the sole purpose of constructing the railway. The horizontal alignment follows the former track solum and the associated land available (I. e. limit of deviation) as defined in the Waverley Act and does not offer any credible alternatives to the horizontal radius proposed. The alignment is further constrained by the existing public road overbridge 011/068 which is located at the north end of the station. The structure is to be retained. The station location is also constrained as it is to be located between a new housing development on the West side of the station and Stow primary school which is located on the east side of the station. Additionally, it has been requested that the existing station The proposed station is to be located on the site of the original Stow station. This is in accordance with the requirements of the legislation on which the project is based (I. e. The Waverley Railway (Scotland) Act 2006). The Act provides powers for the compulsory purchase of land, as identified within it, for the sole purpose of constructing the railway. The horizontal alignment follows the former track solum and the associated land available (I. e. limit of deviation) as defined in the Waverley Act and does not offer any credible alternatives to the horizontal radius proposed. The existing station building is to be retained at the request of Scottish Borders Council for use by the local community. The alignment is further constrained by a new housing development on the West side of the station and Stow primary school which is located on the east side of the station as well as the existing public road overbridge 011/068 which is located at the north end of the station. This structure is to be retained. The proposed track alignment is required to allow those trains which do not stop at Stow to achieve a speed of 70 mph and thus meet the desired timetable requirements. The proposed station is to be located on the site of the original Gorebridge station. The non-compliance relates to 48 m of the 164 m long platform. The 48 m starts at the north end of the platform on a 298 m radius which then transitions to a 1198 m radius over its length. This is in accordance with the requirements of the legislation on which the project is based (I. e. The Waverley Railway (Scotland) Act 2006). The Act provides powers for the compulsory purchase of land, as identified within it, for the sole purpose of constructing of the railway. The horizontal alignment follows the former track solum and the associated land available (I. e. limit of deviation) as defined in the Waverley Act and does not offer any credible alternatives to the horizontal radius proposed. The alignment is further constrained by the existing public road overbridges 011/025 and 011/026 which are located at each end of the station. These structures are to be retained. The station is also to be located within an earthworks cutting which further constrains the alignment. Risk Assessment/Safety Justification Applicant Organisation Severity is low, as proposed platform Network Rail gauging, clearances and stepping distances will continue to meet the necessary Technical Specifications for Interoperability (TSI) and national requirements. Compliant stepping distances and track cant are being provided within the design (I. e. cant is 85 mm). Signal sighting is not affected by the track curvature in this location. The introduction of a reduced horizontal radii curve through the station will have an impact on train dispatch operations as the conductor / guard will be unable to see all the train doors on the up (southbound) platform without further support. The conductor / guard, who has responsibility for dispatching the train, can see all the train doors when dispatching a six-car train from the down (northbound) platform, however, is unable to see all the doors when dispatching a five or six-car train from the up (southbound) platform. Drawing nos. 129713-URS-DRG-ST-CV-805-00004, 005 and 047 are enclosed which highlight the train conductor / guard's position during train dispatch. To aid the conductor / guard's visibility during train dispatch from the up platform, viewing aids (consisting of Close Circuit Television (CCTV) and monitor bank) A derogation workshop between Network Network Rail Rail and the Train Operating Company (First Scotrail) has been held and a subsequent site visit has taken place. Based on output/ findings of these, it has been identified that the bay window on the west gable wall would need to be modified or removed, platform surface hatching and signage would be introduced, the blue badge bays would be relocated to the south side of the existing station building and the train car stops would be positioned to check for any conflicts between train door location and the narrow section of platform. The introduction of a reduced horizontal Network Rail radii curve through the station will not have an impact on the operational and safe running of the railway. Proposed platform gauging, clearances and stepping distances will continue to meet the necessary Technical Specification for Interoperability (TSI) and national requirements. A sketch of the proposed track alignment is enclosed. Network Rail and Scotrail have jointly agreed that the risks associated with the proposed deviation from GI/RT7016 are tolerable and do not warrant any additional measures to be introduced to allow safe train dispatch as the conductor has full visibility of all doors. Compliant stepping distances and track cant are being provided within the design (I. e. cant is 110 mm at the north end of the platform transitioning to 40 mm at the south end of the platform). Signal sighting is affected by the track curvature in this location and, to overcome sighting issues, an OFF indicator shall be provided for signal EMB 276, and a banner repeater shall be provided for signal EMB 277. The conductor/ guard, who has responsibility for dispatching the train, can see all the train doors and the OFF indicator from the centre of the platform. Drawing nos. 129713-URSCompliance would require either nonAlternative proposal has potential for Network Rail provision of flashing sequence into Oxheys drivers to not respond to PN177 at steady Up Passenger Loop, that has been identified YY. This has been considered and is as providing significant operational benefit mitigated by excellent sighting on PN175 with the new turnout speed or provision of a signal and braking distance at linespeed flashing aspect to PN177 signal that has from the sighting point of the PN175 signal signal sighing risks. Due to a curved to junction signal PN173. These allows approach to PN177 it has been determined driver to response to sequence and does not by signal sighting as not being suitable for significantly impact on SPAD risk. Risk provision of a flashing aspect. PN177 has severity is considered to be less than the multiple Overhead Line Electrification (OLE) existing arrangement due to the removal of stanchions on the approach that causes the Main Aspect Red (MAR) and anticipation aspect to appear and disappear several risk that PN173 signal will clear on times in quick succession, potentially approach. Because PN177 cannot flash, imitating a flashing aspects. and deceleration distance to 40 mph is not available from PN175 signal, the advanced permissible warning indicator for the turnout is positioned between PN177 and PN175 signals. Appropriate Automatic Warning System (AWS) suppression controls are provided for this Level Crossing Advance Warning Signs (AWI). The warning indicator is 670 m on the approach to PN175 and has been positioned to ensure PN175 is visible from the warning indicator. See attached Oxheys Signalling Design Review. Certificate Issue Date 05/06/2015 Certificate End Date N/A Lead SC INS Lead SC Approval Date 13/05/2015 Deviation Status Current 05/06/2015 N/A INS 13/05/2015 Current 05/06/2015 N/A INS 13/05/2015 Current 29/04/2015 N/A CCS 19/03/2015 Current Page 22 Deviations Register RGS Number GMRT2466 RGS Issue Number Three RGS Title Railway Wheelsets Certificate Number 15-021-DEV Title Deviation for the use steel grade - ER9T wheel material. RGS Clause 2.9.1 Scope South West Trains (SWT) operate seven Multi-Purpose Vehicles (MPV) manufactured by Windhoff. These vehicles are suffering high tread wear and SWT wish to trial a harder wheel material to increase the tread life. The proposal is to replace the current R8 wheels with ER9T, this is not currently permitted by the standard. The trial will be undertaken on vehicles 98922 and 98972. Nature and Degree The SWT MPV vehicles are currently operating with R8 wheels and these typically require turning to restore the tread condition twice in the autumn leaf fall season. At this time, the vehicles are mainly being used for the laying of Sandite. The time out of service whilst the turning is being undertaken is costly to the railway system. SWT wishes to determine if using a harder wheel steel (ER9T) will reduce the wheel wear and allow the vehicles to operate more effectively. SWT would expect to see an increase in vehicle availability, reduction in wheel turning costs and a commercial benefit from having a longer wheel life. None of this will be achieved if the R8 steel is retained. The 3 standards permitted by GM/RT2466 either list ER9T or have an equivalent to this: BS 5892, Part 3: R9; BS EN 13262: ER9/ ER9T; AAR: M-107/M208. Therefore, ER9 is not an unknown material grade for use in wheel applications. GMRT2181 Three Overhead Line Equipment (OLE) Warning Line on Traction and Rolling Stock 15-019-DEV Sheffield Tram-Train OLE Warning Line Height 5.1.2 This application relates to a total of seven three-car tram-train Electric Multiple Units (EMUs) - unit numbers: · 99001 - 99007, · 99101 - 99107, and · 99201 - 99207. Clause 5. 1. 1 requires the OLE warning line to be positioned no closer than 600 mm to the nearest train-mounted live equipment, and in a position where it is clearly visible when standing at rail level. Clause 5. 1. 2 requires the OLE warning line to be positioned at a minimum height of 3100 mm above rail level. The low-floor design of the tram-train vehicles requires more equipment to be mounted on the roof when compared to a typical mainline rail vehicle, and it is not possible to achieve both the 600 mm electrical clearance required by Clause 5. 1. 1 and the minimum height required by Clause 5. 1. 2. GIRT7033 Two Lineside Operational Safety Signs 15-018-DEV Provision of specific platform stop markers for Class 700 trains. Section AK, sub-section 1, sign AK104z Class 700 'Thameslink Unit' and all its sub- The design specification of the class 700 classes. All routes where Govia Thameslink unit is of fixed formations of eight and twelve Railway operates. cars with a central driving position. There is no provision of a side-window in the cab to facilitate the use of existing platform stop markers and this, in conjunction with the length of the unit, would lead to an unacceptable degree of inaccuracy in the positioning of the train at a platform when using the existing marks (please refer to Stopping Strategy document). Section 13 of this document (`What other options have been considered?') provides further evidence of the potential impacts of complying with GI/RT7033. GERT8000-T3 Five Possession of a running line for engineering 15-017-DEV work Giving Up Possessions Around a Train. 7.1 National change. GIRT7016 Five Interface between Station Platforms, Track and Trains Reduced platform width at West Drayton Station for construction hoardings on Platform 2 and Platform 3. 6.2.2 West Drayton Station Platform 2 and Platform 3. Current Deviations Register as at 09 May 2016 15-015-DEV Currently, if a train is in a possession that has axle counters within it as a means of train detection, and a train is outside of the section detected by axle counters, the Rule Book is not clear if the possession can be given up around a train as the Rule Book states that the line must be signalled by the track circuit block (other than by axle counters). Currently, Rule Book Module T3 Section 7. 1 (bullet point 1) is not clear when giving up a possession around a train when a section detected by axle counters is within the possession and the train is not within that section of line but stands within a section detected by track circuits. A possession could be 20 miles in length with 5 miles of this containing axle counter as the means of detection the other 15 miles could be detected by track circuits but the whole section has to be clear of trains before possession can be given up as the current rule is written. Temporary hoarding will be erected on the platforms 2/3 at West Drayton during construction of lift shaft and stair foundations, which will reduce platform width during construction period. Network Rail wishes to temporarily deviate from this standard whilst construction of a new footbridge is carried out in the centre of platform 2/3 at West Drayton. Please read the below statement alongside attached sketches. The new footbridge design complies with the railway standard as demonstrated by attached Sketch 1. Compliance cannot be achieved for the construction of the structure. Sketch 2 demonstrates this by showing a section of the completed structure and the limited space which remains for formwork and hoarding. Sketch 3 shows a proposal for temporary non-compliance which reduces the platforms to a width of 2. 0 m on Platform 3 and 2. 563 m on Platform 2. This will allow the structure to be constructed and, following completion of the works, the platform widths will be returned to compliant widths. Risk Assessment/Safety Justification Retaining the current R8 material will result in high maintenance costs and it is anticipated that employing the harder ER9T steel will allow these to be reduced. There might be a concern that introducing harder wheels on to the system will result in increased rail wear; however, recent research work has identified that this is not the case. V/T SIC report Wheel/rail hardness and total "system" wear report, by Mark Burstow 18/10/2012 (copy attached) summarised that: "It has been found that increasing the hardness of one material has little or no effect on the wear rate of the other material, and many researchers have actually observed a reduction in the wear rate in both materials when the hardness of one of them is increased. " This was backed up by: "In 1993 an internal British Rail Research report, "Effect of differential hardness on wheel/rail wear - literature survey, reviewed available sets of test data and published papers on wheel and rail wear. " One of the main conclusions was that "the belief that an increase in the hardness of the rail, while giving a decrease in the rail wear rate, will give an increase in wheel wear is not generally felt to be justified. " This conclusion was based on a Clause 5. 1. 1 is considered to be the primary means of reducing the likelihood of a person or their equipment coming into contact with live equipment. It is therefore proposed to position the OLE warning line at 2900 mm above rail level (the maximum that can be achieved when complying with the 600 mm electrical clearance). Note that Clause 5. 1. 4 already permits the OLE warning line to be lower than 3100 mm where there are parts of the vehicle that cannot be liveried. However, there is no physical reason why the OLE warning line cannot be applied to the roof panels at 3100 mm; the reason for the deviation is solely because it is not possible to meet the required 600mm electrical clearance at this height. Clause 5. 1. 4 permits the lower height only when the warning line is sufficiently high for it still to be recognised as a warning line. At 2900 mm, the risk of a warning line not being recognised on the tram-train vehicles is very low, because the relative position of the proposed line in relation to the top of the unit's doors and windows, and the roof-line, is very similar to a typical mainline rail vehicle. Apart from in exceptional circumstances, the tram train will stop at low-level platforms that are The alternative provisions will provide for a robust procedure of bringing class 700 units to a stand at the correct position at the platform for their formation. The design and orientation of the platform stop markers are such that the chance of confusion and misreading are reduced to as low as reasonably practicable. Applicant Organisation Interfleet Technology Ltd Certificate Issue Date 08/05/2015 Certificate End Date N/A Lead SC RST Lead SC Approval Date 17/04/2015 Deviation Status Current Stagecoach Supertram 31/03/2015 N/A RST 12/03/2015 Current Govia Thameslink Railway 29/04/2015 07/10/2016 CCS 19/03/2015 Current No safety or performance risks identified. No safety risks identified as Rule Book module already allows for a possession to be given up when a train is in a track circuited area. Network Rail 24/04/2015 N/A TOM 03/03/2015 Current Signal sighting has been carried out for the Network Rail various sketches. During the excavation works and construction of pile caps, platform widths will be maintained. Works will be carried out during night shifts and possessions so as not to disrupt the train services or impact upon passenger safety. At the end of each shift, a polystyrene block, with recessed, anti-slip road plate, will be inserted into the excavation. Alternatively, a scaffold deck will be fixed into the excavation with anti-slip surfacing. This will allow the full platform to be in use during the day and platform widths can be maintained. The temporary deviation is only required when the superstructure is being constructed. The hoardings for Stage 1 and for Stage 2 will not be in place at the same time. 10/04/2015 30/06/2016 INS 04/03/2015 Current Page 23 Deviations Register RGS Number GCRT5212 RGS Issue Number One RGS Title Requirements for Defining and Maintaining Clearances Certificate Number 15-014-DEV Title Reduced clearances at signal EK4042 at Rochester Bridge Junction RGS Clause G1.2 Scope This non-compliance application relates to signal EK4042 only located alongside the Up Chatham line on ELR VIR at approximately 33m 02ch in Network Rail's Southeast Route. Nature and Degree The non-compliant arrangement proposed is the only reasonably practicable way to achieve the specified performance requirements of the network. The safety implications of the proposed deviation are examined in detail in the accompanying risk assessment which concludes that the risks can be managed to an acceptable level using the mitigation measures discussed later. In summary, the primary risk is of persons becoming injured as a result of coming into contact with the signal whilst leaning from a moving train. It is not possible for passengers to do this from the trains which operate scheduled services over this route, limiting the risk to staff on any train or passengers on infrequent charter operations. It is assumed that drivers, with a clear view of the signal they are approaching, will recognise the existence of the limited clearance and not lean from their cabs (in the case of the Southeastern passenger fleet it is difficult to do this whilst driving the train in any case) and thus the staff risk is primarily to the guards who are present on just less than half of the total train services passing the signal. GKRT0075 Three Lineside Signal Spacing and Speed Signage 15-005-DEV Non-provision of Permissible Speed Warning Indicators at Old Oak Common 3.3.1.4 b) The deviation applies to the successive speed reductions for passenger trains at Ladbroke Grove from 60 mph on Lines 1 and 2 to 50 mph over diverging junctions (MLN1: 1¬ MP to 2¬ MP) with further reductions ahead on: Engine and Carriage LineNorth Pole Line B Crossrail Depot Line 1 Compliance would entail the placement of a PSWI for the associated 15 mph PSI on the E & C Line (at Appendix B braking distance from 60 mph of 562 m) at a position on the approach to signal SN125, which has been deemed by the SSC as potentially confusing - as to whether the warning is for the divergence or the speed restriction beyond. Compliance would entail the placement of a PSWI for the associated 15/35 mph PSI on the North Pole Line B (at Appendix B braking distance from 60 mph of 614 m) at a position 117 m on the approach to the 25/50 divergence, which has been deemed by the SSC as potentially confusing - as to whether the warning is for the divergence or the speed restriction beyond. Compliance would entail additional AWS equipment being required (positioned on Line 4) due to the placement of a PSWI for the associated 25 mph PSI on the Crossrail Depot Line 1, which has been deemed by the SCC as a potential distraction for the vast majority of trains using Crossrail Depot Line 1, which will be approaching from 50 mph Lines 3 to 6. Complex AWS suppression controls would also be required. GKRT0075 Three Lineside Signal Spacing and Speed Signage 15-004-DEV Plassers Crossing, St. George's Cross Sign Appendix X Deceleration Distances: Table X- Plassers AOCL+B Level Crossing, Western Position. 1 - Deceleration distance to speed restriction Route, ELR WEL1 6 _ miles. of 10 mph Table X-2 - Deceleration distance to speed restriction of 20 mph Standard deceleration for both 15 to 10 mph and 25 to 20 mph is 402 metres (tables X. 1 and X. 2 respectively). This large distance would severely impact on train speed for movements onto the Greenford branch, more confusing signage and less advantageous train positioning. The braking shown in the standards is extremely pessimistic, as has been proved having calculated the braking required, in consultation with the TOCs/ FOCs on their current worse case stock. This is inappropriate for the braking of the train, to the X10/20 sign from the Level Crossing Warning Sign on the line to Greenford. GMRT2400 Five Engineering Design of On-track Machines in 15-002-DEV Running Mode Automatic reinstatement of the spring actuated parking brakes that have been manually released BS EN 14033-1: 2011 clause 9. 2. 5. 2 states "Any spring apply air release parking brake actuator shall be provided with a mechanical release, accessible from the outside. It shall be possible to operate such a release from a convenient position with consideration of the risk of contact with an electrified rail of the infrastructure. The parking brake actuators shall reset automatically by filling with compressed air. The parking brake actuators shall still be capable of manual release even when the full service brake is applied. " The MMS machines use a standard Plasser bogie in service throughout the UK, which incorporates a spring applied, air release parking brake. This bogie and brake has always been in compliance with GM/RT2400 under Issue 4 and previous. Issue 5 (which came into effect after contract signing) has changed to refer to the EN which introduced this new requirement. It is not physically possible to modify this bogie to incorporate automatic reset of the handbrake when it has been manually released. `Complete redesign to incorporate a feature not previously mandated is totally unrealistic. Current Deviations Register as at 09 May 2016 2.3.2.3 This deviation applies to eight sets of three permanently coupled vehicles known as MMS (mobile maintenance systems) TOPS Vehicle numbers (for the traction vehicles) DR97501 to DR97508. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Risk Assessment/Safety Justification The East Kent Resignalling Phase 2 (EKR2) Project has been tasked with meeting the following requirements to accommodate growth in passenger numbers in Kent: A reduction in signalling headway through the Medway Towns to allow an increase in train frequency (with a two minute interval between trains specified) The relocation of Rochester station nearer to London whilst maintaining the flexibility of operation of the current layout. Performance modelling has identified that to achieve both of these requirements it is necessary to locate the signal controlling the divergence of the Chatham main line (ELR VIR) to London via Sole Street and the North Kent lines to London via Gravesend (ELR HDR) as close as possible to Rochester Bridge Junction where these lines diverge. This signal is a 4aspect searchlight type LED colour light signal with a 'position 4' (upper right hand) junction indicator. The point of divergence at the junction is immediately beyond the end of the Medway Viaduct (bridge 1046) which is approximately 180m long, has full height lattice girder sides with brick piers and overhead girders linking the two sides of the bridge. It is proposed to locate the signal alongside the brick pier at the London The initial divergences are only 1. 8-2. 4 km from the platform starting signals at Paddington. This proximity negates the "within a distance of 3. 2 km" aspect of the requirement because all trains will start from rest within 3. 2 km of the first reduction. This proximity also reduces the risks posed by driver fatigue and confusion over location. The majority of trains will be fitted with GWATP or ETCS. GW-ATP will govern speeds down to 50 mph before the train leaves the ATP area. Conversely; TPWS will be provided for the speed restrictions which will provide mitigation of risk of over-speeding for those remaining trains not so fitted with GW-ATP or ETCS. Reductions 1) and 2); proposes to augment the PLJIs for signals SN125 and SN105 (due to limited sighting) with Preliminary Route Indicators (PRIs). The junction signalling approaching the 50 mph divergences has been carefully designed to ensure that the drivers can sufficiently control the train speed to 50 mph, to traverse through the points towards the depot lines. Once train speed is at 50 mph, no warning signs are required - drivers upon seeing the PRI's and PLJI's for those diverging routes will decelerate sufficiently, therefore it is suggested that this is an On the 1: 400R gradient GK/RT0075 Appendix A shows the distance to stop from 15mph as 136m and Appendix B shows 109m to stop from 25 mph. Proposal allows the driver to get an AWS indication for the Level Crossing Warning Sign to warn that there is a level crossing as required by the standard GK/RT0192 (Level Crossing Interface Requirements- 2. 11. 1. 1), for freight and passenger trains after completing Station Duties at West Ealing and passing the starting signal. TOCs and FOCs have confirmed that the proposed distances match what they experience operating trains on the Greenford Line. The braking is adequate to reduce to the required speed at the Automatic Level Crossing Speed Restriction Sign (X10/20) and come to a complete stop at the crossing when required. See supporting calculations. Applicant Organisation Network Rail Certificate Issue Date 01/04/2015 Certificate End Date N/A Lead SC INS Lead SC Approval Date 04/03/2015 Deviation Status Current Network Rail 10/03/2015 N/A CCS 19/02/2015 Current Network Rail 10/03/2015 N/A CCS 19/02/2015 Current 20/04/2015 N/A RST 13/02/2015 Current The impact of the alternative provision is a Plasser UK Ltd negligible risk. The parking brake will only be manually wound off in an emergency recovery situation by specialised staff. In these specialised and very rare occasions, it will be necessary for the recovery staff to manually remove the mechanical device used to wind-off the parking brake when parking the vehicles after they have been recovered. This is documented in the recovery procedures they will be following and poses no greater risk in that situation than a vehicle with a manual handbrake that needs to wound on. Page 24 Deviations Register RGS Number GMRT2400 RGS Issue Number Five RGS Title Certificate Number Engineering Design of On-track Machines in 14-175-DEV Running Mode GCRT5212 One Requirements for Defining and Maintaining Clearances 14-174-DEV GIRT7016 Five Interface between Station Platforms, Track and Trains 14-170-DEV GMRT2130 Four Vehicle Fire, Safety and Evacuation GKRT0045 Three Lineside Signals, Indicators and Layout of Signals Current Deviations Register as at 09 May 2016 Title Provision of emergency brake override. RGS Clause 2.3.1.1 Scope This deviation applies to eight sets of three permanently coupled vehicles known as MMS (mobile maintenance systems) TOPS Vehicle numbers (for the traction vehicles) DR97501 to DR97508. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Nature and Degree The brakes on on-track machines, in running mode and when working outside of a possession if designed for working at speeds greater than 30 km/h, shall comply with BS EN 14033-1: 2011 Clause 9. The performance parameters shall be as set out in GM/RT2042 or GM/RT2043 as applicable. Clause 9 of BS EN14033-1 states among many requirements that "An override device for the emergency brake for use by the driver shall be provided where there is the possibility of the emergency brake being applied remotely from the driving cab. " It is not reasonable to comply with this requirement because it would involve reengineering of an existing proven system of control used in other machines of this type. Moreover, it will not provide any safety risk and is not a feature that will be required in the future. Heathrow CTA, platforms 1 and 2 C2.1, Table 2 - Categorisation of clearances This deviation against GC/RT5212 Issue 1 Clause C2 Table 2 provides definition of reduction in clearance during trial of platform for absolute gauging. G4.1 - Alterations is for the installation of rubber platform gap normal/reduced/special reduced clearances gap fillers other than to permit the passage of larger fillers along the full length of the Heathrow in the lower sector. Clause G4. 1 states that rail vehicles. Express CTA station Platforms 1 and 2 for a alterations to infrastructure should not cause second phase of trialling. The impact of the reduction of clearances from one category to installation is to reduce nominal clearance a more severe (smaller clearance) category. between vehicles and the infrastructure from The current platform clearances comply with 80 mm-105 mm (I. e. normal clearance) to the RGS requirements. In this scenario 25 mm-50 mm (I. e. reduced clearance). there have been instances of passengers, The gap filler is, however, flexible and especially those with a small foot size, effective clearance remains greater than this stepping between the platform and the nominal value. The clearance rules of Class 332 and Class 360/2 stepping plate GC/RT5212 Issue 1, however, do not and getting their foot/leg trapped. HEx recognise the possibility of such flexible propose to trial the gap fillers to assess their components and deviation is therefore benefits in reducing the number of such necessary. The trial will be conducted for a accidents on Heathrow CTA Platforms 1 and period of up to 24 months to allow for 2. sufficient trial time and data gathering to demonstrate that the gap filler achieves a safety benefit and the installation is robust under the operating conditions and application of the gap fillers on CTA. Conclusions of the trial and evidence of the benefits will be presented to RSSB once they are available within the 24 month period. If, at any time during the trial period, the findings of the trial indicate that the fillers have an overall negative impact, they will be removed. Please find the details of the Chippenham Station, Platforms 1 &amp; 2 - 6.2 Chippenham Station - Final installation of As an Outside Party funded structure, it reduced platform width at lift shaft and new lift, shaft and stairs. would not be possible to fund the provision stairs. of a compliant solution. The advantages for both the passenger public and the station itself by making Chippenham an Access for All station mean that a viable solution must be found. The extent of the non-compliant section of platform has been kept to its absolute minimum to mitigate as much risk to the public as possible. To minimise the disruption to the public by decreasing the clearance, the lift shaft has been designed to be narrower than a standard lift shaft. Whilst still maintaining the sixteen person capacity, the narrower shaft allows for an increased clearance to the platform edge. Despite the narrow clearances, which cannot be avoided, the risk to passengers is deemed to be acceptable. It is believed that any potential safety risk associated with the reduced clearances will be reduced to an acceptable level. Risk Assessment/Safety Justification Applicant Organisation It is not thought that this non-provision of a Plasser UK Ltd driver override device will have any safety effect at all. In the event of an emergency, the machine consist could be brought to a halt by the actions of the crew in the mess room without any action on the part of the driver. The vehicle could not be set in motion without resetting of that emergency control. The driver would at all times be aware of what had happened and would be in radio contact with the mess room. This is not thought to be an unsafe situation and differs greatly from a situation where passengers are involved and who might start to exit a train in an inappropriate place. Certificate Issue Date 02/02/2015 Certificate End Date N/A Lead SC RST Lead SC Approval Date 16/01/2015 Deviation Status Current The impacts of the proposed gap filler have Heathrow Express Operating been more fully detailed in the supporting Company Ltd documents attached. In summary, the gap filler trial is expected to: Improve passenger safety on CTA Platforms 1 and 2. Maintain acceptable train / platform clearances, as demonstrated in the trials ongoing on Heathrow Terminal 5, whilst not affecting technical compatibility of the railway system through the reduction in normal clearance arrangements. The gap fillers can be removed if railway requirements change in the future, or if the trial proves to be unsuccessful. Have no effect on service performance. Have no direct impact on environment. Supporting documentation attached to this report discusses the details, including the risk assessment. 27/01/2015 15/01/2017 INS 06/01/2015 Current This non-compliance relates to horizontal clearance between the platform edge and the edge of the new lift shaft on Platforms 1 and 2 at Chippenham Station. The permanent deviation has been amended to reflect the dimensions in the attached "proposed general arrangement plan". The lift shaft on the central platform provides clearance of 2531 mm on the Up Main and 2548 mm on the Down Main. The stairs on the central platform also require a deviation from the original standard. The stairs provide clearance of 2780 mm on the Up Main and 2835 mm on the Down Main. Network Rail 19/03/2015 N/A INS 06/01/2015 Current 14-166-DEV Advance stage deviation for installation of Global System for Mobile communications for Railways (GSM-R) to a Class 47 Locomotive. All clauses. Applies to the installation of GSM-R system to 1 x Class 47 locomotive 47830. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. The locomotive will operate with the same level of compliance as all other Class 47 locomotives in the UK that have already been fitted with GSM-R. Freightliner Ltd 05/12/2014 N/A RST 16/01/2015 Current 14-160-DEV SN105 and SN125 non-provision of approach release from red for reduced junction indication visibility. 5.1.3.4 Signals SN105 and SN125 are on Line 1 (Down Direction) leaving Paddington Station, MLN 1¬MP to 2MP. 12/01/2015 N/A CCS 11/12/2014 Current Due to GM/RT2130 Issue 4 being notified as a National Technical Rule (NTR) by the competent authority in the UK, this standard has become applicable to the project following the completion of GSM-R system development, but prior to it being fitted to Class 47 locomotive 47830 (expected to be fitted in early 2015). The design of the GSMR system is compliant with Issue 3 of GM/RT2130. Issue 4 of GM/RT2130 is a fundamental revision of the standard to align it with EN 45545, and demonstrating compliance with Issue 4 would require a complete new assessment. Therefore, complying with the new standard at this advanced stage of the GSM-R project would require significant re-work that would incur additional cost and delays to the project. In addition, fixed system parameters cannot be modified, resulting in the risk that the GSMR system may not comply with the new Euronorm. Complying with the standard would require the signals to have either some form of approach control for the diverging routes, or significant infrastructure alterations to achieve sighting of the junction indicator. Each approach control method would increase the level of complexity of the signalling controls, have negative impact on capacity, increase Signal Passed at Danger (SPAD) risk for the area or increase potential for confusion with other signals in the area. Achieving sighting of the junction indicators is not practical to achieve due to curved approach, amount of OverHead Line Equipment (OHLE) masts on approach and boundary constraints. Further detailed consideration on each option considered is in Section 7 of supporting document NRSDG-NC-123242. 11-000002. No approach release controls are proposed Network Rail as approach speed to the signals will be 60 mph, with diverging routes 50 mph. As such, derailment presents a low safety risk should a train not read the route information. Diverging routes are to depot approach lines (goods lines) and as it is desirable for passenger train drivers to be able to avoid taking these routes should they be misrouted. PRI provision assists in reducing the likely hood of misrouted train entering the depot approach lines. PRIs will provide positive information to train drivers about all the routes from the signals' similar to flashing and splitting distant signals, that would permit non-provision of approach control. See GK/GN0645 GN 550 and GN551. PRIs provide more information than a splitting banner that traditionally would be used to provide increased reading distance of a junction signal. Although no aspect information is provided by the PRI, the junction signals aspects are readable for sufficient distance, and it was consider this information does not require repeating. Page 25 Deviations Register RGS Number GKRT0045 RGS Issue Number Three RGS Title Lineside Signals, Indicators and Layout of Signals Certificate Number 14-159-DEV Title Signals TL4000 and TL4118 alternative route indications. RGS Clause 5.1.2.7 a) Scope Signals TL4000 and TL4118 approaching London Bridge Low Level Station. Nature and Degree TL4000 and TL4118 signals are in a 50 mph permissible speed area with a permissible speed change to 20 mph is approximately 100 m beyond the signals. Alternative routes are available to the platforms 11, 12 and 13 via the 25 mph crossovers (7222 or 7224). Signals are fitted with Standard Alphanumeric Route Indicators displaying only the platform numbers. Compliance would require an additional indication for each alternative route. This would potentially be difficult to provide, and increase the complexity and number of elements on signals that are already complex, I. e. additional Standard Alphanumeric Route Indicator on each signal. GERT8075 One AWS and TPWS Interface Requirements 14-158-DEV Far North Radio Electronic Token Block (RETB) Automatic Warning System (AWS) cancelling indicators at Halkirk Level Crossing (LC). 2.1.12.1 Halkirk LC is located on the WCK line at 145M 59ch. It is not appropriate to attempt to achieve compliance due to the high number of level crossings involved that currently do not have AWS cancelling boards, and the substantial costs associated with installation and future maintenance of AWS cancelling indicators throughout the Far North RETB line. Installation of AWS cancelling boards just at this crossing would create an inconsistency, and therefore the only two options are to maintain the current status quo, with no fitments, or to embark on complete line of route fitment. To achieve full compliance, AWS cancelling indicators would need to be retrospectively installed at all distant boards and level crossing Advance Warning Boards (AWBs) at a substantial cost, both in terms of installation and subsequent ongoing inspection / maintenance. It is therefore not considered reasonably practicable to bring the entire Far North RETB line into compliance with this requirement as the costs far outweigh any safety benefit. GERT8075 One AWS and TPWS Interface Requirements 14-157-DEV Non-provision of commencement and termination of Automatic Warning System (AWS) gap signage at Cannon Street Station. 2.1.9.3 The extent of deviation apples to all lines out of Cannon Street Station terminating platforms to those down direction signals on the first gantry (CBM 0 miles 20 chains) viz TL2519, TL2707, TL2411, TL2717 &amp; TL2715. GERT8075 One AWS and TPWS Interface Requirements 14-156-DEV Non-provision of commencement and termination of Automatic Warning System (AWS) gap signage at London Bridge Low Level Station. 2.1.9.3 Current Deviations Register as at 09 May 2016 Proposal was initially raised in March 2013 against the GE/RT8035, which has since been superseded by GE/RT8075, where the requirement is still pertinent. Compliance with RGS would therefore require either: Fitting of AWS to signals TL2519, TL2707, TL2411, TL2717 and TL2715 Because it is difficult to achieve, it is proposed not to provide AWS at these signals, and a risk assessment has shown that this is acceptable. or Provision of AWS gap signage. This is considered an unnecessary visual distraction for drivers departing (down direction) Cannon Street Station. For trains approaching Cannon Street Station on lines A to E in the up direction, no signage is proposed to be provided to indicate the commencement of an AWS gap at structure 423 (TL2296, TL2412, TL2510, TL2718 &amp; TL2816), as the next stop indication the driver will observe is the relevant buffer stop or the tail lights of a train already in the platform and was considered during the risk assessment that `commencement of AWS gap' signs on the approach into the station will not serve any useful purpose. These conclusions are supported by the risk assessment (N421-JAC-RET-SG-010072, version 3. 0). The extent of deviation apples to all lines out Proposal was initially raised in March 2013 of London Bridge Low Level Station against the GE/RT8035, which has since terminating platforms to those down been superseded by GE/RT8075, where the direction signals on the first gantry (XTD 2 requirement is still pertinent. Compliance miles 9 chains) viz TL4005, TL4119 and with RGS would therefore require either: TL4207. Fitting of AWS to signals TL4005, TL4119 and TL4207. Because it is difficult to achieve, it is proposed not to provide AWS at these signals, and a risk assessment has shown that this is acceptable. or Provision of AWS gap signage . This is considered an unnecessary visual distraction for drivers departing (down direction) London Bridge Low Level Station. For trains approaching London Bridge Low Level Station in the up direction, no signage is proposed to be provided to indicate the commencement of an AWS gap at structure 3501 (TL4118, TL4000 &amp; TL4204): the next stop indication the driver will observe is the relevant buffer stop or the tail lights of a train already in the platform and was considered during the risk assessment that `commencement of AWS gap' signs on the approach into the station will not serve any useful purpose. These conclusions are supported by the Risk Assessment (N421JAC-RET-SG-010071, version 1. 0). Risk Assessment/Safety Justification Using a generic deceleration figure of 0. 74m/s2, this gives a calculated speed at the signals of 34 mph. However, the signal sighting committee have assessed the speed on the approach and believe the likely maximum approach speed to be circa 30 mph. The Signal Sighting Committee (SSC) has endorsed the signal sighting form as such. At either of these approach speeds, the derailment risk is very low but drivers would not be aware which route is set. As such, drivers would need to assume the more restrictive alternative route is set and drive to the 25 mph limit. Approach release controls are proposed as will these provides significant difference in approach to the signals for the alternative routes, allowing drivers to control speed over the crossovers, but also drive to the 20 mph limit for the preferred route. Using NR/L2/SIG/11201Mod B7 approach release will be based on release speed of 25 mph; this equates to a release point of 75 m on approach to the signals. On the RETB line North of Inverness, Network Rail has developed an upgrade of Halkirk LC to ABCL. When passing over a permanent magnet, the driver of the train has to cancel the warning. Where the magnet does not apply to the direction the train travels in, the driver will use route knowledge to establish that it does not apply. This project is similar to previous upgrades at Marrel, Blackwood and Acheilidh LCs carried out by Railtrack in 2002. These previous schemes were approved by Her Majesty's Railway Inspectorate (HMRI) and that approval was given on the basis of the principle established during the formal Department of Transport (DoT) inspection of the original RETB installation between Dingwall and Kyle in November 1984. During that inspection, and duly recorded in the minutes, it was directed that AWS cancelling indicators were of no value and were not required on RETB infrastructure. This principle, having been established as part of the very first RETB DoT inspection was then applied by British Rail to all the subsequent RETB deployments in Scotland. This submission, therefore, seeks a deviation against the current RGS requirement to Trains departing the terminal platforms of Cannon Street Station will be travelling at low speed (15 mph). The relevant signals are all fitted with Train Protection and Warning System (TPWS) Train Stop System (TSS) loops which have been shown to be effective for all trains (passenger at 12%g and 9%g braking, freight at 7. 5%g and 6%g braking) passing the signal at red by stopping them short of the safe overrun distance. This is a perpetuation of what is already an existing arrangement and is envisaged will be for the lifetime of this installation, I. e. circa 30 years +. Risk assessment (N421-JAC-RET-SG-010072, version 3. 0) was conducted and accepted that there is no impact by the non-provision of AWS or AWS gap signage. Applicant Organisation Network Rail Certificate Issue Date 12/01/2015 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 11/12/2014 Deviation Status Current Network Rail 12/01/2015 N/A CCS 11/12/2014 Current Network Rail 12/01/2015 N/A CCS 11/12/2014 Current Trains departing the terminal platforms of Network Rail London Bridge Low Level station will be travelling at low speed (20 mph). The relevant signals are all fitted with Train Protection and Warning System (TPWS) Train Stop System (TSS) loops which have been shown to be effective for all trains (passenger at 12%g and 9%g braking, freight at 7. 5%g and 6%g braking) passing the signal at red by stopping them short of the safe overrun distance. This is a perpetuation of what is already an existing arrangement and is envisaged will be for the lifetime of this installation, I. e. circa 30 years +. Risk Assessment (N421-JAC-RETSG-010071, version 1. 0) was conducted and accepted that there is no impact by the non-provision of AWS or AWS gap signage. 12/01/2015 N/A CCS 11/12/2014 Current Page 26 Deviations Register RGS Number GMRT2461 RGS Issue Number One RGS Title Sanding Equipment Fitted to Multiple Units and on- track Machines Certificate Number 14-155-DEV Title Class 377 Sanding on Trailing Units. GCRT5112 Two Rail Traffic Loading Requirements for the Design of Railway Structures 14-153-DEV Bottesford Station - Installation of footbridge 7.1.3 to enable removal of a foot crossing, bridge support on Platform 1. Bottesford Station, Station Road, Bottesford, Leicestershire, NG13 0GT. Installation of footbridge to enable removal of a foot crossing between Platforms 1 and 2. The severity/impact at Bottesford Station in connection with the proposed footbridge install works is considered generally very low for the use/operational aspect of the finished project; furthermore, an inherent risk identified by the Office of Rail Regulation (ORR) will have been removed, with extensive platform and lighting upgrades already being carried out as part of the overall scheme to generally improve functionality of the station also. A recent footfall survey carried out as part of the Scheme Feasibility clearly suggests a negligible effect to the general and more so "less able" user; this has been demonstrated to and accepted by the Department for Transport (DfT). The safety justification is primarily the removal of an inherent risk identified by the ORR in connection with the foot crossing that the proposed footbridge will permanently replace. GIRT7016 Five Interface between Station Platforms, Track and Trains 14-149-DEV London Bridge station, low level terminating platforms 10-15 - position of canopy columns in overrun risk zone. 6.3.1 London Bridge station, low level terminating platforms 10-15, London end, are included in this application. A fully compliant design is not considered appropriate for the envisaged scenario at the London end of these platforms. One column on each of Platforms 10-15 is within the overrun risk zone. The canopies are designed to remain standing due to the redundancy of design to prevent disproportionate collapse in the event of a train overrun which removes the column in the risk zone associated with any one platform. The canopy column alignment has been set back as far as possible from the platform edge consistent with providing a compliant edge distance and maintaining a straight alignment with those columns across the bridge decks. A straight alignment of canopy columns eases pedestrian flows along the platforms and simplifies structural framing of the canopies. The width between pairs of columns on each island platform is governed by the width of escalator and stair access to platforms. Train Protection and Warning System (TPWS) and a compliant buffer design mitigates any significant risk. GERT8075 One AWS and TPWS Interface Requirements 14-148-DEV Far North Radio Electronic Token Block (RETB) Automatic Warning System (AWS) Cancelling Indicators at Duirinish Level Crossing (LC). 2.1.12.1 Duirinish LC is located on the KYL Line at 56M 58ch. It is not appropriate to attempt to achieve compliance due to the high number of level crossings involved that currently do not have AWS cancelling boards, and the substantial costs associated with installation and future maintenance of AWS cancelling indicators throughout the Far North RETB Line. Installation of AWS Cancelling Boards just at this crossing would create an inconsistency and, therefore, the only two options are to maintain the current status quo with no fitments, or to embark on complete Line of Route fitment. To achieve full compliance, AWS cancelling indicators would need to be retrospectively installed at all Distant Boards and Level Crossing Advance Warning Boards (AWBs) at a substantial cost, both in terms of installation and subsequent ongoing inspection / maintenance. It is therefore not considered reasonably practicable to bring the entire Far North RETB Line into compliance with this requirement as the costs far outweigh any safety benefit. Current Deviations Register as at 09 May 2016 RGS Clause 6.2, 9.1, 9.3.1 Scope Nature and Degree All Class 377 Electric Multiple Units (EMUs). The deviation requests enhanced performance, which is non-compliant with the standard as written, but consistent with the objectives of the standard. Risk Assessment/Safety Justification Sand will only be dispensed during a brake application (step 2, full service or emergency) by units on which the leading vehicle detects wheel slide. As such, trailing units will only dispense sand if they detect wheel slide and have sufficient sand available. The likelihood of sanding on trailing units occurring is lower, as the leading unit will condition the railhead and so the trailing units are likely to experience wheel slide or slip to a lesser extent. This functionality has been developed to increase the safety of the railway in conditions of extremely poor rail head adhesion or where the sanding system on the leading unit does not function correctly (due to a fault or having run out of sand), having a positive impact on overall system performance. Whenever sand is applied on a trailing unit, there will always be at least twelve axles after the initial sand deposition point. The amount of sand deposited and the number axles following the deposition point will be the same as if the units were separate trains following each other. Therefore, it is considered that there is no negative impact in terms of contamination of the railhead, noting that sand will only be deployed on the trailing unit if the railhead has not been Following a territory wide review of all level crossings undertaken by the ORR, Bottesford Station, which has operational vehicular, bridleway and foot crossing points, was identified as a site requiring swift improvements to minimise/eliminate risk at the site by carrying out a scheme of enhancements at the station generally and to all of the crossings on site in particular also. The vehicular and bridleway crossing enhancement works have already been carried out with great success, with only the footbridge install works, which removes use of the foot crossing point, now remaining. Note: the drawings and details provided forming part of this Submission, are as follows: 3D Model Photos; Drawing Nos NG8143-101 &amp; 102; C114050-TG-00XX-DR-C-1001, 1002 &amp; 1003. Details to satisfy the apt standards for the deviation being sought are captured on Drawing Nos NG8143-101 and 102, with 3D Model Photos supplied to add perspective at the location in question also. One column on each of Platforms 10-15 is within the over-run risk zone. The noncompliance was identified in the form 001 (N420-COT-FO1-CV-000004 Section A1. 3) which was signed by Network Rail on 26/02/2013. Some of the columns supporting the shard interface canopy are within the overrun risk zone at the end of the terminating tracks. The canopy is designed to remain standing in the event of a train overrunning; the column in a single overrun zone can be considered as removed and the canopy will remain standing, but simultaneous overrun events are not contemplated as it is very unlikely that two events will occur at the same time. Note that the buffer stop locations have been amended since the Form 001 was written and the attached sketch has been amended to show the revised arrangement. The face of the column on Platforms 10 and 11 is more than 2500 mm from the platform edge, and therefore it complies with Section 6. 2. 2 of GI/RT7016. The other columns are not adjacent to platform faces. The canopy columns have been set as far back as possible from the platform edge consistent with maintaining a straight alignment across the bridge decks. A straight alignment On the RETB Line North of Inverness, Network Rail has developed an upgrade of Duirinish LC to ABCL. When passing over a permanent magnet, the driver of the train has to cancel the warning. Where the magnet does not apply to the direction the train travels in, the driver will use route knowledge to establish that it does not apply. This project is similar to previous upgrades at Marrel, Blackwood and Acheilidh LCs carried out by Railtrack in 2002. These previous schemes were approved by Her Majesty's Railway Inspectorate (HMRI) and that approval was given on the basis of the principle established during the formal Department of Transport (DoT) Inspection of the original RETB installation between Dingwall and Kyle in November 1984. During that Inspection, and duly recorded in the minutes, the DoT directed that AWS Cancelling Indicators were of no value and were not required on RETB Infrastructure. This principle, having been established as part of the very first RETB DoT Inspection, was then applied by British Rail to all the subsequent RETB deployments in Scotland. This submission therefore seeks a deviation against the current RGS requirement to Applicant Organisation Southern Railway Limited Certificate Issue Date 02/01/2015 Certificate End Date N/A Lead SC RST Lead SC Approval Date 05/12/2014 Deviation Status Current Network Rail 07/10/2015 N/A INS 06/01/2015 Current Network Rail 11/12/2014 N/A INS 12/11/2014 Current Network Rail 05/12/2014 N/A CCS 13/11/2014 Current Page 27 Deviations Register RGS Number GKRT0192 RGS Issue Number Two RGS Title Level Crossing Interface Requirements Certificate Number 14-147-DEV Title RGS Clause Woodbridge area - non-provision of 2.11.1.1 Automatic Level Crossing Advance Warning Signs (LCAWIs) Automatic Warning System (AWS). Scope Route: Anglia. Equipment: Ferry Lane, ESK, 79m04ch; Haywards, ESK, 79m07ch. Lime Kiln, ESK, 79m29ch. Sun Wharf, ESK, 79m31ch. Nature and Degree Complying with the requirements will require four additional AWS. If Solid State Interlocking (SSI) data interlocking changes are needed for suppression of the magnets (as this is on a single line), this will increase both costs and timescales for delivering the Automatic Open Crossing, locally monitored, with barrier (AOCL+B) upgrade. The additional costs and programme impact would mean that the level crossing safety benefit of adding the barriers would not be realised as quickly as desired, the costs for meeting the requirement are estimated to be œ25 000. Provision of AWS could cause significant distraction to drivers when approaching level crossings and would increase driver's workload. Risk Assessment/Safety Justification Applicant Organisation The existing arrangement has no AWS Network Rail currently fitted to the LCAWIs between Haywards and Lime Kiln Crossings. The proposal perpetuates this arrangement as the risk reduction/safety benefit achieved at the level crossing itself is the priority. The non-provision of the AWS will mean that train drivers will not receive the warning of approach to the third or fourth level crossing, the warning is provided to draw the driver's attention to the LCAWI and subsequent Special Speed Restriction Board (SSRB) and Driver's Crossing Indicator (DCI). Upon approach to the first crossing, the driver would have received the required AWS warning and as these crossings are so close to one another; they will see the signage for the next crossing when clearing the previous one, therefore will not benefit from another warning. The residual risk will remain the same as it is now, and it is believed that providing additional AWS warnings inbetween the crossings will act as an additional distraction to the driver, who will be concentrating on each crossing in turn and therefore would not benefit from having to react to an additional AWS. Certificate Issue Date 05/12/2014 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 13/11/2014 Deviation Status Current GERT8075 One AWS and TPWS Interface Requirements 14-146-DEV Woodbridge area - non-provision of 2.1.7.4 Table 7, Section H. Automatic Level Crossing Advance Warning Signs (LCAWIs) Automatic Warning System (AWS). Route: Anglia. Equipment: · Ferry Lane; ESK: 79m04ch; · Haywards, ESK: 79m07ch; · Lime Kiln, ESK: 79m29ch; · Sun Wharf, ESK: 79m31ch. Complying with the requirements will require four additional AWS. If Solid State Interlocking (SSI) data interlocking changes are needed for suppression of the magnets (as this is on a single line), this will increase both costs and timescales for delivering the Automatic Open Crossing, locally monitored, with barrier (AOCL+B) upgrade. The additional costs and programme impact would mean that the level crossing safety benefit of adding the barriers would not be realised as quickly as desired, the costs for meeting the requirement are estimated to be œ25 000. Provision of AWS could cause significant distraction to drivers when approaching level crossings and would increase driver's workload. The existing arrangement has no AWS Network Rail currently fitted to the LCAWIs between Haywards and Lime Kiln Crossings. The proposal perpetuates this arrangement as the risk reduction/safety benefit achieved at the level crossing itself is the priority. The non-provision of the AWS will mean that train drivers will not receive the warning of approach to the third or fourth level crossing, the warning is provided to draw the driver's attention to the LCAWI and subsequent Special Speed Restriction Board (SSRB) and Driver's Crossing Indicator (DCI). Upon approach to the first crossing, the driver would have received the required AWS warning and, as these crossings are so close to one another, they will see the signage for the next crossing when clearing the previous one, therefore will not benefit from another warning. The residual risk will remain the same as it is now, and it is believed that providing additional AWS warnings in-between the crossings will act as an additional distraction to the driver, who will be concentrating on each crossing in turn and therefore would not benefit from having to react to an additional AWS. 05/12/2014 N/A CCS 13/11/2014 Current GIRT7016 Five Interface between Station Platforms, Track and Trains 14-145-DEV London Bridge station, platforms 1, 2/3, 4/5, 6/7 &amp; 8/9 eastern (Country) end reduced platform widths a canopy columns. N/A INS 12/11/2014 Current Five Interface between Station Platforms, Track and Trains 14-144-DEV London Bridge Station, Platform 9, Platforms 2.1.1, 2.1.2, 2.1.4 (a) and; (b) 8 &amp; 7, Platforms 6 &amp; 5, Platforms 4 &amp; 3, and Platforms 2 &amp; 1 Horizontal track alignment through station platforms. Six columns at the country end of Platforms Network Rail 1, 2/3, 4/5, 6/7, 8/9 are less than 2500 mm from the platform edge. This is because the width of the land owned by Network Rail, the number of platforms required to run the train service specified and agreed with the Department for Transport (DfT), and the spacing of the rail tracks at this point drives the platform widths. Edge distances are as follows: Platform 1: 1980 mm; Platform 2/3: 2178 mm from Platform 2; 2283 mm from Platform 3;Platform 4/5: 2179/1957 mm from Platform 4; 2376/2139 mm from Platform 5; Platform 6/7: 2492 mm from Platform 6; Platform 8/9: 2493 mm from Platform 8; 2462 mm from Platform 9. Please see diagram attached. The width of the platforms is driven by the track alignments, and these are governed by the width of the viaduct. It is not possible, using the powers available to Network Rail, to widen the viaduct. The design chosen is a balance between widths of platforms across the whole station, and a degree of noncompliance is inevitable. The six terminating platforms (10-15) are slightly wider, as trains terminating discharge all their passengers at once. Not all passengers will alight from 'through' trains The physical constraints of the London Network Rail Bridge Station area and the requirement to install new High Level platforms, new Low Level platforms and a new station building to accommodate twelve-car length trains drives some platform lines to be designed on radii that are tighter than the standard requires. This is a historically constrained site where the existing layout radius is below the current standard requirement. There is no possibility of achieving the 1000 m radius specified due to existing railway curvature with viaduct and structure constraints; however, attempts have been made to maximise the radius as part of the Guide to Railway Investment Project (GRIP) 4 design, while incorporating the mandatory requirement for emergency evacuation of the platforms. Platform widths have been designed to maximise pedestrian access and egress for current and anticipated passenger forecasts. Clear route analysis has been carried out and platform stepping distances have been confirmed as within the Group Standard limits. A permanent deviation has been certificated for the Low level Platforms 10 and 15 (number 13/175/DEV - Tracker No. 15192). 11/12/2014 GIRT7016 London Bridge station, Platforms 1, 2/3, 4/5, One column on Platform 1 is slightly less 6/7 and 8/9 eastern (Country) end, canopy than 2000 mm from the platform edge. It is columns. very close to the end of the platform and east of the emergency escape stair, and so it is in an area of very low pedestrian flow. One other column is less than 2000 mm from the edge of platforms 4/5, but this is close to the end of the operational platform length. All columns that are less than 2500 mm from the platform edge are at the country ends of the platforms where, in normal operation of the station, passenger flows are low. No flow analysis is offered with this submission. If there is a need to evacuate Platforms 2/3, 4/5, 6/7 and 8/9 using the country end escape stairs, pedestrian flows past the non-compliant columns could be high, but the pinch point on the escape routes is always the stairs themselves, and past these columns the flow capability is more than twice the capacity of the escape stairs. Evacuation of Platform 1 would not result in a high pedestrian flow past the non-compliant column because the stair is on the London side of the column. The proposed new track and platform alignment is not significantly different from the layout that exists today, meaning that station personnel and This issue applies throughout London Within the High Level platforms, the Bridge Station (both High and Low Level). designed radii will be: Platform 9: between The lengths of sub-1,000 m radius platform 300 m and 320 m; Platform 8: between 487 faces are as follows by platform: Platform 9: m and 500 7: between 483 m and 497 6: 196 m; Platforms 8 and 7: 168 m; Platforms 338 m; Platform 5 335 m; Platform 4: 6 and 5: approximately 65 m and 85 m; between 268 m and 400 m; Platform 3: 265 Platforms 4 and 3: approximately 206 m m and 403 2: between 250 m and 253 m; and 181 m; Platforms 2 and 1: Platform 1: 247 m and 354 m. There is a approximately 209 m and 250 m. length of straight approximately central to each platform and a length of curve at London end and country end. The extent of straight for each platform is approximately: Platform 9: 51m;Platforms 8 and 7: 82 m; Platforms 6 and 5: 184 m and 178 m; Platforms 4 and 3: 70 m; Platforms 2 and 1: 31 m. The length of straight is longest for Platforms 5 and 6 and decreases toward the platforms at the extreme of the High level tracks (Platforms 1 and 9). The extent and degree of curvature is least for Platforms 5 and 6 and maximum for Platforms 1 and 2. "Clear route" analysis has been run on tracks 1-9 and platform stepping distances confirmed as within prescribed limits for the High level platforms. The new platforms at London Bridge feature an uncluttered design with good visibility end-to-end, except for the presence of the trains themselves. Train dispatch staff will be positioned alongside 11/12/2014 N/A INS 12/11/2014 Current Current Deviations Register as at 09 May 2016 6.2.1, 6.2.2 (a) and; (b) Page 28 Deviations Register RGS Number GCRT5212 RGS Issue Number One RGS Title Requirements for Defining and Maintaining Clearances Certificate Number 14-143-DEV Title RGS Clause Heathrow Airport Terminal 5, Platform 4 C2.1, Table 2 - Categorisation of clearances reduction of clearance at platform gap fillers. for absolute gauging. G4.1 - Alterations other than to permit the passage of larger rail vehicles. GIRT7016 Five Interface between Station Platforms, Track and Trains 14-142-DEV Lea Bridge Station - Platform offset. Appendix 1, Clause 1.2 GERT8075 One AWS and TPWS Interface Requirements 14-139-DEV TPWS application on steam locomotive 34016. GERT8075 One AWS and TPWS Interface Requirements 14-138-DEV GIRT7016 Five Interface between Station Platforms, Track and Trains 14-136-DEV Current Deviations Register as at 09 May 2016 Scope This deviation against GC/RT5212 Issue 1 is for the installation of rubber platform gap fillers at all door positions (for the Class 332 rolling stock that operates the services into the platform in question) along the length of Heathrow Terminal 5 (T5), Platform 4, for a second phase of trialling. Initial trials, installing the gap fillers at a limited number of doors positions, was undertaken following agreement of deviation 13/227/DEV in January 2014. The impact of the installation is to reduce nominal clearance between vehicles and the infrastructure from 70 mm (I. e. normal clearance) to 25 mm (I. e. reduced clearance). The gap filler is, however, flexible and effective clearance remains greater than this nominal value. The clearance rules of GC/RT5212 Issue 1, however, do not recognise the possibility of such flexible components and deviation is therefore necessary. The trial will be conducted for a period of up to 24 months to allow for sufficient trial time and data gathering to demonstrate that the gap filler achieves a safety benefit. Conclusions of the trial and evidence of the benefits will be presented to the RSSB once they are available within the 24 month period. If, at any time during the trial period, the findings Lea Bridge Station. Engineers' Line Reference (ELR): SDC. Mileage: 6m 25ch. Nature and Degree Clause C2 Table 2 provides definition of normal/reduced/special reduced clearances in the lower sector. Clause G4. 1 states that alterations to infrastructure should not cause reduction of clearances from one category to a more severe (smaller clearance) category. The current platform clearances comply with the RGS requirements. In this scenario, there have been incidents of passengers, especially those with a small foot size, stepping between the platform and the Class 332 stepping plate and getting their foot/leg trapped. HEx is trialling the gap fillers to assess their benefits in reducing the number of such accidents on Heathrow Terminal 5 Platform 4. Risk Assessment/Safety Justification Applicant Organisation The impacts of the proposed gap filler have Heathrow Express Operating been more fully detailed in the supporting Company Ltd. documents attached. In summary, the gap filler trial is expected to: Improve passenger safety on the Terminal 5 platform 4. Maintain acceptable train - platform clearances, as demonstrated through Phase 1 trials, whilst affecting technical compatibility of the railway system through the reduction in normal clearance arrangements. The gap fillers can be removed if railway requirements change in the future, or if the trial proves to be unsuccessful. Have no effect on service performance. Have no direct impact on environment. Please see the supporting documentation for details. Compliance with the standard would mean non-compliance with another. 4.1.3.3, 4.2.1.7 and 4.2.3. Operation of the following preserved Steam Locomotive on all lines as agreed by Network Rail Acceptance Panel (NRAP) and, subsequently, by the Transport Undertaking. S. R. West Country steam locomotive `Bodmin'. TOPS No. 98716 Painted No. 34016 Class / Power Classification 7P Wheel Arrangement 4-6-2 Maximum Speed 75 mph. Enhancements to the TPWS DMI and speech warning announcements. Noncompatibility for spares with other steam locomotives currently operating on Network Rail controlled infrastructure under deviations from RGS and non-comparative driver interface for steam locomotives. TPWS application on steam locomotive 76084. 4.1.3.3, 4.2.1.7 and 4.2.3. Operation of the following preserved Steam Locomotive on all lines as agreed by Network Rail Acceptance Panel (NRAP) and subsequently, by the Transport Undertaking. British Railways Standard Class 4 TOPS No. 98484 Painted No. 76084 Class / Power Classification 4MT Wheel Arrangement 2-6-0 Maximum Speed 60 mph. Enhancements to the TPWS DMI and speech warning announcements. Noncompatibility for spares with other steam locomotives currently operating on Network Rail controlled infrastructure under deviations from RGS and non-comparative driver interface for steam locomotives. Strood Station, Platforms 2 and 3 - reduced platform width. 7.3 This deviation relates to Platforms 2 and 3 at As part of the East Kent Resignalling Phase Strood station in Kent. 2 (EKR2) Project, the platforms at Strood station are to be lengthened at the London end to accommodate twelve-car trains in place of the current ten-car maximum. This is required to facilitate service lengthening of Southeastern metro services to twelve-car operation on this route as the networker train fleet used does not have selective door operation capability. The platforms can only be extended at the London end because of the existence of a major junction layout at the country end of the platforms, and hence the extensions are being undertaken at the London end which is on a curve constrained by the position of the entrance to Strood tunnel. This deviation relates only to the Up island platform (Platforms 2 and 3). As the permanent speed restriction applicable to all lines through Strood station is 15 mph, this should have a minimum width of 4000 m for compliance. However, in this instance, it is proposed that the island platform will taper to a minimum width of 2905 mm. The total length of platform less than 4000 mm wide will be 25 m (of a total platform length of circa 270 m). To maximise the space available for the platform extension, Network Rail has purchased adjacent land (the verge Certificate Issue Date 11/12/2014 Certificate End Date 12/11/2016 Lead SC INS Lead SC Approval Date 12/11/2014 Deviation Status Current Minor impact in regards to safety, no affect Network Rail 11/12/2014 to performance: · The increased offset reduced the platform overhang which is the subject of another deviation application Ref. 14/108/DEV (Tracker No. 17890). The preserved steam locomotive is of a West Coast Railway Company 04/12/2014 type that ran safely over the British railway Limited infrastructure since its introduction and continued until its withdrawal from revenue service. The locomotive had a history of reliable service. The locomotive is intended for Heritage Operation only. In order to achieve compliance with all RGSs, the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. · Footplate crew are subject to specific training in the handling of a steam locomotive. Steam locomotive operation requires at least two persons to present in the cab at all times and regularly includes a third person whose role is to independently monitor the performance. · Use of locomotive restricted to <15 k Miles p. a. as a `heritage' vehicle which limits exposure to risk. N/A INS 12/11/2014 Current N/A CCS 13/11/2014 Current The preserved steam locomotive is of a West Coast Railway Company 04/12/2014 type that ran safely over the British railway Limited infrastructure since its introduction and continued until its withdrawal from revenue service. The locomotive had a history of reliable service. The locomotive is intended for Heritage Operation only. In order to achieve compliance with all RGS, the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. Footplate crew are subject to specific training in the handling of a steam locomotive. Steam locomotive operation requires at least two persons to present in the cab at all times and regularly includes a third person whose role is to independently monitor the performance. Use of locomotive restricted to <15 k Miles p. a. as a `heritage' vehicle which limits exposure to risk. N/A CCS 13/11/2014 Current Network Rail have worked with the relevant Network Rail train operating company, Southeastern, to assess the risks arising from the final twelvecar platform arrangements. The resulting risk assessment document is attached and is supportive of this deviation. Control measures proposed over and above those needed to achieve compliance with Railway Group and Network Rail company standards have been identified as follows and will be implemented: Signage to encourage passengers to wait in the appropriate section of the platform; Signage to prohibit passengers from waiting in the narrowest area beyond the 8/10/12-car DOO monitor bank where trains will not routinely stop. It will be ensured that signage and platform finishes (lining and tactiles) remain present, legible and effective for the life of the asset through appropriate maintenance regimes. Note that (unlike the temporary arrangement covered under Tracker No. 18100 14/115/DEV), there is no requirement to restrict where passengers, who need to use the access ramp to board or alight the train, can be accommodated as the platform width - although reduced - is sufficient to allow the ramp to be used safely on the 16 m section that will be in daily use. In the event that N/A INS 12/11/2014 Current 11/12/2014 Page 29 Deviations Register RGS Number GIRT7016 RGS Issue Number Five RGS Title Interface between Station Platforms, Track and Trains Certificate Number 14-135-DEV Title Curvature of Platform Extensions at Strood Station. GMRT2000 Three Engineering Acceptance of Rail Vehicles 14-134-DEV Use of NYMR Teak Bodied Carriages on Network Rail Infrastructure GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 14-133-DEV Richmond Station Platforms 4, 5, 6 and 7. GMRT2000 Three Engineering Acceptance of Rail Vehicles 14-132-DEV Steam Locomotive Bodmin TOPS number 98716. GMRT2000 Three Engineering Acceptance of Rail Vehicles 14-131-DEV Steam Locomotive TOPS number 98484. Current Deviations Register as at 09 May 2016 RGS Clause 2.1.3 Scope This deviation relates to Strood station in Kent (all platforms). Nature and Degree The extension of Platform 1 will be used only by twelve-car trains as all trains stop at the same stopping position at the extreme country end of the platform. The extension of Platform 2 will be used by all trains of eight-cars or more (these currently form about 35% of the weekday train service). The extension of Platform 3 will be rarely used as this platform is predominantly used by short (3 or 4 car) trains for the Medway Valley line shuttle service which stop towards the country end of the platform, near the entrance, where the platform is essentially straight. Usage of the extensions will therefore be focussed primarily on peak times when the longer formations are used. Signal sighting constraints apply only to the extensions of Platforms 2 and 3 with new banner repeating signals being provided to achieve a satisfactory reading distance. The design of the platform extensions (and widening of Platform 3) achieves standard offsets in compliance with GC/RT5212. However, recognising that the platforms are on a tight curve, it has been agreed to provide "Mind the Gap" warning messages on the platform surfaces. With the exception of the short Medway Valley services (which use the straight section of the platform), all 6.6.3 and Appendix H.2 Deviation is requested for seven Ex LNE In the case of GM/RT2000, deviation is Railway teak bodied carriages currently sought from the policy statement laid out in used by the North Yorkshire Moors Railway clause H2 (a) which states: "No additional (NYMR) on its internal services viz: · Brake wooden bodied rail vehicles designed or Third Open: 43567; · Buffet Unclassified: modified to carry persons shall be 641; · Restaurant: 43654; · Tourist Third certificated for registration to operate on Open: 23956, 56856; · Saloon: 3087; · Railtrack Controlled Infrastructure. " The Brake Third Corridor: 3669. NYMR, in association with Network Rail, has been awarded funding from the Coastal Communities initiative for works at Whitby Station to enable the NYMR to improve train services from Whitby to Pickering. The improvement to services will be enhanced and sustained by the use of attractive historic vehicles as an alternative to the Mark 1 sets which would have to be used instead. Deviations from the other quoted RGS requirements are matters of technical content, for which deviations are sought on the basis that the vehicles generally complied with the standards extant at the time of their service use on the London and North Eastern Railway (LNER) and British Rail (BR), but which standards have now been revised in line with current available technology. Generally, compliance with this group of standards would be unreasonably expensive and would detract from the experience of offering a passenger service 2.5.3.4 b) and d) Richmond Station Buffer Stops - Platforms Railway Group Standard GK/RT0045 4, 5, 6 and 7. conflicts with London Underground (LU) Category 1 Standard S1195. RGS GK/RT0045 - Clause 2. 5. 3. 4 b) and d) requires stop lights to be vertically aligned above the centre line of the track and be positioned at the buffer stop, in the same vertical plan as the buffer stop. LU Category 1 Standard S1195, Clause 3. 4. 2. 7. 3 Fixed red lights shall be provided for each track, 2 side-by-side, approximately 3 metres beyond the normal stopping point and, if there is greater than 10 metres between the 2 fixed red lights and the end of the track, a third shall be placed at the extreme end of the track, at sidings and terminal platforms. If site geography does not allow 3 metres between the normal stopping mark and the two red lights, then that distance may be decreased, but it shall not be less than 1. 5 metres. Project felt that the current requirements in GK/RT0045 were overly prescriptive; it should be left with the Signal Sighting Committee to decide the position. The clauses against which non-compliances Operation of the following preserved Steam Steam Locomotive construction and are sought can be found in Appendix 2 page Locomotive on all lines as agreed by operating systems are incompatible with the 1 of the accompanying supporting Network Rail Acceptance Panel (NRAP) areas of RGS specified in the supporting document. and, subsequently, by the Transport document. Undertaking. S. R. West Country steam locomotive `Bodmin': TOPS No. . 98716 Painted No. 34016 Class / Power Classification 7P Wheel Arrangement 4-6-2 Maximum Speed 75 mph. The clauses against which non-compliances Operation of the following preserved Steam are sought can be found in Appendix 2 page Locomotive on all lines as agreed by 1 of the accompanying supporting Network Rail Acceptance Panel (NRAP) and document. subsequently, by the Transport Undertaking. British Railways Standard Class 4 TOPS No. 98484 Painted No. 76084 Class / Power Classification: 4MT Wheel Arrangement: 2-6-0 Maximum Speed: 50 mph. Risk Assessment/Safety Justification Applicant Organisation As part of the East Kent Resignalling Phase Network Rail 2 (EKR2) Project, the platforms at Strood station are to be lengthened at the London end to accommodate twelve-car trains in place of the current ten-car maximum. This is required to facilitate service lengthening of Southeastern metro services to twelve-car operation on this route as the networker train fleet used does not have selective door operation capability. The platforms can only be extended at the London end because of the existence of a major junction layout at the country end of the platforms. At the London end of Strood station, the line curves sharply through approximately 90 degrees in order to enter Strood Tunnel (2127 m long). This curve starts within the length of the existing platforms, and therefore the platform extensions will also be on a curve as there is no practical opportunity to straighten out the layout sufficiently to achieve a 500 m radius curve. The actual track radius, through each of the proposed platform extensions, is as follows: Platform 1 (Down North Kent) - 240 2 (Up North Kent) - 225 3 (Up Strood Loop) 270 m (210 m where existing length of platform is being widened). The permanent speed restriction applicable to all lines through Strood station is 15 mph. The There is unlikely to be any significant impact North Yorkshire Moors Railway with the use of these vehicles on NYMR Enterprises plc services; they have very similar traffic characteristics to the existing fleet of NYMR Mark 1 carriages, with which they are completely interchangeable, although the intention would be to run them as a uniform formation. The benefits to the NYMR of running these vehicles to Whitby in particular are: it increases the pool of available vehicles; it provides a particularly attractive historical train of vehicles of a type which will have worked to Whitby during their LNER and BR service lives. The use of these vehicles would have no effect on the safety of the railway system as they would be used on the same basis as the NYMR Mark 1 fleet. The use of these vehicles will have no effect on the technical compatibility of the railway system now and in the future as they use conventional drop head buck eye couplers, conventional buffers and automatic vacuum brakes. The use of these vehicles does not affect costs or service performance. The NYMR experience of using these vehicles between Pickering and Grosmont shows them to be as reliable in service as our mark one fleet. The affected parties would be Northern Rail as the other The arrangements are complaint to LUL Network Rail standard and meet the operators (LU and LOROL) requirements. The proposed Fixed Red Lights (FRL) arrangements have been supported by the Signal Sighting Chairman and Committee members and mitigates against multiple stop light positions and considers failure of NR or LU lights. A retroreflective buffer beam surface will be provided. No risk introduced, the solution proposed by the Signal Sighting Chairman and committee members and supported by the endorsed SSFs. Certificate Issue Date 19/12/2014 Certificate End Date N/A Lead SC Infrastructure Lead SC Approval Date 12/11/2014 Deviation Status Current 27/11/2014 31/03/2023 RST 31/10/2014 Current 12/11/2014 N/A CCS 16/10/2014 Current As indicated in Appendix 7 of this West Coast Railway Company 03/12/2014 document. The preserved steam locomotive Limited is of a type that ran safely over the British railway infrastructure since its introduction and continued until its withdrawal from revenue service. The locomotive had a history of reliable service. The locomotive is intended for Heritage Operation only. In order to achieve compliance with RGS, the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. N/A RST 31/10/2014 Current Steam Locomotive construction and As indicated in Appendix 7 of this West Coast Railway Company 03/12/2014 operating systems are incompatible with the document. The preserved steam locomotive Limited areas of RGS specified in the supporting is of a type that ran safely over the British document. railway infrastructure since its introduction and continued until its withdrawal from revenue service. The locomotive had a history of reliable service. The locomotive is intended for Heritage Operation only. In order to achieve compliance with RGS, the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. N/A RST 31/10/2014 Current Page 30 Deviations Register RGS Number GMRT2000 RGS Issue Number Three RGS Title Engineering Acceptance of Rail Vehicles Certificate Number 14-130-DEV Title Generic deviation against NNTRs for UK Dual Locomotives. RGS Clause See details of RGS clauses in Annex 1. Scope This deviation is for a new fleet of dual electric/diesel powered locomotives, known as UK Dual (Class 88), supplied by Vossloh España S. A. for operation by Direct Rail Services Ltd. This deviation is sought for the present order of 10 locomotives (8800188010) and all subsequent builds of Class 88 as allowed by the type authorisation rules (subject to major standards changes). The UK Dual locomotive is based on the existing EUROLIGHT and UK Light design. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GKRT0094 One Train Voice Radio Systems 14-129-DEV Global System for Mobile communications for Railways (GSM-R) Calling Line Identity and Contacting Emergency Services. 5.11.3.1 and 5.14.2 The derogation applies to the UK National GSM-R network. GERT8075 One AWS and TPWS Interface Requirements 14-127-DEV Class 170 &amp; 334 Light Emitting Diode (LED) Automatic Warning System (AWS) Indicator Sounder Levels. 4.2.2.1 b) This deviation applies to the LED AWS indicator unit, part no. 062/015808 when fitted to ScotRail Class 170 and 334 trains. GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 14-126-DEV Chiltern Railways Mk3 Galley First Wheelchair (GFW) Auxiliary Power Unit Modification Resistance to Overturning. 2.4.1.1 b) Chiltern Railways Mk3 GFW; extension of derogation 10/046/DGN. Current Deviations Register as at 09 May 2016 Nature and Degree The UK Dual locomotive will be compliant with the Technical Specifications for Interoperability (TSI) requirements, including the Locomotive and Passenger TSI. In addition, it will be compliant with all applicable Notified National Technical Rules (NNTRs) to cover open points and specific cases, and ensure compatibility with the GB mainline system. It will also operate over off Trans-European Network (TEN) routes and therefore the complete suite of RGSs is applicable. Within these RGSs, there are a significant number of requirements that are not directly related to TSI open points, specific cases or compatibility. These requirements have equivalent or comparable requirements within the suite of TSIs, therefore compliance with these RGS requirements duplicates the TSI assessment. Consequently, additional effort and cost will be expended both in respect of production of the evidence of compliance and in its subsequent assessment by the Designated Body. It is also possible that, due to the differences in the detail of the requirements, conflicts might exist that either prevent full compliance with both the TSI and RGS clauses or necessitate a more complex design. Due to both the additional Subscriber Identity Module (SIM) card issue: There is no field on the SIM card (the fields and contents of which are defined by international standards) that can provide this functionality. Public Emergency Call issue: Any GSM-R subscriber making a 999 or 112 call is connected by a point to point call to the Rail Emergency Operator (Level 3) who is able to direct the call to the appropriate person (public emergency services, Network Rail Signaller, Network Rail Route Control). Risk Assessment/Safety Justification Applicant Organisation Certificate Issue Date Use of the alternative actions are considered Vossloh España S.A on behalf 02/12/2014 to deliver an equivalent level of control and of, Direct Rail Services Limited safety as demonstrated in BB14807700005 (-) and will also not require any further ongoing actions or operational constraints. Certificate End Date N/A Lead SC RST Lead SC Approval Date 31/10/2014 Deviation Status Current N/A Network Rail 12/11/2014 N/A CCS 16/10/2014 Current Have a sound level at least 10 dBA above the expected ambient noise level, subject to a minimum of 65 dBA and a maximum of 95 dBA, at a distance of 1 m from the front of the equipment, measured as installed in the driving cab. As part of the approval process to demonstrate compliance with GE/RT8035 (since superseded), sound tests were performed on all First ScotRail (FSR) fleets which were proposed to be fitted with the new indicators. See Atkins reports Let0045022(1 and 2a) for further details. The test included on train measurements of the ambient noise and the warning and clear tones. During testing, it was found that the clear 'ping' tone sounder volume was measured to be slightly lower than the warning 'horn' tone sounder. As a result of this, the class 170 and 334 tests do not meet the requirement for 10dBA above ambient. It is suggested, in the report, that this is likely due to the initial transient nature of the 'ping' signal and meter readings every 0. 125 seconds not providing enough resolution to capture the peak sound level. The supplier Unipart confirmed that the volume levels for both clear and warning are set to the same level. The cost of using meter equipment with a higher sample rate Chiltern Railways intends to modify its locomotive-hauled Mk3 Galley First Wheelchair (GFW) vehicles by removing the motor alternator sets and associated control equipment and installing one modern, solidstate Auxiliary Power Unit (APU). With the proposed new underframe layout of the GFW vehicle in crush laden conditions, using the DeltaRail VAMPIRE modelling software, the vehicle is predicted to overturn at 20. 3ø (non-compliant by 0. 7ø). The singular cause of this deviation, in comparison to the existing GFW vehicle, is due to the mass reduction and higher centre of gravity of the vehicle with the net reduction in vehicle mass. The DeltaRail VAMPIRE software has been previously validated for accuracy against Mk3 vehicle sway test results produced by the British Railways Board (BRB). On the GFW vehicle, a universal accessible toilet and two wheelchair positions are provided at one end and a galley with vestibule-facing serving counter at the other end, which, when calculated in accordance with BRB document TPE24 `Calculation of Passenger Carrying Capacity in Multiple Unit Trains', equates in crush laden conditions to 134 standing passengers. The mass and centre Using a compliant indicator would require a First ScotRail louder sounder. However, drivers have indicated that this louder sound is of discomfort and acts as a potential distraction whilst driving. Using the 90 dBA indicator is felt to be a safer solution (see associated risk assessment FSRM786). Previous conversations with RSSB have stated that there is a view that 6 dBA is the appropriate minimum value as this is specified for controls and indications in the cab in the Rolling Stock Locomotive and Passengers Technical Specifications for Interoperability (RST LOC & PAS TSI), Clause 4. 2. 9. 3. 4 (see email "RE: LED AWS indicators" dated 10/10/2013 22: 04). A further benefit of the new LED style (as opposed to the traditional mechanical style) indicator is increased reliability. This benefit has been witnessed across the 156 fleet which have been fitted with the indicator as a fleet change and have seen an increase in indicator reliability. The increased reliability means that this component is no longer replaced as frequently with associated price savings. Using a uniform style of indicator across the fleet also simplifies stock management, reducing the opportunity for error. 10/11/2014 N/A CCS 16/10/2014 Current None 20/10/2014 N/A RST 03/10/2014 Current Chiltern Railways Page 31 Deviations Register RGS Number GERT8026 RGS Issue Number One RGS Title ,Safety Requirements for, ,Cab Signalling Systems, Certificate Number 14-125-DEV Title RGS Clause Automatic control of train speed 10.3.6 approaching and proceeding over Llanbadarn Automatic Barrier level Crossing Locally monitored by train crew (ABCL) using European Train Control System (ETCS) Level 1 controls on Level 2 ETCS fitted lines when the conditions for the Driver's Crossing Indicator (DCI) to display a white indication are not met. GERT8075 One AWS and TPWS Interface Requirements 14-124-DEV Variation to AWS Indicator Image layout Appendix A GERT8075 One AWS and TPWS Interface Requirements 14-123-DEV Sheffield Tram-Train Train Protection and Warning System (TPWS) receiver position. 3.2.1.3 GMRT2161 One Requirements of Driving Cabs for Railway Vehicles 14-122-DEV Sheffield Tram-Train Windscreen Optical Properties. 6.2.1, 6.2.5 GMRT2176 One Air Quality and Lighting Environment for Traincrew Inside Railway Vehicles 14-121-DEV Sheffield Tram-Train Cab Air Quality. 5.1, 5.2 GMRT2461 One Sanding Equipment Fitted to Multiple Units and on- track Machines 14-120-DEV Sheffield Tram Train Sanding, Issue 2. GMRT2130 Three Vehicle Fire, Safety and Evacuation 14-118-DEV GMRT2130 Three Vehicle Fire, Safety and Evacuation 14-117-DEV Current Deviations Register as at 09 May 2016 Scope Llanbadarn ABCL located between Dovey Jcn and Aberystwyth on the SBA2. Nature and Degree Fully interlocking the crossing with the ETCS would require the crossing to be converted to a Manned Crossing with Barriers (MCB) type which would significantly increase costs, time to implement and extending crossing closure times for users. Deviation 09/169/DGN was granted to permit Automatic Open Crossing locally monitored by train crew (AOCL) and ABCL crossings not be interlocked to the Movement Authority (MA). Part compliance with current RGS is possible by applying a 0 km/h Temporary Speed Restriction (TSR). However, if a zero speed were applied locally to the crossing in place of the proposed 10 km/h, it would prevent a train from proceeding over the crossing as directed in GE/RT8000/TW8 ERTMS Rule Book Level Crossings on ERTMS Lines drivers' instructions Clause 4. 4, without the driver first overriding the on board systems cancelling the MA. Therefore, the train would have to proceed in degraded "Staff Responsible" mode to the next awakening area before returning to a supervised mode, which is considered to increase risk. Risk Assessment/Safety Justification Applicant Organisation The fitment of additional automatic Network Rail protection has been recommended in a report produced by the Rail Accident Investigation Branch (RAIB) and supported by the Office of Rail Regulation (ORR) at Llanbadarn ABCL. Proposal will automatically control the speed of an approaching train to 10 km/h at a predetermined position on the approach to the crossing. The pre-determined position for the 10 km/h commencement shall be calculated such that any train shall be able to stop from 10 km/h before entering the crossing. The 10 km/h restriction shall be enforced on the train continuously from the commencement of the 10 km/h until the front of the train passes clear of the crossing deck. If the vehicle overspeeds, a Class 158 unit will be subject to a service brake application that is released once the vehicle speed has decreased to 10 km/h. Class 97 locomotives will be subject to an emergency brake application, which has the effect of bringing the vehicle to a stand. The brakes may be released by the driver once the vehicle is stationary. The 10 km/h has been selected as the lowest speed it is practicable to reliably drive all types of traction in use on the route. The 10 km/h also reduces the Minimum dimension of AWS Visual Compliance will require the redesign of the No impact on other affected parties. The Mors Smitt UK Ltd. Indicator. This deviation is for a project LED arrangement to use an alternative LED TY341 AWS LED Indicator is a redesign of requiring authorisation for placing in service and filter arrangement. Should the the earlier TY228 AWS LED Indicator under the Railways (Interoperability) application be rejected we will be faced with developed for the Channel Tunnel fleets in Regulations 2011. redesigning the unit. 1991. The indicator uses the same LED display elements and size as the earlier design which has proved satisfactory in use since the Channel Tunnel opened in 1993. It is also the image used to illustrate Appendix A of GE/RT8075. Given that the requested display size has been in use on Class 92 and Class 373 vehicles, and on the Class 395 since June 2009, it is believed that the display diameter of 38 mm has been shown to be adequate for the application. It is not believed that the deviation will have any impact on the following: The safety of the railway system; The technical compatibility of the railway system now and in the future; Costs and service performance, including reliability and availability; If relevant, other essential requirements such as environmental protection and health. Certificate Issue Date 29/04/2015 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 19/03/2015 Deviation Status Current 22/09/2014 N/A CCS 18/09/2014 Current This application relates to a total of seven three-car tram-train EMUs for operation only on routes fitted with axle counters. Unit numbers: 399201 - 399207. Vehicle numbers: 99001 - 99007 99101 9910799201 - 99207. This deviation relates to a total of seven three-car tram-train EMUs. Unit numbers: 399201 - 399207. Vehicle numbers: 99001 99007;99101 - 99107;99201 - 99207. There is no impact of the alternative TPWS Stagecoach Supertram receiver position on the hazard controlled by the standard (that of interference with TI21 track circuits). 12/10/2015 N/A CCS 03/09/2015 Current See Appendix. Stagecoach Supertram 12/11/2014 N/A RST 03/10/2014 Current This application relates to a total of seven See Appendix. three-car tram-train EMUs. Unit numbers: 399201 - 399207. Vehicle numbers: 99001 99007;99101 - 99107;99201 - 99207. See Appendix. Stagecoach Supertram 12/11/2014 N/A RST 03/10/2014 Current 7.1, 9.1, 10 This application relates to a total of seven three-car tram-train Electric Multiple Units (EMUs). Unit numbers: 399201 - 399207. Vehicle numbers: 99001 - 99007; 99101 99107; 99201 - 99207. Sanding is ahead of the leading wheelset Stagecoach Supertram and risk to train detection is discussed in Appendix A. The mainline route is fitted with axle counters that are immune to sanders. 02/09/2015 31/12/2016 RST 24/07/2015 Current Contradiction of Running Time Requirements - Class 387. 2.3.3 Twenty-nine four-car Class 387/1 EMUs and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. It is considered that there is no negative impact from complying with the relevant clause of the SRT TSI instead of GM/RT2130. The requirement of the SRT TSI is considered to be an appropriate requirement for the Class 387 units. Bombardier Transportation 02/09/2014 N/A RST N/A Current Class 387 Cab-Saloon Door not Self Closing. 2.5.5 Twenty-nine four-car Class 387/1 EMUs and up to thirty-five four-car Class 387/x EMUs (an option on the current contract. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. It is considered that there is no negative Bombardier Transportation impact of this deviation since train crew are already used to closing the cab-saloon door. Therefore, a fire barrier is always maintained. 02/09/2014 N/A RST N/A Current Full compliance with the GE/RT8075 Issue 1, Clause 3. 2. 1. 3 would necessitate a significant redesign of the vehicle, and would add considerable time and cost to the project even if it were found to be technically feasible. See Appendix. The tram-trains are not permitted to continue in service with isolated sanders. The tramtrain is fitted with a distributed sanding system, when operating on the mainline: only the leading sander will be used. The sand used will be the same as for the Sheffield Supertram. To comply with Clause 2. 