Goddard Space Flight Center HST Project ACS-R SMOV Optimization Campaign Iteration 1 Summary June 2, 2009 Ed Cheng Goddard Space Flight Center Summary HST Project • • Performance is outstanding, and as intended. ACS-R Team and STScI agree that the Optimization Campaign can be truncated. Current SMS constraints allow us to shorten to two weeks. Enables early start to normal SMOV activities (and science). • • Discovered a minor bug and making some minor tweeks. Realtime uplink commanding is limited to adjusting one set of voltage offsets. Mostly affects half-speed mode. • Bias 100 sec Dark Mission accomplished! ACS-R SMOV Optimization Campaign 2 June 2, 2009 Goddard Space Flight Center Performance Summary HST Project Parameter Jan 2007 (actual) May 2009 (predicted) “Problemmatic” May 2009 (OC Iter 1) Read noise (e-) C&S: 5.5 DSI: 4.0 10 DSI: 4.0-4.8 C&S: 4.4-5.7 Dark current (e-/pix/hr) 10.7 15 100 20-25 Hot pixels (%) 0.68 1.1 1.5 1.1 84,000 84,000 40,000 ~80,000 < 0.1 < 0.1 0.5 TBD 0.999949 0.999921 0.99990 0.99989 Cross-talk 4x10-5 4x10-5 4x10-4 1x10-4 Gain instability (%) < 0.1 < 0.1 < 0.2 TBD Full well depth (e-) Non-linearity (%) CTE ACS-R SMOV Optimization Campaign 3 June 2, 2009 Goddard Space Flight Center Optimization Campaign Timeline HST Project Deletion Recommended Now ACS-R SMOV Optimization Campaign 4 June 2, 2009 Goddard Space Flight Center Iteration 1 Main Discoveries HST Project Discovery Action Minor timing irregularities noted in oscilloscope mode data. Bug in Flight Assembly Code found and resolved in ground testing. No impact to normal operations. Will be repaired in final FAC drop. Half-speed mode noise is unrealistically low. Saturation of ADCs because offset is not optimized for half-speed mode. Offset change requested in realtime uplink. Science Data Control Register Examining result more carefully. Taking optimization shows lower noise for a non- a little more time before deciding on default value. uplinking any new values. Reset Gate voltage is well-behaved at a lower value than pre-failure. Keeping the new default (8V) instead of the pre-failure value (12V). Slight noise benefit and stability benefit. Margin demonstrated by proper operation at 7V. “Hypersensitivity” of Quadrant to C a small change in Vod. Investigation in progress. Default value appears to give good performance. ACS-R SMOV Optimization Campaign 5 June 2, 2009 Goddard Space Flight Center Realtime Uplink Request HST Project ACS-R SMOV Optimization Campaign 6 June 2, 2009 Goddard Space Flight Center To Do HST Project • • Understand the funnies and figure out if we want an uplink for Iteration 2 to address these. Confirm results with Iteration 2 data. ACS-R SMOV Optimization Campaign 7 June 2, 2009