3. 3, it would be necessary to provide significant protection of systems and/or redundancy to enable the units to operate for 15 minutes after the outbreak of a fire. Control cabling in any area judged to be vulnerable would need to be protected by some form of shielding. Some systems may need redundancy with cabling routed in separate locations. To achieve this, there would be significant design changes and additional equipment. This would add significant cost to the project. In addition, maintenance of the vehicles would be changed and in some cases hindered by the extra protection. At the outer ends of a train the cab/saloon door forms part of the fire barrier between the cab and the passenger saloon, and it is locked shut to prevent passenger access to the cab. This door is not self-closing. To comply with the clause, a closing device would have to be added to the door. It is considered that, if such a device was fitted, train crew could rely on the device and may not check that the door is securely closed. There is a risk that the closing device would shut the door, but not fully, which presents a risk to the train security. It should be noted that, when the cab is in the middle of a multiple formation, the cab/saloon door is locked in the converted position, preventing passenger access to the cab controls, and a compliant gangway door operates as part of the fire barrier. Page 32 Deviations Register RGS Number GMRT2130 RGS Issue Number Three RGS Title Vehicle Fire, Safety and Evacuation Certificate Number 14-116-DEV Title Class 387 Emergency Lighting Performance. RGS Clause 4.3.1, 4.3.2, 4.3.6 GCRT5033 Two Terminal Tracks - Requirements for Buffer Stops, Arresting Devices and End Impact Walls 14-112-DEV Waterloo International, Platforms 20-23 track curvature at buffer stop 2.3.1 GERT8000-SP Four Speeds 14-111-DEV Class 68 Locomotives Running Light Engine 2.2 at Permissible Speeds. GMRT2149 Three Requirements for Defining and Maintaining the Size of Railway Vehicle 14-110-DEV Class 375/6 Automatic Power Control (APC) B10.3 Receiver Gauging. GMRT2130 Four Vehicle Fire, Safety and Evacuation 14-109-DEV Advance stage deviation for installation of Global System for Mobile communications for Railways (GSM-R) to Class 37 Locomotives. Current Deviations Register as at 09 May 2016 All clauses. Scope Twenty-nine four-car Class 387/1 Electric Multiple Units (EMUs) and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Nature and Degree · Light above doorway: There is limited space above each doorway due to the UK loading gauge and the space requirements of the door header gear. To fit emergency lighting directly above each bodyside door, the lighting unit would have to be fitted between the door gear and the header gear trim panel, moving the trim panel lower. This would reduce the door throughway height, which is already lower than that required by GM/RT2473 Clause B5. 1. 2; a separate deviation application applies to this clause. The lower doorway would increase the risk of passengers striking their head, and would impede evacuation. Controls and signage in field of illumination: The door controls and signage are located on stand backs to the side of the doorways, and back from the door itself. It is not possible to have a single light pointing at the door threshold and at the controls. Therefore, multiple lights would be required. This would contradict the objective of not attracting passengers to the vestibule (as described in guidance note GM/RC2531 Clause RC024). Provide lighting for charging photoluminescent signage: As above, this would require a bright light directed at the signage, which would emphasise the emergency · P20 radius 220m at proposed location; · P21 radius 223m at proposed location; · P22 radius 227m at proposed location; · P23 radius 241m at proposed location. Please refer to the attached document 'Waterloo International Terminal - Buffer Stop Derogation - Issue 3'. Risk Assessment/Safety Justification It is considered that there are no negative impacts from the Class 387 emergency lighting design. Position of lights and illumination of controls: GM/RT2130 (together with guidance note GM/RC2531) gives two reasons for requiring emergency lights above the door and not in the centre of the vestibule. o Firstly, it should avoid encouraging passengers towards the vestibule. This is not applicable to vehicles such as Class 387 where the vestibules are at 1/3 and 2/3 positions in the vehicle, and there is no full partition between the passenger seats. Any lighting in the vestibule, at the centre or at the doorway, will be visible to passengers. The proposed location of lighting will create even lighting along the vehicle, without attracting passengers to any area. o Secondly, lighting from the centre would mean that passengers created shadows over any equipment they tried to use since the light would be behind the passengers. The position of the lighting on Class 387 minimises this issue within the space constraints of the doorway. The problems with shadows are minimised due to the position of the normal and emergency door controls (and passenger emergency alarm) Waterloo International, Platforms 20-23. The Waterloo International Station platforms were originally designed to operate using the areas under the platforms (arrivals and departures with passport controls) for the low frequency Eurostar services. Changing to a high intensity service requires additional space behind the buffer stops to allow passenger congregation and access to and from the platforms to occur safely, where opposing passenger flows will occur. The station structure and platforms have a small existing straight section (approximately 35 m) at the buffer stop end, and then curve at radii between 220-241 m. The proposed location for the buffer stop is approximately 57 m from its current position, which is compatible with track remodelling options from GRIP 2 and existing structural bracing of the elevated track slabs. The modifications being proposed to the existing structure are so significant, Section 2. 3 General Requirements for New Construction have been applied. A risk assessment using GC/RC5633 has been undertaken to satisfy Section 2. 4 - Requirements for Existing Locations. The need for a straight approach to the buffer stops, to satisfy Clause 2. 3. 1. 1, is to ensure a collision with the buffer stop beam is not at an angle. This This deviation applies to all light engine The current RGS was written for the historic This alternative action will allow better use of movements of Class 68 Locomotives by situation where locomotives had a braking available line capacity since a class 68 Direct Rail Services on Network Rail capability worse than the vehicles that they locomotive running light engine will be able Infrastructure. Direct Rail Services seeks to were hauling. The Class 68 is a modern to run at the permissible speeds. This permit Class 68 locomotives running as light locomotive with braking capability better approach is reasonable since the braking engine to run at permissible line speed. than that shown in figure 3 of GM/RT2042 capability of a class 68 is sufficient for all `Stopping Distance Curve - Maximum signalled routes on Network Rail Speed 125 mile/h Performance for Traction infrastructure. The class 68 is fitted with Units required to operate over routes automatic sanders and modern Wheel Slide signalled in accordance with Appendix 3 of Protection (WSP) systems to minimise the GK/RT0034'. The locomotive meets the risk of poor rail adhesion. Direct Rail required stopping distances for all signalled Services drivers' will be briefed on this routes on Network Rail infrastructure, deviation pending planned revision of Rule therefore the RGS assumption is not Book module SP to permit this. It is notable appropriate to the class 68 locomotive. that Rule Book module SP already Complying with the current RGS will result in recognises that these restrictions do not under-utilisation of track capacity due to need to apply for locomotives with enhanced reduced running speeds of Class 68 braking (such as Class 67) and this locomotives running light or hauling short deviation seeks to apply this principle to a trains. new locomotive with similar braking capability. Class 375/6 rolling stock. If the replacement APC receiver were to be The attached reference document set up within the gauge specified in (3EER400018-6880) compares the Class GM/RT2149, it will be outside the 375 fleet with other Electrostar fleets which specifications that the manufacturer will have had the same deviation accepted, as guarantee operation, and therefore subject well as other typical British Rail vehicles to failing to operate correctly. (Classes 313 and 365). This comparison demonstrates that the gauging risk for the new APC receiver is no greater than those fleets for which derogations have been made or the existing British Rail fleets. It is considered that the risk of the APC not operating when required, due to being outside the manufacturer design limits is greater than the gauging risk considered above. It is therefore considered appropriate to progress with this deviation. Applies to the installation of GSM-R system Due to GM/RT2130 Issue 4 being notified as The machine will operate with the same to 4x Class 37 locomotives; a National Technical Rule (NTR) by the level of compliance as all other Class 37 37116/175/219/421. This deviation is for a competent authority in the UK, this standard locomotives in the UK that have already project requiring authorisation for placing in has become applicable to the project been fitted with GSM-R. service under the Railways (Interoperability) following the completion of GSM-R system Regulations 2011. development, but prior to it being fitted to Class 37 locomotives 37116/175/219/421 (expected to be fitted in Summer/Autumn 2014). The design of the GSM-R system is compliant with Issue 3 of GM/RT2130. Issue 4 of GM/RT2130 is a fundamental revision of the standard to align it with EN 45545 and demonstrating compliance with Issue 4 would require a complete new assessment. Therefore, complying with the new standard at this advanced stage of the GSM-R project would require significant re-work that would incur additional cost and delays to the project. In addition, fixed system parameters cannot be modified, resulting in the risk that the GSM-R system may not comply with the new Euronorm. Applicant Organisation Bombardier Transportation Certificate Issue Date 02/09/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date N/A Deviation Status Current Network Rail 12/12/2014 N/A INS 12/11/2014 Current Direct Rail Services 27/08/2014 N/A TOM N/A Current London and South Eastern Railway 19/08/2014 N/A RST N/A Current Colas Rail Ltd 04/08/2014 N/A RST N/A Current Page 33 Deviations Register RGS Number GIRT7016 RGS Issue Number Five RGS Title Interface between Station Platforms, Track and Trains Certificate Number 14-108-DEV Title RGS Clause Re-opening of Lea Bridge Station - provision 11.1.4.1 Provision of recess beneath of recess platform edge Scope Lea Bridge Station. ELR: SDC. Mileage: 6m 25ch. Nature and Degree Minor impact in regards to safety, no effect to performance: The overhang will still be present but not to the extent required in GI/RT7016. Please note that the route has requested that a 760 mm offset is used rather than the normal 730 mm, to provide clearances for W10 and W12, this affects the remaining overhang. Compliant stepping distances will be provided, an overhang will be present with a minimum proposed dimension of 160 mm. The platform extensions will be compliant. GKRT0075 Two Lineside Signal Spacing and Speed Signage 14-106-DEV Up Slow Permissible Speed Warning Indicator (PSWI) position approaching Thornton Heath Station. 40 PSWI (UVS9M13CHU) on Up Victoria Slow at on approach to Thornton Heath Station. Currently, a permanent PSWI is installed at a compliant position on signal T64 at the start of the 60 mph line speed. As per GK/RT0075. An Automatic Warning System (AWS) is provided 171 metres from signal T64, acting as the AWS for both the signal and the PSWI. This was resulting in a horn vice bell warning to drivers when T64 was displaying a green aspect, thus causing confusion. As a result, T64 Signal is currently restricted to double yellow. GKRT0075 Two Lineside Signal Spacing and Speed Signage 14-105-DEV Non-provision of Permissible speed warning 3.3.1.4 indicators (PSWI) boards in the vicinity of Bricklayers Arms Junction. GKRT0075 Two Lineside Signal Spacing and Speed Signage 14-104-DEV Non-provision of Permissible Speed Warning Indicators (PSWI) boards in the vicinity of Spa Road. Current Deviations Register as at 09 May 2016 3.3.5.5 d) 3.3.1.4 b) Risk Assessment/Safety Justification Applicant Organisation The project is planning to re-open Lea Network Rail Bridge Station, which was closed in 1985. The new station will have a footbridge (reusing the old station deck spanning the tracks), two lifts and be extended to accommodate eight-car trains. The old platforms are still present and in reasonable condition (with the copers removed). They have the existing OLE support structures and other services in the platform which make it not reasonably practicable to demolish them. As such, the old platforms from the closed station are to be reused and extended. When the new copers and surface are installed, there will not be a 300 mm recess beneath the platform edge; the existing construction of the platform is a brick front wall which it is not reasonably practicable to demolish to construct platform compliant to this clause. Accompanying this application are details of the proposed overhang dimensions. This was identified as part of the design process and identified that it would be un-economical to demolish due to its good condition and the presence of numerous OLE mast foundations in the platform structure. Deceleration distances shown in the Network Rail standards is extremely pessimistic. Calculating the deceleration distance required, to reduce to the required speed shows sufficient distance. See supporting information for calculations. At assumed braking rate of 8%g (passenger trains), approximately 295 m deceleration distance required to reduce speed from 60 mph to 40mph. At assumed braking rate of 6%g, approximately 400 m deceleration distance required to reduce speed from 60 mph to 40 mph. Line speed on approach to the 60 mph PSR at T64 is maximum of 30 mph/40 mph. Freight trains are not expected to attain a speed greater than 40 mph due to 30 mph approach. Based on a four-car unit and acceleration rate of 6. 5%g, maximum attainable speed would be approximately 55 mph, only 5 mph greater than speed that a train could be expected to brake to a stand in accordance with GK/RT0075 Appendix B and permitted to be used for deceleration distance in Section 3. 2. 3. 3 b). Analysis of track circuit data conducted by the Route over two separate weeks before and after the T64 YY restriction was introduced has shown the average speed of trains through the affected section of line to be 28. 12 mph Non-provision of PSWI boards in the vicinity Permissible speed warning indicators All approaches to the 40mph speed Network Rail of Bricklayers Arms Junction. (PSWI) would need to be provided in the Up restriction are via a high speed turnout at direction for the following speed reductions: Bricklayers Arms Junction, which is 60 mph from the Up Sussex Fast to 40 mph immediately followed by a section of line at PSR on the Sussex Reversible at LBC 2816 50 mph requiring the driver to slow down m; 60 mph from the Up Sussex Slow to 40 from 60 mph. The 50 mph section is 400m+ mph PSR on the Sussex Reversible at long on approach to the 40 mph restriction. LBC;60 mph - 40 mph speed reduction This will allow sufficient time/sighting for the would require a PSWI at minimum of 630 m driver to reduce speed accordingly. Taking (at approximately LBC 3446 m) from the into account all potential warning board speed restriction. This would place it within positions detailed in section 10, it is the switches and crossings (S &amp; C) at considered that the benefits of providing a Bricklayers Arms Junction so the PSWI warning of the reduction in speed is board would have to be moved back clear of outweighed by the risk of overloading crossover 8005/8006. There are 35/40 drivers with information and liable to cause diverging Permanent Speed Restriction confusion. (Note this is described in (PSR) boards at this position for routes GK/RT0075 Section 3. 2. 2). towards the Bermondsey Reversible and the Up Bermondsey Spur. The PSWI board for the 'straight ahead' route from the Down Sussex Slow to the Sussex Reversible Line could be placed alongside the existing Diverging PSR board. The PSWI board for the 'straight ahead' route from the Down Sussex Fast to the Sussex Reversible Line cannot be similarly positioned because there is no space. However, it could be placed on the right hand side opposite the Diverging PSR board. This issue was discussed at Non-provision of PSWI boards in the vicinity Permissible Speed Warning Indicators All approaches to the 30 and 40 mph speed Network Rail of Spa Road. (PSWI) would need to be provided in the restrictions are via 50 mph crossovers or are Down direction for the following speed on a line with a maximum linespeed of 50 reductions: 60 mph from the Down Sussex mph for a distance of 500 m+ on approach, Slow to 40 mph PSR on the Sussex which should allow sufficient time/sighting Reversible at LBC 2624 m; 60 mph from the for the driver to reduce speed accordingly. Sussex Reversible to 40 mph PSR on the Taking into account all potential warning Sussex Reversible at LBC 2624 m; 60 mph board positions detailed in Section 10, it is from the South London Reversible to 40 considered that the benefits of providing mph PSR on the South London Reversible PSWI for the reduction in speed is at LBC 2624 m;60 mph from the South outweighed by the risk of overloading London Reversible to 30 mph PSR on the drivers with information and liable to cause South London Reversible at LBC 2624 m;60 confusion. (Note this risk is described in mph - 40 mph speed reduction would GK/RT0075 Section 3. 2. 2). require a PSWI at minimum of 706 m (at approximately 4865 m) from the speed restriction;60 mph - 30 mph speed reduction would require a PSWI at minimum of 805 m (at approximately 4766 m) from the speed restriction. The first logical position for the PSWIs would be combined with the 30/50 mph turnout board at 3m00ch on the Down Sussex Slow, combined with the 30/50 mph turnout at 2m78ch on the Sussex Reversible and approximately 2m78ch on the South London Reversible. However, in order to physically fit the boards in the 6ft, they would require to be positioned in a stack formation, which would mean the combined height Certificate Issue Date 08/12/2014 Certificate End Date N/A Lead SC INS Lead SC Approval Date 12/11/2014 Deviation Status Current 01/10/2014 N/A CCS 18/09/2014 Current 24/09/2014 N/A CCS 21/08/2014 Current 24/09/2014 N/A CCS 21/08/2014 Current Page 34 Deviations Register RGS Number GMRT2461 RGS Issue Number One RGS Title Sanding Equipment Fitted to Multiple Units and on- track Machines Certificate Number 14-097-DEV Title Class 142, 143, 144, 150, 153, 155 and 156 manual sander systems; sand application prior to commencement of braking. RGS Clause 6.4 Scope The scope of the deviation shall include all Class 142, 143, 144, 150, 153, 155 and 156 Diesel Mechanical Multiple Unit (DMMU) pacer and sprinter units operated by Northern Rail, First Great Western and Arriva Trains Wales over all routes operated over by the named companies with the detailed traction types. GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 14-095-DEV London Bridge station low level terminal platforms buffer stop lights. 2.5.3.4 b) London Bridge station low level platforms. GKRT0192 Two Level Crossing Interface Requirements 14-094-DEV Telephone requirements for Automatic 2.10.2.1 Barrier Level Crossing Locally Monitored by train crew (ABCL) converted from Automatic Open Crossing Locally Monitored (AOCL). GERT8075 One AWS and TPWS Interface Requirements 14-093-DEV Class 387 Train Protection and Warning System (TPWS) Labelling. Current Deviations Register as at 09 May 2016 4.1.3.1 and Appendix F, clauses F3.6 and; F3.7 Nature and Degree This is already dealt with in Deviation 14/083/DEV for the fitment and use of brake step one sanding (will cover all 14X and 15X units so fitted with the manual sanding device). This is an extension of this and looks to allow sand to be applied prior to brake step one taking place to ensure the train wheels are on a sand treated rail prior to braking commencing. Note: this does not cover units fitted with auto-devices that links into the Wheel Slide Protection (WSP) systems (I. e. 158, 321, 322, 333 etc. ). Previously, deviations were raised against the requirements of GM/RT2461 regarding the manual application of sand on 14X and 153 units which do not comply to the standard requirements due to their wheel/axle formation. The deviation was in way of asking for permission to have sanding devices fitted to these units despite the wording of the procedure. Initial fitment saw a step three system placed on the units which was immediately recognised as being not fit for purpose, and a deviation was raised to have this changed to step two application. The step two sanding was an improvement; however, it was recognised that, to achieve better results, a deviation should be requested for step one sanding to Track on approach to the buffers is curved. If the rolling stock approaches the buffer stop lights positioned in the centre of the track, then at approximately 10 m, the driver would lose sight of the buffer stop lights. This is due to the driver's position being within the left hand half of the driving cab, and much of the rolling stock having centre gangways. Risk Assessment/Safety Justification Applicant Organisation It should be acknowledged that the main Northern Rail Ltd impacts of the deviation regarding the use of sanders has been covered in the deviation for brake step one sanding. The main issues raised are the train coming to a stand "beached" on sand. The application of additional sand prior to the initial application of the brake will have no effect on what occurs at the end of the braking when the train comes to a stand. It is hoped that one impact will be the increased ability of the train, especially the 14x units to be able to sustain a step one brake application more readily if the application commences on a pre-treated rail. 14X units are susceptible to sliding when the brake is initially applied and have a low tolerance to rail head conditions. The application of sand post the brake application may not allow the sand to propagate along the train prior to the slide commencing and, once the leading axle is sliding, this tends to act like a plough pushing the applied sand from the rail head and preventing the trailing axles from gaining any benefit. Northern have also noted that, during 2013, there was a marked increase in 14x wheel set wear. Whilst the reasons for this are as yet unclear, there are possible links to the fitment and use of sand Line speed on approach to the Buffer Stops Network Rail is 20 mph. The existing London Bridge Station terminating Platform 8 - 16 inclusive operate with left hand mounted buffer stops lights. This reflects application of old standard CP-PM-040, Section 4. 2. 2. This permitted this option if curvature of approach track and rolling stock limits / loss of viewing of the buffer stops on the approach to the buffer stops. It has been proposed in recent updates planned to RGS to allow buffer stop lights to be positioned to improve visibility and not fixed to the centre line. Second stage of the remodelling the eastern approach to London Bridge Low Level station (designated LL04) took place in March 2014, when new Platforms 14 and 15 were brought in to use. The third stage (LL07 August 2014) and fourth stage (LL09 January 2015) bring remaining new Platforms 10 to 13 into use. The application is to cover all terminating platforms. Certificate Issue Date 14/08/2014 Certificate End Date 31/12/2017 Lead SC RST Lead SC Approval Date 25/07/2014 Deviation Status Current 21/08/2014 N/A CCS 24/07/2014 Current National application for conversions of Automatic Open Crossing Locally Monitored (AOCL) to Automatic Barrier Crossing Locally Monitored (ABCL). Many AOCL crossings do not have public telephones. The impact of adding phones at the time of conversion to ABCL would require signaller ergonomic aspects to be considered. Addition of telephones at level crossings with barriers can affect the signaller's workload, particularly due to nuisance usage of telephones. This can distract signallers from safe operation of railway and other crossings. Workload would need to be assessed to ensure that it will not adversely affect the performance of the signaller. In some cases, an increase of the number of telephones within a control area may lead to the assessment requiring more resources to adequately manage the control area. A fundamental part of conversion to ABCL Network Rail is that the crossing remains locally monitored by the train driver. The telephones associated with locally monitored crossing types are not required to be utilised for making emergency calls, and they are of a type that is not self-proving. Their use is primarily to report equipment failure, and to request permission to cross in vehicles that are likely to need additional crossing time (typically slow freight vehicles, wide loads, and low loaders at risk of grounding). The addition of telephones at locally monitored crossings does very little to improve risk management, since the primary safety operation of the crossing includes monitoring of the crossing area by train drivers and trains operated at speed such they can stop short of the crossing if it does not operate correctly. 21/08/2014 N/A CCS N/A Current Four-car Class 387/1 Electric Multiple Units (EMUs) and four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Fully complying with Clauses F3. 6 and F3. 7 of GE/RT8075 would make the TPWS labels inconsistent with the labelling in the remainder of the cab. The control pushbuttons are different sizes. Complying with GE/RT8075 Clause F3. 6, vertically aligning the rows for each label, causes the space between the control and the label to be different and larger than necessary. This is not consistent with good practice whereby space between the label and control is consistent. Text would be considerably larger than the existing labels and would appear more prominent than on other controls and indicators. This could be interpreted as the TPWS interface being more important than other displays in the cab. Although it is a primary instrument, it should not be prioritised over other primary instrumentation. There is insufficient space to make all other labelling consistent with the specified text size. This good practice of consistency is identified within the "Ten principles for good interface design", shown on page 36 of the RSSB's "Understanding Human Factors - A Guide for Railway Industry" 2008, and is contained within the guidance notes of the RSSB's "Alarms and Alerts Guidance and Evaluation Tool". All current existing Electrostar units feature Bombardier Transportation TPWS Driver Machine Interface (DMI) labels with a character height of 3 mm and a similar arrangement to that proposed for the Class 387. The worst case angle subtended at the eye is 11. 3 minutes of arc, which is comparable to and better than other labels on the driver's desk that comply with good practice. There is no evidence that the existing controls are difficult to read, and so it is not considered that there is a negative impact from this non-compliance. 21/08/2014 N/A CCS 24/07/2014 Current Page 35 Deviations Register RGS Number GMRT2461 RGS Issue Number One RGS Title Sanding Equipment Fitted to Multiple Units and on- track Machines Certificate Number 14-092-DEV Title Class 387 Sanding on Trailing Units. RGS Clause 6.2, 9.1 and 9.3.1 Scope Four-car Class 387/1 Electric Multiple Units (EMUs) and four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 14-091-DEV Class 387 - Emergency brake override indication. B11.4 Twenty-nine four-car Class 387/1 Electric Multiple Units (EMUs) and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GMRT2161 One Requirements for Driving Cabs of Railway Vehicles 14-090-DEV Class 387 Windscreen Wipers Obscuring Sightline. 6.2.6 Twenty-nine four-car Class 387/1 Electric Multiple Units (EMUs) and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 14-089-DEV Class 387 - Locking Doors Out of Use. B9.1, B10.1, B10.2 and B11.1 Twenty-nine four-car Class 387/1 EMUs and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Current Deviations Register as at 09 May 2016 Nature and Degree The deviation requests enhanced performance which is non-compliant with the standard as written, but consistent with the objectives of the standard. Risk Assessment/Safety Justification Applicant Organisation Sand will only be dispensed during a brake Bombardier Transportation application (step 2, full service or emergency) by units on which the leading vehicle detects wheel slide. As such, trailing units will only dispense sand if they detect wheel slide and have sufficient sand available. The likelihood of sanding on trailing units occurring is lower, as the leading unit will condition the railhead and so the trailing units are likely to experience wheel slide or slip to a lesser extent. This functionality has been developed to increase the safety of the railway in conditions of extremely poor rail head adhesion or where the sanding system on the leading unit does not function correctly (due to a fault or having run out of sand), having a positive impact on overall system performance. When sand is deployed on the leading unit of a train, sixteen axles will have passed over the sand, dispersing it on the rail head, prior to the trailing unit deploying further sand (assuming that the training unit is experiencing slide). Any sand deployed by the final unit in a train will be dispersed on the rail head by fourteen axles. Therefore, the amount of sand deposited and the number axles following the deposition points will be the same as if the units were To comply with this requirement extra There are considered to be no negative Bombardier Transportation functionality would have to be added to an impacts of the proposed design as it is a existing indicator, or an additional indicator continuation of the existing Class 377 would have to be added to the driver's desk. design, to which drivers are already In either case, changes to the units' accustomed. The design adequately warns schematics and wiring would be needed to the driver that an emergency brake override illuminate the indicator when an emergency has been made. brake application had been overridden. The change would make the cab desk different from the existing Class 377 fleet and would require additional training for the driver; the additional desk indicator could be confusing to drivers used to the existing Class 377 desk. To comply with the standard would require a When the proposed wipers are in the Bombardier Transportation, change to the wiper arm, to incorporate a parked position (I. e. when not in use) part Southern `dog-leg' design. This would necessitate of the support arms for the wiper blade that Class 387 units have a different spare obscures part of the primary vision area, low part from other existing Electrostars. down and to the right of the driver's vision. This obscured part of the driver's sight lines (taken from the driver's seat position) measures 94 mm upwards and 48. 5 mm to the left of the bottom right corner of the primary vision area. The attached drawing No. 3EER400014-6151 indicates the obscured portion of the windscreen from the exterior perspective of the cab, although the dimensions are as observed from the driver's seat position. The area obscured is required by case (a) of the sightlines required for seated drivers, I. e. : A view of the track (at rail height) at 5 m beyond the vehicle buffers (or vehicle end) for vehicles subject to frequent coupling and uncoupling activities. The wiper arm will slightly obscure the right-hand rail (from the driver's perspective). A small movement of the driver's head to the left will allow the obscured area to be viewed. Case (b) - line side signals - and case (d) - a view of the track in the distance - are not obscured. There are no known negative impacts from the current design. The infringement is All previous Electrostar builds have the The Electrostar functionality was previously Bombardier Transportation following functionality when a door is locked permitted for "all passenger vehicles fitted out of service (which complies with with power operated doors with. . . GO/OTS300, the standard in force at the emergency access and egress devices" time the original design was created): Door under non-compliance 08/059/NC. interlock is bypassed and so the door status However, this non-compliance applies to is no longer monitored. Door emergency GM/RT2473 Issue 1. GM/RT2473 has egress devices have no effect on a door subsequently been up-issued to Issue 2 and which has been locked out of service. Door so the non-compliance cannot be applied to emergency access devices have no effect the Class 387 units. 08/059/NC states: "A on a door which has been locked out of number of deviations are listed against service. Changing the design to fully comply GM/RT2473 Clauses B9. 1 and B10. 1. The with Clauses B9. 1, B10. 1, B10. 2 and B11. deviations relate to the ability of the access 1 of GM/RT2473 would: Require the door and egress device to open a door that has system to be redesigned. Increase the been manually locked out of use by the train security and vandalism risks associated with crew. The deviations are: 04/265/DGN unauthorised access to the train. Conflict relating to Clauses B9 and B10 which with the requirements in the High Speed applies to the unlocking of passenger doors Rolling Stock Technical Specification of via the emergency egress and access Interoperability (HS RST TSI) (referred to devices. 05/031/DGN relating to Clauses B9. from the SRT TSI). Part of Clause 4. 2. 2. 4. 1, B10 and B11. 2 which applies to the 2. 1 of the TSI states ". . . Each door shall position of the passenger egress device, the be provided with an individual opening direction to operate the emergency access device, accessible to passengers, to allow device and the unlocking of passenger that door to be opened for emergency doors via the emergency egress and access reasons, at speeds below 10 km/h. This devices. 07/205/DGN relating to Clauses device shall have no effect on 'a door locked B9. 1 and B10. 1 which applies to the out of service'. . . "Be inconsistent with the unlocking of passenger doors, via the remainder of Southern's Electrostar fleet. emergency egress and access devices that Certificate Issue Date 14/08/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date 25/07/2014 Deviation Status Current 09/07/2014 N/A RST N/A Current 09/07/2014 N/A Rolling Stock N/A Current 09/07/2014 N/A RST N/A Current Page 36 Deviations Register RGS Number GMRT2473 RGS Issue Number Two RGS Title Power Operated External Doors on Passenger Carrying Rail Vehicles Certificate Number 14-088-DEV Title Class 387 Door Auto-Close Timing. RGS Clause B7.10 Scope Twenty-nine four-car Class 387/1 Electric Multiple Units (EMUs) and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Nature and Degree All previous Electrostar builds (as well as some other non-Bombardier products such as the Hitachi Class 395) have used a door auto-close time of around 15 seconds, rather than the 45 second minimum specified in GM/RT2473. The energy consumption of the Heating, Ventilating and Air Conditioning (HVAC) system would be increased and passenger comfort reduced if the auto-close time was increased from around 15 to 45 seconds. GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 14-087-DEV Class 387 Ready-to-start Pushbutton Texture and Functionality. B8.4.2 Twenty-nine four-car Class 387/1 EMUs and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. All the Southern Electrostar fleets are designed as follows: The 'ready to start' pushbutton is not textured (and neither is the surround), because the control is located close to the textured 'door close' pushbutton at most locations. The 'ready to start' pushbutton on the saloon guard's control panels is only active when all the passenger doors are locked closed. The 'ready to start' pushbutton in a cab will operate irrespective of the status of the passenger doors. Changing the design to comply with the RGS requirements would introduce inconsistency across Govia Thameslink Railway's Class 377 fleet, and would prevent the `ready to start' pushbutton in the nonactive cab from functioning. Complying with this RGS requirement would also make the design inconsistent with the Rule Book, GE/RT8000/SS1, Station Duties and Train Dispatch, Issue 3. GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 14-086-DEV Class 387 Door Throughway. B5.1.2 Twenty-nine four-car Class 387/1 EMUs and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. To comply with this clause would require the doorway to be enlarged by approximately 10 mm. This would require the car body design to be changed, and new structural validation of the car body design would be needed. Door header gear would have to be moved upwards and the door design altered. New interior trim would be needed for the new installation. This would add significant cost to the units. GMRT2149 Three Requirements for Defining and Maintaining the Size of Railway Vehicle 14-085-DEV Class 387 Shoegear Gauge. B10.2 GMRT2149 Three Requirements for Defining and Maintaining the Size of Railway Vehicle 14-084-DEV Class 387 Automatic Power Control (APC) Gauge. B10.3 Current Deviations Register as at 09 May 2016 Applicant Organisation Bombardier Transportation Certificate Issue Date 09/07/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date N/A Deviation Status Current Bombardier Transportation, Southern 09/07/2014 N/A RST N/A Current A door throughway height of 1900 mm (in Bombardier Transportation accordance with GM/RT2473) permits a 92nd percentile male to board the train without ducking. The proposed alternative action would result in a minimum door throughway height of 1880 mm, which permits an 87th percentile male to board the train without ducking. The nominal height of the throughway of 1890 mm permits a 90th percentile male to board the train without ducking. Note that neither throughway height permits the standard design case 95th percentile male to board the train without ducking. A door throughway height of 1880 mm permits a >99th percentile female to board the train without ducking. Note that, once the door threshold is passed, the minimum ceiling height is 206 mm. All anthropometric data is taken from People Size 2008 and includes a 40 mm shoe correction. Twenty-nine four-car Class 387/1 Electric It is possible to comply with the The nominal shoegear height setting on the Bombardier Transportation Multiple Units (EMUs) and up to thirty-five requirements by raising the shoegear height, Class 387 is 57 mm ARL in the static tare four-car Class 387/x EMUs (an option on the but this would cause extremely poor contact laden condition. When the two cases of current contract). This deviation is for a between the conductor rail and the GM/RT2149 are applied, this leads to a project requiring authorisation for placing in shoegear. If the Class 387 shoegear is set worst case exceedance of the swept service under the Railways (Interoperability) to comply with GM/RT2149, then the envelope of 13. 2 mm. All Electrostar units Regulations 2011. following risks arise: The shoes will lose fitted with shoegear are subject to deviations contact with the third rail and thus prevent to permit shoegear height setting which the Class 387 from being powered if static infringes the swept envelope defined in and present unreliable operation if running GM/RT2149 Appendix B (see 08/145/DGN dynamically. When running dynamically the and 10/218/DGN). The oldest DC shoes would periodically lose contact with Electrostar fleet (Class 375) has been the third rail which will cause significant running on Network Rail infrastructure for arching and the electrical interference over 10 years. There have been no generated as a result of this would give rise significant issues as a result of the gauge to signalling compatibility issues. infringement. 09/07/2014 N/A RST N/A Current 09/07/2014 N/A RST N/A Current Twenty-nine four-car Class 387/1 Electric Multiple Units (EMUs) and up to thirty-five four-car Class 387/x EMUs (an option on the current contract). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. 09/07/2014 N/A RST N/A Current If the APC receiver is fitted in a location which complies with Clause B10. 3 of GM/RT2149 Issue 3, the manufacturer will not underwrite the performance of the device. There is no alternative supplier for the APC receiver. If the receiver is not positioned in accordance with the manufacturer's requirements, the receiver may not function correctly. Risk Assessment/Safety Justification A fifteen-second door auto-close time was previously permitted for "all passenger vehicles fitted with power operated doors with an autoclose facility" by non-compliance 08/059/NC. However, this non-compliance applies to GM/RT2473 Issue 1. GM/RT2473 has subsequently been up-issued to Issue 2 (a small-scale change not affecting the autoclose timing requirement) and so the noncompliance cannot be applied to the Class 387 units. 08/059/NC states: "The requirement in Clause B7. 10 is the responsibility of the Railway Undertaking and is therefore not within the scope of Railway Group Standards. This clause is a single duty holders responsibility and should be removed from GM/RT2473. A number of deviations are listed against GM/RT2473 Clause B7. 10. The deviations relate to the reduction of the door autoclose facility from 45 seconds to a time determined by the Railway Undertaking. Allowing Railway Undertakings to determine the optimum door auto-close timing for power operated doors would potentially reduce the risk to passengers of slip / trip hazards due to inclement weather conditions. It would also increase passenger comfort by reducing the exposure of the interior of the vehicle to the The alternative actions are not considered to have any adverse effect on safety. The proposed design increases the level of safety, as guards are already familiar with the design, and all passenger doors have to be closed prior to the guard giving the `ready to start' signal. When the guard is in the rear cab and the cab door is open, traction cannot be taken until the cab door is shut as the door interlock circuit will not be made. This APC receiver has been designed to be Bombardier Transportation dimensionally set-up in accordance with the manufacturer's requirements. When the inservice conditions of the bogie (and subsequently APC receiver) are analysed for gauging purposes and compared to the APC gauge as defined in Appendix C of GM/RT2149, both a lateral infringement of 17. 25 mm and a vertical infringement of 24 mm to the gauge line is experienced. Lateral Infringement: GE/GN8573 Guidance on Gauging, Part 4, defines a lower sector vehicle gauge that can be used by vehicle manufacturers to ensure compliance with the relevant Railway Group Standards. After considering all appropriate static displacement and dynamic movements (including tolerances and vehicle maintenance), if the vehicle and components on it are within the limits defined in Part 4 of GE/GN8573, compliance has been demonstrated. When the lateral movements of the Class 387 APC receiver are superimposed against the Lower Sector Vehicle Gauge as shown in Drawing Ref. 100173029, it can be seen that there is no lateral infringement, and hence the lateral infringement of 17. 25 mm against GM/RT2149, Clause B10. 3 is considered Page 37 Deviations Register RGS Number GMRT2461 RGS Issue Number One RGS Title Sanding Equipment Fitted to Multiple Units and on- track Machines Certificate Number 14-083-DEV Title Class 142, 143, 144, 150, 153, 155 and 156 units Sanding in Brake Steps 1 &amp; 2. GIRT7016 Five Interface between Station Platforms, Track and Trains 14-082-DEV Unused Bay Platform at Pontypridd Station - 2.1 Horizontal curvature. GERT8000-SP Four Speeds 14-081-DEV Class 68 Running Light Engine &amp; 2.2 Hauling Short Trains at Permissible Speeds. GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 14-080-DEV Non-fitment of Train Protection and Warning 4.1.3.4 a) System (TPWS) to signals that display the single yellow aspect as part of the nonstandard four-aspect sequence on Great Eastern Main Line (GEML). GKRT0192 Two Level Crossing Interface Requirements 14-079-DEV Chaffers TMOB - Stop boards Close to Crossing. Current Deviations Register as at 09 May 2016 RGS Clause 6.4 2.1.2.2 Scope All Class 142, 143, 144, 150, 153, 155 and 156 units. Nature and Degree The multiple unit fleets within the scope of this application have either step 2 or step 1 sanding enabled, making them noncompliant with Clause 6. 4 of RGS GM/RT2461; either permanent or temporary deviations are in place to permit this. When first fitted, the sanders were initially configured to discharge automatically in emergency brake or manually in step 3 when the driver depresses the sanding button. Since then, a number of temporary deviations have been sought and approved to allow trials of manually sanding in braking step 2 and, more recently, braking step 1, with some permanent deviations now approved. Current status: 10/082/DGN step 2 - Class 150/2 (ATW) - permanent; 11/137/DGN - step 3 and emergency Classes 14X &amp; 153 (all operators) permanent;11/054/DGN - step 2 - Class 156 (AGA) - permanent;13/066/DGN - step 2 class 150 (FGW) - permanent;13/074/DEV step 1 trial - Classes 14X &amp; 153 (FGW, NT, ATW, AGA) - expires 31/07/2014;13/075/DEV - step 1 trial Classes 150, 155 &amp; 156 (FGW, NT, ATW, AGA) - expires 31/07/2015; 13/171/DEV - step 2 trial - Class 153 (LM, AGA, EMT) - expires 31/07/2014. The variation applies to the currently unused Minor - Although the radius of the platform is Bay Platform at Pontypridd Station, Wales. much less than the minimum required, the design will provide compliant stepping distances and safe train dispatch arrangements. This is shown in attached evidence "AFC-Proposed Bay Combined. pdf". Risk Assessment/Safety Justification This alternative provision has been proven to have the following advantages: It supports driver instruction to brake light and early in areas of poor adhesion; The ability to lay sand earlier in the braking curve permits drivers to react earlier to low adhesion, applying sand whilst the wheels are still rotating; Drivers regularly switch between classes of train, standardisation satisfies their desire for consistency. There have been no Wrong Side Track Circuit Failure (WSTCF) attributed to the trials, nor have network Rail Route Asset Managers Signalling reported any other detriments attributable to the change. A survey of Drivers reported widespread positive feedback of the trial. It is the intention of this application to consolidate the trials undertaken to both reduce the number of future applications and standardise the nonWheel Slide Protection (WSP) fleets by means of a permanent deviation which will, in turn, allow for improved sander operation. Neither the step 2 nor the step 1 trials have resulted in an increase in wrong side track circuit failures. The potential for an increase in the risk of this failure mode is therefore considered to be very low. Weighted against the reduced risk of signals passed at Existing unused bay platform at Pontypridd Station is to be brought back into operational use as a Turnback platform. The platform forms one side of the island platform (and is currently fenced off). The horizontal track radius through the usable length of the bay platform is 280 m which is less than 1000 m and therefore does not comply with GI/RT7016, Clause 2. 1. A joint risk assessment workshop "106610-TRT Curvature Joint Risk Assessment-signed. pdf" was undertaken and evidence of this has been included in the derogation application pack. This deviation applies to all light engine and The current RGS was written for the historic This alternative action will reduce rescue short train movements of class 68 situation where locomotives had a braking times for failed locomotive hauled trains on locomotives by the Chiltern Railway capability worse than the coaches they were Chiltern Railways routes and allow better Company Limited ("Chiltern Railways") on hauling. The class 68 is a modern use of available line capacity since a class Network Rail infrastructure. Chiltern locomotive with braking capability better 68 running light engine or hauling a short Railways seeks to permit class 68 than the figure 3 curve of GM/RT2042 (for train can run at the permissible speeds. locomotives running as light engine or use on lines signalled to GK/RT0024 This approach is reasonable since the brake hauling short trains of Mk3 coaches to run at appendix 3) and, therefore, this RGS capability of a class 68 is sufficient for all the permissible line speed. assumption is not appropriate to the class signalled routes on Network Rail 68 locomotive. Complying with the current infrastructure. The class 68 is fitted with RGS results in: Under-utilisation of track automatic sanders and modern Wheel Slide capacity due to reduced running speeds of Protection (WSP) systems to minimise the class 68 running light on Empty Coaching risk of poor rail adhesion. Chiltern Railways Stock (ECS) movements or hauling short drivers will be briefed on this derogation trains. Increased rescue times for rescuing pending planned revision of rule book failed trains with a class 68 locomotive. module SP to permit this. It is notable that Rule Book module SP already recognises that these restrictions do not need to apply for locomotives with enhanced braking (such as class 67s) and this derogation seeks to apply this principle to a new locomotive with similar braking capability. Modified signals on the Up and Down Electric Lines of the GEML between Pudding Mill Lane (Stratford area) and Guide a Park. Signals without TPWS: L331, L935, L365, L377, L381, L383, L412, L414. Details of all the signals affected by Crossrail are given in Table A. Fitment of TPWS at all signals affected by Crossrail that display a single yellow aspect as part of the non-standard four-aspect sequence is considered not reasonable. A number of signals affected have a low Signal Passed at Danger (SPAD) risk (Signal Assessment Tool (SAT) score less than 75) and, considering this low risk, do not justify fitment of TPWS. Complying with the requirements of RGS will increase assets that are required to be implemented and maintained that have no justifiable benefit or purpose. Crossrail works alters a number of signals on a section of the GEML route that makes extensive use of nonstandard four-aspect sequences (see Table A attached). Full compliance to current standard for all signals in this area would require TPWS fitment on most signals on Up and Down Electric Lines, of the GEML. Applicant Organisation Arriva Trains Wales, Northern Rail Ltd, Abellio Greater Anglia, First Great Western, London and Birmingham Railway Limited (trading as London Midland), East Midlands Trains Ltd, First Scotrail Limited Certificate Issue Date 30/07/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date 25/07/2014 Deviation Status Current Network Rail 03/09/2014 N/A INS 09/07/2014 Current The Chiltern Railways Company Ltd 04/07/2014 N/A TOM 24/06/2014 Current 07/08/2014 N/A CCS 26/06/2014 Current 16/07/2014 N/A CCS 26/06/2014 Current Proposed alternative approach means that Network Rail some signals assessed as "low risk" signals that display the single yellow aspect as part of the non-standard four-aspect sequence would not be fitted with TPWS. The intent of TPWS fitment is to mitigate any increase risk of an overrun (SPAD) that arises at a signal as its preliminary caution would also be the preliminary caution for the signal ahead of it. The driver could, therefore, misinterpret the true meaning of the preliminary caution (double yellow) aspect and, as a result, approach the previous signal, which would be at single yellow, at a higher than intended speed with the potential of a SPAD at the signal in question. A Signal Overrun Risk Assessment (SORA) using the Signal Assessment Tool (SAT) has been carried out on all signals on the Electric Lines that will be used by Crossrail services. This assessment has been used to determine the SPAD "risk score" of all signals. The normal "risk score" for carrying out assessment for further mitigations on new or altered signals (that may lead to the fitment of additional TPWS protection), is 150 or greater. It is, however, proposed to reduce this threshold to "risk score" of 75 and apply TPWS as SPAD mitigation. With Chaffers level crossing is located on the Moving the stop board to a compliant With respect to the stop board positions, LNW North Gannow Jcn to Colne (GJC) single line at 25 position of 50 m from the crossing will have changing the operation of the crossing is not miles and 62 chains. Linespeed: 50 mph. an adverse effect on the sighting of the expected to have significant impact on the The crossing is classed as a Train Crew crossing, and increase the barrier down safety profile of the crossing. Trains have Operated Barrier (TMOB). times. It would adversely affect the sighting been stopping at these stop boards for many of the St George's Cross sign in the up years without recorded incident. As there is direction, and the stop board in the down no pull cord to draw up to, trains may stop direction. The attached risk assessment has further from the stop boards, which may fully assessed the change to the risk profile slightly reduce the risk of passing these that would be introduced by configuring the accidentally. The wording on the stop crossing with signs in a position that boards will be altered to remove reference complies with the requirement. to the pull cord, which will be no longer part of the operation of the crossing, and the railway undertakings will be briefed on the change in operation. Removal of the pull cord is designed to mitigate for vandalism to it; members of the public have been smearing the cord with excrement, which is a health hazard. The proposed method of operation removes the need for the driver to contact anything in normal operation, as the crossing is initiated by treadle. Controls monitor the train from strike-in, and these do not allow the driver's white light indication to flash until the train has come to a stand. Page 38 Deviations Register RGS Number GIRT7033 RGS Issue Number Two RGS Title Lineside Operational Safety Signs Certificate Number 14-078-DEV Title Reduced Sized Temporary Speed Restriction Boards for Thameslink. GERT8000-TW5 Five Preparation and movement of trains. Defective or isolated vehicles and on-train equipment 14-077-DEV Door defects on passenger vehicles 6.1 exemption from isolating a vehicle where the first or last sets of passenger doors are locked out of use. GIRT7016 Four Interface between Station Platforms, Track and Trains 14-072-DEV East Ham driver's access walkway footbridge - reduced buffer stop overun risk zone. GMRT2483 One Visibility Requirements for Trains 14-070-DEV Sheffield Tram-Train Visibility (Issue 5). GMRT2400 Five Engineering Design of On-track Machines in 14-068-DEV Running Mode Addition of drain at the base of the fuel tank. 2.4.1.1 To fit a drain plug to the fuel tank, thus having an opening in the fuel tank below the maximum fuel level. For the following TSU vehicles: DR 97501DR 97502 DR 97503 DR 97504DR 97505DR 97506DR 97507DR 97508. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Clause 16. 3 of BS EN 14033-1: 2011 mandates "All openings in the fuel tank shall be above the maximum fuel level". Without a drain plug fitted to the fuel tank, there would not be the facility to routinely remove any condensation build-up. Due to the weather conditions in the United Kingdom and the working routines in which On-Track Machines are operated throughout the winter months, fuel tanks are highly susceptible to condensation contamination. The machine's fuel tank will quite often be manually re-filled from a barrel, which carries a high risk of water contamination. There is a necessity to drain the water from the tank to reduce the risk of damage to the fuel system. Plasser &amp; Theurer have a large number Plasser UK Ltd of machines currently in service on Network Rail infrastructure, compliant to Issue 4 (and earlier versions of GM/RT2400) where fitting a drain to the base of the fuel tank was permitted and has not caused an issue. There are no impacts of the alternative action proposed. GMRT2000 Three Engineering Acceptance of Rail Vehicles Derogation for a Steam Locomotive. Operation of the following preserved steam locomotive from Sheringham East Network Rail / North Norfolk Railway (NNR) boundary to Cromer bufferstops Platform 2, with diversionary route to Cromer Platform 1 for contingency purposes. Note that: There is no run round facility at Cromer; Movements from the NNR must be routed to Platform 2 at Cromer and the route set throughout; There is limited scope for parallel movements - only at Cromer; Sheringham East Network Rail (NR) boundary is protected by rail stop devices vice Train Protection and Warning System (TPWS);Working of single lines by Pilotman is currently implemented for all Cromer to NNR movements London and North Eastern Railway (LNER). B12 class steam locomotive No. 8572 TOPS No. 98472 Painted No. 8572 Class / Power Classification 4 Wheel Arrangement 4-6-0 Maximum Speed 25 mph. For further details, see Appendix 8. It would not be practical to revise the RGS to include steam locomotives, due to their wide diversity of design from modern traction units and the general scarcity of technical information now available to prove their compliance or otherwise. In a number of recent re-issues of RGS, specific exemptions for steam locomotives, shown in the previous issues, have been withdrawn, increasing the number of non-compliances for which derogation has now to be sought. Current Deviations Register as at 09 May 2016 14-066-DEV RGS Clause B6.1, Appendix A Signs AF02m, AF03, AF04m. Risk Assessment/Safety Justification Applicant Organisation Readability of the smaller sized sign has Network Rail been designed to be at least as effective at 60 mph as the standard sized sign at 125 mph which complies with current standards. As this size of font is already suitable for speeds up to 125 mph, the reduced size boards proposed here have better readability than those already approved for use. The proposed smaller signs reduces the risk of a TSR boards being struck by a train and reduces the cost of operational delays by minimising the length of TSR sites. Reduced size signs are proposed for a scope area where the maximum line speed does not exceed 60 mph. Trials have been undertaken to prove that, at line speed 60 mph, the reduced size board is at least as visible as the standard sign at 125 mph, which is currently approved. A reduced sized sign was tested against the requirement for a sign to be readable for four seconds at 60 mph, a distance of 107. 26 m. This will provide a surface area approximately 60% of the size of a normal sign. Class 700 `Thameslink EMU' and all its sub- The following diagram shows the scaled The driver's primary means of egress from First Capital Connect classes. layout of the leading and trailing vehicles, the cab would normally be via the cab doors. including the lockable first class partition However, there may be occasions when they door. [See drawing]. The class 700 does would be required to egress the train via the not have conventional gangway or vestibule passenger doors in the saloon. In an doors between the vehicles; rather, it is open emergency, they would be required to plan, thus allowing quick access from one unlock the partition door to reach the vehicle to the next. Both sub-classes of the standard accommodation area; however, train are fitted with two pairs of deployable this is not considered to be any different to gangway partitions per unit. Compliance accessing the second coach of a train that with the existing rule would result in the has been locked out of use as per the leading or rear three vehicles being locked existing Rule Book requirements. out of use by means of the deployable gangway partitions due to their location within the unit. This would result in the train being taken out of service as continuation would result in excessive dwell times and confusion amongst passengers attempting to alight at subsequent station stops which are adjacent to the locked vehicles. The diagram below demonstrates deployment of the gangway partitions and the consequent impact this would have on the leading or trailing three vehicles if the current Rule Book requirements are applied. [See drawing]. Certificate Issue Date 16/07/2014 Certificate End Date 22/10/2018 Lead SC CCS Lead SC Approval Date 26/06/2014 Deviation Status Current 16/07/2014 N/A TOM 24/06/2014 Current 6.3.1 This application is to request permission to install the new footbridge at the location, being the most practicable and feasible, to provide a safe crossing for the drivers at the end of the walkway. The East Ham driver's access walkway scheme is being proposed to provide a route for train drivers from the train station at East Ham to the C2C depot (and vice-versa). As part of providing a safe crossing for train drivers over the 60 mph Down Main FSS1 line, a footbridge is being proposed over the line. Due to the footprint constraint to implement the crossing over the down main line, the deviation will involve the footbridge being constructed within the overrun risk zone as defined by Clause 6. 3. 1 of GI/RT/7016. The bottom of the stairs for the new footbridge will be 2. 47 m from the face of the buffer stop. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. 29/10/2014 N/A INS 21/05/2014 Current C1.1, C1.2, C2.1, C2.2, C2.3.1, C2.4, C2.5, C3.2.1, C3.3 This application relates to a total of seven The tram train is required to provide lighting Please refer to Appendix 1 attached for the three-car tram-train EMUs: Unit numbers: that complies with the road vehicle lighting justification for the alternative provisions. 399201 - 399207. Vehicle numbers: 99001 - regulations 1989 and ORR RSP2 (Guidance 99007, 99101 - 99107, 99201 - 99207. on tramways). 14/10/2015 N/A Rolling Stock 28/08/2015 Current 05/06/2014 N/A RST 24/04/2014 Current As indicated in Appendix 7 of this West Coast Railway Company 05/06/2014 document. The preserved steam locomotive Ltd is of a type that ran safely over the British railway infrastructure since its introduction in 1928, and continued until its withdrawal from revenue service. The design was an updated version of an earlier design from 1913 (the B12/1). The improved locomotive design had a history of reliable service. The locomotive is intended for Heritage Operation only. In order to achieve compliance with RGS, the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a `heritage' vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. In addition, complying with some elements of RGS would be of limited benefit, due to the specific characteristics of the route to be operated on. N/A Rolling Stock 15/05/2014 Current 6.6.3 and Appendix H Scope The scope of using these Temporary Speed Restriction (TSR) boards covers the geographical area of London Bridge on the Thameslink Programme. The extents of which are: All lines on ELR XTD from Charing Cross to Hither Green; All lines on ELR LBW from London Bridge to Brockley; All lines on ELR LBC from London Bridge to Bricklayers Arms Junction; All lines on ELR CBM from Canon Street to London Bridge; All lines on ELR CSW from Canon street to Metropolitan Junction; All lines on ELR HHH and BMJ from Blackfriars to Metropolitan Junction. The equipment involved is a temporary speed restriction sign of identical construction to those already in use with a reduced surface area. Note that the same design of sign is used for emergency speed restrictions, and this usage is in scope of this deviation. Nature and Degree Due to the complex layout and works around London Bridge, temporary speed restrictions for multiple lines often require a large number of signs to be placed in the same location, which becomes foul of gauge once three or more standard sized signs are placed on top of each other if the currently authorised signs are continued to be used. In order to avoid them being struck by trains, it may be necessary to greatly extend temporary speed restrictions, which is undesirable. Compliance cannot be achieved due to site specific constraints. The risk level of overrun is extremely low since the sand trap is designed to prevent trains from entering the Down Mainline. The Solid State Signalling Interlocking (SSSI) signalling system is designed to prevent wrong routed movements towards the trap point. The severity of non-compliance will be minor. The primary function of the current sand drag and buffer stop is to prevent runaway train units from the depot from entering the Fenchurch Street to Southend (FSS) down main line. With the gradient for this site 1 in 200 away from the buffer stops, it implies a non-braked unit would travel away from the sand drag and buffer stop rather than towards it. There have been no reported emergency uses in the last 40 years, so the likelihood of this happening would be rated as extremely low. In addition, the line speed is listed as 15 mph; however, from the depot yard the starting point is 5 mph with facing spring points, and trap points set in the wrong position would require a major signalling failure allowing for the trains to move in the wrong direction. To achieve this within the footprint available, Network Rail the major component of the new structure (I. e. the substructure of the footbridge) will be located within the zone extending 20 m behind the face of the buffer stop, although the footbridge superstructure is adjacent to the buffer stop. In addition, the access to the footbridge is located within 5 m of the left hand side of the projected centre line of the track approaching the buffer stop, but does not lay parallel to the tracks or buffer stop. Stagecoach Supertram Page 39 Deviations Register RGS Number GERT8014 RGS Issue Number Two RGS Title Hot Axle Bearing Detection Certificate Number 14-065-DEV Title Sheffield Tram Train Bearing Condition Detection. RGS Clause 2.1.1 Scope This application relates to a total of seven three-car Tram Train EMUs: Unit numbers: 399201 - 399207. Vehicle numbers: 99001 99007 99101 - 99107 99201 - 99207. Nature and Degree Risk Assessment/Safety Justification Applicant Organisation BS EN 15437-1: 2009 is not applicable See Appendix (GE/RT8014, Sheffield Tram- Stagecoach Supertram because the tram-train vehicles are fitted Train Bearing Condition Detection, Issue 2). with inboard axle bearings. Clause 2. 1. 1 of GE/RT8014 therefore requires an onboard axle bearing monitoring system to be fitted. The tram-train vehicles are being built to an existing design which, in common with other tram vehicles, does not have any bearing monitoring equipment fitted. Fitting a bearing monitoring system would require redesign of the vehicle and development and validation of onboard systems to incorporate the associated alarm functions. Certificate Issue Date 20/10/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date 03/10/2014 Deviation Status Current GMRT2491 Two Design Requirements for a Driver's Reminder Appliance (DRA) 14-064-DEV Sheffield Tram Train DRA Fitment. 3.1.1 This application relates to a total of seven three-car tram-train EMUs. Unit numbers: 399201 - 399207. Vehicle numbers: 99001 99007, 99101 - 99107,99201 - 99207. The tram-train vehicles are being built to an See Appendix. existing design which, in common with other tram vehicles, does not have a Driver's Reminder Appliance (DRA) system fitted. Integration of the DRA system would require a series of design changes, including further modification to the driving cab environment. Stagecoach Supertram 12/11/2014 N/A RST 03/10/2014 Current GKRT0192 Two Level Crossing Interface Requirements 14-062-DEV Telephones requirements for Automatic Open Crossing, locally monitored, with barrier (AOCL+B) crossing type. 2.10.2.1 All Automatic Open Crossings Locally Monitored (AOCL) that are being provided with addition of half barriers. Network Rail have designated this crossing type as AOCL+B. Network Rail 28/05/2014 N/A CCS 01/05/2014 Current GERT8000-TW5 Four Preparation and movement of trains Defective or isolated vehicles and on-train equipment 14-060-DEV AWS required to be sealed to enter service deviation. 4.2 06/08/2014 N/A TOM 20/05/2014 Current GMRT2130 Four Vehicle Fire, Safety and Evacuation 14-059-DEV Deviation against GM/RT2130 Issue 4 for GSM-R Equipment Installation. All clauses. 11/04/2014 N/A Rolling Stock N/A Current GERT8075 One AWS and TPWS Interface Requirements 14-057-DEV Deviation against the TPWS and AWS requirements of GE/RT8075 Issue One. All clauses. The main impact potentially would be a train Northern Rail Limited entering service with AWS isolated due to the driver either forgetting or choosing to not re-instate the system. Once the AWS is reinstated, there is no impact on safety or any other concerned party. The rule book now permits a unit to run Empty Coaching Stock (ECS) with AWS isolated to a depot. What the rule book does not do is stipulate what sort of distance this journey may be so, potentially, a unit could run a great distance to get to a depot for repair with the AWS isolated in line with GE/RT8000/TW5, Clause 4. 4. What Northern are proposing is a safer system which allows for the fact that the AWS has been made operative prior to the journey commencing. Drivers will receive a full briefing on the deviation and the method of working and details will be recorded on the Northern contingency plan (DOTE). Northern controllers will also be briefed on the specific requirements. The frequency of these events is low, which reduces the amount of times a unit will be required to run with the AWS unsealed. The measures to ensure that the AWS systems are not being misused are: · other drivers who safety check and operate the units in should be reporting any seals that are It is proposed that due to the advanced state Southeastern of the project, this is sufficient to progress to submission and approval. As the GSM-R installation is fully compliant with GM/RT2130 Issue 3, there is no safety implication of this proposed deviation. The 10 new Class 70 locomotives (70801 to The deviation 13/044/DGN against Mk3 TPWS equipment from Thales, which GE Transportation 70810 inclusive) manufactured by General GE/RT8030 Issue 4 to allow the installation GE Transportation plan to install to the newly Electric (GE) in 2013 and 2014 onwards for and usage of the Thales MK3 TPWS built locomotives, is compliant with Colas Rail. This deviation is for a project equipment (which complies with GE/RT8030 GE/RT8030 Issue 2 but not GE/RT8075 requiring authorisation for placing in service Issue 2) was granted to the project. With the Issue 1. Derogation was granted in midunder the Railways (Interoperability) publication of GE/RT8075 Issue 1 to 2013 for this, prior to the publication of Regulations 2011. supersede GE/RT8030 Issue 4, the project GE/RT8075. is seeking to extend the deviation to apply to GE/RT8075 Issue 1. The need for this deviation follows the update by the Department for Transport (DfT) of the Notified National Technical Rule (NNTR) list, whilst the locos development / manufacture is at a very advance stage (the first three locomotives are currently in the UK). As presented in the previous deviation application, production Thales Mk4 TPWS equipment that is validated as being compliant with GE/RT8075 Issue 1 was only recently made available for procurement on the market by Thales. The production of the locomotives had been started by then and had reached final stages, with one locomotive already completed. The integration of the MK4 TPWS equipment would have caused a delay of 4 to 6 months and large integration costs of design and installation. In addition, this delay would have had major ramifications due to other 19/05/2014 N/A CCS 01/05/2014 Current Current Deviations Register as at 09 May 2016 Installation of telephones at all sites being converted to AOCL+B crossings will require additional design and installation exercise, which would delay provision of the barriers at currently open crossings, type AOCL. The impact of adding phones would require signaller ergonomic aspects to be considered. Addition of telephones at level crossings with barriers can affect the signaller's workload, particularly due to nuisance usage of telephones. This can distract signallers from safe operation of railway and other crossings. Workload would need to be assessed to ensure that it will not adversely affect the performance of the signaller. In some cases, an increase of the number of telephones within a control area may lead to the assessment requiring more resources to adequately manage the control area. This additional work would make provision of barriers, which provide the intended safety improvement, less cost effective and may lead to fewer crossings being enhanced. Class 142, 144 and 150/1 Diesel Any unit has the potential for coming to a Mechanical Multiple Unit (DMMU) which stand with the on board AWS equipment employ a traditional isolating handle with directly above the track AWS equipment seal for the Automatic Warning System which results in the AWS having to be (AWS). The deviation is with regards to the isolated to be able to move the vehicle off AWS seal being broken and does not in any the magnet. This more often occurs with the way seek to deviate against the rules for rear vehicle when arriving in stations such AWS isolation. It is assumed that the AWS as Leeds where AWS is used in the will still be operative but for operational platforms for bi-directional working; a driver reasons the AWS seal has had to be broken changes ends and discovers that the vehicle to affect a temporary isolation following the is stood over the magnet. With most train coming to a stand on the AWS track modern units, this results in the AWS being equipment. isolated and a fitter or engineer being required to reinstate the AWS. However, with 142, 144 and 150/1 units, a traditional AWS isolating handle with seal is used. This means that the driver can isolate the AWS, move the unit and then reinstate the AWS, but cannot reseal the AWS handle. We are then left with a unit which has a fully functioning AWS system but which is not permitted to enter passenger service due to the seal being missing and, if we do not have a fitter to hand, we have to then cancel the service or severely delay it. However, this is not a frequent occurrence. Note that we are not looking to change any rules or obtain any deviations to any rules appertaining to the AWS remaining isolated Applicable for Southeastern operated Class The GSM-R Project is at an advanced stage 465, 466, 375, 376 and 395 rolling stock. and demonstrating compliance with the updated standard would delay the project implementation. As a fundamental part of AOCL+B is the existing AOCL, the crossing remains locally monitored by the train driver. Telephones associated with locally monitored crossing types including AOCL+B are not required to be utilised for making emergency calls, and they are of a type that is not self-proving. Their primarily use is to report equipment failure, and request permission to cross in vehicles that need additional crossing time (typically slow freight vehicles, wide loads, and low loaders at risk of grounding). Addition of telephones at locally monitored crossings does very little to improve overall risk management when compared to the addition of the barrier. Since the primary safety operation of the crossing includes monitoring of the crossing area by train driver and trains operated at speed such they can stop short of the crossing if it does not operate correctly, non-provision of phones is not considered to have an impact of crossing safety. Page 40 Deviations Register RGS Number GMRT2130 RGS Issue Number Four RGS Title Vehicle Fire, Safety and Evacuation GMRT2400 Five GMRT2466 Title Advance stage deviation for installation of GSM-R to Plasser &amp; Theurer 09-16 CSM Tampers. RGS Clause All clauses. Scope Applies to the installation of GSM-R system to DR 73105. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Engineering Design of On-track Machines in 14-050-DEV Running Mode Advance stage deviation for installation of GSM-R to Plasser &amp; Theurer 09-16 CSM Tampers. All clauses Applies to the installation of GSM-R system to DR 73105. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Three Railway Wheelsets 14-049-DEV Revised 15-06-2015 Sheffield Tram Train Wheelsets (Mainline Testing). Clauses relating to the use of monobloc wheels: 2.3.1, 2.9.1. Clauses relating to wheel profile: 2.5.2, 2.5.3, 2.6.1, 4.4.1. GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 14-048-DEV Class 700 (Thameslink EMU) - Resistance to Roll-over. 2.4.1.1 b) Class 700/0 (Thameslink EMU eight-car unit) and Class 700/1 (Thameslink EMU twelve-car unit) trailer cars (TOSW_12, TOSW_8, TOS2_12, TOS3_12, TOSLW_12, TOSLW_8). This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 14-047-DEV No Route Indication for Straight Route on EK4157 signal at Rainham, Kent. 5.1.2.4 EK4157 signal on Down Chatham Line approaching Rainham Station. Current Deviations Register as at 09 May 2016 Certificate Number 14-051-DEV Nature and Degree Due to GM/RT2130 Issue 4 being notified as a National Technical Rule (NTR) by the competent authority in the UK, this standard has become applicable to the project following the completion of Global System for Mobile communications for Railways (GSM-R) system development, but prior to it being fitted to DR 73105 (expected to be fitted in March/April 2014). The design of the GSM-R system is compliant with Issue 3 of GM/RT2130. Issue 4 of GM/RT2130 is a fundamental revision of the standard to align it with EN 45545, and demonstrating compliance with Issue 4 would require a complete new assessment. Therefore, checking compliance with the new standard at this advanced stage of the GSM-R project would require significant new assessment which would incur additional cost and delays to the project. In addition, fixed system parameters cannot be modified, resulting in the risk that the GSM-R system may not comply with the new Euronorm. Risk Assessment/Safety Justification The machine will operate with the same level of compliance as all other on-track machines in the UK that have already been fitted with GSM-R. Applicant Organisation dg8 Design and Engineering Ltd Certificate Issue Date 02/05/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date 11/04/2014 Deviation Status Current Due to GM/RT2400 Issue 5 being notified as a National Technical Rule (NTR) by the competent authority in the UK, this standard has become applicable to the project following the completion of GSM-R system development, but prior to it being fitted to DR 73105 (expected to be fitted in March/April 2014). The design of the GSMR system is compliant with Issue 4 of GM/RT2400 and the other relevant RGS that have been excluded by Issue 5 of GM/RT2400. Issue 5 of GM/RT2400 is a fundamental revision of the standard to align it with the prevailing Euronorm EN 14 033 and demonstrating compliance with Issue 5 would require a complete new assessment. Therefore, checking compliance with the new standard at this advanced stage of the GSM-R project would require significant new assessment which would incur additional unjustified cost and delays to the project. This application relates to a total of seven Changing the wheelset to a monobloc tram trains for test operation on mainline design would compromise the project infrastructure between Meadowhall South objective of using a `standard' tram train and Parkgate. Operation is subject to the vehicle, and add significant cost for no completion of infrastructure changes that are practical benefit. The use of a wheel profile essential for compatibility, such as the permitted by GM/RT2466 Issue 3 Appendix raising of check rails by at least 45 mm. The A would result in a fundamental Tram Train units will use wheelsets that do incompatibility with the Sheffield tramway, not meet RGS requirements in two areas: as flange-tip running is necessary to Monobloc wheels will not be used; The negotiate switches and crossings on the wheel profile is not currently permitted, and tramway. will not meet the requirements for flange tip/back blend and flange toe radii. This application does not relate to a project requiring authorisation under the Railways (Interoperability) Regulations 2011. Tram train vehicles are included on the Approved List of Exclusions published by the Department for Transport. The machine will operate with the same level of compliance as all other on-track machines in the UK that have already been fitted with GSM-R. dg8 Design and Engineering Ltd 02/05/2014 N/A RST 11/04/2014 Current 15/06/2015 31/12/2016 RST 13/03/2014 Current 11/04/2014 N/A RST 13/03/2014 Current 01/04/2014 N/A CCS 06/03/2014 Current Class 700 (Thameslink EMU) vehicles are designed as lightweight vehicles with high payload, in terms of a whole life, whole system optimisation. In combination with the conventional high floor level, and consequently high centres of gravity, this design leads generally to disagreement with the 21° criterion of GM/RT2141. Resistance to roll-over induced by overspeeding was calculated according to GM/RT2141 with multi body simulation software. Here, the trailer cars are predicted to infringe the 21° rollover limit of GM/RT2141 Issue 3. In crush-laden condition, the most critical vehicles are predicted not to overturn up to 19. 5° cant deficiency (non-compliant by less than 1. 5°). All pantograph and motor cars comply with 21° limit. The design has been optimised with respect to weight reduction in the new bogie and carbody design. Moreover, the interior layout has been designed to carry more passengers during rush hours. Notwithstanding, measures to lower down the centres of gravity as much as possible were introduced during the vehicle design process: Classes 700/0 and 700/1 have a lower floor height (1100 mm) in comparison with existing suburban rolling stock (1140 mm). This lowers the centre of Rainham Station area is to be resignalled and the track layout remodelled with the provision an additional bay platform. Trains approaching on the Down Chatham line may be routed three ways from the junction signal (EK4157) via main class routes into Rainham Station: Route A(M) - Down Chatham line (straight ahead) into Platform 2 and subsequently onwards towards the coast. Route B(M) - Across to Up Chatham line and into Platform 1 to terminate at a fixed red light. Route C(M) - Across to Bay Platform 0 to terminate. Application of a route indication for the straight ahead route without approach control would not be compatible with the readability performance of the standard alpha-numeric route indicator due to the line speed for the straight-ahead route. Approach control of the signal for the straight-ahead route which is likely to result in a Signal Passed at Danger (SPAD) trap as drivers as would routinely clearing as the train approaches. This is consequently not considered to be a satisfactory arrangement by the signal sighting committee. Therefore, it is considered that the arrangement of providing a standard route indicator with an indication only for the divergent routes The use of resilient wheels fitted with tyres Stagecoach Supertram is consistent with Stagecoach Supertram's existing fleet and normal practice for tram vehicles, and is not considered to have a significant impact on any other party. The use of the revised wheel profile requires existing mainline check rails to be raised by at least 45 mm to ensure compatibility. Network Rail is managing this change to the infrastructure alongside other changes required for tram train operation, and will consider the effect on other rolling stock as part of their engineering change process. IRR Report 81/95 Issue 2, Tram-Train Wheel Profile Design, dated 27/09/2013, documents the design process followed in developing the proposed wheel profile. Safety against derailment and compatibility are considered in this report as part of determining the optimum tram train wheel profile. The impact of a deviation from the 21° First Capital Connect criterion of GM/RT2141 was investigated in detail, and a summary of the findings is described in the document `Deviation Against 21° Limit of GM/RT2141 (Class 700, Thameslink EMU)', [Doc-ID: EN1 A6Z00035402944 000 B]. The investigation shows that, based on the design limits and provision instructions from the RGS (GC/RT5021, GE/RT8075, GK/RT0075), the lower roll-over resistance does not introduce an additional risk of such extent as to be unacceptable. It is shown that the differences in terms of overspeed remain negligible for the worst case. A substantial margin of overspeeding remains between intervention of AWS or TPWS, respectively, and the predicted overturn. Therefore, the possibility of train overspeed (and hence rolling over in a curve) is reduced to a level that is as low as reasonably practicable. Furthermore, the vehicles in question which do not comply with GM/RT2141 are intermediate cars which show a lower sensitivity for wind effects than leading cars complying with the 21° requirement, whether both leading and intermediate cars comply with the GM/RT2142 requirement regarding resistance against overturning in gales. The EK4157 signal has been assessed during Network Rail the signal sighting process as being visible from 800 m away with an essentially straight approach and the line speed on the approach is 80 mph. The divergent routes into platforms 1 and 0 are to be approachcontrolled from red due to the step down in speed required to traverse the divergent routes through the crossovers into the platforms (these shall be restricted to 25 mph). Impact is considered to be minor as both diverging routes from the signal are approach-released from red. Therefore, if the signal is sighted displaying a proceed aspect from a significant distance, the driver will be aware that this corresponds to the straight-ahead route for which a route indication is not provided. The proposed route indication arrangement shall be clearly shown in the signalling notice and other briefing material prepared for operational staff associated with the commissioning of the new signalling system including for Southeastern's train crew. In the longer term, following the commissioning of the new signalling, an appreciation of the route indication arrangements at this signal by drivers shall be maintained through the route knowledge management process. As the Page 41 Deviations Register RGS Number GKRT0075 RGS Issue Number Two RGS Title Lineside Signal Spacing and Speed Signage Certificate Number 14-045-DEV Title Automatic Warning System (AWS) position for LTN00538 permissible speed warning indicator located approaching Forest Gate Station. RGS Clause 3.3.8.2 a) GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 14-044-DEV OFF indicator legend at Maidstone West Station Platform 2. 2.4.5.2 Table 16 GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 14-043-DEV OFF indicator legends at Clapham Junction Station Platform 17. 2.4.5.2 Table 16 GKRT0192 Two Level Crossing Interface Requirements 14-041-DEV Signal T869 in close proximity to Billingshurst Level Crossing. 2.1.1.3 a) Current Deviations Register as at 09 May 2016 Scope AWS position for LTN00538 permissible speed warning indicator located on the Up Electric line of the GE route from Liverpool Street to Shenfield, approaching Forest Gate station, at 5M 38CH. Nature and Degree Requirement for AWS at permissible speed warning indicators is specified as exactly 180 m in GK/RT0075. Given existing signal spacing in the area is circa 300 m, compliance is not possible without moving signals or putting signal AWS at less than normal 180 m or move the permissible speed warning indicator without compromising one or more of the other clauses in GK/RT0075: 3. 3. 8. 1. - The AWS magnet shall: b) be positioned not less than 4 seconds running time from any other AWS equipment. c) not be positioned between any other AWS equipment and its associated signal, board or indicator. 3. 3. 5. 1 a): The board must be positioned as close as practicable to the longest deceleration distance from the PSR. 3. 3. 8. 1: An AWS magnet shall be provided on the approach to all permissible speed warning indicators provided to satisfy the criteria set out in 3. 3. 1. 4. 3. 3. 5. 1 b): The board must not be positioned between a signal and its AWS. To position the AWS at less than 180 m is considered the least onerous to break. Train Operating Companies (TOCs), Freight Operating Companies (FOCs) and Network Rail agree that positioning the permissible speed warning indicator's AWS OFF indicator at Maidstone West Platform 2 As a consequence of bi-directional for Signal EK4753. ELR PWS1, 42 miles 36 signalling being installed at Maidstone West chains. Platform 2, an OFF indicator with a legend needs to provide an indication of the direction in which it applies. Maidstone West station, although a through station, is located at a transition point in line designations and Engineers' Line References (ELRs) such that all trains leaving the station are effectively "Up" trains, regardless of their direction of travel (the line designations change at the platform starting signal to which the OFF indicator refers). Only directional information permitted is the text "UP" or "DN". Compliant OFF indicator means that the "UP" or "DN" text would cause confusion to the platform staff giving with consequent risk of unauthorised movements taking place. Confusion to the dispatch staff increases likelihood of start away Signal Passed at Danger (SPAD), thus increasing SPAD risk on EK4753 and EK4750. Risk Assessment/Safety Justification Applicant Organisation Impacts are considered minor. The AWS Network Rail will still be in position in line with requirements of GE/RT8075: 2. 1. 8. 1. allows a signal AWS to be positioned a minimum of 3 seconds from the signal, and2. 1. 8. 2. h) permits a signal sighting committee (SSC) to recommend an alternative position and this achieves a reduction in risk. Drivers use signal AWS to assist with stopping at signals so a standard 180 m distance is import; no equivalent use is made of AWS at permissible speed warning indicator. GN158 in GK/GN0675 implies variation is permitted, but wording in GK/RT0075 means a deviation is still required. GN158 states: "GE/RT8035: Automatic Warning System (AWS) permits the distance from the AWS magnet to the permissible speed warning indicator to be reduced to a minimum of 3 seconds running time. This accounts for the 1 second delay after passing over the permanent magnet before the AWS equipment gives a warning indication and provides the driver with a minimum of 2 seconds to respond to the AWS indication, observe the speed sign and acknowledge the warning. " Certificate Issue Date 01/04/2014 Certificate End Date N/A Lead SC Control Command and Signalling Lead SC Approval Date 06/03/2014 Deviation Status Current The directional identifier proposed has been Network Rail selected so as to use a distinctive and recognisable abbreviation of the next principal station name in the direction of travel, which all operating staff in the area would be aware of as part of the route/local knowledge necessary for the safe and effective execution of their duties. Proposed directional legend of the OFF indicator will provide a clear identification of the direction of the movement which has been authorised. Proposed legends present a lower risk than a standard legend, as they will not cause confusion as to the direction of an authorised train movement. The proposed legend shall be clearly shown in the signalling notice and other briefing material prepared for operational staff for the Railway Undertakings associated with the commissioning of the new signalling system, including for Southeastern's train crew and platform staff. In the longer term, following the commissioning of the new signalling, an appreciation of the meaning of the nonstandard legend by operational staff shall be maintained through the route/local knowledge applicable to their role. 01/04/2014 N/A CCS 06/03/2014 Current Proposed alternative identifiers have been Network Rail selected to use distinctive characters that minimise the risk of confusion between legend. They are also both recognisable abbreviations to local station names that all operating staff in the area are aware of as part of their current route/local knowledge necessary for the safe and effective execution of their duties. Proposed directional legend of the OFF indicator will provide a clear identification of the direction of the movement which has been authorised. Proposed legends present a lower risk than standard legends as they will not cause confusion as to the direction of an authorised train movement. Legends will be shown in the signalling notice and other briefing material prepared for operational staff associated with the commissioning of the new signalling equipment. All will be briefed to the Train operating Company (TOC) and Freight Operating Company (FOC) drivers and platform dispatch staff. In the longer term, following commissioning of the new signalling equipment, an appreciation of the meaning of the non-standard legend by operational staff shall be maintained through the route/local knowledge applicable to their role. Signal T869 at Billingshurst Station is In order to comply with the RGS The principal risk that is mitigated by the Network Rail positioned 15m from the Level Crossing, but requirement, the signal would have to be level crossing controls is that arising from is only utilised as a Turn Back Signal and positioned at least 25 m from the crossing. Signal Passed at Danger (SPAD). The thus non-approached. The signal has been Standage for trains in the normal direction is signal is not normally approachable by trains positioned in parallel to the main running sufficient for trains to occupy the whole as there is no wrong direction signalling. signal T867 which has been configured so platform. This in turn would mean that trains The signal has good sighting due to the that movement authorities towards the stop reversing at Billingshurst would have to pull position of the train at its allocated stopping signal are only displayed when the level forward in normal direction of travel to a position and architecture of the station, and crossing is closed to road traffic. point that allows the other end of the train to also for trains approaching under perturbed be positioned to view signal T869. The working without being signalled. TPWS signal and its base would have to be reTSS is fitted, principally to mitigate the installed in the compliant position. SPAD risk associated with the conflict on the cross-over, but has a secondary mitigation role to arrest a SPAD and therefore minimise the potential risk of collision on the level crossing. 01/04/2014 N/A CCS 06/03/2014 Current 25/03/2014 N/A CCS 06/03/2014 Current OFF indicators at Clapham Junction Station As a consequence of platform extension Platform 17 for Signals VC600 and VC607 works, OFF indicators are needed on signals. Route Kent/Sussex, ELR TTB1, 2 Platform 17 at Clapham Station. Due to a miles 57 chains. curve through the platform, which continues once the platform is extended; the signal VC600 mounted on the left hand side cannot be seen from the platform by the dispatch staff. Signal VC607 cannot be seen due to the passenger over-bridge restricting dispatch staff visibility of the signal. Existing Platform 17 Up and Down directions are the opposite to the rest of the platforms at the Clapham Junction (Up to Wandsworth, Down to Kensington). Trains depart from Platform 17 via the Up West London, either towards the Down West London line or the Down Brighton Slow line. This means all trains depart in a down direction. Only directional information permitted is the suffix (or prefix) "UP" or "DN". A compliant OFF indicator means that the "UP" or "DN" text would cause confusion to the platform staff with consequent risk of unauthorised movements taking place. Confusion to the dispatch staff increases likelihood of start away Signal Passed at Danger (SPAD), thus increasing SPAD risk on VC600 and VC607. Page 42 Deviations Register RGS Number GERT8075 RGS Issue Number One RGS Title AWS and TPWS Interface Requirements Certificate Number 14-038-DEV Title TPWS receiver position on Class 68 UK Light locomotive. RGS Clause 3.2.1.3 Scope UK Light locomotives manufactured by Vossloh España S. A. (Class 68) (limited to a maximum of 41 units due to stage IIIA engine). This application is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GERT8000-T3 Three Possession of a running line for engineering 14-037-DEV Revised work 02-09-2015 LNE Route - 'Flexible Train Arrival Point' 2.2, 9.7 National. GERT8000-HB12 Two Duties of the engineering supervisor (ES) 14-036-DEV LNE Route - 'Flexible Train Arrival Point' 3.2 National. The current RGS requires that, when possession is taken around a train, it is done so whilst the engineering train is standing at a signal which is being held at danger. This means the High Output (HO) trains are positioned away from their planned start-ofwork site, and between 10 and 20 minutes of lost production occur at the start of work whilst the train is positioned in the correct place to start work. This can equate to an estimated 50,000 Pounds Sterling in lost production. GERT8000-HB11 Two Duties of the person in charge of a possession (PICOP) 14-035-DEV LNE Route - 'Flexible Train Arrival Point'. 4.2 National. The current RGS requires that, when possession is taken around a train, it is done so whilst the engineering train is standing at a signal which is being held at danger. This means the High Output (HO) trains are positioned away from their planned start-ofwork site, and between 10 and 20 minutes of lost production occur at the start of work whilst the train is positioned in the correct place to start work. This can equate to an estimated 50,000 Pounds Sterling in lost production. GIRT7016 Four Interface between Station Platforms, Track and Trains 14-032-DEV Finsbury Park Station Platform 3 (old Platform 1) - platform height. 3.1.1 Platform Height Finsbury Park to Alexandra Palace Capacity The platform height within the existing, Improvements Project. Finsbury Park interim and final stages exceed the Station Platform 3 (old Platform 1). maximum allowable of 915 mm, the worst case being 952, 952 and 944 mm in the existing, interim and final stages respectively. These are 37, 37 and 29 mm greater than the 915 mm target height. The platform within this area of non-compliance cannot be lowered due to the construction of the platform (steel deck with GRP surface between Ch 4120 and 4150). There is no action plan being put in place due to the disproportionate costs associated with the magnitude of work to bring the steel deck platform area into conformity with the standard. Current Deviations Register as at 09 May 2016 Nature and Degree The Vossloh Class 68 (UK Light) project is already at an advanced stage, with the first units already built and the lead unit in the UK for commissioning. The project was previously being assessed against GE/RT8030 Issue 4 as amended by deviation 12/116/DGN which has already been granted. To future proof further locomotive builds and to comply with the latest list of NNTRs published by the UK Department for Transport (DfT) in midOctober, Vossloh have decided to demonstrate compliance against GE/RT8075 Issue 1 rather than GE/RT8030 Issue 4. As such, a new/updated deviation against Clause 3. 2. 1. 3 of GE/RT8075 Issue 1 is required, covering the same technical requirements as derogation 12/116/DGN against GE/RT8030 Issue 4. The UK Light design is based on the existing EuroLight locomotive. The arrangement of the UK Light locomotive components is such that it is impossible to fit the Train Protection and Warning System (TPWS) antenna no further than 2. 3 m behind the leading wheelset. This is due to: The lack of available space behind the leading wheelset. Any installation of the TPWS receiver 2. 3 m behind the leading axle will The current RGS requires that, when possession is taken around a train, it is done so whilst the engineering train is standing at a signal which is being held at danger. This means the High Output (HO) trains are positioned away from their planned start-ofwork site, and between 10 and 20 minutes of lost production occur at the start of work whilst the train is positioned in the correct place to start work. This can equate to an estimated œ50,000 in lost production. Risk Assessment/Safety Justification Applicant Organisation Certificate Issue Date The requirement to position the TPWS Vossloh España S.A. on behalf 25/03/2014 receiver behind the leading axle was of, Direct Rail Services Limited introduced to avoid spurious operation of TPWS caused by interference from TI21 track circuits. A number of derogations have previously been granted against the same technical requirement in GE/RT8030 Issue 4, which permit the TPWS antenna to be located ahead of the leading axle (for instance derogations 10/045/DGN, 06/105/DGN and 05/032/DGN). On this basis, it is considered that the risk associated with the TPWS antenna being located ahead of the leading axle is controlled. The new location avoids the technical and geometrical problems of the original position (available space and EMC emissions). Certificate End Date N/A Lead SC CCS Lead SC Approval Date 06/03/2014 Deviation Status Current The HO train would be stopped at the FTAP at the exact location of work (which would ordinarily be distant from a signal) and possession would be taken around the train at that point. It is estimated that this would allow 10 to 20 minutes of additional production time on every HO shift. This could equate to an estimated œ50,000 increase in production each shift. As part of the initial study, a risk assessment has been performed, involving stakeholders from route operations, National Delivery Service (NDS), Freightliner, RSSB and HO Operations. As possession will not be granted until the HO train is at the FTAP, then no personnel will be on or near the line whilst the train is in motion. There is a risk that the HO train overshoots the FTAP. Threats relating to this have been assessed and mitigated, principally by driver briefing and the use of countdown markers on the approach to the FTAP (see FTAP proposal document). The HO train would be stopped at the FTAP at the exact location of work (which would ordinarily be distant from a signal) and possession would be taken around the train at that point. It is estimated that this would allow 10 to 20 minutes of additional production time on every HO shift. This could equate to an estimated œ50,000 Pounds Sterling increase in production each shift. As part of the initial study, a risk assessment has been performed, involving stakeholders from route operations, National Delivery Service (NDS), Freightliner, RSSB and HO Operations. As possession will not be granted until the HO train is at the FTAP, then no personnel will be on or near the line whilst the train is in motion. There is a risk that the HO train overshoots the FTAP. Threats relating to this have been assessed and mitigated, principally by driver briefing and the use of countdown markers on the approach to the FTAP (see FTAP proposal document). The HO train would be stopped at the FTAP at the exact location of work (which would ordinarily be distant from a signal) and possession would be taken around the train at that point. It is estimated that this would allow 10 to 20 minutes of additional production time on every HO shift. This could equate to an estimated 50,000 Pounds Sterling increase in production each shift. As part of the initial study, a risk assessment has been performed, involving stakeholders from route operations, National Delivery Service (NDS), Freightliner, RSSB and HO Operations. As possession will not be granted until the HO train is at the FTAP, then no personnel will be on or near the line whilst the train is in motion. There is a risk that the HO train overshoots the FTAP. Threats relating to this have been assessed and mitigated, principally by driver briefing and the use of countdown markers on the approach to the FTAP (see FTAP proposal document). A snapshot has been taken from Track Design Handbook NR/L2/TRK/2049 Issue 12 to be used as a visual aid and illustration purposes showing the dimensions relating to the recess value. (See attached documents for application with diagram on). A full stepping analysis has been carried out to all passenger stock and is compliant to group standard. There is no worsening of the platform heights to its current position today. Network Rail 02/09/2015 31/12/2017 Traffic Operation and Management 28/07/2015 Current Network Rail 02/09/2015 31/12/2017 TOM 28/07/2015 Current Network Rail 02/09/2015 31/12/2017 Traffic Operation and Management 28/07/2015 Current Network Rail 07/04/2014 N/A INS 05/03/2014 Current Page 43 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 14-031-DEV Title Winchmore Hill Platform 2 - reduced width of recess. RGS Clause 11.1.4.1 Scope Winchmore Hill Platform 2, Hertfordshire, UK Nature and Degree Winchmore Hill Platform 2 (140 m in length / reduced recess will be over a 10 m section): If measured from the coping stone face, the recess will be reduced to a minimum of 258 mm, 42 mm less than the minimum standard requirement. There are no physical track works currently planned at Winchmore Hill. Thus, technically, the recess is not reduced by adjustment of the coping stone. When measuring the dimension from the running edge of the nearest rail, the X dimension of 730 mm dimension increases due to the setback of the coping stone. A full stepping analysis has been carried out against existing track / existing platform and against final platform/ theoretical track. As a result of the coper lifts at the London end of the platform, the stepping will be improved and, thus, create a fully compliant platform for stepping dimensions. Risk Assessment/Safety Justification Applicant Organisation Winchmore Hill - Platform 2, Down Network Rail Hertford: Throughout the length of the 140 m platform, there is an existing compliant (Z1) recess value in excess of the 300 mm requirement. The existing dimensions are minimum 304 mm and maximum 331 mm. Due to the required adjustments of the copers by means of setting back or trimming the coper face, there is a small 10 m section between Ch260m and Ch270m, whereby the recess value is reduced by 47 mm. The adjusted dimensions are minimum 258 mm and maximum 288 mm. (Please refer to general arrangement drawing). There is a theoretical smoothing track alignment submitted in support of the Civil Engineering design to provide assurance that the new profile of the platform face will be compliant to the future track realignment scheme. Below is a snapshot taken from Track Design Handbook NR/L2/TRK/2049 Issue 12, for illustration purposes, showing the minimum dimension of the recess value (*a=300 mm). (See attached document for application with diagram on). Certificate Issue Date 07/04/2014 Certificate End Date N/A Lead SC INS Lead SC Approval Date 05/03/2014 Deviation Status Current GIRT7016 Four Interface between Station Platforms, Track and Trains 14-030-DEV Oakleigh Park Station Platform 1 and 2 reduced platform width at mid-platform fencing. 6.2.2 Oakleigh Park Station Platform 1 and 2. Station Capacity Planner, Fire Safety Engineer, Route Asset Manager Buildings and Route Safety Improvement Manager have all approved the proposed fencing design and support this deviation. Support is also present from the Customer Service Safety Business Partner for First Capital Connect (FCC) who runs the station. Extensive design review has taken place from the Station Capacity Planner, Fire Safety Engineer, Route Asset Manager Buildings and Route Safety Improvement Manager who all support the design and this derogation application. The station facility owner FCC also supports this derogation via the Customer Service Safety Business Partner. Finally, it is very similar to previously granted derogations for suicide mitigation fencing at Southall (Certificate No 12/198/DGN), Hayes and Harlington (Certificate No 12/231/DGN) and Goring and Streatley (Certificate No 13/089/DEV). For reasons of fire safety and pedestrian flow, this is the best option for the fenceline to take. Network Rail 02/05/2014 N/A INS 05/03/2014 Current GIRT7016 Four Interface between Station Platforms, Track and Trains 14-029-DEV New Southgate Station Platforms 3 &amp; 4 - 6.2.2 reduced platform width at mid platform fencing. New Southgate Station Platforms 3 &amp; 4. New fencing would be introduced to prevent suicide. The fenceline would follow an existing non-compliance and cannot comply for pedestrian flow and fire safety reasons. The existing outer edge of the stairs has 2720 mm clearance, a non-compliance; therefore, the fenceline cannot be placed further from the platform edge and is not making the situation worse. Network Rail 09/04/2014 N/A INS 05/03/2014 Current GIRT7016 Four Interface between Station Platforms, Track and Trains 14-028-DEV Brookmans Park Station - mid platform fencing. 6.2.2 Brookmans Park Station. The Fire Safety Engineer, Station Capacity Planner, Route Asset Manager Buildings and Route Safety Improvement Manager have all extensively checked and approve the designs and derogation. The derogation is also supported by the Customer Service Safety Business Partner for First Capital Connect (FCC) who manages the station. They are confident that it does not import unacceptable risk to any station users. Fire Safety Engineer, Station Capacity Planner, Route Asset Manager for Buildings and Route Safety Improvement Manager have been involved in the development and checking of designs, which they approve, and support this derogation application. The FCC Customer Service Safety Business Partner supports this application for derogation. For reasons of fire safety and pedestrian flow, this is the best possible option for our fenceline to take. Network Rail 08/04/2014 N/A INS 05/03/2014 Current GIRT7016 Four Interface between Station Platforms, Track and Trains 14-024-DEV Paddock Wood Station, Platform 2 Reduced platform width and column in overrun risk zone. 6.2.2 and 6.3.1 Paddock Wood Station Platform 2. ELR XTD/PWS1. A major rebuild of the station canopy would be required. Oakleigh Park Station - approximately 8 m of the proposed fenceline, at the bottom of the stairs to platform 1/2, has a platform clearance of 2600 mm to the Up Fast Side. The minimum clearance in accordance with GI/RT7016 is 3000 mm. The proposed fenceline directly replaces an existing fence at the base of the stairs therefore is not making the arrangement worse. The final 4 m of the proposed fenceline to the south end of Platform 2 is also non-compliant. This section of fence is proposed at 2500 mm clearance from the Up Fast platform edge (GI/RT7016 requires 3000 mm). This would be the installation of new fencing which, where the derogation is needed, would not be installed until this derogation were approved. This new fencing is to save lives Oakleigh Park which has seen three instances of suicide from the platform edge over the last five years. The Peterborough to London Kings Cross stretch of the East Coast Main Line has had 30 mid-platform suicides and many others from people walking off platform ends (which has been mitigated through platform end gating here). It is the worst area for suicide on our route and plans are in place to improve defences at every station in this area. The introduction of 247 metres of 1. 4 m high grey galvanised mid-platform fencing at the location is intended to restrict the access by passengers to the fast line edge of the track so as to discourage suicide, access where it is necessary (e. g. in an emergency stopping service) is maintained through the introduction of 3 m wide gates which will not be locked and clearly identified by signage. The deviation for New Southgate is for 5 m of the proposed fenceline, at the bottom of the stairs to Platforms 3 &amp; 4, which has a platform clearance of 2720 mm to the Down Fast Side. The minimum clearance in accordance with GI/RT7016 is 3000 mm. The introduction of this fencing is intended to save life at a station where four people have intentionally taken their lives in the last five years. There is an existing non-compliance which we intend to extend - this is very similar to approved derogations for Southall (Certificate No 12/198/DGN), Hayes and Harlington (Certificate No 12/231/DGN) and Goring and Streatley (Certificate No 13/089/DEV). Pedestrian flow and fire safety analysis have been performed at the station and on these designs. They have been approved as not making the situation worse and not representing any Brookmans Park Station: As part of fatality mitigation works to combat railway suicide which, over the last 5 years and year to date, has resulted in 281 deaths on the London North Eastern (LNE) and East Midlands Routes, Network Rail has decided to utilise the guidance of the Network Rail National Suicide Prevention Steering Group to implement mid-platform fencing at a number of stations. The national guidance was issued following the implementation of midplatform fencing at 10 stations, including Southall (Certificate No. 12/198/DGN), Hayes and Harlington (Certificate No. 12/231/DGN) and Goring and Streatley (Certificate No. 13/089/DEV), which were granted deviations. The introduction of 247 metres of 1. 4 m high grey galvanised mid platform fencing at the location is intended to restrict the access by passengers to the fast line edge of the track so as to discourage suicide, access where it is necessary (e. g. in an emergency stopping service) is maintained through the introduction of 2. 5 m wide gates which will not be locked and clearly identified by signage. Where the fenceline stops before the platform end, hatching and signage will be provided to direct passengers to the correct side of the The canopy cannot be supported without the positioning of a column within a buffer overrun zone and at a sub-standard clearance from the platform edge. Network Rail 11/04/2014 N/A INS 05/03/2014 Current Current Deviations Register as at 09 May 2016 Page 44 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 14-023-DEV Title RGS Clause Paddock Wood Station, Platform 1 6.2.2 reduced platform width at replaced columns. GMRT2100 Five Requirements for Rail Vehicle Structures 14-020-DEV Advanced stage deviation to GM/RT2100 Issue 5 for Class 68 UK Light locomotive based on the already granted deviation 12/115/DGN that includes GM/RT2100 Issue 4. GMRT2130 Three Vehicle Fire, Safety and Evacuation 14-019-DEV Fire compliance of Rollers on Balfour Beatty 2.9.1.1 a) Overhead Line Electrification (OLE) Modules. This deviation applies to Balfour Beatty OLE Installation Modules fitted to wagons VTG 95382 and VTG95385. GMRT2000 Three Engineering Acceptance of Rail Vehicles 14-017-DEV Derogation for a Steam Locomotive. 6.6.3 and Appendix H Operation of the following preserved steam locomotive on all lines, as agreed by the Network Rail Acceptance Body (NRAB) and subsequently by the Licensed Operator. SR Merchant Navy class steam locomotive No. 35018 `British India Line'. TOPS No. 98818 Painted No. 35018 Class / Power Classification 8P Wheel Arrangement 4-6-2 Maximum Speed 75 mph. GMRT2161 One Requirements for Driving Cabs of Railway Vehicles 14-016-DEV Revised 02-07-2014 Use of transportable GSM-R equipment on steam locomotives registered to operate on Network Rail. 7.2.1 (j) GWR steam Rail Motor Class: Steam Rail Motor Original number: 93 TOPS number: 99093 Max speed (mph) Forward/reverse: 25/25 King Edward II Class: King class Original number: 6023 TOPS number: 98823 Max speed (mph) Forward/reverse: 75/45 Pendennis Castle Class: Castle class Original number: 4079 TOPS number: 98779 Max speed (mph) Forward/reverse: 75/45 Lady of Legend Class: Based on Saint class Original number: 2999 TOPS number: 98499 Max speed (mph) Forward/reverse: 75/45 County of Glamorgan Class: Based on 1000 class Original number: 1014 TOPS number: 98614 Max speed (mph) Forward/reverse: 75/45. Current Deviations Register as at 09 May 2016 Scope Paddock Wood Station Platform 1. ELR XTD/PWS1. Part 2 Part 3 (except 3.3.3) Part 4 Part 5 Class 68 UK Light locomotives (except 5.4 and; 5.5) Part 7 Part 8 (except manufactured by Vossloh España S. A. 8.1.6, 8.1.7, 8.1.8, 8.3.1.2, 8.3.1.3 and 8.3.2.3) Clauses 9.1.1.1 to 9.1.1.3 and 9.2.1, 9.2.3 and 9.2.4. Nature and Degree It is proposed that two new columns are installed to support the existing canopy upon removal of the existing footbridge, which currently provides support. The columns are to match the existing double column arrangement. The column nearest the platform will be 1. 733 m from the platform edge. Risk Assessment/Safety Justification The canopy modification support design for Platform 1 does not comply with the requirements of Railway Group Standard GI/RT7016 Clause 6. 2. 2. The clearance from the proposed outer canopy support column is 1. 733 m, less than 2. 5 m required. The design has been developed to match the existing arrangement of the canopy support structure, which do not comply with this standard. Compliance with the standard would require a column positioned 2. 5 m from the platform edge which would not align with the existing canopy support columns and by doing so would impede sighting along the platform. This deviation is for a project requiring There is no predicted adverse impact authorisation for placing in service under the arising from continued use of the current Railways (Interoperability) Regulations 2011. standard. The Class 68 UK Light project is already in an advanced stage, with the firsts units already built and expected to arrive for commissioning in the UK in late January. The project is being assessed against GM/RT2100 Issue 4 as amended by deviation 12/115/DGN which has already been granted. As GM/RT2100 has been upissued to Issue 5 since derogation 12/115/DGN was granted, Vossloh need to apply for this deviation to meet the Office of Rail Regulation (ORR) requirement for authorisation to place in to service against the latest NNTR list. The UK Department for Transport (DfT) published an updated list of NNTRs in mid-October 2013, which replaces GM/RT2100 Issue 4 with GM/RT2100 Issue 5. Reassessment work would be necessary to demonstrate compliance with GM/RT2100 Issue 5 at this late stage in the project. This previous deviation 12/115/DGN remains in place and is not withdrawn as a result of this further deviation. There are no changes to the standards requirements that are the subject of this application between Issues 4 and 5 Surfaces and materials shall have fire The alternative provisions detailed in properties as set out in Appendix A. The Section 11 (Proposed alternative provisions) materials used for the rollers and tensioning will ensure that, when possible sources of drums on the tensioning and access ignition are present on the machines from modules have been selected specifically for electrical systems and combustion engines, their frictional and wear characteristics trained operators are present, equipped with which are integral to the performance of fire extinguishers and able to address any each module's intended function. The issues with the non-compliant materials. design of the modules and their They will also ensure that this condition will performance has been developed and only occur when the machine is removed evolved over a number of years. Altering from the operational railway by being within the materials would negate the experience a possession. that has been gained and jeopardise the performance of the modules. Materials used on the contact surfaces of rollers and tension drums on the modules (listed below) do not meet the materials requirements of the standard (minimum limiting oxygen index of 28%). The drums and rollers have steel centres/axles and are mounted in steel frames. Grooved plastic pads on the tensioner drums, rollers on the tensioner' Performance: Oxygen index (ISO 4589-1/-2) 25%; HB/HB according to UL 94 (3/6mm thickness). Rollers on the drum stands and main masts (Ertalon 66 SA black) Performance: Oxygen index (ISO 4589) 26%; HB/HB according to UL 94 (3/6mm thickness). Rollers at either end of the It would not be practical to revise the RGS to As indicated in Appendix 7. The preserved include steam locomotives, due to their wide steam locomotive is of a type that ran safely diversity of design from modern traction over the British railway infrastructure since units and the general scarcity of technical its introduction in May 1945 and continued information now available to prove their until its withdrawal from revenue service. compliance or otherwise. In a number of The locomotive had a history of reliable recent re-issues of RGSs, specific service. The locomotive is intended for exemptions for steam locomotives shown in Heritage Operation only. In order to achieve the previous issues have been withdrawn, compliance with RGS, the cost would be increasing the number of non-compliances prohibitive and such engineering change for which derogation has now to be sought. would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. Due to its limited application solely to British Impacts on company: Improved flexibility steam locomotives operating on Network rail and reduced costs. Improved security as controlled infrastructure, the deviation does equipment can be securely locked away not require authorisation under the Railways when not in use. Impacts on affected (Interoperability) Regulations 2011. The parties: Impacts already covered in deviation would apply to steam locomotives deviation 12/032/DGN. Impact on the crew: registered to operate on Network Rail and Footplate crew have improved visibility of will permit the use of a restrained the equipment over the normal fixed transportable Global System for Mobile installation. Impact on the safety of the communications for Railways (GSM-R) as railway system: No increased risk over that an alternative to a permanently installed accepted in deviation 12/032/GDN. system. The deviation is to be implemented Technical compatibility: Fully compatible by the Railway Undertaking where a limited with the GSM-R system. Cost and service number of operations and geographical performance: Reduced cost of installation. scope might impose disproportionate effort Improved availability as equipment can be in order to gain the benefits of fitting a easily swapped. Procedures will be permanently fixed system. As stated in produced covering the installation, derogation 12/032/DGN, it is not practicable operation, maintenance and repair of the to fit the GSM-R equipment within reach of equipment, as is the case for fixed the driver's position on a steam locomotive installations. Attachments: Appendix B due to the restricted space that is available User instruction for transportable GSM-R; and the temperatures that potentially occur Appendix C - Technical specification of the in the area immediately beside the driver, equipment. It should be noted that steam which are beyond the known reliability range locomotives that operate on the national rail of the GSM-R equipment. The derogation network are: Registered, certified and allows the equipment to be sited behind the maintained to operate safely; Limited to a driver due to the fact that there is more than maximum of 15,000 miles per annum; Have, one person on the footplate and, therefore, as a minimum, a second person in the cab there are additional trained and competent (fireman) that are trained and competent to Applicant Organisation Network Rail Certificate Issue Date 08/04/2014 Certificate End Date N/A Lead SC INS Lead SC Approval Date 05/03/2014 Deviation Status Current Vossloh España S.A. on behalf 31/01/2014 of, Direct Rail Services Limited N/A INS N/A Current Balfour Beatty Rail Ltd 03/03/2014 N/A RST 14/02/2014 Current West Coast Railway Company 06/03/2014 Ltd N/A RST 14/02/2014 Current West Coast Railway Company 02/07/2014 Ltd N/A RST N/A Current Page 45 Deviations Register RGS Number GMRT2130 RGS Issue Number Four RGS Title Vehicle Fire, Safety and Evacuation Certificate Number 14-015-DEV Title Advanced stage deviation to GM/RT2130 Issue 4 for Class 68 UK Light locomotive. RGS Clause All clauses. Scope Class 68 UK Light locomotives manufactured by Vossloh España S. A. GMRT2484 Two Audibility Requirements for Trains 14-014-DEV Warning horns Vossloh España S.A - Class 68 UK Light locomotive. All clauses 41 x Class 68 UK Light locomotives manufactured by Vossloh España S. A. GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 14-008-DEV TJ30/37 Signal - use of unrestricted aspect sequence for junction signalling controls 5.2.2.1 a) GKRT0192 Two Level Crossing Interface Requirements 14-007-DEV PT249 and PT449 signals in the proximity of 2.1.1.3 Llanelli East level crossing. GKRT0192 Two Level Crossing Interface Requirements 14-006-DEV Signal TEB1372 in close proximity to Polegate Level Crossing. Current Deviations Register as at 09 May 2016 2.1.1.3 a) Nature and Degree This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. The Class 68 UK Light project is already in an advance stage, with the firsts units already built and expected to arrive for commissioning in the UK in late January. The design and assessment of the UK Light locomotive has been based on the requirements of GM/RT2130 Issue 3 as amended by derogation 12/115/DGN which has already been granted. Reassessment work would therefore be necessary to demonstrate compliance with GM/RT2130 Issue 4 at this late stage in the project. GM/RT2130 Issue 4 was issued in December 2013 but does not come into force until 01/03/2014. This is after the date that the Vossloh Class 68 UK Light Locomotives Final Technical File is expected to have been submitted to the Office of Rail Regulation (ORR) for granting authorisation (an interim issue of the Technical File containing GM/RT2130 Issue 3 assessment was already submitted to the ORR on August 2013). However, it is unknown whether GM/RT2130 Issue 4 will be listed as a NNTR by the UK Department for Transport (DfT) prior to the coming into The Technical Specification for Interoperability (TSI) relating to the rolling stock subsystem - `Locomotives and passenger rolling stock' of the transEuropean conventional rail system establishes the warning horn sound pressure levels in its clause 4. 2. 7. 2. 2: "The C weighted sound pressure level produced by each horn sounded separately (or in a group if designed to sound simultaneously as a chord) shall be between 115 dB and 123 dB, as defined in EN 151532: 2007, Clause 4. 3. 2. " The TSI includes a permanent Specific case UK for Great Britain in its clause 7. 3. 2. 12, that allows access of TSI compliant rolling stock: "('P') Rolling stock for national use only, may be compliant with the horn sound pressure levels as stipulated in the national technical rules notified for this purpose in the UK. Trains intended for international use shall be compliant with the horn sound pressure levels as stipulated in this TSI. " This specific case does not prevent the access of TSI compliant rolling stock to the national network. " Vossloh aims to get the UK Light locomotives assessed against the currently published Locomotive and Passenger TSI to simplify future mainland European To comply with the RGS would require one of the following options to be implemented: Junction Method 3 - Approach Control from red: the impact of this would be an increased Signal Passed at Danger (SPAD) risk by creation of consecutive approach release sequences. Junction Method 2 Flashing yellow aspect sequence: the impact of this would be an increased complexity in the design and alteration to existing equipment due to be removed in approximately two years. Lower permissible speed on approach for passenger trains (to achieve junction method 1: Unrestricted aspect sequence) - the impact of this would be to impose a capacity constraint for all passenger trains that was not considered acceptable when viewed against over speed risks at the junction. None of the methods above were considered appropriate as the final solution (see also attached supporting statement). Risk Assessment/Safety Justification There is no predicted adverse impact arising from continued use of the current standard. The main safety related risks associated with the use of non-GM/RT2484 compliant warning horn sound pressure levels are: Inadequate warning to persons on or about the track when trains are approaching. Noise Pollution. Damage to staff hearing. The risks from item 2 will be limited due to the limited number of locomotives in the fleet (41 maximum). Item 3 will be controlled by company specific instructions for operating staff regarding the use of the warning horn in depots and yard if necessary. Item 1 is controlled by the fact that the sound pressure levels mandated in the Loc & Pas TSI are higher than those mandated in GM/RT2484 and thus provide a better level of warning. The effectiveness of Loc & Pas TSI (EN15153-2: 2007) compliant warning horns is proven by their use in mainland Europe. The Common Safety Methods (CSM) Directive allows the application of codes of practice as a risk acceptance criterion. On this basis, by complying with requirements of TSI Loc & Pas clause 4. 2. 7. 2. 2 (EN15153-2: 2007), it is considered that the risks associated with the warning horn sound pressure level are controlled. In addition, the Loc & Pas TSI (2011/291/EU) states that vehicles equipped with TSI TJ30/37B(M) Route, Gainsborough Trent Line-speed on the Up Main from Thrumpton Junction. to the junction signal TJ30/37 is currently 30/40 mph. The turn out speed for the junction is 25 mph. The permissible speed differential of 15 mph is 5 mph over that which the standard permits, and the risk of overspeeding are considered low as sighting of the junction indicator is in region of 500 m, and gives sufficient time for the driver to identify signal and control train speed to that of the turnout. Route knowledge learning and briefing are being carried out for project works and new signalling arrangements are part of this work. Other changes are being undertaken but, as turn out speed is not changing, existing route knowledge will also mitigate any overspeed risk at the junction. This deviation will allow removal of the TSR applied to make differential in speed 10mph, covered under Deviation No. 13/228/DEV (tracker No. 15381) which expires on 28/02/2014. Further details on the analysis of proposed arrangements are contained in the supporting information. PT249 and PT449 signals in the proximity of It is not practicable to move PT249 or PT449 If a train approaching PT249 does not Llanelli East level crossing situated on the due to the close proximity of both Llanelli trigger the SPAD Prediction equipment to GW900 Pilining to Fishguard Harbour ELR East and West level crossings adjacent to commence a warning sequence on Llanelli SWM2 Western Route. Llanelli East is both ends of the platform, and prior works East level crossing, the user will not see any located at 225 miles 14 chain. have taken place to enable First Great indication from the road traffic lights or Western trains to stand in the platform audible warning until the train has come to a where train stop boards have been stand in the station, and the forward route is provided. Any further adjustment of these set; the level crossing then goes through the signals would not allow the service to use full sequence of amber and flashing red this station. It is not practicable to close lights before the barriers come down. If the either of the level crossings to create SPAD Prediction equipment calculates that additional standage at the platforms. a SPAD is likely, then the red flashing road lights are initiated to give at least five seconds of warning to road users to get clear, but the barriers are not lowered. The risk of this happening is judged to be very low, I. e. the train will not SPAD or the forward route is set and the crossing is already closed to the road. This SPAD prediction initiation supplements the initiation caused when the train passes the red signal. The design of SPAD prediction timers are based on deceleration of a train, and gives an improved warning time of the actual SPAD of the train, which will trigger the red flashing road traffic lights at less than five seconds. Signal PT449 controls reversing moves, and cannot be approached by trains in normal operation. Polegate level crossing. In order to comply with the RGS The principle risk that is mitigated by the requirement, the signal would have to be level crossing controls is that arising from positioned at least 25m from the crossing. SPAD. The signal is not approachable by Standage for trains in the normal direction is trains as there is no wrong direction sufficient for trains to occupy the whole signalling. The signal has good sighting due platform. This in turn would mean that trains to the position of the train at its allocated reversing at Polegate would have to pull stopping position and architecture of the forward in normal direction of travel to a station. TPWS TSS is fitted, principally to point that allows the other end of the train to mitigate the SPAD risk associated with the be positioned to view signal TEB1372. The conflict on the cross-over, but has a signal and its base would have to be resecondary mitigation role to arrest a SPAD installed in the compliant position. and therefore minimise the potential risk of collision on the level crossing. Applicant Organisation Certificate Issue Date Vossloh España S.A. on behalf 31/01/2014 of, Direct Rail Services Limited Certificate End Date N/A Lead SC RST Lead SC Approval Date N/A Deviation Status Current Vossloh España S.A. on behalf 25/02/2014 of, Direct Rail Services Limited N/A RST 14/02/2014 Current Network Rail 27/02/2014 N/A CCS 06/02/2014 Current Network Rail 27/02/2014 N/A CCS 06/02/2014 Current Network Rail 27/02/2014 N/A CCS 06/02/2014 Current Page 46 Deviations Register RGS Number GMRT2130 RGS Issue Number Four RGS Title Vehicle Fire, Safety and Evacuation Certificate Number 14-002-DEV Title Deviation against the requirements of GM/RT2130 Issue 4. RGS Clause All clauses. Scope The new Class 70 locomotives manufactured by General Electric (GE) in 2013 and 2014 onwards. GCRT5112 Two Rail Traffic Loading Requirements for the Design of Railway Structures 14-001-DEV Bridge 110 in Tanners Hill area - Design for collision loading. 7.1.3 Localised derogation for deck and new trestles for Bridge 110 in the Tanners Hill area. GERT8000-SS2 Three Shunting 13-242-DEV Entering a shed or building - Non-sounding of the warning horn before restarting. Clause 5.7, bullet point 3. GIRT7016 Five Interface between Station Platforms, Track and Trains 13-241-DEV Revised 23-06-2015 Hendon Station, Platform 3 - reduced platform width at mid platform fencing. 7.2.1 Current Deviations Register as at 09 May 2016 Nature and Degree Risk Assessment/Safety Justification GE has developed and is in the process of None. manufacturing 10 new Class 70 locomotives for Colas Rail. Three of these locomotives (70801, 70803, 70805) are currently in the UK and undergoing final commissioning. The September 2013 RGS catalogue has been applied as the basis of the current Notified National Technical Rules (NNTRs) (as per the current Department for Transport (DfT) published NNTR list). However, as the December 2013 RGS catalogue includes an update to GM/RT2130 (to Issue 4), there is a potential for this to be listed as an NNTR before the completed application for authorisation is made to the Office of Rail Regulation (ORR) under RIR2011. In addition, a derogation has already been granted to GM/RT2130 Issue 3 (13/041/DGN). Therefore the project wishes to obtain a derogation to GM/RT 2130 issue 4, and instead continue to use issue 3, on the basis of advanced stage of development. Applicant Organisation GE Transportation Certificate Issue Date 13/01/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date N/A Deviation Status Current Permission is being sought to place new supports to a structure within the hazard zone (4. 5 m from the cess rail and anywhere between the tracks) which have not been designed to withstand accidental impact. No action plan has been adopted to achieve the compliance. Alternative design approaches have been developed and a risk assessment has been undertaken to evaluate the risk. The risk assessment showed that it is not reasonably practical to seek compliance (please see Part 4 of the Tracker Application Form for compliance cost). As a result, the derogation is being sought. The new steel support trestles are designed to allow for a passive collapse of just the trestle when a train collides with them. The superstructure will be strengthened, such that it will not fail in the ultimate limit state, in the event that a train derailment has caused the removal of one of the new supporting trestles. Therefore, it is believed that the proposed solution fulfils the "spirit" or intention of Clause 7. 1. 3. namely that, in the case of a derailment, an overhead structure is not brought down onto the train, causing additional injuries to either train passengers or people using the bridge. However, derogation is sought as the The deviation only applies across First Great There have been concerns raised by Health Western (FGW) depot buildings that have and Safety representatives relating to depot protection systems in operation. The shunters and fleet operatives being exposed deviation applies to the rule requiring the to high noise levels when drivers use the warning horn to be used as a warning before warning horn upon entering depot buildings. restarting and entering a shed or building. Depot Operating Instructions require the Shunters to be at shed doors to: · operate depot protection and · authorise a train into the shed. Operation of the warning horn is to warn personnel in the area that a train is entering the shed; this safety feature is adequately covered by the shunter on the door, verbally warning his colleagues in the area and operation of the depot protection system. The depot protection system gives an audible and visual warning that movements are taking place. It is believed that sounding the warning horn, in addition to the above requirements, introduces an unnecessary hazard to shunters and fleet colleagues, causing a risk of ill health injuries. An existing footbridge (Bridge 110) Network Rail currently spans three tracks of the four-track XTD (Charing Cross to Dover) mainline and a reversible single LVT (Lewisham Vale and Tanners Hill Line) track at Tanners Hill, with two existing steel support trestles adjacent to the railway without any derailment protection. In order to double the LVT line, one existing steel support trestle needs to be removed as it clashes with the proposed new alignment. Options considered included: Replacement of footbridge with a completely new and compliant structure, with supports outside the hazard zone. However, this solution has been deemed excessively expensive and disruptive to the travelling public (the footbridge provides access to St John's station) and has thus been rejected outright. Installation of two new supports within the hazard zone, but with the provision of derailment plinths to ensure that these supports would not be affected by the predicted loads acting in the event of a train derailing and striking the structure. These plinths would thus ensure compliance with Clause 7. 1. 3 of standard GC/RT5112. This solution has been developed, and a cost of this solution derived, which is used in the enclosed UIC This proposed alternative will reduce the First Greater Western Ltd risk of ill health claims against FGW and reduce the risk of injury to all colleagues who operate on a depot. Safeguards have been included in the proposed instructions that, if any system is not in place, Shunter to authorise the movement or depot protection system not operating, the driver will operate the horn as a warning before restarting a movement into a shed or building. Risk assessments undertaken have indicated that the risk is categorised as low, with the following controls in place: · Depot Protection Procedure (SMS-1875-00 SPM Depot Operating Instructions) · Production support / shunter on door of shed · Depot protection warning lights · Depot protection bell / siren sounded during movements · Personal track safety of all colleagues operating in the area · Track awareness briefings for all colleagues operating in the area · Regular safety briefs. 10/04/2014 N/A INS 05/03/2014 Current 21/02/2014 N/A TOM 04/02/2014 Current Platform 3, Hendon Station, Station Road, Hendon NW4 4PT. To assist in suicide prevention, midNetwork Rail platform fencing is being installed at 5No Stations on the East Midlands route, namely: Hendon, Radlett, Mill Hill Broadway, Cricklewood, and Elstree &amp; Borehamwood. The proposed gated midplatform fencing will prevent access to the fast lines, which are only used in times of engineering work or disruption. There has been a significant increase in the average cost per incident, this is thought to be due to an increase in suicides in high impact locations, and during the peak of passenger travel. Due to obstructions both on and within the platform construction, the platform fencing cannot be positioned to provide the compliant 3 m clearance from coping stone edge to fence. This non-compliance varies from 2941 mm at the country end, 2970 mm at various positions and 2990 mm in one location on Platform 3. This can be seen on accompanying as built Drawing No C1290BCS-DRG-CV-000101 Rev Z01, and on the attached as built photographs Ref. 17054 Hendon. doc. This replaces Tracker No. 15644. 24/06/2015 N/A INS 13/05/2015 Current The severity/impact at Hendon Station is considered generally low. The reduced platform width affects the fast lines only. The fast line platform is only used during slow line closures and during perturbed working. To assist in suicide prevention, mid-platform fencing is being installed at 5No Stations on the East Midlands route, namely: Hendon, Radlett, Mill Hill Broadway, Cricklewood, and Elstree &amp; Borehamwood. Page 47 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-240-DEV Title Mill Hill Broadway Station, Platform 3 reduced platform width at mid platform fencing. RGS Clause 7.2.1 Scope Platform 3, Mill Hill Broadway Station, Station Road, Mill Hill, NW7 2JU. Nature and Degree Based on the drawings / details in existence that reflect the proposed fencing layouts at Mill Hill Broadway Station (copy attached), full compliance is unachievable and, therefore, in the absence of a deviation being granted, then the scheme in its entirety will be undeliverable. The severity / impact at Mill Hill Broadway Station is considered generally low, given the reduced platform width affects the fast lines only and there are currently no services whatsoever "Stopping Off" whereby the embarkation/disembarkation of passengers would not be an issue, however consideration by virtue of additional gated access points along the lengths of the general fence line could be incorporated at cost within the scheme, to be used / managed / policed only by the Train Operating Company (TOC) / station management staff under emergency situations or engineering works and thereby built into the Station Management Strategy Plan. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-239-DEV Elstree &amp; Borehamwood station, Platform 3 - reduced platform width at mid platform fencing. 7.2.1 Platform 3, Elstree &amp; Borehamwood Station, Allum Lane, Elstree, WD6 3LS. Based on the drawings / details in existence that reflect the proposed fencing layouts at Elstree &amp; Borehamwood Station (copy attached), full compliance is unachievable and, therefore, in the absence of a deviation being granted, then the scheme in its entirety will be undeliverable. The severity / impact at Elstree &amp; Borehamwood Station is considered generally low, given the reduced platform width affects the fast lines only, and there are currently no services whatsoever "Stopping Off", whereby the embarkation/disembarkation of passengers would not be an issue; however, consideration by virtue of additional gated access points along the lengths of the general fence line could be incorporated at cost within the scheme, to be used / managed / policed only by the Train Operating Company (TOC) / station management staff under emergency situations or engineering works and thereby built into the Station Management Strategy Plan. GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 13-236-DEV Class 323 External Passenger Door Closing B6.1 Forces. GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 13-234-DEV Flashing aspects for P468 signal at Peterborough. Current Deviations Register as at 09 May 2016 5.2.3.1 This deviation applies to all Class 323s operated by London Midland. The deviation applies to the external passenger door control system (specifically the Electronic Door Control Unit, the EDCU). Software variables within the EDCU control a number of parameters, including opening and closing forces. Each pair of bi-parting passenger doors is controlled by an individual EDCU. New software (version F0) has been written and is required to be installed to the EDCUs, to replace the existing software (version E2). The purpose of the new software is to increase the door closing forces to overcome problems with door failing to close in service. As built, Class 323s were fitted with an analogue type of door control unit, referred to here as the Analogue EDCU. The Analogue EDCU operated the doors with closing forces in excess of the maximum figures specified with GM/RT2473 Issue 2. However, the door system on these EMUs was not designed to comply with this standard: Class 323s were built in 1992 / 1993, and GM/RT2473 was introduced ten years later, in 2003. Over time, the Analogue EDCU became obsolete as more advanced electronic door control systems were developed. In 2009, the door equipment OEM, Faiveley, introduced a new EDCU. Signal 468 4(M) and 5(M) flashing aspects Compliance could be maintained by routes, reading from the Up Fast to Platform continuing to use approach release from red 2 or 3, controlled by Peterborough PSB. on P468. This control currently causes trains proceeding from the Up Fast to Platform 2 or 3 to decelerate to P468 at red before the aspect is released to proceed over 1243 and 1242 points. The controls currently have a risk of anticipation and that required trains to accelerate towards the points after the signal clears due to 1243 points being 700 m from P468 signal. Train Operating Companies have raised these issues from performance and safety perspective, and requested the controls are amended. Risk Assessment/Safety Justification To prevent suicides at 5No Stations on the East Midlands Route, namely: Hendon, Radlett, Mill Hill Broadway, Cricklewood, &amp; Elstree &amp; Borehamwood. The proposed gated mid-platform fencing will prevent access to the fast lines, which are only used in times of engineering work or disruption. The installation of fencing at Purley and Harrow &amp; Wealdstone (see attached photos) has proved effective in preventing suicides since their commissioning in 2008/2010 respectively. In order to maintain the majority width (minimum 3 m) on the operational "Slow" sides of the affected platforms at Mill Hill Broadway Station (I. e. the platforms at which the trains consistently stop to allow passenger embarkation/disembarkation) and in line with TOC / safety expectations and "best linear fit" to fully consider evasion of underground service or above ground lighting, drainage channels, shelters, Driver Only Operation (DOO) mirrors etc. , the residual width of platform left adjacent the "Fast" lines is reduced down to a noncompliant width, as can be seen on the accompanying Drawing NopC1290-BCSDRG-CV-000301 Rev P01. To prevent suicides at 5No Stations on the East Midlands Route, namely: Hendon, Radlett, Mill Hill Broadway, Cricklewood, &amp; Elstree &amp; Borehamwood. The proposed gated mid-platform fencing will prevent access to the fast lines, which are only used in times of engineering work or disruption. The installation of fencing at Purley and Harrow &amp; Wealdstone (see attached photos) has proved effective in preventing suicides since their commissioning in 2008/2010 respectively. In order to maintain the majority width (minimum 3 m) on the operational "Slow" sides of the affected Platforms at Elstree &amp; Borehamwood Station (I. e. the platforms at which the trains consistently stop to allow passenger embarkation / disembarkation) and in line with Train Operating Company (TOC) / safety expectations and "best linear fit" to fully consider evasion of underground service or above ground Lighting, drainage channels, shelters, Driver Only Operation (DOO) mirrors etc. , the residual width of platform left adjacent the "Fast" lines is reduced down to a non-compliant width, as can be seen on the accompanying Drawing NopC1290-BCS-DRG-CV-000501 Rev P01. The consequences of the higher door closing forces are discussed below, and include a justification that the affect upon passenger safety is acceptable. A history of Class 323 passenger door safety: London Midland record all accidents reported by passengers, station staff or train crew, and the information is held on a database. London Midland has carried out a search stretching back five years to establish how many accidents have been attributed to trapping in doors, and the events relating to each accident. Since November 2008, there have been 38 recorded accidents involving people becoming trapped in the passenger doors on London Midland's Class 323 fleet. From the limited information given in the `Comments' field in the accident report, it is difficult to interpret a clear picture of exactly what happened: what were the sequence of events and what were the causal factors with each accident. The information consists mainly of allegations and statements from passengers. There is no evidence to support or disclaim the events as recorded. We do not know at what door position the accident occurred. Therefore, it is prudent not to form firm conclusions. Nevertheless, studying the information shows a number of The flashing aspect sequence will reduce the risk of trains accelerating towards the divergence after receiving a delayed aspect release on the junction signal, as majority of diverging trains will be signalled with the flashing aspects rather than Main Aspect Red (MAR). The SPAD risk from anticipation on P468 is reduced. Flashing aspects exist for a range of different turnout speeds on this route, including lower speeds, and driver route knowledge is acceptable as the primary means of speed control for this junction, which has little potential for confusion with other junctions in this area. Provision of PSWI with AWS arrangement is considered to adequately manage the over-speed risk at the junction, and assist with driver route knowledge as to what speed the flashing sequence relates. Provision of MAY-FA can have an impact on SPAD risk the signal after the junction. Controls and TPWS have been provided in line with current RGS to manage these risks. In addition to the reduced SPAD and derailing risk due to accelerating to excess speed, the performance benefit of this arrangement has been estimated at 90 s when compared to current MAR arrangements. Future S & C renewal is Applicant Organisation Network Rail Certificate Issue Date 23/04/2014 Certificate End Date N/A Lead SC INS Lead SC Approval Date 05/03/2014 Deviation Status Current Network Rail 23/04/2014 N/A INS 05/03/2014 Current Porterbrook Maintenance Ltd 30/01/2014 N/A RST 17/01/2014 Current Network Rail 28/02/2014 N/A CCS N/A Current Page 48 Deviations Register RGS Number GMRT2000 RGS Issue Number Three RGS Title Engineering Acceptance of Rail Vehicles Certificate Number 13-230-DEV Title Derogation in accordance with GM/RT2000 Clauses 6.6.3 for Tyne and Wear Battery Locomotives. RGS Clause 6.6.3 - Vehicles for heritage or special services only 6.8.6 - Vehicles for heritage or special services only Appendix H Requirement for Engineering Acceptance of non-compliant Vehicles for limited use on heritage or special service trains. Scope The deviation applies to three battery locomotives owned and operated by Tyne and Wear Metro, currently used for the purposes of shunting Metro units around the depot, and for rescuing in-service stranded Metro units, for example due to Overhead Line Electrification (OLE) failure. This deviation is required to allow these locomotives to run on the part of Network Rail Infrastructure between Pelaw Metro Junction and Sunderland, including Boldon loop and Burdon Road sidings at Sunderland, between Sunderland and South Hylton, the Boldon to Port of Tyne branch and the refuge off the main Sunderland line. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-226-DEV Willesden Junction High Level Station platform extension on track curvature less than 1000 m radius. 2.1 Willesden Junction High Level Station Platform 5. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-225-DEV South Acton Station, Platform 1 - reduced width of platform extension. 7.2.1 GIRT7016 Four Interface between Station Platforms, Track and Trains 13-224-DEV Finchley Road &amp; Frognal Station, Platform 2 - reduced width of platform extension. 7.2.1 GMRT2473 Two Power Operated External Doors on Passenger Carrying Rail Vehicles 13-223-DEV Derogation for the power operated passenger doors as fitted to new Class 377/7 Electric Multiple Units (EMU). All clauses. The deviation applies to a platform extension of some 27. 5 m (final length to be developed in detailed design), on the Down Line at the London end of Platform 1 at South Acton station. The minimum platform width will be 2. 4 m. All relevant Guidance Notes within GI/GN7616 Issue 1 have been considered prior to the submission of the deviation request. The platform extension is required due to the introduction of five-car Class 378 operations on the London Overground network, which will commence on the North London Line in 2015. The extension is required as the existing platform is only long enough for a four-car CL378 unit. As part of the approval in principle of the design, a gauging and stepping analysis has been conducted and Track Form A produced for this platform. The Form A has been reviewed and signed by the Network Rail Gauging Engineer and Track RAM for Anglia and shows that there is no worsening of the existing gauging and stepping values at this location and that all values are within the `stepping triangle' albeit towards the upper end of the range. A copy of this report is included with this submission. Similarly, copies of relevant Civils drawings of the proposal are included with this submission. The deviation applies to 16 m of the proposed 20. 35 m platform extension (final length to be developed in detailed design), on the Up Line at the country end of Platform 2 at Finchley Road &amp; Frognal station. Over the 16 m length there will be a reduced platform width of 2025 mm tapering to a compliant width. All relevant Guidance Notes within GIGN7616 Issue 1 have been considered prior to the submission of the deviation request. The platform extension is required due to the introduction of five-car Class 378 operations on the London Overground network which will commence on the North London Line in 2015. The extension is required as the existing platform is only long enough for a four-car CL378 unit. As part of the approval in principle of the design, a gauging and stepping analysis has been conducted and Track Form A produced for this platform. The Form A has been reviewed and signed by the Network Rail Gauging Engineer and Track RAM for Anglia and shows that there is no worsening of the existing gauging and stepping values at this location and that all values are within the `stepping triangle' albeit towards the upper end of the range. A copy of this report is included with this submission. Similarly, Class 377/7 units (8 x 5 car units), power operated doors. This application is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Current Deviations Register as at 09 May 2016 Nature and Degree Clause 6. 6. 3 allows applications for derogations for non-compliant vehicles with an annual mileage not exceeding 15,000 miles to be submitted as a single request. The battery locomotives were manufactured in 1989. The requirement is for the operating lines of these locomotives to be extended to include the section of Network Rail infrastructure used by Metro trains between Pelaw Metro Junction and Sunderland, and from Sunderland to South Hylton in the event of an OLE failure, rather than hiring locomotives. In addition, various loops and sidings (see Section 7 - Scope of deviation) may be required as refuge for the failed train or as a potential alternative route for dispatch of trains for refurbishment. The cost of either procuring a compliant shunter (which would be a unique design as batteries are required for running with no OLE in tunnels) or making the existing shunters compliant would be disproportionate to the occasional use for which they would be required. Clause 6. 8. 6 and associated appendix give special arrangements due to the special circumstances of operating a heritage or special service. It allows, under certain circumstances, that a maintenance and an The only method of complying with the current RGS requirement would be to introduce Automatic Selective Door Opening at this location. Early consultation with LOROL determined this was not a preferred option as: Dwell times would increase to an intolerable level and impact on the service frequency and punctuality. Platform passenger flows would be markedly affected, at the London end of the platform Train evacuation times would not be acceptable in the event of a fire . As the use of ASDO did not have the support of LOROL, the option was not pursued. The only method of complying with the current RGS requirement would be to introduce Automatic Selective Door Opening at this location. Early consultation with LOROL determined this was not a preferred option as: Dwell times would increase to an intolerable level and impact on the service frequency and punctuality Platform passenger flows would be markedly affected, at the London end of the platform Train evacuation times would not be acceptable in the event of a fire. As the use of ASDO did not have the support of LOROL, the option was not pursued. Risk Assessment/Safety Justification The normal operating procedures for dealing with a failed Metro unit is for the following unit to couple up and move it to the depot. If this is not possible, for example due to a failed OLE power supply (e. g. lines down or power supply failure), then they will need to be rescued by a locomotive with an independent power source. On most of the Tyne and Wear system, this is conducted by these battery locomotives that have a compatible mechanical, electrical and pneumatic coupling system. This deviation is being requested such that this procedure can be extended to the Network Rail infrastructure as detailed in Section 7 above, if similar circumstances were to occur here. The battery locomotives are being used and stored in the Tyne and Wear maintenance facility at South Gosforth. They are being maintained by the same trained staff and under the same maintenance controls and structure as the Metro stock. Certification shall remain valid as long as the maintenance procedures remain unchanged within the scope of the certification (I. e. maintenance to ensure the continued compliance with Railway Group Standards), at the same facility as the Metro stock, and under the same maintenance controls, I. e. LOROL have confirmed that the current Driver Only Operation (DOO) train dispatch with in-cab Close Circuit Television (CCTV) is satisfactory for the increased length of the platform for five-car trains. Stepping distances are no worse than at the existing platform and are within the stepping triangle. Willesden Junction High Level Station operates with extended dwell times currently and these will be maintained in the future at 90 seconds; extended dwell times at this location are required due to the numbers of boarders and alighters. Applicant Organisation SGS CORREL Rail Ltd Certificate Issue Date 02/04/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date 17/01/2014 Deviation Status Current London Overground Capacity Improvement Project 11/04/2014 N/A INS 05/03/2014 Current The provision of additional platform London Overground Capacity dispatch staff maintains the current safe Improvement Project method of train dispatch and does not materially affect the future operation of the station. Extending the current train dispatch arrangements to cater for five-car operation will necessarily increase the OPEX costs for the Station Operator, LOROL; these additional costs are being accounted for in the renegotiation of the current franchise arrangements which will come into force when five-car operations commence. 21/02/2014 N/A INS 07/01/2014 Current The only method of complying with the current RGS requirement would be to introduce Automatic Selective Door Opening at this location. Early consultation with LOROL determined this was not a preferred option as: Dwell times would increase to an intolerable level and impact on the service frequency and punctuality Platform passenger flows would be markedly affected, at the London end of the platform Train evacuation times would not be acceptable in the event of a fire. As the use of ASDO did not have the support of LOROL, the option was not pursued. The provision of additional platform London Overground Capacity dispatch staff maintains the current safe Improvement Project method of train dispatch and does not materially affect the future operation of the station. Extending the current train dispatch arrangements to cater for five-car operation will necessarily increase the OPEX costs for the Station Operator, LOROL; these additional costs are being accounted for in the renegotiation of the current franchise arrangements which will come into force when five-car operations commence. 13/02/2014 N/A INS 07/01/2014 Current The Department for Transport (DfT) have published an updated list of Notified National Technical Rules (NNTRs), which now includes GM/RT2473 Issue 2, replacing Issue 1 as referenced in the previously published list of NNTRs. The Class 377/7 project is already at an advanced stage of production and, with the exception of elements dedicated to running under Overhead Line Electrification (OLE), the design is as close to identical to the Class 377/6 units as is feasible, in order to aid maintenance and spares holding. Therefore, the design and assessment of the passenger doors has been based on the requirements of the superseded standard. An assessment of the changes of GM/RT2473 from Issue 1 to Issue 2 indicates that, whilst the changes are minor, there has been no consideration of the derogations that have been granted against Issue 1. As compliance is being demonstrated in line Southern Railway Limited with the standards applied on recent builds, there are not expected to be any adverse impacts. 22/01/2014 N/A RST N/A Current Page 49 Deviations Register RGS Number GERT8075 RGS Issue Number One RGS Title AWS and TPWS Interface Requirements Certificate Number 13-222-DEV Title Derogation for the supply of AWS and TPWS equipment fitted to new Class 377/7 Electric Multiple Units in accordance with GE/RT8030 Issue 4 and GE/RT8035 Issue 2. RGS Clause All clauses. Scope Equipment fitted in each cab of 8 off five-car Class 377/7 units, I. e. 16 AWS/TPWS systems. This application is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. Nature and Degree The Department for Transport (DfT) have published an updated list of Notified National Technical Rules (NNTRs), which now includes GE/RT8075 Issue 1, replacing GE/RT8030 Issue 4 requirements for the Train Protection and Warnings System (TPWS) and GE/RT8035 Issue 2 Automatic Warning System (AWS), as referenced in the previously published list of NNTRs. The Class 377/7 project is already at an advanced stage of production, and with the exception of elements dedicated to running under OLE, the design is as close to identical to the Class 377/6 units as is feasible, in order to aid maintenance and spares holding. Therefore, the design and assessment of the AWS/TPWS equipment has been based on the requirements of the superseded standards. Consequentially, reassessment work would be required to demonstrate compliance with GE/RT8075 Issue 1, and individual derogations sought if non-compliances are to be found. Risk Assessment/Safety Justification Applicant Organisation As compliance is being demonstrated in line Southern Railway Limited with the standards applied on recent builds, there are not expected to be any adverse impacts. Certificate Issue Date 28/01/2014 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 09/01/2013 Deviation Status Current GMRT2132 One On-board Energy Metering for Billing Purposes 13-217-DEV Class 357 Energy Metering 2.2.6, 2.2.8 a) and; b), 2.3.2, 2.3.5, 2.6.3, A1.1, A1.2 and A1.3. 74 x Class 357 EMU Units (357001 - 046 and 357201 - 228). None - Data for billing purposes is still available at the required accuracy and frequency. 22/05/2014 N/A RST 13/03/2014 Current GMRT2307 One Self contained electrical power supply systems fitted to infrastructure support vehicles 13-215-DEV Revised 23-01-2014 Derogation to GM/RT2307 Issue 1 for the Clause 4.1.1 (99 70 9131 010 - 9, 99 70 MPVs and Wagons of the Network Rail High 9131 008-3, 99 70 9131 009-1) Clause 4.4 Output OLE Construction System (HOPS). (99 70 9131 010 - 9, 99 70 9131 008-3, 99 70 9131 009-1) Clause 6.4 (all vehicles quoted in Section 7) Clause 6.5 (all vehicles quoted in Section 7) Clause 6.6 (all vehicles quoted in Section 7) This application is to permit noncompliance with the RGS standard clauses of GM/RT2307 Issue 1 as identified in 6b above (RGS Clause), for the following: MPV vehicles: Type 1 (SOPB): · 99 70 9131 010 9. Type 3 (SNPB): · 99 70 9131 015 - 8 · 99 70 9131 020 - 8. Type 5 (SORB): · 99 70 9131 014 - 1. Wagons: Type KFA recertified as On-Track machines: · 99 70 9131 008 - 3 · 99 70 9131 009 - 1 · 99 70 9131 019 - 0. `Bonding methods': Vehicles 99 70 9131 Windhoff Bahn- und 010-9, 99709131008-3 and 99709131009-1 Anlagentechnik GmbH are connected to each other electrically using a protective conductor system (IT system) in accordance with German industry standard DIN VDE 0100-410: 2007-06; thus, RCDs are not required because personnel protection is guaranteed by the protective conductor system. In consequence, it is considered that the risk is controlled to As Low As Reasonably Possible (ALARP) level and is equivalent or better than would be the case if an RCD based protection system had been fitted. Pilot Protection (Inter-vehicle connection): Due to the screwed connection, the unintentional disconnection of the specific inter-vehicle connectors is prevented and is only undertaken by competent staff using tools for the purpose. It is therefore considered that the risks are controlled to ALARP and are no greater than they would have been had a pilot protection system been fitted. The system and procedure used is similar to previous derogations 01/265/DGN, rail grinders and 03/038/DGN, track measuring machines. 16/01/2014 N/A PLT 12/12/2014 Current GMRT2130 Three Vehicle Fire, Safety and Evacuation 13-214-DEV Derogation to GM/RT2130 Issue 03 for the 2.5.4b). MPVs and Wagons of the Network Rail High Output OLE Construction System (HOPS). This application is to permit noncompliance with the RGS standard clauses of GM/RT2130 Issue 3 as identified in 6b above (RGS clauses), for the following. MPV vehicles: Type 1 (SOPB): · 99 70 9131 010 - 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4, · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7. Type 3 (SNPB): · 99 70 9131 015 - 8 · 99 70 9131 018 - 2 · 99 70 9131 020 - 8. Type 4 (HNPB): · 99 70 9131 003 - 4. Type 5 (SORB): · 99 70 9131 014 - 1. Wagons: · KFA 99709131019-0. This deviation is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. The proposed energy metering system for the class 357 Electrostar units utilises the existing traction control electronics to provide the measurements, with new software to assimilate and record the data. The RGS was written principally with discrete meters in mind, and so some features of the traction electronics cannot exactly replicate the functions of a standalone meter. Some data assimilation functions are stated as being completed onboard but must be completed off-board. Removal and retesting of the Voltage Measurement Transformer (VMT), Current Measurement Transformer (CMT) and electronics for the Energy Calculation Function (ECF) would not be practical and would be prohibitively expensive. The deviation presents the technical argument, test data and component accuracy for the existing train components as an alternative. All efforts have been made to ensure that the solution complies with the standard but this has not been possible for certain clauses. The changes required to be fully compliant would require hardware upgrade and software change meaning the solution would be prohibitively expensive, add hardware and complexity to the train and would The MPVs and work modules being delivered to the Project are based on current in-service vehicles that provide the functionality required. However, it is acknowledged that the bonding criteria for the three vehicles of the concrete mixing/batching plant as well as specific vehicle inter-connectors differ from those defined in GM/RT2307 Issue 1. `Bonding methods': Within HOPS, three vehicles are equipped with concrete mixing/batching plant modules. These modules are boughtin proprietary equipment which comply with the EU Machinery Directive. The comprehensive protection system provided on each of these modules does not use an RCD as required by the Standard. In consequence and in contrast to the generator applications of all other vehicles within HOPS, the bonding method used on these three vehicles does not feature a threephase a. c. with the star point connected to the vehicle frame. Pilot Protection (Intervehicle connection): Within HOPS, two vehicle pairs and one three-vehicle formation feature inter-vehicle connections at a voltage of 110/230/400V for work equipment fitted to the modules on these permanently coupled vehicles. The interThe Multi-Purpose Vehicles (MPVs) have been designed to be compliant with Technical Specifications for Interoperability (TSI) requirements, including the Locomotive and Passenger TSI, and are closely based on the existing MPV design which is EN 14033 compliant. This design is based on fire performance in accordance with DIN 5510-2. Changes to the cab design to meet full GM/RT2130 compliance would invalidate the previously assessed design, not only with respect to fire safety but also other requirements. It is considered that using the current design, as detailed below, is adequate to control the risks and that the significant additional work to achieve full GM/RT2130 compliance is not beneficial. This principle is consistent with the previously granted deviation, 13/013/DGN, which permits use of DIN 5510-2 for fire properties of materials. Although the cab floor fire barriers have not Windhoff Bahn- und been demonstrated as compliant to Anlagentechnik GmbH GM/RT2130 requirements, the risks to onboard staff are considered to be adequately controlled because: · DIN 5510 fire barriers are fitted (note it is not possible to directly equate these to UK fire resistance durations due to different nature of the standards). · The fire sources directly under the cabs are small - diesel cab heaters only. · Selfmonitoring fire detection and suppression systems are fitted. · Limited numbers of people on board, and they are all trained staff. · Train speed is limited to 60 mph, hence train can be stopped in around 30 seconds. · Direct communication is available between all staff locations and the driver. · Manual fire extinguishers are fitted to the vehicles, which can be used if necessary. Therefore, even in the unlikely event of a failure of the fire detection/suppression system, there will be sufficient time to stop and evacuate the train before the floor barrier is compromised. 07/02/2014 N/A RST 06/12/2013 Current Current Deviations Register as at 09 May 2016 c2c Rail Ltd Page 50 Deviations Register RGS Number GMRT2461 RGS Issue Number One RGS Title Sanding Equipment Fitted to Multiple Units and on- track Machines Certificate Number 13-180-DEV Title RGS Clause Additional sanding devices on 11th axle as 9.1 permissible by TSI CCS (2012/88/EC) while complying to the overall sanding rates as defined by GM/RT2461. GMRT2149 Three Requirements for Defining and Maintaining the Size of Railway Vehicle 13-179-DEV Class 700 (Thameslink EMU) shoegear height. B10.2 GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 13-178-DEV Resistance to Derailment - Use of Multiple Regression for Technical Conformity in lieu of UK On-track Tests. E.2.1 Test conditions E.5 Performance requirements GIRT7016 Four Interface between Station Platforms, Track and Trains 13-177-DEV Installation of additional platform and track at 2.1 Whitby Station - platform curvature. Current Deviations Register as at 09 May 2016 Scope Class 700 trains. Nature and Degree Class 700 trains are eight-car and twelvecar units in fixed formation, consisting 20 m cars. On Class 700, a first active sanding device is placed in front of the third axle and a second active sanding device is placed in front of the eleventh axle in direction of driving, whereas the above clause does not allow a second active sanding on the train. The recommended sanding rate approaching, but not exceeding, 2kg/minute per rail will be distributed and the maximum quantity of sand dispensed will be compliant to GM/RT2461. For operation in braking mode, sand shall be delivered to the railhead by the leading vehicle only for all train formations (including multiple formations), at a location forward of the third axle and after the second axle, in the direction of travel. There are different concepts described in GM/RT2461 and the Technical Specification for Interoperability (TSI) Control Command and Signalling (CCS) concerning the sanding rate and amount of active sanding devices. The Group Standard GM/RT2461 limits the number of active sanding devices to one device per unit and rail. It also recommends a sanding rate approaching, but not exceeding, 2kg/minute per rail. The TSI Class 700 'Thameslink EMU' and all its This deviation relates to the Class 700 subclasses. 'Thameslink EMU' non-compliance with the swept envelope for shoegear as defined in Clause B10. 2 and Appendix B of GM/RT2149. Complying with the requirements by raising the shoegear height would cause extremely poor contact between the conductor rail and the shoegear. It is important to note that, if the shoegear is set higher in order to comply with GM/RT2149, then the following risks arise: The shoes will lose contact with the third rail and thus prevent the Class 700 'Thameslink EMU' from being powered if static, and cause unreliable operation if moving. When moving the shoes would periodically lose contact with the third rail, which will cause significant arcing and the electrical interference generated as a result of this may give rise to signalling compatibility issues. Drawing number M59134-02-LT provides the assessment of the shoegear against the swept envelope defined in Appendix B of GM/RT2149. This assessment includes: · the maximum lateral movement derived for Cases A and B (defined in Clause B10. 2) for any vehicle condition, · vertical movements for any relevant vehicle condition (I. e. load or wear Class 700 `Thameslink EMU' and all its sub- As the Class 700 needs to comply with the classes. Locomotives and Passenger Rolling Stock Conventional Rail Technical Specification for Interoperability (CR TSI LOC PAS) ( 2011/291/EU, Commission Decision 26/04/2011 concerning a technical specification for interoperability relating to the rolling stock subsystem - `Locomotives and passenger rolling stock' of the transEuropean conventional rail system'), a full vehicle testing in accordance with EN14363: 2005 ( Railway applications - Testing and Simulation for the acceptance of running characteristics of railway vehicles - Running Behaviour and stationary tests ) is required, which will not be possible in UK due to the absence of required test zones on routes accessible with the Thameslink gauge. Therefore, on-track tests according EN14363: 2005 are scheduled to be performed outside UK. Complying with GM/RT2141 Appendix D or Appendix E would call for additional dynamic on-track ride tests in UK. Limited accessibility of Thameslink routes for vehicle testing introduces a project risk in terms of delay in the approval and homologation process due to the resulting late availability of the generated test report. The Deviation relates to the re-instatement At present, Whitby Station is a single track, of a station platform and associated track at single platform terminus of the Network Rail Whitby Station where the radius of the curve single line branch from Middlesbrough. The will be less than 1000 m. NYMR service cannot meet demand nor offer a full range of journey opportunities to potential travellers unless the number of services is increased. Funding for this work has been obtained from national funding agencies keen to stimulate the economy of Whitby through the enhancement of tourist related rail services into the North York Moors National Park and from Network Rail itself. To do this requires the commissioning of a second platform and options appraisals show that the only meaningful option is the reinstatement of the demolished part of the former Platform 2 in its original location. The rebuilt platform will have a fractionally greater radius compared with the existing Platform 1 currently used by all services. The reinstated platform would normally be used by NYMR trains but would be accessible to other users. Northern Rail are the franchise operator and will continue normally to use Platform 1. Occasional charters (currently around 2 - 3 per year) visit Whitby and may use either platform depending on circumstances. Northern Rail normally uses Classes 153 and 156 Diesel Risk Assessment/Safety Justification Applicant Organisation Safety of the railway system: The lower First Capital Connect sanding rate recommended by the TSI CCS insures that no signal devices are isolated by a too high amount of sand. The second active sanding device allows a more even distribution of sand on the track will therefore improve the performance during low adhesion condition. Technical compatibility: This solution is compliant to TSI CCS. Certificate Issue Date 28/01/2014 Certificate End Date N/A Lead SC RST Lead SC Approval Date 05/12/2013 Deviation Status Current None, providing that structure clearance is provided in accordance with NR/GN/ELP/27010 5. 9 for a minimum dynamic shoegear height of 25 mm ARL. 27/01/2014 N/A RST 06/12/2013 Current The method of multi linear regression was First Capital Connect 27/01/2014 recently investigated within the European railway dynamics research project DynoTRAIN. It will be introduced in the revised EN 14363 (prEN 14363: 2013, `Railway applications - Testing and Simulation for the acceptance of running characteristics of railway vehicles - Running Behaviour and stationary tests') to the assessment of rolling stock dynamic behaviour at different track geometry levels. Moreover, the method was already introduced in the clarification document ERA/TD/2012-17/INT (European Railway Agency, Interoperability Unit, Running Dynamics Applications of EN 14363: 2005 Modifications and Clarifications) for the same purpose (see Clause 4. 4. 8 and Annex A of the corresponding document). According to the documents mentioned above, the multi linear regression is a suitable method to estimate the result of a vehicle assessment even if the test conditions do not meet the requirements to reflect the vehicle's dynamic behaviour in the operating conditions completely. Therefore, the safety, the technical compatibility, the performance and other properties of the railway system will not be affected. The The speed restriction over the reinstated North Yorkshire Moors Railway 12/11/2013 terminal platform line will be 10 mph. Trains Enterprises Plc entering the platform will have been stopped at the end of the single line section, to allow operation of the Ground Frame controlled points. Trains leaving the station will stop once clear of the loop again to allow operation of the Ground Frame. The end throw of the Mark 1 vehicles on the inside of the curved platform will result in the end doors being closer to the platform edge. The centre doors of these vehicles are permanently secured out of use. Train despatch will be from the guard to driver with assistance from other competent persons with monitoring, sighting, and relaying of hand signals as necessary. The guard's location towards the rear of the train, adjacent to the brake van, where the platform curvature is greatest will ease sighting distance. Northern Rail trains will normally continue to use Platform 1, where their vehicles are on the outside of the curve, although occasional use of the new platform is possible. The end doors on Classes 153, 155, 156 and 158 units and 14x vehicles currently used by Northern Rail will also be closer to the platform edge through the curvature, while these vehicles also benefit N/A RST 06/12/2013 Current N/A INS 11/09/2013 Current First Capital Connect Page 51 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-176-DEV Title Richmond Platforms 4 to 7 - platform edge position. RGS Clause 3.1 Scope Richmond Platforms 4 - 7. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-175-DEV London Bridge Station - Platforms 10 and 11, 12 and 13, 14 and 15 - platform curvature. Part 2; Clause 2.1.2 This issue applies throughout London Bridge Station (both High and Low Level). For Platforms 14 and 15, the length of sub1000 m radius is approximately 165 m. For Platforms 12 and 13, the length of sub-1000 m radius is approximately 160 m. For Platforms 10 and 11, the length of sub-1000 m radius is approximately 25 m. GMRT2044 Four Braking System Requirements and Performance for Multiple Units 13-167-DEV Unit 317 722, Difference between Service and Emergency Brake Pressures. 5.4.1 a) Unit 317 722. GKRT0075 Two Lineside Signal Spacing and Speed Signage 13-162-DEV Carmuirs East Jnc to Grangemouth Jnc, CEJ10 to GH6 braking distance for trains at 40 mph Appendix A. 2.3.3 Signal section CEJ10 to GH6, Carmuirs East Junction to Grangemouth Junction, Scotland Route. LOR : SSC109, ELR : PMT. Current Deviations Register as at 09 May 2016 Nature and Degree With input from DfT and Disabled Persons Transport Advisory Committee (DPTAC), LU has assessed all of the 248 platforms served by S Stock to see where through the application of reasonable effort, compliance with the RVAR (2010) at the two nominated S Stock doorways can be achieved. This is the equivalent platform length of approximately 29 metres. Compliance with Clause 4. 2. 3 of GI/RT7016 results in a stepping distance both horizontally and vertically greater than maximum permitted offset set by the RVAR (2010). The platform listed in Section 6 has heights and/or offsets that largely do not comply with the requirements of GI/RT7016 with respect to height (915 mm) and offset (730 mm). All platforms have datum plates fitted. Platform copers elsewhere on the platform have been moved back to accommodate S Stock. Under the platform copers, cable brackets have been found to infringe the lower sector structure gauge (Figure 1 GC/RT5212) by up to 50 mm and have been recessed into the platform wall where necessary to accommodate S Stock. S Stock has been designed to meet LU Standard S1156 platform offset of 711 mm and height of 950 mm. The scope of introduction of S Stock Within the Low Level platforms 14 and 15, the designed radii will be between 700 and 704 m. There is a length of straight in front of the new buffer stops at the London end and a length of 1000 m/1004 m radius curve at the country end. For Platforms 12 and 13, the radii are 750 and 753 m and, again, there is a length of straight (approximately 60 m) in front of the buffers stops. Platforms 10 and 11 contain a short length (circa 25 m) of 520 m radius at their eastern end. Clear route analysis has been run on Low Level tracks and platform stepping distances have been confirmed as acceptable for Low Level platforms. This layout will be installed with new components throughout incorporating track lateral resistance measures where necessary. The new platforms will be designed to the proposed track alignment design throughout. The proposed new track and platform alignment is not significantly different from the layout that exists today, meaning that station personnel and maintenance staff will be alert to the risks associated with curved platforms. It is believed that the current deviation delivers a solution with minimum safety risk. Risk Assessment/Safety Justification Applicant Organisation The proposal is to make a portion of Network Rail Richmond Platforms 4-7 on the Network Rail Richmond branch higher and closer to trains than standard, in order to provide level access to one particular type of rolling stock using the Branch - the new LU S stock. A similar amendment to Kew Gardens Platform 1 on the branch was approved in an earlier deviation submission. The 29 m long level access portion is designed to serve particular doors on the train matching similar raised platforms on other stations the stock calls at. However, the platforms are used by both LU and conventional railway rolling stock, and the design therefore retains compatibility to all vehicles that are authorised to use the Branch. Railway Group Standard GI/RT7016 requires offsets (in the plane of rail) of Y = 915 mm X = 730 mm for straight and level track. The LU RVAR standard requires offsets (in the plane of rail) of Y = 950 mm X = 711 mm for straight and level track. Along a 29 m length at Richmond Platforms 4-7 localised platform coper adjustments will be undertaken so that the step from an S Stock to the platform is less than 75 mm horizontally and 50 mm vertically. The table below shows the resultant average stepping The physical constraints of the London Network Rail Bridge Station area and the requirement to install 9No High Level platforms, 6No Low Level platforms and a new station building to accommodate twelve-car length trains drives some platform lines to be designed on radii that are tighter than the standard requires. Refer to Track team derogation application against NR/L2/TRK/2049 Ref KO2-RS-DEV-029. Platform widths have been designed to maximise pedestrian access and egress for current and anticipated passenger forecasts. Certificate Issue Date 11/12/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 13/11/2013 Deviation Status Current 09/12/2013 N/A INS 13/11/2013 Current AT/VI3174, Issue 2A, `VOI, Class 317 Electrical Multiple Unit (EMU), C4 Overhaul', Job No. V*S 0029 for the Class 317 Greater Anglia fleet, requires a brakes test, as summarised in Table 1 below. This shows that the emergency brake pressure can be 39% higher than the service brake pressure on the MS vehicle type (see 3 Max and Emergency Max), this being the highest differential for the fleet. [See Table - Class 317/3, 317/5. 317/7 and 317/8 Pressure Setting Table for Brake Test - Table 1 Extract from AT/VI3174, Issue 2A, `VOI, Class 317 EMU, C4 Overhaul', Job No. V*S 0029] For the Class 317 fleet, the unit differential of brake force between the step 3 service brake and the emergency brake is calculated using the following: Vehicle weight information: · DTS - 31. 4t · DTC 31. 6t · MS - 51. 3t · TS - 30. 2t Total unit weight = 144. 5t. Nominal brake cylinder pressure differences between step 3 brake pressure and emergency brake pressure: · DTS - 35% · DTC - 35% · MS - 35% · TS 34%. Calculation to determine overall unit braking performance: [(31. 4 x 35) + (31. 6 x 35) + (51. 3 x 35) + (30. 2 x 34)] / 144. 5 = 34. 8% overall effect on train braking performance. For Class 317 units, the Current standards for gradient of 1: 200 in Appendix A. 1 table, required braking distance of 990 m for trains at 40 mph. Existing Carmuirs East Jcn Signal CEJ10 to Grangemouth Jcn Signal GH6 is a threeaspect signal section that has a braking distance of 922 m on a gradient of 1: 210 which is 68 m short. To achieve compliance with current standards either, signals would require to be repositioning add signalling controls, adding an additional signal or line speed reduction. Moving CEJ10 towards Falkirk Camelon Station would convert the signal from a remote platform starter to a platform starter, and require CEJ10 AWS magnet to be moved and fitted with special suppression circuitry. It would also reduce the braking from CEJ9 which is on the limits of minimum spacing. CEJ9 signal rear is optimally positioned for freight train standage issues on the Up Grahamston line (clear of Larbert Junction S & C) so could not be moved. Moving GH6 away from Falkirk Camelon Station would compromise braking to GH4 signal for the 50 mph line speed. Other compliant technical options considered have included the introduction of an isolated four-aspect sequence that would convert CEJ9 signal to be an isolated signal, The alternative proposal will retain Abellio Greater Anglia Ltd compatibility and standardisation of the `Post C4 Brakes Test', for unit 317 722 with the rest of the Greater Anglia fleet. This alternative proposal will: Not have any detrimental effect on the safety of the railway system Retain the technical compatibility of the railway system, now and in the future Not have any implications associated with cost and service performance, including reliability and availability Not have any implications associated with other essential requirements, such as environmental protection and health. 27/11/2013 N/A RST 01/11/2013 Current Required braking distance between CEJ10 Network Rail and GH6 signals is only deficient by 68 m per current GK/RT0075. Signal sighting of both signals is compliant with current standards. CEJ10 signal has 212 m sighting, sufficient to give additional sighting at 40 mph to allow the driver to take action a minimum of 68 m on approach to signal thus mitigating short spacing to GH6 signal. It is not considered reasonable to attempt modify the current infrastructure to achieve compliance with current standards. This is on the grounds that there is little safety justification proportionate to the expenditure required to deliver compliance. There is no SPAD history at GH6. Only one SPAD recorded at CEJ10 in 2005, due to driver error. As such, there have been no SPADs or driver complaints related to signal spacing issues since that time, since 1997 when the signalling system was commissioned. Scotland Route has considered this site and the options to deliver signal spacing compliance. It is considered that the risks arising from this deviation are very low. Freight trains have been running over this section of line at speeds of 40 mph since 1997 without any recorded issues. Current signals were 14/11/2013 N/A CCS 31/10/2013 Current Page 52 Deviations Register RGS Number GMRT2400 RGS Issue Number Five RGS Title Certificate Number Engineering Design of On-track Machines in 13-161-DEV Running Mode Title Advance stage deviation for Plasser 94x4/4S Tamper. RGS Clause All clauses Scope Plasser &amp; Theurer 09-4x4/4S Tamping Machine Number 99 70 9128 001-3. The application is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. GMRT2400 Five Engineering Design of On-track Machines in 13-160-DEV Running Mode Advanced stage deviation to GM/RT2400 Issue 5 for High Output OLE Construction System (HOPS) Multi-Purpose Vehicles (MPVs). All clauses This application is to permit non-compliance with the RGS standard GM/RT2400 Issue 5 for the following MPV vehicles: Type 1 (SOPB): · 99 70 9131 010 - 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4 · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7. Type 3 (SNPB): · 99 70 9131 015 8 · 99 70 9131 018 - 2 · 99 70 9131 020 - 8 Type 4 (HNPB): · 99 70 9131 003 - 4. Type 5 (SORB): · 99 70 9131 014 - 1. GKRT0094 One Train Voice Radio Systems 13-159-DEV Advanced stage deviation to GK/RT0094 Issue 1 for High Output OLE Construction System (HOPS) MPVs. All clauses in GK/RT0094 Issue 1. This application is to permit noncompliance with the RGS standard GK/RT0094 Issue 1, for the following MPV vehicles: Type 1 (SOPB): · 99 70 9131 010 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4 · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7. Type 5 (SORB): · 99 70 9131 014 - 1. GERT8075 One AWS and TPWS Interface Requirements 13-158-DEV Advanced stage deviation to GE/RT8075 Issue 1 for High Output OLE Construction System (HOPS) MPVs. All clauses in GE/RT8075 Issue 1. This application is to permit noncompliance with the RGS standard GE/RT8075 Issue 1, for the following MPV vehicles: Type 1 (SOPB): · 99 70 9131 010 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4, · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7. Type 5 (SORB) : · 99 70 9131 014 - 1. Current Deviations Register as at 09 May 2016 Nature and Degree Due to it being notified as an National Technical Rule (NTR) by the competent authority in the UK, this standard has become applicable to the project following completion of the machine but prior to it being Authorised into service. The design of the machine is compliant to Issue 4 of GM/RT2400 and the other relevant RGS that have been excluded by issue 5 of GM/RT2400. Issue 5 of GM/RT2400 is a fundamental revision of the standard to align it with the prevailing Euronorm EN 14 033 and demonstrating compliance with the Issue 5 would require a complete new assessment. Therefore, complying with the new standard at this late stage of the project would require a huge amount of re-work and incur an unfeasibly long delay. The Department for Transport (DfT) plan to publish an updated list of NTRs in midOctober 2013, which is expected to replace GM/RT2400 Issue 4 by Issue 5. GM/RT2400 Issue 5 was issued in September 2013 but does not come into force until 07/12/2013l; however, once the DfT publish the updated National Technical Rule (NTR) list, GM/RT2400 Issue 5 will become the mandatory NTR and compatibility and the open points in the Technical Specifications for Interoperability (TSIs) can no longer be satisfied by compliance with GM/RT2400 Issue 4. The HOPS project is already at an advanced stage, with the first units already completed and expected to arrive for commissioning in the UK in early November. The design of the machine is compliant to Issue 4 of GM/RT2400 and the other relevant RGS that have now been excluded by Issue 5 of GM/RT2400. Issue 5 of GM/RT2400 is a fundamental revision of the standard to align it with the prevailing Euronorm EN 14033 and demonstrating compliance with the Issue 5 would require a complete new assessment and potentially design changes. Therefore, complying with the new standard at this late stage of the project would require a significant amount of The Department for Transport (DfT) plan to publish an updated list of NTRs in midOctober 2013, which is expected to replace GE/RT8080 Issue 1, GE/RT8081 Issue 1 and GE/RT8082 Issue 1, with GK/RT0094 Issue 1. GK/RT0094 Issue 1 was issued in March 2013 and came into force in June 2013. Once DfT publish the updated Notified Technical Rule (NTR) list, GK/RT0094 Issue 1 will become the mandatory NTR and the UK Global System for Mobile communications for Railways (GSM-R) requirements can no longer be satisfied by compliance with GE/RT8080 Issue 1, GE/RT8081 Issue 1 and GE/RT8082 Issue 1. The High Output (OLE) Construction System (HOPS) project commenced in late 2011 and the GSM-R equipment was procured early in the project. This equipment was procured against GE/RT8080, GE/RT8081 and GE/RT8082 and is the same as being fitted under the Network Rail managed National GSM-R project. The HOPs project is at an advanced stage, with the first units already completed and expected to arrive for commissioning in the UK in early November. The design and assessment of the GSM-R equipment for the HOPS Multi-Purpose The Department for Transport (DfT) plan to publish an updated list of NTRs in midOctober 2013, which is expected to replace GE/RT8030 Issue 4 and GE/RT8035 Issue 2, with GE/RT8075 Issue 1. GE/RT8075 Issue 1 was issued in September 2013 but does not come into force until 07/12/2013, however, once the DfT publish the updated NTR list, GE/RT8075 Issue 1 will become the mandatory NTR and the open points in the TSIs regarding AWS/TPWS can no longer be satisfied by compliance with GE/RT8030 Issue 4 and GE/RT8035 Issue 2. The HOPS project is already at an advanced stage, with the first units already completed and expected to arrive for commissioning in the UK in early November. The design and assessment of the AWS/TPWS equipment for the HOPS MPVs has been based on the requirements of GE/RT8030 Issue 4 and GE/RT8035 Issue 2; reassessment work would therefore be necessary to demonstrate compliance with GE/RT8075 Issue 1 at this late stage in the project. Additionally, design and manufacturing changes might also be required. Risk Assessment/Safety Justification The machine will enter into service with the same level of compliance as all other ontrack machines in the UK as GM/RT2400 Issue 5 is not yet in force as a Railway Group Standard. Applicant Organisation Plasser UK Ltd Certificate Issue Date 27/11/2013 Certificate End Date N/A Lead SC RST Lead SC Approval Date 01/11/2013 Deviation Status Current The MPVs will be compliant with Windhoff Bahn- und GM/RT2400 Issue 4, subject to the Anlagentechnik GmbH deviations 12/160/DGN and 12/161/DGN which have already been granted. Windhoff Bahn does not perceive an inacceptable risk since that what is demonstrated being in compliance with the requirements of GM/RT2400 Issue 4 until December 2013 is also still valid after that date. 16/01/2014 N/A RST 01/11/2013 Current There is no predicted adverse impact arising from continued use of the current standards. Windhoff Bahn- und Anlagentechnik GmbH 18/12/2013 N/A CCS 31/10/2013 Current There is no predicted adverse impact arising from continued use of the current standards. Windhoff Bahn- und Anlagentechnik GmbH 18/12/2013 N/A CCS 31/10/2013 Current Page 53 Deviations Register RGS Number GMRT2473 RGS Issue Number Two RGS Title Power Operated External Doors on Passenger Carrying Rail Vehicles Certificate Number 13-157-DEV Title RGS Clause Supply of seats for 20 new Class 350 All requirements in GM/RT2473 Issue 2. Electric Multiple Units (EMU) to a preexisting design in accordance with Siemens Strategy for the Introduction of Additional Vehicles to an Existing Design, 27/01/2012 Issue 1. Scope · 10 x Class 350/3 for First Transpennine Express · 10 x Class 350/4 for London Midland. GMRT2100 Five Requirements for Rail Vehicle Structures 13-156-DEV Supply of seats for 20 new Class 350 6.2.1.2 and 6.2.4.1-3 Electric Multiple Units (EMU) to a preexisting design in accordance with Siemens Strategy for the Introduction of Additional Vehicles to an Existing Design, 27/01/2012 Issue 1. · 10 x Class 350/3 for First Transpennine Express · 10 x Class 350/4 for London Midland. GMRT2100 Five Requirements for Rail Vehicle Structures 13-155-DEV Derogation for the manufacture and supply of new Class 350 Electric Multiple Units (EMU) with vehicle bodyshell structures, bogies and glazing manufactured in accordance with GM/RT2100 Issue 3. Supply of 20 new four-car EMUs. GERT8075 One AWS and TPWS Interface Requirements 13-153-DEV Advance stage deviation for AWS/TPWS on All clauses. Plasser 09-4x4/4S Tamper. Current Deviations Register as at 09 May 2016 2.1.1.4, 2.1.2.1, 2.1.5.1c); 3.1.1, 3.2.2, 3.3.1.1, 3.3.3.1a); 5.2.2, 5.3.2, 5.3.3.2, 5.3.3.3, 5.3.4; 6.5.2.1, 6.9.1.2. Plasser &amp; Theurer 09-4x4/4S Tamping Machine Number 99 70 9128 001-3. Nature and Degree This is an update to derogation 12/171/DGN (which has already been granted against GM/RT2100 Issue 4) to reflect that GM/RT2100 has been up-issued to Issue 5 since the previous derogation was granted. There have been no technical changes to either the nature of the non-compliance or the requirements against which the derogation is being sought. Siemens are in the process of supplying of twenty new fourcar EMUs that, with the exception of certain internal layout differences and other minor changes, will be identical to the existing Class 350/2 (`Desiro') EMUs presently operated by London Midland. A strategy outlining approach to be taken in the assessment of the new units, including the methodology and actions required to meet the approvals requirements for the introduction of the new EMUs of an existing design into passenger service, has been approved by the Rolling Stock Standards Committee at its meeting held on 17/02/2012. The strategy requires consideration of new standards and changes to existing standards made in the period between the introduction of the original vehicles and the present. The strategy and some particularly high risk (to This is an update to derogation 12/171/DGN (which has already been granted against GM/RT2100 Issue 4) to reflect that GM/RT2100 has been up-issued to Issue 5 since the previous derogation was granted. There have been no technical changes to either the nature of the non-compliance or the requirements against which the derogation is being sought. Siemens are in the process of supplying of twenty new fourcar EMUs that, with the exception of certain internal layout differences and other minor changes, will be identical to the existing Class 350/2 (`Desiro') EMUs presently operated by London Midland. A strategy outlining approach to be taken in the assessment of the new units, including the methodology and actions required to meet the approvals requirements for the introduction of the new EMUs of an existing design into passenger service, has been approved by the Rolling Stock Standards Committee at its meeting held on 17/02/2012. The strategy requires consideration of new standards and changes to existing standards made in the period between the introduction of the original vehicles and the present. The strategy and some particularly high risk (to This is an update to derogation 12/014/DGN (which has already been granted against GM/RT2100 Issue 4) to reflect that GM/RT2100 has been up-issued to Issue 5 since the previous derogation was granted. There have been no technical changes to either the nature of the non-compliance or the requirements against which the derogation is being sought. Siemens are in the process of supplying 20 new four-car EMUs that, with the exception of certain internal layout differences and other minor changes, will be identical to the existing Class 350/2 (`Desiro') EMUs operated by London Midland. The new EMUs shall be operated by London Midland (10 four-car units) and First Transpennine Express (10 four-car units) along their respective operational routes. Derogation 12/014/DGN has already been granted for this project, against the same requirements in GM/RT2100 Issue 4. Because GM/RT2100 has been up-issued to Issue 5 since the previous derogation was granted, Siemens need to up-issue this derogation to meet the ORR requirement for authorisation to place in to service against the latest NNTR list. There are no changes to the standards requirements that are the subject of this The application is for a project requiring authorisation for placing in service under the Railways (Interoperability) Regulations 2011. The Department for Transport (DfT) Interoperability help note on 'Dispensations from Notified National Technical Rules' sets out how an industry process can be used by projects to obtain deviations from a national rule. The process for obtaining deviations from RGSs in accordance with the RGS Code is recognised as an established industry process in this context. Due to it being notified as a Notified Technical Rule (NTR) by the competent authority in the UK, this standard has become applicable to the project following completion of the machine but prior to it being authorised into service. The design of the machine incorporates AWS/TPWS equipment which is compliant to GE/RT8030 Issue 4 and GE/RT8035 Issue 2 subject to deviations 12/176/DGN and 12/177/DGN due to equipment compliant to the standards current at the time of construction not being available. Complying with the new standard at this late stage of the project would require significant additional work and incur a sizable delay. Risk Assessment/Safety Justification There is no predicted adverse impact arising from the introduction of the revised seat fixing arrangements of the alternative seating arrangements. Applicant Organisation Siemens plc Certificate Issue Date 20/11/2013 Certificate End Date N/A Lead SC RST Lead SC Approval Date 01/11/2013 Deviation Status Current There is no predicted adverse impact arising from the introduction of the revised seat fixing arrangements of the alternative seating arrangements. Siemens plc 20/11/2013 N/A RST 01/11/2013 Current The proposed new EMUs are mechanically Siemens plc similar to the existing Class 350/2 EMUs operated by London Midland, which were manufactured in 2008-2009 and were proven to be demonstrably compliant with GM/RT2100 Issue 3. Given that the Class 350/2 fleet is a relatively modern design and the proposed additional vehicles will be very similar to these vehicles, it can be concluded that the introduction of the additional trains on London Midland and First Transpennine Express routes will not introduce any adverse risks to third parties, and the risks to passengers will be comparable to existing trains. Siemens confirm that they have not raised any concerns regarding the structural integrity of the Class 350/2 fleet currently in passenger service. Please refer to `Supporting Paper for LM TPE Class 350 Issue 1' for full details. 20/11/2013 N/A RST 01/11/2013 Current The machine will enter into service with Plasser UK Ltd AWS/TPWS equipment identical to that fitted to the majority of rolling stock in the UK as GE/RT8075 is not yet in force as a Railway Group Standard and equipment fully compliant to GE/RT8030 Issue 4 and GE/RT8035 Issue 2 has only recently become available. 27/11/2013 N/A CCS 31/10/2013 Current Page 54 Deviations Register RGS Number GERT8075 RGS Issue Number One RGS Title AWS and TPWS Interface Requirements Certificate Number 13-152-DEV Revised 22-11-2013 Title Derogation for the manufacture and supply of new Class 350 Electric Multiple Units (EMU) with AWS/TPWS equipment manufactured in accordance with GE/RT8030 Issue 4 and GE/RT8035 Issue 2. RGS Clause All requirements in GE/RT8075 Issue 1. Scope · 10 x Class 350/3 for First Transpennine Express · 10 x Class 350/4 for London Midland. GKRT0192 Two Level Crossing Interface Requirements 13-151-DEV Signal TEB1429 in close proximity to Havensmouth level crossing. 2.1.1.3 a) This application applies only to signal TEB1429 which is proposed to be located 4 m from the crossing edge. GKRT0192 Two Level Crossing Interface Requirements 13-150-DEV Signals TEB1361 and TEB1363 in close proximity to Berwick level crossing. 2.1.1.3 a) This application applies to signals TEB1361 Placing new signal TEB1361 at 25 m from and TEB1363 which will be positioned 8 m the crossing is not possible due to the and 5 m respectively from Berwick MCB presence of the station buildings and the level crossing. 'Out of Hours' station exit. The first location that TEB1361 could occupy is at 29 m from the crossing - this would necessitate moving the stopping position plus a platform extension of circa 28 m, the total cost being œ420,000. The position for signal TEB1363 is designed to be in parallel with TEB1361, and allows a three-car train to stand between it and the stopping position in the up direction. To enable TEB1363 to be installed at 25 m from the level crossing, the platform would have to be extended by a similar amount to that described for TEB1361 above and with a similar cost. As an alternative to placing TEB1361 in a compliant position, configuring the signalling system to allow movement authorities to pass the signal in rear (TEB1359) only when the level crossing is closed to road traffic was considered. It was discounted as it would delay trains approaching the station until the crossing was closed, and increase the crossing closure time affecting road users adversely. GKRT0192 Two Level Crossing Interface Requirements 13-149-DEV Signal TEB1378 in close proximity to Hampden Park level crossing. 2.1.1.3 a) This application applies only to signal TEB1378 which is proposed to be located 23 m from the crossing edge. Current Deviations Register as at 09 May 2016 Nature and Degree The Department for Transport (DfT) plan to publish an updated list of NNTRs on 11/10/2013, which is expected to replace GE/RT8030 Issue 4 and GE/RT8035 Issue 2, with GE/RT8075 Issue 1. GE/RT8075 Issue 1 was issued in September 2013 but does not come into force until 07/12/2013. This is after the date that the units are expected to have been granted authorisation by the Office of Rail Regulation (ORR). GE/RT8030 Issue 4 and GE/RT8035 Issue 2 will not be withdrawn until 07/12/2013. However, once the DfT publish the updated NNTR list, GE/RT8075 Issue 1 will become a mandatory NNTR and the open points in the TSIs regarding AWS/TPWS can no longer be satisfied by compliance with GE/RT8030 Issue 4 and GE/RT8035 Issue 2. The Class 350/3 and 350/4 project is already at an advanced stage, with the first units already built and expected to arrive for commissioning in the UK in early November. A draft version of the Technical File has already been submitted to the ORR for review. The design and assessment of the AWS/TPWS equipment for the Class 350/3 and 350/4 fleets has been based on the requirements of GE/RT8030 Issue 4 and GE/RT8035 Issue 2; reassessment work Placing new signal TEB1429 at 25 m from the crossing is not possible as after considering stopping positions, a platform extension of 20 m at a cost of œ15,000 per linear metre would be required, and the total cost of œ300,000 is considered too high. Configuring the signalling system to allow movement authorities to pass the signal in rear (TEB1427) only when the level crossing is closed to road traffic is considered unacceptable due to the length of travelling time from the signal to the station combined with the platform dwell time. Signal TEB1378 would require a new substructure which would necessitate works on the platform and shortening the available platform length to maintain the stopping distance from the signal. To preserve the operational length of the platform, it would need to be extended, which would necessitate relocation of the reversing crossover at the south end of the station. As an alternative to relocation of signal TEB1378, configuring the signalling system to only allow trains to pass the signal in rear when the crossing has been closed to road traffic was considered. It was discounted as it would increase the crossing closure time unacceptably. Risk Assessment/Safety Justification There is no predicted adverse impact arising from continued use of the current standards. Applicant Organisation Siemens plc Certificate Issue Date 20/11/2013 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 31/10/2013 Deviation Status Current The `Stowmarket Controls' are designed Network Rail such that an overrunning train should only reach the crossing after it has gone through a full light sequence (I. e. 3s amber lights followed by 5s red lights). In line with Network Rail standards, it is not proposed to lower the barriers in conjunction with the control. Havensmouth crossing is, due to the road width, proposed to be a two-barrier crossing and, therefore, automatically lowering the barriers presents a risk of trapping users. It is considered that the infrequent application of the control and the nature of the crossing use will mean that operating the lights without lowering the barriers is unlikely to create or compound crossing misuse. The analysis of the proposed arrangements and consideration of the alternatives is detailed in document reference RAR-NWR-119966-64195265 Version 3, "Havensmouth MG Level Crossing Renewal, Crossing and Signalling Assessment". 27/02/2014 N/A CCS 31/10/2013 Current The `Stowmarket Controls' are designed Network Rail such that an overrunning train should only reach the crossing after it has gone through a full light sequence (I. e. 3s amber lights followed by 5s red lights). In addition, the barriers will be lowered at the end of the light sequence, which is consistent with a normal operating sequence; this is primarily to ensure a consistent user experience. The TSS loops provided at signals TEB1361 and TEB1363 will mitigate the start-away SPAD risk by virtue of minimising the speed and distance of an overrunning train starting from rest at the station. In addition, on occupying the replacing track section, the red road lights will operate immediately in line with standard controls. The Up direction car stop marks will be located so that the driver of a train reversing on signal TEB1363 will have good sight of the signal. This signal will only be used at times of perturbation and not as part of normal timetabled operation and, therefore, there will be greater supervision of the move by the signaller. The analysis of the proposed arrangements and consideration of the alternatives is detailed in document reference RAR-NWR-119966-64195276 Version 3, "Berwick MCB Level Crossing TPWS will achieve some mitigation against Network Rail a potential overrun of the signal by at least reducing the speed of an overrunning train and, in some circumstances, will stop the train before it reaches the crossing. It has been selected in the absence of the other available control measures being suitable for the crossing, given its level of usage and misuse. The analysis of the proposed arrangements and consideration of the alternatives is detailed in document reference RAR-NWR-119966-64195267 Version 3, "Hampden Park MCB Level Crossing Renewal, Crossing and Signalling Assessment". 27/02/2014 N/A CCS 06/02/2014 Current 27/02/2014 N/A CCS 06/02/2014 Current Page 55 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-143-DEV Title Kew Gardens Station Platform 1 - platform edge position RGS Clause 3.1.1 and 3.2.1 GIRT7016 Four Interface between Station Platforms, Track and Trains 13-142-DEV Pegswood Station (Down Line) Platform Two - Platform Recess. 11.1.4 GIRT7016 Four Interface between Station Platforms, Track and Trains 13-140-DEV Thirsk Station (Down Line) Platform Two Platform Recess. 11.1.4 GIRT7016 Four Interface between Station Platforms, Track and Trains 13-139-DEV Thirsk Station (Up Line) Platform One Platform Recess. 11.1.4 Current Deviations Register as at 09 May 2016 Scope Kew Gardens Station Platform 1. Kew Gardens Station Platform 2 will not receive raised portions due to the tight curvature at the location of the raised portion. Nature and Degree With input from DfT and DPTAC, LUL, has assessed all 248 platforms served by S Stock to see where, through the application of reasonable effort, compliance with the Rail Vehicle Accessibility (RVA) Regulations (2010) at the two nominated S Stock doorways can be achieved. This is the equivalent platform length of approximately 29 metres. Compliance with GI/RT7016 Clauses 3. 1. 1 and 3. 2. 1 results in a stepping distance both horizontally and vertically greater than maximum permitted offset set by the RVA Regulations (2010). Platform copers elsewhere on Platform 1 at Kew Gardens have been moved back in places to accommodate S Stock. The scope of introduction of S Stock by LUL does not provide reasonable opportunity to rebuild all of the existing platform. The revised profile of the platforms will prevent certain current stock (that is currently permitted elsewhere on the network but not on the Richmond Branch) and possibly some future stock from achieving compatibility to use this Branch if this is requested by a Train Operating Company (TOC) at some stage in the future. There are designed special reduced clearances following these RVAR platform modification works at Kew Gardens. This scheme is the result of an initiative led Within the scope of the project, it would not by the Department of Transport (DfT) to be reasonably practicable to provide a bring about the specification, design, compliant solution at the station platform. It construction and entry into service of routes is not deemed as a reasonable opportunity to accommodate larger intermodal traffic to comply with the standard as the costs of freight trains. W12 2nd Generation and compliance would place unreasonable costs W6a lower sector gauges are required to on the project and industry. The cost of a enable the movement of 9'6" high containers compliant solution (design and execution) on standard height wagons without any would be difficult to quantify, however the operating or speed restrictions. The cost of simply building a compliant solution platform alterations are a direct result of a would be circa œ800,000. This does not gauge improvement portfolio across a take into account the possessions, waste, number of projects to clear for W12 2nd compensation and additional service costs, Generation and W6a lower sector gauges. which could easily estimated to be circa This deviation application applies to the œ1,000,000. The cost of our alternative nonDown Platform (No. 2) Pegswood Station compliant solution (design and execution) is only and, specifically, non-compliance to the circa œ216,000. safe recess ("Z"). In principle, the works will have moderate effect on the recess. The deviation application is required as Network Rail does not plan to resolve the existing noncompliance. The proposed design comprises both an element of Civils works, to the existing coper positions, as well as track work. The existing recess "Z" will be affected by the proposed works, but this effect is extremely limited. Overall, the existing platform has a 100% non-compliant recess over its "usable" operational length; This scheme is the result of an initiative led Within the scope of the project, it would not by the Department of Transport (DfT) to be reasonably practicable to provide a bring about the specification, design, compliant solution at the station platform. It construction and entry into service of routes is not deemed as a reasonable opportunity to accommodate larger intermodal traffic to comply with the standard as the costs of freight trains. W12 2nd Generation and compliance would place unreasonable costs W6a lower sector gauges are required to on the project and industry. However, the enable the movement of 9'6" high containers project will reduce the severity of the existing on standard height wagons without any non-compliances. The cost of a compliant operating or speed restrictions. The solution (design and execution) would be platform alterations are a direct result of a difficult to quantify; however, the cost of gauge improvement portfolio across a simply building a compliant solution would number of projects to clear for W12 2nd be circa œ1,000,000. This does not take Generation and W6a lower sector gauges. into account the possessions, waste, This deviation application applies to the compensation and additional service costs, Down Platform (No. 2) Thirsk Station only, which could easily estimated to be circa and specifically non-compliance to the safe œ1,500,000. The cost of our alternative nonrecess ("Z"). In principle, the works will compliant solution (design and execution) is have moderate effect on the recess. The circa œ210,000. deviation application is required as Network Rail does not plan to resolve the existing noncompliance. The proposed design comprises both an element of Civils works, to the existing coper positions, as well as track work. Safe Recess (Clause 11. 1. 4, Sub-clause 11. 1. 4. 1) The existing recess "Z" will be affected by the proposed works, but this effect is extremely limited. Overall, the existing platform is mostly compliant with This scheme is the result of an initiative led Within the scope of the project, it would not by the Department of Transport (DfT) to be reasonably practicable to provide a bring about the specification, design, compliant solution at the station platform. It construction and entry into service of routes is not deemed as a reasonable opportunity to accommodate larger intermodal traffic to comply with the standard, as the costs of freight trains. W12 2nd Generation and compliance would place unreasonable costs W6a lower sector gauges are required to on the project and industry. However, the enable the movement of 9'6" high containers project will reduce the severity of the existing on standard height wagons without any non-compliances. The cost of a compliant operating or speed restrictions. The solution (design and execution) would be platform alterations are a direct result of a difficult to quantify; however, the cost of gauge improvement portfolio across a simply building a compliant solution would number of projects to clear for W12 2nd be circa œ1,000,000. This does not take Generation and W6a lower sector gauges. into account the possessions, waste, This deviation application applies to the Up compensation and additional service costs, Platform (No. 1) Thirsk Station only and which could easily be estimated to be circa specifically to non-compliance to the safe œ1,500,000. The cost of our alternative nonrecess ("Z"). In principle, the works will compliant solution (design and execution) is have moderate effect on the recess. The circa œ210,000. deviation application is required as we do not plan to resolve the existing noncompliance. The proposed design comprises both an element of Civils works, to the existing coper positions, as well as track work. Safe Recess (Clause 11. 1. 4, Sub-clause 11. 1. 4. 1): The existing recess "Z" will be affected by the proposed works, but this effect is extremely limited. Overall the existing platform has a 100% non- Risk Assessment/Safety Justification The proposal is to make a portion of Kew Gardens Platform 1 on the Network Rail Richmond Branch higher and closer to trains than standard, in order to provide level access to one particular type of rolling stock using the branch - the new LU S stock. Similar amendments to other platforms on the branch will form a subsequent derogation submission. The 29 m long level access portion is designed to serve particular doors on the train, matching similar raised platforms on other stations the stock calls at. However, the platform is used by both LUL and conventional railway rolling stock, and the design therefore retains compatibility to all vehicles that are authorised to use the branch. Group Standard GI/RT7016 requires offsets (in the plane of rail) of Y = 915 mm X = 730 mm for straight and level track. The LUL RVAR Standard requires offsets (in the plane of rail) of Y = 950 mm X = 711 mm for straight and level track. Along a 29 m length at Kew Gardens Platform 1, localised platform coper adjustments will be undertaken so that the step from a S Stock to the platform is less than 75 mm horizontally and 50 mm vertically. The table below shows the resultant average stepping distance for each The impact of the proposed alternative solution is low, as it maintains the existing situation. The risk and impact to the various stakeholders is assessed in more details within the risk assessment, Appendix D. The analysis has taken into to account the most frequently used platform length. Most trains stop within this length of platform; chainage 998 m to 1090 m. Operationally, the station has a total of 1,904 entries and exits per annum or five people per day (Office of Rail Regulation (ORR) estimates). Stepping distances have been assessed for relevant rolling stock. The stepping distances will remain in the stepping triangle with a maximum worsenment of 24 mm horizontal and 11 mm vertical. In some locations, stepping distances will be improved by up to 42 mm horizontal and 12 mm vertical. In order to achieve the objectives of the project as stated above, it is deemed to be unreasonable for the project to incur such alteration costs when the proposed alternative works could be classed as a platform modification. To correct the existing non-compliances, the project would incur significant additional costs. Overall, the "safe space" dimension between the running edge and the vertical Impact: The impact of the proposed alternative solution is low, as it maintains or betters the existing situation. The risk and impact to the various stakeholders is assessed in more details within the risk assessment, Appendix D. The analysis has taken into account the most frequently used platform length. Most trains stop within this length of platform; chainage 1005 m to 1150 m. Operationally, the station has a total of 188,484 entries and exits per annum, or 516 people per day (Office of Rail Regulation (ORR) estimates). Stepping distances have been considered and there are minor changes (in many cases improvements) as a result of the platform alterations, which are supported by the affected railway undertakings. Rationale: Project Scope: In order to achieve the objectives of the project, as stated above, it is deemed to be unreasonable for the project to incur such alteration costs when the proposed alternative works could be classed as a platform modification. To correct the existing non-compliances, the project would incur significant additional costs. The reduced recess of 270 mm, occurs on a part of the platform within the section of platform where the majority of trains stop. Overall, Impact: The impact of the proposed alternative solution is low, as it maintains or betters the existing situation. The risk and impact to the various stakeholders is assessed in more details within the risk assessment, Appendix D. The analysis has taken into account the most frequently used platform length. Most trains stop within this length of platform; chainage 995 m to 1180 m. Operationally, the station has a total of 188,484 entries and exits per annum or 516 people per day (Office of Rail Regulation (ORR) estimates). Stepping distances have been considered and there are minor changes (in many cases improvements) as a result of the platform alterations, which are supported by the affected railway undertakings. Rationale: Project Scope: In order to achieve the objectives of the project, as stated above, it is deemed to be unreasonable for the project to incur such alteration costs when the proposed alternative works could be classed as a platform modification. To correct the existing non-compliances, the project would incur significant additional costs. The reduced recess of 190 mm occurs on a part of the platform within the section of platform where the majority of trains stop. Overall, Applicant Organisation Network Rail Certificate Issue Date 20/01/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 11/09/2013 Deviation Status Current Network Rail 08/04/2014 N/A INS 11/09/2013 Current Network Rail 15/05/2014 N/A INS 11/09/2013 Current Network Rail 15/05/2014 N/A INS 11/09/2013 Current Page 56 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-137-DEV Title Moorthorpe Station (Down Line) Platform Two - Platform Recess. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-136-DEV Moorthorpe Station (UP Line) Platform One - 11.1.4 Platform Recess. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-133-DEV Dinsdale Station (Down Line) Platform Two - 11.1.4 Platform Recess. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-129-DEV Thornaby Station (Down Line) Platform Two - 11.1.4 Platform Recess. Current Deviations Register as at 09 May 2016 RGS Clause 11.1.4 Scope This scheme is the result of an initiative led by the Department of Transport (DfT) to bring about the specification, design, construction and entry into service of routes to accommodate larger intermodal traffic freight trains. W12 2nd Generation and W6a lower sector gauges are required to enable the movement of 9'6" high containers on standard height wagons without any operating or speed restrictions. The platform alterations are a direct result of a gauge improvement portfolio across a number of projects to clear for W12 2nd Generation and W6a lower sector gauges. This deviation applies to the Down platform (No. 2) Moorthorpe Station only. Specifically, it is a non-compliance to the safe recess ("Z"). In principle, the works will have negligible effect on the existing recess. The deviation is required as Network Rail does not plan to resolve the existing noncompliance. The proposed design comprises both an element of civils works to the existing coper positions, as well as track work. The existing recess "Z" will be affected by the proposed works, but this effect is extremely limited. Overall, the existing platform is 100% non-compliant over its "usable" operational length; the This scheme is the result of an initiative led by the Department of Transport (DfT) to bring about the specification, design, construction and entry into service of routes to accommodate larger intermodal traffic freight trains. W12 2nd Generation and W6a lower sector gauges are required to enable the movement of 9'6" high containers on standard height wagons without any operating or speed restrictions. The platform alterations are a direct result of a gauge improvement portfolio across a number of projects to clear for W12 2nd Generation and W6a lower sector gauges. This deviation applies to the Up Platform (No. 1) Moorthorpe Station only. Specifically, it is a non-compliance to the safe recess ("Z"). In principle, the works will have negligible effect on the existing recess. The deviation is required as Network Rail does not plan to resolve the existing noncompliance. The proposed design comprises both an element of civils works, to the existing coper positions, as well as track work. The existing recess "Z" will be affected by the proposed works, but this effect is extremely limited. Overall, the existing platform has a compliant recess of 13% over its "usable" operational length; the Seven Sisters Station / Platform 2 temporary hoarding only. Nature and Degree Within the scope of the project, it would not be reasonably practicable to provide a compliant solution at the station platform. It is not deemed as a reasonable opportunity to comply with the standard as the costs of compliance would place unreasonable costs on the project and industry. The cost of a compliant solution (design and execution) would be difficult to quantify; however, the cost of simply building a compliant solution would be circa œ1,500,000. This does not take into account the possessions, waste, compensation and additional service costs, which could easily be estimated to be circa œ2,500,000. The cost of Network Rail's alternative non-compliant solution (design and execution) is circa œ100,000. This scheme is the result of an initiative led by the Department of Transport (DfT) to bring about the specification, design, construction and entry into service of routes to accommodate larger intermodal traffic freight trains. W12 2nd Generation and W6a lower sector gauges are required to enable the movement of 9'6" high containers on standard height wagons without any operating or speed restrictions. The platform alterations are a direct result of a gauge improvement portfolio across a number of projects to clear for W12 2nd Generation and W6a lower sector gauges. This deviation application applies to the Down Platform (No. 2) at Thornaby Station only, specifically non-compliance to the safe recess ("Z"). In principle, the works will have a negligible effect on the recess. The deviation application is required as Network Rail do not plan to resolve the existing noncompliance. The proposed design comprises both an element of Civils works, to the existing coper positions, as well as track work. The existing recess dimensions range from 255 mm to 339 mm and are mostly around 300 mm. The proposed recess dimensions range from 277 mm to 396 mm and are improved in most cases. Within the scope of the project, it would not be reasonably practicable to provide a compliant solution at the station platform. It is not deemed as a reasonable opportunity to comply with the standard as the costs of compliance would place unreasonable costs on the project and industry. However, the project will reduce the severity of the existing non-compliances. The cost of a compliant solution (design and execution) would be difficult to quantify; however, the cost of simply building a compliant solution would be circa œ1,000,000. This does not take into account the possessions, waste, compensation and additional service costs, which could easily be estimated to be circa œ1,500,000. The cost of our alternative noncompliant solution (design and execution) is circa œ120,000. Within the scope of the project, it would not be reasonably practicable to provide a compliant solution at the station platform. It is not deemed as a reasonable opportunity to comply with the standard as the costs of compliance would place unreasonable costs on the project and industry. The cost of a compliant solution (design and execution) would be difficult to quantify, however the cost of simply building a compliant solution would be circa œ1,500,000. This does not take into account the possessions, waste, compensation and additional service costs, which could easily be estimated to be circa œ2,500,000. The cost of Network Rail's alternative non-compliant solution (design and execution) is circa œ100,000. Within the scope of the project, it would not be reasonably practicable to provide a compliant solution at the station platform. It is not deemed as a reasonable opportunity to comply with the standard as the costs of compliance would place unreasonable costs on the project and industry. The cost of a compliant solution (design and execution) would be difficult to quantify, however the cost of simply building a compliant solution would be circa œ1,500,000. This does not take into account the possessions, waste, compensation and additional service costs, which could easily be estimated to be circa œ2,500,000. The cost of our alternative noncompliant solution (design and execution) is circa œ150,000. Risk Assessment/Safety Justification Impact: The impact of the proposed alternative solution is low, as it maintains the existing situation. The risk and impact to the various stakeholders is assessed in more detail within the risk assessment, Appendix D. The analysis has taken into account the most frequently used platform length. Most trains stop within this length of platform; chainage 1020 m to 1100 m. Over this length, the recess overall is improved. Operationally, the station has a total of 200,258 entries and exits per annum or 549 people per day (Office of Rail Regulation estimates). Stepping distances have been assessed for relevant rolling stock. The stepping distances will remain in the stepping triangle with a maximum worsenment of 51 mm horizontal and 45 mm vertical. Where most trains stop, there is a betterment of 28 mm horizontal and, in most cases, less than 10 mm effect on vertical. Rationale: In order to achieve the objectives of the project as stated above, it is deemed to be unreasonable for the project to incur such alteration costs when the proposed alternative works could be classed as a platform modification. To correct the existing non-compliances, the project would incur significant additional costs. See Impact: The impact of the proposed alternative solution is low, as it essentially maintains the existing situation. The risk and impact to the various stakeholders is assessed in more details within the Risk Assessment, Appendix D of the supplementary information. The analysis has taken into account the most frequently used platform length. Most trains stop within this length of platform; chainage 1020m to 1100m. Operationally, the station has a total of 200,258 Entries and Exits per annum or 549 people per day (ORR Estimates). Stepping distances have been assessed for relevant rolling stock. The stepping distances will remain in the stepping triangle with a maximum worsenment of 41 mm horizontal and 51 mm vertical. In some locations, stepping distances will be improved by up to 12 mm horizontal and 39 mm vertical. Rationale: In order to achieve the objectives of the project, as stated above, it is deemed to be unreasonable for the project to incur such alteration costs when the proposed alternative works could be classed as a platform modification. To correct the existing non-compliances the project would incur significant additional costs. The alternative solution is considered Stepping distances: Stepping distance analysis has been carried out for the potentially affected trains. The worst case stepping distance will be marginally improved and the typical stepping distance will be marginally worsened. The propose platform edge position will be compliant in terms of height and offset. Impact: The impact of the proposed alternative solution is low. The risk and impact to the various stakeholders is assessed in more details within the Risk Assessment, Appendix D. The analysis has taken into to account the most frequently used platform length. Most trains stop within this length of platform; chainage 1025 m to 1075 m. Operationally, the station has a total of 28,378 entries and exits per annum or 78 people per day (Office of Rail Regulation (ORR) estimates). Rationale: Project Scope: "This scheme is the result of an initiative led by the Department of Transport (DfT) to bring about the specification, design, construction and entry into service of routes to accommodate larger intermodal traffic freight trains. W12 2nd Generation and W6a lower sector gauges are required to enable the movement of 9'6" high containers on standard height wagons without any The impact of the proposed alternative solution is low, as it maintains or improves the existing situation. The risk and impact to the various stakeholders is assessed in more details within the Risk Assessment, Appendix D. The analysis has taken into to account the most frequently used platform length. Most trains stop within this length of platform; chainage 1030 m to 1105 m. Operationally, the station has a total of 574,596 entries and exits per annum or 1575 people per day (Office of Rail Regulation (ORR) estimates). Stepping distances have been assessed for relevant rolling stock. In achieving a standard platform offset (with tolerances) for 2. 6 m wide containers, stepping distances have increased. Class 14x units usually stop at the straight section of platform where stepping distances are not affected by curvature. In order to achieve the objectives of the project, as stated above, it is deemed to be unreasonable for the project to incur such alteration costs when the proposed alternative works could be classed as a platform modification. To correct the existing non-compliances, the project would incur significant additional costs. Overall, the "safe space" dimension between the running edge and the vertical Applicant Organisation Network Rail Certificate Issue Date 12/03/2014 Certificate End Date N/A Lead SC INS Lead SC Approval Date 11/09/2013 Deviation Status Current Network Rail 12/03/2014 N/A INS 11/09/2013 Current Network Rail 29/10/2013 N/A INS 11/09/2013 Current Network Rail 05/06/2014 N/A INS 11/09/2013 Current Page 57 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-126-DEV Title RGS Clause Richmond Station platforms 4, 5, 6 &amp; 7. 11.1.3 GIRT7016 Four Interface between Station Platforms, Track and Trains 13-124-DEV Paddington Station realigned Platforms 12 and 14 - reduced platform width at column. 6.2.2 GIRT7016 Four Interface between Station Platforms, Track and Trains 13-118-DEV Proposed Low Moor New Station (New Up &amp; Down Side Platforms) - platform radius. 2.1.2 GMRT2100 Five Requirements for Rail Vehicle Structures 13-117-DEV Rail vehicle interior construction - loading requirements for glazed elements. 6.5.2.2 Current Deviations Register as at 09 May 2016 Scope Nature and Degree Richmond Station platforms 4, 5, 6 &amp; 7. Existing situation: The cross falls gradient of the existing Richmond platforms within the area of the proposed Rail Vehicle Accessibility Regulations (RVAR) works already contravene Railway Group Standards (they are not within limits 1: 20 to 1: 80) and are as follows: · Platform 4 approximately 1: 85 to 1: 3000 · Platform 5 approximately 1: 45 to 1: 150 · Platform 6 approximately 1: 40 to 1: 1250 · Platform 7 approximately 1: 40 to 1: 210. Proposed situation: To provide `step-free' access at platform level under RAVR, it is proposed to adjust the coper height and offset for Platforms 4, 5, 6 &amp; 7 within the RVAR area, and re-surface the platform area to suit. As a result, the platforms cross fall gradient change as follow: · Platform 4 approximately 1: 110 to 1: 700 (nosing height adjustment range from -31mm to 2mm, horizontal adjustment range from 23mm to 63mm) · Platform 5 approximately 1: 40 to 1: 150 (nosing height adjustment range from -10mm to 2mm, horizontal adjustment range from 47mm to 72mm) · Platform 6 - approximately 1: 30 to 1: 110 (nosing height adjustment range from 20mm to 35mm, horizontal adjustment range from 30mm to 72mm) · Platform 7 ELR: MLN1 Mileage: From 0m 0000y To The clearance to the Train Shed Column is 0m 0440y Paddington Station realigned currently non-compliant and is unchanged. Platforms 12 and 14. All the dimensions are to be verified at GRIP Stage 5. The design of the platform modifications has been based on diverting passengers away from the 2 m restriction at the Train Shed Column. The length of the restriction is not more than 5 m in length. Supported by signage, the intent is for passengers to only walk through the 2 m restriction when alighting from the front door of a train, when they will be protected from the platform edge by the stationary train. A much wider pedestrian route is provided to the opposite side of the column, significantly improving the existing situation. Risk Assessment/Safety Justification Applicant Organisation Note there is an existing deviation Network Rail (10/118/DGN) - for RVAR works the risks and Mitigations are as follow: Platform Gradient out of regulation at RVAR Hump too shallow. Consequences: Not all RVAR door areas are covered by canopy. Rain / water does not run away to drainage. Ponding of water when wet. Potential freezing. Slips and falls on water / ice Minor injuries. Fall towards / into PTI Gap Potential fatality (normally minor injury). Mitigations: - Design for Kew Gardens Platform 1 is within regulations. - Richmond RVAR Hump design improves the Platform Gradient closer to regulations than current. Where not within regulation the gradient is not expected to cause significant ponding. One third of Richmond platforms RVAR areas are covered by a canopy. - Gradients generally fall away from platform edge / PTI gap. Where the gradient is towards, the gradient is improved on existing and is not considered significant. - NR approved nonslip surface, tactiles and nosing stones used. Risk estimation: Better - Minor. Platform Gradient out of regulation at RVAR Hump - too steep. Consequences: Not all RVAR door areas are covered by canopy. Rain / water falls too fast into drainage The clearances from the proposed edge of Network Rail Platform 14 to the following existing structures will be less than the 2500 mm required by Railway Group Standard GI/RT7016: · Train Shed Column - 2. 00 m proposed (2. 00 m existing). Certificate Issue Date 11/10/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 11/09/2013 Deviation Status Current 04/12/2014 N/A INS 13/11/2013 Current The deviation applies to track curvature through a proposed new station at Low Moor situated on the railway between Halifax and Bradford Interchange (ELR: MRB) at 37 miles 650 yards. The proposed new rail station is located at OS GRID Ref. SE 164 283, immediately west of Cleckheaton Road Bridge. Please see Appendix B. The site is brownfield area and comprises of rough ground lying between New Works Road to the north and Ogden's Yard to the south. There are two tracks (Up and Down Main). The track alignment is shown in Appendix B which shows (starting at the low mileage end), the horizontal alignment following a reverse curve into a left hand curve with an existing radius of between 730 m and 800 m where the proposed platforms are situated. The curved track alignment is constrained by a tunnel at each end. The topographical survey shows the existing cant peaks at 100 mm at CH165 and averages 80 mm through the area of the proposed platforms. The line speed is currently 55 mph. The existing track consists of flat bottom rail seated on concrete sleepers. There is no overhead or 3rd rail electrification present and no signal present within the vicinity of the proposed station. The purpose of a new station at Low Hitachi Class 800 / 801 vehicles, to be used on Great Western and East Coast services. It is not reasonably practical to comply with the existing requirement in the current RGS of not placing platforms on horizontal curves with radii less than 1000 m. Compliant track radii would require re alignment of both the up and down lines. This is considered not reasonably practical due to: · The upside would encroach on the exclusion zone around the High Pressure gas main. · Northern Gas Networks have indicated that they would formally object to this proposal (see Appendix C). · Relocating the high pressure gas main would cost in the region of œ450k; track re-alignment would be costly (estimated to be in the region of œ500k) and cause disruption to the busy Caldervale line between Bradford, Halifax, Manchester Victoria and York to Blackpool services. The total cost of diverting the gas main and increasing the track radius to 1000 m through the station would therefore be in the region of œ950k which equates to an increase of 17% of the capital cost of the station. The impacts of the proposal to maintain West Yorkshire Passenger track curvature would be: Safety of the Transport Executive railway system: minimal as conductor sight lines for four-car DMUs only would be affected. It should be noted that a mixture of two, three and four-car DMUs will serve the station. Technical compatibility of the railway system: No effective impact stepping distances are compliant with the requirements of clause 3. 3. 1 of GI/RT7016. The new station will not prevent the planned line speed increases (as part of the Northern Hub works) or electrification in the future. In the event that longer trains are required to stop at the station in the future, selective door opening could be deployed as a costeffective solution to eliminate the issue. Costs and service performance: track and platform curvature will have no effect on service costs and performance. The impacts will have no direct effect on Metro as a Passenger Transport Executive. The station, when built on the existing track curvature, will impact on Network Rail's infrastructure and has the support of the Route Asset Manager Track. Please see letter of support in Appendix A. 12/11/2013 N/A INS 11/09/2013 Current GM/RT2100 Section 6. 5. 2 is ambiguous and open to interpretation, particularly the use of the word "without failure" in the first sentence of Section 6. 5. 2. 2. The sentence states "Interior glazing shall withstand without failure, the following ultimate load cases". It is Hitachi's contention that laminated glass may perfectly well withstand the specified ultimate static loads with the glass intact and in position although it may be cracked or crazed. This would not be the case if toughened glass were to become cracked or crazed. In these circumstances, a toughened glass panel would form small glass "dices" and lose any ability to contain load or provide "containment" of passengers or their luggage in impact conditions. Hitachi intend to interpret the word "failure" in these circumstances such that laminated glass may be allowed to crack or craze whilst the ultimate loads are applied or removed, providing that the glazed panel provides integrity, "containment" and remains securely retained by its fixings. Hitachi believes that the proposed deviation Hitachi Rail Europe Ltd and interpretation complies with the aims of the Railway Group Standard and does not affect the safety of the railway system now or in the future. 27/11/2013 N/A RST 01/11/2013 Current Page 58 Deviations Register RGS Number GERT8000-DC RGS Issue Number One RGS Title DC Electrified lines Certificate Number 13-116-DEV Title Controlled evacuations. RGS Clause 6.4b) Scope Nature and Degree The deviation will apply to all lines electrified The current rules require that, before a using DC third or fourth rail systems. controlled evacuation of a train takes place, a temporary isolation must be taken on any line where passengers may walk. A temporary isolation is managed in accordance with Network Rail company instructions, but it does require that one or more short-circuiting devices are placed at the site to prevent accidental reenergisation. It is not always possible to be compliant with the current requirement as temporary isolations cannot be taken on all areas of the DC railway. This is because a short-circuiting device cannot be placed: where the traction return rail is next to the conductor rail, where there is a guard board between the conductor rail and the adjacent running rail, or a yellow plastic shroud is fitted to the underside of the conductor rail. Furthermore, if multiple lines have to be crossed by passengers, each line must be provided with a short-circuiting bar. This might mean a considerable delay whilst sufficient bars are conveyed to site, which would in turn encourage self-evacuation of passengers and result in an emergency switch-off anyway. Risk Assessment/Safety Justification Applicant Organisation The proposed benefit allows for a choice of Network Rail response to be taken dependant on the scenario, the location and the availability of staff. It also allows for quicker decision making, which should reduce the overall time taken to evacuate passengers and thus reduce the probability of other passengers on other trains detraining without authorisation. Network Rail recognises that the use of an emergency switch-off can create performance issues, although under these circumstances it can be possible to move trains from the affected and abutting sections before implementing the emergency switch-off, and thus reducing the overall impact of the situation. Certificate Issue Date 16/10/2013 Certificate End Date N/A Lead SC TOM Lead SC Approval Date 17/09/2013 Deviation Status Current GMRT2132 One On-board Energy Metering for Billing Purposes 13-114-DEV Deviation against clause 2.2.1 of GM/RT2132 to allow DC metering only on class 375/6 stock where AC equipment is maintained and operational but not in use. 2.2.1 Deviation for class 375/6 dual voltage units to be metered on DC collection points only. N/A Southeastern 01/11/2013 N/A RST 04/10/2013 Current GMRT2466 Three Railway Wheelsets 13-113-DEV Railway Wheelsets 3.5.2 N/A Freightliner Ltd 15/08/2013 N/A RST 02/08/2013 Current GMRT2400 Four Engineering design of on-track machines 13-108-DEV Derogation to GM/RT2400 Issue 4 Clause 3.5.4 Parking Brake. Clause 3.5.4, sub-clauses 3.5.4.1 a) and 3.5.4.1 b) The functionality of the parking brake Windhoff Bahn- und remains the same and the impact of Anlagentechnik GmbH retaining the existing arrangement is considered minor as the vehicles are compliant if carrying freight containers to the same GLW. The vehicles will be used in train formation in the same way as a freight wagon, this risk is therefore unchanged. The following measures will be in place: · An operating instruction to state that the KFA wagons are not to be uncoupled from an MPV on gradients greater than 1 in 40. · A label to that effect is to be fitted to each wagon adjacent to the couplings. 02/12/2013 N/A PLT 17/10/2013 Current GERT8082 One GSM-R Cab Mobile, Great Britain Open Interface Requirements (Rapid Response) 13-107-DEV Call quality requirements for GSM-R Radio 3.9.1, 3.9.2, 3.9.3, 3.9.4, 3.9.5 and 3.9.7 installations using single handset Cab Audio Control Units on Southeastern Cl375, 376, 465 and 466 fleets. There are no negative impacts of the Southeastern alternative actions. This is because maintaining the use of a single handset reduces the level of change effected by the introduction of the GSM-R radio to the Classes 375, 376, 465 and 466 cab designs thereby maintaining current driver practice of controlling voice communications through a single handset. 04/09/2013 N/A CCS 15/08/2013 Current GERT8000-HB7 Three General duties of a controller of site safety (COSS) 13-101-DEV Revised 30-09-2014 The On-Track Machine (OTM)-PZ project intends to carry out tranche 2 of trials. To allow Tranche 2 of trials of Phase 1a of Network Rail the OTM protection zone procedure to proceed a deviation is required against Clause 4. 4. The deviation is to add the OTM protection zone procedure as a reason to consider the line to be blocked and for it to be used to set up a safe system of work. This application will support the continued trialling of Phase 1a of the OTM protection zone procedure. Network Rail would now like to trial Tranche 2 of the new form of protection of the line that allows the operation of a single on-track machine working on a line not under possession; the method of operation can be found in the Trial Operations Manual (OTMPZ/Phase 1a/TOM/050613) document. 30/09/2014 30/06/2016 TOM N/A Current Current Deviations Register as at 09 May 2016 4.4 Metering the AC component of the vehicles mentioned in part 7 would be of no benefit as Southeastern do not use (or intend to use) the AC equipment for energy collection for the class 375/6 fleet. All wheelsets used on Network Rail The standard mandates that electrical managed infrastructure that are of a testing is performed on all wheelsets in monobloc all steel construction with an accordance with applicable standards. interference fit between wheel and axle. Introduction of this additional requirement would entail the development of test equipment and the revision of existing maintenance instructions. The likely costs involved are deemed to be disproportionate to the benefits expected. This application is for eight existing KFA These vehicles were designed as container wagons modified by Windhoff Bahn- und carrying freight vehicles and are compliant Anlagentechnik GmbH and re-classified as with the applicable RGS. The vehicles are OTMs to form part of the Network Rail High now to be used in the HOPS OLE Output OLE Construction System (HOPS). construction train to carry various loads, The application is to permit non-compliance including plant and machinery modules with the RGS clause identified in 6b) above mounted on the vehicle twist locks. for the following vehicles: · 99709131002-6 GM/RT2000 Issue 3 clause 6. 4 specifies · 99709131004-2 · 99709131008-3 · that such a combination shall be classified 99709131012-5 · 99709131016-6 · as an on-track machine, hence GM/RT2400 99709131017-4 · 99709131019-0 · applies. The vehicles were designed to 99709131009-1. comply with freight vehicle RGS, I. e. a 1 in 40 gradient requirement and no minimum hand wheel diameter. The vehicles will hold on a worst case 1 in 37 gradient (I. e. within the limit prescribed for a freight vehicle) and have a parking brake hand wheel of diameter 270 mm. To achieve the requirements specified by GM/RT2400 to hold on a gradient of 1 in 30 would require considerable re-design of the vehicle, and there is not sufficient space to fit a hand wheel of diameter 400 mm. A standard GSM-R installation utilises a As with derogations 09/285/DGN, dedicated GSM-R handset for radio 10/048/DGN and 12/102/DGN, there is no communication function. However, vehicles known route whereby compliance to the currently fitted with a single handset will clauses in Section 6 can be achieved. The have their Cab Audio Communication Unit Southeastern Classes 375 and 376 fleets (CACU, sometimes known as Drivers have had a single handset arrangement Interface Unit - DIU) modified to allow the since they were introduced into service. The existing single handset to work in existing handset occupies the optimum conjunction with the GSM-R radio, thus position in terms of driver ergonomics. maintaining the existing arrangement Fitment of a dedicated GSM-R handset whereby all cab audio functions are would require the GSM-R handset to be managed through a single handset. This placed in another location, away from the deviation application applies to the use of optimum location. The Southeastern the existing handset (Whiteley/BTROS Classes 465 and 466 underwent a TD500 or DAC handset) in place of a modification programme to replace separate dedicated GSM-R handset on the Classes radio and PA handsets with a single handset 375 and 376 Electrostar fleets and the arrangement. This new arrangement only Classes 465 and 466 Networker fleets, allows for one handset to be fitted in the noting that the existing handset and CACU optimum cab location. This means the arrangement will not pass the test fitment of a dedicated GSM-R handset requirements in the clauses identified in would require drivers to change the way the Section 6 of this application (Details of operate the GSM-R radio in comparison to Railway Group Standard). It should be current practice. noted that the scope of this deviation is similar to that for derogations 09/285/DGN, 10/048/DGN and 12/102/DGN which also relate to the use of a single handset and CACU arrangement which cannot pass the test criteria as set out in section 6 above. The Phase 1a trials will be limited to single This handbook clause details that the COSS and double track lines in track circuit block may use a blocked line as part of the safe areas that do not have axle counters, level system of work; it then lays down guidelines crossings or ground frames in non-DC on when a line may be considered to be electrified areas. Trial Areas/Routes will blocked. The project continues to require include: Anglia Route Delivery Units: · the addition of the OTM protection zone as Tottenham · Romford · Ipswich. Western reason why a line should be considered to Route Delivery Units: · Bristol · Swindon · be blocked to allow Tranche 2 of Phase 1a Plymouth · Reading. Wessex Route trials to take place to evaluate the procedure Delivery Unit: · Eastleigh. Scotland Route further. Delivery Units: · Motherwell · Glasgow · Perth · Edinburgh. Wales Route Delivery Units: · Shrewsbury · Cardiff. LNE Route Delivery Units: · Hitchin · York · Leeds · Sheffield. LNW Route (WM & C) Delivery Units: · Saltley · Sandwell &amp; Dudley. Page 59 Deviations Register RGS Number GERT8000-TW5 RGS Issue Number Five RGS Title Preparation and Movement of Trains: Defective or Isolated Vehicles and On-Train Equipment Certificate Number 13-099-DEV Revised 30-06-2014 Title The OTM-PZ project intends to carry out tranche 2 of trials. RGS Clause 4.3, 4.4 and 21.3 Scope The Phase 1a trials will be limited to single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames in non-DC electrified areas. Trial areas/routes will include: Anglia Route Delivery Units: · Tottenham · Romford · Ipswich. Western Route Delivery Units: · Bristol · Swindon · Plymouth · Reading. Wessex Route Delivery Unit: · Eastleigh. Scotland Route Delivery Units: · Motherwell · Glasgow · Perth · Edinburgh. Wales Route Delivery Units: · Shrewsbury · Cardiff. LNE Route Delivery Units: · Hitchin · York · Leeds · Sheffield. LNW Route (WM & C) Delivery Units: · Saltley · Sandwell &amp; Dudley. GERT8000-TW7 Four Wrong-direction movements 13-098-DEV Revised 30-09-2014 The On-Track Machine (OTM)-PZ project intends to carry out Tranche 2 of trials. 1.1 and 1.2 The Phase 1a trials will be limited to single and double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames in non-DC electrified areas. Trial Areas/Routes will include: Anglia Route Delivery Units: · Tottenham · Romford · Ipswich. Western Route Delivery Units: · Bristol · Swindon · Plymouth · Reading. Wessex Route Delivery Unit: · Eastleigh. Scotland Route Delivery Units: · Motherwell · Glasgow · Perth · Edinburgh. Wales Route Delivery Units: · Shrewsbury · Cardiff. LNE Route Delivery Units: · Hitchin · York · Leeds · Sheffield. LNW Route (WM & C) Delivery Units: · Saltley · Sandwell &amp; Dudley. GERT8000-OTM Five Working of on-track machines (OTM) 13-097-DEV Revised 30-09-2014 The OTM-PZ project intends to carry out tranche 2 of trials. 4.1 and 4.2 The Phase 1a trials will be limited to single &amp; double track lines in track circuit block areas that do not have axle counters, level crossings or ground frames in non-DC electrified areas. Trial areas/routes will include: Anglia Route Delivery Units: · Tottenham · Romford · Ipswich. Western Route Delivery Units: · Bristol · Swindon · Plymouth · Reading. Wessex Route Delivery Unit: · Eastleigh. Scotland Route Delivery Units: · Motherwell · Glasgow · Perth · Edinburgh. Wales Route Delivery Units: · Shrewsbury · Cardiff. LNE Route Delivery Units: · Hitchin · York · Leeds · Sheffield. LNW Route (WM & C) Delivery Units: · Saltley · Sandwell &amp; Dudley. GMRT2483 One Visibility Requirements for Trains 13-093-DEV Revised 25-11-2013 Use of TSI/EN Compliant Head, Marker and C2.1, C2.3.1, Appendix 3 Tables 2, 3, 5, 7 Tail Lights on GB non-TENs Routes. and 10, Appendix 4 Table 11. Current Deviations Register as at 09 May 2016 Nature and Degree These clauses relate to train borne defective/isolated Automatic Warning System and Track Circuit Actuators. These clauses instruct the driver that the signaller must be informed immediately of defective/isolated equipment and that further movement must not be made until authorised. The clauses go on to document what action must be taken before the train can proceed. The project requests that the OTM driver does not need to comply with these clauses as part of the OTM protection zone trials. Risk Assessment/Safety Justification Applicant Organisation To allow the continued trialling of Phase 1a Network Rail of the OTM protection zone procedure a deviation against clauses B5. 2, B5. 3 and B32. 3. The OTM-PZ project continues to require the addition of the OTM protection zone as reason why a line should be considered to be blocked to allow Tranche 2 of Phase 1a trials to take place to evaluate the procedure further. When tampers are in "work mode", their on-board equipment is powered by a 24 volt system. To minimise the draw on this power supply, certain tampers are designed so that certain on board equipment is effectively isolated. This means that when these tampers are in work mode, the on-board AWS and TCA cannot be relied upon to work. The mitigation measure built into the OTM protection zone procedure is the use of a supplementary protection method that disables the signalling equipment and stops the signaller from routing another train into the protected area if the OTM was to disappear from the track circuits whilst in work mode. This application will support the continued trialling of Phase 1a of the OTM protection zone procedure. Network Rail would now like to trial Tranche 2 of the new form of protection of the line that allows the This clause documents the ten occasions To allow the continued trialling of Phase 1a Network Rail when a signaller may authorise the driver to of the OTM protection zone procedure, a make wrong direction movement for which a temporary deviation against clause 1. 1 is signal is not provided. To allow Tranche 2 requested to allow wrong direction of trials of Phase 1a of the OTM protection movements where no signal is provided as zone to proceed, there is a requirement to required. A further deviation is required add the trials of this procedure to the list of against clause 1. 2 to add the TQS to the list reasons when a wrong direction movement of people who can authorise the OTM driver can be made without the authority of a to make a wrong direction movement. This signal. Additionally, there is a need to add application will support the continued the Track Quality Supervisor (TQS) to the trialling of Phase 1a of the OTM protection list of people who can authorise the OTM zone procedure. Network Rail would now driver to make a wrong direction movement. like to trial Tranche 2 of the new form of protection of the line; that allows the operation of a single on-track machine working on a line not under possession; the method of operation can be found in the Trial Operations Manual (OTMPZ/Phase 1a/TOM/050613) document. Clause 4. 1 stipulates that the work will not require wrong direction movements (except as described for the rail grinding train), the on-track machine (OTM) that will be trialled as part of the OTM protection zone procedure (Tampers &amp; Stoneblowers) need to make at least 2-3 wrong direction movements as part of their normal method of operation. The clause also stipulates that a machine may so work if signalled as an Engineering train requiring to stop in section, but not on a TCB lines or where intermediate block signals are provided. Clause 4. 2 stipulates that the driver must tell the signaller that the OTM will be working outside of a possession as part of the trials of the OTM protection zone procedure there is not requirement for the driver to do this as the signaller will be made aware by the published WON notice and the TQS. So a deviation is sought to allow Tranche 2 of Phase 1a trials of the OTM protection zone procedure on track circuit block lines and to allow the OTM to make wrong direction movements as required. The deviation will be used to carry out trials in selected routes on Network Rail infrastructure. Tranche 2 of the trials will be managed by the Maintenance Services, Use of Interoperable constituent head, GM/RT2483 is not compatible with the marker and taillights compliant with the requirements of the CR Loc and Pas TSI, Conventional Rail Locomotive and which contains clauses from EN 15153-1: Passenger Technical Specification for 2013. Head, marker and taillights designed Interoperability (CR Loc &amp; Pas TSI) and to meet the requirements of the TSI (for EN15153-1: 2013 on all applicable vehicles, running on GB TENs Routes) and EN 15153when replacing headlamps fitted to both 1 2013, certified as Interoperable vehicle ends. Constituents, do not comply with the requirements of GM/RT2483. The previous head lamp designs which comply with GM/RT2483 are Tungsten Halogen Bulb and High Intensity Discharge (HID) technology. Continued compliance to GM/RT2483 for head lamps would preclude the use of LED head lamps which are being specified for vehicles running on GB TENs Routes. Continued compliance to GM/RT2483 would preclude the use of standard components already available from a number of European Union (EU) manufacturers. Cost, reliability improvements and power savings from the use of LED headlamps would not be realised (supplied by BMAC): · Tungsten Halogen Bulb: 1000 hours life, 55w or 70w power consumption dependant on fitment · HID: 6000 hours, 42w power consumption · LED Headlamp: 47393 hours life, 20w power consumption. Costs for a light unit containing a head, marker and tail lamp with Certificate Issue Date 30/09/2014 Certificate End Date 30/06/2016 Lead SC TOM Lead SC Approval Date N/A Deviation Status Current 30/09/2014 30/06/2016 TOM N/A Current Trial sites will be assessed by the local Network Rail Delivery Unit (DU) team using the OTM-PZ project team's Site Scoping Form that will allow an informed decision by the local DU and project teams about the suitability of the site for a trial. All staff involved in each trial will be briefed on the procedure to make sure that they fully understand the procedure and their role in it. Feedback will be gathered after each trial and, if improvements to the procedure are highlighted, the project will make the necessary amendments before returning to TOM SC and seeking the final rule book change. 30/09/2014 30/06/2016 TOM N/A Current Head, marker and tail lamps complying with First Greater Western Ltd the requirements CR Loc &amp; Pas TSI are required to be installed on new rolling stock for operation on GB TENs routes, I. e. the majority of higher speed lines including West Coast Main Line (WCML), East Coast Main Line (ECML), Midland Mainline (MML), Great Western Main Line (GWML), etc. The requirements of the CR Loc &amp; Pas TSI, EN 15153-1 2013 differ from GM/RT2483 in the following respects: · C2. 1 and C2. 3. 1 (c) and (d): The TSI EN lighting arrangement of two lower head lights with full/dimmed headlight differs from the day time and night time headlight arrangement specified in GM/RT2483. · Tables 2 and 5: The GM/RT2483 maximum day and night time headlight luminosities in the vertical plane above 2 degrees up are not specified in the CR Loc &amp; Pas TSI or EN 15153-1 2013, and therefore are not required parameters for the TSI/EN headlights. · Tables 3 and 7: The minimum full and dimmed headlight luminous intensities are only specified by EN 15153-1 2013 over beam spread in the horizontal plane, not above and below horizontal as required by GM/RT2483. The GM/RT2483 headlight colour is specified as White Class B, 14/08/2013 N/A RST 02/08/2013 Current Page 60 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-092-DEV Title Apsley Station Platforms 2 and 3 - Suicide Reduction Fencing and Reduced Platform Width. GERT8030 Four Requirements for Train Protection and Warning System (TPWS) 13-091-DEV GE/RT8030 Appendix F Clause F.2.1 TPWS F2.1.1, F2.1.3 (part), F2.1.4, F 2.10.7. DMI appearance and labelling. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-089-DEV Langley station, platforms 2 and 3 - distance 6.2.2 of fencing from platform edge 168. 4 m of 1. 4 m high fencing grey galvanised fencing to restrict access to the main line side of the island platform (platforms 2 and 3) at Langley; of this 168. 4 m, 11 m would be out of compliance and is what the derogation relates to. There will be four sliding gates within the fence to allow access and egress where necessary between the main lines and relief lines. These gates can be left open in the rare occasions where services need to call on the main line platforms at the station and or when the station is unmanned, such as overnight. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-087-DEV Goring &amp; Streatley platforms 2 and 3 distance of fencing from platform edge. 140 m of 1. 4 m high grey galvanised fencing to restrict access to the main line side of the island platform (platforms 2 and 3) at Goring &amp; Streatley. There will be four sliding gates within the fence to allow access and egress where necessary between the main lines and relief lines. These gates can be left open in the rare occasions where services need to call on the main line platforms at the station and or when the station is unmanned. Current Deviations Register as at 09 May 2016 RGS Clause 6.4.2, 7.2.1, 7.3.1 6.2.2 Scope London Midland is implementing a joint industry suicide prevention initiative at eight of its stations on the West Coast Main Line (WCML) to "fence-off" the fast line platforms at the stations it operates on the West Coast South route. The deviation sought relates to platforms 2 and 3 at Apsley Station. Platform 2/3 at Apsley is a double-face platform. Platform 2 is on the Up Fast Line, has an eight-car capacity, and the line speed is 125 mph. Platform 3 is in the Down Slow Line, has a twelve-car capacity, and the line speed is 100 mph. A report was commissioned to identify and make recommendations regarding any safety issues that might arise out of the proposals. It was identified that, due to the existing platform dimensions at Apsley Station, the erection of a fence on the island platform (Platforms 2 and 3) effectively divides the platform into two single-faced platforms and converts an existing non-compliance with Clause 7. 3. 1 of GI/RT7016 into a new noncompliance with Clause 6. 4. 1 for the final 13. 5 metres platform length at the southern end. A workshop was held on 30/04/2013 to consider the report referred to above and, having considered the options set out in the report, the proposed non-compliance with This application is for the MPV vehicles supplied by Windhoff Bahn- und Anlagentechnik GmbH which form part of the Network Rail High Output OLE Construction System (HOPS) and is to permit non-compliance with the RGS standard clauses as identified in 6b above, for the following vehicles: MPV Type 1 (SOPB): · 99 70 9131 010-9 · 99 70 9131 013-3 · 99 70 9131 021-6 · 99 70 9131 022-4 · 99 70 9131 023-2. MPV Type 2 (HOPB): · 99 70 9131 001-8 · 99 70 9131 005-9 · 99 70 9131 006-7 · 99 70 9131 011-7. MPV Type 5 (SORB): · 99 70 9131 014-1. Nature and Degree Providing the minimum distance to the platform edge of 3. 0 m required by GI/RT7016 Clause 6. 4. 2 on the affected section of platform 2 would involve substantial re-engineering of both the track layout and platform structures, not just of Platforms 2/3 but also Platforms 1 and 4. The costs of such re-engineering would be grossly disproportionate to the benefits of the proposed suicide reduction measures. London Midland's proposed alternative provisions substantially mitigate the risks presented by the proposals, enabling the realisation of the benefits of proposed suicide reduction measures and therefore an improvement in the overall level of safety. Derogation 12/162/DGN was authorised in November 2012 to permit a TPWS installation in accordance with GE/RT8030 Issue 2 to be installed on these vehicles instead of a system compliant with Issue 4 of the Standard. This derogation was sought due to the risk that validated TPWS equipment compliant with Issue 4 of the Standard would not be available within the project delivery timescales current at that time. This application was subsequently supported by derogation 13/010/DGN authorised in March 2013 to permit noncompliance with Clause 2. 6. 8. 2 of GE/RT8035 Issue 2 which requires the capability to isolate train borne AWS equipment independent of the isolation of TPWS equipment. Inclusion of this requirement was not possible since the new generation TPWS equipment was not available. In seeking these derogations, Windhoff committed to design the vehicles to accept equipment supplied to them at that time for which approval was being sought by Unipart, and which was believed to be compliant with GE/RT8030. The Project also committed to retrofit equipment compliant with GE/RT8030 issue 4 as and when approved equipment became The non-compliance lies solely on the main line side of the platform (Platform 2) where the clearance would be between 2300 mm and 3000 mm for the first 11 m of the fence line. As the staircase on the island platform is already out of compliance with the standard, the new fence will create an area of 18 m in length, which will be between 2100 mm and 3000 mm from the platform edge. The main line side of the island platform is little used (normally used only during diversions as a result of engineering work on the Relief Lines) and the fence will restrict public access to this side of the platform when the main lines are not being used by stopping services. Access to the area where clearance is less than standard will therefore be minimal. Sixty six fatalities have occurred at the nineteen stations between Paddington and Didcot Parkway since 2006. The majority of these fatalities involved a member of the public accessing the main lines via the island platform. The introduction of these fences has proved a successful anti-fatality mitigation at locations where they have been introduced across the rail network to date and is endorsed and supported by the National Fatality Prevention Steering Group. Twenty metres of fencing on Platform 3 will be closer to the platform edge than the standard dictates by virtue of being between 2300 mm and 2500 mm from the platform edge where the adjacent line speed is 100 mph. For 18 m of the total 20 m, the fence is also between 2400 mm and 3000 mm from the main line Platform 2 where the line speed is 125 mph. The main line platforms are little used (normally used only during diversions as a result of engineering work on the Relief Lines) and the fence will restrict public access to this side of the platform when the main lines are not being used by stopping services. Access to the area of Platform 2 where clearance is less than standard will therefore be minimal. On both sides of the platform, there is sufficient space for two and three car turbo units to stop in the station without any of the doors being in the 'derogation area', so passenger access and egress into and out of this area should be limited. For Class 180 and six-car turbos, which also call at the station, only one set of doors would open into the area. The area of reduced width is at the far end of the platform away from the station footbridge and has no canopy, so is not an area where people tend to dwell. Sixty-six Risk Assessment/Safety Justification London Midland's proposals at Apsley enable the implementation of a worthwhile mitigation measure that will discourage suicides. Although this location is not a "hotspot" for such events, the density of traffic on the WCML is such that the impact in terms of significant delays and disruptions is proportionately greater than most other routes on the GB Mainline Railway. Suicides have an emotional impact not just on the families affected, but also seriously affect front line railway staff involved in them, as well as those called to deal with the immediate aftermath. London Midland's proposals, for which this deviation is being sought, allow the retention of the existing operational capacity of the station at Apsley, and also suitably mitigating the impact of the proposed suicide reduction fencing in the event that an emergency evacuation is required of trains longer than the operational capacity of platform 2 (eight-cars). The erection of suicide reduction fencing at Apsley provides an incidental but significant safety benefit in discouraging access to the fast line platforms during "normal" operation, in an area of the platforms where the combined platform width presents an existing non-compliance. London Midland is Retention of the earlier version DMI panels will remove the need to substantially change the driver's desk layout, construction and associated components. The current layout has also been agreed with the vehicle owner (Network Rail) and Operator (Amey) and will negate the requirement for further consultation on any potential changes. The differences between the DMI panel currently fitted and the later supplied approved panel are; The AWS isolation light is included in the current panel; this is not compliant with clauses F2. 1. 1, F2. 1. 3 and F2. 1. 4 of GE/RT8030 Issue 4. The labelling of the panel is smaller than specified by clause F 2. 10. 7 of GE/RT8030 Issue 4. The inclusion of the AWS isolation light in the DMI panel has been the subject of a previous derogation application 12/203/DGN, and the labelling of the DMI panel of derogation application 12/204/DGN. In both cases, the derogations were submitted but subsequently withdrawn by Unipart. The Train Operator has also been consulted in the use of this panel and does not foresee any problems. Vehicle drivers will be fully briefed, instructed and trained on the individual controls and indicators installed in the current DMI. The use of the A fence is planned to be added along the island platform at Langley which serves the down relief and up main lines. The purpose of the fence is to achieve a greater degree of physical separation between the lightly used main line platform face (Platform 2) and the highly used relief line platform (Platform 3) because Langley is a suicide `hot spot'. Langley station has witnessed three fatalities in the past four years. The majority of the 66 fatalities at the 19 stations in the four track section between Paddington and Didcot Parkway which have occurred since 2006 involved a member of the public stepping from the island platform into the passage of a train on the adjacent main lines. Providing the fence will make it less easy for the public to access the main line side of the fence (which is generally not used) and, more importantly, make it visibly clearer should someone access that side, so that preventative action can be taken. Details of the proposed fence are as follows: · 157. 4 m of the fence line would be within compliance · 11 m of would be new fence would be out of compliance. The fence would contain four sliding gates to allow access and egress between the main and relief sides of the island platform where A fence is planned to be added along the island platform at Goring &amp; Streatley which serves the Down Relief and Up Main Lines. The purpose of the fence is to achieve a greater degree of physical separation between the lightly used main line platform face and the highly used relief line platform face. There have been 66 fatalities at the 19 stations in the four-track section between Paddington and Didcot Parkway since 2006, the majority of which involved a member of the public stepping from the island platform into the passage of a train on the adjacent main lines. Providing the fence will make it less easy for the public to access the main line side of the fence (which is generally not used) and, more importantly, make it visibly clearer should someone access that side so that preventative action can be taken. The Country-End half of the station platform is currently divided in a similar fashion by a 1 m high metal barrier, which is currently out of compliance by the same amount as the new fence will need to be, as it is being replaced in the area of reduced width at the country end of platform. Details of the proposed new fence are as follows: · The total platform length is 154 m and the mid- Applicant Organisation London and Birmingham Railway Company Certificate Issue Date 27/08/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 10/07/2013 Deviation Status Current Windhoff Bahn- und Anlagentechnik GmbH 07/08/2013 N/A CCS 11/07/2013 Current Network Rail 12/08/2013 N/A INS 10/07/2013 Current Network Rail 12/08/2013 N/A INS 10/07/2013 Current Page 61 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-086-DEV Title Streatham Hill Station, Platform 2 extension (Down Slow line at Country end) - platform width. RGS Clause 7.2.1 and 7.4.1 Scope Streatham Hill Station: Station platform Platform 2 (Down Slow line at Country end). Platform 2 is to be extended at the Country end. The proposed platform extension works will maintain the existing track alignment. Due to the presence of an existing retaining wall that supports a cutting slope, it will not be possible to comply with the minimum width requirements of Clause 7. 2. 1b of 2. 5 m and derogation from the Railway Group Standard will be required. GMRT2161 One Requirements for Driving Cabs of Railway Vehicles 13-085-DEV Deviation for windscreen wiper swept area on Class 70 locomotive. 6.1.1 and; 6.2.6 All Class 70 locomotives. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-084-DEV Didcot Station, Platform 5 - Driver Only Operation (DOO) Mirror headroom. 8.1 b) Project Ref. 118833 - DOO Mirrors Scheme to renew the existing DOO Mirrors at 34 Stations in the Thames Valley Area. This issue is at Didcot Station, Platform 5. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-083-DEV Hungerford Station, Platform 1 - Driver Only 8.1 b) Operation (DOO) Mirror headroom. Project Ref. 118833 - DOO Mirrors Scheme to renew the existing 59 DOO mirrors at 34 stations in the Thames Valley Area. This issue is at Hungerford Station, Platform 1. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-082-DEV Midgham Station, Platform 2 - Driver Only Operation (DOO) Mirror headroom. 8.1 Project Ref. 118833 - DOO Mirrors Scheme to renew the existing DOO Mirrors at 34 Stations in the Thames Valley Area. This issue is at Midgam Station, Platform 2. No action has been taken, as the existing mirror has been in situ for at least ten years at a height of 2. 15 m with no known problems and the new mirror is an improvement to the situation. GIRT7016 Four Interface between Station Platforms, Track and Trains 13-081-DEV Shiplake Station Platform 1 - Driver Operation Only (DOO) mirrors headroom. 8.1 b) Project Ref. 118833 - DOO Mirrors Scheme Shiplake Station Platform 1 (single line No action has been taken as the existing to renew the existing DOO Mirrors at 34 railway between Twyford and Henley) - (2 x mirror has been in situ for at least 10 years Stations in the Thames Valley Area. mirrors). The existing mirrors on Platform 1 with no known problems. at CS 2/3 and CS 3/4/5 in the Twyford direction were identified during the survey that the height from the underside of the mirror housing to platform level was less than 2500 mm, which is below the minimum requirement as stated in GI/RT7016 Section 8. 1. It has been confirmed that new mirrors cannot be raised to achieve the minimum height clearance whilst maintaining a compliant image due to obstruction by the canopy. · CS2/3: The new mirror height is 2. 4 compared to the original mirror height of 2. 2 m; the mirror is 1650 mm from the platform edge, thus erecting a barrier to the edge of the mirror would force the passengers close to the platform edge. There are also two additional car stops on the platform CS 4/5/6, plus CS 7 which is used during the Henley Regatta week; erecting a barrier would affect access to the train doors. · CS4/5/6: The new mirror height is 2. 2 m compared to the original mirror height of 1. 9 m; the mirror is 780 mm from the platform edge. There is also a CS 7 which is used during the Henley Regatta week, erecting a barrier would affect access Current Deviations Register as at 09 May 2016 Nature and Degree The proposed extension of 24 m will be 2. 5 m wide, except for a section of 4 m where it will be 2425 mm due to the wall alignment. The platform extension is on the country end of the Down Platform 2 and is 24 m long affecting the front coach. The exit to/from the platform is via a footbridge where the stairs face London and passengers movement from trains is generally from the middle coaches of the train. Risk Assessment/Safety Justification Applicant Organisation The Sussex Route Suburban Train Network Rail Lengthening project seeks to increase passenger capacity over selected routes by increasing train lengths from eight to ten cars. This requires platform extensions on the Slow Lines at a number of stations including Streatham Hill. Streatham Hill station comprises two platforms as follows: · Platform 1 - Up Slow; · Platform 2 - Down Slow. The main station entrance is located on a footbridge structure that abuts a road over bridge at approximately the country end of the station with inter platform access via a footbridge staircase starting towards the middle of the platform. GE Transportation has recently been The design modification proposed by GE GE Transportation working to increase the reliability of the Transportation will lead to an increase in the windscreen wipers on the Class 70 reliability of the windscreen wipers while locomotives. Part of the existing problem is providing the best swept areas of the that tolerance build ups can lead to the wipers, without undertaking major redesign wider blades striking the edge of the of the cab structure / windscreen. It windscreen. During the development of the provides a reliability improvement over the modification, it was identified that the existing design. The new design is only sightline requirements for cases A and C (as marginally non-compliant, and is considered described above) do not pass through the to present no greater risk than on other area of the windscreen that is wiped by the vehicles where similar derogations have windscreen wipers when viewed from the been granted in the past. Please refer to the same point in the reference cube. (The attached document for further details. sightlines do pass through the windscreen itself, and they do pass through the wiper's swept area if viewed from different points in the reference cube). The attached paper provides additional explanation. To date, in the three years that Class 70s have been in service, there have been no recorded complaints or problems for drivers in respect to the RGS sightlines not passing through the swept area (problems have related to the faults with the wipers themselves). The changes proposed by GE Transportation to increase the wiper arm and wiper blade length, whilst reducing the angular sweep of the arms, will provide improvements in reliability, whilst having a Didcot Station - The existing mirror on No action has been taken as the existing Network Rail Platform 5 is canopy mounted and it was mirror has been in situ for at least ten years identified during the survey that the mirror with no known problems. height from the underside of the mirror housing to platform level is 2. 20 m, which is below the minimum requirement of 2500 mm as stated in GI/RT7016 Section 8. 1. Hungerford Station - The existing mirror on No action has been taken as the existing Network Rail Platform 1 was mounted on a post and was mirror has been in situ for at least ten years identified during the survey that the mirror with no known problems. height from the underside of the mirror housing to platform level was 2200 mm, which is below the minimum requirement of 2500 mm as stated in GI/RT7016 Section 8. 1. The new mirror was commissioned on 12/01/2013 with the intention of raising the clearance height from the underside of the mirror to platform to 2500 mm. However, a compliant image could not be achieved at this height, therefore the mirror was lowered until a compliant image was achieved. The new clearance from underside of mirror to Platform is now 2320 mm, which is an improvement on the old mirror. Due to the mirrors proximity to the platform edge, erecting a barrier to the edge of the mirror would force the passengers to less than 1250 mm from the platform edge. Certificate Issue Date 09/09/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 10/07/2013 Deviation Status Current 18/07/2013 N/A RST 28/06/2013 Current 19/08/2013 N/A INS 10/07/2013 Current 01/08/2013 N/A INS 10/07/2013 Current Midgham Station, Platform 2, Car Stop S: It was identified during the survey that the existing Mirror height from the underside of the Mirror housing to platform level was 2. 15 m, which is below the minimum requirement of 2500 mm as stated in GI/RT7016 Section 8. 1. The new mirror was installed at a height of 2. 50 m. However, during commissioning, Network Rail could not get a compliant image at this height, and the mirror was therefore lowered until a compliant image could be viewed; this was at a height of 2. 36 m (note this is an improvement to the old mirror). Network Rail 01/08/2013 N/A INS 10/07/2013 Current Network Rail 12/09/2013 N/A INS 10/07/2013 Current Page 62 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-080-DEV Title Cholsey Station, Platform 3 - Driver Only Operation (DOO) Mirror headroom RGS Clause 8.1 b) GIRT7016 Four Interface between Station Platforms, Track and Trains 13-079-DEV Wargrave Station Platform 1 - Driver Only Operation (DOO) Mirror headroom. 8.1 b) GIRT7016 Four Interface between Station Platforms, Track and Trains 13-078-DEV Shiplake Station Platform 1 - Driver Operation Only (DOO) mirrors headroom. 8.1 b) GIRT7016 Four Interface between Station Platforms, Track and Trains 13-077-DEV Cookham Station, Platform 1 (Marlow direction) - Driver Only Operation (DOO) Mirror headroom. 8.1 b) GIRT7016 Four Interface between Station Platforms, Track and Trains 13-076-DEV Newbury station, platform 1- Driver Operation Only (DOO) Mirror headroom. 8.1 b) GMRT2307 One Self contained electrical power supply systems fitted to infrastructure support vehicles 13-073-DEV Use of voltages higher than Low Voltage (LV). 4.6 Current Deviations Register as at 09 May 2016 Scope Project Ref. 118833 - DOO Mirrors Scheme to renew the existing DOO mirrors at 34 Stations in the Thames Valley Area. This issue is a Cholsey Station, Platform 3. Nature and Degree Cholsey - The existing Mirror on Platform 3 (car Stop 2/3/4) was identified during the survey that the Mirror height from the underside of the Mirror housing to platform level was 2060 mm, which is below the minimum requirement of 2500 mm as stated in GI/RT7016 Section 8. 1. It has been confirmed that a new mirror cannot be raised to achieve the minimum height clearance whilst maintaining a compliant image, although the new mirror height is 2300 mm, an improvement on the old mirror. Due to the mirrors location on the platform, erecting a barrier would force the passengers to less than 1250 mm from the platform edge. Project Ref. 118833 - DOO Mirrors Scheme Wargrave Station - The existing mirror on to renew the existing DOO Mirrors at 34 Platform 1 was identified during the survey Stations in the Thames Valley Area. that the mirror height from the underside of the mirror housing to platform level is 1950 mm, which is below the minimum requirement of 2500 mm as stated in GI/RT7016 Section 8. 1. It has been confirmed that a new mirror cannot be raised to achieve the minimum height clearance whilst maintaining a compliant image. The new mirror height is 2440 mm (which is better than the old mirror) and is 1900 mm from the platform edge. This is a single line railway (Twyford to Henley); the Mirror is in the Twyford direction, CS 2/3, there is also CS 4/5/6 in the same direction and an S CS in the Henley direction, thus erecting a barrier to the edge of the mirror would force the passengers quite close to the platform edge, and also could affect the access to train doors for trains stopping at the other two-car stops. The mirror is 1900 mm from the platform edge thus erecting a barrier to the edge of the mirror would force the passengers quite close to the platform edge, and also could affect the access to train doors for trains stopping at the other two-car stops. Project Ref. 118833 - DOO Mirrors Scheme Shiplake Station Platform 1 (single line to renew the existing DOO Mirrors at 34 railway between Twyford and Henley) - (2 x Stations in the Thames Valley Area. mirrors). The existing mirrors on Platform 1 at CS 2/3 and CS 3/4/5 in the Twyford direction were identified during the survey that the height from the underside of the mirror housing to platform level was less than 2500 mm, which is below the minimum requirement as stated in GI/RT7016 Section 8. 1. It has been confirmed that new mirrors cannot be raised to achieve the minimum height clearance whilst maintaining a compliant image. · CS2/3: The new mirror height is 2. 4 m compared to the original mirror height of 2. 2 m; the mirror is 1650 mm from the platform edge, thus erecting a barrier to the edge of the mirror would force the passengers close to the platform edge. There are also two additional car stops on the platform CS 4/5/6, plus CS 7 which is used during the Henley Regatta week; erecting a barrier would affect access to the train doors. · CS4/5/6: The new mirror height is 2. 2 m compared to the original mirror height of 1. 9 m; the mirror is 780 mm from the platform edge. There is also a CS 7 which is used during the Henley Regatta week, erecting a barrier would affect access to the train doors. Additionally, this is a Project Ref. 118833 - Mirrors Scheme to Cookham Station - The existing mirror on renew the existing DOO mirrors at 34 Platform 1: it was identified during the Stations in the Thames Valley Area. This survey that the mirror height from the issue is at Cookham Station, Platform 1 underside of the mirror housing to platform (Marlow direction). level is 2200 mm which was below the minimum requirement of 2500 mm as stated in GI/RT7016 Section 8. 1. The mirror is 1250 mm from the platform edge, thus erecting a barrier to the edge of the mirror would block the access to the waiting room and station exit. Project Ref. 118833 - DOO Mirrors Newbury Station - The existing Mirror on Scheme to renew the existing DOO Mirrors Platform 1 is canopy mounted and it was at 34 Stations in the Thames Valley Area. identified during the survey that the mirror This issue is at Newbury station, Platform 1. height from the underside of the mirror housing to platform level is 2160 mm, which is below the minimum requirement of 2500 mm as stated in GI/RT7016 Section 8. 1. The mirror is 1750 mm from the platform edge thus erecting a barrier to the edge of the mirror would force the passengers to less than 1250 mm from the platform edge. Risk Assessment/Safety Justification Applicant Organisation No action has been taken as the existing Network Rail mirror has been in situ for at least ten years with no known problems. The new mirror is installed at a greater height (2. 30 m) than the old (2. 06 m). Certificate Issue Date 01/08/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 10/07/2013 Deviation Status Current No action has been taken as the existing mirror has been in situ for at least ten years with no known problems. Network Rail 01/08/2013 N/A INS 10/07/2013 Current No action has been taken as the existing mirror has been in situ for at least 10 years with no known problems. Network Rail 17/09/2013 N/A INS 10/07/2013 Current No action has been taken as the existing Network Rail mirror had been in situ for at least 10 years with no known problems, and the new mirror is an improvement in height. 01/08/2013 N/A INS 10/07/2013 Current No action has been taken as the existing mirror has been in situ for at least 10 years with no known problems. 17/10/2013 N/A INS 10/07/2013 Current Applies to portable electrical tools used in The size and capacity of the electrical tools the ROBEL MMU vehicles and the electrical means it is not practical to power them using supply to power them. An MMU consists of a RLV or ELV supply. three semi-permanently coupled bogied vehicles with a driving cab at each end. There are no safety implications of using this Plasser UK Ltd alternative supply as it reflects modern standard electrical practice in construction sites. Additionally, this reflects common practice in continental Europe on this type of machine. 04/09/2013 N/A PLT 15/08/2013 Current Network Rail Page 63 Deviations Register RGS Number GERT8075 RGS Issue Number One RGS Title AWS and TPWS Interface Requirements Certificate Number 13-070-DEV Title RGS Clause AWS Caution acknowledgement period for 2.2.4.7 Class 390 and Class 221 Super Voyager operated by Virgin Trains on the West Coast Mainline. Scope The deviation applies to all 390 and 221 operated by Virgin Trains. GMRT2461 One Sanding Equipment Fitted to Multiple Units and On-Track Machines. 13-068-DGN Railway Undertaking, RSSB Member 9.1 All Class 377/1, Class 377/2, Class 377/3, Class 377/4 units. GMRT2149 Three Requirements for Defining and Maintaining the Size of Railway Vehicle 13-067-DGN Railway Undertaking, RSSB Member B10.3 Class 377/2, Class 377/6 (if converted for DV operation) and Class 377/7 fleets. (It should be noted that the design of the APC receiver is the same as that fitted to Class 377/5, Class 378 and Class 379 units). GMRT2461 One Sanding Equipment Fitted to Multiple Units and On-Track Machines. 13-066-DGN FGW 150 Step 2 Sanding 9.3.1 This deviation applies Class 150 vehicles operated by First Great Western (FGW). Current fleet size is 78 fitted vehicles, and this would apply to any future Class 150 vehicles FGW may operate. Current Deviations Register as at 09 May 2016 Nature and Degree During the last three full Railway years and three periods of the current 2013/14 year, the total number of AWS late to cancel events stands at 135 (see chart). It can be seen from the year on year data that we are getting worse. We believe some of this might be due to a higher density of traffic and considered normalising on mileage but to do so would only serve to disguise the problem. The random nature of late to cancel AWS warnings supports the theory of unexpected AWS warnings and high workload being at the centre of the issue however the low period 6 figures are interesting and no explanation for this has been identified as yet. [See chart]. Both the 390 and 221 are speed supervised allowing the trains to run at EPS. Part of the TASS system is an arrangement to warn of the approach to speed restrictions where the train measures an approach speed higher than desirable. This initiates an in-cab audible warning that requires a driver brake application to avoid an automatic emergency brake application. Should the driver fail to respond to the warning and should an automatic brake application apply, then the driver must acknowledge the intervention in order to gain release of and resume control There are no impacts with complying with the current RGS requirement. This deviation requests enhanced performance which is non-compliant with the standard as written, but consistent with the objectives of the standard. The APC receiver originally used on the Class 377/2 Electrostar vehicles are now obsolete, thus requiring a new APC receiver to be installed. Unipart rail have designed a replacement for the existing APC receiver which is to be dimensionally set-up in exactly the same way as the now obsolete version. This replacement APC receiver is fitted on the Class 377/5, Class 378 and Class 379 fleets, and derogations against GM/RT2149 are already in place for these fleets. In replacing any failed Class 377/2 APC receivers, and in the design of the APC receiver for the new Class 377/6 and Class 377/7 fleets, there has been an intention to maintain commonality with the Class 377/5 design, simplifying stores and maintenance activities. Whilst the Class 377/6 vehicles are currently being built for DC operation only, the capability to operate under 25Kv OLE has been considered in the design from the start, and this includes the gauging provision for all associated equipment, based on the Class 377/5 design. Having undertaken analysis of the in-service conditions (static primary suspension conditions of tare to crush, spring creep, wheel wear, and set up tolerances), an infringement to the APC Gauge (Appendix FGW 150 units have been operating with Step 2 sanding from 2008, this provided the Drivers with a consistent as provision of sanding when compared to the Class 158 and 166 also operated by FGW. When the classes 143 and 153 were fitted with sanders, these were also configured to step 2 sanding as soon as reasonably practicable (as authorised by11/137/DGN). Sand provision in step 3 and emergency is not compatible with the defensive driving techniques practiced by FGW Drivers. All FGW Diesel Multiple Unit (DMU) traction is currently able to apply sand in brake step 2; this consistency allows a driver to respond with confidence to a low adhesion incident and apply sand before an incident develops. Risk Assessment/Safety Justification We know, from experience, that the reduced acknowledgment period increases the likelihood of late to cancel AWS/TPWS activations. RSSB research has shown that unnecessary AWS/TPWS interventions reduce driver confidence in these systems and increase the likelihood of TPWS reset and continue events. Since the implementation of the AWS system, the infrastructure and train have changed in many ways. The inclusion of TPWS and the OSS+ at critical locations has significantly reduced the risk from a SPAD. Virgin Class 390 and 221 tilting trains have speed supervision from track mounted balises through the Tilt Authorisation and Speed Supervision (TASS) system. The numerous braking systems cope very well with the demands of the high speed Railway and equally well under emergency braking. The brake performance of the 221 and 390 fleet under emergency braking following actual late to cancel incidents is reproduced below for both classes. [See charts]. The two charts depict actual AWS late to cancel at 125 mph and the time and distance table beneath each chart represents both values taken from the moment AWS goes false and the emergency brake applies to reaching full In the condition where the leading unit has a sand level of below 20%, sanding will be enabled on both the leading and trailing units. If the leading vehicle in either unit detects wheel slide, sand will be dispensed by that unit. If the leading vehicle detects wheelspin, and the driver selects `Sand in Traction', sand will be dispensed by that unit. As such, both units will dispense sand if both detect wheel slide and have sufficient sand available. The likelihood of this occurring is low, as the leading unit will condition the railhead and so the trailing unit is unlikely to experience wheel slide. Wherever sand is applied, there will always be at least eleven axles, and usually fifteen axles, after the initial sand deposition point. Therefore, it is considered that there is no negative impact in terms of contamination of the railhead, and so compatibility with the railway system is unaffected. This APC receiver has been designed to be dimensionally set-up in exactly the same way as the now obsolete version. This setup is in-line with the manufacturer's recommendations, and adjusting this set-up height may introduce the risk of the receiver not functioning correctly. When the inservice conditions of the bogie (and subsequently APC receiver) are analysed for gauging purposes and compared to the APC gauge as defined in Appendix C of GM/RT2149, both a lateral infringement of 17. 25 mm and a vertical infringement of 24 mm to the gauge line is experienced. Lateral Infringement: GE/GN8573 Guidance on Gauging, Part E, defines a lower sector vehicle gauge that can be used by vehicle manufacturers to ensure compliance with the relevant Railway Group Standards. After considering all appropriate static and dynamic movements (including tolerances and vehicle maintenance), if the vehicle and components on it are within the limits defined in Part E of GE/GN8573, compliance has been demonstrated. When the lateral movements of the Class 377/2, Class 377/6 and Class 377/7 APC receiver are superimposed against the Lower Sector Vehicle Gauge as shown in Drawing Ref. There is a theoretical risk of a unit coming to rest on a quantity of sand that could prevent the track circuit being shunted. However, since the introduction of step 2 sanding, there have been no Wrong Side Track Circuit Failure (WSTCF) attributed to step 2 sanding on Class 150 (or any other class operated by FGW with step 2 sanding). This monitoring has been conducted with Network Rail's Regional Fleet Engineer and Network Rail's Seasonal Specialist. WSTCF has been reported for other reasons, including rail head contamination with sand deployed by Mobile Operations Managers (MOMs), leaf and cement from building works. These other reports give confidence that this is robust. These periodic meetings with Network Rail will continue. Applicant Organisation West Coast Trains Ltd Certificate Issue Date 18/10/2013 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 03/10/2013 Deviation Status Current Selhurst Traincare Depot 19/07/2013 N/A RST 24/05/2013 Current Southern Railway Limited 19/07/2013 N/A RST 24/05/2013 Current First Great Western Limited 03/06/2013 N/A RST 24/05/2013 Current Page 64 Deviations Register RGS Number GERT8000-HB8 RGS Issue Number Two RGS Title IWA, COSS or PC blocking a line Certificate Number 13-065-DGN Title Engineers' Possession Reminder (EPR) Line Blockages GERT8000-TS1 Seven General Signalling Regulations 13-064-DGN Engineers' Possession reminder (EPR) Line 13.2.4 Blockages GORT3440 Two Steam Locomotive Operation 13-059-DEV Maximum Speed for Steam Locomotive 98466. 2.2.2.1 GORT3440 Two Steam Locomotive Operation 13-058-DEV Steam locomotive operation (TOPS 9851) 2.2.1.1 and 2.3.2.1 Current Deviations Register as at 09 May 2016 RGS Clause 2.2 Scope National. Will apply anywhere on the Network Rail managed infrastructure where EPR is provided. Nature and Degree The derogation will apply to the use of Engineers' Possession Reminder (EPR) as an alternative means of providing additional protection for line blockages. In signalling centre areas using Visual Display Units (VDU) based signalling systems, modern day axle counter train detection and working under Track Circuit Block signalling regulations. " The current rules concerning line blockages mandate four methods of additional protection: detonators, disconnections, T-CODs, and tokens. In signalling centre areas using axle counter train detection and working under Track Circuit Block signalling regulations, it is not practicable to use T-CODs or tokens. Moreover, with the introduction of clearer line blockage rules in December 2010 and Network Rail's continuing policy of encouraging the use of line blockages in preference to safe systems of work using lookout warning, there has been a significant increase in the number of line blockage requests (between 25-135% on EMCC workstations) which has highlighted limitations with the other methods of additional protection available. In the case of disconnections, the average time for completing the process between the National. The deviation will apply anywhere Please note that this application is in on Network Rail managed infrastructure connection with previous temporary nonwhere EPR is provided. The deviation will compliance Ref. 12/075/TNC (Tracker No. apply to the use of Engineers' Possession 10547). The current rules concerning line Reminder (EPR) as an alternative means of blockages mandate four methods of providing additional protection for line additional protection: detonators, blockages. In signalling centre areas using disconnections, T-CODs, and tokens. In VDU based signalling systems, modern day signalling centre areas using axle counter axle counter train detection and working train detection and working under Track under Track Circuit Block signalling Circuit Block signalling regulations, it is not regulations. practicable to use T-CODs or tokens. Moreover, with the introduction of clearer line blockage rules in December 2010 and Network Rail's continuing policy of encouraging the use of line blockages in preference to safe systems of work using lookout warning, there has been a significant increase in the number of line blockage requests (between 25-135% on EMCC workstations) which has highlighted limitations with the other methods of additional protection available. In the case of disconnections, the average time for completing the process between the signaller and signalling technician is 15 minutes and the process is vulnerable to disruption or abandonment if the signalling technician is called upon to attend to faults and failures. Where detonators are used, Any operation of Class 94xx Steam This locomotive 9466 would have to be Locomotive 9466 registered on TOPS as restricted to a maximum permissible speed 98466 on Network Rail's managed of 35 mph to comply with Table A of infrastructure. GO/RT3440 Issue 2. Historically, 9466 has operated on Network Rail's managed infrastructure at speeds up to 45 mph, and further journeys have been contracted by West Coast Railways with Network Rail and planned on this basis. Risk Assessment/Safety Justification The use of EPR to provide additional protection is predicted to be possible without introducing any significant new risks or materially increasing the existing residual risks associated with the four existing methods of additional protection mandated within the Rule Book. Furthermore, it involves a minimal amount of procedural change for the COSS, IWA and PC roles and, in the case of signallers, they will be utilising equipment and procedural arrangements with which they are already familiar for other purposes. The potential benefits of using EPR by comparison with other methods of additional protection have been identified as follows: · A reduction in the number of ground staff required to work on or near the line to provide protection. · A reduction in the time required to apply and remove the protection because all the resources necessary are located in close proximity within the same signalling location. This potentially increases the number of line blockage opportunities available for carrying out work that affects the safety of the line. · Removal of reliance on signalling technicians who may not be available to deal with line blockage disconnections if called to deal with faults and failures. · A reduction in The use of EPR to provide additional protection is predicted to be possible without introducing any significant new risks or materially increasing the existing residual risks associated with the four existing methods of additional protection mandated within the Rule Book. Furthermore, it involves a minimal amount of procedural change for the COSS, IWA and PC roles and, in the case of signallers, they will be utilising equipment and procedural arrangements with which they are already familiar for other purposes. The potential benefits of using EPR by comparison with other methods of additional protection have been identified as follows: · A reduction in the number of ground staff required to work on or near the line to provide protection · A reduction in the time required to apply and remove the protection because all the resources necessary are located in close proximity within the same signalling location. This potentially increases the number of line blockage opportunities available for carrying out work that affects the safety of the line. · Removal of reliance on signalling technicians who may not be available to deal with line blockage disconnections if called to deal with faults and failures. · A reduction in A maximum speed of 35 mph unduly limits the operation of this locomotive to very restricted diagrams. The locomotive has been registered for operation at RSL since May 1996, having operated without incident on NRCI on a number of occasions. The ex BR (W) fleet of 210 locomotives of this class frequently operated diagrams requiring 50 mph maximum speeds in passenger traffic with no records of derailments due to poor riding. The locomotive has undergone various assessments in 2007: · Safety and satisfactory performance completed on 02/11/2007 by an accredited Vehicle Acceptance Body having been fitted with TPWS and OTMR. · Since the locomotive has been de-registered for some time, it was subject to a trial run as required by GM/RT2003 on 01/11/2007. · Assessed for ride quality and braking performance, and for maximum speed on 01/11/2007: the tests carried out showed that brake systems were functioning and performing satisfactorily; the ride performance was excellent at all speeds up to 50 mph. A derogation has been granted (Ref. 07/093/DGN), accepting the locomotive for operation at a maximum speed of 45 mph and this, together with the issue of a full VAB Any operation of Class 8F steam locomotive This locomotive 48151 would have to be This deviation is to prevent a number of 48151 registered on TOPS as 98851 on restricted to a maximum permissible speed planned trains being cancelled, leading to Network Rail's managed infrastructure. of 35 mph to comply with Table A of financial and reputational loss for the GO/RT3440 Issue 2. Historically, 48151 has industry with no identified safety benefit, operated on Network Rail's managed though if more of this type of locomotive infrastructure at speeds up to 50 mph, and were to be permitted to operate, there further journeys have been contracted by would, over time, be an increased risk of West Coast Railways with Network Rail and damaged track causing derailment requiring planned on this basis. increased inspection and maintenance to prevent it. A control in this case is therefore the fact that only one locomotive is involved. Applicant Organisation Network Rail Certificate Issue Date 11/06/2013 Certificate End Date N/A Lead SC TOM Lead SC Approval Date 21/05/2013 Deviation Status Current Network Rail 11/06/2013 N/A TOM 21/05/2013 Current West Coast Railway Company 11/06/2013 N/A TOM 21/05/2013 Current West Coast Railway Company 11/06/2013 N/A TOM 21/05/2013 Current Page 65 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-056-DGN Title Birkenhead North Station DDA Footbridge Island Platform lateral clearances and stair widths. RGS Clause 6.2.1, 6.2.2 b) and 6.2.3. GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 13-054-DGN Flashing aspects for P468 signal at Peterborough. 5.2.3.1 GKRT0045 Three Lineside Signals, Indicators and Layout of Signals 13-053-DGN Flashing aspects for HM567 on the Down Main in the Mirfield East Junction area. GKRT0064 One Provision of Overlaps, Flank Protection and Trapping 13-052-DGN PN245 signal overlap length, Lancaster. Current Deviations Register as at 09 May 2016 Scope As part of the DfT National programme for step-free disabled passenger DDA Compliance, the "Access for All" initiative, the project remit is to replace the existing station footbridge, Structure Number CWK2/8, at Birkenhead North Station, which provides the only access to the island platform 1&amp;2. The proposed new replacement footbridge will incorporate stepfree access to the platforms via DDA compliant lifts, and also provide access to a newly constructed car park adjacent to the station. Working in partnership with DfT, Network Rail, and Merseytravel PTE, the local devolved concession organisation, it has been mutually agreed that this project is to be designed and delivered by Merseyrail as a TOC delivered enhancement scheme. Due to the very limited width of the existing island platform, and the constrained railway land footprint available at this location, there is insufficient space to meet the dimensional requirements of (a) GI/RT7016 regarding usable platform width, (b) the DfT CoP regarding the width of the stair access to the platform, (c) NR/SP/ELP/27228 regarding the dimensions of the lift car. In respect of GI/RT7016, the new bridge will result in a useable platform width of 2300 mm being Signal 468 4(M) and 5(M) flashing aspects routes, reading from the Up Fast to Platform 2 or 3, controlled by Peterborough PSB. Nature and Degree To ensure compliance major reconstruction and remodelling of the station and related track, signalling, telecoms, and third rail traction power railway infrastructure would need to be undertaken requiring an investment of at least cœ8m- œ10m over and above the level of funding available for the core remitted footbridge replacement and enhancement scheme. 5.2.3.1 (a) Junction signal HM567 flashing aspects route over crossover 2071A/B. Down Main in the Mirfield East Junction area on ELR: MVN2, 31m50ch. Compliance could be maintained by continuing to use approach release from red on HM567. This control currently causes trains approaching with a diverging route set to decelerate excessively before accelerating over the points. The controls currently have a risk of anticipation and acceleration towards the next signal that could be at red. The permissible speed over the crossover of 60 mph is not used, reducing performance. 4.3.2 PN245 signal only. Platform 5 Lancaster Station. New routes are being provided to PN245 signal as part of S & C renewal work at Lancaster Station. PN245 signal is an existing signal that has no main route approaches currently, and so no overlap. At 400 m on approach to PN245 signal, the line speed is 40 mph; however, at 315 m on approach, the line speed reduces to 10 mph and stays at that speed up to the signal. To comply with the 400 m requirement would require either no overlap being provided to the neck, extending of the neck to permit a 40 mph reduced overlap (minimum 80 m) or reduction in line speed. These options were considered (see section 11 - What other options have been considered?) but would affect performance of other routes and layout or have a relatively large cost compared to the safety benefit. Compliance could be maintained by continuing to use approach release from red on P468. This control currently causes trains proceeding from the Up Fast to Platform 2 or 3 to decelerate to P468 at red before the aspect is released to proceed over 1243 and 1242 points. The controls currently have a risk of anticipation and that required trains to accelerate towards the points after the signal clears due to 1243 points being 700 m from P468 signal. Train Operating Companies have raised these issues from performance and safety perspective, and requested the controls are amended. Risk Assessment/Safety Justification The proposed footbridge stair width, and width of the existing platform alongside the new footbridge, will not be reduced relative to the existing dimensions, and existing signal sighting not adversely affected in relation to present conditions. Line speeds adjacent to the platform are relatively low (Platform 1 - 15 mph, Platform 2 - 60 mph, increasing from 35 mph just before the station) and there is no regular booked freight traffic over this route (freight speed limits are 15 and 20 mph respectively). See attached extract from Network Rail Sectional Appendix within the Approval in Principle Form 001 design submission document, produced to Network Rail Form 001 template, referenced as Doc Ref: NG8106/BIR Form 1 Date: February 2013, appended to this application. The area of reduced platform width alongside the footbridge stair will only be used for access to the front car of trains, and for access to and from the proposed lift. Note: it may be possible to place a three-car stop sign west of the new footbridge, so the areas of reduced platform width will only be used by the extreme end doors and service door of a discrete number of daily peak hours six-car train services; however, this measure is not The flashing aspect sequence will reduce the risk of trains accelerating towards the divergence after receiving a delayed aspect release on the junction signal, as majority of diverging trains will be signalled with the flashing aspects rather than MAR. The SPAD risk from anticipation on P468 is reduced. Flashing aspects exist for a range of different turnout speeds on this route, including lower speeds, and driver route knowledge is acceptable as the primary means of speed control for this junction, which has little potential for confusion with other junctions in this area. Provision of PSWI with AWS arrangement is considered to adequately manage the over-speed risk at the junction, and assist with driver route knowledge as to what speed the flashing sequence relates. Provision of MAY-FA can have an impact on SPAD risk the signal after the junction. Controls and TPWS have been provided in line with current RGS to manage these risks. In addition to the reduced SPAD and derailing risk due to accelerating to excess speed, the performance benefit of this arrangement has been estimated at 90 s when compared to current MAR arrangements. Future S & C renewal is planned to include improvements allowing The flashing aspect sequence will reduce the risk of trains accelerating towards the next signal after receiving a delayed aspect release on the junction signal, as the majority of diverging trains will be signalled with the flashing aspects rather than MAR. The SPAD risk from anticipation on HM567 is reduced. Flashing aspects exist for a range of different turnout speeds on this route, including moderate speeds. Existing linespeed on the approach to HM567 is only 5 mph below the lower limit of the permissible speed approaching a divergence of 40 mph or greater, as detailed in table 23. The proposed use of flashing aspects in this situation is compliant with Network Rail Company standard NR/L2/SIG/19609, Issue 1, section 10. 1. 1(e). Under MAY-FA, the driver will receive earlier notification of a divergent route set than under the existing MAR controls. Therefore, the severity of the proposed noncompliance is minimal and driver route knowledge is acceptable as the primary means of speed control for this junction, which is considered to have adequate physical separation from other use of flashing aspects on the route. Provision of MAY-FA can have an impact on SPAD risk Risk assessment for the reduced overlap has been conducted as per requirements of section 4. 9 of GK/RT0064 and considered the overlap risk to be ALARP (see attached SORA report Appendix F). Permissible speed is very low (10 mph) and begins 315 m on approach to the signal and hence only 85 m short of the requirement. GK/RT0075 states that braking at 10 mph on a 1 in 100 fall gradient to be 118 m, thus the 400 m approach distance is significantly more than that required to actually stop at PN245. TPWS is provided at the signal and will be fully effective for train with up to 9%g effective brakes. Trains with an emergency brake of less that 9%g are mitigated by the provision of a sliding buffer that will retard the train in a controlled manner. Applicant Organisation Merseyrail Electrics 2002 Ltd Certificate Issue Date 10/06/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 08/05/2013 Deviation Status Current Network Rail 21/05/2013 N/A CCS 18/04/2013 Current Network Rail 21/05/2013 N/A CCS 18/04/2013 Current Network Rail 21/05/2013 N/A CCS 18/04/2013 Current Page 66 Deviations Register RGS Number GKRT0044 RGS Issue Number One RGS Title Controls for Signalling a Train onto an Occupied Line Certificate Number 13-051-DGN Title PN226(3C) and (4C) Route Controls Lancaster South. GKRT0063 One Approach Locking &amp; Train Operated Route Release 13-050-DGN GMRT2472 One Data Recorders on Trains - Design Requirements GMRT2130 Three Vehicle Fire, Safety and Evacuation Current Deviations Register as at 09 May 2016 RGS Clause 5.3.2c, 5.3.2e, 5.3.3a Scope PN226(3C) and (4C) - Lancaster South. New call on routes on an existing signal. Nature and Degree Permissive routes have been provided from PN226 signals into platforms 4 and 5. The call-on routes have been requested by the operator for consistency with existing route (1C) to the Down Platform, for use as contingency in time of perturbation. Complying will lead to a fair amount of nonstandard design within the interlocking. As the current interlocking is Westpac, it does not support all the controls as standard and will require the controls to be free wired to meet requirement of the current RGS. This non-standard design will lead to inconsistency with other permissive routes at Lancaster 232, 234, 235, 239, 240, 241, 242, 245, 248 and 249 signals. This inconsistency would also introduce a technical complexity and cost that is considered disproportionate to the risk being managed by the controls. Estimated cost to provide fully compliant controls would be in the order of œ330k (design œ120k, installation and testing œ180k (including materials), project costs œ30k). Risk Assessment/Safety Justification Applicant Organisation New permissive routes will be classified as Network Rail `Emergency Use Only' (PP-X) in the section appendix. This will limit the use of permissive working, and only allow to be used for contingency and not booked moves. The principle is that provision for emergency use is better than no route at all or calling trains past a red signal. Emergency (PP-X) use of the call-on routes require the signaller to contact the driver prior to setting, so mandating 5. 3. 3 a) by procedure. This will be recorded as a matter of course in box instruction that shall also include instruction that 5. 3. 2 c) shall be applied by signaller. Call-on moves were assessed during the SORA process (see SORA report Appendix F) where it was agreed: "DA Representatives concluded that these routes are only for contingency use under the control of the signaller (better to have a signalled move than calling past a signal at stop) and no further mitigation measures need to be put in place. " There have been no reported incidents associated with current controls in use at Lancaster. Certificate Issue Date 23/05/2013 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 18/04/2013 Deviation Status Current Reading Station Area - Unconditional Train 5.3 Operated Route Release (TORR) for routes equipped with axle counters. Reading Station Area Redevelopment (RSAR) Project, routes equipped with axle counters. Provision of additional train detection sections and/or treadles for the purpose of TORR would incur additional costs for provision and on-going maintenance. Also, additional equipment would increase the likelihood of any secondary risks that may occur in the event of failure of the additional equipment. 23/05/2013 N/A CCS 18/04/2013 Current 13-048-DGN Derogation against event recorder crash protection requirements in GM/RT2472 Issue 1. B5.2.1, B5.2.2, B5.2.3 and B5.2.4. Extension of derogation Ref. 08/191/DGN for up to twenty more Class 70 locomotives manufactured and supplied by General Electric in 2013-2014. It is understood that the main purpose of the Network Rail additional sequence was to address risks associated with potential common mode failures on track circuits sharing Insulated Rail Joints (IRJs). The RSAR project is using Thales axle counter train detection that significantly reduces the risk of spurious operation that might satisfy the Train in Section Proving (TISP) and TORR conditions. No specific risk has been identified and, as such, no alternative action proposed so, with less trackside equipment, there is less maintenance required. As such, this application offers a 'safer' railway through less equipment, which would be required trackside without the provision of 'Unconditional TORR'. The call-on routes will require the approaching train to be signalled in to the station at low speed as the release of the call-on aspect will require the train to be more or less at a stand to release the call-on aspect in to the platforms and will be undertaken by the berth track section being occupied for a time. If the driver of the train misjudges the requirement of slowing down on the approach to the signal in question (for the call on route) and passes the signal at danger, then the train protection equipment (TPWS) will enforce The requirements set out in GM/RT2472 GE Transportation Issue 1, Section B5. 2, are designed to ensure that the stored data is retrievable following physical damage as the result of a crash. However, testing against the FRA crashworthiness requirements has already demonstrated that the integrity of the data recorder is maintained whilst subjected to the possible consequences of a crash. Therefore, it is believed that the impact of the use of the Wabtec TTX-IDR-03 data recorder will be minimal. GE Transportation's previous and extensive experience with this model of data recorder means that it has been possible to integrate it into the design of the new locomotive in a manner that offers the following benefits: · the design and installation is already proven on other locomotive designs; · eliminates the risk of interference with other train systems that a new data recorder could introduce; · eliminates the risk of design errors that integrating an unfamiliar item of equipment could introduce; · reduces design costs and testing requirements for the installation. 20/05/2013 N/A RST 19/04/2013 Current 13-047-DGN Derogation related to fire containment on main engine. 2.12.3.2 and 2.12.7 For derogation 09/186/DGN, evidence was GE Transportation provided as to why GE Transportation believes that there is no practical difference between the fire risk management philosophy currently accepted on the fleet of over 450 Class 66/67 locomotives that are already in operation in the UK and the proposed arrangement on the Class 70 locomotive. See discussion paper attached to derogation 09/186/DGN for further detail. 20/05/2013 N/A RST 19/04/2013 Current In derogation Ref. 08/191/DGN (granted), the use of a Wabtec Railway Electronics TTX-IDR-03 data recorder was proposed; which, whilst it is currently in use throughout the USA, has not undergone testing against the crash protection requirements set out in Section B5. 2 of GM/RT2472. In order to establish its suitability for use in the USA, the data recorder has been tested and shown to be compliant with the crashworthiness requirements in the Federal Railroad Administration (FRA) standard 49 FRA Part 229 - Locomotive Event Recorders: Final Rule. A copy of the test report for the TTX-IDR-03 data recorder is attached. In order to demonstrate compliance with the crash requirements of GM/RT2472, this model of data recorder would have to undergo testing, at a cost of approximately œ59,400 (2009 figures). This cost is made up of œ45,000 to undertake a full suite of tests, and œ14,400 to purchase nine data recorders on which to perform the tests. Note that nine data recorders was the quantity previously used to complete the suite of tests against GM/RT2472 on the QTron data recorder. In addition, being forced to fix RGS compliant OTMRs would add further redesign costs, delay, and Extension of derogation 09/186/DGN, to add The locomotive design is compliant to the up to an additional twenty new Class 70 fire detection and prevention requirements in locomotives, for use by unspecified the Loc & Pas TSI and SRT TSI, for a diesel operators (I. e. not just Freightliner as was freight locomotive. Therefore, this is the case for the initial locomotives 70001 considered to fulfil the essential 70030). These will be built by GE requirements in the Interoperability directive, Transportation in 2013-2014. in this regard. The risk is also similar to that on the existing UK diesel freight locomotive fleet. Compliance to the clauses in the RGS would incur significant redesign (e. g. increased thermal insulation and sealing etc. of the engine cabinet), and face practical difficulties, given the limit space and weight available within the existing loco design. Major redesign would also invoke significant reassessment, on a loco that is otherwise considered to be an `existing authorised design' within the Loc & Pas TSI. Such changes would also potentially have other knock-on effects, e. g. increased heat within the engine cabinet. Page 67 Deviations Register RGS Number GMRT2100 RGS Issue Number Three RGS Title Requirements for Rail Vehicle Structures Certificate Number 13-046-DGN Title RGS Clause Derogation from GM/RT2100 to comply with Sections 6,7,8,9,10 and 12. EN standards. Scope Fleet of heavy haul freight diesel-electric locomotives to be manufactured and supplied by General Electric (GE) in 2013 and 2014, to the maximum number of twenty locomotives. This derogation is to extend the scope of an existing derogation, 09/209/DGN, which originally gave exemption to specific load cases and requirements of GM/RT2100 Issue 3 for thirty locos for Freightliner (applying EN 12663 and EN 15227 instead). The requested extension is to cover up to a further twenty class 70 locomotives, for operation by unspecified operators. GMRT2466 Three Railway Wheelsets 13-045-DGN Derogation to use steel grade - ER9 for a wheel material. 2.9.1 Extension of scope of derogation Ref. 09/037/DGN (which was to Issue 2 of this standard) to include up to twenty more Class 70 freight locomotives to be manufactured by GE Transportation in 2013-2014 for undisclosed operators, and to cover Issue 3. GERT8030 Four Requirements for Train Protection and Warning System (TPWS) 13-044-DGN Use of TPWS equipment compliant with GE/RT8030 Issue 2 for ten Class 70 locomotives. Appendices F and H - All clauses Up to 10 (ten) new Class 70 locomotives to be manufactured by GE prior to September 2014 for unspecified operators. GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 13-043-DGN Dynamic modelling for the Class 70 dieselelectric locomotives, rather than testing on Network Rail infrastructure. D2 Extension of derogation Ref. 09/160/DGN to the manufacture and supply of up to twenty more Class 70 diesel-electric locomotives by GE Transportation in 2013-2014. GMRT2176 One Air Quality and Lighting Environment for Traincrew Inside Railway Vehicles 13-042-DGN Extension of scope of derogation against the 5.1 requirement for cab fresh air flow. This deviation application seeks to extend Whilst the Class 70 locomotives are No other impact identified. the scope of derogation 09/213/DGN to the normally driver only operated, the cab has manufacture and supply of twenty more provision for a second man and is therefore Class 70 locomotives by GE Transportation. required to meet 120 m3 per hour. The air flow testing conducted by GE Transportation has concluded that the rate of 120 m3 of fresh air per hour is only achieved at speeds of 23 mph and above. The measured air flow when stationary is approx. 27 m3/hr and increases with speed. In order to comply with this requirement, GE Transportation will have to undertake notable modifications to the HVAC system, which will have a significant cost and timescale impact on GE Transportation's delivery targets. GE Transportation has already delivered vehicle numbers 70001-70030 to the UK market, which have been in service without significant complaint about this issue. Increasing air flow through HVAC unit will also have knock-on effects in terms of compliance with the cab noise level limits in the Noise Technical Specification for Interoperability (TSI), which may further increase the suite of modifications required. It may also cause excessive draughts in the cab at higher speed. GMRT2130 Three Vehicle Fire, Safety and Evacuation 13-041-DGN Derogation against GM/RT2130 to exhaust the APU through the underframe. Existing Class 70 locomotives (7000170030) and a further build of up to twenty more Class 70 locomotives manufactured and supplied by General Electric in 20132014 to be operated on Network Rail infrastructure when outside a possession. Current Deviations Register as at 09 May 2016 3.1.1 Nature and Degree Risk Assessment/Safety Justification Whilst GM/RT2100 Issue 5 now includes The locomotive design is compliant with the reference to EN 15227 and EN 12663, other structural crashworthiness requirements of aspects are different to those applied in EN 15227 and the load cases of EN 12663, 2009 to the existing design, and the project and consequently with anticipated structural entity wishes to use the clause in Section 10 requirements of the Loc & Pas TSI and of GM/RT2100 Issue 5 which permits new GM/RT2100 Issue 5. If this derogation vehicles to be built to an existing authorised request is granted, then GE Transportation design up June 2017. As the `existing will be able to provide its prospective UK design' had derogation 09/209/DGN applied operators with more Class 70 locomotives, to it, it is considered appropriate to formally based on the design that is already in extend that derogation to cover the new service. locomotives. GE Transportation plans to manufacture and supply more Class 70 locomotives based on the existing design (existing design being for vehicle numbers 70001 - 70030). This existing design was built with consideration to GM/RT2100 Issue 3 and was granted derogation 09/209/DGN. To comply with the latest issue of the standard (GM/RT2100 Issue 5), GE Transportation will need to significantly modify the current design, and / or undertake new testing (e. g. for windows and windscreens, etc. ), leading to significant additional costs and timescale issues. This derogation request therefore seeks the extension of the scope of the existing derogation (09/209/DGN) on the existing design for the manufacture of the To achieve derogation 09/037/DGN, the The impacts will be minimal, since the project worked to GM/RT2466 Issue 2 performance characteristics of ER9 are (August 2008) and complied with the suite of similar to R9T and AAR M-107 Class B, both European Standards it identified. This of which are, or have been, approved. The provided some degree of "future proofing" at rim and web mechanical characteristics that point in time for the design and, as a (including minimum rim hardness) have consequence, avoid both potential some comparatively better properties when difficulties with material sourcing for the using ER9 rather than ER8. ER9 is harder initial fleet and redesign work for any follow- than ER8 and has a higher Ultimate Tensile on orders. The only material that is Strength (UTS) and yield strength, and approved in GM/RT2466 Issue 2 for the EN therefore is more resistant to Rolling Contact suite of standards is ER8. However, the Fatigue (RCF) and wear. project wishes to use ER9 because it has similar performance characteristics to the material AAR M-107 Class B, which GE Transportation uses as their standard material for this application. It also assists GE Transportation in their development of a common bogie for both the UK and mainland Europe, as ER9 is an already approved material in Europe. GE Transportation wants to use ER9 for this application for the production of the new class 70 locomotives. GM/RT2466 Issue 2 does not permit a `mix and match' between different suites of standards, therefore it is not permissible to simply apply AAR M-107 Class B material whilst using EN requirements for the remainder. Production of TPWS equipment that is The equipment is proven to be compatible validated as being compliant with with UK infrastructure and does not GE/RT8030 Issue 4 is not yet available. The introduce any new safety risks. need to await availability is estimated to add an additional four to six month delay in project delivery and large costs of integration design and installation. In addition, this delay has major ramifications due to the timescales imposed by other EU Directives. The attached additional explanation provides more details of this. Derogation 09/160/DGN was granted to N/A permit GE Transportation to use a validated dynamic model of the class 70 locomotives, in place of undertaking real UK on-track tests. This was subsequently done, and the Class 70s have been in service operation with Freightliner since late 2009. It is now requested to extend the derogation to cover additional new class 70 locomotives which GE Transportation will be building in 20132014, and to include issue 3 of GM/RT2141, as the original derogation was granted against issue 2. This will enable the 2009 modelling and assessment / scrutiny to be reused for the new locos, avoiding UK based on-track ride testing. Due to the location of the APU and with the limited amount of space available as a result of compliance with locomotive gauge, routing the APU exhaust so that it discharges in a location which is compliant with GM/RT2130 Clause 3. 1. 1 is difficult and introduces a number of additional risks. These are discussed in detail in the supporting paper attached to 09/038/TNC. Applicant Organisation GE Transportation Certificate Issue Date 20/05/2013 Certificate End Date N/A Lead SC RST Lead SC Approval Date 19/04/2013 Deviation Status Current GE Transportation 20/05/2013 N/A RST 19/04/2013 Current GE Transportation 21/05/2013 N/A CCS 18/04/2013 Current GE Transportation Ltd 20/05/2013 N/A RST 19/04/2013 Current GE Transportation 20/05/2013 N/A RST 19/04/2013 Current The circumstances under which the APU will GE Transportation be required to operate are very limited, and the impact on the railway is considered to be negligible. This is discussed in detail in the supporting paper attached to 09/038/TNC. It is also noted that many OTMs exhaust much larger engines to the underframe, such as MPVs. 03/09/2013 N/A RST 19/04/2013 Current Page 68 Deviations Register RGS Number GMRT2473 RGS Issue Number One RGS Title Power Operated External Doors on Passenger Carrying Rail Vehicles Certificate Number 13-040-DGN Title Replacement header gear for Class 319 vehicle passenger door system. RGS Clause B6.1 Scope As a result of both obsolescence and reliability issues, Porterbrook Leasing Company Ltd commissioned IFE Automatic Door Systems (part of the Knorr-Bremse Group) to redesign the passenger door header gear for the class 319. The deviation applies only to the door opening and closing forces associated with this redesign. GERT8000-TS2 Three Track Circuit Block Regulations 13-038-DGN Permissive Working - National 3.3.2 National GKRT0094 One Train Voice Radio Systems 13-035-DGN Operational use of GSM-R Handheld as mitigation against a failed fixed GSM-R cab radio. 3.20.1 and 7.1.1 GKRT0192 Two Level Crossing Interface Requirements 13-034-DGN Thatcham LC: Deficient position of signal T2855 relative to crossing. 2.1.1.3 a) Operational use of a GSM-R OPH in driving The impact of complying with current RGS cabs as a mitigation measure against failure requirements for the transportable radio of the fixed cab mobile radio. would be: · 3. 20. 1 - Full compliance would result in a need for the CT3 number of the existing fixed cab mobile radio to be removed from the network by the TEC before the OPH could be provisioned on the network. This would negatively impact on the speed of deployment of the equipment and increase the risk of a negative impact on performance. Also, in situations where a maintainer is not readily available, the programming of the CT3 number into the OPH would need to be carried out by a driver who, currently, is not trained to undertake this function. This would be a new procedure and may be prone to error as the raw CT3 number need to be understood by the driver; e. g. Cab A of unit 323001 would be 31632300101. This is considered an unnecessary complication and likely to cause confusion. · 7. 1. 1 - Full compliance would need an OPH to be connected to the main GSM-R antenna of the train. This would introduce a disproportionately high cost against a relatively small radio performance benefit due to the costs involved in modification of the train cab environment; additionally, this also presents Thatcham MCB - CCTV, ELR: BHL, Signal The RORI project is remitted to relock and T2855, Reading Outer Relock &amp; recontrol the signalling through this location, Immunise (RORI) Project. and renew the train detection equipment. The existing LC protecting signal T2855 is in a non-compliant position 22 m from Thatcham LC. The project remit is in compliance with the Signalling Compliance Approach - Western Mainline Signalling Renewal, Section 3. 1 (Signal profiles). Form and layout of the L2855 signal is unaltered, the project therefore does not intend to move the signal to a compliant position. Compliance would mean moving signal 3 m, and also moving all associated platform equipment such as DOO and car stop markers. If T2855 is moved, the 3 m required to achieve compliance with current standards for DOO equipment would be required to be followed. This would mean that the stopping point should be ideally 25 m but minimum, subject to risk assessment, 15 m from the signal because of the prominence of the signal 15 m likely be acceptable. This means that trains would stop at least 18 m further back than currently; a six-car turbo (class 166) is 138 m in length and the usable platform length would become less than this and as such platform extension would be required. Current Deviations Register as at 09 May 2016 Nature and Degree The redesign incorporates a new sliding cylinder which actuates the opening and closing of the doors; the function is identical to the previous design with the exception of the forces; both incorporate a pushback system. The peak closing force of the new sliding cylinder is 327N and the peak opening force is 389N; the pushback force is 128N. Whilst the closing and opening forces of this cylinder is above the stated 300N peak force, the pushback force of 128N is within the specified 150N limit in 6c above; this would act to limit the clamping force when the doors were shut (or close to being shut). The redesign is an improvement on the existing design where the close force of the cylinder is 341N and push back is 143N. The opening force has remained the same at 389N. After discussion with the current supplier of door header gear, it was stated that, in order to comply with group standards, we would need to redesign the pneumatic system and include a control module with an obstacle detection system as well as changing the door cylinder from the existing duplex design to a conventional cushion type. This would have added considerable extra complexity to the door system with the MPVs are not currently listed as an authorised vehicle permitted to operate under 'Permissive Platform Arrangements'. The current rules associated with the operation of multi-purpose vehicles (MPVs) prohibit them from being operated in accordance with 'Permissive Platform Arrangements'. Risk Assessment/Safety Justification Applicant Organisation A cost benefit analysis has been undertaken First Capital Connect Ltd to understand the order of change required to reduce injuries as a result of door trap incidents to ALARP. This concluded that in the very worst case and for a fifteen year remaining life of the vehicles that there was no case to redesign the doors. As such, the approach taken was one to remove obsolescence issues and use the synergy created to gain any performance benefits of the change. There is no impact to the railway system as a result of the proposed change. Implementing the new door header gear will result in a system which is more compliant to the current Railway Group Standard than the existing design. It is expected that there will be a reliability benefit from fitting the new door header gear. Certificate Issue Date 20/05/2013 Certificate End Date N/A Lead SC RST Lead SC Approval Date 19/04/2013 Deviation Status Current This derogation is to enable MPVs to be Network Rail included in the list of authorised vehicles able to occupy a permissive platform line (as per Rule Book Module TS2, Clause 3. 3. 2). Platform lines 1, 2, 3 ECS (MPV), 5, 9 and 0. Over the past three years, MPVs have been operating under trial conditions to allow MPVs fitted with CCTV cameras for examinations of switches and crossings (S & C); this approach reduces the need for placing track workers at risk in complex track areas if the optical camera train is not utilised and inspections are undertaken on foot. In addition to the CCTV MPV, other MPVs have also (under trial conditions) been allowed to occupy platforms under 'Permissive Platform Arrangements', in order to allow greater flexibility in the timetabling of MPVs for seasonal preparedness. This flexibility allows more track miles to be treated (Railhead), in turn reducing the consequences of Poor Railhead incidents including SPADs. A permanent change in the Rule Book would provide the benefits of these trials to be appreciated across the industry. More areas treated less risk of SPADs and station overruns. Track inspections in complex areas utilising the optical MPV removes the With consideration of the foregoing, the First ScotRail Ltd level of impact / risk is considered to lie within acceptable bounds because: · 3. 20. 1 - The use of the OPH is expected to be infrequent (see Appendix B) due to the predicted reliability of the installed fixed cab radio. Operational rules permit a train to operate without a radio in some circumstances. Therefore, it is safer and has performance benefits to run with an OPH than with no radio. Operational rules and procedures for the use of the OPH will be implemented across the Network stipulating that the OPH should be CT2 registered if an OPH is to be used, therefore reducing the risk of non-identification / misscommunication. Signallers will be fully briefed on the operational use of OPH radios by drivers. This includes the unique engine number that the OPH will have, I. e. 000xxxA; therefore, highlighting the identity in advance and, if necessary voice protocols, will be used to establish the identity of the caller. · 7. 1. 1 - To support a case for the operational use of OPHs as a mitigation measure for failure of a fixed cab mobile using its own antenna, a number of test runs using similar performing (2 watt) handheld equipment and laptop data The project is not affecting level crossing Network Rail interface between road and rail from that which currently exists. T2855 has been in this non-compliant position for many years with no known SPAD issues. The signal would have been commissioned when 25 yards from the crossing was permitted making this signal less that 1 yard defficient. The risk of a collision on the crossing because of the deficient position of the protecting signal will be mitigated by providing speed measuring treadles. Refer to scheme plan Ref. 11-GW-019/03, version 2. 1. This will initiate the crossing sequence in the event of a train approaching T2855 at a speed which is likely to result in a SPAD. 13/05/2013 N/A TOM 09/04/2013 Current 08/07/2013 N/A CCS 21/03/2013 Current CCS 21/03/2013 Current 11/04/2013 Page 69 Deviations Register RGS Number GKRT0192 RGS Issue Number Two RGS Title Level Crossing Interface Requirements Certificate Number 13-032-DGN Title Balne Lowgate LC: Deficient position of signal D862 relative to crossing. RGS Clause 2.1.1.3 a) GKRT0192 Two Level Crossing Interface Requirements 13-031-DGN Burn Lane LC: Deficient position of signal S875 relative to crossing 2.1.1.3 a) GKRT0192 Two Level Crossing Interface Requirements 13-030-DGN Henwick Hall LC: Deficient position of signal 2.1.1.3 a) S878 relative to crossing. GKRT0192 Two Level Crossing Interface Requirements 13-029-DGN Heyworth LC: Deficient position of signal D856 relative to crossing. Current Deviations Register as at 09 May 2016 2.1.1.3 a) Scope Balne Lowgate LC, ELR: ECM2, Mileage: 165m22ch, Linespeed: 125mph, D862 on the Up Main controlled from Doncaster PSB. Nature and Degree The project is remitted to renew Balne Lowgate LC from MCG to MCB-OD crossing type as part of a scheme to reduce the number of signal boxes in the LNE area. The existing LC protecting signal D862 is in a non-compliant position 23m from the Balne Lowgate LC. To comply would require D862 moving by at least 27m to a position 50m from the crossing. A move is technically possible, but would introduce a certain degree of unfamiliarity and additional route learning/familiarisation that may introduce risk, as drivers are familiar with the current position of the signal. The estimated total cost of œ215k is fairly high when compare to alternative proposal. Risk Assessment/Safety Justification The project is not affecting level crossing interface between train driver and crossing from that which currently exists. D862 has been in this non-compliant position for many years with no known SPAD issues. If the signal was at 50 m from the crossing, the train would have to be travelling at 20 mph to give 5 seconds red road lights before train arrives at the crossing. The Stowmarket treadle is positioned such that a train travelling up to 50 mph will still give at least 5 seconds of red road lights before train arrives at the crossing, thus improving SPAD mitigation. Using statistical data from the Signal Assessment Tool (SAT), the probability of a SPAD travelling 50 m is only 7% less than travelling 23 m. This minor increase in probability of the SPAD reaching the crossing would only slightly improved SPAD risk at the crossing if a compliant signal position was provided. This additional risk of a collision on the crossing will be mitigated by longer warning times provided by `Stowmarket' controls and overrun treadles when train approaches at red signal. Further information on impact can be found in the supporting Risk Assessments. Burn Lane LC, ELR: TCW1, Mileage: The project is remitted to renew Burn Lane The project is not affecting level crossing 170m70ch, Linespeed: 75mph, S875 on the LC from MCG to MCB-OD crossing type as interface between train driver and crossing Dn Selby controlled from Selby West SB. part of a scheme to reduce the number of from that which currently exists. S875 has signal boxes in the LNE area. The existing been in this non-compliant position for many LC protecting signal S875 is in a nonyears with no known SPAD issues. If the compliant position 23 m from the Burn Lane signal was at 50 m from the crossing the LC. To comply would require S875 moving train would have to be travelling at 20 mph by at least 27 m to a position 50 m from the to give 5 seconds red road lights before train crossing. A move is technically possible, arrives at the crossing. The Stowmarket but would introduce a certain degree of treadle is positioned such that a train unfamiliarity and additional route travelling up to 50 mph will still give at least learning/familiarisation that may introduce 5 seconds of red road lights before train risk, as drivers are familiar with the current arrives at the crossing, thus improving position of the signal. The estimated total SPAD mitigation. Using statistical data from cost of œ215k is fairly high when compare to the Signal Assessment Tool (SAT) the alternative proposal. probability of a SPAD travelling 50 m is only 7% less than travelling 23 m. This minor increase in probability of the SPAD reaching the crossing would only slightly improved SPAD risk at the crossing if a compliant signal position was provided. This additional risk of a collision on the crossing will be mitigated by longer warning times provided by `Stowmarket' controls and overrun treadles when train approaches at red signal. Further information on impact can be found in the supporting Risk Assessments. Henwick Hall LC, ELR: TCW1, Mileage: The project is remitted to renew Henwick The project is not affecting level crossing 172m20ch, Linespeed: 75 mph, S878 on the Hall LC from MCG to MCB-OD crossing interface between train driver and crossing Up Selby controlled from Selby West SB. type as part of a scheme to reduce the from that which currently exists. S878 has number of signal boxes in the LNE area. been in this non-compliant position for many The existing LC protecting signal S878 is in years with no known SPAD issues. If the a non-compliant position 26 m from the signal was at 50 m from the crossing, the Henwick Hall LC. To comply would require train would have to be travelling at 20 mph S878 moving by at least 24 m to a position to give 5 seconds red road lights before train 50 m from the crossing. A move is arrives at the crossing. The Stowmarket technically possible, but would introduce a treadle is positioned such that a train certain degree of unfamiliarity and additional travelling up to 50 mph will still give at least route learning/familiarisation that may 5 seconds of red road lights before train introduce risk, as drivers are familiar with arrives at the crossing, thus improving the current position of the signal. The SPAD mitigation. Using statistical data from estimated total cost of œ215k is fairly high the Signal Assessment Tool (SAT) the when compare to alternative proposal. probability of a SPAD travelling 50 m is only 7% less than travelling 26 m. This minor increase in probability of the SPAD reaching the crossing would only slightly improved SPAD risk at the crossing if a compliant signal position was provided. This additional risk of a collision on the crossing will be mitigated by longer warning times provided by `Stowmarket' controls and overrun treadles when train approaches at red signal. Further information on impact can be found in the supporting Risk Assessments. Heyworth LC, ELR: ECM2, Mileage: The project is remitted to renew Heyworth The project is not affecting level crossing 162m55ch, Linespeed: 125mph, D856 on LC from MCG to MCB-OD crossing type as interface between train driver and crossing the Up Main controlled from Doncaster PSB. part of a scheme to reduce the number of from that which currently exists. D856 has signal boxes in the LNE area. The existing been in this non-compliant position for many LC protecting signal D856 is in a nonyears with no known SPAD issues. If the compliant position 26 m from the Heyworth signal was at 50 m from the crossing, the LC. To comply would require D856 moving train would have to be travelling at 20 mph by at least 24 m to a position 50 m from the to give 5 seconds red road lights before train crossing. A move is technically possible, arrives at the crossing. The Stowmarket but would introduce a certain degree of treadle is positioned such that a train unfamiliarity and additional route travelling up to 50 mph will still give at least learning/familiarisation that may introduce 5 seconds of red road lights before train risk, as drivers are familiar with the current arrives at the crossing, thus improving position of the signal. The estimated total SPAD mitigation. Using statistical data from cost of œ215k is fairly high when compare to the Signal Assessment Tool (SAT) the alternative proposal and would worsen the probability of a SPAD travelling 50 m is only existing distance (844 m) to Barcroft LC 7% less than travelling 26 m. This minor which this signal also protects. increase in probability of the SPAD reaching the crossing would only slightly improved SPAD risk at the crossing if a compliant signal position was provided. This additional risk of a collision on the crossing will be mitigated by longer warning times provided by `Stowmarket' controls and overrun treadles when train approaches at red signal. Applicant Organisation Network Rail Certificate Issue Date 31/05/2013 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 16/05/2013 Deviation Status Current Network Rail 31/05/2013 N/A CCS 16/05/2013 Current Network Rail 31/05/2013 N/A CCS 16/05/2013 Current Network Rail 31/05/2013 N/A CCS 16/05/2013 Current Page 70 Deviations Register RGS Number GORT3056E RGS Issue Number Two RGS Title Movement of Freight Trains Certificate Number 13-028-DGN Title Higher priority Freight trains. RGS Clause E4.2 Scope National. Nature and Degree Currently, Freight trains are restricted to class 4, 6, 7, 8, dependant on the permissible speed of the train and wagons. We currently have a number of train services on the network conveying high consequence and perishable goods. At certain times, and also in line with transit requirements, there needs to be a way of defining these services as having a higher priority (but not necessary a higher speed). By changing the headcodes to become a class 3, with a suitable route briefing pack, the trains can be managed differently on the network, and treat with higher priority where allowed. Risk Assessment/Safety Justification Applicant Organisation Identification of the current and future freight Network Rail services that convey high consequence and perishable goods. These services need to be amended in the working timetable and any other requirements changed to allow the services to operate. A proposal has been submitted via a "proposal for change document - SDP 1226". Previous conversations on the subject have taken place with all the main Freight Operators, including DB Schenker, Freightliner, Direct Rail Services, GBRf and Colas. Due to a specific incident in 2012 involving high consequence goods, a new requirement for the conveyance of this traffic has led to an urgent requirement to address the issue. DB Schenker has requested that a specific train has a different headcode with immediate effect, and Direct Rail Services have shown considerable support for the perishable goods that they carry. Also, discussions with the Network Rail Freight Director and his team have taken place, and they are looking into any commercial issues that may arise with the change. Certificate Issue Date 01/03/2013 Certificate End Date N/A Lead SC TOM Lead SC Approval Date 05/02/2013 Deviation Status Current GORT3056A Two Introduction and Classification of Freight Trains 13-027-DGN Higher priority Freight trains. A2.1 National. Currently, Freight trains are restricted to class 4, 6, 7, 8, dependant on the permissible speed of the train and wagons. We currently have a number of train services on the network conveying high consequence and perishable goods. At certain times, and also in line with transit requirements, there needs to be a way of defining these services as having a higher priority (but not necessary a higher speed). By changing the headcodes to become a class 3, with a suitable route briefing pack, the trains can be managed differently on the network, and treat with higher priority where allowed. Identification of the current and future freight Network Rail services that convey high consequence and perishable goods. These services need to be amended in the working timetable and any other requirements changed to allow the services to operate. A proposal has been submitted via a "proposal for change document - SDP 1226". Previous conversations on the subject have taken place with all the main Freight Operators, including DB Schenker, Freightliner, Direct Rail Services, GBRf and Colas. Due to a specific incident in 2012 involving high consequence goods, a new requirement for the conveyance of this traffic has led to an urgent requirement to address the issue. DB Schenker has requested that a specific train has a different headcode with immediate effect, and Direct Rail Services have shown considerable support for the perishable goods that they carry. Also, discussions with the Network Rail Freight Director and his team have taken place, and they are looking into any commercial issues that may arise with the change. 01/03/2013 N/A TOM 05/02/2013 Current GIRT7016 Four Interface between Station Platforms, Track and Trains 13-026-DGN Lewes station, Down Siding - Equipment in overrun risk zone. 6.3.1.1 The position of the gate line is dictated by its position in relation to the existing over bridge stairs (a minimum run off of six metres is required from the bottom of the stairs to avoid queuing up them) and also the need for visibility for platform staff to dispatch trains. The position of the existing ramp and steps from the platform would mean passengers exiting the gates would have to make a 90 degree turn to exit the station which would cause congestion on both the ramp and platform and also obscure the view for train dispatch. N/A INS 06/03/2013 Current Four Interface between Station Platforms, Track and Trains 13-022-DGN Elstree and Borehamwood station platform 2- 6.2.2 3 - reduced platform width at lift shaft and stairs The existing layout is shown on drawing Southern Railway 5437/02/06. The risk weighting factor (calculated using the methodology in Appendix A of GI/GN7616 - Guidance on Station Platform Geometry Issue One December 2010) is 81. 28. The proposed layout is shown on drawing 5437/02/07. The risk weighting factor (calculated using the methodology in Appendix A of GI/GN7616 Guidance on Station Platform Geometry Issue One December 2010) is 81. 28. The analysis shows that the risk within the buffer stop overrun remains the same and is unaffected by the proposals. For the installation of a new footbridge and The action taken as previously described Network Rail lifts at Elstree &amp; Borehamwood station has been undertaken to try to achieve following design iterations, a derogation compliance or minimise the effect of the against platform width is required. For required derogation. Minor degree - A linespeeds less than 100 mph, the minimum reduction of 60 mm below the requirements clear dimensions to the platform edge to the of NR/L2/TRK/2049 and GI/RT7016 will be nearest face of the building structure shall provided over a limited length of platform. be 2500 mm, only 2440 mm will be provided The reduction covers the 6 m length of the over limited lengths. The Access for All lift shaft and LMR and approximately 5 m of works at Elstree and Borehamwood Station platform adjacent to the lower flight of the require the installation of a new footbridge stairs. and lifts on all platforms. The central island platform, Platforms 2 and 3, are of limited width. If the 3000 mm required clearance on Platform 3 is provided, the clear platform width on Platform 2 will be 2440 mm a reduction of 60 mm below the requirements of the standards. 12/03/2013 GIRT7016 Lewes station. The deviation applies to the construction of a set of steps and installation of a ticket vending machine within the 20 m overrun from the buffer stops to the down siding at Lewes Station (as shown on drawings: 5437/02/06 and 5437/02/07). New access steps: Located in Area A "High" risk zone. New Ticket Vending Machine: Located in Area A "High" risk zone. The Down Siding can only be accessed by use of a Ground Frame and there are very few movements that will be approaching the buffer stops during normal operating hours. The lift shaft, lift machine room, and footbridge stair on Platform 2-3 at Elstree and Borehamwood station will have reduced clearance on the Platform 2 side only. 22/03/2013 N/A INS 06/03/2013 Current GIRT7016 Four Interface between Station Platforms, Track and Trains 13-019-DGN Euston station platform 18 - reduced buffer stop overrun risk zone Geographical scope is the southern end of Euston platform 18. Existing platform 18 buffer stop and secondary units. Proposed new equipment is a Modular Sliding Friction Buffer Stop currently as used at Euston platforms 5 and 6. Please refer to attached drawing Ref. BBRTS DWG No. 141977. The project seeks to replace the existing buffer stop and install the new unit 11 m closer to the terminal wall. This brings existing structures, specifically some unoccupied rooms, inside the overrun risk zone. It also brings an existing roof support column closer to the buffer stop face. Please see attached drawing B90308-DRGCIV0002 for details of the areas affected and the attached reports. Our requirements to become compliant, without a derogation, would entail major station or track restructuring. As part of the Grip 3 report, a risk assessment has been carried out that supports the proposal. 26/04/2013 N/A INS 06/03/2013 Current Current Deviations Register as at 09 May 2016 6.3.2.1 The unoccupied rooms behind the platform Network Rail end wall have a zero weighting as per risk assessment process outlined in GC/RC5633 and GI/GN7616, and therefore have zero impact on the risk assessment process with regards risk of fatality to passengers, staff &amp; members of the public (please see report attached). Furthermore, the southern end of platform 18 is rarely frequented by members of the public. The existing combined roof support/OHLE column is the last column of the trainshed roof. All the other columns are within the derailment risk zone, approximately 1. 5 m from the nearest rail. Moving the buffer stop back by 11 m will bring the second till last column out of the overrun risk zone and into the derailment risk zone and bring the last column from 17 m to 6 m behind the buffer stop face. · The proposed Buffer stop arrangement is already in use on platforms 5 and 6 at Euston with similar stopping tolerances. The buffer stop will reduce the trains speed by the same amount as the current buffer stop arrangement within a reduced sliding distance. · The rooms behind the platform end wall are unoccupied as detailed within the reports attached. · The southern end of platform 18 is rarely frequented by members Page 71 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 13-017-DGN Title Selhurst Station - extension of platforms; reduced platform recess. RGS Clause 11.1.4 Scope Selhurst Station is located approximately 9 miles 31 chains from London. Equipment involved: station platforms, bridge girders. GKRT0045 Two Lineside Signals, Indicators and Layout of Signals 13-015-DGN Performance Category for Colour Light Signals at London Bridge (Medium-Range Signals). 2.2.1.10 and 2.2.1.11 Permit use of medium range colour light signals for signals in the London Bridge area. London Bridge re-signalled area including all lines from stations: Charing Cross/Cannon Street/Farringdon/London Bridge Platforms 8-16, to stations: Deptford, St Johns, Brockley and Queens Road Peckham'. GKRT0075 Two Lineside Signal Spacing and Speed Signage 13-014-DGN Minimum Braking Distances MLN1 for Reading Outer Relock. 2.3.1 · Reading Outer Relock &amp; Immunise (RORI) West, B & H Project Area · Reading Outer (West) MLN1 41m 60ch to 51m 50ch · Up Main - T832 (Appendix B & C), T824 (Appendix B & C), T816 (Appendix B), T808 (Appendix B), T800 (Appendix B), T792 (Appendix B), T784 (Appendix B) · Down Main - T821 (Appendix B & C), T829 (Appendix B & C), T837 (Appendix C), T845 (Appendix C) · Up Relief - T786 (Appendix B), T794 (Appendix B), T802 (Appendix B), T810(Appendix B), T818(Appendix B), T826(Appendix B), T834(Appendix B) · Down Relief - T831 (Appendix B), T823 (Appendix B). · Reading Outer (B & H ) BHL 38m 70ch to 56m 09ch · Up Westbury T2856 (Appendix B). GMRT2130 Three Vehicle Fire, Safety and Evacuation 13-013-DGN Revised 25-10-2013 Derogation to GM/RT2130 Issue 3 for the MPVs (Base vehicle, including Open-line MPVs and Wagons of the Network Rail High and In-Possession cabs), Wagons (InOutput OLE Construction System (HOPS). Possession cabs on wagons): · Clause 2.1 Vehicle fire performance categories · Clause 2.2 General requirements (except clause 2.2.4) · Clause 2.3 Safeguarding continued operation in the event of fire · Clause 2.7 Equipment cubicles and equipment cases · Clause 2.9 Material fire performance categories and selection · Clause 2.10 Layered materials and assemblies (except clauses 2.10.6 and; 2.10.7). MPVs and; Wagons (Working equipment, including Work Modules and Welfare Modules): · All clauses. GERT8030 Four Requirements for Train Protection and Warning System 13-012-DGN TPWS enhanced functionality for three Class 66 locomotives converted for use in the UK. Current Deviations Register as at 09 May 2016 Appendix F and Appendix H This application is to permit non-compliance with the RGS standard clauses of GM/RT2130 Issue 3 as identified in 6b above (RGS clauses) for the following vehicles. MPV vehicles: Type 1 (SOPB): · 99 70 9131 010 - 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4 · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7. Type 3 (SNPB): · 99 70 9131 015 - 8 · 99 70 9131 018 - 2 · 99 70 9131 020 - 8. Type 4 (HNPB): · 99 70 9131 003 - 4. Type 5 (SORB): · 99 70 9131 014 - 1. Wagons: Type KFA: · 99709131002-6 · 997091310042 · 99709131008-3 · 99709131009-1 · 99709131012-5 · 99709131016-6 · 99709131017-4 · 99709131019-0. Type JNA: · NLU 29024. Nature and Degree Sussex Train Lengthening Project involves the extension of platforms on the Sussex suburban route (ELR: BTH2) to accept tencarriage length trains (from eight-carriages). Selhurst Station is sited some 9 miles 31 chains from London. The useable length of Platform 1 (Down Slow) is to be extended on the London End by 26. 350 m and Platform 2 (Up Slow) is to be extended by 43. 950 m to 203 m. This involves extending the platform over a 20 m length of the existing girders of an underline bridge. It is not reasonably practicable to provide a compliant solution: in order to comply with all of the RGS requirements the existing bridge decks forming Dagnall Park underbridge VTB1 55A would require reconstruction. The site is constrained by the current track geometry and the current railway corridor boundaries. The track layout and geometry constraints to the immediate north and south of the station are carried by a series of arches and underbridges on the North by Dagnall Park Road Underbridge, and on the South by A213 Selhurst Road Underbridge. It is only possible to extend towards the North over Dagnall Park Road Bridge. The proposed platform extensions at these locations are proposed to be supported by new platform Use of signals to Category 1 or 2 are not the most appropriate solution at London Bridge due to the risk of read-across and readthrough there. Risk Assessment/Safety Justification Applicant Organisation Low severity issue. Passengers waiting for Network Rail trains in the morning peak spread out along the platform. The station entrance is at the opposite end of the platform, with the waiting room and canopied area about half way along. The maximum platform length proposed to have non-compliant recess/refuge provision is approximately 24 m. The maximum distance from a compliant refuge will therefore be no greater than approximately 12 m. The non-compliance is at the opposite end of the platform from the station entrance, beyond the waiting room and canopied area which are about half way along. Certificate Issue Date 03/04/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 06/03/2013 Deviation Status Current The workshop recommended two types of Network Rail signal: medium-range, narrow-beam and medium-range, wide-beam. Note that medium-range, wide-beam signals achieve the same performance as conventional filament lamp signals fitted with a spreadlight lens, which have been in use for a significant period. Medium-range, widebeam colour light signal: · 400 m, performance, up to +/-10 degrees off axis with a gradual reduction in intensity outside of this range. Medium-range, narrow-beam colour light signal: · 400 m, performance up to +/- 3 degrees off axis with a sharp drop in intensity outside this range. The mediumrange signals will be developed via the product acceptance process and adhere to Network Rail Standard `Product Introduction and Change' - NR/L2/RSE/100/05, Issue 1. 20/03/2013 N/A CCS 21/02/2013 Current To make signals compliant would require significant changes to the layout and position of all signals on the routes. It is not considered reasonably practicable to make compliant with the standard requirements as the costs of moving signals and further driver route knowledge outweighs any safety benefit, and would delay roll out of ERTMS and electrification on the route. See attached Signalling Compliance Approach Western Mainline Signalling Renewal, and Tracker 11067 Supportive Information. As there will be no change to the Network Rail operational railway, maintaining the current signal positions (and non-compliance) is considered to have a minimal impact. As detailed within Risk Assessment Report Reading Outer Re-signal and Immunise (RORI) - Appendix C, each signal identified by SDG Service Braking Model has been reviewed and considered as part of the risk assessment process in the development of the scheme, and it has been concluded that current signal position is acceptable. It is not considered reasonably practicable to make compliant with the standard requirements as the costs of repositioning signals and further driver route knowledge/learning outweighs any safety benefits of moving signals a few metres. Speeds and Signals were reviewed as part of the introduction of HSTs in the late 1970s. Revision of speed was considered unnecessary and unacceptable from a performance point of view. See attached Signalling Compliance Approach Western Mainline Signalling Renewal, section 3. 1 (Signal positions, spacing and sighting), and Tracker 11067 Supportive Information. Use of the alternative actions are considered Windhoff Bahn- und to deliver an equivalent level of control and Anlagentechnik GmbH safety and will not require any further ongoing actions or operational constraints. 20/03/2013 N/A CCS 21/02/2013 Current 12/03/2013 N/A Rolling Stock 04/10/2013 Current The TPWS equipment fitted to these three GB Railfreight Ltd locomotives would be identical to that fitted to the remainder of the fleet of Class 66 operated by GB Railfreight. The applicant believes that the TPWS equipment is in fact identical to all other Class 66s owned and operated by other freight companies in the UK. Given the number of occasions when Class 66s are hired from one freight operator to another, or when one FOC driver drives another FOC's locomotive as part of their normal duties, consistency between locomotive fleets is important. As these Class 66s will be operated as part of a nationwide fleet, use of consistent TPWS equipment minimise the risk of confusion and errors, particularly in emergency situations. A consistent TPWS MMI, buttons and indicator lights is considered to offer the clearest interface to drivers. 20/03/2013 N/A CCS 21/02/2013 Current In travelling/transit mode, these MPVs will be compliant with the Technical Specifications for Interoperability (TSI) requirements, including the Locomotive and Passenger TSI. In addition, they will be compliant with all applicable Notified National Technical Rules (NNTRs) to cover open points and specific cases, and ensure compatibility with the GB mainline system (Network Rail managed infrastructure). GMRT2130 is a listed NNTR and the application for derogation (12/167/DGN) originally sought non-compliance with Clause 2. 9. The current application has been expanded to include additional clauses as detailed in 6b above (Clause requirements). Within GMRT2130 Issue 3, there are a number of requirements that are neither related to TSI Open points/Specific cases nor compatibility with the GB system. These requirements have comparable requirements within the suite of TSIs, therefore compliance with these RGS requirements duplicates the TSI assessment. Consequently, additional effort and cost will be expended both in respect of production of the evidence of compliance and in its subsequent assessment by the Designated Body. It is also possible that, Fitting of TPWS equipment to three Class TPWS equipment that is validated as 66 locomotives, numbers 92 70 0066 747-1, compliant with the requirements of 92 70 0066 748-9 and 92 70 0066 749-7 to GE/RT8030 Issue 4 is not available. The allow operation in the UK. It is proposed to two suppliers of TPWS equipment are fit these three locomotives with TPWS developing and testing suitable equipment equipment compliant with Issue 2 of but it will not be available during the GE/RT8030. conversion and delivery programme for these three locomotives. The impact of complying with the current RGS requirement would be to delay significantly the introduction to service of these three locomotives, with a consequent effect upon the ability of GB Railfreight to provide traction for UK railfreight services. Were the equipment available, a considerable amount of design and re-engineering would be required prior to fitment, particularly within the cab area, leading to these three locomotives having a significantly different cab arrangement to the remainder of the fleet in the UK. Page 72 Deviations Register RGS Number GMRT2461 RGS Issue Number One RGS Title Sanding Equipment Fitted to Multiple Units and On-Track Machines. Certificate Number 13-011-DGN Title Derogation to GM/RT 2461 Issue 1 Sanding system for Windhoff MPV on-track machines. RGS Clause Clause 8.5 - System testing facility Clause 9.1 - Delivery to the rail head Clause 9.3.1 Braking mode. Scope This application is to permit noncompliance with the RGS standard clauses of GM/RT2461 Issue 1 as identified in 6b above, for the following MPV vehicles. Type 1 (SOPB): · 99 70 9131 010 - 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4 · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7 . Type 3 (SNPB): · 99 70 9131 015 8 · 99 70 9131 018 - 2 · 99 70 9131 020 - 8. Type 4 (HNPB): · 99 70 9131 003 - 4. GERT8035 Two Automatic Warning System (AWS) 13-010-DGN Derogation to GE/RT 8035 Issue 2 Automatic Warning System (AWS) for Windhoff MPV on-track machines. Clause 2.6.8.2 This application is to permit noncompliance with the RGS standard clause of GE/RT8035 Issue 2 as identified in 6b above, for the following MPV vehicles: Type 1 (SOPB): · 99 70 9131 010 - 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4 · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7. Type 5 (SORB): · 99 70 9131 014 1. GMRT2000 Three Engineering Acceptance of Rail Vehicles 13-009-DGN Derogation to GM/RT2000 Issue 3 for the MPVs of the Network Rail High Output OLE Construction System (HOPS) See details of RGS clauses in Appendix 1. Type 1 (SOPB): · 99 70 9131 010 - 9, · 99 70 9131 013 - 3, · 99 70 9131 021 - 6, · 99 70 9131 022 - 4, · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8, · 99 70 9131 005 - 9, · 99 70 9131 006 - 7, · 99 70 9131 011 - 7. Type 3 (SNPB): · 99 70 9131 015 - 8, · 99 70 9131 018 - 2, · 99 70 9131 020 - 8 . Type 4 (HNPB): · 99 70 9131 003 4. Type 5 (SORB): · 99 70 9131 014 - 1. GMRT2400 Four Engineering design of on-track machines 13-008-DGN Non-provision of lifeguards on an OTM operating as lead vehicle in a possession. 3.25.12 GERT8000-TW1 Eight Preparation and movement of trains General 13-007-DGN Higher priority Freight trains. Section 2 Current Deviations Register as at 09 May 2016 Nature and Degree The MPV test facility is situated in the drivers cab, not on the underframe, and the basis of the Network Rail High Output OLE Construction System (HOPS) Project design is to utilise read-over (existing) design systems and equipment that are proven in application wherever possible. To comply with the standard will entail a number of design changes to be implemented, with no significant improvement in safety or functionality. The MPVs have four axles only. Two powered axles are fitted to one bogie and two non-powered axles are fitted to the other bogie. The axles of the powered bogie are fitted with sanding units outboard of each wheel. The group standard was written to accommodate conventional twocar units with a total of eight axles. Without a complete redesign and re-build of the MPVs, it is not possible to comply with the requirements of the standard. The stopping distance under low adhesion conditions is naturally lengthened, and it can get out of driver's control, unless mitigations are considered. The option not to fit sanding for braking is therefore not acceptable. (See also previous approved derogation (11/137/DGN) which described two low speed collisions involving Class 142 multiple TPWS equipment that is validated as compliant with the requirements of GE/RT8030 Issue 4 is not available. The two suppliers of TPWS equipment are developing and testing suitable equipment but it will not be available during the construction and delivery programme for these machines. The functionality required to achieve compliance with the requirements of clause 2. 6. 8. 2 of GE/RT8035 Issue 2 forms part of the new generation TPWS equipment and is not currently available. The impact of complying with the current RGS requirement would be to significantly delay the project to introduce this type of machine to the UK. Applicant Organisation Windhoff Bahn- und Anlagentechnik GmbH Certificate Issue Date 20/03/2013 Certificate End Date N/A Lead SC RST Lead SC Approval Date 15/02/2013 Deviation Status Current Windhoff Bahn- und Anlagentechnik GmbH 20/03/2013 N/A CCS 21/02/2013 Current Use of the alternative actions are considered Windhoff Bahn- und to deliver an equivalent level of control and Anlagentechnik GmbH safety and will also not require any further ongoing actions or operational constraints. 22/03/2013 N/A RST 15/02/2013 Current Installation of an on-track plant type device Windhoff Bahn- und that meets the requirements of RIS-1530Anlagentechnik GmbH PLT Issue 4 may pose a risk when the vehicles are in travel mode outside possession. In order to mitigate this risk, the design will be retractable or removable. Evidence of compliance with RIS-1530-PLT when the machine is working within a possession and other standards when travelling outside a possession will be submitted to the NoBo/DeBo/CP in support of demonstrating conformance of the vehicles to all required standards. The use of this alternative action is considered to deliver an equivalent level of control and safety that will not require further actions or operational constraints. Currently, Freight trains are restricted to Identification of the current and future freight Network Rail class 4, 6, 7, 8, dependant on the services that convey high consequence and permissible speed of the train and wagons. perishable goods. These services need to We currently have a number of train be amended in the working timetable and services on the network conveying high any other requirements changed to allow the consequence and perishable goods. At services to operate. A proposal has been certain times, and also in line with transit submitted via a "proposal for change requirements, there needs to be a way of document - SDP 1226". Previous defining these services as having a higher conversations on the subject have taken priority (but not necessary a higher speed). place with all the main Freight Operators, By changing the headcodes to become a including DB Schenker, Freightliner, Direct class 3, with a suitable route briefing pack, Rail Services, GBRf and Colas. Due to a the trains can be managed differently on the specific incident in 2012 involving high network, and treat with higher priority where consequence goods, a new requirement for allowed. the conveyance of this traffic has led to an urgent requirement to address the issue. DB Schenker has requested that a specific train has a different headcode with immediate effect, and Direct Rail Services have shown considerable support for the perishable goods that they carry. Also, discussions with the Network Rail Freight Director and his team have taken place, and they are looking into any commercial issues that may arise with the change. 04/03/2013 N/A PLT 07/02/2013 Current 01/03/2013 N/A TOM 05/02/2013 Current These MPVs will be compliant with the Technical Specifications for Interoperability (TSI) requirements, including the Locomotive and Passenger TSI. In addition, they will be compliant with all applicable Notified National Technical Rules (NNTRs) to cover open points and specific cases, and ensure compatibility with the GB mainline system. They will also operate off transEuropean Network (TEN) routes and therefore the complete suite of RGSs is applicable. Within these RGSs, there are a significant number of requirements that are not directly related to TSI open points, specific cases or compatibility. These requirements have equivalent or comparable requirements within the suite of TSIs, therefore compliance with these RGS requirements duplicates the TSI assessment. Consequently, additional effort and cost will be expended both in respect of production of the evidence of compliance and in its subsequent assessment by the Designated Body. It is also possible that, due to the differences in the detail of the requirements, conflicts might exist that either prevent full compliance with both the TSI and RGS clauses, or necessitate a more complex design. Due to both the additional This application applies to existing KFA and The retro design and fitting of lifeguards Falcon wagons modified and re-classified as compliant with the standard would be OTMs to form part of the Network Rail High extremely difficult since the wagons are Output OLE Construction System (HOPS) fitted with traditional freight bogies which that will be hauled in train formation when were not designed as a leading bogie to travelling to and from site, and either hauled carry lifeguards. The associated costs with or propelled when working in a possession the design and testing of a compliant retro fit or work site. This application applies to the lifeguard are also considered prohibitive and following vehicles when propelled as the for these reasons, it is considered leading vehicle. KFA wagons: · unreasonable to comply with the quoted 99709131002-6 · 99709131004-2 · RGS clause. 99709131008-3 · 99709131012-5 · 99709131016-6 · 99709131017-4 · 99709131019-0 · 99709131009-1 (not to be fitted with lifeguards). Falcon wagon: · 99709131007-5. National. Risk Assessment/Safety Justification Operation of the test facility from the driving cab requires the driver to actuate the test from the cab and then check that sand has been discharged to the rail head. However, this can be done as part of the normal train preparation as is current practice. The requirements of GM/RT2461 regarding sanding positions with regard to wheelsets and sand deposition rates were based on ensuring that the train applying sand, and the train following the train applying sand would be detected, I. e. would operate track circuits. However, the other key requirement is that the sanding system is effective. In considering the impact, the Project has reviewed the history of the fitment of sanding systems to the Class 142 DMU fleet (two-car MU with a total of four axles). Extensive testing was carried out to investigate the effect of sanding with regards to track circuits for these units. These tests supported the derogation for these lightweight units with a reduced number of wheel sets. The Project has concluded that, under transit arrangements, the impact of the MPV design with sanding devices to the leading wheel set at significantly increased axle loads (20 tonnes), compared to the Class 14X forward of the first axle, is The TPWS/AWS installed on these machines would have the same functionality as on all relevant self-propelled Windhoff machines supplied to the UK. The annual mileages covered by On-Track Machines when transiting is significantly lower than for locomotives and multiple units. Almost all transit moves are undertaken outside peak traffic hours. The reliability of the current design of equipment is extremely good and the lack of ability to separately isolate AWS is not seen as causing any significant increase in risk. Page 73 Deviations Register RGS Number GERT8035 RGS Issue Number Two RGS Title Automatic Warning System (AWS) Certificate Number 13-004-DGN Title RGS Clause AWS caution acknowledgment period for 2.8.5.1 Class 350/4 operated by First Transpennine Express GIRT7016 Four Interface between Station Platforms, Track and Trains 13-002-DGN Streatham Common Station, Platform 2 (Up Slow line at Country end.) - platform width. GMRT2400 Four Engineering Design of On Track Machines 12-234-DGN Volumetric mixers proof and fatigue loading. 3.25.6 GERT8035 Two Automatic Warning System (AWS) 12-233-DGN Non-provision of AWS at HS1 to Network Rail Interface for Class 92 locomotives. Current Deviations Register as at 09 May 2016 7.2.1 (b), 7.4.1 2.2.2.1 Scope Nature and Degree The derogation being sought would apply to Experience has shown that the rate of Class 350 / 4 EMUs operated by First occurrence of late to cancel AWS/TPWS Transpennine Express. incidents increases when the AWS acknowledgement period is set at two seconds. The response of the brakes is almost instantaneous. It is now intended to construct the new Class 35/4 EMU with a maximum speed capability of 110 mph. These units will be operated by First Transpennine on the West Coast Mainline from Manchester, Liverpool to Glasgow / Edinburgh and return. The construction and introduction of this fleet will increase capacity on the afore-mentioned route, furthermore allowing FTPE to cascade Class 185s currently on this route to the Transpennine route, again dramatically enhancing capacity. Under the current requirements of clause 2. 8. 5. 2 (GE/RT8035), it would be required to introduce these units with a two second AWS audible warning cancellation timescale. This would introduce inconsistency with the reset timescales of the other FTPE traction fleets (others being 2. 7 seconds). This inconsistency will result in late AWS cancellations occurring on the Class 350/4 units in service. These late cancellations will introduce safety risk and Streatham Common Station: Station The Sussex Route Suburban Train platform - Platform 2 (Up Slow line at Lengthening project seeks to increase Country end). passenger capacity over selected routes by increasing train lengths from eight to ten cars. This requires platform extensions on the Slow Lines at a number of stations including Streatham Common. Streatham Common station comprises four platforms as follows: · Platform 1 - Down Slow. · Platforms 2/3 - Up Slow/Down Fast. · Platform 4 - Up Fast. The main station entrance is located on the Down side at approximately the middle of the station with inter platform access via a footbridge located towards the Country end. A footbridge (bridge No. 39 at 6m 50ch) provides a secondary access on the Up side onto Greyhound Lane. At the London end of the station, the junction with the Streatham Spurs is at the end of the Slow Lines platforms. At the Country end, the railway is crossed by an overbridge (bridge No. 40 at 6m 51ch - Greyhound Lane) which comprise two spans over the Slow and Fast Lines respectively with a tapered pier in the interval between the Up Slow and Down Fast lines. The interval between the Up Slow and Down Fast reduces beyond the overbridge. · Platform 2 is to be extended at Balfour Beatty's volumetric concrete mixer Balfour Beatty has installed a pair of as defined in the attached description. volumetric concrete mixers from a highway Vehicle number NLU93264. based vehicle onto a container flat railway wagon. The mixer modules do not meet the fatigue requirements of Rail Group Standard GM/RT2400 issue 4 section 3. 25. 6 (body mounted equipment). The manufacturer advises that if the side walls of the hoppers are strengthened to meet the standard, it will quickly lead to failure of the hopper side panels and frame. Additionally, the manufacturer advises that strengthening the side walls will reduce the effectiveness of the vibrators leading to an uneven mix quality. (See attached letter dated 14/05/2012 from NuRock limited). The subframe on which the hoppers are mounted similarly fails to meet requirements of the standard. Complying with the current RGS requirement would mean the mixer will not be suitable for purpose and Balfour Beatty would not be able to continue to use it. Risk Assessment/Safety Justification We know, from previous incident frequency, that the reduced acknowledgement period increases the likelihood of late AWS cancellations and subsequent emergency stops. RSSB research has shown that unnecessary AWS interventions reduce driver confidence in the system. Reducing the AWS acknowledgement time means less time for the driver to view and consider a fixed signal aspect, or speed sign, etc. , before acknowledging the warning. It is therefore desirable to afford the maximum time to the driver before cancelling the AWS enabling greater assimilation of the signal / sign being viewed. It should also be noted that, at many signals on the West Coast Main line, the prevailing distance from the AWS magnet to the fixed signal exceeds the 180 metres laid out in GE/RT8035. The impact of 2. 7 seconds, compared to the two seconds, is mitigated by the additional distance provided between these signals and the AWS equipment. Furthermore many signals and permanent speed restrictions on the routes these units will operate are fitted with TPWS to mitigate any driver error on approach. Any marginal increase in operational risk, should the AWS reset timescale be expanded, is mitigated by The overall objective of the Sussex Route Suburban Train Lengthening project is to increase passenger capacity and reduce overcrowding while maintaining or improving safety. At Streatham Common, the scheme will be developed to ensure that the track and platform design of the extended platform will be compliant with the requirements for stepping distances, passing and lateral clearances. The length of platform with limited width is at the country end of the station beyond the position of the main station entrance. AF042, AF046 and AF048 signals on Up and Down CTRL/NLL Connection. At the boundaries between CTRL managed infrastructure and Network Rail managed infrastructure in the St Pancras area, the distant signals are not provided with AWS since these signals are controlled by CTRL and within a CTRL designated AWS gap area. The non-provision of AWS was accepted by the CTRL SRP with the support of Eurostar and Southeastern. As a consequence, CTRL signals leading to the Network Rail interface on the CTRL/NLL Connection are not fitted with AWS and are therefore not compliant with GE/RT8035 clause 2. 2. 1 b). A current derogation covers this issue (07/099/DGN, Tracker No. 4733) that details the use of the KVB, as being mitigation for the non-provision of AWS on the distant signal. It is intended to run Class 92 freight trains, which are not fitted with this KVB system, along the CTRL/NLL Connection. To comply with the current derogation would require fitment of KVB to Class 92 or provide AWS in line with Clause 2. 2. 2. 1 b) on the distant signal approaching NL1117 that has previously been deemed to `introduce additional risks' and `complicate the changeover process'. The cost and complexity of fitting AWS far outweighs the potential safety benefits. Applicant Organisation First / Keolis Transpennine Express Certificate Issue Date 20/03/2013 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 21/02/2013 Deviation Status Current Network Rail 10/07/2013 N/A INS 08/05/2013 Current The impacts of allowing significant Balfour Beatty Rail R Plant Ltd 24/05/2013 permanent deformation of the aggregate hopper following critical acceleration levels determined in BS EN 12663-1: 2010 are crack formation and possible structural failure. The daily inspection regime which has been put in place will ensure earliest signs of failure are spotted and inspections will be carried out following any rough shunt. Restrictions preventing haulage in freight trains of the loaded vehicle will reduce the risk further. Consultation has taken place with the Network Rail client. GM/RT2400 issue 5 Draft 2i (August 2012) is expected to become mandatory and hence the alternative actions for the remaining components of the mixer module are in accordance with current industry best practice. N/A PLT 10/04/2013 Current Trains leaving the high speed line bound for Network Rail Network Rail infrastructure (via the NLL connection) will have the AWS/TPWS switched on and proved operational during the changeover between TVM430 cab signalling and lineside signalling. The speed of approach to each of the stop signals is low (25 mph maximum). Additionally, TPWS is provided at the stop signals and this has been designed to be effective mitigation at controlling overruns at NL1117. Lineside signage has been located at each interface to remind the driver he is entering an AWS fitted area and appropriate signs are provided for the traction configuration changeover at NL1117 on the NLL Connection. As a further current mitigation, all trains must stop at signal NL1117 on the NLL Connection, which is the first NR signal. While stopped at this signal, the driver must change the cab configuration from BR HSL to BR AC mode. This again switches on the AWS and TPWS and performs a self-test of both systems. The movement of trains onto the North London Line connection from CTRL is under the control of the North London Line signaller at Upminster Signalling Control Centre. Routes to the NLL connection are requested N/A CCS 24/01/2013 Current 02/05/2013 Page 74 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 12-231-DGN Title Hayes and Harlington, platforms 2 and 3 reduced platform width at new fenceline RGS Clause 6.2.2 Scope 144. 3 m of 1. 4 m high grey galvanised fencing to restrict access to the main line side of the island platform (platforms 2 and 3) at Hayes and Harlington; of this 144. 3 m, 9 m would be out of compliance and is what the derogation relates to. There will be five sliding gates within the fence to allow access and egress where necessary between the main lines and relief lines. These gates will be left open in the rare occasions where services need to call on the main line platforms at the station and will be left open for all of the time that the station is unmanned, such as overnight. GERT8073 Two Requirements for the Application of Standard Vehicle Gauges 12-230-DGN Ecofret `Triple set' wagons - calculation of side wind loads for W10 gauge. 1.2.7.6 and 2.1.2.5 This derogation covers the Ecofret wagons which are being introduced in service in Winter 2012. These wagons are configured as a `Triple set' consisting of three vehicles, two outer vehicles of car kind code FWA(A) outer and one 'inner vehicle of car kind code FWA(B), design code IFE966. This derogation covers only inner wagon as the outer wagons have already been granted a derogation number 12/088/DGN. The wagons are fitted with SCT bogies and are required to carry 9' 6'' high containers in the W10 gauge. GMRT2000 Three Engineering Acceptance of Rail Vehicles 12-229-DGN Derogation for a Steam Locomotive The clauses against which non-compliances Operation of the following preserved Steam are sought can be found in Appendix 2 of Locomotive on all lines, as agreed by the this document. NRAB and subsequently by the Licensed Operator. B1 Class locomotive built in 1947 for the LNER Railway by the North British Locomotive Co. Locomotive no. 61306 `Mayflower. TOPS No. 98506 Painted No. 61306 Class / Power Classification 5 Wheel Arrangement 4-6-0 Maximum Speed 75 mph. GMRT2000 Three Engineering Acceptance of Rail Vehicles 12-228-DGN Derogation for a Steam Locomotive GIRT7016 Four Interface between Station Platforms, Track and Trains 12-227-DGN Gravesend Station platforms 1, 2 (new platform) and 3 (existing platform 2). Current Deviations Register as at 09 May 2016 Nature and Degree A fence is planned to be added along the island platform at Hayes and Harlington which serves the Down Relief and Up Main Lines. The purpose of the fence is to achieve a greater degree of physical separation between the lightly used main line platform face and the highly used relief line platform, because Hayes and Harlington is a suicide "Hot Spot" which has seen nine fatalities take place since 2006. The majority of these fatalities involved a member of the public stepping from the island platform into the passage of a train on the adjacent main lines. Providing the fence will make it less easy for the public to access the main line side of the fence (which is generally not used) and, more importantly, make it visibly clearer, should someone access that side, so that preventative action can be taken. Details of the proposed fence are as follows: · 135. 3 m of which would be new fencing within compliance · 9 m of which would be new fencing which would be out of compliance. The fence would contain four 3 m sliding gates and one 4 m sliding gate to allow access and egress between the main and relief sides of the island platform where necessary. The line speed on the adjacent lines to the island platform at One of the requirements for the W10 gauge from GE/RT8073 appendix F shows a second dynamic gauge line that includes the effect of a wind loading. Although the W10 and W12 gauges are shown with an additional gauge for dynamic movements with wind, there is no information or other guidance given in either GE/RT8073 or GE/GN8573 on how to calculate the effect of wind on a vehicle, such that it can be compared against the relevant gauge line. Various sources of information were sought on this issue, but no one contacted at Network Rail, RSSB or other industry experts could shed light on the method to be used for this assessment. Therefore, a reasonable approach was derived as follows by calculating the moment on the vehicle due to the wind loading using the methodology from GM/RT2142 issue 3 Resistance of Railway Vehicles to Roll-Over in Gales. Calculations have been carried out (see report Ecofret Gauging with Wind Calculation - calculation 170902C02B) based on the approach set out in section 9 of this certificate - Proposed alternative actions, which show that the Ecofret FWA(B) (triple inner ) wagons with SCT bogies are within the gauge line for W10 gauge set out It would not be practical to revise the RGS to include steam locomotives, due to their wide diversity of design from modern traction units and the general scarcity of technical information now available to prove their compliance or otherwise. In a number of recent re-issues of RGS, specific exemptions for steam locomotives, shown in the previous issues, have been withdrawn, increasing the number of non-compliances for which derogation has now to be sought. Risk Assessment/Safety Justification Applicant Organisation Nine metres of fencing will be closer to the Network Rail platform edge than the standard dictates; however, the main line platforms are little used (normally used only during diversions as a result of engineering work on the Relief Lines) and the fence will restrict public access to this side of the platform when the main lines are not being used by stopping services. Access to the area where clearance is less than standard will therefore be minimal. The fenceline was agreed at a site visit on the 30th of August between Network Rail, Birse Rail, FGW and BTP attendees listed below: · Network Rail: Operations Risk Advisor, Works Delivery Manager, Performance Improvement Manager · British Transport Police: Crime Reduction and Architectural Liaison Officer · First Great Western: Head of Safety, Project Interface Manager, Station Manager. Approval for the fence-line has been gained by all parties present and, additionally, by two cross-industry groups: the Community Safety Partnership Group and Fatality Working Groups. Both the BTP and the Samaritans approve of the plans and similar fencing schemes have been successful in preventing fatalities at stations elsewhere in the country, such as those in place at Purley, It is suggested that the intention of GB Railfreight Ltd GE/RT8073 is to use a mean side wind speed with an appropriate gust speed. All other requirements to demonstrate compliance with W10, including requirements for static gauge and dynamic movements, will be complied with. As indicated in Appendix 7 of this document. The preserved steam locomotive is of a type that ran safely over the British railway infrastructure since its introduction in 1942 and continued until its withdrawal from revenue service. The locomotive was one of the first locomotives to operate on BR under the `return to steam' project in the 1970's and had a history of reliable service. The locomotive is intended for Heritage Operation only. In order to achieve compliance with RGS the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. The clauses against which non-compliances Operation of the following preserved Steam It would not be practical to revise the RGS to As indicated in Appendix 7 of this are sought can be found in Appendix 2 of Locomotive on all lines, as agreed by the include steam locomotives, due to their wide document. The preserved steam locomotive this document. NRAB and subsequently by the Licensed diversity of design from modern traction is of a type that ran safely over the British Operator. LMS Jubilee class steam units and the general scarcity of technical railway infrastructure since its introduction in locomotive No. 45596 `Bahamas'. TOPS information now available to prove their 1934 and continued until its withdrawal from No. 98696 Painted No. 45596 Class / Power compliance or otherwise. In a number of revenue service in 1966. After undergoing Classification 6P Wheel Arrangement 4-6-0 recent re-issues of RGS, specific overhaul the locomotive continued to Maximum Speed 75 mph. This section has exemptions for steam locomotives, shown in operate for on BR lines at speed of up to been revised to correct the TOPS number the previous issues, have been withdrawn, 75mph until 1994. The locomotive is from 98966 to 98696. increasing the number of non-compliances intended for Heritage Operation only. In for which derogation has now to be sought. order to achieve compliance with RGS the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. 7.2.1, 2.1.2, 6.3.1 and 11.1.3 Gravesend Station platforms 1, 2 (new platform) and 3 (existing platform 2) ELR HDR Mileage: 23m 51ch. This is an application for an amendment to the derogation obtained July 2011 for Gravesend Station No. 11/069/DGN, Tracker No 8775. This application reflects the complete derogation requested. This is an application for deviation from four clauses of Railway Group Standard GI/RT7016 for the proposed platform extensions at Gravesend Station: Clause 7. 2. 1 - Platform Width Clause 2. 1. 2 Platform Curvature Clause 6. 3. 1 - Buffer Stop Over Run Clause 11. 1. 3 - Platform Cross Falls Clause 7. 2. 1 - Platform Width (Platform 1 and 2 only): Approximately the last 40 m of the extension to Platforms 1 and 2 will taper from 2. 5 m to approximately 2. 1 m, and the short linking walkway between Platform 1 and the new Platform 2 will be 2. 0 m wide only. Platform 3 is compliant with respect to width, however. Clause 2. 1. 2 Platform Curvature (Platforms 1, 2 and 3) The new island platform and the extensions to the existing platforms will all have a radius in places of below 1,000 m, and as low as 270 m at the Country end for approximately 90 m of the platform length. Stepping distances are compliant throughout, however, for all classes of rolling stock operated by Southeastern over the route. Certificate Issue Date 22/03/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 06/03/2013 Deviation Status Current 05/03/2013 N/A INS 08/01/2013 Current West Coast Railway Company 06/02/2013 Ltd N/A RST 18/01/2013 Current West Coast Railway Company 18/06/2013 Ltd N/A Rolling Stock 28/06/2013 Current N/A INS 06/03/2013 Current Due to the physical constraints of the Network Rail station, it is impracticable to provide a compliant solution to GI/RT7016. A HAZOP risk assessment has been jointly undertaken by Network Rail and Southeastern to evaluate the possible risks associated with deviation from clauses 7. 2. 1, 2. 1. 2 and 11. 1. 3, and to consider possible additional operational controls to mitigate those risks. A separate technical buffer stop risk assessment (GC/RT5633) has been carried out by the designer in accordance with standards. The risk assessments took into account operator knowledge of passenger footfall and pedflow at each location. Network Rail and Southeastern have subsequently jointly concluded and agreed that the risks associated with the proposed deviations from GI/RT7016 are, in fact, tolerable and can be maintained ALARP by adopting and implementing the additional mitigating operational controls identified through the HAZOP risk assessment process. The output of the risk assessments is set out in Appendices C and D of the attached document. Southeastern, as Duty Holder, fully supports and endorses this application (see Appendix E of attached document). For the purposes of the 22/03/2013 Page 75 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 12-224-DGN Title Southall Platform 1, Down Main line reduced platform width. RGS Clause 6.5, 7.2 and 7.4. GMTT0088 One Permissible Track Forces for Railway Vehicles 12-222-DGN Reduction of Operational Diameter for wheels of 102 tonne GLW Wagons with TF25 Bogies. 5.2 c) GERT8082 One GSM-R Cab Mobile, Great Britain Open Interface Requirements (Rapid Response) 12-220-DGN HMI on/off control arrangement for a GSM-R 3.3.2.7 b) Transportable Radio. GERT8035 Two Automatic Warning System (AWS) 12-210-DGN SN199 AWS Position. 2.2.1.7 and 2.2.1.10 GKRT0063 One Approach Locking &amp; Train Operated Route Release 12-209-DGN West Hampstead Train Approaching Approach Locking Release with Conditional Double Red Appendix A - A4 Current Deviations Register as at 09 May 2016 Scope Great Western Main Line (MLN1) Southall Platform 1, Down Main line. Nature and Degree At Southall station, Platforms 1 and 2 serve the Main lines (linespeed 125 mph) while Platforms 3 and 4 serve the Reliefs (linespeed 80 mph Down Relief, 85 mph Up Relief). Platform 1 is on the north face of an island platform of solid infill construction with brick riser walls; Platform 1's wall is corbelled for the final 10 m of the London end of the Platform. The northern face is currently operational and serves the Down Main line. The southern face is no longer operational and is adjacent to the Southall Down Yard lines (linespeed 15 mph); there is no physical barrier to this platform face. The proposed Crossrail service will operate a 205 m-long ten-car service using Platforms 3 and 4 during normal operations (the Relief Lines) and Platforms 1 and 2 during perturbed situations when the Relief Lines are out of use. As part of the proposed works at Southall, it is planned to extend Platform 1 by 59. 175 m; this extension will be single face only (as shown in Drawing No WSN1B-ECV-DRG-AEA000201 A02). Since Platform 1 serves the Down Main line (linespeed 125 mph), the requirement for platform extensions is a width of 3000 mm, with any lighting columns being the same distance away from the 102 tonne GLW HAA and MJA wagons fitted This is an extension upon derogation with TF25 bogie operated by Freightliner Certificate Number 01/082/DGN (issued Ltd. 23/04/2001) allowing operation at 25. 4 tonne axle load on wheel diameters of between 840 mm and 790 mm giving a Q/D value of 0. 158 at the lower diameter, and an extension to the previously granted temporary non-compliance 09/127/TNC. It is proposed to reduce the permitted wheel diameters from 790 mm to 770 mm last turning and from 778 mm to 764 mm at scrapping, giving a Q/D value of 0. 165 at the scrapping diameter. Currently, Freightliner holds a derogation (Certificate Number 01/082/DGN issued 23/4/2001) for these vehicles to operate at full load on wheel diameters of between 840 mm and 790 mm (which would demonstrate noncompliance to clause 5. 2(c)). GSM-R Transportable Radios proposed to The impact of complying with current RGS be used by drivers, in cabs, on all of the GB requirements for the transportable radio Railway Network that has or will have GSM- would be: Complying with clause 3. 3. 2. 7 R coverage. part b would require a software change which would introduce a grossly disproportionate cost when considering the intent of the main clause 3. 3. 2. 7 is satisfied and the transportable is a different application to the fixed cab mobile installation that is implied by the standard. Risk Assessment/Safety Justification No action plan is being put in place since the alternatives are deemed as impracticable. There is no impact on existing services. Low. Platform 1 will not be used by a stopping Crossrail service unless the relief lines are out of service. As such, it is unlikely that trains will be using Platform 1 during peak hours. Applicant Organisation Network Rail Certificate Issue Date 31/01/2013 Certificate End Date N/A Lead SC Infrastructure Lead SC Approval Date 08/01/2013 Deviation Status Current 06/12/2012 N/A RST 26/07/2012 Current East Coast Main Line Company Ltd 19/12/2012 N/A CCS 06/12/2012 Current Network Rail 10/01/2013 N/A CCS 06/12/2012 Current Network Rail 10/01/2013 N/A CCS 06/12/2012 Current Investigations undertaken (Interfleet Report Freightliner Heavyhaul Ltd ITLR-T22695-002 refers) show that reducing the wheel diameter to this level will have minimal deviation from the allowances made in the previous derogation (Certificate Number 01/082/DGN issued on 23/4/2001) and further to show that such a derogation will have negligible effect on the rail contact stress. Previously, the derogation application was declined in favour of a temporary non-compliance by Infrastructure Standards Committee due to the lack of knowledge relating to Q/D ratios as an effective measure of contact stress. Freightliner understands that a research project is underway. With consideration of the foregoing, the level of impact / risk is considered to lie within acceptable bounds because: · The transportable has been developed as a temporary mitigation against fixed cab radio failure, not as a permanent solution. It is proposed that the transportable is used for as short amount of time as reasonably possible to minimise against the loss of DSD, PA and OTMR connectivity. · The Transportable achieves the intent of clause 3. 3. 2. 7, although it has a different configuration to the two options presented in clauses 3. 3. 2. 7 a) and 3. 3. 2. 7 b). · This specific requirement ceases to be a mandatory in the proposed new Train Voice Radio Standard. In this respect, the transportable is compliant with the draft Train Voice Radio Standard GK/RT0094 Issue 1 that is intended to replace GE/RT8082 in 2013. SN199 is on Down Relief Line located 4 To provide a compliant solution would Impact of alternative action meets all of the 3/4m + 6ch on MLN1. The proposed AWSs require SN199 not to be repositioned at this requirements of 2. 2. 1. 4, 2. 2. 1. 5, 2. 2. 1. 6 will be on Down Relief and Down Goods stage, and proposed signal spacing would and 2. 2. 4, but does increase the time and lines - (see attached plan extract). not be achievable due to signal spacing distance to greater than that defined in 2. 2. constraints, or the temporary junction 1. 7. It is recognised that, due to train positioned towards London, which would drivers using signal AWS position to assist mean the required standage would not with stopping at signals, the distance is achieved on the Goods Lines. Both options important and, if the magnet cannot be would have significant cost in placed at the standard distance, a longer implementation when compared to a minor distance is generally better than a shorter increase in AWS distance. one. When passing a yellow aspect, drivers are told to slow to a speed appropriate to stop from the AWS when the AWS sounds the train is then braked to a stand. This is particularly important at night where the distance to the signal is very difficult to judge. For passenger trains, the yellow to AWS speed is about 25 mph and for freights is 5 or 10 mph. Due to the S & C, a compliant solution is not possible, the above is the reason for selecting a position at a greater distance than the standard requirement rather than one that is less than the standard (147 m as shown on the scheme plan). This position has been endorsed by SSC as per 2. 2. 1. 11 as the most suitable position. Eight pairs of signals affected in the West To provide a compliant solution would Impact of the provision of a conditional Hampstead PSB control area as part of the require extending the train approaching look- double red, means that the distant aspects Midland Mainline Linespeed Improvement back for an additional signal section due the then moving one signal back. See Project. Look back arrangements apply to requirement for provision of Conditional consultation report for full details. However, the inner signal approach locking release Double Red (CDR) sequence. The CDR is the outer signal has an aspect only level of only. · Inner WH61 outer WH59 (Down Fast required as part of the project for SPAD control (designed to extend the influence of approach to Radlett Junction) · Inner WH54 mitigation due to the increase line speeds the TPWS) and that signal does not require outer WH56 (Up Fast approach to Radlett proposed. Provision of this additional to any additional interlocking provision. Junction) · Inner WH84 outer WH86 (Up section, in most cases at West Hampsted When the junction is not available or Fast approach to Harpenden Junction) · PSB area, would involve significant replaced, the outer signal will be held at red Inner WH112 outer WH114 (Up Fast alterations to existing interlocking and only until the approaching train has passed a approach to Leagrave Junction) · Inner lineside infrastructure due to current TPWS (OSS) at a position on the approach WH134 outer WH136 (Up Fast approach to interlocking boundaries. Such changes to the outer signal. Under these Flitwick Junction) · Inner WH143 outer would be substantial and disproportionate to circumstances, the outer signal will always WH141 (Down Fast approach to Bedford the benefits offered - see attached clear (therefore effectively acting as a more South Junction) · Inner WH156 outer consultation report. robust inner junction signal). Because the WH158 (Up Fast approach to Bedford South outer signal will always clear on the Junction) · Inner WH162 outer WH164 approach of the train, the stopping position (Bedford North Junction). of the train is therefore at the same place as it would be prior to the provision of CDR controls. If the signal was put back, while a driver may be `surprised' by a reversion, no additional hazard arises because the outer signal will always clear as the train approaches, permitting the train to proceed to the same position at which the driver was planning to stop anyway. The release of locking on the inner signal following a signal reversion will be mitigated by the TPWS Page 76 Deviations Register RGS Number GMRT2142 RGS Issue Number Three RGS Title Certificate Number Resistance of Railway Vehicles to Roll-Over 12-202-DGN in Gales Title RGS Clause Derogation against GM/RT2142 Issue 3 2.1.1.1 b) Resistance of Railway Vehicles to Roll-Over in Gales. Scope · Wagon Type Code: Tafoos · Description: 102t Biomass Hopper Wagons for UK Use Only · Vehicle Number Range: 83700698001-0 to 83700698501-9. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-201-DGN Stalybridge Station Proposed Platforms 4 and 5 - reduced platform width. 7.2.1 (b), 7.3.1 (b), 7.4.1 Stalybridge Station Proposed Platforms 4 and 5. ELR MVL2 7M1527yds to MVL2 1557yds Down Huddersfield Line. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-200-DGN Brighton Station - Overrun risk zone. 6.3.1.1 As shown on drawing 5374/CC/02/01 Rev ORR. Excess Fare and Information Booth: Side in Area C "Low" risk zone Retail Unit 12: Side in Area C "Low" risk zone. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-198-DGN Southall station fencing between platforms 2/3 - reduced platform width. 6.2.2 The scope of the deviation relates to 123. 4 m of 1. 4 m high grey galvanised fencing to restrict access to the main line side of the island platform (platforms 2 and 3) at Southall; of this 123. 4 m, 10. 1 m would be out of compliance. There will be five sliding gates within the fence to allow access and egress where necessary between the main lines and relief lines. These gates will be left open in the rare occasions where services need to call on the main line platforms at the station and will be left open for all of the time that the station is unmanned, such as overnight. GCRT5112 Two Rail Traffic Loading Requirements for the Design of Railway Structures 12-195-DGN Limehouse Station Platform 2 - loading on lift shaft. 7.1.2 and 7.1.3 Current Deviations Register as at 09 May 2016 Nature and Degree The impact of complying with Issue 3 of GM/RT2142 would be a combination of a reduction in the operating speed below 75 mph (tare) and an increase in tare mass. The ability for these vehicles to run at 75 mph is a significant advantage to the owner / operator when securing paths on the network. Equally, the client requires the wagon to carry the maximum possible payload, and this is achieved by reducing the tare mass as much as possible (estimated at 29. 25t). Increasing the tare mass to comply with this standard would significantly compromise the payload capacity of the wagon. Alternatively, to comply with the standard, the side area of the vehicle would need to be reduced, as this is the major factor in calculation. This could only be achieved via major redesign of the vehicle structure leading to a reduction of the carrying capacity of the vehicle. The vehicle would then be uneconomic to operate. Stalybridge Station Platforms 4 and 5. A new bay platform, Platform 5, is to be constructed adjacent to existing Platform 1 (which will be renumbered as Platform 4). The proposed permanent way alignments at the Ashton end of the station restrict the usable width of these new arrangements: on the shared double face Platform 4 and 5 to 3915 mm tapering from 4000 mm over a 2160 mm distance (at the end of Platform 4); on single face Platform 5 to 2050 mm tapering from 2500 mm over a 9440 mm distance at the end of Platform 5. The proposed platform layout is shown on drawing No. 664687-CIV-DRG-0001-C01A1 'Stalybridge Station Platform Extension General Arrangement'. An overview of the area can be seen in drawing 'SP&amp;C_LNW_002_Stalybridge version 5. 0. pdf'. The proposed commissioning date is November 2012. Excess Fare and Information Booth would be limited in size and configuration and could not provide all welfare and security requirements for staff working in the booth, preventing Gateline reconfiguration proceeding. Passenger facilities worsen and business case for project fails due to removal of Retail Unit 12. A fence is planned to be added along the island platform at Southall which serves the Down Relief and Up Main Lines. The purpose of the fence is to achieve a greater degree of physical separation between the lightly used main line platform face and the highly used relief line platform because Southall is a suicide "Hot Spot". Southall station has witnessed eight fatalities in the past five years, six of which have occurred since the start of 2011. The majority of these fatalities involved a member of the public stepping from the island platform into the passage of a train on the adjacent Up Main line. Providing the fence will make it less easy for the public to access the main line side of the fence (which is generally not used) and, more importantly, make it visibly clearer should someone access that side so that preventative action can be taken. Details of the proposed fence are as follows: · 92 m of which would be removing an existing non-compliant fence and replacing it with a compliant fence · 21. 3 m of which would be new fencing within compliance · 10. 1 m of which would be new fencing which would be out of compliance. The fence will contain four 3 m sliding gates and one 4 m sliding gate to allow access and Limehouse Station Platform 2 - proposed lift The proposed lift shaft at Limehouse Station shaft. on platform 2 will be located at a minimum distance of 3. 1 m from the nearest running rail. It is not proposed to design the lift shaft against train impact loading due to the insufficient space to cater for the additional member sizes. The existing platform consists of a timber beam and GRP slab construction, supported on steel I-beams that span between the brick walls of the station building. Substantial increase in member sizes will either mean that the lift size will be reduced making the lift noncompliant (it has already been value engineered for the smallest practical compliant solution) or the shaft size is increased, further reducing the platform edge clearance from the proposed structure (which is already the subject of derogation Ref. 12/194/DGN - Tracker No. 11528), any increase will affect passenger flows and potentially increase the safety risk to passengers using this platform. Risk Assessment/Safety Justification Applicant Organisation The proposed action allows WH Davis Ltd to WH Davis Limited deliver the project as required by the customer. We do not believe there is any additional safety risk to the railway with the introduction of these vehicles as there are a significant number of vehicles that fail the current requirements of this standard already in service with proven service history such as the HYA coal hoppers. The alternative action is included in RSSB Research Project T961 as a recommended change to the standard. Certificate Issue Date 21/12/2012 Certificate End Date N/A Lead SC RST Lead SC Approval Date 30/11/2012 Deviation Status Current Low severity. The minimum width of the Network Rail platforms is sufficient to accommodate the maximum anticipated passenger usage and the possibility of allowing for the detraining of passengers. The key factors considered were: Safe accommodation of passenger access/egress (including emergency evacuation), circulation, waiting and boarding/alighting in respect to the potential hazard from the platform edge or passing trains. Safe accommodation of operational activity, e. g. station management and maintenance. Safe arrangement and positioning of structures, platform furniture and equipment. The non-compliant section of Platform 4 lies beyond the extent of a ninecar train positioned at the nine-car stop board and so is unlikely to be routinely used by passengers. Most of the non-compliant section of Platform 5 lies beyond the extent of the trains that will use the bay platform and stop at the normal 2 m stopping distance from the buffer stop. The proposed non-compliances affect short sections of platform at the remote end from the station entrance. The maximum number of passengers using the section of platforms is anticipated to be small and so the risks to passenger access/egress, circulation and The existing layout is shown on drawing Southern Railway 5374/SK/57. The risk weighting factor (calculated using the methodology in Appendix A of GI/GN7616 Guidance on Station Platform Geometry Issue 1, December 2010) is 27. 87. The proposed layout is shown on drawing 5374/CC/02/01 Rev ORR. The risk weighting factor (calculated using the methodology in Appendix A of GI/GN7616 Guidance on Station Platform Geometry Issue 1, December 2010) is 25. 54. In addition, a road-by-road analysis of risk has also been carried out. Roads 3 and 6 are unaffected by the proposals. All possible risks to Roads 4 and 5 (I. e. not including the supporting columns for the roof) have been eliminated by the proposals. Roads 2 and 7 have a marginal increase in risk where the building encroach on the "Low" risk zone. 08/03/2013 N/A INS 14/11/2012 Current 11/01/2013 N/A INS 14/11/2012 Current Not applicable as the requirements cannot Network Rail be followed due to the location of the staircase at the station as outlined. 10. 1 m of fencing will be closer to the platform edge than the standard dictates; however the main line platforms are little used (normally used only during diversions as a result of engineering work on the Relief Lines) and the fence will restrict public access to this side of the platform when the main lines are not being used by stopping services. Access to the area where clearance is less than standard will therefore be minimal. 92 m of existing fencing on the platform would be brought into compliance as a result of the works. The fenceline has been agreed at a site visit between Network Rail, Birse Rail, FGW and BTP attendees listed below: · Network Rail: Operations Risk Advisor, Works Delivery Manager, Performance Improvement Manager · BTP: Crime Reduction and Architectural Liaison Officer · First Great Western: Head of Safety, Project Interface Manager, Station Manager · Birse Rail: Delivering the project. Approval for the fence-line has been gained by all parties present and additionally by two crossindustry groups, the Community Safety Partnership Group and Fatality Working Low Severity: The diagram on the Network Rail derogation report attached (figure 3,2) shows that the mitigating factors for not designing the lift shaft for collision loading are: Curved permanent way (tracks) away from the proposed lift shaft Slow line speed (20 mph) at this station Existing infrastructure would fail first (e. g. platform) The lift shaft size would become too large to fit into the proposed space at platform level. The track curves away from the lift so the likelihood of derailment towards the proposed lift shaft is minimal; the line speed is also very slow at this station, so it is highly unlikely that a derailed train would ever reach the lift shaft. Further information is contained within the derogation report (attached to this submission). 12/12/2012 N/A INS 14/11/2012 Current 12/12/2012 N/A INS 14/11/2012 Current Page 77 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 12-194-DGN Title Limehouse Station Platform 2 - platform width. RGS Clause 6.2.2 b) Scope Limehouse Station Platform 2 - platform width at proposed lift shaft. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-193-DGN Kew Bridge Station Platform 2. 7.2.1b Kew Bridge Station Platform 2. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-190-DGN Ealing Broadway Station Platform 4, Up Relief line - platform width. 6.2.2 GIRT7016 Four Interface between Station Platforms, Track and Trains 12-189-DGN Conon Bridge: length of station platform 5.1.1 GKRT0192 One Level Crossing Interface Requirements 12-185-DGN Signals PT249 and PT449 Distance to Llanelli East Level Crossing. 2.1.1.3 Great Western Main Line (MLN1) - Ealing It is proposed to construct a new (escape) Broadway Station Platform 4, Up Relief line. footbridge at Ealing Broadway station. The required minimum clearance of this footbridge to the edge of the platforms is 2. 5 m (line speed up to 100 mph). Due to space constraints at Platform 4, the maximum available distance between the new footbridge and the edge of the Platform (to the Up Relief Line) is 2. 1 m. The length of this substandard width is about 10 m and is located some 18 m from the eastern end of Platform 4 (around 150 m from the passenger entrance to the platform). Pedestrian flow analysis did not identify any congestion issues at this part of the platform with the anticipated passenger numbers (Year 2026 + 28% growth); furthermore, no safety issues were identified regarding the evacuation of passengers in the event of a fire. This reduced platform width only affects the first car of a ten-car (Crossrail) train. Conon Bridge, between Dingwall and The Highland Council initially proposed a Inverness: length of station platform. new station between Muir of Ord and Dingwall on the Wick line, on behalf of the Council, Halcrow carried out an appraisal in 2006 which demonstrated strong economic benefits and Scott Wilson Railways Ltd carried out a feasibility study which determined that after considering a number of alternative locations, the new station should be built on the site of the old Conon Bridge Station (approximately 16m 660y). In conjunction with the Highlands and Islands Strategic Transport Partnership (HITRANS), The Highland Council promoted and funded GRIP 1-4, work subsequently deferred due to financial constraints. Following the award of development funding from Scottish Government in 2011 to the now principal promoter, HITRANS engaged Network Rail to develop the project to GRIP Stage 5, the intention being that HITRANS would then seek funding for implementation in future years. The requirement to accelerate delivery of the project has subsequently been identified in order to assist in mitigating the impact to the travelling public of significantly disruptive road closures of the A9 (Kessock Road Bridge refurbishment works where due to road re-surfacing there Signals PT249 and PT449 protecting Llanelli The Llanelli project will involve the renewal East Crossing situated at 225 miles 14 of Llanelli East MCB-CCTV and Llanelli chain, Pilning to Fishguard Harbour (ELR West MCB to MCB-OD and the control of SWM2). these crossing transferred from Llanelli West Ground Frame to Port Talbot Power Signal Box. Llanelli East level crossing is to be converted to MCB-OD operation. The level crossing protection signals are positioned as shown below: · PT249 Up main is positioned 22 metres from Llanelli East level Crossing. Should PT249 be repositioned 3 metres further from Llanelli East crossing, the signal would not provide the required standage for the train service using Llanelli station, due to train standing on Llanelli West crossing. · PT449 Dn Main, wrong direction move from the Dn main platform to the Up main is 13 metres from Llanelli East Level Crossing. Should PT449 be repositioned 12 metres further from Llanelli East crossing, the signal would not provide the required standage for the train service using Llanelli station for the reversing move over 960 points. Due to the close proximity of Llanelli station, these signals can't be moved due to the train service and the type of train stock being used. Current Deviations Register as at 09 May 2016 Nature and Degree The proposed lift shaft on Platform 2 at Limehouse Station will be located a minimum distance of 2180 mm from the platform edge. (See figure 2. 1 of attached derogation report and details contained within it). The platform will not be closed during construction. Why meeting the standard is not practicable: There is no scope to locate the proposed lift to Platform 2 outside of the current station boundary due to the adjacent road network, railway over bridge and high concentration of existing infrastructure. There is also little opportunity to reconfigure the station concourse internally without significant redevelopment and investment. The existing layout of the station concourse, coupled with the extremely tight site constraints, has therefore dictated the proposed layout of the lift shaft on Platform 2. This prescribed location has not only resulted in a bespoke lift shaft but reduced clearances to the existing platform edge to below the required levels set out in Railway Group Standards. It should be noted that there is currently a high concentration of existing station infrastructure on Platform 2 that does not fall in line with relevant design standards. The current line speeds at the station are very Low risk. The country end of the platform (where the extension is located) is lightly used as passengers tend to join or alight nearer the exit which is at the London end. The waiting shelter and customer information screen are also near the entrance. The extension only takes two cars of a train set hence footfall will be low in the area of non-compliance. The reduced width is only 100 mm less than the minimum width of 2500mm and is marginal. Risk Assessment/Safety Justification Applicant Organisation Low Severity, given that the existing bridge Network Rail parapet (2. 14 m from the platform edge) and canopy columns (1. 83 m from the platform edge) are currently worse than the proposed lift shaft edge (2. 18 m) from the platform edge. The proposed lift shaft does not, as a consequence of its position, move passengers flows any further towards the platform edge than existing obstructions such as the bridge parapet and existing platform columns. The waiting area will be relocated to the London end of the station via a new purpose built waiting shelter to the rear of the platform. The proposed location has been agreed by all stakeholders as the only solution that will fill the project remit (lift to Platform 2). The location is supported by the Train Operator Company (TOC) c2c and Network Rail. A HAZOP study was conducted with the TOC and Network Rail Safety Staff and is attached as a supporting document. Certificate Issue Date 12/12/2012 Certificate End Date N/A Lead SC INS Lead SC Approval Date 14/11/2012 Deviation Status Current South West Trains have confirmed their acceptance. Network Rail 13/06/2014 N/A INS 14/11/2012 Current Due to space constraints imposed by the Network Rail location of existing infrastructure, it would not be reasonably practicable to provide a compliant solution. Low severity. Restrictions to passenger safety and movement are minimal - the footbridge is at the far end of the platform from the entrance, and pedestrian flow modelling demonstrates that there will be adequate circulation available between the stairs and the platform edge (taking account of the future growth in usage). During construction, this footbridge will be used for short periods when the main footbridge is unavailable; the main flow of passengers will be along Platform 4 and straight onto the bridge via the stairs, and so have little impact on the area of limited clearance, in front of the proposed stairs. 12/12/2012 N/A INS 14/11/2012 Current First ScotRail already have operational Network Rail procedures in place for a 15 m platform at Beauly Station and have operated this for 10 years without incident, and the conductors and drivers are all trained and briefed accordingly and are very familiar with the operation. Projected passenger numbers for Conan Bridge are in the region of 25% less than at Beauly. The risk assessment information also shows the severity of derogation from standard is low and supports this application. As defined in section 4. Risk Assessments provided. 06/11/2012 N/A INS 12/09/2012 Current All practical mitigations have been Network Rail considered and applied to the scheme plan. Due PT249 signal provision of SPAD mitigation any impacts of the reduction in distance from the crossing are minor. The SPAD mitigation proposed would provide adequate warning time (5s of flashing RTLs) to vehicular traffic for train approaching PT249 and trains starting away from Llanelli will be mitigated by good sighting of the signal and view of the crossing. Due to the low speed of proposed use of the PT449 signal, any increase in distance will have minor reduction in crossing risk. 27/11/2012 N/A CCS 08/11/2012 Current Page 78 Deviations Register RGS Number GCRT5021 RGS Issue Number Five RGS Title Track System Requirements Certificate Number 12-184-DGN Title RGS Clause Use of Turn-back facility at Horsforth - Track 2.8.2 gradient. Scope Use of turn-back facility at Horsforth. Nature and Degree The scheme involves the construction of a turn-back facility at Horsforth. The turn-back facility is to be positioned between Horsforth station and Bramhope Tunnel on the route to Harrogate and is mainly to cater for a fourcar 15X train or equivalent. This forms part of a larger Department for Transport (DfT) requirement to increase the passenger service between Horsforth and Leeds with an aim to reduce congestion of the train service. The turn-back facility will also allow access for plant from the stabling point to the running line. The track gradient is 1 in 80 rising toward Harrogate, steeper than the required 1 in 500 where trains are planned to turn back in the facility. The exceptions stated concerning non-use by On-Track Plant (OTP) and On-Track Machines (OTMs) have now been reviewed, and this derogation extends the deviation Ref. 09/189/DGN (Tracker No. 6720) to permit use by these machines. GKRT0064 One Provision of Overlaps, Flank Protection and Trapping 12-183-DGN Signal BH58 Overlap Length. 4.2.1 BH58 Signal, Up Slow Line (LEC4) protecting Basford Hall Junction. The application of this derogation is against an existing deficiency which has been submitted as a result of a change in speed. This deviation is for the future linespeed increase from 75 mph to 100 mph. This deviation is also to be extended to cater for the future linespeed increase from 75 mph to 100 mph. Compliance would require relocation of the Insulated Rail Joints and associated track circuit alterations at a cost of approximately œ40k, with very little overall safety improvement. No work is currently planned in the area as part of linespeed improvements. GKRT0192 One Level Crossing Interface Requirements 12-182-DGN Signal SC8464 Distance to Nantwich Crossing 2.1.1.3 Signal SC8464, on the Shrewsbury to Crewe Modular Signalling Pilot Scheme, protecting Nantwich MCB-OD Up Approach (wrong direction). GK/RT0192 requires SC8464 at the end of the Down platform at Nantwich to be 25 m from the crossing. The site arrangements at Nantwich do not allow the 25 m distance to be easily achieved, as the end of the platform is only 18 m away from the crossing and is in close proximity to the passenger access/egress to the platform. Options for compliance would involve non-standard signal structures which would, despite possible use of lightweight structures and thinking, still be up to œ20k. Any option that involved platform extension would cost œ10k per metre. A review of the cost and benefits of compliance has been undertaken as per the attached Safety Justification document and comparison to other sites. This has shown that the cost benefit of compliance to GK/RT0192 is only a few hundred pounds. GKRT0045 Two Lineside Signals, Indicators and Layout of Signals 12-181-DGN Signal WS6299 exceeding 800m for signalling of a divergence. 3.1.1.4 Junction Signal WS6299 and associated splitting banner signal protecting Trent Valley No. 1 Junction, provides route information to either the Down Slow or the New Down Stafford Goods Loop, exceeding the 800 m rule for signalling of a divergence. GKRT0063 One Approach Locking &amp; Train Operated Route Release 12-180-DGN Cardiff Area TORR Release Conditions. 5.3 Cardiff Area Signalling Renewal (CASR) project area. Routes without required number of track sections. Current Deviations Register as at 09 May 2016 Risk Assessment/Safety Justification Mitigation proposed involves the use of classes of rolling stock that have design features and braking systems capable of remaining stationary on any gradient up to 1: 30 that make their use whilst braked within the facility operationally safe. Operational restrictions will be put in place to ensure that the driver applies the brake and removes the key before transferring to the opposite end of the train. The rolling stock proposed automatically applies the parking brake when the driver removes the key. The Train Operating Company (TOC) will put further operational mitigation measures in place for the operation of their rolling stock (supporting document attached). A Sectional Appendix Instruction will ensure that only agreed rolling stock with an airbraked system capable of holding on a 1: 30 gradient will use the turn-back facility and use of the facility for stabling will be strictly prohibited. The driver will stay with the train at all times and only leave the train whilst changing cabs, thus limiting the risk of brake failure over time. On-Track Plant will not be stabled on the turn back facility. The siding will be used as a headshunt only for access to/from the stabling point and the running line. This is an existing deficiency for the current permissible linespeed of 75 mph. The safe overrun distance (SOD) is 260 m, which negates the overlap being at 177. 4 m as a train is more likely to be using the junction that standing ahead of BH58 under the current service pattern. BH58 signal has TPWS+ and was deemed ALARP for existing and higher line speed by DA committee upon review of this signal at DA workshop held for the proposed line speed increase. No further mitigation measures were deemed necessary. The signal has good sighting, with available reading distance in excess of 500 m with a required reading distance of 357 m at the proposed higher linespeed. Nantwich Down Platform signal SC 8464 is a Wrong Direction signal for Up moves over the crossing, there is no main signalled routes that approach to the Down Platform from the Up direction, all approaches are via shunt signal. Positioning the signal and associated modular housing off of the platform retains the current platform length and passenger access. Due to the low proposed use of the signal, the provision of SPAD mitigation for train approaching SC8464 any impacts of the reduction in distance from the crossing are minor. Further justification and review of position is contained in the attached Qualitative Safety Justification and Cost Benefit Analysis. In summary, the SPAD mitigation proposed would provide adequate warning time (5s of flashing RTLs) to vehicular traffic for train approaching SC8464 and trains starting away from Natwich will be mitigated by good sighting of the signal and view of the crossing. Applicant Organisation Network Rail Certificate Issue Date 11/11/2014 Certificate End Date N/A Lead SC INS Lead SC Approval Date 14/11/2012 Deviation Status Current Network Rail 27/11/2012 N/A CCS 08/11/2012 Current Network Rail 27/11/2012 N/A CCS 08/11/2012 Current The factors preventing WS6299 from being positioned closer to the new divergence are: · Rickerscote OLE Neutral section exclusion zone is between 840 m and 500 m from the new divergence · Achieving compliant signal sighting. 5 seconds uninterrupted cannot be achieved between 500 m and 320 m from the new divergence (320 m is the distance from the new divergence to a 225 m overlap length clear of the RBS3 clearance point). To achieve compliance with the 800 m rule, the signal would either need to be positioned in the Neutral section (as it is today) or ahead of the neutral section, where compliant sighting cannot be achieved and the overrun risks, with the proximity of Trent Valley No. 1 Jcn, would be intolerably high. There is the potential for a driver to forget Network Rail that they have been signalled for the 30 mph Goods Loop and not the 60 mph Down Slow. To mitigate these concerns, the project is reinforcing the positive indication of the route to the Goods Loop with an MAYFA approach and a splitting banner on the junction signal. Additional benefits of moving the signal further away from Trent Valley No. 1 Junction are: · By also adjusting the position of WS6297 (the signal approaching WS6299), signal spacing can be regularised. · The TPWS protection is effective for all line users with respect to protecting a SPAD at WS6299 from reaching the converging conflict at Trent Valley No. 1 Jcn. · The signal, and its associated splitting banners can be better sighted at the new proposed position. 27/11/2012 N/A CCS 08/11/2012 Current There are a number of routes on the project where the paucity of train detection sections would require additional detection elements solely for the purpose of TORR. Provision of these sections would incur additional costs for provision and ongoing maintenance. Also, additional track sections would increase the likely hood of any secondary risks that may occur in the event of failure of the additional equipment. It is understood that the main purpose of the Network Rail additional sequence was to address risks associated with potential common mode failures on track circuits sharing IRJ's. The CASR project is using Frauscher FAdC axle counter train detection that significantly reduces the risk of spurious operation that might satisfy the TISP and TORR conditions. See also attached HAZID which was conducted by the modular project. This has been reviewed and remains valid for the CASR application because the traffic levels were not deemed a mitigation. 27/11/2012 N/A CCS 08/11/2012 Current Page 79 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 12-178-DGN Title Alton and Aldershot stations - reduced platform widths at liftshafts. RGS Clause 6.2.1 and 6.2.2 b) Scope The deviation relates to the need to locally reduce the available platform width to less than 2,500 mm, measured from the platform edge to the face of the liftshaft cladding. This will extend along the platform for the length of the lift, approximately 3,000 mm. The design currently sits, with dimensions now finalised, at GRIP4-5. Specifically, this relates to the following platform locations. · Aldershot Station - island platform 2/3 (see drawing for outline design dimensions). · Alton Station - island platforms 2 (SSWT) and 3 ( Watercress Line ) (see drawing for outline design dimensions). Nature and Degree In both cases, the existing island platform widths are insufficient to accommodate the necessary sixteen person lift car and supporting structure without building into the distance of between 2,500 mm and 1,950 mm. The locations chosen are best placed for sighting and all other issues. Further investigation at commencement of outline design has shown that the originally assumed locations initially positioned the liftshaft at the same location as potential disabled train access/exit doors on the train, thus restricting the use of mobile PTI ramps. The relocation now avoids this conflict. Please refer to location plans and site plans given as Attachment 1 to this Application. GERT8035 Two Automatic Warning System (AWS) 12-177-DGN Separate Isolation of AWS for Plasser &amp; Theurer Tamping Machine. 2.8.5.2 Plasser &amp; Theurer 09-4x4/4S Tamping Machine Number 99 70 9128 001-3. TPWS equipment that is validated as compliant with the requirements of GE/RT8030 Issue 4 is not available. The two suppliers of TPWS equipment are developing and testing suitable equipment but it will not be available during the construction and delivery programme for this machine. The functionality required to achieve compliance with the requirements of clause 2. 6. 8. 2 of GE/RT8035 Issue 2 forms part of the new generation TPWS equipment and is not currently available. The impact of complying with the current RGS requirement would be to significantly delay the project to introduce this type of machine to the UK. GERT8030 Four Requirements for the Train Protection and Warning System (TPWS) 12-176-DGN TPWS Enhanced Functionality for Plasser &amp; Theurer Tamping Machine. Appendix F Appendix H Plasser &amp; Theurer 09-4x4/4S Tamping Machine Number 99 70 9128 001-3. GMRT2466 Three Railway Wheelsets 12-173-DGN Supply of axles for 20 new Class 350 2.1.1, 2.8.1, 3.3.1.1-3 and 3.3.2.2 Electric Multiple Units (EMU) to a preexisting design in accordance with Siemens Strategy for the Introduction of Additional Vehicles to an Existing Design, 27/01/2012 Issue 1. 128 axles to be supplied for fitment to: · 10 x Class 350/3 for First Transpennine Express and · 10 x Class 350/4 London Midland. GMRT2130 Three Vehicle Fire, Safety and Evacuation 12-172-DGN Fire Performance and Emergency Lighting 10 x Class 350/3 for First Transpennine Express and 10 x Class 350/4 London Midland. Current Deviations Register as at 09 May 2016 2.2.3, 2.2.4 b) and Part 4 Risk Assessment/Safety Justification Drawings prepared to GRIP stage 4 are attached in Attachment 1 to the rear of this Application. No practical alternatives to this Application for Deviation have been identified, to provide a DDA compliant lift facility. The railway authorities are charged with taking all reasonable measures to provide a DDA accessible railway and obviously maintaining health and safety standards. The existing island platforms on both stations were not originally designed to accommodate a liftshaft, and the local reduction in width, to accommodate this, is therefore somewhat inevitable. All other impacts, I. e. signal sighting, have been considered as part of the design process, but the platform width reduction, to no less than 1,950 mm, cannot be designed out without major station and track redesign. Of note, at both stations, permissible train speeds are significantly less than 100 mph. At Alton, trains are approaching a buffer stop at the country end of the platform (SSWT) and London end (Watercress Line). With reference to the DTP Accessible Train Station Design For Disabled People - A Code of Practice - v3, section W2, Platforms - platform design: · W2. 2 - the minimum width of platform without obstacles shall be, The TPWS/AWS installed on this machine would have the same functionality as on all self-propelled Plasser &amp; Theurer machines supplied to the UK since October 2004. The annual mileages covered by OnTrack Machines when transiting is significantly lower than for locomotives and multiple units. Almost all transit moves are undertaken outside peak traffic hours. The reliability of the current design of equipment is extremely good and the lack of ability to separately isolate AWS is not seen as causing any significant increase in risk. Applicant Organisation Stagecoach South Western Trains Limited Certificate Issue Date 23/01/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 14/11/2012 Deviation Status Current Plasser UK Ltd 30/11/2012 N/A CCS 08/11/2012 Current TPWS equipment that is validated as compliant with the requirements of GE/RT8030 Issue 4 is not available. The two suppliers of TPWS equipment are developing and testing suitable equipment but it will not be available during the construction and delivery programme for this machine. The impact of complying with the current RGS requirement would be to significantly delay the project to introduce this type of machine to the UK. The TPWS installed on this machine would Plasser UK Ltd have the same functionality as on all selfpropelled Plasser &amp; Theurer machines supplied to the UK since October 2004. The annual mileages covered by On-Track Machines when transiting is significantly lower than for locomotives and multiple units. Almost all transit moves are undertaken outside peak traffic hours. The maximum speed of this machine (60 mile/h) is lower than all locomotives and multiple units with the exception of heavy haul freight locomotives. As a result, the risk posed by the "reset and proceed" phenomenon is lower for On-Track Machines. This machine will pose no greater risk than that for all Plasser &amp; Theurer machines introduced into service in the UK since October 2004. 30/11/2012 N/A CCS 08/11/2012 Current Siemens are in the process of supplying of twenty new four-car EMUs that, with the exception of certain internal layout differences and other minor changes, will be identical to the existing Class 350/2 (`Desiro') EMUs presently operated by London Midland. A strategy outlining approach to be taken in the assessment of the new units, including the methodology and actions required to meet the approvals requirements for the introduction of the new EMUs of an existing design into passenger service, has been approved by the Rolling Stock Standards Committee at its meeting held on the 17/02/2012. The strategy requires consideration of new standards and changes to existing standards made in the period between the introduction of the original vehicles and the present. The strategy and some particularly high risk (to the project) structural non-conformances were also presented to the Rolling Stock Standards Committee in February 2012 and were acknowledged and regularised by the issue of derogation No 12/014/DGN. This second stage derogation, in accordance with the above strategy, addresses of the design that have been identified together with changes of Railway Group Standards as Siemens are in the process of supplying of twenty new four-car EMUs that, with the exception of certain internal layout differences and other minor changes, will be identical to the existing Class 350/2 (`Desiro') EMUs presently operated by London Midland. A strategy outlining approach to be taken in the assessment of the new units, including the methodology and actions required to meet the approvals requirements for the introduction of the new EMUs of an existing design into passenger service, has been approved by the Rolling Stock Standards Committee at its meeting held on the 17/02/2012. The strategy requires consideration of new standards and changes to existing standards made in the period between the introduction of the original vehicles and the present. The strategy and some particularly high risk (to the project) structural non-conformances were also presented to the Rolling Stock Standards Committee in February 2012 and were acknowledged and regularised by the issue of derogation No 12/014/DGN. This second stage derogation, in accordance with the above strategy, addresses of the design that have been identified together with changes of Railway Group Standards as There is no predicted adverse impact Siemens plc arising from the introduction of the new trains with wheelsets non-compliant to GM/RT2466 Issue 3 as they are mechanically similar to the existing Class 350/2 EMUs operated by London Midland, which were manufactured in 2008-2009 and are demonstrably safe and reliable. The class 350/2 fleet is a relatively modern design and the proposed additional vehicles will not introduce any negative risks to third parties and the risks to passengers will be comparable to existing trains. 28/01/2013 N/A RST 30/11/2012 Current There is no predicted adverse impact arising from the changes to the design that affect the fire performance or emergency lighting. 31/01/2013 N/A RST 26/10/2012 Current Rail Systems Proposals Page 80 Deviations Register RGS Number GMRT2100 RGS Issue Number Four RGS Title Requirements for Rail Vehicle Structures Certificate Number 12-171-DGN Title RGS Clause Supply of seats for 20 new Class 350 6.2.1.2 and 6.2.4.1-3 Electric Multiple Units (EMU) to a preexisting design in accordance with Siemens Strategy for the Introduction of Additional Vehicles to an Existing Design, 27/01/2012 Issue 1. Scope 10 x Class 350/3 for First Transpennine Express and 10 x Class 350/4 London Midland. GMRT2130 Three Vehicle Fire, Safety and Evacuation 12-168-DGN Derogation to Engine Exhaust Requirements 3.1.1 defined in GM/RT2130 Issue 3 Clause 3.1. Windhoff Multi-Purpose Vehicle (MPV). GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 12-164-DGN Derogation to GM/RT 2141 Issue 3 Resistance of Railway Vehicles to Derailment and Roll-Over - Use of Computer Simulation in lieu of UK Ride Tests. GMRT2100 Five Requirements for Rail Vehicle Structures 12-163-DGN Derogation to GM/RT2100 Issue 4 Clauses 5.4 and 5.5 5.4 and 5.5 - MPVs for the High Output OLE Construction System (HOPS). This application is to permit noncompliance with the RGS as identified in 6b above. The requirements of Appendix C will be met; however, the requirements of sections D. 1, D. 2, D. 3 and D. 4 of Appendix D will not be met due to the use of a validated simulation in lieu of on-track ride tests. Derogation is sought for the following MPV vehicles: Type 1 (SOPB): · 99 70 9131 010 - 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4 · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7. Type 3 (SNPB): · 99 70 9131 015 - 8 · 99 70 9131 018 - 2 · 99 70 9131 020 - 8. Type 4 (HNPB): · 99 70 9131 003 - 4. Type 5 (SORB): · 99 70 9131 014 - 1. The MPV and wagon vehicle numbers are the following: Type 1 (SOPB): · 99 70 9131 010 - 9 · 99 70 9131 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 022 - 4 · 99 70 9131 023 - 2. Type 2 (HOPB): · 99 70 9131 001 8 · 99 70 9131 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 011 - 7. Type 3 (SNPB): · 99 70 9131 015 - 8 · 99 70 9131 018 - 2 · 99 70 9131 020 - 8. Type 4 (HNPB): · 99 70 9131 003 - 4. Type 5 (SORB): · 99 70 9131 014 1. Wagon: · 99 70 9131 019 - 0. Current Deviations Register as at 09 May 2016 All clauses Nature and Degree Siemens are in the process of supplying of twenty new four-car EMUs that, with the exception of certain internal layout differences and other minor changes, will be identical to the existing Class 350/2 (`Desiro') EMUs presently operated by London Midland. A strategy outlining approach to be taken in the assessment of the new units, including the methodology and actions required to meet the approvals requirements for the introduction of the new EMUs of an existing design into passenger service, has been approved by the Rolling Stock Standards Committee at its meeting held on 17/02/2012. The strategy requires consideration of new standards and changes to existing standards made in the period between the introduction of the original vehicles and the present. The strategy and some particularly high risk (to the project) structural non-conformances were also presented to the Rolling Stock Standards Committee in February 2012 and were acknowledged and regularised by the issue of derogation No 12/014/DGN. This second stage derogation, in accordance with the above strategy, addresses of the design that have been identified together with changes of Railway Group Standards as The Windhoff Multi-Purpose Vehicle (MPV) will operate in transit mode on the Network Rail Managed Infrastructure as well as selfpowered within a Possession. The MPV Main Engine exhaust direction is as depicted in Figure 2 below and is therefore in an area that GM/RT2130 states should be avoided. [See Figure 2 and drawing showing Exhaust Outlet Pipe]. The MPV main engine is under floor mounted between the bogies. The exhaust system outlet is downwards towards the track and outwards as depicted. The MPV design concept for the construction and maintenance of the upper part of the railway infrastructure in terms of the modules that can be accommodated would be severely compromised if the exhaust system outlet was in compliance with GM/RT2130. The primary purpose of the HOPS is to construct the Overhead Line Equipment and supporting structures and requires machinery and operative to work at height. A number of structures would be required to facilitate the installation of a compliant exhaust system and this would severely impact the functionality of the HOPS MPV. Risk Assessment/Safety Justification There is no predicted adverse impact arising from the introduction of the revised seat fixing arrangements of the alternative seating arrangements. Applicant Organisation Siemens plc Certificate Issue Date 28/01/2013 Certificate End Date N/A Lead SC RST Lead SC Approval Date 30/11/2012 Deviation Status Current The performance requirements of the HOPS has resulted in the selection of an exhaust outlet direction that is proven in application and accepted as in compliant with European Standards. However, the impact of using this design has been considered and the following summarises this work: The MPV is an On-Track Machine and will tend not to stop in Railway Stations. It is acknowledged that there is a low risk to the public as the machine passes through a station and to track workers along the way. However, with the exhaust outlets is below the platform level any particles from the exhaust will be very unlikely to cause harm; for example, the worst case would be eye irritation to the public and track workers, but this is considered improbable. The risks to the HOPS Ground Crew Operatives with the exhaust arrangement being mounted under the floor are seen as very low as they will be aware of the position of the outlet. For the MPV Operatives that are working on the upper part of the railway infrastructure, the risks from the exhaust system are greatly reduced compared to an RGS compliant design. The track record of operations of other OTM that have previously been granted a deviation because they have Static validation of wheel unloading using It is considered that there is no significant dQ/Q test and bogie rotation, X-factor, would impact on safety. Computer ride simulation be required. Additionally, on-track ride tests and analysis is an established methodology. to validate resistance to derailment would A similar approach has been used for two have to be carried out in the UK. It would other On Track Machines with simulation therefore be necessary to transport several validated against ride tests in Switzerland MPV vehicles to the UK for testing. This (see derogations 04/169/DGN and would increase timescales and impose 10/133/DGN) and for eight other machines significant additional costs. with simulation validated against ride tests in Austria (see derogations 02/097/DGN, 03/283/DGN, 03/284/DGN, 03/326/DGN, 05/033/DGN, 05/041/DGN, 06/128/DGN, and 09/194/DGN). The MPV vehicles do not have novel suspension or running gear and are proven in-service. A number of similar MPV vehicles are in operation in the UK on Network Rail managed infrastructure. Windhoff Bahn- und Anlagentechnik GmbH 01/03/2013 N/A RST 26/10/2012 Current Windhoff Bahn- und Anlagentechnik GmbH 03/07/2013 N/A RST 02/08/2013 Current GM/RT2400 Issue 4 Clause 3. 22. 1 states that, although OTM are excluded from the scope of GM/RT2100, doors, door handles, steps, handrails and railings shall meet the requirements of 5. 4 and 5. 5 of GM/RT2100 Issue 4. There are two issues with the MPV design in this respect, described below. MPV Steps: the design of the MPVs for the High Output OLE Construction System (HOPS) is based on the use of read-over designs that are proven in application (29 ea. MPV delivered since 2008 / no incidents reported) and approved as in conformance to European standards for On-Track Machines. The MPV Platform Mounted Equipment (access from the vehicle deck) defined by Windhoff is, in the main, based on commercial off the shelf equipment that are already utilised in European Railway Infrastructure maintenance and renewals activities, I. e. similar case in comparison to existing Road Rail Vehicles (RRVs) and excavators in use (in possession). Clause 5. 5: MPV Cab Doors, Door Handles, Handrails and Railings will be demonstrated as in compliance with GM/RT 2100 Issue 4. However, the MPV Steps have been designed to be in conformance with the PAS &amp; LOC TSI and as a result the design Windhoff Bahn- und Anlagentechnik GmbH 12/03/2013 N/A RST 26/10/2012 Current The operator of the MPVs for the High Output OLE Construction System (HOPS) and Network Rail HOPS Project are aware of the alternative action that is to demonstrate compliance with the LOC &amp; PAS TSI for the steps and use of commercial off the shelf equipment for platform mounted equipment. Page 81 Deviations Register RGS Number GERT8030 RGS Issue Number Four RGS Title Requirements for the Train Protection and Warning System (TPWS) Certificate Number 12-162-DGN Title RGS Clause Fitment of Train Protection and Warning Appendix F System (TPWS) to factory train MultiPurpose Vehicle (MPV) On-Track Machines (OTM) that is in conformance with GE/RT8030 Issue 2. Nature and Degree The High Output OLE Construction System (HOPS) project timescales require the procurement of in-service systems and equipment with a proven track record of safe and reliable design. The Windhoff MPV design is frozen in many areas, including the design of the TPWS installation which is in accordance to GE/RT8030 Issue 2. The project risks associated with the delivery of TPWS that is not validated at the point of fitment to the vehicles represents unacceptable risk to the project and has the potential to cause severe delay. GMRT2400 Four Engineering Design of On Track Machines 12-161-DEV Revised 16-01-2014 Derogation to GM/RT2400 Issue 4 Clause 3.25 - Structural Requirements The MPVs being delivered to the Network Rail High Output OLE Construction System (HOPS) Project are designed to be compliant with the current Loc &amp; Pas TSI and referenced EN standards. Evidence of this compliance will be provided to, and reviewed by, the projects Notified Body (NoBo), Designated Body (DeBo) and Competent Person (CP) as appropriate. The requirements of the Loc &amp; Pass TSI and referenced EN standards are similar but not identical to the requirements of the sub-clauses of Section 3. 25 of GM/RT2400. However, it is considered that the intent of the RGS has been met, and compliance with the specific requirements of GM/RT2400 will not provide any additional safety, engineering or operational benefits. GMRT2400 Four Engineering Design of On Track Machines 12-160-DGN Revised 02-10-2013 Derogation to Crane Stability Requirements defined in GM/RT 2400 Issue 4 - Clause 3.13.2. 3.13.2 GERT8000-TW5 Three Preparation and Movement of Trains: Defective or Isolated Vehicles and On-Train Equipment 12-159-DGN Allowing a unit to enter service with a defective sander. 28.1 Current Deviations Register as at 09 May 2016 Scope The 10 vehicles affected by this deviation are: · 99709131001-8 · 99709131005-9 · 99709131006-7 · 99709131010-9 · 99709131011-7 · 99709131013-3 · 99709131014-1 · 99709131021-6 · 99709131022-4 · 99709131023-2. The deviation applies to the MPVs of the high output Overhead Line Electrification (OLE) Construction System (HOPS) that are designated OTMs. These OTMs will operate in "transit mode" on the UK National Rail Network. During the procurement phase, it has been identified that the various suppliers of TPWS equipment did not produce any systems that are in conformance with GE/RT8030 Issue 3. The reason being that GE/RT8030 Issue 4 has now been released and an Issue 3 system would not be in conformance with Issue 4. Windhoff has investigated the availability of TPWS equipment that is in conformance to GE/RT8030 Issue 4, and there is a risk that a "validated" system will not be available in the timescales required for deployment of the Factory Train. Windhoff has designed the installation for the Unipart supplied TPWS that is in conformance with GE/RT8030 Issue 4. It is anticipated that the system will have gained product approval Clause 3.25.1 - General Requirements This application is to permit nonClause 3.25.2 - Load Factors Clause 3.25.3 - compliance with the RGS standard clauses On-track Machine Bodies - Proof Loads of GM/RT2400 Issue 4, as identified above, Longitudinal Loads Clause 3.25.4 - On-track for the following MPV vehicles. Type 1 Machine Bodies - Proof Loads - Vertical (SOPB): · 99 70 9131 010 - 9 · 99 70 9131 Loads Clause 3.25.5 - On-Track Machine 013 - 3 · 99 70 9131 021 - 6 · 99 70 9131 Bodies - Fatigue Loads Clause 3.25.6 022 - 4 · 99 70 9131 023 - 2. Type 2 Equipment Attached to On-track Machine (HOPB): · 99 70 9131 001 - 8 · 99 70 9131 Bodies Clause 3.25.9 - Lifting and Jacking 005 - 9 · 99 70 9131 006 - 7 · 99 70 9131 Points Clause 3.25.10 - Bogie Structures 011 - 7. Type 3 (SNPB): · 99 70 9131 015 Clause 3.25.11 - Equipment Attached to 8 · 99 70 9131 018 - 2 · 99 70 9131 020 - 8. Bogie Frames Type 4 (HNPB): · 99 70 9131 003 - 4. Type 5 (SORB): · 99 70 9131 014 - 1. Wagons (KFA) now classified as OTM: · 99 70 9131 019 - 0. Risk Assessment/Safety Justification Applicant Organisation Windhoff and the Operator are satisfied that Windhoff Bahn- und the fitment of TPWS System to the MPV that Anlagentechnik GmbH is in conformance to GE/RT8030 Issue 2 but capable of being fitted with a GE/RT8030 Issue 4 system is a pragmatic solution that does not pose significant risk to the Railway Group. Certificate Issue Date 27/11/2012 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 08/11/2012 Deviation Status Current It is not considered that compliance with the Windhoff Bahn- und Loc &amp; Pas TSI and referenced EN Anlagentechnik GmbH standards rather than the identified subclauses of GM/RT2400 Issue 4 Section 3. 25, will have any impact on the safe operation or maintenance of the MPVs. The HOPS Project have considered the impacts of the alternative actions in relation to the current RSSB and Railway Group initiatives to align the UK RGS (GM/RT2400) for the Engineering Design of On-Track Machines (OTMs) in Travelling Mode with the Technical Specifications for Interoperability (TSI) and Euro Norms (ENs). The project has reviewed the latest draft of GM/RT2400 Issue 5 and RIS 1702 as part of the compilation of this application. The following extract from GM/RT2400 Issue 5 Draft 2h dated July 2012 issued for consultation by the RSSB is considered relevant to this application since the requirements align with the current design of the MPVs. Strength of vehicle structure: · The static frame strength of on-track machines shall comply with BS EN 14033-1: 2011, clause 6. 2. · The dynamic frame strength of on-track machines shall comply with BS EN 12663-1: 2010, clause 6. 6. · Attachments to the on-track machine frame, Clause 3. 13. 2 Stability Characteristics: The requirements set out in Clause 3. 13. 2 The High Output OLE Construction System Amey Fleet Services Ltd Note: all cranes on the Multi-Purpose can be achieved by the cranes that are (HOPS) Operator and Network Rail HOPS Vehicles (MPVs) of the High Output OLE being utilised on the MPVs of the High Project are aware of the alternative action Construction System (HOPS) are classified Output OLE Construction System (HOPS), that is proposed and endorse the proposal. as Loader Cranes. Stability requirements but this will create a significant reduction in The Operator will ensure that the necessary relate to both operating free on rail at vehicle operational capability available to the HOPS operational processes and procedures are stand-still and travelling whilst craning. Project. This is particularly significant in aligned to a design that is in conformance to Vehicles to which this application refers: those MPVs where the specification requires recognised and proven ENs. Note: Windhoff no RSL Crane MEWP (Palfinger) a crane and a Mobile Elevated Work Windhoff has been informed that key 1. 1. 1/2721 99709131001-8 PKR 800 - 1. 1. Platform (MEWP) to be installed on a members of the UK Railway Group are 3/2721 99709131003-4 PKR 800 - 1. 1. vehicle and used quasi-simultaneously. It is aware that the crane stability requirements 5/2721 99709131005-9 PKR 800 - 1. 2. therefore proposed instead to design the defined in GM/RT2400 Issue 4 are not 1/2726 99709131006-7 Hitachi - 2. 1. 1/2721 vehicles in accordance with BS-EN14033aligned to the proven engineering principles 99709131011-7 PK 85002 PA 360 2. 1. Part 2: 2011. To quantify the difference in that are now defined in the proposed 3a/2721 99709131013-3 PK 29002 - 2. 2. operational capability when using the alternative European Standards. It is widely 1/2721 99709131014-1 PKR 290 - 2. 2. different standards, sample calculations for anticipated that stability requirements for 2/2721 99709131015-8 PK 12502 PA 360 2. two crane types are set out in the Table cranes operating in "Working Mode" within a 2. 4/2721 99709131018-2 PK 12502 PA 360 below: Crane Ref: PK29002D PK85002D Network Rail Managed Infrastructure 3. 1 /2721 99709131022-4 PK 12502 PA Max reach (m): 14,5 13,5 Effective hook possession will be changed and aligned to 360. load (kg): 1,500 5,300 Test load BSthose being applied by the Crane installed EN12999: 2,270 6,625 Test load on the MPVs of the High Output OLE GM/RT2400 Iss 4: 3,500 7,950 Loss in Construction System (HOPS). performance: 54% 20% 16/01/2014 N/A RST 18/10/2012 Current 02/10/2013 N/A PLT 19/10/2012 Current Northern, on occasion, may require a unit to enter service with a defective sander to facilitate the units working to a location where it can be repaired. To do this, Northern plan to have the defective unit coupled in rear of another unit which is fully fit for service, or to ensure that the unit is so turned that the defective sander is on the rear vehicle of the unit. The way in which the sanders work means that the defective unit coupled in rear would not be required to lay sand as the only vehicle which will deposit sand is the leading vehicle of the train. This effectively makes it irrelevant that the sander is defective on the rear unit. This would also be the case if a two car unit was so turned that the defective sander was on the rear vehicle. Northern require the deviation to allow a unit with a defective sander to enter service providing that the defective sander is not on the leading vehicle. The sander on the leading vehicle must be working. 31/10/2012 N/A TOM 16/10/2012 Current As the rule is currently written should a unit There are no safety implications with this fail at a location with a defective sander, it is derogation. impossible to comply with the rules to get the unit moved to a location where it can be fixed. It is also noted that, in the proposed tranche changes to Module TW5, the rules quoted are being withdrawn. Northern Rail Page 82 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 12-157-DGN Title Harold Wood Station OLE Structure 15/01 on Platform 4 (Down Electric) - reduced platform width. RGS Clause 6.5.2 and 6.5.3 GKRT0045 Two Lineside Signals, Indicators and Layout of Signals 12-156-DGN Buffer Stop Light Position - Crystal Palace (Plat 3 &amp;5) &amp; Clapham Junction (Plat 1). 2.5.3.4 a) and; d), and 2.5.3.5 GMRT2100 Five Requirements for Rail Vehicle Structures 12-154-DGN Window being fitted into two new air intake 5.3.3.1b) filter panels replacing the sliding front doors on a Mk3 DVT. The scope of this application applies to the following MK3 DVTs vehicle numbers: 82111, 82124, 82129 and 82145. The deviation applies to a window being fitted into two new air intake filter panels replacing the sliding front doors on a Mk3 DVT for the Network Rail PLPR project. This panel provides an air supply for the new Generator set being fitted to the vehicle (see illustration attached). The original brief for the work was to remove the existing windows from the doors and re-use them in the new filter door. This proved impractical as the existing windows cannot be removed from the doors intact due to the method used for installing and securing the windows in the original installation. The number of vehicles required for the contract is only four, with two windows per vehicle, so a small quantity exacerbates supply issues. A new production of the existing design would not meet the Group Standard requirements. We have sought alternative windows and the result is that shown in Appendix 2. GKRT0060 Four Interlocking Principles 12-151-DGN ESOC provision for Marston Vale VHLC Interlockings The VHLC interlocking areas for the Bedford to Bletchley(B2B) line that were commissioned in 2004 are: · Feny Stratford · Bow Brickhill · Woburn Sands · Aspley Guise · Ridgmont · Lidlington · Marston · Stewartby Green Lane · Stewartby Brickworks · Forders Sidings · Wotton Broadmead · Kempston Hardwick · Bedfords St Johns, plus new interlocking recontrolling the flyover junction. All are controlled from the MCS control system at Marston Vale Signalling Control Centre, with the new interlocking being added to the current MCS operators' workstation at Marston Vale CC. This application has been identified as part changes proposed to add flyover junction to Marson Vale by provision of new VHLC interlockings controlled from Marston Vale SCC. Provision of ESOC for the flyover junction only will create inconsistencies from an operational point of view. It can be argued that the full B2B line should be retrofitted, this is not practical and no justified on the basis of supporting information gathered. Considering the B2B, including the flyover junction, due to the distributed nature of the VHLC interlocking, implementation of ESOC would require the provision of fifteen control paths, and because the interlockings are located remotely from the control system, an additional fifteen diverse paths, for control. The implementation would be an onerous, both in term of design time and cost. The implementation of ESOC requires line side cables along the B2B route, 32 miles to be installed, that is a major contributor to the high cost. The architecture of the VHLC is such that the provision of the ESOC would require a complicated arrangement for the delivery of the controls between the control system and the various distributed remote interlockings. Current Deviations Register as at 09 May 2016 C8.1.2 Scope Harold Wood Station OLE Structure 15/01 on Platform 4 (Down Electric). Nature and Degree Platform 4 (Down Main) at Harold Wood station is being extended eastwards to accommodate ten-car (205 m length) Crossrail trains. The extension of this platform will result in the existing overhead line structure 15/01 being engulfed by the platform extension. The distance between the face of this structure and the platform edge will be 1960 mm (I. e. less that minimum distance of 2500 mm required by Clause 6. 5. 2) and 40 mm less than the 2000 mm stated in Clause 6. 5. 3. (The derogation is based on a GRIP 4 level of design. Detailed design and setting out details will be produced as part of GRIP 5 and the opportunity will be taken to establish whether a 2000 mm platform is achievable. ) The new structure leg could be located behind the new platform extension to provide more than 3000 mm clearance, but this would result in a loss of parking which is considered unacceptable as well as requiring a longer extension to the existing portal boom. The structure 15/01 was installed in 1939 as part of the GE Electrification and its slender construction might not meet current structural standards. It is probable that a completely new portal structure over the Up and Down Electric · Crystal Palace - Platform 3 · Crystal Palace To comply with the requirement of the - Platform 5 (Existing) · Clapham Junction - standard would introduce inconsistency with Platform 1. the position of the lights at different buffer stops regularly approached by LOROL drivers. The Train Operating Companies (TOCs) have requested white lights rather than red to avoid driver confusion mistaking them for main light signals and for consistency with other buffer stops. The TOCs who regularly use the platforms have requested the proposed arrangement of the buffer stops lights as part of the Signal Sighting Process that reviewed the approach to the buffers. Risk Assessment/Safety Justification Applicant Organisation It is not deemed practicable to provide a Network Rail compliant solution. (The opportunity will be taken at the detailed design stage (GRIP 5) to further investigate whether a 2000 mm clearance can be provided. ) Low. The overall width of the platform extension is 3 metres, the restricted clearance only applies over the 150 mm width of structure 15/01. Structure 15/01 is located at the eastern end of Platform 4 (Down Electric) in the vicinity of the second coach from the front. The station entrance and exit is at the west end of the station and passengers alighting and boarding at Harold Wood will tend to use the rear portion of the train rather than the front portion. The location of the structure 15/01 is therefore not within that part of the platform where passenger density is greatest. The residual risk to passengers is deemed to be very low. Certificate Issue Date 12/12/2012 Certificate End Date N/A Lead SC INS Lead SC Approval Date 14/11/2012 Deviation Status Current The arrangement for which derogation is Network Rail sought is that which is in place in other locations and drivers are used to approaching such buffer stop arrangements. The buffer stop light position provides an additional 3 metres of margin for the driver before the buffer stop would be struck. A train striking the lights/mounting post is not considered to constitute a significant risk, as the posts that the lights are mounted are hinged and designed to be collapsible, and windscreen glass on the trains using the platforms shall comply with ATOC code of practice ACOP/EC/01003, which includes that, in the event of a windscreen suffering impact damage, no glass spall should enter the driver's cab area. Buffer stop lights are considered as the limit of the movement authority not the buffers and drivers are used to the arrangement at other locations and meet with LOROL driving standards policy. Impact of buffer stop is low - see attached buffer stop risk assessments. The TOCs consulted as part of the signal sighting process consider this to be a safer arrangement than the arrangements required for strict compliance with standards - see attached signal sighting forms. The TOCs who will regularly use the platforms We propose the use of the window detailed Brush Traction in Appendix 2. This window meets the 3kPa requirement of GM/RT2100 Issue 5 Section 5. 3. 3. 1 d), but not the 6kPa of part b. 31/10/2012 N/A CCS 12/10/2012 Current 15/10/2012 N/A RST 28/09/2012 Current The likelihood of a failure of a part of the Network Rail system where the signalman could not replace a signal to 'ON' and where the remote interlockings would not do this automatically, is very remote. During failures of the communication links to the interlocking, the interlocking will automatically revert to 'All Signals On' status without signallers' interaction. A diverse communication route for path protection has been provided. There is a risk that, in providing ESOC for the flyover interlocking only, the signaller could be misled into thinking that all signals in the control area will be replaced. The likelihood of a failure of a part of the system where the signalman could not replace a signal to 'ON' and where the remote interlockings would not do this automatically, is very remote. It is also worth noting that the new VHLC at Bletchley Flyover Junction has one train working controls between MV64/66 and MV63, which is the portion of the Up Bletchley / Down Bletchley that passes over the flyover. These controls only allow one train at a time onto this section to which the extension proposed is being provided. 31/10/2012 N/A CCS 12/10/2012 Current Page 83 Deviations Register RGS Number GMRT2130 RGS Issue Number Three RGS Title Vehicle Fire, Safety and Evacuation Certificate Number 12-150-DGN Title Derogation for the manufacture and supply of 26 new Class 66 locomotives as an existing design, retaining the existing degree of fire performance. RGS Clause 2.3 Safeguarding continued operation in the event of fire 2.5 Reducing the risk of fire development 2.7 Equipment cubicles and equipment cases 2.9 Material fire performance categories and selection Scope Supply of maximum 26 class 66 vehicles to the existing design as authorised for service in the UK (with the exception of minor changes to the engine to comply with tier 3A emissions requirements, fitment of GSM-R voice radio and cab air cooling equipment). Nature and Degree Compliance with the full requirements of GM/RT2130 would require the manufacture to reconsider the existing vehicle fire performance and obtain additional compliance information for components and design features of the existing class 66 design. The design costs of performing a full design review of the locomotive will add significant costs for a small quantity of locomotives, and the delays in manufacture incurred would impact on supply of locomotives before the 2014 deadline for supply of the class 3A emissions compliant engine. Uncertainty over the necessary compliance to be achieved affects commercial negotiations and the ability to achieve manufacture before the 3A engine deadline. Use of alternative components or other design changes would have an impact on provisions of spares and maintenance costs. GMRT2100 Five Requirements for Rail Vehicle Structures 12-149-DGN Derogation for the manufacture and supply of new Class 66 locomotives with vehicle bodyshell structures, bogies and glazing designed in accordance with GM/RT2100 Issue 2. Complete document Supply of maximum 26 class 66 vehicles to the existing design as authorised for service in the UK (with the exception of minor changes to the engine to comply with tier 3A emissions requirements, fitment of GSM-R voice radio and cab air cooling equipment). GMRT2141 Three Resistance of Railway Vehicles to Derailment and Roll-Over 12-148-DGN Computer Simulation in place of On Track Ride Testing. Appendix D (Acceptance using method 2). Plasser 09-4x4/4S Tamping Machines. GM/RT2100 clause 10. 2. 4 permits the manufacture of an existing design of authorised vehicle. This derogation is to ratify the use of the existing structural design against GM/RT2100 issue 2. Compliance with the full technical requirements of GM/RT2100 issue 5 would require a large scale redesign of the vehicle body structure and running gear to meet changes in crash worthiness and other requirements. Such a revision would incur large design development and manufacturing costs and would introduce delay. The costs for such a redesign are disproportionate for the limited number of vehicles that can be supplied with the 3A emissions level engine. Timescales for such a redesign would cause significant delays and prevent use of the existing engine under the emissions directive. As a consequence the order would not be economically viable and GBRf would seek to procure alternate locomotives. This would entail continued or extended use of aged locomotives with increased operating cost and a lower level of compliance for crashworthiness, driver comfort, noise etc. Compliance with clause 10. 2. 4 permits the build of further vehicles to an existing authorised design. The existing design In order to deliver the machine into the UK by rail, it must be certificated in advance of leaving Austria. The alternative of delivery by road prior to a UK ride test is impractical. GERT8035 Two Automatic Warning System (AWS) 12-144-DGN AWS caution acknowledgment period for Class 350 (all subclasses) operated by London and Birmingham Railway Company Limited. 2.8.5.2 The Derogation being sought would apply to all Class 350/1, 350/2 and 350/3 operated by London And Birmingham Railway Company Limited. GMRT2000 Three Engineering Acceptance of Rail Vehicles 12-143-DGN Deviation against GM/RT2000 for the reintroduction of 8 KFA (Y) wagons 6.6.1.c) and 6.6.2 b) paragraph 2 The deviation applies to eight KFA wagons from the following eleven wagons: 93242, 93243, 03244, 93245, 93254, 93256, 93258, 93260, 93263, 93276, and 93280. These wagons will be used as part of the High Output Plant System being developed to electrify parts of the national network. Current Deviations Register as at 09 May 2016 The rate of occurrence of late to cancel AWS/TPWS incidents increases when the AWS acknowledgement period is set at 2 seconds. London Midland applied for derogation previously for Class 350/2s operating at speeds up to 100 mph, which was subsequently regularised by the changed requirement brought about by clause 2. 8. 5. 2 of GE/RT8035 Issue 2. There is a proposal to increase operating speeds of Class 350/1 and yet to be built class 350/3 to increase capacity and service frequency on the west coast south routes with a consequent worthwhile reduction in journey times. The timetabled mileage for operating at 110 mph on a weekly basis for Class 350/1 is 18. 83% of the class 350/1 total mileage and 12. 37% of the total 350 fleet mileage. Under the current requirements of clause 2. 8. 5. 2 of GE/RT8035, London Midland will have to apply an AWS acknowledgement period of 2 seconds to its class 350/1 and 350/3 units. For consistency, and to avoid further confusion for drivers, the 2 second period would also be applied to class 350/2s, even though the standard allows 2. 7 seconds for 100 mph capable units. Risk Assessment/Safety Justification There are currently over 380 class 66 locomotives operating in the UK. The existing class 66 have an excellent fire safety record and the existing fire performance would be retained. It is considered that the risk is suitably managed through other mitigating factors, specifically when operational the locomotives are manned by trained personnel only and other design features on the locomotive reduce the likelihood of a fire starting. Given that the Class 66 fleet is a relatively modern design and the proposed additional locomotives will be very similar to these locomotives, it can be concluded that the introduction of the additional locomotives on GBRf operations will not introduce any adverse risks to third parties. Economic procurement of additional class 66 enables cost effective operation of rail services to attract additional freight traffic onto the rail Network and to service existing demand. The Railway Interoperability Directive and LocPas TSI recognise the costs and timescales to achieve compliance with Interoperability requirements and permit existing designs to be manufactured until 2017. Note: the design is the same as that of the existing locomotives currently in service. There are already more than 380 class 66 locomotives authorised to operate on the GB Network. The additional 26 locomotives would maintain the current level of safety and compatibility on the Network. The class 66 has proven to have a good safety record and structural integrity during derailment. Driver safety would be maintained at current levels. The existing class 66 fleet has not exhibited structural problems and structural integrity throughout the loco service life is expected to be retained. Given that the Class 66 fleet is a relatively modern design and the proposed additional locomotives will be very similar to these locos, it can be concluded that the introduction of the additional locomotives on GBRf operations will not introduce any adverse risks to third parties. Procurement of further class 66 locomotives enables common interworking with the existing locomotive fleet and optimisation of existing maintenance capabilities and component supplies. Economic procurement of additional class 66 enables cost effective operation of rail services to attract additional freight traffic onto the rail Network and to service existing demand. The Railway Interoperability Directive and LocPas TSI recognise the See attached risk assessment. Applicant Organisation GB Railfreight Ltd Certificate Issue Date 15/10/2012 Certificate End Date N/A Lead SC RST Lead SC Approval Date 28/09/2012 Deviation Status Current GB Railfreight Ltd 15/10/2012 N/A RST 28/09/2012 Current Plasser UK Ltd. 27/11/2012 N/A RST 28/09/2012 Current 06/12/2012 N/A CCS 06/12/2012 Current 24/10/2012 N/A RST 28/09/2012 Current We know, from experience, that the London and Birmingham reduced acknowledgment period increases Railway Company Limited the likelihood of late to cancel AWS/TPWS activations and. in turn. RSSB research has shown that unnecessary AWS/TPWS interventions reduce driver confidence in AWS/TPWS and increase the likelihood of TPWS reset and continue events. Reducing the AWS acknowledgement time means less time for a driver to assimilate a signal aspect before acknowledging the warning. It is desirable to afford the driver the maximum time to properly assimilate the signal aspect prior to acknowledging the AWS warning. It should also be noted that, on the West Coast South, the prevailing distance from the AWS magnet to the signal is 230 metres rather than the standard requirement of 180 metres as laid out in GE/RT8035. The impact of 2. 7 seconds compared to 2 seconds is mitigated by the additional distance provided by between the AWS magnet and signals on the West Coast South and, in addition, the West Coast South is fitted with TPWS at signals protecting conflicts and selectively with TPWS + at higher speed/risk signals. Any marginal increase in risk is effectively mitigated by the above considerations. The These wagons are 60' container flats and There will be no detrimental impact of the Network Rail were part of an order for approximately two alternative actions; the vehicles will be hundred vehicles delivered by Rautarukki of maintained in accordance with Railway Finland in 1987. Forty vehicles from the Group Standards and Network Railway order were modified with strengthened Policy and Standards. headstocks by Network Rail for use as part of the Rail Delivery Train and then transferred for use to make up the Rail Head Treatment Train wagon fleet until 2005/2006, all of which are currently registered nonoperational. Edinburgh District Council currently operates a small fleet of these vehicles for the waste disposal services. These have been operational continuously for the period whilst the Network Rail owned vehicles are non-operational. Due to the age of these vehicles, a significant amount of work would be required to demonstrate that the existing wagons comply with the mandatory requirements contained in the current RGS. This would be further complicated by severely limited availability of original design information. Page 84 Deviations Register RGS Number GMRT2461 RGS Issue Number One RGS Title Sanding Equipment Fitted to Multiple Units and On-Track Machines Certificate Number 12-137-DGN Title RGS Clause Position of Sand Delivery System on Plasser 9.1 09-4x4/4S. Scope Plasser 09-4x4/4S Tamping Machines. Nature and Degree For operation in braking mode, sand shall be delivered to the railhead by the leading vehicle only for all train formations (including multiple formations), at a location forward of the third axle and after the second axle, in the direction of travel. To meet the requirements of GM/RT2461, one of the sanding units (on each side of the machine) would need to be mounted on the satellite unit. When the machine is tamping, the continuous action (a feature of this type of tamper) is achieved by the satellite unit moving semi-independently of the main machine. This means that the sanding units and their hoppers would have to be mounted on the Satellite Unit and this has potential implications for the safe riding of the bogie supporting the satellite unit. Additionally, special sand delivery systems would have to be designed to fit on the satellite bogie and these would have to withstand the working environment of the satellite unit in close proximity to the tamping banks. Risk Assessment/Safety Justification Applicant Organisation The 09-4x4/4S Tamping Machine is Plasser UK Ltd mounted on five bogies, each with two axles, a total of ten axles. By mounting the sand delivery system in advance of the fifth axle for travel in the working direction, there would still be six axles in rear of the delivery system. This meets the requirement of the third paragraph of clause 9. 1. It is therefore considered that this system would still meet with the spirit of the RGS requirements and there is therefore no impact. Certificate Issue Date 08/11/2012 GIRT7033 Two Lineside Operational Safety Signs 12-136-DGN Trial car stop markers Section AK, B10.1, B10.2. South West Trains proposes the use of car stop signs not currently included in RGS GI/RT7033 as required by section B10 of that RGS. South West Trains (SSWT) (in association with Network Rail Wessex Route) is seeking ways to reduce station instances of trains stopping short on platforms. Sign AK104z (with TOC variations) is the design of car stop marker generally used on stations. South West Trains has, over time, significantly reduced the number of car stop markers on its stations; however, the number of trains stopping short on platforms remains unacceptably high. Changes in the design and colour of way-finding signage now means car stop markers are becoming less conspicuous in some instances. Car stop signs are small and can sometimes be difficult to discern amongst other signage. SSWT currently has a deviation Ref. 11/161/TNC which it is seeking to extend beyond 30/09/2012 while a derogation is considered for the use of these signs. (NOTE: SSWT also has a further deviation Ref. 11/160/TNC which will not be extended and the trial signs associated with this deviation will be removed). The car stop markers are larger than Stagecoach South Western existing signage (the size is multiplied up Trains Ltd (trading as South from existing design). The specification of West Trains) the designs also includes a slight tilt when the sign is installed to pick up ambient lighting, especially at lamp columns where existing signs often do not pick up the light making them difficult to see at night. The trial signage is currently in place (or planned*) at the following locations: Ashford (Surrey); Moreton; Staines (*); Branksome; New Milton; New Milton; Brookwood (*); Parkstone(*); Sway; Christchurch; Portchester; Swaythling; Esher; Redbridge; Whitton (*); Godalming; St. Deny's; Wimbledon; Hinton Admiral (*); Salisbury; Woking; Millbrook; Southampton Airport Parkway; Worplesdon. This list includes a number of locations with high number of stop short incidents. See Appendix A for design of car stop markers. 28/09/2012 GMRT2473 One Power Operated External Doors on Passenger Carrying Rail vehicles. 12-135-DEV Emergency brake override indication B11.4 Class 377/6 (26 five-car trains / 52 cabs) plus 40 additional Class 377/7 vehicles. There are considered to be no negative Southern Railway Limited impacts of the proposed design as it is a continuation of the existing Class 377 design, to which drivers are already accustomed. The design adequately warns the driver that an emergency brake override has been made. 08/01/2014 GMRT2130 Three Vehicle Fire, Safety and Evacuation 12-134-DEV Self-closing cab-saloon door 2.5.5 Class 377/6 (26 five-car trains / 52 cabs) plus 40 additional Class 377/7 vehicles. It is considered that there is no negative impact of this non-compliance since train crew are already used to closing the cabsaloon door. Therefore, a fire barrier is always maintained. Southern Railway Limited GMRT2461 One Sanding Equipment Fitted to Multiple Units and On-Track Machines 12-133-DEV Sanding on second, trailing unit 9.1 Class 377/6 (26 five-car trains / 52 cabs) plus 40 additional Class 377/7 vehicles. To comply with this requirement extra functionality would have to be added to an existing indicator, or an additional indicator would have to be added to the driver's desk. In either case, changes to the units' schematics and wiring would be needed to illuminate the indicator when an emergency brake application had been overridden. The change would make the cab desk different from the existing Class 377 fleet, and would require additional training for the driver; the additional desk indicator could be confusing to drivers used to the existing Class 377 desk. At the outer ends of a train the cab/saloon door forms part of the fire barrier between the cab and the passenger saloon, and it is locked shut to prevent passenger access to the cab. This door is not self-closing. To comply with the clause a closing device would have to be added to the door. It is considered that if such a device was fitted, train crew could rely on the device, and may not check that the door is securely closed. There is a risk that the closing device would shut the door, but not fully, which presents a risk to the train security. It should be noted that when the cab is in the middle of a multiple formation the cab/saloon door is locked in the converted position, preventing passenger access to the cab controls, and a compliant gangway door operates as part of the fire barrier. This deviation requests enhanced performance which is non-compliant with the standard as written, but consistent with the objectives of the standard. In the condition where the leading unit has a Southern Railway Limited sand level of below 20%, sanding will be enabled on both the leading and trailing units. If the leading vehicle in either unit detects wheel slide, sand will be dispensed by that unit. If the leading vehicle detects wheelspin and the driver selects `Sand in Traction', sand will be dispensed by that unit. As such, both units will dispense sand if both detect wheel slide and have sufficient sand available. The likelihood of this occurring is low, as the leading unit will condition the railhead and so the trailing unit is unlikely to experience wheel slide. Wherever sand is applied, there will always be at least eighteen axles after the sand deposition point. Therefore, it is considered that there is no negative impact in terms of contamination of the railhead, and so compatibility with the railway system is unaffected. This functionality has been developed to increase the safety of the railway in conditions of extremely poor rail head adhesion, having a positive impact on overall system performance. Current Deviations Register as at 09 May 2016 Certificate End Date N/A Lead SC RST Lead SC Approval Date 31/08/2012 Deviation Status Current CCS 12/09/2012 Current N/A Rolling Stock 06/12/2013 Current 08/01/2014 N/A Rolling Stock 06/12/2013 Current 08/01/2014 N/A Rolling Stock 06/12/2013 Current Page 85 Deviations Register RGS Number GMRT2130 RGS Issue Number Three RGS Title Vehicle Fire, Safety and Evacuation Certificate Number 12-132-DEV Title Emergency lighting positions. RGS Clause 4.3.1, 4.3.2, 4.3.6 Scope Class 377/6 (26 five-car trains / 52 cabs) plus 40 additional Class 377/7 vehicles. GMRT2130 Three Vehicle Fire, Safety and Evacuation 12-131-DEV Continued operation after a fire. 2.3.3 Class 377/6 (26 five-car trains / 52 cabs) plus 40 additional Class 377/7 vehicles. GMRT2161 One Requirements for Driving Cabs of Railway Vehicles 12-130-DEV Windscreen wiper arm position 6.2.6 Class 377/6 (26 five-car trains / 52 cabs) plus 40 additional Class 377/7 vehicles. GERT8035 Two Automatic Warning System (AWS) 12-129-DGN TPWS functionality on Class 377/6 fleet. The deviation splits into a number of sections, all related to Appendix F of GE/RT8030 and one clause of GE/RT8035. There are a number of areas where full compliance is not achieved: Individual Isolation of AWS / TPWS: GE/RT8035 2.6.8.2. Class 377/6 (26 five-car trains / 52 cabs) plus a contract option for additional 40 vehicles. Current Deviations Register as at 09 May 2016 Nature and Degree · Light above doorway: There is limited space above each doorway due to the UK loading gauge and the space requirements of the door header gear. To fit emergency lighting directly above each bodyside door, the lighting unit would have to be fitted between the doorgear and the header gear trim panel, moving the trim panel lower. This would reduce the door throughway height, which is already lower than that required by GM/RT2473 clause B5. 1. 2; a separate derogation is raised to this clause. The lower doorway would increase the risk of passenger striking their head, and would impede evacuation. · Controls and signage in field of illumination: The door controls and signage are located on standbacks to the side of the doorways, and back from the door itself. It is not possible to have a single light pointing at the door threshold and at the controls. Therefore, multiple lights would be required. This would contradict the objective of not attracting passengers to the vestibule (as described in GM/RT2531 note RC024). · Provide lighting for charging photo-luminescent signage: As above, this would require a bright light directed at the signage, which would emphasise the emergency egress device and encourage To comply with Clause 2. 3. 3, it would be necessary to provide significant protection of systems and/or redundancy to enable the units to operate for 15 minutes after the outbreak of a fire. Control cabling in any area judged to be vulnerable would need to be protected by some form of shielding. Some systems may need redundancy with cabling routed in separate locations. To achieve this, there would be significant design changes and additional equipment. This would add significant cost to the project. In addition, maintenance of the vehicles would be changed and in some cases hindered by the extra protection. To comply with the standard would require a change to the wiper arm, to incorporate a `dog-leg' design. This would necessitate that Class 377/6 units have a different spare part from existing Class 377s operated by Southern. There are two areas of impact from complying with the RGS requirements: · The manufacturing and validation timescales for compliant TPWS equipment do not meet the overall Class 377/6 programme and would lead to a project delay. · Achieving full compliance with the requirements would require a number of design changes from the Class 379 and Class 377/5 designs, on which the Class 377/6 design is based. These changes would have a significant impact on the project, and are likely to delay the project. Enhanced TPWS equipment is being manufactured by two suppliers, but both suppliers' equipment is still under development and testing. Delivery of the equipment is required in September 2012, which cannot be achieved. Full validation of the equipment would be required to support certification for on-track testing in May 2013. There is no assurance that suppliers' validation programmes will definitely achieve these dates. The Class 377/5 and Class 379 units were fitted with Thales Mk. 1 TPWS control units. Modifying these designs to achieve full compliance with GE/RT8030 Issue 4 would require: · installation of a new control unit, which, depending on the supplier, may be Risk Assessment/Safety Justification Applicant Organisation It is considered that there are no negative Southern Railway Limited impacts from the Class 377/6 emergency lighting design. Position of lights and illumination of controls: GM/RT2130 (together with guidance note GM/RC2531) has two reasons for requiring emergency lights above the door and not in the centre of the vestibule. · Firstly, it should avoid encouraging passengers towards the vestibule. This is not applicable to vehicles such as Class 377/6 where the vestibules are at 1/3 and 2/3 positions in the vehicle and there is no full partition between seating the passenger seats. Any lighting in the vestibule, at the centre or the doorway, will be visible to passengers. The proposed location of lighting will create even lighting along the vehicle, without attracting passengers to any area. · Secondly, lighting from the centre would mean that passengers created shadows over any equipment they tried to use since the light would be behind the passengers. The position of the lighting on Class 377/6 minimises this issue within the space constraints of the doorway. The problems with shadows are minimised due to the position of the normal and emergency door controls (and passenger emergency alarm) on standbacks and not directly It is considered that there is no negative Southern Railway Limited impact from complying with the SRT TSI instead of GM/RT2130. The requirement of the SRT TSI is considered to be an appropriate requirement for the Class 377/6 units. Certificate Issue Date 08/01/2014 Certificate End Date N/A Lead SC Rolling Stock Lead SC Approval Date 06/12/2013 Deviation Status Current 09/01/2014 N/A Rolling Stock 06/12/2013 Current When the proposed wipers are in the Southern Railway Limited parked position (I. e. when not in use) part of the support arms for the wiper blade obscures part of the primary vision area, low down and to the right of the driver's vision. This obscured part of the driver's sight lines (taken from the driver's seat position) measures 94 mm upwards and 48. 5 mm to the left of the bottom right corner of the primary vision area. The attached drawing 3EER400014-6151 indicates the obscured portion of the windscreen from the exterior perspective of the cab, although the dimensions are as observed from the driver's seat position. The area obscured is required by case (a) of the sightlines required for seated drivers, I. e. : · A view of the track (at rail height) at 5 m beyond the vehicle buffers (or vehicle end) for vehicles subject to frequent coupling and uncoupling activities. · The wiper arm will slightly obscure the right-hand rail (from the driver's perspective). A small movement of the driver's head to the left will allow the obscured area to be viewed. Case (b) lineside signals - and case (d) - a view of the track in the distance - are not obscured. There are no known negative impacts from the current design. The infringement is Individual Isolation of AWS/TPWS: Southern Railway Limited GE/RT8030 requires that TPWS can be isolated, which can be achieved by isolating the whole AWS / TPWS. GE/RT8035 requires that AWS can be isolated independently from the TPWS, which cannot be achieved. Providing separate isolation would permit one system to be maintained if the other fails, while a unit is taken out of service. The Mk. 3 control unit does not permit separate isolation. Given that the Mk. 3 unit contains reliability improvements and that the Class 377/6 units will operate relatively short distances from depots (compared to freight locomotives or Intercity trains) there is not considered to be any significant impact from not providing isolation. 08/01/2014 N/A Rolling Stock 06/12/2013 Current 17/09/2012 N/A CCS 16/08/2012 Current Page 86 Deviations Register RGS Number GERT8030 RGS Issue Number Four RGS Title Requirements for the Train Protection and Warning System (TPWS) Certificate Number 12-128-DGN Title TPWS functionality on Class 377/6 fleet RGS Clause The deviation splits into a number of sections, all related to Appendix F of GE/RT8030 and one clause of GE/RT8035. There are a number of areas where full compliance is not achieved: · Enhanced Functionality - Identification of type of AWS/TPWS brake application: GE/RT8030 App. F - F.2.1.2/.3/.5, F.2.3.2/.3/.5-.9, F.2.4.1, F.3.4.1.6 · Enhanced Functionality Separate brake application acknowledgement and brake reset: GE/RT8030 App. F - F.2.8.1-.4, F.2.9.1-.3, F.3.3.2/.3, F.3.3.4.1-.5 · Audible Alerts and Warnings GE/RT8030 App. F - F.2.7.1.1-.7, F.2.7.2.1-.3, F2.7.3.1/.2/.5, F.3.4.1.2/.6, Appendix H · AWS Fault Handling GE/RT8030 App. F - F.3.4.1.3/.4 · AWS Power-up Test Fault Indication GE/RT8030 App. F - F.2.5.3 · Enhanced OTDR Interface GE/RT8030 App. F - F.3.5.1 · Control Unit Not Backward Compatible GE/RT8030 App. F - F.3.6.1 · Design and; Labelling of Existing Controls GE/RT8030 App. F F.2.6.5, F.2.10.1-.4/.6/.7 · No set-up per Unit GE/RT8030 App. F - F.3.6.2. Scope Class 377/6 (26 five-car trains / 52 cabs) plus a contract option for additional 40 vehicles. GERT8035 Two Automatic Warning System (AWS) 12-127-DGN AWS alarm audibility 2.6.4.1 b) Class 377/6 (26 five-car trains / 52 cabs) plus a contract option for additional 40 vehicles. GMRT2473 One Power Operated External Doors on Passenger Carrying Rail vehicles. 12-126-DEV Ready to start pushbutton texture / functionality. B8.4.2 Class 377/6 (26 five-car trains / 52 cabs) plus 40 additional Class 377/7 vehicles. GMRT2473 One Power Operated External Doors on Passenger Carrying Rail Vehicles. 12-125-DEV Doorway vertical throughway. B5.1.2 GKRT0044 One Controls for Signalling a Train onto an Occupied Line 12-123-DGN York Station Permissive Controls - Y205, Y211,Y213 Signals. 5.3.3 Current Deviations Register as at 09 May 2016 Nature and Degree There are two areas of impact from complying with the RGS requirements: · The manufacturing and validation timescales for compliant TPWS equipment do not meet the overall Class 377/6 programme and would lead to a project delay. · Achieving full compliance with the requirements would require a number of design changes from the Class 379 and Class 377/5 designs, on which the Class 377/6 design is based. These changes would have a significant impact on the project, and are likely to delay the project. Enhanced TPWS equipment is being manufactured by two suppliers, but both suppliers' equipment is still under development and testing. Delivery of the equipment is required in September 2012, which cannot be achieved. Full validation of the equipment would be required to support certification for on-track testing in May 2013. There is no assurance that suppliers' validation programmes will definitely achieve these dates. The Class 377/5 and Class 379 units were fitted with Thales Mk. 1 TPWS control units. Modifying these designs to achieve full compliance with GE/RT8030 Issue 4 would require: · Installation of a new control unit, which, depending on the supplier, may be To comply with this clause, it would be necessary to raise the volume of the AWS from that set for all other Class 377s. This would make the Class 377/6 units inconsistent and could cause complaints from drivers due to the AWS being uncomfortably loud. There would also be considerable cost with re-designing the AWS installation and re-validating the new volume. The new Class 377/6 units will operate alongside Southern's existing fleet of Class 377s, which are designed as follows: · The 'ready to start' pushbutton is not textured (and neither is the surround), because the control is located close to the textured 'door close' pushbutton at most locations. · The 'ready to start' pushbutton on the saloon guard's control panels is only active when all the passenger doors are closed. · The `ready to start' pushbutton in a cab will operate irrespective of the status of the passenger doors. Changing the design to comply with the RGS requirements would introduce inconsistency across Southern's fleet, and would prevent the `ready to start' pushbutton in the non-active cab from functioning. Complying with the RGS would also make the design inconsistent with the Rule Book, GE/RT8000/SS1, Station Duties and Train Dispatch, Issue 2. Risk Assessment/Safety Justification Applicant Organisation The partially-enhanced Mk. 3 control unit Southern Railway Limited will not achieve a number of functions and features required by Appendix F of the GE/RT8030 Issue 4. However, the proposed Class 377/6 design is considered to adequately manage the known risks and issues with TPWS, as summarised in document 3EER400017-1076. · Enhanced Functionality - Identification of type of AWS/TPWS brake application: Issue 4 requires that the cause of the AWS/TPWS brake application is identified to the driver. Additional indicators are required for this purpose. This function assists the driver in diagnosing the cause of a brake application when communicating with the signaller, and highlights when a SPAD has occurred. The proposed design will not have the enhanced DMI and will not identify the source of brake application, but will remind the driver to speak to the signaller, and will warn the driver that a SPAD may have occurred. If the driver contacts the signaller, it will be possible to determine if a SPAD has occurred. · Enhanced Functionality Separate brake application acknowledgement and brake reset: Issue 4 requires that separate actions are required to acknowledge the brake application and to The non-compliance is considered to have Southern Railway Limited no negative impact. Extensive testing and service experience has shown that the proposed level is effective and is tolerable for drivers. The safety of the railway is unaffected as, in the event of the driver failing to hear the audible indication and respond accordingly, the brakes automatically apply. Certificate Issue Date 17/09/2012 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 16/08/2012 Deviation Status Current 17/09/2012 N/A CCS 16/08/2012 Current The alternative actions are not considered to Southern Railway Limited have any adverse affect on safety. The proposed design increases the level of safety, as guards are already familiar with the design, and all passenger doors have to be closed prior to the guard giving the `ready to start' signal. When the guard is in the rear cab and the cab door is open, traction cannot be taken until the cab door is shut as the door interlock circuit will not be made. 08/01/2014 N/A Rolling Stock 06/12/2013 Current Class 377/6 (26 five-car trains / 52 cabs) plus 40 additional Class 377/7 vehicles. To comply with this clause would require the doorway to be enlarged by approximately 10 mm. This would require the car body design to be changed, and new structural validation of the car body design would be needed. Door header gear would have to be moved upwards and the door design altered. New interior trim would be needed for the new installation. This would add significant cost to the units. A door throughway height of 1900 mm (in Southern Railway Limited accordance with GM/RT2473) permits a 92nd percentile male to board the train without ducking. The proposed alternative action would result in a minimum door throughway height of 1880 mm, which permits an 87th percentile male to board the train without ducking. The nominal height of the throughway of 1890 mm permits a 90th percentile male to board the train without ducking. A door throughway height of 1880 mm permits a >99th percentile female to board the train without ducking. Note that, once the door threshold is passed, the minimum ceiling height is 2060 mm. While this deviation will be a minor inconvenience to those males above the 87th percentile height, we do not consider that this alternative has any safety or operational impact. All anthropometric data is taken from People Size 2008 and includes a 40 mm shoe correction. 08/01/2014 N/A Rolling Stock 06/12/2013 Current York Station; YORKSTH and YORKNTH1 SSI interlocking systems. Permissive routes as listed below, applying to Platform 11 as we;; as 9 and 10 for the Section 7 routes: · Y205(C)C1, Y205(C)C2, Y205(C)C3, Y205(C)D1, Y205(C)D2, Y205(C)E · Y207(C)A, Y207(C)B, Y207(C)C · Y211(C)C1, Y211(C)C2, Y211(C)C3, Y211(C)D1, Y211(C)D2, Y211(C)E · Y213(C)C, Y213(C)D · Y629(S)A, Y629(S)B, Y629(S)C. Adding the full controls to comply would need a significant extension to the SSI equipment as it is currently close to maximum memory capacity. The cost would be disproportionate to the safety benefits. Controls onto an occupied line are not Network Rail included in the original set of requirements to which controls in York Station interlocking systems are currently implemented. Existing arrangement have been in place for twenty-two years, while interlocking principles have been further developed, resulting in existing controls not being in line with current standards. A HAZOP workshop has been convened to assess risk of controls onto an occupied line not being provided in the interlocking. Based on the conclusions of the workshop, the severity of the non-compliance is low, since it is currently mitigated by Signal Box instructions, which reinforce provisions of Rule Book Module TS2 regarding permissive working. Only a violation of these rules would result in a potential collision situation. The risk of ARS action has been considered and the conclusion is that the risk is low. There is no precedent for such breach of regulations in York Station. The risk of not providing the controls listed in GK/RT0044 section 5. 3. 3 is also mitigated by the fact that all permissive movements at York station are timetabled and are non-passenger movements only that are used for the joining 18/09/2012 N/A CCS 16/08/2012 Current Page 87 Deviations Register RGS Number GKRT0045 RGS Issue Number Two RGS Title Lineside Signals, Indicators and Layout of Signals Certificate Number 12-122-DGN Title RGS Clause Stafford Station, flashing aspects for LS3585 5.2.3 Down Fast to Platform 3 MAY-FA. GIRT7033 Two Lineside Operational Safety Signs 12-121-DGN Platform Countdown Markers at _, « and ¬ mile on the approach to a station Section AK and B10, B10.1, B10.2, B10.3 and; B10.4 GMRT2000 Three Engineering Acceptance of Rail Vehicles 12-115-DGN Derogation against RGSs for UK Light Locomotive See details of RGS clauses in Annex 1. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-104-DGN Hackney Central - extension of existing ticket 6.2 hall along same plane to allow gate line extension Current Deviations Register as at 09 May 2016 Scope Stafford Station, LS3585 signal MAY-FA to Platform 3. Nature and Degree Compliance would either require one of the following options : MAR controls applied: stopping trains would take longer to clear the Down Fast into platform 3, which would be considered a worsening of the capacity/headway arrangements currently in place. Reduction of the Approaching EPS linespeed to 75mph: bringing EPS speed in line with table 23 (75 mph approach, 25 mph divergence). This would be a worsening of the Down Fast capacity/headway arrangements currently in place. 3 ) Increase the turnout speed from 25 mph to the 40 mph: bringing it in line with table 23 (85 mph approach, 40 mph divergence). This option had to be discounted due to track realignment restrictions at Stafford. Risk Assessment/Safety Justification Currently approaching Stafford station from the south, there is a flashing aspect sequence on the Down Fast with existing signal SD4-83 having an MAY-FA route into platform 3. The MAY-FA sequence was overlayed onto the existing signal arrangement within the last 10 years by the WCRM project. The addition of the sequence was to clear the Down Fast of passenger trains as quickly as possible. Operations have indicated to the Stafford Area Improvements project team that they would wish to retain this facility, as have Virgin Trains during signal sighting and consultation activities. The approach speed is 75/85EPS with a turnout speed of 25 mph. The predominant users of the MAY-FA sequence would be capable of driving to the 85 mph EPS speed, therefore the divergence speed is non-compliant with table 23. However, as the EPS capable trains have enhanced supervision and braking capabilities, it is felt that in this case exceeding the upper limit by 10 mph does not introduce any additional risks. The junction signal and flashing signals are to be located in identical positions to the current signalling arrangement. Exit signal (SC5591) has been moved by 24 m, further Network Rail Scotland Route. Network Rail and First ScotRail propose the Additional sign applicable to First ScotRail design of an alternate new sign not currently trains only. First ScotRail views the use of included in RGS GI/RT7033 as required by station approach markers as one of the section B10 of that RGS. First ScotRail (in measures for mitigating against station association with Network Rail Scotland overruns and instances of 'fail to call' where Route) is seeking ways to reduce station misjudgement is a factor. First ScotRail is overruns and instances of 'fail to call' where continuously reviewing its Professional misjudgement of braking distance is a Driving Policy and route learning factor. Sign AK102 allows for markers from documentation over affected routes to brief 300 m on the approach to a location (with locations that may be difficult to stop at. additional markers up to 600m if required). Detail below provides some relevant These signs are considered insufficient statistics from the Network Rail Wessex distance from the station to give drivers Route where overruns have generally advance information of a station that could reduced since the introduction of station be difficult to stop at. approach markers to provide a reference point for drivers to judge their braking. At locations where station approach markers are provided in other Network Rail Routes, some locations have seen a significant reduction in station overruns: · Chandlers Ford - Installed October 2005: No further station overruns · Whimple - Installed February 2006: Prior thirteen overruns, since one overrun (2008 - late braking) · Rowlands Castle - One station overrun in 2010 (driver forgetting station stop) · Liss No further overruns/SPAD's attributed to misjudgement · Only Earley continues to suffer station overruns (four in 2009, three in Diesel locomotives, known as UK Light, The UK Light locomotive will be compliant Use of the alternative actions are considered supplied by Vossloh Espa¤a S. A. for with the Technical Specifications for to deliver an equivalent level of control and operation by Direct Rail Services Ltd (limited Interoperability (TSI) requirements, including safety and will also not require any further to a maximum of 41 units). The UK Light the Locomotive and Passenger TSI. In ongoing actions or operational constraints. locomotive is based on the existing addition, it will be compliant with all EUROLIGHT design. applicable Notified National Technical Rules (NNTRs) to cover open points and specific cases, and ensure compatibility with the GB mainline system. It will also operate over off trans-European Network (TEN) routes and therefore the complete suite of RGSs is applicable. Within these RGSs, there are a significant number of requirements that are not directly related to TSI open points, specific cases or compatibility. These requirements have equivalent or comparable requirements within the suite of TSIs, therefore compliance with these RGS requirements duplicates the TSI assessment. Consequently, additional effort and cost will be expended both in respect of production of the evidence of compliance and in its subsequent assessment by the Designated Body. It is also possible that, due to the differences in the detail of the requirements, conflicts might exist that either prevent full compliance with both the TSI and RGS clauses, or necessitate a more complex design. Due to both the additional This non-compliance relates to horizontal Complying with the existing RGS The Risk Assessment undertaken by the clearance between the platform edge and an requirement will make it impossible to install LOROL Safety team identified that the extension to the existing building on Platform the urgently required ATG extension without current escape rates from the station are as 2 at Hackney Central station. The existing demolishing the existing wall interfacing with follows: Before ATG Installation: Booking building is to be extended on the same the platform, which would result in the Hall: 1650m wide; 132 persons per minute plane to enable the installation of an footprint of the ticket hall being reduced and Total: 132ppm, or 6. 76 minutes for 892 extended ATG gate line. The extension runs therefore worsening the overcrowding which passengers (Crush Loaded 378 Capitalstar). parallel to the platform and does not is currently witnessed on a frequent basis. In the worst case scenario of the evacuation encroach further towards the platform edge Crowding will be further worsened by the of a crush-loaded four-car train, the station than the existing building. The extended Access for All lift installation which is can be evacuated in 6. 76 minutes. The ticket hall and ATG array will ease crowding currently taking place at the station and installation of the new extended gateline significantly and improve passenger flows which will encourage additional mobility(which will be open first to last service) will around the station. impaired customers to use an already introduce an additional means of escape crowded ticket hall. with the existing side gate being brought into use as an emergency gate (on magnetic locking linked to the gateline EMO). Calculation of time it would take to evacuate a crush-loaded four-car train with the new layout is demonstrated as follows: After ATG Installation: Booking Hall: 1650mm wide, 132 persons per minute Platform 1 Side Gate: 1200mm wide; 96 persons per minute Total: 228ppm, or 3. 91 minutes 892 passengers (Crush Loaded 378 Capitalstar). Therefore, the introduction of the new gating array will have no negative effect on the evacuation from the station and will in fact improve evacuation times from those currently achievable. Applicant Organisation Network Rail Certificate Issue Date 05/09/2012 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 16/08/2012 Deviation Status Current Network Rail 29/11/2012 N/A CCS 16/08/2012 Current Direct Rail Services Limited 14/08/2014 N/A Rolling Stock 25/07/2014 Current Overground House 12/12/2012 N/A INS 14/11/2012 Current Page 88 Deviations Register RGS Number GMRT2400 RGS Issue Number Four RGS Title Engineering Design of On Track Machines Certificate Number 12-103-DGN Title RGS Clause Palfinger crane operators cab door lock and 3.22.1 b) and 3.6.2 window. GERT8082 One GSM-R Cab Mobile, Great Britain Open Interface Requirements 12-102-DGN Derogation against GE/RT8082 call quality requirements for GSM-R Radio installations using single handset Cab Audio Control Units. 3.9.1, 3.9.2, 3.9.3, 3.9.4, 3.9.5 and 3.9.7 GORT3413 One Provision of Information and Signs for Access on the Railway 12-100-DGN Signing of authorised access points to running lines. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-097-DGN Rochester Station (New) - Platform horizontal curvature. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-092-DGN Cardiff Central Station proposed Platform 8 - 2.1.2 170m 26c - 170m 34c, SWM2. Horizontal curve radius Current Deviations Register as at 09 May 2016 Scope Balfour Beatty's Plasser General Purpose TRAMM 98215 Nature and Degree Balfour Beatty is installing a new Palfinger crane in place of the original crane on the Plasser General Purpose TRAMM. To meet requirements of the standard, the company will expend money needlessly to replace original equipment supplied lock and glass in the crane access door. Due to the working methods implemented not meeting requirements of the clauses in the standard imports no increased risk to either network or operating staff. Use of the existing Whiteley/BTROS TD500 This deviation applies to the use of the handset or the equivalent replacement DAC existing handset (Whiteley/BTROS TD500) handset in place of a single GSM-R handset or equivalent replacement (DAC) in place of on the Class 357 Electrostar fleet operated a dedicated GSM-R handset on the Class by c2c. A standard GSM-R installation 357 Electrostar fleet, noting that the existing utilises a dedicated GSM-R handset for handset and CACU arrangement will not radio communication function. However, pass the test requirements in the clauses vehicles currently fitted with a single handset identified in section 6. will have their Cab Audio Communication Unit (CACU) modified to allow the existing single handset to work in conjunction with the GSM-R radio, thus maintaining the existing arrangement whereby all cab audio functions are managed through a single handset. It should be noted that the scope of this deviation is similar to that for derogations 09/285/DGN and 10/048/DGN, which also relate to the use of a single handset and CACU arrangement which cannot pass the test criteria as set out in section 6 above. Risk Assessment/Safety Justification Applicant Organisation Allowing the proposal to accept the standard Balfour Beatty Rail crane as built introduces no risk to staff or Renewals/Plant Development infrastructure. Certificate Issue Date 12/09/2012 Certificate End Date N/A Lead SC Plant Lead SC Approval Date 15/08/2012 Deviation Status Current There are no negative impacts of the Network Rail alternative actions. This is because maintaining the use of a single handset reduces the level of change effected by the introduction of the GSM-R radio to the Class 357 cab design, thereby maintaining current driver practice of controlling voice communications through a single handset. 31/07/2012 N/A CCS 12/07/2012 Current 2.1.3 and 3.1.3 National. The standard requires that all access points on Network Rail Managed Infrastructure are fitted with a sign. Other than access points on West Coast Main Line (WCML) and some other ad hoc areas, this is not the case. It is believed that this requirement was captured in Group Standards as a retrospective requirement following the example of the WCRM project, but that this was never affected in reality. A significant number of access points do not have signs and there is no intention to provide these signs. The cost of fitting signs at all access points has been estimated at œ10 million. The benefit cost ratio is estimated at 0. 18, such that a nationwide programme of fitment currently lacks a suitable business justification. Additionally, access points represent only a small proportion of the points of access to the network, which include level crossings and station platform ends. There is currently no requirement to sign these. Finally, the fitment of signs does not take account of the direction that Network Rail has set out through Project ORBIS, which is to provide information direct to the user via handhelds. A requirements capture form has been Network Rail completed by the Safety Change Leader for Project ORBIS, such that the information requirements referred to in Clause 2. 1. 3 are incorporated into the project for delivery via handhelds. Staff have alternative means to identify their location and track access is covered by a planning process The BCR for the fitment of signage across the network is not sufficient to justify a national programme of fitment with an estimated benefit cost ratio of 0. 18. 13/08/2012 N/A TOM 24/07/2012 Current 2.1.2 Rochester Station (New), Corporation Street, Rochester, Kent. It is proposed to provide a new threeplatform station at Rochester. The proposed platforms (1 and 2/3) are located on a curve with a radii of less than 1000 m. Platform 1 will serve the existing Up Chatham line (Upbound trains only) with a proposed linespeed of 30 mph. Platform 2 will serve the existing Dn Chatham line (bi-directional traffic) with a proposed linespeed of 30 mph. Platform 3 will serve a new Dn Rochester Loop (approx. 600 m long) and accommodate both passenger and freight services through the station. Linespeed is also proposed to be no more than 30 mph and is also proposed to provide bidirectional facility. Current track radii through the existing Up and Dn Chatham lines ranges from straight down to the tightest point of 347 m radii at 33 m 0608 yds on the Dn Chatham line. In addition to the platforms, a new bespoke station building will also be provided. It should be noted that the proposed platforms will have compliant stepping distances. It would not be reasonably practicable to provide a compliant solution. Relatively minor. · Platform 1 (Up Network Rail Chatham) minimum radius = 369 m: Working from the Country End to London End: 70 m compliant to GI/RT7016 (straight) into 30 m transition, into 70 m of 435 m radii, into 30 m transition, into 55 m of 369 m radii. · Platform 2 (Dn Chatham) minimum radius = 420 m: Working from the Country End to London End; 75 m compliant to GI/RT7016 (straight) into 30 m transition, into 120 m of 420 radii, into 30 m transition. · Platform 3 (Down Rochester Loop) minimum radius = 316 m: Working from the Country End to London End; 80 m compliant to GI/RT7016 (straight) into 30 m transition, into 30 m of 500 m radii, into 30 m transition, into 85 m of 316 m radii. The proposed platform solutions will have compliant stepping distances. The platform curvature has been subject to risk assessment involving an expert judgement panel including representatives from Network Rail and Southeastern. In summary, it was identified that hazards such as falling from platform onto track, and between platform edge and train would be mitigated in the same way as any other station, through appropriately designed platform waiting areas and circulation routes. The possibility Cardiff Central Station proposed Platform 8 - As part of the Cardiff Area Signalling Low. Stepping distances will be compliant, Network Rail 170m 26c - 170m 34c, SWM2. Horizontal Renewal (CASR) project, enhancement and Arriva Trains Wales station curve radius works will be undertaken at Cardiff Central management will be involved with the Station. This includes the construction of an positioning of TRTS/RA equipment. additional Platform (8) to serve the Valley Locating the proposed platform on a radius Lines network. This Platform will be 154 m below 1000 m will provide all rolling stock long and be located on a new track (Down with compliant stepping distances. Barry Loop) at 170 m 26c - 170 m 34c, SWM2. The geometric constraints of the site, the requirement to mate with the existing station buildings, and the characteristics of the railway infrastructure do not provide reasonable opportunity to provide a compliant solution. The horizontal alignment of the new platform will replicate the existing Platform 7 alignment with a compound curve with radii varying between 400 m and 790 m, with sections of the platform being on straight or above 1000 m radii. (Note that the stepping distances to the modified lengths of Platform 7 are compliant. ) 20/08/2012 N/A INS 11/07/2012 Current 07/08/2012 N/A INS 11/07/2012 Current Page 89 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 12-091-DGN Title Caerphilly Station. Structures located within the overrun risk zone. GERT8073 Two Requirements for the Application of Standard Vehicle Gauges 12-088-DGN Ecofret FWA(A) (twin outer) wagons with 1.2.7.6 and 2.1.2.5 SCT bogies and a 9'6'' high x 2500 mm wide container side wind loading for application to W10 gauge GMRT2000 Three Engineering Acceptance of Rail Vehicles 12-087-DGN Derogation for a Steam Railmotor Vehicle GIRT7016 Four Interface between Station Platforms, Track and Trains 12-086-DGN Finsbury Park Station - Extremity of Platform 7.2.1 5 extension to northern end, Down Slow 1 line, Country Bound GKRT0064 One Provision of Overlaps, Flank Protection and Trapping 12-083-DGN Reduced overlap on M499 signal at Holytown Junction Current Deviations Register as at 09 May 2016 RGS Clause 6.3.2.1 6.6.3 and Appendix H1 a) 4.2.1 Scope Nature and Degree Caerphilly Station. Structures located within The Cardiff Area Signalling Renewal the overrun risk zone. (CASR) Project involves enhancement works at Caerphilly Station. These works include the construction of a 150 m long bay platform (from the top of the ramp to buffer stop). It is proposed that the bay platform will terminate at a Friction Buffer Stop with a 7 m slide length. Canopy support columns will be located 12. 4 m behind the buffer face and an occupied station office will be located about 21 m from the buffer face. Thus the proposed arrangements do not comply with Clause 6. 3. 1. 1 of GI/RT7016. To achieve a minimum of 20 m clearance, the starter signal and new S & C (turnout and crossover) would have to be moved by 15 m towards the Country. This will have an impact on platform standage: based on 6 x 23. 710 m long carriages, plus 2 m stopping distance and 5 m for "inaccurate stopping distance" requires at least 149. 260 m length of platform. The platform would not therefore be long enough for its intended usage, but extending the platform would require the repositioning of S & C and affect the position of a RRV access point, thereby restricting maintenance activities. It is not therefore deemed practicable to provide a compliant solution. This derogation covers the Ecofret wagons The requirements for the W10 gauge from which are being introduced in service in GE/RT8073 appendix F show a second Autumn 2012. These wagons are dynamic gauge line that includes the effect configured as a `Twin set' consisting of two of a wind loading. Although the W10 and vehicles of car kind code FWA(A) outer, W12 gauges are shown with an additional design code IFE966. The wagons are fitted gauge for dynamic movements with wind, with SCT bogies and are required to carry 9' there is no information or other guidance 6'' high containers in the W10 gauge. given in either GE/RT8073 or GE/GN8573 on how to calculate the effect of wind on a vehicle, such that it can be compared against the relevant gauge line. Various sources of information were sought on this issue, but no one contacted at Network Rail, RSSB or other industry experts could shed light on the method to be used for this assessment. Therefore a reasonable approach was derived as follows by calculating the moment on the vehicle due to the wind loading using the methodology from GM/RT2142 issue 3 Resistance of Railway Vehicles to Roll-Over in Gales. Calculations have been carried out (see report Ecofret Gauging with Wind Calculation - calculation 170902C02A) based on the approach set out in section 9 of this certificate which show that the Ecofret FWA(A) (twin outer) wagons with SCT bogies are within the gauge lines for W10 gauge set out in GE/RT8073 Appendix F. Operation of the following preserved Steam It would not be practical to revise the RGS to Railmotor on lines, as agreed by the NRAB include steam powered vehicles, due to their and subsequently by the Licensed Operator. wide diversity of design from modern · GWR Steam Railmotor Number 93 · TOPS traction units and the general scarcity of No. 99093 · Painted No. 93 · Class / Power technical information now available to prove Classification 1P · Wheel Arrangement 0-4- their compliance or otherwise. In a number 0 + Bo · Maximum Speed 25 mph. of recent re-issues of RGS, specific exemptions for steam powered vehicles, shown in the previous issues, have been withdrawn, increasing the number of noncompliances for which derogation has now to be sought. Risk Assessment/Safety Justification Applicant Organisation It is not deemed to be reasonably Network Rail practicable to provide a compliant solution. Low. The low entry speed into the bay platform, coupled with signal protection, minimises the probability and consequences of an impact with the infrastructure located behind the buffer stop. The proposed CASR signalling system is designed to stop all nonfreight trains hitting the buffer stop. Based on 25 mph linespeed, the Signalling &amp; Control system (TPWS) will stop all nonfreight trains hitting the buffer stop. The control measures are designed to prevent any train impacting the building. The canopy is a "side" canopy, and the location under the side canopy can be fenced off to reduce any possible risk of passengers waiting in the overrun zone. Certificate Issue Date 01/03/2013 Certificate End Date N/A Lead SC INS Lead SC Approval Date 08/01/2013 Deviation Status Current It is suggested that the intention of GE/RT8073 is to use a mean side wind speed with an appropriate gust speed. 27/09/2012 N/A INS 11/07/2012 Current As indicated in Appendix 7 of this West Coast Railway Company 11/07/2012 document. The preserved steam railmotor Ltd is of a type that ran safely over the British Railway infrastructure since its introduction in 1903 and continued until its withdrawal from revenue service in 1935. The vehicle is intended for Heritage Operation only. In order to achieve compliance with RGS, the cost would be prohibitive and such engineering change would also destroy the vehicles fundamental nature and authenticity as a "heritage" vehicle. Making the vehicle compliant would, in many instances, be impractical because of the design of the vehicle and the location of the boiler and driving controls. The risk of SPADs is mitigated by the presence of two people in the cab. In addition, two data GPS devices will be installed, one in each cab. The moquette used for the seats was a previously approved railway material. Finsbury Park Station. Clause 7. 2. 1 The current capacity of Finsbury Park It would be impractical to provide a Network Rail 21/06/2012 Extremity of Platform 5 extension to northern Station is to be enhanced by the construction compliant solution. Low risk: see attached end, Down Slow 1 line, Country Bound. of extensions to Platforms 3 and 5, and the risk assessment. The substandard platform refurbishment and extension of platform 0/- width is limited to a 10. 5 m length at the end 1. The extensions will form 245 m long of Platform 5, and this area is unlikely to platforms. The width of the proposed experience peak passenger crowding. extension to Platform 5 will taper down to 1. 81 m; the usable length of the substandard width of platform is 10. 6 m. The width of the platform at the position of the last vehicle passenger door is 1. 91 m. Full overlap on M499 signal at Holytown The planned S & C Renewal at Holytown The signal is adequately sighted on a falling Network Rail 28/09/2012 Junction, Scotland. Junction will increase the overlap to 177 m gradient of 1: 117. The speed rises from 60 from the current 162 m. Options to achieve to 65 mph approximately 400 m before the compliance identified are: Movement of signal and after passing the previous signal. signal to make the overlap compliant would If the line speed remained at 60 mph, then a require full signal sighting and, due to site reduced overlap of 135 m would be conditions, the probable addition of a banner sufficient. The adjustment of the TPWS repeater, Redesign of the junction however reduces the risk of a SPAD reaching the this is not possible within the physical point of conflict and there is no history of confines without significant reductions in SPADs at the signal. An overrun risk speed, Extension of the overlap through the assessment has been undertaken and it has S & C which would impact on route capacity, been agreed that, rather than the enhanced Provision of a restricted approach (creating TPWS described, the relocation of the a restricted overlap) which would be existing equipment will produce similar unacceptable to the train operators, Reduce safety benefits. the speed on approach to M499 which would not be acceptable to operations. N/A RST 22/06/2012 Current N/A Infrastructure 16/05/2012 Current N/A CCS 14/06/2012 Current Freightliner Group Page 90 Deviations Register RGS Number GKRT0192 RGS Issue Number One RGS Title Level Crossing Interface Requirements Certificate Number 12-082-DGN Title Provision of protecting signal less than 25m from MCB-Obstacle Detector (OD) at Huncoat Station GKRT0192 One Level Crossing Interface Requirements 12-080-DGN GKRT0045 Two Lineside Signals, Indicators and Layout of Signals GIRT7016 Four Interface between Station Platforms, Track and Trains Current Deviations Register as at 09 May 2016 RGS Clause 2.1.1.3 Scope PN401 signal situated on the Up approach to Huncoat MCB-OD (Engineer's Line Reference FHR5 17 miles 36 chains). Nature and Degree As part of the East Lancashire Level Crossing Renewal Scheme, Huncoat MCB is being converted to MCB(OD). The current protecting signal in the Up direction is PN401 (located about 260 m from the crossing) slotted by Huncoat No. 6 lever. The signal is located prior to the station platform. The change to MCB-OD and the control of the area remotely leads to a preferred position of a protecting signal as close as reasonable to the crossing (to support the management of degraded working) and preferably between a station and the crossing to reduce road closure time. Positioning the signal 25 m from the crossing would place it in the vicinity of a passenger shelter which would need to be relocated and require either a bracket signal or the station entrance to be extensively modified. The extra costs of the work are estimated at œ150,000 for the extra platform extension and change to signal structure. Risk Assessment/Safety Justification Applicant Organisation The likelihood of a forward route not being Network Rail available is low and hence it is not considered that the potential for a SPAD is significant. There are benefits to the passengers of keeping the train stopping position closer to the entrance. The risk of a train approaching (and then passing at danger) the signal at red and entering a road crossing with road users still on the crossing are mitigated by the auto lower sequence being triggered when the train is on the approach to the crossing. An independent risk assessment has been undertaken for the Level Crossing and the report is attached. Certificate Issue Date 10/07/2012 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 14/06/2012 Deviation Status Current Provision of protecting signal less than 25m 2.1.1.3 from Brierfield MCB-Obstacle Detector (OD) level crossing PN552 signal situated on the Up approach to Brierfield MCB-OD Up Approach (Engineer's Line Reference GJC 24 miles 16 chains). The likelihood of a forward route not being available is low due to this being a single line and hence it is not considered that the potential for a SPAD is significant. There are benefits to the passengers of keeping the train stopping position closer to the entrance. The risk of a train approaching (and then passing at danger) the signal at red and entering a road crossing with road users still on the crossing are mitigated by the auto lower sequence being triggered when the train is 125 m from the crossing. An independent risk assessment has been undertaken for each Level Crossing and reports are attached. Network Rail 10/07/2012 N/A CCS 14/06/2012 Current 12-078-DGN Close Door and Right Away Indicators on platforms 2, 7 and 8 at Victoria Station. Appendix C, Section C.1.1 CD/RA Indicators on platforms 2, 7 and 8 at Victoria Station. N/A CCS 14/06/2012 Current Sutton Station Platform 3 and Platform 4 horizontal curves and minimum platform width. 2.1.2 and 7.2.1 b Sutton Station Platform 3 and Platform 4 horizontal curves and minimum platform width No alternative measures are planned as the Network Rail risks are considered to be mitigated by the controlled lighting levels within the station. It should be noted that the reading distance of these indicators is governed by the lighting conditions, the size of the characters and the visual acuity of train drivers. The 65 m distance is based on a worst case combination of lighting levels (which affect contrast) and driver eyesight (with the vast majority of drivers exceeding the minimum requirement). The arrangements have been supported by the Signal Sighting Committee. The controlled light levels within the station mean that the indicator is visible at 68 metres in the worst instance. The renewal of the CD/RA banner indicators is to provide operational improvements by allowing trains to be dispatched more efficiently. The sighting of the CD/RA banner indications was undertaken in conjunction with the re-sighting of the platform starting signals; the sighting of the latter will be greatly improved by this scheme as read across/read through was a known problem within the station area, and this has been eliminated with the new alignment and arrangement of signalling elements on the platform starting signals. It would not be reasonably practicable to Network Rail provide a compliant solution. Due to site constraints, such a solution would require substantial and expensive construction works to support deep cuts into the cutting slopes bounding the platforms, and the rebuilding of the station overbridge. Low severity. Passengers waiting for trains in the morning peak spread out along Platform 3. The station staircases to the platforms and the waiting room/canopied area are about half way along the platforms. Overcrowding at the Country ends of Platform 3 and 4 is therefore unlikely. Low risk to passengers: the station is not subject to crowding or congestion problems in normal circumstances. Compliant stepping distances will be provided. 10/07/2012 12-071-DGN As part of the East Lancashire Level Crossing Renewal Scheme, Brierfield MCB is being converted to MCB (OD). The current protecting signal in the Up direction is Brierfield No. 1 signal located prior to the platform. The change to MCB-OD and the control of the area remotely leads to a preferred position of a protecting signal as close as reasonable to the crossing (to support the management of degraded working) and preferably between a station and the crossing to reduce road closure time. Positioning the signal 25 m from the crossing would place it in the vicinity of a passenger shelter, and would require either a bracket signal or the station entrance to be extensively modified and the platform to be extended. The extra costs of the work are estimated at œ190,000 (extra signal structure costs and platform extension). At Victoria station, three CD/RA banner indicators on the terminal platforms 2, 7 and 8 will be outside of the 65 metres readability that this standard allows in certain circumstances: · VS3R(3)-CD-RA(3) will be 67 metres away from the driver of a two carriage train; · VS15R(4)-CD-RA(4) will be 66 metres away from the member of platform dispatch staff who uses the TRTS buttons; · VS17 will be 68 metres from the driver of an eight carriage train. Additional indicators could be installed, but the whole life cost, particularly in terms of installation and maintenance, is wholly disproportionate to the benefits. The platform would become extremely cluttered in certain locations where large numbers of commuters would be trying to exit the platforms. The driver and platform dispatch staff may also be distracted by too many indicators being in view conveying the same indication. In the case of VS3R(3)-CD-RA(3), new stop markers could be installed for a two carriage train on the approach to the buffer stops to seek compliance to the 65 metres readability. This solution would severely affect the platform's capacity by limiting the length of any train that would be able to share this platform with a two carriage train. Clause 2. 1. 2 requires platforms to have a minimum curvature of 1000 m. Clause 7. 2. 1b) requires a minimum 2. 5 m wide single face platform for adjacent line speeds of less than 100 mph. The Sussex Train Lengthening Project involves extending the platforms on the Sussex suburban route to accept ten-carriage length trains (from eightcarriage length trains). As part of this project, at Sutton Station it is proposed to construct a 42. 88 m long extension at the Country End of Platform 4, and a 36. 94 m long extension at the Country end of Platform 3. Due to site constraints, the useable platform width for both platforms is proposed to be a minimum of 2. 0 m on a curve radii of 475 m. Stepping distances will be compliant. The existing horizontal alignments through Platforms 3 and 4 are about 366 m and 376 m respectively. The proposed extensions are situated on an average radius replicating the existing horizontal alignments of the Up Wallington (Platform 3) and the Down Wallington (Platform 4) lines. 18/07/2012 N/A INS 16/05/2012 Current Page 91 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 12-070-DGN Title RGS Clause Reading Station Platforms 5 and 6: 6.3.1 and; 6.3.2 permanent new structures within the overrun risk zone. Scope Reading Station Platforms 5 and 6: permanent new structures within the overrun risk zone. Third rail DC electrification. Platforms used for South-West Trains services between Reading and London Waterloo and for First Great Western services to Gatwick. Platforms to be lengthened to accommodate twelve-car formations. Overall length of platforms is 285 m with an operational length of 265 m. Both platforms are fitted with friction grip sliding buffers and buffer stop lighting. TPWS buffer stop over speed protection is fitted. Approach speed into the platforms is 15 mph. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-067-DGN Cheam Station Platform 1: minimum width of 7.2.1 b) single-faced platform Cheam Station Platform 1: minimum width of single-faced platform. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-066-DGN Epsom Downs - single faced platform: 2.1.2, 7.2.1 platform on a horizontal curve and minimum width of the platform. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-065-DGN Wakefield Westgate Station - Up main platform; minimum platform width Epsom Downs - single faced platform: Clause 2. 1. 2 requires station platforms to platform on a horizontal curve and minimum be located on horizontal curves with radii width of the platform. less than 1000 m. Clause 7. 2. 1b) requires a minimum 2. 5 m wide single face platform for adjacent line speeds of less than 100 mph. The aim of the Sussex Train Lengthening Project is to extend the length of existing station platforms on the Sussex suburban route from eight- to ten-carriage platforms without reducing the number of trains able to utilise the route. Epsom Downs is a terminal station with a single line and single faced platform. The useable length of the platform will be extended by 45 m (at the London end) to 205 m. The extension is constrained by the boundary fence line and the need to maintain a public footpath to the rear of the platform. The existing platform and track alignment is to be maintained and the proposed platform extension at the London end is to be situated on curve of 720 m radius, and the width of the platform at its narrowest point will be 1. 8 m. Stepping distances are compliant. Because of the limited land available to the rear of the existing platform, it would not be reasonably practicable to provide a compliant solution: such a solution would require either an Order under the Transport Wakefield Westgate Station - Up main Wakefield Westgate Station consists of two platform; minimum platform width. single faced platforms serving the Up main and Down loop on the Doncaster to Leeds section of the East Coast Main Line (DOL2). The Up platform is to be extended at its Country (Leeds) end by 11. 346 m to accommodate ten-car IEP services. The line speed is 45 mph. Behind the platform is Wakefield Signalling Relay room, which is accessed via a pathway which runs at the back of the existing platform ramp. The pathway is formed by a large covered cable route (which carries a considerable number of signalling cables into the relay room), beyond which lies a large troughing route (which again forms part of the pathway and contains a considerable number of cables). Due to the presence of the existing cable route, it is not reasonably practical to provide a minimum platform width of 2500 mm. It is proposed to provide an extended platform with a width of 1. 9 m: this matches the width of the existing platform ramp that the extension will replace. Due to the constraints imposed by the existing cables, it would not be reasonably practicable to provide a compliant solution. Current Deviations Register as at 09 May 2016 7.2.1. b) Nature and Degree The columns to the existing canopies on Platforms 5 and 6 at Reading Station are located within the overrun risk zone. Due to site constraints these columns cannot be relocated without substantial reconstruction and reconfiguring of the platforms and track. The available overall width of the platform behind the re-positioned buffer stop with new canopy columns along the line of the previous columns is insufficient to allow the columns to be repositioned outside the overrun risk zone. This results in three of the canopy columns being located within the 5 m exclusion zone (within the Overrun Risk Zone). The distance from the projected centre line of the track to the centreline of the columns is 4641 mm on Platform 5 and 4946 mm on Platform 6 side. Platforms 5 and 6 are not of equal width. The original situation at the buffer stop ends of platforms 4A and 4B, prior to the RSAR project remodelling works, was non-compliant to Clause 6. 3. 1: the distance from the existing buffer on platform 4B to the escalator/stairs/lift machinery room behind the buffer was about 5 m, and the existing main station canopy roof columns were within the overrun risk zone behind platform 4A. Impact walls had been installed behind the buffers. The Clause 7. 2. 1 b) requires a minimum 2. 5 m wide single face platform for adjacent line speeds of less than 100 mph. Sussex Train Lengthening Project involves the extension of platforms on the Sussex suburban route (ELR: BTH2) to accept ten-carriage length trains (from eight-carriages). As part of this Project, at Cheam Station it is proposed to extend the useable length of Platform 1 on the London End by 28. 5 m (from 172. 5 m to 201 m); of which 5 m will have a compliant width of 2. 5 m and the remaining 23. 5 m length will have a minimum width of 1. 8 m. The existing horizontal alignment through Platform 1 is straight. Risk Assessment/Safety Justification Applicant Organisation Due to the constraints of the site, it would Network Rail not be reasonably practicable to provide a compliant solution. Details of the risks introduced by this non-compliance, and other options are described in the application. Low risk: the three columns behind the buffer stops are 359 mm within the exclusion zone on Platform 5 side and 54 mm within for Platform 6 side. The risk of an overrun resulting in an impact by rolling stock on a canopy column is considered to be very low. Certificate Issue Date 01/06/2012 Certificate End Date N/A Lead SC INS Lead SC Approval Date 16/05/2012 Deviation Status Current It would be impracticable to provide a Network Rail compliant solution. Low severity. Passengers waiting for trains in the morning peak spread out along the platform. The station entrance is at the opposite end of the platform, with the waiting room and canopied area about half-way along. This is a lightly used station, and the risk to passengers generated by the sub-standard width of the platform is deemed to be acceptable. 07/08/2012 N/A INS 16/05/2012 Current Low severity. This station is lightly used. Network Rail Passengers waiting for trains in the morning peak spread out along the platform. The station entrance is at the opposite end of the platform, with the waiting room and canopied area about half way along. Epsom Downs is a lightly used station and the risk to passengers generated by this deviation is deemed to be acceptable. Compliant stepping distances are provided along the platform extension. 13/09/2012 N/A INS 16/05/2012 Current The risk to passengers generated by the Network Rail non-compliance is deemed to be acceptable. The Up platform is to be extended by 11. 346 m at the Country end at a substandard width of 1. 9 m. This will be at the rear of the train in the normal direction of travel and will only impact upon the rearmost door of the final carriage. This would be positioned 4 m from the end of the platform extension with the train position at the stop board. The platform length has been determined using normal 5 m stopping tolerances - a 1 m overshoot and 4 m undershoot to the stop board position. It is anticipated that passenger numbers wishing to board or alight from the affected door will be low. Wakefield Station is the first stop for Leeds to London services. The affected door is both at the furthest point from the entrance to Wakefield station and at the London terminus and should not attract significant numbers of passengers. Similarly, any commuters making the 12 minute Leeds to Wakefield journey are unlikely to occupy the platform extension as it is at the furthest point from the station exit. The restriction will only impact upon ten-car IEP services. The existing platform is of sufficient length for all other current 07/08/2012 N/A INS 16/05/2012 Current Page 92 Deviations Register RGS Number GMRT2142 RGS Issue Number Three RGS Title Certificate Number Resistance of Railway Vehicles to Roll-Over 12-063-DGN in Gales Title RGS Clause Resistance of Railway Vehicles to Roll-Over 2.1.1.1 b) in Gales - FXA Wagon to Carry 60' long x 9'6" high containers. Scope FXA wagons carrying 60' long x 9'6'' containers. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-062-DGN Arlesey station: Up slow platform - items 6.5 located less than 2000 mm from the platform edge. Arlesey station: Up slow platform - items It is proposed to extend the Up slow platform located less than 2000 mm from the platform at Arlesey Station on the East Coast Main edge. Line by 80. 5 m to accommodate twelve-car Thameslink services to and from London Kings Cross. The width of the extended platform is 3. 0 m. OLE E59/14 is located within the Up cess 37. 0 m from the proposed Country end of the extension. The mast lies within the footprint of the proposed extension and supports a headspan crossing all four tracks of the East Coast Main Line from which is suspended the 25kV OLE. All lighting columns and other signage within the extension will be positioned not less than 2. 5 m from the platform edge. To the rear of the proposed platform is the existing station car park. An Armco barrier will be used to protect the platform from vehicular collision. The line speed on the Up slow line is 80 mph. GMRT2000 Three Engineering Acceptance of Rail Vehicles 12-059-DGN Derogation for Ex. London &amp; North 6.6.3 Eastern Railway K4 Class 5P6F 2-6-0 steam locomotive TOPS No. 98642 `The Great Marquess'. Operation of the following preserved Steam Locomotive on all lines, as agreed by the NRAB and subsequently by the licensed operator: Ex. London and North Eastern Railway Class K4 TOPS No. 98642 Painted No. 61994 Name: `The Great Marquess' Power Classification: 5P6F Wheel Arrangement 2-6-0 Maximum Speed 50 mph / 45 mph tender first. GKRT0045 One Lineside Signals, Indicators and Layout of Signals 12-058-DGN Flashing aspects on the approach to TN4917 signal, Beeston near Nottingham Current Deviations Register as at 09 May 2016 5.2.3.1 Nature and Degree Non-compliance to minimum acceptable intrinsic roll-over wind speed for FXA wagons carrying 60' long x 9'6" high containers (Equivalent to three 20' or a 20' plus a 40' containers). The FXA wagon is a reduced deck height version of the FCA/FYA wagons allowing transit of 9'6" high cube containers in W10 gauge. To comply to the minimum acceptable roll-over wind speed of 30. 8 m/s as stipulated in GM/RT2142 Issue 3, it would not be possible to transport 60' long of 9'6" high containers, unless the wagon speed was limited to 45 mph in the tare condition (60' long of 9'6" empty containers); this would restrict the use of the wagon to transport empty 9'6" containers, resulting in a loss of business. Steam locomotives are in a minority group and subject to the restrictions in GM/RT2000 for "Heritage Vehicles". This preserved steam locomotive is of a type that ran safely over the London North Eastern Railway and British Railways infrastructure since their introduction in 1936, and continued until withdrawal from revenue service in 1961. Locomotive 61994 entered service in July 1938 and withdrawn in December 1961. The locomotive is intended for heritage operation only. In order to achieve compliance with RGS, the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage vehicle". Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. The following list summarizes the Railway Group Standards where K4 class steam locomotive 61994, `The Great Marquess', does not meet the requirements, either wholly or in part, or where sufficient data is unavailable to prove or disprove compliance. Where no reference is made to a Railway Group Standard, the locomotive is considered compliant. RGS numbers: GE/RT8014 Iss Flashing aspect sequence on approach to Compliance would require the provision of Signal TN4917 located near Beeston, routes approach release from red on TN4917 C(M) TN4917 C(M) and E(M) read on to the Down &amp; TN4917 E(M) routes, which would and Up Nottingham Slow lines respectively. further reduce the speed of freight trains adding a significant delay to clearing the Down and Up Nottingham lines on this busy route, thereby reducing freight capacity. The cost of this delay will vary between œ0. 00 (no delay) to œ109. 15 per minute per train for EMT Passenger Trains. There is also the risk that freight trains may need to accelerate after the signal clears. Risk Assessment/Safety Justification The FXA wagon has been compared to the FEA (B) type wagon; the wagons have similar side area and reference height. However, the FXA tare weight is greater by 4. 8 tonnes. During the process of comparing the FXA to the FEA wagon, a query relating to minimum acceptable intrinsic roll-over wind speed of 30. 8 m/s was discussed with RSSB, who advised that research project T961 was underway to examine non compliances to GM/RT2142 Issue 3. Following recommended actions arising from the RAIB report into the detachment of containers in strong winds at Hardendale and Cheddington, the FEA (B) wagon was reviewed and found not to comply with requirements of GM/RT2142 Issue 3. More recently, calculations were produced for a new build of coal hopper assessed against GMRT2142 Issue 3, which also showed that the wagon was noncompliant. Calculations undertaken on the same vehicle to GM/RT2142 Issue 2 gave a compliant result with some margin. These results raised concerns regarding the acceptance limit within GM/RT2142 Issue 3 which resulted in research project T961 `Investigation of freight vehicle aerodynamic performance in accordance with Given the minor degree of non-compliance, the risks involved during construction works, the increase in risk of collision from vehicles were the mast to be relocated and the associated costs of the works, it is not considered reasonably practicable to relocate the mast. Mast E59/14 is positioned 37. 0 m from the proposed country end of the extended Up (slow) platform at a distance of circa 1965 mm from the proposed platform edge which is 35 mm less than 2000 mm required for an isolated column. The restriction will only affect passengers boarding the rear two carriages (Four passenger doors) only of any twelvecar services using the platform. The minor severity of the non-compliance to mast E59/14 (up side) is mitigated by the virtue that its position is towards the northern end of the platform and will affect only the trailing two carriages of twelve-car services. Given that the area of platform beyond the restriction affects the rear of the train, remote from the station entrance at Arlesey and also from the terminus exit at Kings Cross, passenger numbers passing the restriction point will not be high. As a London commuter station, during the worst case (am) peak for the Up direction, A fundamental part of the business portfolio of DB Schenker (UK) Ltd is the operation of the steam locomotive hauled Special Train services that were vested into rail express systems on the privatisation of British Rail. The planned operation of K4 locomotive 61994 in North East Scotland during May 2012 forms a key part of an eight-day steam hauled tour of Great Britain. This is a very costly operation for the promoter and DB Schenker. The choice of locomotive takes into account the fact that the DB Schenker already authorised steam locomotives are too heavy for the Inverness to Kyle route. It is of note that the planned operation will satisfy the Maximum Loading Table for the route, as set by the DB Schenker Engineer and Operations Standards Manager and agreed with Network Rail. The operation will be vacuum-braked from Inverness northward and the selected DB Schenker footplate crew will receive refresher training prior to the operation. The following contingences and initiatives will be in place: · Dual-braked class 37 locomotive will be standing by at Inverness · Through air pipe has recently been fitted and tested on locomotive 61994 · DB Schenker FTR Examiner will carry out additional functional The use of flashing aspects MAY-FA on this section of railway approaching the Down and Up Nottingham Slow lines would be a benefit as it will give freight train drivers the earliest possible indication that they are being signalled into the loops clear of the main line. This will allow drivers of trains signalled onto the slow lines to regulate their speed more effectively, thus reducing any delay to following services. This method of signalling has been introduced at the request of the Operations Department to prevent any possible delay, as this section of line caters for seven trains per hour. The compliant solution is to provide approach release from red, which was discounted due to the need to reduce the speed of freight trains when approaching the junction with the potential to then accelerate towards the junction. The diverging speed on the routes on to the Up and Down Nottingham Slow lines are the same at 25 mph, and therefore the drivers' expected actions are the same for both routes and reduces the SPAD risk from anticipation. The approach at this junction is consistent with the signalling controls provided at other junctions within the East Midlands Signalling Renewal area and future proofs against the junction being Applicant Organisation DB Schenker Rail (UK) Ltd Certificate Issue Date 07/06/2012 Certificate End Date N/A Lead SC RST Lead SC Approval Date 25/05/2012 Deviation Status Current Network Rail 28/06/2012 N/A INS 16/05/2012 Current DB Schenker Rail (UK) Ltd 16/05/2012 N/A RST 27/04/2012 Current Network Rail 28/05/2012 CCS 17/05/2012 Current Page 93 Deviations Register RGS Number GKRT0192 RGS Issue Number One RGS Title Level Crossing Interface Requirements Certificate Number 12-055-DGN Title RGS Clause Position of Signal T894 at Littlehaven station 2.1.1.3 less than 25m from level crossing edge. Scope Signal T894 located at the Up end of platform 1 at Littlehaven station controlled from Three Bridges. Nature and Degree Signal T894 is currently positioned 25 m from the crossing edge. However, the crossing is being upgraded from manned gates to manned gates remotely monitored by CCTV. In order to bring the roadway and associated footpaths into compliance, the edge of the crossing needs to be moved approximately 3 m closer to the protecting signal. Repositioning the signal would require a re-evaluation of the stopping position of trains in the platform, an extension to the platform and construction work in the vicinity of the signal to allow passenger access and exit at considerable cost compared to benefits. The sole passenger access to the platform is from the roadway adjacent to the level crossing and up the platform ramp past the signal. GKRT0041 One Track Circuit Block 12-054-DGN Provision of alternative emergency alarm between fringe signalboxes during stageworks on Modular Signalling projects. 6 Modular Signalling is designed to be deployed on secondary routes which cannot justify conventional power signalling due to low density traffic patterns and rural business. These will generally be classified no higher than a Conventional TENS route and typically unclassified. This application is generic in nature for modular schemes where the modular signalling will be introduced in stages with temporary fringes. Initial deployment will be on the pilot route of Ely to Norwich, specifically at Harling Road. It is technically possible to provide an emergency alarm between the control centre for the modular signalled area and the adjacent box, however the fringe is typically in use for a few weeks and, therefore, the costs and risks associated with providing a communications link and the temporary alterations to both signalling centres is disproportionate to the risks being managed. GKRT0045 Two Lineside Signals, Indicators and Layout of Signals 12-051-DGN Use of "X" indication on Signal SN132 for main class route at Old Oak Common. 2.3.2.5 GKRT0051 One Single Line Control 12-049-DGN Non provision of separate replacement facilities on PN254 and PN257 distant signals at Preston (Bare Lane) Part H, clause 6.6.4 GKRT0075 Two Lineside Signal Spacing and Speed Signage 12-043-DGN Non provision of AWI boards between Elephant &amp; Castle and Blackfriars 3.3.1.4 Current Deviations Register as at 09 May 2016 Risk Assessment/Safety Justification Applicant Organisation The objective of the distance between the Network Rail protecting signal and the level crossing is understood to be to provide sufficient time for the crossing system to respond to a SPAD at the protecting signal and provide a warning to road users, hence reducing the risk that a train will collide with a road user/vehicle. The controls proposed (often referred to as Stowmarket controls) cause the crossing sequence to commence as the train approaches the signal at red. In normal circumstances, by the time the train has stopped in the station and completed station duties, the signaller will be able to set the forward route and operate the crossing clear control. This will provide no appreciable delay to road users and reduce the length of the time the crossing is closed, as opposed to requiring the crossing closed prior to an approach to T894. This proposal has been reviewed and Network Rail agreed with the Network Rail Operations Principles and Standards Manager, a representative of the Network Rail Professional Head of S & T Engineering and a representative of the Network Rail Professional Head of Ergonomics as part of the development of a method of temporary fringe working for Modular Signalling schemes (minutes attached). The ethos of a Modular Signalling scheme is for the period between staged commissioning's to be short, as the short durations of the commissioning periods allow track access to be obtained more easily than for a traditional resignalling. It is not intended that a period of temporary fringe working will exceed two weeks, but it is recognised that, exceptionally, a duration longer than this may be necessary. This extended situation has also been reviewed with the OP & S Manager, and the representative for S & T Engineering and Ergonomics. T hey agreed that the use of mobile phones for extended periods in the context of a lightly used line did not present an unacceptable risk. The first application, at Harling Road on the Ely Norwich route will be for a period of approximately five months. All level Signal SN132 , Engineers Line Reference The project proposes to use the single No change in overall risk to the operational Network Rail MLN1 approx. 2¬ miles. character 'X' indication in a standard railway - more risk (driver confusion) is likely indicator for main route SN132C(M). SN132 to be introduced if other indications are used is on the Carriage Line. This route is not to achieve compliance with current standard. towards a limit of shunt, but is for wrong Non-compliance has been granted for direction moves up to the Down Relief Line several similar SI "X" indications on this main aspect signal SN126. The position of project and others. The indications to this signal is cramped due to it being drivers in this area have been considered sighted under a bridge and in the space and agreed by the TOC/FOC between two lines. The Signal Sighting representatives. These indications present Committee has asked for the signal to be the least possible confusion to drivers and mounted at circa 2 m height. This is to that 'X' is commonly used to indicated routes make it distinguishable from signal SN134 to 'Wrong Direction' signals. Nonon the UR. PLJI and double character compliance to clause 2. 3. 2. 5 c) will not indicators have been considered; they don't reduce the safety of the signalling system. fit at proposed height. The other main route All main aspect routes from SN132 are the on this signal is towards the Up Relief Line same speed which is 25 mph. The next for which "U" is proposed. "R" would not be signal ahead on the main aspect routes is at appropriate for up moves on the DR 527 and 537 m from SN132. They are fitted because "R" is normally used for moves on with TPWS and GW ATP. the right direction Relief Line. "D" is used for the Depot Line on other signals within 200 m of SN132. Preston (Bare Lane) Signals PN254 and The two track signalling arrangements Replacement of the Distant signals due to Network Rail PN257 between Bare Lane and Morecambe are lamp failure in the associated Stop signals unusual in that both lines are independent would be provided for automatically within single lines designated Up &amp; Dn the interlocking. These signals are distant Morecambe and Up &amp; Dn Heysham. signals reading up to Stop signals protecting The Up &amp; Dn Morecambe is currently Bare Lane MCB (CCTV) level crossing. No controlled under One Train Working risk has been identified which would be (Without Staff) arrangements with sequential mitigated by the provision of separate Track Circuit operation. The Up &amp; Dn replacement facilities. It is considered that Heysham is currently controlled under One the requirement to provide a separate Train Working (With Staff) arrangements replacement switch does not offer any with sequential Track Circuit operation. significant reduction in risk. Under the proposed scheme, both single lines will become One Train Working (Without Staff). The proposed works include conversion of the Up Distant Signals PN254 and PN257 to worked colour lights from the existing Distant Marker Boards. Both signals shall repeat the Stop Signals protecting Bare Lane LC (PN262 and PN259 respectively). During development, the requirement to provide replacement facilities for PN254 and PN257 was discussed, with reference to GK/RT0060 - Interlocking Principles, Clause C. 7. 4 - Control of Distant Signals, Paragraph 2, which states: "A replacement switch shall also be provided for distant signals reading from absolute block sections or where reading up The sections of Up Holborn Fast and Up The placement of the Advanced Warning It is not considered appropriate for the Network Rail Holborn Slow between Loughborough Indicators would position them either in front introduction of AWI boards between Junction and Blackfriars Junction where the of a signal or between an AWS and its Elephant &amp; Castle and Blackfriars as speed reduces from 60 mph to 50 mph to 40 signal - both of which are not permitted. It the project believes the standard has been mph to 30 mph. would also not be possible to provide written around higher line speeds where compliant AWS magnets if these were their application would be more beneficial. required. This would increase clutter and On the Thameslink Programme, the signals potential driver confusion thus reducing are closely spaced and compliance with the driveability. standard would breach the signal sighting standards. The project believes that there no additional risks by not installing the AWIs, as the current route does not have any fitted today with virtually the same speed profile. The current speed reduction / signage have been employed on the route between Loughborough Junction and Blackfriars Junction for many years and the Thameslink resignalling does not fundamentally amend the speed reduction within the short section. Given the risk to signal sighting standards, the project believes retention of the current practice is applicable in this situation. Certificate Issue Date 03/05/2012 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 19/04/2012 Deviation Status Current 03/05/2012 N/A CCS 19/04/2012 Current 03/05/2012 N/A CCS 19/04/2012 Current 03/05/2012 N/A CCS 19/04/2012 Current 10/04/2012 N/A CCS 22/03/2012 Current Page 94 Deviations Register RGS Number GMRT2483 RGS Issue Number One RGS Title Visibility Requirements for Trains Certificate Number 12-039-DGN Title RGS Clause Scope Use of TSI/EN Compliant Head, Marker and C2.1 C2.3.1 C2.4 Appendix 3 Tables 2, 4, 5, Use of Interoperable Constituent head, Tail Lights on non-TENS Routes 8 and 10 Appendix 4 Table 11 marker and tail lights complying with the CR Locomotive and Passenger TSI and EN15153-1 on Harsco Model C rail grinders for operation on the GB network non-TENS routes. Vehicles affected: DR79266/DR79276 to DR79268/DR79278 inclusive. GIRT7016 Four Interface between Station Platforms, Track and Trains 12-038-DGN Clapham Junction Station Platform 1 - Buffer 6.3.2.1 stop overrun risk zone GKRT0045 One Lineside Signals, Indicators and Layout of Signals 12-037-DGN Non-provision or route indications for straight routes on VS1230 and VS1268 at Blackfriars. 5.1.2.4 GMRT2000 Three Engineering Acceptance of Rail Vehicles 12-036-DGN Derogation for a Steam Locomotive The clauses against which non-compliances Operation of the following preserved Steam are sought can be found in Appendix 2 of Locomotive on all lines, as agreed by the this document. NRAB and subsequently by the Licensed Operator. LMS Black 5 steam locomotive no. 44767 `George Stephenson'. TOPS No. 98567 Painted No. 44767 Class / Power Classification 5P5F Wheel Arrangement 4-60 Maximum Speed 60 mph. GIRT7033 Two Lineside Operational Safety Signs 12-034-DGN Utilisation of miniature permanent speed indicator for Urlay Nook Up 60 mph PSR Appendix A, Section AD: Sign AD01m Current Deviations Register as at 09 May 2016 Nature and Degree The previous light designs, which comply with Group Standards, are not compatible with the requirements of the CR Loc & Pas TSI or EN 15153-1: 2007. The head, marker and tail lights designed to meet the requirements of the TSI (for running on GB TENs routes) and EN 15153-1: 2007, which have been certified as Interoperable Constituents, do not comply with GM/RT2483. The design and manufacture of a lights which comply with GM/RT2483 and the CR Loc & Pas TSI is uneconomic for a small quantity of vehicles. There is no space on the vehicle end for installation of two sets of headlights. Switching from one type or performance of headlight to another when transferring from TENs to non-TENs routes (or vice-versa) would be confusing for operators. The headlight flashing requirements in EN 14033-1 differ from GM/RT2483. Risk Assessment/Safety Justification Applicant Organisation Head, marker and tail lights complying with Harsco Rail Ltd the requirements CR Locomotive and Passenger TSI are now required to be installed on new rolling stock for operation on GB TENs routes, I. e. the majority of higher speed lines including WCML, ECML, MML, GWML etc. (Head, marker and tail lights which comply with EN15153-1: 2007 also comply with the CR Loc & Pas TSI). However, the requirements of the CR Loc & Pas TSI, EN 15153-1 and EN 14033-1 differ from GM/RT2483 in the following respects with relevance to the Harsco EU rail grinder type (which is limited to 60 mph): · C2. 1 and C2. 3. 1 (c) and (d): The TSI/EN lighting arrangement of two lower head lights with full/dimmed headlight differs from the day time and night time headlight arrangement specified in GM/RT2483. · C2. 4: EN 14033-1 requires an alternate headlight flash function with a frequency of 2Hz, whereas GM/RT2483 specifies 40 cycles +/-10% per minute synchronised. · Tables 2 and 5: The GM/RT2483 maximum day and night time headlight luminosities in the vertical plane above 2 degrees up are not specified in the CR Loc & Pas TSI or EN 15153-1 and, therefore, are not required parameters for the TSI/EN headlights. The Buffer stop at terminal end of Platform 1 at To facilitate improvements to the A buffer stop risk assessment has been Network Rail Clapham Junction Station. Signal W304. environment on Platforms 1 and 2 at undertaken in accordance with GC/RC5633 Existing Platform 1 canopy columns. Clapham Junction Station a number of and GI/GN7616 to support this application. interventions are proposed by Network Rail The Estimated Weighted Equivalent (funded by Transport for London). This Fatalities (EWEF) figure per 100 years will includes the relocation of the buffer stop at increase by a small amount as a result of the the terminal end of Platform 1. The aim of proposed relocation and remains below the this proposal is to: Reduce the interchange 0. 03 lowest threshold. Based on the distance between East and West London numerical risk-assessment method Line trains stabled on Platform 1 and 2 described in GC/RC5633 , relocating the respectively. Encourage more passengers train stop position on Platform 1 will have a disembarking from West London Line negligible impact upon the Estimated services on Platform 1 to use the footbridge Weighted Equivalent Fatalities (EWEF) for cross-platform interchange. Equalise the figure per 100 years. The benefits split of passengers using the two sets of associated with more evenly distributing stairs down to the subway and the station passengers between the stairs down to the exit below. The London end staircase is subway and encouraging more use of the currently more congested as a consequence footbridge to cross between platforms rather of the existing train stop position. A than the subway will reduce the probability derogation is sought to enable the relocation of crushing injuries to passengers at peak of the buffer stop to be in a position 10 m times. from the terminal end of the platform. This will introduce Signal W304 into the overrun risk zone, 13 m from the buffer face (a single post signal structure mounted on the London end of Platform 2). Achieving compliance would require the recently constructed signal W304 on the end of Platform 2 to be reconstructed away from the platform end. Signals VS1230 and VS1268 are the Outer It is proposed to relax this condition for The approach to Blackfriars Bay Platforms Network Rail Home Signals to the approach to Blackfriars signals VS1230 and VS1268 at Blackfriars, reduces to 20 mph and the signals are New Bay Platforms. The line speed has where the provision of an indication for all within the high capacity core area. reduced from 30 mph to 20 mph at these routes would lead to confusion to the drivers. Therefore, the drivers are approaching more signals, and all movements (straight or Southeastern Trains considered that the cautiously and with route knowledge; there diverging) are also at 20 mph. provision of a straight ahead route indication should be no ambiguity to the routing of the would lead the driver to believe the route train. The signals in question are fitted with was available right into Blackfriars Bay SRIs as a recommendation by the signal Platforms with the potential to disregard sighting committee, and the legends signals VS1266 and VS1228. Although the displayed were accepted by all new Blackfriars layout does resemble the representatives of that process. The final / current London Bridge approaches, the overall Thameslink scheme plan (without TOCs are concerned the straight ahead these indications) was subjected to the SAT route indication will make the signals in / DA process with no issues identified. The advanced multi SPAD signals. project feels the current standard has been incorrectly written and does not allow for the non-indication of straight ahead routes which were allowable in previous standards. It would not be practical to revise the RGS to include steam locomotives, due to their wide diversity of design from modern traction units and the general scarcity of technical information now available to prove their compliance or otherwise. In a number of recent re-issues of RGS, specific exemptions for steam locomotives, shown in the previous issues, have been withdrawn, increasing the number of non-compliances for which derogation has now to be sought. The scope of the derogation is limited to the A replacement 60 mph Permissible Speed proposed new 60 mph PSI at 7 m 12 chains Indicator (PSI) Sign AD02m (450 mm x 450 (SSF DSN1US712U) on LER DSN1 for mm) has been proposed for project 115545 Urlay Nook. (Urlay Nook Re-control to Bowesfield) by the Signal Sighting Committee at the position of, and fixed to, the post of proposed new B963 signal to comply with GE/RT8037 clause C1. 5 in preference to the requirement with GI/RT7033 Appendix A which specifies the use of Sign AD01m (900 mm x 900 mm). GE/RT8037 clause C1. 5 states "Lineside signs, required to be observed by a driver for the purpose of controlling the train, shall be positioned so as not to create unnecessary distraction from the driver's primary role of observing signals. So far as is reasonably practicable, signs shall not be positioned between the signal and its associated AWS or within 50 m beyond the signal. If the sign has AWS equipment associated with it, the sign shall be positioned such that the AWS for the sign does not fall between the signal and its AWS equipment. Where this is not achievable, the sign shall be positioned at the signal and consideration shall be given to the size, lateral position and reflective properties to ensure that all the information displayed is proportionate and that no part is so Certificate Issue Date 21/03/2012 Certificate End Date N/A Lead SC RST Lead SC Approval Date 15/03/2012 Deviation Status Current 11/04/2012 N/A INS 07/03/2012 Current 19/04/2012 N/A CCS N/A Current As indicated in Appendix 7 of this West Coast Railway Company 05/04/2012 document. The preserved steam locomotive Ltd is of a type that ran safely over the British railway infrastructure since its introduction in 1947 and continued until its withdrawal from revenue service in 1967. The locomotive is intended for Heritage Operation only. In order to achieve compliance with RGS, the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. N/A RST 16/03/2012 Current It is not deemed practicable to provide a Network Rail 900 mm x 900 mm AD01m sign at signal B963, as the additional cost to locate the PSI in a position that avoids unnecessary distraction from the driver's prime purpose of observing signals will be disproportionate to the benefit gained. The practice of using Sign AD02m in this circumstance is widespread across Network Rail infrastructure with no known reported issues when used as a PSI for an increase in permissible line speed, and meets the requirements within 'Signal Positioning and Visibility' Clause C1. 5 and associated guidance within GE/GN8537. The risk of the 60 mph PSI being misread leading to a train travelling at incorrect line speed is low because the readability requirement of minimum 4 seconds within GI/RT7033 AD01m is exceeded at the approach speed of 50 mph (89 m at 50 mph). Additionally, if the sign is not read, it will result in a train travelling at 50 mph rather than the permitted 60 mph, although driver route knowledge should mitigate the likelihood of this occurring. There are no level crossings or speed dependant signalling infrastructure that would be affected by a train travelling at less than permissible line speed. N/A CCS 22/03/2012 Current 10/04/2012 Page 95 Deviations Register RGS Number GMRT2161 RGS Issue Number One RGS Title Requirements for Driving Cabs of Railway Vehicles Certificate Number 12-032-DGN Title Fitment of GSM-R - Steam Locomotives Operated by Applicants that are mainline operated RGS Clause 7.2.1 (j) Scope The scope of the deviation is to include the following Steam Locomotives operated by the applicants that are Mainline Registered: TOPS No. / BR No. : 98429 / 75029; 98466 / 9466; 98476 / 76079; 98536 / 4936; 98549 / 4965; 98564 / 61264; 98572 / 5972; 98577 / 30777; 98605 / 62005; 98625 / 30825; ; 98642 / 61994; 98690 / 5690; 98713 / 70013; 98715 / 46115; 98728 / 5029; 98743 / 5043; 98767 / 34067; 98801/ 6201; 98802 / 71000; 98809 / 60009; 98819 / 60019; 98824 / 6024; 98828 / 35028; 98834 / 46233/6233; 98851 / 48151; 98863 / 60163; 98872 / 60103; 98898 / 60007; 98505 / 45305; 98531 / 45231; 98507 / 45407; 98571 / 44871. [See table for more details]. Nature and Degree It would not be practical to revise the RGS to include steam locomotives, due to their wide diversity of design from modern traction. Steam Locomotives are in a minority group, and subject to the restrictions in GM/RT2000 for "Heritage Vehicles". The cab environment of a steam locomotive is a noisy environment. Risk Assessment/Safety Justification With consideration of the foregoing, the level of impact / risk is considered to lie within acceptable bounds because: · For a steam locomotive to be included, it has to be registered and maintained to operate safely on the mainline. · Steam locomotives are limited to a maximum of 15,000 miles per year. · On steam locomotives, there is always a second-man (fireman) and often a traction inspector on the footplate who will be trained and assessed as competent to operate the radio. Applicant Organisation Certificate Issue Date West Coast Railway Company 13/03/2013 Ltd, North Yorkshire Moors Railway Enterprises plc, DB Schenker Rail (UK) Ltd Certificate End Date N/A Lead SC Rolling Stock Lead SC Approval Date 15/02/2013 Deviation Status Current GERT8080 One Train Radio Systems for Voice Related Messaging Communication 12-031-DGN Fitment of GSM-R - Steam Locomotives Operated by Applicants that are mainline operated. 5.2.11 and 5.2.17 The scope of the deviation is to include the following Steam Locomotives operated by the applicants that are Mainline Registered: TOPS No. / BR No. : 98429 / 75029; 98466 / 9466; 98476 / 76079; 98536 / 4936; 98549 / 4965; 98564 / 61264; 98572 / 5972; 98577 / 30777; 98605 / 62005; 98625 / 30825; 98642 / 61994; 98690 / 5690; 98713 / 70013; 98715 / 46115; 98728 / 5029; 98743 / 5043; 98767 / 34067; 98801/ 6201; 98802 / 71000; 98809 / 60009; 98819 / 60019; 98824 / 6024; 98828 / 35028; 98834 / 46233/6233; 98851 / 48151; 98863 / 60163; 98872 / 60103; 98898 / 60007; 98505 / 45305; 98531 / 45231; 98507 / 45407; 98571 / 44871; 98746 / 34046; 98700 / 70000. [See table for more details]. It would not be practical to revise the RGS to include steam locomotives, due to their wide diversity of design from modern traction. Steam Locomotives are in a minority group, and subject to the restrictions in GM/RT2000 for "Heritage Vehicles". The cab environment of a steam locomotive is a noisy environment. With consideration of the foregoing, the level of impact / risk is considered to lie within acceptable bounds because: · For a steam locomotive to be included, it has to be registered and maintained to operate safely on the mainline. · Steam locomotives are limited to a maximum of 15,000 miles per year. · On steam locomotives, there is always a second-man (fireman), and often a traction inspector on the footplate who will be trained and assessed as competent to operate the radio. West Coast Railway Company 17/05/2012 Ltd, North Yorkshire Moors Railway Enterprises plc, DB Schenker Rail (UK) Ltd N/A Control Command and Signalling 21/02/2013 Current GIRT7016 Four Interface between Station Platforms, Track and Trains 12-028-DGN Stalybridge station Platforms 1 and 3 horizontal alignment 2.1.2 Stalybridge station Platforms 1 and 3 horizontal alignment Stalybridge Station The Up Huddersfield line alignment along part of the proposed Platform 1 has a 550m radius: the length of the non compliant radius is 131m. The Up/Down Middle line alignment along part of the proposed extended Platform 3 has a 575m radius: the length of the non compliant radius is 59m. 11/04/2012 N/A INS 07/03/2012 Current GIRT7016 Four Interface between Station Platforms, Track and Trains 12-027-DGN St Neots Station Platforms 1, 2, 3 and 4: reduced platform clearance to structures 6.2.2 17/05/2012 N/A INS 07/03/2012 Current GERT8000-TW3 Two Preparation and movement of locomotive hauled trains (including HSTs, push-pull, postal, parcels) 12-025-DGN Class 67 Running Light Engine and Hauling Short Trains at Permissible Speeds 2.1 22/03/2012 N/A TOM 06/03/2012 Current GIRT7016 Four Interface between Station Platforms, Track and Trains 12-021-DGN Beccles station - currently unused platform - 2.1.2 Horizontal track alignment. 20/09/2012 N/A INS 07/03/2012 Current Current Deviations Register as at 09 May 2016 Given the physical constraints on this site, it Network Rail would not be practicable to provide a compliant solution. Within the design consideration has been given to; · Platform stepping distances · Platform clearances · Visibility along the length of the train The degree of non compliance is not considered severe; the lengths of the non-compliant curves are short and occur towards the ends of the platforms. The proposed platform 1 is on the inside of the non- compliant curve, and so visibility along the train is not considered to be a problem. The noncompliant radii on Platform 3 is on the outside of the curve at the East end of the Platform and visibility along the platform will not be affected. The non-compliance should not introduce an unacceptable risk to users of the station. St Neots Station Platforms 1, 2, 3 and 4: It is proposed to install a new footbridge at Site constraints are such that compliant Network Rail reduced platform clearance to structures. St Neots station. The scheme is funded platform clearances cannot be achieved primarily by outside parties (Council and whilst ensuring that sufficient stair widths are Property Developer) as part of a Section 106 provided to safely evacuate passengers agreement to improve the station and from the station in case of emergency. access for passengers. The new bridge Despite the narrow clearances, the risk to offers a significant improvement on the passengers is deemed to be acceptable. St station facilities and offers level access for Neots station is a category D station, and so disabled passengers. The bridge is to be there are no significant passenger volumes sited at the widest point of the platform, using the facilities. With the mitigations whilst avoiding OLE structures, existing previously noted, it is believed that any station buildings and other operational potential safety risk associated with the equipment. At this point, the platform widths reduced clearances will be reduced to an are: · Platform 1/2 : 7. 2 m (1. 7 m acceptable level. remaining width with compliant clearances), · Platform 3/4: 7. 4 m (1. 9 m remaining width with compliant clearances). To fulfil the emergency evacuation requirements at the station, the staircases must have at least the clear width of the existing staircases. This gives an overall construction width of approximately 2. 3 m, and thus the available space on each platform results in reduced clearances. The fast lines (Platforms 2 and 3) are both 125 mph linespeed, and so the minimum platform clearances are to be achieved (as far as reasonably practicable) to minimise the risk associated with the aerodynamic effects of passing trains. The This deviation applies to all light engine and Rule Book TW3 was written for the situation This alternative action will allow better use of Arriva Trains Wales/Trenau short train movements of class 67 where locomotives had a braking line capacity when operating light engine or Arriva Cymru Limited locomotives by Arriva Trains Wales on performance worse than the coaches they with short formations of coaches. It will also Network Rail infrastructure. Arriva Trains were hauling. The class 67 is a modern reduce rescue times in the event of a Wales seeks to permit class 67 locomotives locomotive with braking performance that locomotive hauled train failure on Arriva running as light engine or hauling three or exceeds curve A3 of GM/RT2042 (for use on Trains Wales routes. This approach is less coaches to run up to the permissible lines signalled to GK/RT0075 Appendix C). reasonable since the brake performance of a line speed (it is noted that clause 2. 2 of Therefore, this Rule Book assumption is not class 67 is sufficient for all signalled routes TW3 already contains an exemption to allow appropriate to the class 67 locomotive. on Network Rail infrastructure. The class 67 class 67 locomotives hauling four or more Complying with the current RGS results in : is fitted with automatic sanders and modern coaches to operate up to the permissible Under utilisation of track capacity due to WSP system to minimise the risk of poor rail line speed). reduced running speeds of class 67 running adhesion. Arriva Trains Wales drivers will light engine. Increased rescue times for be briefed on this derogation pending rescuing failed trains with a class 67 planned revision of TW3 to permit this. locomotive. Beccles station - currently unused platform. It is proposed to reinstate the existing As the platform is only being reinstated for Network Rail Horizontal track alignment. A separate redundant platform at Beccles station, as trains of length 100 m or less and the application (12/020/DGN - Tracker No. part of the Beccles Loop project on the East platform is on the inside of the curve, 9756) has been made to cover the nonSuffolk (ESK) line. The track radius of the conductors/drivers should have no problem compliant size of the recess beneath the loop is 371 m at this location. observing the whole train whilst on the platform. platform. No station mirrors or monitors are required to achieve this. A HAZOP study was undertaken, involving the Railway Undertaking (RU), where it was identified that there were no significant risks in bringing the redundant platform back into operational use. The RU agreed that all the risks identified were manageable to acceptable levels using current operating procedures for this route. The severity of the non-compliance will not introduce an unacceptable risk to users of the platform. Risks to passengers are deemed to be acceptable. Page 96 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 12-020-DGN Title Beccles station - size of recess beneath out of use platform RGS Clause 11.1.4.1 Scope Beccles station - size of recess beneath out of use platform. A separate application (12/021/DGN - Tracker No. 9907) has been made to cover for the non-compliant horizontal track alignment (clause 2. 1. 2 of GI/RT7016). Nature and Degree It is proposed to reinstate the existing redundant platform at Beccles station, as part of the Beccles Loop project on the East Suffolk (ESK) line. The refuge at these locations is formed of four staggered courses of brickwork beneath the existing coper, forming an average overhang of approximately 100 mm. It would not be reasonably practicable to provide a compliant solution along the full length of the second platform at Beccles. To provide a compliant recess, the existing platform wall would need to be demolished and re-built further away from the track. This would significantly disrupt the operation of the rail network, and require possessions which would affect the East Suffolk Line. GKRT0063 One Approach Locking &amp; Train Operated Route Release 12-017-DGN Improved risk management at mechanical signalboxes supervising a controlled level crossing where approach locking (or equivalent) is not currently provided on the protecting signals or the level crossing directly through barrier inhibition. 3, 4.1, 4.2 and; 4.2.1, A2. Mechanical signalboxes supervising a controlled level crossing where approach locking (or equivalent) is not currently provided on the protecting signals or the level crossing directly. A risk has been identified with 118 mechanical signalboxes with controlled level crossings (gates or barriers) directly supervised and protected by signals controlled from the signalbox. Historically, the signaller was required to observe the passage of trains and not replace protecting signals until the train had passed all moveable infrastructure. Approach locking is not provided at these locations. The application of conventional approach locking to the protecting signals would require bespoke design, the addition or modification of train detection and a change in the method of working. The cost of applying conventional approach locking has been estimated at œ47M and, due to the bespoke design at each site, it would not be possible to address the safety risk in a timely manner. GIRT7016 Four nterface between Station Platforms, Track and Trains 12-016-DGN Barnes Station, Platform 3 &amp; 4. Platform extension and recess 11.1.4.1 Barnes Station, Platform 3 &amp; 4. GKRT0060 Four Interlocking Principles 12-015-DGN Locking level controls between L44 signal at Appendix 1, Table 2, Item 1 Metropolitan Junction and Blackfriars Interlocking on the Blackfriars Spur Lines. Ronnie Bignell, Network Rail (Thameslink Programme), C/O Chris Folwell, 5th Floor, Desk 19, 40 Melton Street, London NW1 2EE GMRT2100 Four Requirements for Rail Vehicle Structures 12-014-DGN Derogation for the manufacture and supply of new Class 350 Electric Multiple Units (EMU) with vehicle bodyshell structures, bogies and glazing manufactured in accordance with GM/RT2100 Issue 3. Supply of 20 new four-car EMUs. Current Deviations Register as at 09 May 2016 Please refer to `Supporting Paper for LM TPE Class 350 Issue 1' Risk Assessment/Safety Justification Applicant Organisation A HAZOP, involving the Railway Network Rail Undertaking (RU) and other affected stakeholders, showed that there were no significant risks in bringing the redundant platform back into operational route. The RU agreed that all the risks identified were manageable to acceptable levels using current operating procedures for this route. The severity is considered low - see risk assessment. Points to note: · Access for maintenance is restricted to periods when trains are not running: the area between the platforms will not be used for inspection and maintenance purposes whilst trains are running, so the absence of a refuge will not affect any risk arising from undertaking maintenance activities. · No visibility problem: as the platform is being reinstated for use by trains less than 100 m long and the platform is on the inside of the curve, conductors/drivers should have no problem observing the whole train at the platform should a passenger slip / fall onto the track. · The platform surfacing along the operational platform will be renewed as part of these works: this will reduce the risk of slips/falls on the platform. · There is a low probability of overcrowding on the platform: a station usage report has been compiled by This addresses a risk which has arisen Network Rail where a number of mechanical boxes rely on the signaller following the rules to not replace signals until a train has passed all moveable infrastructure within a route. Following an error by a signaller, it has been decided that the signaller should be supported by a solution which prevents the level crossing being opened once a train has been signalled towards it. This needs to be achieved quickly at a number of sites. The proposed solution is considered to meet the safety objectives of approach locking and has been subject to a range of assessments and HAZIDs. It is estimated that this will reduce the cost by œ233,346 per crossing safety saving the industry a total of œ23M whilst, in Network Rail's opinion, delivering an equivalent safety benefit to the application of approach locking (taking account of the faster provision). Certificate Issue Date 20/09/2012 Certificate End Date N/A Lead SC INS Lead SC Approval Date 07/03/2012 Deviation Status Current 06/03/2012 N/A CCS 23/02/2012 Current Platform extension works at Barnes Station required the Down fast and Down slow lines to be slewed to provide a sufficient width to the island platform. The works involved alteration of a 51. 57 m length of Platform 3 (Down Fast), and a 77. 67 m length of Platform 4. Prior to the works, Platforms 3 and 4 comprised a riser wall and fill infill; the former had no recess beneath the coper, whereas the latter had a 300 mm recess below the coper. Through widening of Platform 3 (See DRG-0905), a recess of between 0 to 300 mm was constructed over a 30 m length. The coper was realigned for the first 12 m (see section A) and an oversail block provided with the realigned coper over the remaining 18 m section (see section B & C). At Platform 4, the track was slewed towards the platform, and this required cutting the platform back (See DRG-0906). Because of the time limits imposed by working within the possession, a 42. 5 m length of the platform was demolished and rebuilt (compliant) with precast units, but on a 20 m or so length the oversail block was cut back (see Section C) and on a 20 m or so length the copers were realigned (see Section D). Given the limitations of the length of the available possession, it was not Compliance would require significant alterations in London Bridge to provide locking level slots including panel changes, with safety benefits much less than the cost of the alterations. Due to the constraints of the site, it was not Network Rail practicable to provide a compliant solution within the timeframe of the project. A compliant solution would have required the abandonment of the agreed possessions and a resheduling of the works. It would have taken some time to agree the resheduling, and it still might not have been practicable to provide a compliant solution. Low risk to passengers using the Platforms. Although a non-compliance has been introduced to Platform 4, the situation has been much improved on Platform 3. The lengthening of the platforms might also improve safety by reducing passenger density on the platforms. The numbers of passengers using the London End of Down Platform 3 and 4 are low. The risk to passengers is low. 11/04/2012 N/A INS 07/03/2012 Current Following the HazID meeting, the stage Network Rail scheme plan has been drafted and reviewed by MSRP, including Kent and Sussex route Ops and the recommendations made by the HazID report were endorsed. Given the uncertainty of the final Thameslink layout in this area and the knowledge the second phase of Thameslink will be replacing the interlockings, it made sense to defer any modifications until the second phase of the project as apposed to wasting money on abortive work with no real gain. The current fringe arrangements have been in place for many years and no significant risks were identified during the HazID Workshop. 08/03/2012 N/A CCS 23/02/2012 Current Siemens are in discussion with the Department for Transport (DfT) regarding the supply of 20 new four-car EMUs that, with the exception of certain internal layout differences and other minor changes, will be identical to the existing Class 350/2 (`Desiro') EMUs operated by London Midland. The proposed new EMUs shall be operated by London Midland (10 four-car units) and First Transpennine Express (10 four-car units) along their respective operational routes. A strategy outlining the methodology and actions required to meet the approvals requirements necessary for the introduction of the new EMUs into passenger service has been presented to the RSSB via letter 20111222-LET-RSSB. The strategy considers new standards and changes to those standards made in the period between the introduction of the original vehicles and the present. This derogation meets part of the strategy requirement and seeks acceptance of deviations from the specific mandatory requirements of GM/RT2100 Issue 4 (and the standards referenced within the specific clauses) to permit the manufacture of the new EMUs and their entry into passenger service. A full technical description of the The proposed new EMUs are mechanically Siemens plc similar to the existing Class 350/2 EMUs operated by London Midland, which were manufactured in 2008-2009 and were proven to be demonstrably compliant with GM/RT2100 Issue 3. Given that the Class 350/2 fleet is a relatively modern design and the proposed additional vehicles will be very similar to these vehicles, it can be concluded that the introduction of the additional trains on London Midland and First Transpennine Express routes will not introduce any adverse risks to third parties and the risks to passengers will be comparable to existing trains. Siemens confirm that they have not raised any concerns regarding the structural integrity of the Class 350/2 fleet currently in passenger service. Please refer to `Supporting Paper for LM TPE Class 350 Issue 1' for full details. 06/03/2012 N/A RST 17/02/2012 Current Page 97 Deviations Register RGS Number GMRT2400 RGS Issue Number Four RGS Title Engineering Design of On-Track Machines Certificate Number 12-008-DGN Title Non-provision of lifeguard on an On-Track machine that operates self-propelled only when in a possession. RGS Clause 3.25.12 GMRT2000 Three Engineering Acceptance of Rail Vehicles 12-007-DGN Re-introduction of KFA (Y) wagons to service 6.5 GKRT0044 One Controls for Signalling a Train onto an Occupied Line 11-209-DGN Platform Sharing at Peterborough Station. 5.1.3 Existing Signals P421, P423, P466, P468 &amp; P470 controlling movements into existing and new platforms. New Signal P799. GKRT0064 One Provision of Overlaps, Flank Protection and Trapping 11-208-DGN Non Provision of trapping protection for platforms at Nottingham Station and from Eastcroft Siding. 6.1.1 GMRT2000 Three Engineering Acceptance of Rail Vehicles 11-206-DGN Limited operation of Windhoff Channel Tunnel Rail Link (CTRL) Multi-Purpose Vehicles (MPVs) for inspection of the Overhead Line Equipment (OLE) in the Ashford station and immediate surrounding area. Please refer to `Supporting Paper for CTRL MPV OLE Inspection Issue 1' for a list of affected RGSs. Current Deviations Register as at 09 May 2016 Scope The deviation applies to the Railvac vehicle (99 70 9515 001-4), which is an On-Track Machine (OTM) that is hauled in train formation and operates self-propelled only when in a possession. The Railvac OTM is formed from the conversion of an existing 90 tonne GLW flat wagon, by the addition of the Railvac equipment and an in-possession only drive system. When in train formation, the Railvac OTM is effectively a freight wagon and, as such, is never a leading vehicle. The scope of the deviation was extended on 20/03/2014 to also apply to the following five new RailVac machines, which are on the same design as the previously approved scope for the above vehicle. · 99 709 515 002-2 · 99 709 515 003-0 · 99 709 515 004-8 · 99 709 515 005-5 · 99 709 515 006-3. KFA (Y) wagons NLU93264 and NLU93274 (RSL Design Code KF055C). Used as OnTrack Machines, the two wagons were registered non-operational in 2009 and 2005 respectively due to date limitations associated with the modules mounted on the wagons. Nature and Degree The retro design and fitment of lifeguards to the Railvac vehicle would be extremely difficult as the Y25 LS series bogie is a traditional freight bogie which was not designed as a leading bogie to carry lifeguards. The costs associated with the design and testing of a compliant lifeguard are considered prohibitive as, at this stage, the Railvac is a one-off design. Risk Assessment/Safety Justification Applicant Organisation Installation of an OTP type, non-metallic, stiff GB Railfreight (GBRf) rubber strip device that meets the requirements of RIS 1539 Issue 2 may pose a risk when the Railvac is in transit mode. In order to control these risks, the design will be retractable / removable to ensure it cannot pose a risk when the vehicle is in transit mode as a Wagon. Certificate Issue Date 12/03/2012 Certificate End Date N/A Lead SC Plant Lead SC Approval Date 09/04/2014 Deviation Status Current These wagons are 60' container flats and were part of an order for approximately 200 vehicles delivered by Rautarukki of Finland in 1987. Initially, they were used for freight services before being used by Network Rail as part of the Rail Head Treatment Train. Roughly, 25 vehicles from the order were used by Network Rail for this purpose, all of which are currently registered non operational. 167 of the remaining vehicles are registered as operational, but all have had the original Gloucester GPS20 bogies changed for Sambre et Meuse VNH1 bogies. Consequently, these wagons have a different RSL Design Code (KF010D) from NLU93264 and NLU93274 which still have GPS20 bogies. See section 13 (Additional Actions and Observations) for further information on the reason for the change of bogies. The purpose of re-introducing these wagons in to service is to utilise them with Balfour Beatty's TRAMM vehicles to deliver the Northwest Electrification project. The wagons themselves would be used to host a purpose-built volumetric cement mixer and carry steel sections of the OLE structure. The TRAMM has a maximum speed of 40 mph and so this would be the maximum speed of the wagons in this application. The The total distance from the signals controlling the movements to the second train to the commencement of the platform shall not be greater than 600m as per existing non-compliance 04-010-NC (Tracker No 4652). Two new platforms are to be provided at Peterborough which will require new permissive moves to be undertaken from new and existing signals. 4 existing platforms are to be altered in length. These platforms require permissive moves today from existing signals and some will have new permissive moves from new signals. The most appropriate position for the protecting signals (taking account of the line speed of the main lines) is for the signals to be greater than 600m from the platforms. Compliance would either require extra signals leading to non standard aspect sequences with delayed clearance or the prohibition of platform sharing. The alternative actions will implement the process set out in GM/RT2000 and ensure that the wagons are re-introduced into service without an increase to the level of risk on the railway. They will not have any impact on any third parties. The reintroduction of these wagons will enable Balfour Beatty to utilise a purpose built volumetric concrete mixer hauled by a TRAMM to deliver the Northwest Electrification project. This will maximise time on site and deliver significantly higher quantities of concrete with minimum waste when compared to other potential solutions. Balfour Beatty Rail Ltd 05/03/2012 N/A RST 17/02/2012 Current A DA and a permissive working workshop has been undertaken and signal sighting has been completed, and the risks were deemed to be ALARP. Following the upgrade works, the station will fall into four distinct parts: · P1/2 · P4 · P5 · P6/7. Network Rail 24/02/2012 N/A CCS 26/01/2012 Current Nottingham Station Platforms 1 to 7 (west end) and the Down Eastcroft siding. The Down Eastcroft Siding could be provided with trap points or a derailer however the falling gradient of 1: 290 towards the buffer stops, the track layout and the slow speeds in the areas make this an expensive provision. Provision of trapping protection at the west end of all the platforms is not practicable due to the constrained nature of the layout with a constricted overbridge. Any solution is likely to introduce more risk from the derailment especially since in the event of a SPAD it could be a passenger train which is derailed. An alternative is to ban the stabling of trains for extended periods (e. g. overnight) however this has been custom and practice and this location for at least 20 years. The Down Eastcroft Siding is located on a Network Rail gradient of 1 in 290 that falls away from exit of the siding and for compliance with clause 6. 1. 1 trap points should be fitted to prevent unauthorised or unintentional movements fouling running lines. However with the falling gradient any rolling stock that runs away will do so towards the buffer stop and not proceed to a position that results in fouling running lines. Any unauthorised movement resulting in a SPAD of TN4022 signal is mitigated against by the fitment of a TPWS TSS loop at this signal. The platform lines within Nottingham station are located on a 1 in 270 gradient. These platform lines are regularly used for the stabling of unattended rolling stock. The rolling stock stabled within Nottingham station is multiple units of modern design with parking brakes. Therefore unintentional run away movements are extremely unlikely to take place. Unauthorised movements are controlled by the provision of TPWS TSS loops on all platform starter signals which are shown to be fully effective as detailed in the Signal Overrun Risk Assessment (SORA) report. 02/08/2012 N/A CCS 26/01/2012 Current The issue of RSSB Deviation 11/053/DGN on 17/05/2011 allowed the CTRL MPVs to operate unladen (without modules fitted) at low speed in the Ashford station area to access Ashford works and the Class 395 (`Javelin') depot for wheel turning. Network Rail has subsequently requested the MPVs to be approved with modules fitted to allow the OLE in the Ashford station area to be inspected, this being the only section of overhead line (OLE) on Network Rail infrastructure in the area. This derogation seeks acceptance of deviations from the verification requirements of GM/RT2000 and other RGSs to allow the MPVs to operate, whilst carrying modules in the Ashford station area. The increased mass, additional routes and implications of operating the MPVs as On-Track Machines are considered in the document `Supporting Paper for CTRL MPV OLE Inspection Issue 1'. Complying with RGSs would require a significant amount of verification work and it is likely that this would result in a number of modifications. Such modifications are not considered necessary as it is considered that the risks associated with noncompliance or not fully verifying performance can be adequately controlled given the small number of vehicles (four, operating as two pairs) and the limited geographical scope of operation. As well as resulting in significant costs, this assessment and any modification work would also require a considerable amount of time to complete. Network Rail would like to use the MPVs as soon as possible to allow the inspection work to be undertaken. Given that the Windhoff Tranche 1 and Balfour Beatty Rail Limited Tranche 2 MPVs operated by Network Rail have safely operated on Network Rail infrastructure for the past ten years, and the CTRL MPVs are very similar to these vehicles, it is not anticipated that any adverse impacts on 3rd parties will occur as a result of this deviation. The MPVs will operate with modules fitted, as they do on a routine basis on CTRL infrastructure. The gauging issues have been agreed between Network Rail's gauging team following a Clear Route analysis with the largest module fitted. 28/03/2012 N/A RST 20/01/2012 Current Page 98 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title ,Interface between Station Platforms,, ,Track and Trains, Certificate Number 11-204-DGN Title Kirk Sandall, New Shelter Panels RGS Clause 6.4.2 GCRT5033 Two Terminal Tracks - Requirements for Buffer Stops, Arresting Devices and End Impact Walls 11-202-DGN Huntingdon station bay platform 1 - Buffer stop arrangement 2.1.1.4 and 2.3.1.2 GMRT2100 Four Requirements for Rail Vehicle Structures 11-201-DGN Structural strength of burst through door panels 6.5.2.2 GMRT2161 One Requirements for Driving Cabs of Railway Vehicles 11-200-DGN Class 319 - Visibility from Driving Cab 6.1.1 Seated Drivers, Case (b) GCRT5112 Two Rail Traffic Loading Requirements for the Design of Railway Structures 11-195-DGN North face of the new West Hampstead Thameslink Station - piled foundation. 7.1.2 Current Deviations Register as at 09 May 2016 Scope The Island platform is 5000 mm wide. The shelter currently gives 2500 mm clearance each side and the shelter does not provide any protection to passengers. The panels will protrude 500 mm each side so clearance will now be 2000 mm each side and provide passengers with protection from the elements. A new DfT compliant footbridge is to be installed at the station to provide improved access to station facilities. The location to be installed is within 20 m of the buffer stop location. A deviation has previously been submitted and agreed (Ref. 11/028/DGN Tracker No. 8527). A condition of this derogation (see section 9) was to replace the existing fixed buffer stop with a energy absorbing sliding buffer. A buffer stop risk assessment was included with this deviation and has been attached for information. The design has determined that, owing to the limited occupancy, the rate of retardation must be greater that that stated in the standard. Replacement vestibule door for No. 2 end on ScotRail class 156 diesel multiple units featuring a burst through element. The design is described in drawings UR-EG30001 Issue P2, UR-EG-3000 Issue P32 Issue P2, UR-EG-30003 Issue P3, UR-EG30004 Issue P2 and UR-EG-30005 Issue P3. Nature and Degree If we comply with the RGS, then it is impossible to provide a shelter which provides any sort of protection from the elements from either side. The proposal outlined solution best suits compliance and provides a solution for passenger protection at a station which is particularly exposed. Clause 2. 1. 1. 4: Four-car units will decelerate at a maximum rate of 0. 364g (greater than the 0. 25g permitted by Railway Group Standards). Eight-car units will decelerate at an average rate of 0. 192g (greater than the 0. 15g permitted by Railway Group Standards). Clause 2. 1. 1. 4: The available occupancy is limited to 8 m. This cannot be increased by moving the new buffer closer to the exit signal due to existing restricted standage for eight-car units. Major signalling and track works would be required. The occupancy cannot be increased behind the existing buffer as this would require the platform to be reconstructed and reconfiguration of OLE structures. The proposed footbridge and existing station buildings would also be affected. Clause 2. 3. 1. 2: Proposed track radius for section behind the buffer stop is 2445 m. In order to comply with recommendation 76 (option 3) of the Cullen enquiry into the Southall and Ladbroke Grove accidents, the vestibule door is to be equipped with a burst through panel to aid egress in the event that a Class 156 vehicle is involved in an incident that leads to all internal doors on a vehicle requiring opening against gravity. Compliance with the requirements of GM/RT2100 Issue 4 are as follows: "6. 5. 2. 2 Interior glazing shall withstand without failure the following ultimate load cases. Where both sides of the glazing are accessible by passengers or traincrew, the load cases shall be applied to both sides independently. The glazing shall remain intact and in position throughout the application and removal of the loads. The ultimate load cases are: A concentrated perpendicular load of 2. 5 kN applied over an area of 0. 1 m x 0. 1 m at any position on the surface. A pressure of 2. 5 kPa applied over its entire surface plus a concentrated perpendicular load of 0. 8 kN applied over an area of 0. 1 m x 0. 1 m at any position on the surface. " Compliance with the above requirements would necessitate a stiffer rubber section resulting in either difficulty or inability to remove the burst through Class 319 wiper modification. First Capital Connect (FCC) proposes to improve the reliability of the windscreen wiper system by the following. · Development of the existing wiper motor to improve sweep consistency, wiper arm security, and the prevention of GRP/blade impacts · Replacement of the wiper arm with a more robust design that incorporates an anti-life device · Replacement of the existing blade with an improved version to provide more effective cleaning of the windscreen statically and at speed. Due to this change to `cab facilities', a review of GM/RT2161 was undertaken by Interfleet Technology Limited. During this review, a sightline drawing was produced which shows a dimensional representation of the Class 319 windscreen to GM/RT 2161 section 6. 1. 1. Case (a) is obscured by the top of the existing desk. Case (b): The view of signals at 6. 0 m height above rail is obscured by the existing destination indicator and sunblind. And in the event of rain, the wiper system will not clear the top section directly below the sunblind. The new wiper system follows the almost identical sweep area as the existing system apart from a very small area at the top sweep arc (see drawing ITL-T28627-001 at North face of the new West Hampstead During the installation of one of the piled Thameslink Station Building located on the foundations to the new West Hampstead SPC1 line (Hendon Line) between 3m1540y Thameslink Station Building, one of the and 3m1570y (see drawing N280-HYD-DRG- 450mm diameter piles could not be installed AR-000001), particularly the pile group at in the designed location due to unforeseen the intersection of gridlines 4 and A (see obstructions within the ground. The piled drawing N280-HYD-DRG-CV-000010). foundation was redesigned and reconfigured to support the loads applied by the building, but the altered design led to one pile within the group now being located within 4. 5m of the nearest cess rail (see pile P51 on drawing N280-HYD-DRG-CV-000010). The volume of reinforcing steel required for the pile to resist the mandated impact load in GC/RT5112 could not be accommodated in this pile: a compliant solution would have required the installation of a larger and deeper pile. Risk Assessment/Safety Justification The actions will ensure that there is a reasonable clearance from the platform edge at the shelters longest point (2000 mm), whilst giving the passengers the chance to shelter from conditions in behind the new panels. Passengers when seated inside the shelter will be sat 2300 mm from the platform edge. Clause 2. 1. 1. 4: The limits of deceleration in Group Standards are specified for passenger safety/comfort reasons. However, the current operating rules at Huntingdon do not permit passenger stock to enter the bay with passengers on board. Therefore, in the event of a buffer overrun, the stock will be empty with only train crew on board. Whilst designed with a higher deceleration rate than the normal limits, the new sliding friction buffer will still bring the train to rest in a fully controlled manner and will offer significant safety improvement over the existing (defective) fixed buffer. Clause 2. 3. 1. 2: The proposed track radius of 2445 m is relatively flat, the corresponding versine over the 8 m buffer occupancy length is only 3 mm, therefore the occupancy length of track can be considered to be nominally straight and is within installation tolerance of straight track (+/-15 mm between 10 m offsets or difference between overlapping 20 m chords). The proposal to implement a sliding buffer stop offers a significant safety improvement on the existing fixed buffer stop which is in poor condition. The present use of the bay platform is for empty trains only. That is, only train crew and driver will be aboard the The new Emergency Egress Panel Assembly is specifically designed to aid egress in the event that a Class 156 vehicle is involved in an incident that leads to the internal doors on a vehicle requiring opening against gravity. The new panel assembly is designed to comply with recommendation 76 (option 3) of the Cullen enquiry into the Southall and Ladbroke Grove accidents. The design is described in drawings UR-EG30001 Issue P2, UR-EG-3000 Issue P32 Issue P2, UR-EG-30003 Issue P3, UR-EG30004 Issue P2 and UR-EG-30005 Issue P3. Applicant Organisation Northern Rail Limited Certificate Issue Date 10/02/2012 Certificate End Date N/A Lead SC INS Lead SC Approval Date 10/01/2012 Deviation Status Current Network Rail 21/03/2012 N/A INS 10/01/2012 Current First ScotRail 06/03/2012 N/A RST 20/01/2012 Current FCC expects a significant improvement in First Capital Connect the reliability of the windscreen wiping system. These changes will result in greatly improved driver visibility with less distraction, due to the wiper blade and arm no longer striking the GRP window surround or lifting off the windscreen. 03/02/2012 N/A RST 20/01/2012 Current Very low. The affected pile (pile P51) is one Network Rail of 49No. piles that form the foundation of the building. All other piles are located 4. 5m or further from the nearest cess rail. The piles are protected by the existing reinforced concrete retaining wall which runs parallel to the running line, the compressible filler and a concrete arch behind the retaining wall. In the event of a collision due to the derailment of a train, the retaining wall and concrete arch will bear the brunt of the impact, with the wall also acting as a robust kerb to protect the pile and guide the derailed train back towards the intended direction of travel. In the event of an impact, 48 of the piles supporting the station lie outside the zone where it is deemed necessary to design for impact loading. Pile 51 is 3. 9m away from the nearest rail and an impact that would compromise its integrity would not result in the catastrophic failure of the building. 20/12/2011 N/A INS 16/11/2011 Current Page 99 Deviations Register RGS Number GKRT0045 RGS Issue Number One RGS Title Lineside Signals, Indicators and Layout of Signals Certificate Number 11-194-DGN Title Reduced Readable Distance of Dual Legend OFF Indicators at Faversham, Margate and Ramsgate Stations. RGS Clause 2.4.5.7 GIRT7016 Four Interface between Station Platforms, Track and Trains 11-191-DGN Alexandra Palace Station. 2.1.2 GMRT2473 One Power Operated External Doors on Passenger Carrying Rail Vehicles. 11-188-DGN Power Door Mk3 Trainsets with Manually Operated SDO System. B12 GIRT7016 Four Interface between Station Platforms, Track and Trains 11-187-DGN Finsbury Park Station: minimum horizontal curve, useable width of platform and minimum width of recess beneath platform. 2.1.2, 7.2.1, 11.1.4 GERT8082 One GSM-R Cab Mobile, Great Britain Open Interface Requirements (Rapid Response) 11-186-DGN Cab Mobile v2, Pre defined message acknowledge - FTN/GSM-R Project 4.2.5.4, 4.3.3.2 Table 4.3 Current Deviations Register as at 09 May 2016 Scope This non-compliance application relates to Faversham, Margate and Ramsgate stations. These stations are within the area of the EKR1 Project which is undertaking a full resignalling of the area bounded by Sittingbourne, Minster and Kearsney stations and virtually all signalling equipment in the area is new. The specific equipment affected is listed below: Faversham: · Platform 1: EK4332/4339 R(1) and EK4332/4339 R(2) · Platform 3: EK4335/4336 R(1) and EK4335/4336 R(2) · Platform 4: EK4333/4338 R(1) and EK4333/4338 R(2). Note that a pair of identical OFF indicators are already in service on platform 2 at Faversham having been installed as part of the EKR1 Project's stage works in 2009 and will remain in operation following commissioning of the new signalling system. These indicators are the subject of derogation certificate number 09/218/DGN. Margate: · Platform 1 EK5109/5122 R(1) and EK5109/5122 R(2) · Platform 2 - EK5111/5120 R(1) and EK5111/5120 R(2) · Platform 3 EK5118/5113 R(1) and EK5118/5113 R(2). Ramsgate: · Platform 1 - EK4982/5178 R(1) and EK4982/5178 R(2) · Platform 2 EK4984/5176 R(1) and EK4984/5176 R(2) · Alexandra Palace Station - enhanced capacity of Platforms. ELR: ECM1, 4 m 1716 yards Platforms 0/1: Proposed Up Slow 1 and Up Slow 2 lines. London bound: track radii of 750 m-790 m over the southern 80 m of the proposed platforms. Line speed 35/60 mph. Operational length of platforms 170 m. Nature and Degree Two potentially compliant options were identified to meet the requirement to be capable of displaying both legends simultaneously as below: · Option 1: Utilise pairs of standard BR 1651 Part 2 Indicators to form the required indications stacked vertically. · Option 2: Utilise pairs of standard BR 1651 Part 2 Indicators to form the required indications grouped horizontally. All the indicators are to be installed beneath existing platform canopies which places a restriction on the available headroom without extensive alterations to the canopies. It should be noted that the canopies were constructed in the 19th and early 20th centuries and that both Faversham and Ramsgate stations have listed building status. Site survey identified that option 1 is not possible without either altering the height of the platform canopies or reducing the clearance between the underside of the indicators and the platform surface to a non-compliant figure. The former course of action is not reasonably practicable for cost and listed building consent reasons and the latter could result in head injury to passengers and staff and also to the lower legend becoming obscured by people on the platform. Option 1 was It is proposed to enhance the capacity of Alexandra Palace Station through (a) the construction of an additional platform serving the proposed Up Slow 2 line, and (b) the modification and remodelling of the existing platform 1 serving the Up Slow 1 line. The site is constrained by the track geometry imposed by the multi-span overbridge ECM1/30, Buckingham Road, to the north of the station. The provision of a compliant solution would require extensive permanent way realignment and reconstruction of this overbridge. 10-off MK3 trainsets operated by Chiltern Chiltern Railways plans to introduce 4-off Railways comprising of DVT + GFW + (5-6) Mk3 trainsets into service from March 2012. x TSO + cl 67 Where DVT = Driving Van This fleet will be grown with passenger Trailer GFW = Galley First Wheelchair TSO demand with a maximum of 10-off Mk3 = Trailer Standard Open cl 67 = Class 67 trainsets by the end of the Chiltern Railways locomotive. franchise in 2021. These trainsets will be unique for Mk3 trainsets due to the installation of powered bodyside doors to reduce boarding times, improve safe access to these vehicles and aid accessibility. These trainsets will be limited to specific routes by their NRAP certificate due to widened footsteps. Chiltern Railways has included a guard operated Selective Door (SDO) System in the train design to allow selected doors to be opened, should the trains be required to stop in service at short platforms. This Derogation seeks permission to use a manual SDO system following risk assessments and ORR consultation. GM/RT2473 requires installation of a fully automatic SDO system to control the opening of doors and limit the opening to doors that are on a short platform. All other fleets that have automatic SDO systems in use on the UK mainline network benefit from: Economies of scale from use on fleets of over 500 vehicles (Southern class 377 &amp; South Eastern cl Finsbury Park Station: · Platform 1 The capacity of Finsbury Park Station is to minimum horizontal curve · Platform 5 be enhanced by: (a) extending Platforms 3 useable width of platform · Platforms - 0, 3 and 5 and (b) extending and refurbishing the and 5 - minimum width of recess beneath currently disused island platform 0/-1. To platform. cater for twelve-car trains, the platforms are to be extended to a length of 245 m. The site is constrained by the existing track geometry and boundaries of the station. The station is elevated above the surrounding ground and, at the north and south of the station, the lines are carried over a series of bridges over two main roads. Extending the platforms (in either direction) will affect the adjacent highways. Extending the platforms at the northern end of the station will have the least requirements for reconstruction works, but it would be impracticable to provide a compliant solution. Due to the constraints on the site, it would be impracticable to provide a compliant solution. Details of the proposed arrangements are provided in the attached risk assessment. The refurbished/extended Platform -1, serving the Up Goods lines, occupies a 525 m radius curve at its northern end to a 935 m curve at its southern end; these curves are separated by a 75 m long straight section. The width of the proposed extension to Platform 5 will taper National. Cab Mobile v2 can also receive and send the Acknowledgement in the CONNECT (4. 2. 5. 4). Pre-defined message acknowledge does not include the Functional ID (4. 3. 3. 2 Table 4. 3). 4. 2. 5. 4: It is not practical to constrain Cab Mobile v2 to only send the Acknowledge in the Disconnect or Release Complete given that Acknowledgement in the CONNECT is a desirable feature and supported by the network. 4. 3. 3. 2 Table 4. 3: The functional ID is sent in the SETUP and thus also sending the functional ID with the Acknowledge (I. e. in the DISCONNECT or CONNECT) would serve no purpose. It is thus not practical to incur the cost/timescale impact of enhancing enhance Cab Mobile v2 to support this. Risk Assessment/Safety Justification Applicant Organisation The impact of the reduced readable Network Rail distance has primarily been mitigated by careful consideration of the interface between the OFF indicator position and routine operations on the platforms affected as detailed below. Car stop marker boards are provided at various points along the platforms to optimise stopping positions for trains of less than 12 cars (the maximum formation being used only during peak hours) taking account of signal visibility, position of canopies/platform waiting facilities for passengers and platform access routes such that shorter formation trains will generally use the central sections of the platforms which are well covered by the OFF indicators as noted above. As part of the briefing of their staff on the changes to the signalling system being commissioned at Christmas 2011 Southeastern shall include guidance on the need to stand in a position from which an OFF indicator, appropriate starting signal (or banner repeater where provided) can be clearly read when dispatching trains. Train services on this route are currently comprised of the following types of trains: Electrostar (class 375) units from which the guard can dispatch the train from Low severity. The minimum radii of the Network Rail proposed Platform 0/1 is 750-790 m; this curve extends over the southern 80 m end of the Platform before transitioning into a straight alignment to the north. Over the length of the non-compliant (radii) Platform, the platform edge offsets will be aligned to provide compliant stepping distances. Certificate Issue Date 15/12/2011 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 15/12/2011 Deviation Status Current 10/02/2012 N/A INS 16/11/2011 Current The proposed alternative action will allow Chiltern Railway Company Ltd 06/02/2012 Chiltern Railways to bring the Mk3 trainsets ("Chiltern Railways") with powered doors into service as planned and for them to be used at short platforms following platform specific risk assessments and ORR consultation. The manually operated SDO system is reasonable since: The fleet is small (4 trainsets at present with an expected maximum of 10 trainsets as the fleet grows), and the cost of a fully automatic SDO system is not justified by the cost given the relatively small fleet and the reduced life compared to a new train. A derogation would not have been required to operate Mk3 HST vehicles with slam doors using the CDL SDO system since this has "grandfather rights". However, a derogation is required to operate the Mk3s with powered bodyside doors, although these are fully compliant with GM/RT2473 in all other respects and offer significant safety &amp; accessibility improvements compared to existing Mk3 vehicles. Other vehicles fitted with manually operated SDO systems operate over these routes. These fleets include Classes 170, 172/2 and 172/3, although the function of the SDO system is different. N/A RST 20/01/2012 Current Low risk - see attached risk assessment. Network Rail The risk to passengers generated by these non-compliances is deemed to be acceptably low. The proposed substandard width area of platform 5 is relatively small and would not be readily used during the normal operation of the platform. In addition, the sub-standard width area is to the departure end of the platform and, as such, the position of door opening would be in an area of acceptable platform width. Additional mitigation measures such as warning signage can be adopted if considered necessary to advise of the platform width restrictions. 27/02/2012 N/A INS 16/11/2011 Current No impact - the function is carried out as effectively and is compliant with the TSI. 12/01/2012 N/A CCS 15/12/2011 Current Network Rail Page 100 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 11-183-DGN Title RGS Clause New waiting shelter(s), clearance to platform 6.2.2 b edge(s) GIRT7016 Four Interface between Station Platforms, Track and Trains 11-182-DGN West Croydon Station, Platform 1 - Buffer stop overrun. 6.3.1 GKRT0045 One Lineside Signals, Indicators and Layout of Signals 11-180-DGN Non provision of route indications for shunt moves from Salford Crescent Station platform starter signals 5.1.2.5 GKRT0045 One Lineside Signals, Indicators and Layout of Signals 11-179-DGN Non-standard Legends for OFF Indicators at 2.4.5.2 Ramsgate Station. GKRT0044 One Controls for Signalling a Train onto an Occupied Line 11-178-DGN Excess Call-On Distance from EK5126 Signal at Margate. Current Deviations Register as at 09 May 2016 Part B, 5.1.3 Scope This derogation relates to horizontal clearances between the platform edge(s) and proposed new waiting shelter(s) at stations listed below: Arriva Trains Wales is proposing to replace the existing waiting shelters at a number of locations which currently are within 2500mm from the platform edge. Site constraints do not allow for the installation of the new proposed shelters to achieve the RGS. Therefore we are seeking derogation from the RGS to install on the existing footprint: · Fairwater Two platforms - 2 new shelters proposed. Line speed 55mph. · Danescourt - Two platforms - 2 new shelters proposed. Line speed 55mph Nature and Degree The existing shelters at the named stations in section 7 are all within 2500mm of the platform edge. Each location has its own difficulties to allow the TOC to comply with the RGS requirement for the following reasons: Generally: The shelter width is 1600mm from the centre line of each post, in calculating the proposed distance to platform edge 1700mm has been used as the overall shelter width from outside of post to outside of post. · Fairwater (Platform to Coryton) - The existing shelter is 2. 17m from the platform edge. The existing shelter is 1. 56m in width; the proposed new shelter is 1. 7m in width and therefore reduces the current position by 140mm. · Fairwater (Platform to Radyr) - The existing shelter is 2. 21m from the platform edge. The existing shelter is 1. 53m in width; the proposed new shelter is 1. 7m in width, and therefore reduces the current position by 170mm. · Danescourt (Platform to Coryton) - The existing shelter is 2. 18m from the platform edge. The existing shelter is 1. 54m in width; the proposed new shelter is 1. 7m in width, and therefore reduces the current position by 160mm. · Danescourt (Platform to Radyr) - The existing shelter is 2. 23m from the platform edge. The existing shelter Application for deviation against clause 6. 3. Existing platform dividing wall will continue 1 of GI/RT7016 with respect to buffer stop to encroach upon overrun zone. However, overrun at West Croydon Station. Platform the vast majority of the zone will be 1 is required to be extended by 11m at the permanently fenced off from all passengers Country end, thereby requiring the buffer with no thoroughfare permitted. The stop (and 20m x 10m buffer stop overrun remainder and vast majority of the buffer zone) to be moved back by the same overrun zone will be securely enclosed by distance. The existing adjacent platform the platform dividing wall and adjacent dividing wall between Platforms 1 and 3 palisade fencing, preventing any already lies partly with in the overrun zone thoroughfare. (4. 2m from the track centreline), but the wall curves towards Platform 1 at the Country end, and this distance will be reduced to 3. 2m at the far end of the 20m zone. Risk Assessment/Safety Justification Applicant Organisation · Fairwater - To comply with RGS the land Arriva Trains Wales behind the shelters would require the construction of a supporting wall and new concrete base to enable the proposed waiting shelter to be located the required 2500mm from the platform edge. The construction of supporting walls will have serious cost implications to the funding of the proposed programme. Diversion of existing cabling would also be required. · Danescourt (Platform to Coryton) - To comply with RGS the land behind the shelters would require the construction of a supporting wall and new concrete base to enable the proposed waiting shelter to be located the required 2500mm from the platform edge. The construction of supporting walls will have serious cost implications to the funding of the proposed programme. Diversion of existing cabling would also be required · Danescourt Platform to Radyr) - To comply with RGS the land behind the shelters would require the demolition and subsequent construction of a supporting wall and new concrete base to enable the proposed waiting shelter to be located the required 2500mm from the platform edge. The demolition / construction of a supporting wall will have serious cost On the basis of the proper risk assessments Network Rail having been undertaken, the Project Team (together with the affected operators) is satisfied that the risks to all passengers on the adjacent platforms and on a train entering the station are ALARP. Certificate Issue Date 13/12/2011 Certificate End Date N/A Lead SC INS Lead SC Approval Date 16/11/2011 Deviation Status Current 15/12/2011 N/A INS 16/11/2011 Current Salford Crescent Station at approx. 1_ miles The existing signals are not provided with on MVE1. Signals MP505 &amp; MP507. MI and the destination is a fan of 2 sidings of equal length. The destination is unaffected by the alteration. Provision of indicators would require alterations within the interlocking, additional cable cores, alterations within the location cases for signals which are only being relocated. The sidings are used to park tampers and to Network Rail occasionally turn back Northern Trains empty stock when margins do not exist within Salford Crescent Station. FOCs do not currently use this siding. The safety implications of not providing new MIs are considered to be negligible. The existing non-provision is being perpetuated. No additional risk is being imported. No call-on class routes exist at these signals. It should also be noted that the sidings to which the shunt routes apply are very rarely used. 07/12/2011 N/A CCS 17/11/2011 Current The standard only permits the use of "UP" Network Rail and "DN" as directional identifiers for OFF indicator legends. Movements leaving either end of the platforms at Ramsgate are Up direction movements and hence compliance with the standard would result in either: the legends for both directions being identical (and hence useless) or a need to define a Down departure direction which would cause confusion or drive a change of line designations across a significant area. Compliance is therefore not considered to be appropriate in this case. Alternative directional identifier legends have been proposed which provide clarity as to the direction in which a movement has been authorised for this location. The direction description elements of the OFF indicator legends will not be compliant with GK/RT0045. However, they will provide a clear identification of the direction of the movement which has been authorised. Compliant legends cannot be used as trains leaving either end of Ramsgate station are travelling in an Up direction and GK/RT0045 only permits the use of "UP" and "DN" as directional identifiers. The alternative directional identifiers proposed have been selected so as to use distinctive character Margate Station - EK5126 signal to Platform Network Rail already has a national nonIt is considered that the only practicable Network Rail 4. compliance (certificate number 04/010/NC) means of achieving compliance would be to which extends the maximum required relocate EK5126 signal towards Margate distance between the signal controlling the such that its overlap required 2325 movement of the second train and the crossover locked normal. This is platform to 600m. The protecting signal is considered to be unduly operationally positioned to provide good signal visibility restrictive given the low level of usage of the and compliant braking distances for through call-on class route and therefore a nontrains. Compliance would require one of the compliance is sought to permit the use of following: - relocation fo the signal to a sub- call-on class movements from EK5126 optimal position, the prohibition of platform signal for platform sharing purposes with the sharing which would be operationally signal in excess of 600m from the platform restrictive, Provide an additional signal for the life of the installation. The signal is between EK5126 and the platform, Extend 285 metres further from the platform than the the platform towards Ramsgate, Provision of standard (and 85m further than the existing a mid-platform signal. national non-compliance) permits. The new interlocking has been designed in accordance with modern principles and consequently requires a first train to be detected within the platform and for the second train to have been occupying the berth track section at EK5126 signal for a period of time (GUD occupied for 25 seconds) to obtain the proceed aspect for the call on class route. The initial speed of the train entering the route is therefore controlled to an appropriate level. The subsidiary aspect on EK5126 signal can only be cleared for call on class routes and 07/12/2011 N/A CCS 17/11/2011 Current 07/12/2011 N/A CCS 17/11/2011 Current OFF indicators provided at Ramsgate station. Compliant indications would result in the OFF indicators for both directions reading "OFF UP" since the direction changes in the middle of the platform with up lines departing both ends. Page 101 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 11-177-DGN Title Corbridge Station, platforms 1 and 2: clearance of structures to the edge of the platform. GIRT7016 Four Interface between Station Platforms, Track and Trains 11-176-DGN GKRT0064 One Provision of Overlaps, Flank Protection and Trapping GKRT0044 One GKRT0045 One Scope Corbridge Station, platforms 1 and 2: clearance of structures to the edge of the platform. Nature and Degree NEC2/73 footbridge links platforms 1 and 2 of Corbridge Railway Station. The footbridge is adjacent to the western face of railway overbridge NEC2/72, including a link span between the overbridge to footbridge NEC2/73. The condition of Corbridge Station footbridge is such that it has to be replaced. The bridge is currently closed to the public. The staircase on Platform 1 is supported on scaffolding to allow public access from road level to the platform, and the stairs on Platform 2 are supported on scaffolding. To meet planning requirements and site constraints, it is proposed to reconstruct the footbridge on a like-for-like basis, but using steel rather than wrought iron. In constructing a like-for-like replacement, the width of the existing platforms limits the clearance between the platform edge and the footbridge. The existing (non-compliant) platform edge clearances are 1798 mm and 1998 mm on platforms 1 and 2 respectively. Risk Assessment/Safety Justification Applicant Organisation Minor: the existing (admittedly nonNetwork Rail compliant) platform clearances will not be reduced. Relatively low risk: the like-for-like replacement does not worsen the existing platform clearances. Certificate Issue Date 22/03/2012 Certificate End Date N/A Lead SC INS Lead SC Approval Date 10/01/2012 Deviation Status Current New waiting shelter(s), clearance to platform 6.2.2 b edge(s) This derogation relates to horizontal clearances between the platform edge(s) and proposed new waiting shelter(s) at stations listed below: Arriva Trains Wales is proposing to replace the existing waiting shelters at a number of locations which currently are within 2500mm from the platform edge. Site constraints do not allow for the installation of the new proposed shelters to achieve the RGS. Therefore we are seeking derogation from the RGS to install on the existing footprint: Maesteg Single platform - 1 new shelter proposed. Line speed 25mphEwenny Road - Single platform - 1 new shelter proposed. Line speed 35mph Garth - Single platform- 1 new shelter proposed. Line speed 40mphSarn Single platform - 1 new shelter proposed. Line speed 50mph Fernhill - Single platform 1 new shelter proposed. Line speed 40mph Penrhiwceiber - Single platform - 1 new shelter proposed. Line speed 50mph Treforest Estate - Island platform - 1 dual shelter proposed. 40mph. N/A Infrastructure 16/11/2011 Current Non provision of trapping protection in Immingham East area. 6.1.1 No provision of trapping protection from Eastern Jetty, Freight Terminal Sidings and Ridley's Sidings in Immingham East SB control area. Maesteg - To comply with RGS the land Arriva Trains Wales behind the shelter would require the construction of a supporting wall to enable the proposed waiting shelter to be located the required 2500mm from the platform edge. The construction of a supporting wall would have a big impact on the DDA ramp which is located behind the existing shelter and would also reduce the width of the ramp and therefore make it unsuitable for wheelchair users etc. The land adjacent to the ramp is not in Network Rail's ownership. Ewenny Road - To comply with RGS the land behind the shelter would require the construction of a 1. 38m high wall on an embankment to enable the proposed waiting shelter to be located the required 2500mm from the platform edge. The construction of the 1. 38m high wall will have serious cost implications to the funding of the proposed programme. Garth - To comply with RGS the land behind the shelter would require the construction of a supporting wall to enable the proposed waiting shelter to be located the required 2500mm from the platform edge The construction of a supporting wall will have serious cost implications to the funding of the proposed programme. Sarn To comply with RGS the land behind the The existing arrangement has been Network Rail considered to be reasonably practicable due to the following specifics: Line speed of only 30mph. The re-signalling scheme does not encompass Ulceby North Jcn. It is evident that there are no existing trapping arrangements in place against the freight only line from the junction to the renewal area. The current junction protecting signal UJ19 is provided with TPWS TSS (Proved to be effective @ 6%g with 10second free wheel time). There are two rising gradients between Humber Road Junction and Ulceby North Junction. (1: 176 and 1: 300 giving a maximum net height gain of 2. 2m to be overcome). The risk of vehicles running away from the Immingham East Junction area has been eliminated by the rising gradient and distance to Ulceby Junction approximately 6 miles away. 20/12/2011 11-175-DGN 07/12/2011 N/A CCS 17/11/2011 Current Controls for Signalling a Train onto an Occupied Line 11-174-DGN Permissive moves into Nottingham platform 5.1.3 4. Nottingham Station permissive movements into platform 4 from signals TN4961, TN4963, TN4965 &amp; TN4967. The existing shelters at the named stations in section 7 are all within 2500mm of the platform edge. Each location has its own difficulties to allow the TOC to comply with the RGS requirement for the following reasons: Generally: The shelter width is 1600mm from the centre line of each post, in calculating the proposed distance to platform edge 1700mm has been used as the overall shelter width from outside of post to outside of post. The shelter width is 1800mm from the centre line of each post, in calculating the proposed distance to platform edge 1900mm has been used as the overall shelter width from outside of post to outside of post. Maesteg - The existing shelter is 2. 22m from the platform edge. The existing shelter is 2. 09m in width; the proposed new shelter is 1. 9m in width and therefore improves the current position by 190mm, however this would still not achieve the 2500mm rule. Ewenny Road - The existing shelter is 2. 21m from the platform edge. The existing shelter is 1. 83m in width; the proposed new shelter is 1. 7m in width, and therefore improves the current position by 130mm, however this would still not achieve the 2500mm rule. Garth - The existing shelter is 2. 17m from the platform This is an existing non compliance in that trap points are not currently provided at the exit of the Eastern Jetty in order to provide trapping protection for the passenger line at Ulceby North Junction. Given the overall rising gradient between the area under consideration and Ulceby North Junction, the low speeds involved and the constraints of the site in providing trap points on the Eastern Jetty, it is proposed to perpetuate the existing arrangements. Additionally, it is proposed to remove the existing trap points on the connections to the Freight Terminal Sidings and Ridley's Sidings as part of the re-signalling project. The removal of these trap points has been subject to Risk Assessment in the form of SORA and Reduced Overlap RA which considered the immediate safety risk arising from a collision with a de-railed train. The removal of the trap points has also been reviewed on a cost benefit basis. The position of the protecting signals is fixed by the topography of the area and the only compliant solutions are not to provide the new Platform 4 or to prohibit permissive moves using the new platform. A Risk Assessment has been completed for Network Rail the permissive working which confirmed that the risk from the proposed method of working is acceptable. There is adequate sighting on the approach to platform for a train to stop short of the platform due to the low speed of 15 mph. The alternative of not providing call-on moves from these signals would result in having to authorise non signalled movements in the event of having movements enter the platform when occupied during perturbed working. The position light routes could also be used in accordance with the rule book in degraded situations when there is a track circuit failure in the platform instead of the risks associated with authorising the driver to pass a signal at danger. 07/12/2011 N/A CCS 17/11/2011 Current Lineside Signals, Indicators and Layout of Signals 11-173-DGN Non provision of route indicators on shunt signals leading to Riverside Sidings, Northampton · Signal RY1216 is located on the Down Northampton Fast ELR ref HNR, approx. 66 1/4 MP. · Signal RY1220 is located on the Down Goods Loop ELR ref HNR, approx. 66 1/4 MP. RY1216 and RY1220 are existing signals. Compliance requires provision of alphanumeric miniature indicators for all seven routes from signals RY1216 and RY1220, plus the addition of a further MI to signals RY1028, 1030, 1036 and 1038. Provision of indicators is constrained by SSI capacity; in order to complete the work there would be a requirement to adjust the SSI interlocking boundary at great cost (Northampton interlocking is at full capacity, having 55 TFMs today). The Northampton Re-control Project is converting the hand points at Riverside Sidings to Clamplock operation, thus affecting the controls from position light ground signals RY1216 and RY1220. Signalled in accordance with standards Network Rail circa 1991. The signal route already exists today. The project is providing clamplock electrical detection rather than hand points and consider this a betterment. Compliant with standards applicable at the time the existing signalling was brought into service. The provision of clamplocks with full detection rather than handpoints and the sidings are fully track circuited for signaller indication purposes only. The likelihood and consequence of incident through nonprovision of miniature indicators for these routes is seen as low, therefore further risk reduction measures are not necessary. No incident reports have been recorded. 24/05/2012 N/A CCS 17/11/2011 Current Current Deviations Register as at 09 May 2016 RGS Clause 6.2.2 and 6.5.3 5.1.2.6 Page 102 Deviations Register RGS Number GKRT0060 RGS Issue Number Four RGS Title Interlocking Principles Certificate Number 11-172-DGN Title Non provision of distant signal replacement switch or train detection on modular signalling routes. GERT8000-TW3 Two Preparation and movement of locomotive hauled trains (including HSTs, push-pull, postal, parcels) 11-169-DGN Class 67 Running Light Engine &amp; 2.1 Hauling Short Trains at Permissible Speeds Restrictions in the following table apply to locomotive-hauled trains in the formation shown and all locomotives running light. Table lists maximum permitted speeds against permissible line speeds. GIRT7016 Four Interface between Station Platforms, Track and Trains 11-168-DGN Clapham Junction Station Platform 15: horizontal track alignment through station Platforms 2.1.2 Clapham Junction Station Platform 15: horizontal track alignment through station Platforms. The Sussex Train Lengthening Project will extend the station platforms on the Sussex suburban route (ELR: VBT1) to accept tencarriage trains. The useable length of Platform 15 is to be extended from 165. 9 m to 203 m: the extension will be towards the London end of the station. The existing horizontal alignment through Platforms 14 and 15 has left hand curves at the London end, reversing into right hand curves and then reversing again into left hand curves at the Country end of the platforms. The left hand curves tie into S & C both at the London and Country ends of the platforms. The existing horizontal track alignment along the proposed extension of the London end of Platform 15 has a maximum radius of 952 m; thus without realigning the track, the platform extension will have a radius of curvature of less than 1000 m. To provide a compliant horizontal curve flatter than 1000 m would necessitate a complete reconstruction of the Platform, including the relocation of the existing subway access and staircase and lift to the existing footbridge. GIRT7016 Four Interface between Station Platforms, Track and Trains 11-165-DGN Clapham Junction Station Platform 16 location of platform furniture; useable width of single faced platforms. 6.4.2 and; 7.2.1 Clapham Junction Station Platform 16 location of platform furniture; useable width of single faced platforms. GIRT7033 Two Lineside Operational Safety Signs 11-162-DGN Station approach countdown markers in the South West Trains, Network Rail Wessex route. Section AK, B10 to B10.2 South West Trains proposes the design of a new sign not currently included in RGS GI/RT7033 as required by section B10 of that RGS for the use on the South West Trains Network Rail Wessex Route. Current Deviations Register as at 09 May 2016 RGS Clause C7.4 Scope Modular Signalling Schemes. Nature and Degree Modular signalling is designed to be deployed on secondary routes which cannot justify conventional power signalling due to low density traffic patterns and rural business. These will generally be classified no higher than a Conventional TENS route and typically unclassified. Distant signal replacement will be undertaken by the action of replacing the home signal (the distant signal will act as an auto-distant) and not by the use of a separate device (for Modular signalling this would be a control on the VDU screen) or track section. The cost of compliance has been estimated at up to œ10k per scheme. Risk Assessment/Safety Justification The controls applied to distant signals for Modular Signalling will be: All lamps in signals ahead proved lit (the stop signal) Any separate track sections up to the stop signal proved clear (this would generally be where a berth track is present for approach control purposes; this track section would also act as a replacement track section for the distant which, in the view of the RSSB, would be a suitable method to be compliant with GK/RT0060 Clause C7. 4). The distant would display a yellow aspect if the associated stop signal was at red and a green aspect if the stop signal was at green. The distant signal would be replaced when the stop signal is replaced which would either be as a result of the train passing the stop signal (normal signal disengagement), the forward route being 'pulled' or the application of SGRC (SGRC is being provided with one button per signalling island). The current RGS was written for the historic This alternative action will reduce rescue situation where locomotives had a braking times for failed locomotive hauled trains on capability worse than the coaches they were Chiltern Railways routes and allow better hauling. The class 67 is a modern use of available line capacity since a cl 67 locomotive with braking capability better running light engine or hauling a short train than the figure 3 curve of GM/RT2042 (for can run at the permissible speeds. This use on lines signalled to GK/RT0024 approach is reasonable since the brake appendix 3) and therefore this RGS capability of a cl 67 is sufficient for all assumption is not appropriate to the cl 67 signalled routes on Network Rail locomotive. Complying with the current infrastructure. The class 67 is fitted with RGS results in: · Under utilisation of track automatic sanders and modern WSP capacity due to reduced running speeds of systems to minimise the risk of poor rail cl 67 running light on ECS movements. · adhesion. Chiltern Railways drivers will be Increased rescue times for rescuing failed briefed on this derogation pending planned trains with a cl 67 locomotive. revision of TW3 to permit this. Applicant Organisation Network Rail Certificate Issue Date 04/01/2012 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 17/11/2011 Deviation Status Current The Chiltern Railways Company Ltd ("Chiltern Railways") 25/11/2011 N/A TOM 08/11/2011 Current Low severity: marginal non-compliance of Network Rail less than 1000 m radius over a length of about 40 m. Passenger safety will not be significantly affected by the non-compliance. 22/03/2012 N/A INS 16/11/2011 Current As part of the Sussex Route Surburban Train Lengthening project, Platform 15 (Down Brighton Slow Line) at Clapham Junction is to be extended to accommodate 10-car trains (presently it accommodates 8car trains). Platforms 15 and 16 make up a double-faced island platform except for a short single-faced section of Platform 15 at the London end. It is necessary to raise the level of the copers on Platform 15 to provide a compliant stepping distance. This requires the introduction of a step on the island platform (15/16) and an accompanying protective fence. As a consequence the width of the first 30m of Platform 16 will be less than 2. 5m: the minimum width will be 2. 0m. Similarly, the distance of a 30m length of the fence from the edge of Platform 16 will be less than 2. 5m. The speed of trains through Platforms 15 and 16 will remain at 20mph. Within the scope of the project (timetable Network Rail and cost) it is not reasonably practicable to provide a compliant solution. The degree of risk to users of the network associated with the non-compliance is low. Relatively low: the risk to users of the network is deemed to be acceptable. The overall objective of the Sussex Route Suburban Train Lengthening project is to increase passenger capacity and reduce overcrowding whilst maintaining or improving safety. The works at Clapham Junction will provide an extended platform that is compliant with regard to stepping distances, passing and lateral clearances. Currently, Platform 15 is non-compliant with regard to both horizontal and diagonal stepping distances. These non-compliances will be eliminated and thereby improve safety, and outweigh any risks generated by the introduction of a narrow platform. 15/12/2011 N/A INS 16/11/2011 Current South West Trains (in association with Wessex Route) is seeking ways to reduce station overruns where misjudgement of braking distance is a factor. Sign AK102 allows for markers from 300m on the approach to a location (with additional markers up to 600m if required). These signs are considered insufficient distance from the station to give drivers advance information of a station that could be difficult to stop at. South West Trains views the use of station South West Trains approach markers as one of the measures for mitigating against station overruns where misjudgement is a factor. South West Trains is continuously reviewing its Professional Driving Policy and route learning documentation over affected routes to brief locations that may be difficult to stop at. Section 13 of this form provides some relevant statistics where overruns have generally reduced since the introduction of station approach markers to provide a reference point for Drivers to judge their braking. Proposed locations for station approach signs The current proposals for the signs at Kempton Park and Claygate are recommendations from the South West Trains Autumn Preparedness Group. Both these locations had a high instance of station overruns during the leaf fall season in 2009. It is proposed that these signs become permanent installations. Design of sign Sign AK102 has been used as a basis for the station approach signs - although dimensions have been modified to allow inclusion of a place name. The station approach sign to have a white reflective background (Class 1 reflectivity or better) with black lettering and red numerals. 10/11/2011 N/A CCS 20/10/2011 Current Page 103 Deviations Register RGS Number GKRT0045 RGS Issue Number One RGS Title Lineside Signals, Indicators and Layout of Signals Certificate Number 11-158-DGN Title Use of Standard Alphanumeric Indicators at SN324 and SN326 with theoretical 80mph approach. GKRT0045 One Lineside Signals, Indicators and Layout of Signals 11-156-DGN This non-compliance application relates to 5.1.2.4 EK5126 signal at Margate station only. Margate station is within the area of the East Kent Resignalling Phase 1 Project which is undertaking a full resignalling of the area bounded by Sittingbourne, Minster and Kearsney stations and all signalling equipment in the area is new. The existing track layout in the Margate area is not being significantly altered. This non-compliance application relates to EK5126 signal at Margate station only. Margate station is within the area of the East Kent Resignalling Phase 1 Project which is undertaking a full resignalling of the area bounded by Sittingbourne, Minster and Kearsney stations and all signalling equipment in the area is new. The existing track layout in the Margate area is not being significantly altered. GKRT0045 One Lineside Signals, Indicators and Layout of Signals 11-154-DGN Hayes Station, SN281 non-provision of SI route indication for straight on route 5.1.2.4.c) SN281 - 17 135m - approx. 10 1/2 mp - Up Relief, MLN1 GIRT7033 Two Lineside Operational Safety Signs 11-153-DGN Termination boards at a high risk low adhesion site B10 National. The standard currently shows a 'commencement board' for a site of low adhesion, but there is nothing that refers to a termination board (picture of sign attached). There are currently a number of sites on the Western route where both a commencement board and termination board are located to inform drivers of the extent of a site of low rail adhesion. Without the termination board, the driver will have no visible (line side) indication of where the site of low rail adhesion will end. GIRT7016 Four Interface between Station Platforms, Track and Trains 11-151-DGN Leagrave Station Platform 2 Extension: Platform Width 7.2 and 7.4 Platform 2, Down Slow, line speed 85mph. It is proposed that the first 6. 3m of the single face platform extension at the C/E will taper from 2500mm to 2319mm at the platform end. Platforms are constructed but are not in use: they are due to come into operation in 2012. It is not considered reasonably practicable to provide a compliant solution Platform 2: A 239. 5m platform has been provided for 12 car class 377 trains (243m long). The area of noncompliance will affect the first 7. 3m of the 1st carriage. Extensive reconstruction would be required to provide a compliant solution. With the train stopping 1m beyond the stop board, only the first passenger door will be in an area of platform where the width is below 2500mm. Current Deviations Register as at 09 May 2016 RGS Clause Appendix C.1.1 Scope Nature and Degree SN324 - 20 108m, SN326 - SN326 20 115m, The project proposes to use Standard HLL. Indicators (performance category 2) on signals SN324 and SN326 when the approach speed is theoretically 80mph. The permitted speed reduces approximately 200m in advance of the signals to 50mph. Whilst it would be technically feasible to widen the tunnel sections in this area to gain the space required for PLJI, it would be necessary to remove the existing tunnel roof to do so. If the tunnel was enlarged a complicating issue is the waste site through which the tunnel is constructed - with methane barriers between the waste and the tunnel. Track access is limited due to the intensive HEx service. These works would be prohibitively expensive and disruptive. A reduction of speed has also been considered, but the 80mph is necessary for Crossrail and Heathrow Express service/time table resilience. As part of the East Kent Resignalling Phase 1 Project the lines through Margate station are to be resignalled. Trains approaching in the Up direction may be routed into either along the Up Thanet line to platform 3 (a through line) or into the terminal Up Bay line (platform 4). The new signal which shall control this junction (to be numbered EK5126) is to be provided with a standard alphanumeric route indicator which shall display a route indication only for the divergent route into terminal platform 4. This is non-compliant with part c) of GK/RT0045 clause 5. 1. 2. 4 as all the routes lead to station platforms. EK5126 signal is positioned on a straight section of line and has been assessed during the signal sighting process as being visible from the signal in rear which is 780m away and the line speed on the approach is 80mph. The divergent route into terminal platform 4 is to be approach controlled from red. A standard route indicator is a category 2 device which means that it is required to be readable at 250m from the signal at a maximum speed of 60mph. Clause 5. 1. 3. 3 of GK/RT0045 requires that, where practicable, junction signals are arranged so that a driver can read the route indication at Standards require a SI into a bay platform, however the main line route speed is 60mph which would require the signal to be approach controlled to ensure readability. Risk Assessment/Safety Justification Whilst the enhanced readability of PLJIs is advantageous in many situations, there is no advantage gained here due to the curved tunnel approach with limited signal visibility. These signals are only visible from approx. 220m (there is a Banner Repeater signal in rear of each of the signals affected). The tunnel environment aids signal readability due to the lack of daylight and visual distraction. The distant and banner repeater signals acting as countdown markers for the main signals. Both signals will have ATP loops on approach, and in use for ALL trains. SN324C(M): A standard indicator is currently used on this signal. Due to the addition of a third route at Heathrow Tunnel Junction, it is not possible to retain the existing junction signalling unchanged. The position of this signal is cramped due to it being in the cut and cover part of the Heathrow Tunnels squeezed between the tunnel wall and the kinematic envelope. There is insufficient space to use PLJIs (nos. 1 and 4 would now be required). It is proposed to use a Standard Indicator on this signal for all three routes. SN326C(M): This signal currently has a position 4 PLJI for the main route crossing to the Down Airport (up direction). Due to the addition of a third The fact that the divergent route reads up to the buffer stops in a terminal platform precludes the use of a position light junction indicator in order to comply with the requirements of Network Rail Company Standard NR/L2/SIG/19609 as was identified during a review of draft scheme plans by the Network Rail Major Schemes Review Panel (see item 142 on the East Kent Phase 1 Signalling Renewals MSRP Meeting Minutes version 3. 4) and so a standard alphanumeric indicator was substituted. This was designed to provide an indication only for the divergent route due to the readability performance of a category 2 device being insufficient for use with an unrestricted main aspect sequence at this particular location. This configuration was compliant with the standards in force at the time at which the scheme received Approval in Principle (June 2009). The requirement to display a route indication for all routes from a signal provided with a standard route indicator when at least one of those routes leads into a platform was introduced with the publication of GK/RT0045 in February 2010 by which time detailed control table design and signal erection had commenced. The existence of this non-compliance was Although other indications could be provided this signal has been considered by the Signalling Design team and Signal Sighting Committee. In the wider context of the Stockley Scheme Plan, it is felt that no indication for the straight route at 60mph has a clear meaning and a 'B' for the 25mph entry to the Bay is the clearest arrangement. This also complies with 5. 1. 2. 4. b). Another signal [for a slow speed approach] shows "UR" for this destination. The equipment on SN281 signal is restricted due to it being on a drop cage from a gantry therefore a double indication would be difficult. U and R individually would not uniquely define the destination. It is suggested that the standard should be amended to permit omission of SI indications for highest speed route even if it is through a platform. Amend 5. 1. 2. . 4. . c) to say "If all routes are into a terminus station. " The indications to drivers in this area have been considered and agreed by the TOC/FOC representatives. These indications present the least possible confusion to drivers. In preparation for this autumn (2011), the Western route is looking to inform drivers of a low rail adhesion risk site (both lines) at Camborne station. For this to be effective, the driver needs to be made aware of the location where the low adhesion conditions commence and the location where the risk site ends. The installation of the commencement and termination boards at Camborne is as a result of a risk assessment into Truro and Camborne level crossing arrangements. Removal of the termination board would not assist train drivers. The majority of the platforms comply with GI/RT7016. The Designed Platform Extensions comply with sizing requirements in normal and perturbation scenarios. The affected area affects the first door only of the 1st carriage where passenger density will be at its lowest. The non-compliant areas will have strip lighting mounted on solid fences so as not to create pinch points. Applicant Organisation Network Rail Certificate Issue Date 10/11/2011 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 20/10/2011 Deviation Status Current Network Rail 10/11/2011 N/A CCS 20/10/2011 Current Network Rail 10/11/2011 N/A CCS 20/10/2011 Current Network Rail 20/04/2012 N/A CCS 23/02/2012 Current Network Rail 21/10/2011 N/A INS 16/11/2011 Current Page 104 Deviations Register RGS Number GKRT0045 RGS Issue Number One RGS Title Lineside Signals, Indicators and Layout of Signals Certificate Number 11-149-DGN Title Junction signalling arrangements in the Down direction at Hitchin RGS Clause 5.2.3.3 Scope Flashing aspect sequence approaching K699 signal at Hitchin Nature and Degree The flashing double yellow would need to be displayed on K679 signal which currently displays a flashing single yellow for the south junction when 689 is set for the divergent route. This would lead to a noncompliance with 5. 5. 1. 1 d) of the standard as it would be an overlapping flashing aspect sequence. The alternative would be to provide an alternative method of junction signalling for either K689 or K699, however there are physical constraints preventing splitting distants and the use of MAR (approach release from red) at either junction would be operationally restrictive and not enable the planned timetable to be delivered. Risk Assessment/Safety Justification Applicant Organisation A driver being signalled through the south Network Rail junction from Down Fast to Down Slow will receive a normal aspect sequence which is fully compliant. Additionally the routing will be confirmed by 689 PRI which can display a Position 0 or Position 1 arrow. A driver being signalled through the north junction from the Down Fast to either the Down Slow or the Down Flyover will receive a steady double yellow on 679, a Position 0 arrow on 689 PRI, a flashing single yellow on 689, a Position 1 or 2 arrow on 699 PRI (note that 697 PRI can not also be illuminated). The arrangements enables: - trains on the Down Fast to be signalled into the Down Slow platform quickly to clear the Down Fast for following trains, trains on the Down Fast to be signalled via the north junction to the Down Flyover with minimal loss of speed hence clearing the Down Fast quickly, drivers to clearly establish which junction they are being routed through. There is sighting of K689 from K679. GMRT2000 Three Engineering Acceptance of Rail Vehicles 11-148-DGN Derogation Steam Locomotive 6.6.3 and Appendix H1 Operation of the following preserved Steam Locomotive on all lines, as agreed by the NRAB and subsequently by the Licensed Operator. GWR 57xx Class 0-6-0PT Steam Locomotive TOPS No. 98452 Painted No. L94 (7752) Class / Power Classification 4F Wheel Arrangement 0-6-0T Maximum Speed 45 mph. It would not be practical to revise the RGS to include steam locomotives, due to their wide diversity of design from modern traction units and the general scarcity of technical information now available to prove their compliance or otherwise. In a number of recent re-issues of RGS, specific exemptions for steam locomotives, shown in the previous issues, have been withdrawn, increasing the number of non-compliances for which derogation has now to be sought. Steam Locomotives are in a minority group, and subject to the restrictions in GM/RT2000 for "Heritage Vehicles". GCRT5112 Two Rail Traffic Loading Requirements for the Design of Railway Structures 11-147-DGN Edinburgh Waverley Station; Platforms 8 and 9 Market Street Footbridge Support Columns; Design of Structures to Resist Collision Loads 7.1.2.3 Edinburgh Waverley Station; Platforms 8 and 9, Market Street Footbridge Support Columns; Design of Structures to Resist Collision Loads. GIRT7016 Four Interface between Station Platforms, Track and Trains 11-146-DGN Bushey Station Platform 3 (former Down 7.2.1 and 11.1.4 Fast Line Platform): minimum platform width, and width of recess beneath platform. As indicated in Appendix 7 of this document. The preserved steam locomotive is one of 862 locomotives of its class which ran safely over the British railway infrastructure since its introduction by the Great Western Railway in 1930 and continued until its withdrawal from revenue service with London Transport in 1971. The locomotive is intended for Heritage Operation only. In order to achieve compliance with RGS the cost would be prohibitive and such engineering change would also destroy the locomotive's fundamental nature and authenticity as a "heritage" vehicle. Making the locomotive compliant would, in many instances, be impractical because of the bulk and location of the locomotive boiler. Relatively low as the infrastructure adjacent to the columns does shield the columns from impact. The design achieves a resistance to collision loads of 440kN at 3. 0 m above ground (against 500kN specified) and 400kN at 1. 2 m above ground (against 200kN specified). It is considered that the risk of a train derailment itself is minimal and, in the extremely unlikely event this should occur, the mitigating factors, described in section 9 - Proposed alternative actions render the chances of a derailment leading to bridge collapse to be extremely small. The Corporate Social Responsibility profile of the company is also increased by maintaining the integrity of Edinburgh Waverley Station as a listed building, and by retaining the serviceable parts of the station as opposed to being replaced unnecessarily. The proposed solution will minimise the impact on station users, in particular limiting the amount of time that the New Street car park lift is out of action for disabled access. All of the above will be achieved with a minimal risk due to the factors detailed earlier in this form. In particular, it is felt that the low line speeds together with the design against disproportionate collapse means that, even Due to site constraints, it is not reasonably practicable to provide a compliant solution. Low risk to passengers. Based on London Midland figures, the number of passengers alighting at Platform 3 will be less than 40 (see attached data on current passenger usage). The reduced width is deemed to be adequate for the number of passengers likely to alight on the proposed noncompliant length of the platform. GKRT0045 One Lineside Signals, Indicators and Layout of Signals 11-144-DGN Provision of route indicators on WH1019, WH1014, WH1034, WH3005, WH3010, WH3016 &amp; VS3022 (Thameslink Core Area) Current Deviations Register as at 09 May 2016 5.1.3.3 and 5.1.3.4 By inspection, the current bridge dating from 1901 is non-compliant with clause 7. 1. 2. 3. The bridge is to be replaced in 2011/12 and it will not be possible to locate support columns out with the hazard zone or to achieve the design load resistance specified in clause 7. 1. 2. 3. As the existing bridge is to be taken out of passenger use in October 2011; no immediate action is planned. In constructing the new bridge, it is not reasonably practicable to comply for the reasons (refer to attached drawing C1555200-019-rev00 and photos 1-4 to crossreference column numbers with locations): · Space constraints mean that support columns 1, 2 and 3 cannot be moved further from the cess rail. It is not possible to bear the bridge directly onto the main train shed wall between platforms 9 and 10, as the ability of the wall and foundations to sustain this cannot be confirmed. · Due to pile congestion, the columns cannot be designed to withstand the necessary loading. · Due to the station's Grade A listed status and location within a World Heritage Site, the new bridge is subject to strict architectural guidelines which require a slim and unobtrusive structure. OLE clearances and DDA compliance with floor levels are Bushey Station: minimum platform width, The aim of the project is to bring back into and width of recess beneath platform. operational use the existing disused Bushey Station is located on the junction of Platform 3 at Bushey Station. The the West Coast Mainline (LEC1) and the DC reinstatement of this platform will require a lines (CWJ) between Euston and Watford minimum usable platform length of 88m to Junction Station. The former Down Fast line accommodate four-car trains. Trains are platform, Platform 3, has been disused for planned to stop at the station only when the over a decade. It is proposed to reinstate Slow lines are blocked every other week to this platform into operational use when enable maintenance to be undertaken on the maintenance works are being undertaken on WCML. The stopping services are expected the WCML. to be: Monday to Friday, 3 trains after 22: 00; Saturday, 3 trains after 20: 00; Sunday, 5 trains hourly between 0700 and 1200. Compliant stepping distances will be provided in accordance with GI/RT7016 and also the design of the platform reinstatement will comply with requirements of GE/RT8025. At the southern end of the station, Platform 2 is approximately 750mm higher than Platform 3 and there is an existing brick retaining wall separating the two (refer to Photos 1 &amp; 2). Due to the constraint of the site, an 18. 0m length at the southern end of Platform 3 will have a width of less than 3000mm, the minimum width will be 2200mm. The position of the existing platform riser wall in relation to the track does not have sufficient clearance to provide the required recess beneath the platform Signal Numbers WH1019, WH1014, The majority of the Thameslink Core route WH1034, WH3005, WH3010, WH3016 is contained within tunnels, where clearance &amp; VS3022. is tight and we have been unable to install Standard Indicators (SI) on the junction protecting signal. All new signals have been signal sighted and the site restrictions limit the project to the use of Miniature Indicators (MI) instead. Compliance with 5. 1. 3. 3 would require that the junction signals were held at red until the Category 5 MI is guaranteed to be readable (65m). This would restrict the speed of trains and increase the number of trains approaching red aspects with the potential of SPADs. Certificate Issue Date 07/10/2011 Certificate End Date N/A Lead SC CCS Lead SC Approval Date 22/09/2011 Deviation Status Current West Coast Railway Company 24/10/2011 Ltd N/A RST 06/10/2011 Current Network Rail 02/04/2012 N/A INS 14/09/2011 Current Network Rail 21/10/2011 N/A INS 14/09/2011 Current The previous standard GK/RT0031 gave the Network Rail category rating for the MI's as category 3 100m viewable distance. We consider it appropriate to not approach control these signals because: - The Core Route line speed is a maximum of 30mph. Inadequate clearances for alternative indicators Performance and SPAD risk from applying standard The distance from the sighting point of the signal to the AWS is an adequate distance to bring a train under control. The signal size / type as signal sighted is adequate at this line speed and provide suitable reading distance. 100m sighting distance in use today along the route. the route indicators are in limited natural daylight. the route indicators will not be used for normal running. This was a requirement of the sighting committee who were satisfied with the readable distance of the indicators. A HazID (attached) did not identify any additional risks in this approach. 07/10/2011 N/A CCS 22/09/2011 Current Page 105 Deviations Register RGS Number GIRT7016 RGS Issue Number Four RGS Title Interface between Station Platforms, Track and Trains Certificate Number 11-143-DGN Title Letchworth Station: clearance of isolated column to platform edge RGS Clause 6.5 Scope Letchworth Station: clearance of isolated column to platform edge. GIRT7016 Four Interface between Station Platforms, Track and Trains 11-142-DGN Caerphilly Station - new support to existing footbridge 6.2.2 b) and 8.1 b) Caerphilly Station, new support to existing footbridge. GIRT7016 Four Interface between Station Platforms, Track and Trains 11-141-DGN Cardiff Queen Street Station, Platform 5 reduced depth of clearance under platform edge. 11.1.4.1 Cardiff Queen Street Station, Platform 5: reduced depth of clearance under platform edge. GIRT7016 Four Interface between Station Platforms, Track and Trains 11-140-DGN Down Barry Platforms 6 and 7: location of buildings and structures on platforms. 6.2.2 b) GMRT2461 One Sanding Equipment Fitted to Multiple Units and on-track Machines 11-137-DGN Revised 21-11-2011 Fitting manually operated sanders with sanding rate of 2kg/wheel/min to classes 14X and 153 units. 9.1, 9.3.1 Current Deviations Register as at 09 May 2016 Nature and Degree The Up platform at Letchworth Station is to be extended by 51. 6m to accommodate 12car train services to/from London Kings Cross. The platform is to be 2. 75m wide along its length: the width is restricted by the topography of the site (it is located in a cutting). OLE mast EC55/22 is located in the Up cess, 23m within the proposed London end of the extension at the base of the cutting slope. The mast lies within the footprint of the proposed extension and supports a cantilever from which is suspended the 25kV OLE for the Up line. As it stands, the mast will have a 1933mm clearance to the edge of the proposed platform. The line speed on the Up line is 85mph. Due to the topography of the site, it is impracticable to provide a compliant solution. As part of the Cardiff Area Resignalling Renewal scheme a new bay platform is to be provided at Caerphilly Station. There is an existing footbridge spanning the station that is owned by a Third Party. The bridge does not provide rail passengers access to the platforms; it is a means for non-rail passengers to cross the tracks without accessing the station. The bridge has a clearance between the existing platform edge and its support in excess of 2500mm, and a clearance between the platform level to the underside of the lowest structural member in excess of 2500mm. It is proposed to install a new platform and relocate the footbridge support to the centre of this to give clearances of 2315mm to each side of the support to the platform edge. See attached drawing 5091070-RLS-CSE0006-A02. This will also provide a minimum headroom to the bay platform side of 2230mm - increasing to 3046mm over a 1000mm length. The length of the platform affected will be kept to a minimum and will comprise the width of the column (outline design sizes 305x305 UC). During construction, hoardings will be required to undertake the works but this will have no effect as this area of the platform is nonAs part of the Cardiff Area Resignalling Project (CASR), a number of enhancements are being provided to support an increase in train frequency. A key part of these enhancements is the plan to reinstate the disused platform at Cardiff Queen Street Station (to the West Side) to be named platform 5. The new platform will support the proposed Up Llandaff Loop line. The current platform spans two subways: · Passenger Subway - CAM (1 m 9. 5 ch) 200 mm substandard over a length of 5 m · Luggage Subway - CAM (1 m 13. 75 ch) 200 mm substandard over a length of 4 m At these locations, the front face of the passenger subway is built into the front face of the platform. Due to the requirements of the new P-way alignment, the platform wall will be reconstructed to provide a compliant 300 mm overhang but, due to their location, it will only be possible to provide a 100 mm recess over the length of the subways. Risk Assessment/Safety Justification The signal CF2947 is to be positioned at 170. 5mp -92m serving Down Barry (Platform 7 side As part of the Cardiff Area Signalling scheme, it is necessary to install a cantilever structure on Platforms 6 and 7. The proposed position of this structure will not provide the minimum lateral clearance of 2500 mm. The proposed clearances are 2478 mm and 2412 mm for platforms 7 &amp; 6 respectively. National - class 14X and 153 units Both types of units considered here have 4 axles only. The group standard was written to accommodate conventional 2 car units with a total of eight axles. For Classes 14X &amp; 153 units, without a complete redesign and rebuild, it is not possible to comply. The stopping distance under low adhesion conditions is naturally lengthened, and it can get out of driver's control, unless mitigations are considered. The option not to fit sanding for braking is not acceptable due to the risks described below. Two incidents occurred just over three months apart, in each case a class 142 unit collided with a stationary train in a platform, when the class 142 unit was permitted to occupy a part of a platform already occupied by another train in normal working. On 03/10/2009 unit 142016 forming 2D11 passed signal T895 at danger and collided with 1S07, an IC 225 set, in platform 4 at Darlington station. Damage was minor and no serious injuries occurred. The cause was rail contamination with leaf residue believed to have been exacerbated by the IC225 set on the approaches to Darlington station following high winds carrying leaves from far away to the site of the station approach which did not have a history of low adhesion Applicant Organisation Network Rail Certificate Issue Date 27/10/2011 Certificate End Date N/A Lead SC INS Lead SC Approval Date 14/09/2011 Deviation Status Current The restricted space at the station does not Network Rail make it reasonably practicable to provide a compliant solution. Low risk - the scale of the non compliance for clearance is 185 mm to either platform face and up to 270 mm vertically. The proposed bay platform 1 is provided with a buffer stop, and so trains will be travelling towards a stop at a maximum permissible speed of 25mph. The existing Platform 1 (Proposed Platform 2), servicing the Dn Rhymney has a 50 mph line speed. The length of platform affected is 305 mm (based on the proposed 305x305 UC being confirmed at GRIP 5-8). The track is straight coming from the Cardiff direction with good sighting changing to a 2050 m radius curve at the bridge. The reduced headroom will be highlighted to the public via signage and black and yellow barrier tape. It is considered that there is an insignificant risk to passenger safety. 22/12/2011 N/A INS 14/09/2011 Current Low risk to passengers. Relatively short non- Network Rail compliant lengths, and low line speed of proposed Up Llandafff Loop (20mph). 22/12/2011 N/A INS 14/09/2011 Current The restricted space on the platform Network Rail precludes the provision of a compliant solution. Low risk. The proposed arrangements will not introduce an unacceptable risk to passengers using the platform. The non-compliances are 22 mm on platform 7 and 88 mm on platform 6 over a length of 610 mm. The line speed through the station is 20 mph, the track is straight and there is good visibility at the location. The risk to passenger safety has been assessed to be insignificant. There are three consequences of adopting Network Rail the proposed alternative: The sand delivery rate will give an enhanced braking rate in low adhesion conditions equivalent to an increase of 3% g above the prevailing adhesion level. Due to the reduced number of axles on the units under consideration the train will stop with all wheels likely to be on the sand deposited by the same train. There is a risk that train detection may be lost. The increase in adhesion following the deposition of sand by these units is in line with that seen on all other multiple units fitted with san