IPL Harding Street BESS Project J401 Interconnection Process Task Force March 26, 2015 1 1 174 MWs and growing 2 2 Tait Energy Storage Resource • Interconnection filed November 2012 • Project approval March 2013 • Commercial Operations September 2013 • 40MW flexible range • More than 160,000 MWs regulation served as of September 2014 3 3 64 MW Storage Resource - PJM 4 4 Over 30 GW or simple cycle gas turbines expected in next 10 years in US alone, 3X globally 5 Storage a better option than new peakers High utilization for system security, peaking, and renewable support MISO Interconnection Queue Project J401 • New IPL project • The 20 MW (40MW Flexible Range) battery installation to be in service Spring 2016 • Can expand up to 200MWs in the future if warranted • This site can access most of IPL’s units at this site for potential black start • Will be connected to the 138 kV • IPL is an Indiana utility which is owned by AES 7 7 HSS 20 MW (Flexible 40 MW) Battery Storage Project A 1 hour battery design 8 8 Energy storage equipment is in rows of racks, similar to computer equipment in a data center Cells Modules Trays Moveable & Scalable Racks 9 9 9 Permitting profile is similar to a warehouse or data center, not a traditional electricity generation project Site Permitting Profile Energy Storage Warehouse Power Plant Air Water Fuel Building Permit Stormwater No air emissions No process water No fuel Required Required Required Required Required Project Attributes • • • • • • • 10 Economic development Technology leadership Environmental friendly solution Enables renewables Modernization of infrastructure More efficient use of existing power plants Exciting 10 Energy storage warehouse design and permitting profile similar to a datacenter Building construction One story building, concrete and steel construction Firewalls between equipment rooms and for outside walls Occupancy class per International Building Code Fire Suppression system Equipment: Power conditioning systems (inverters) Sealed cell batteries, data center racks 425 tons of cooling Switchgear and transformers Tie-line to existing 13.8kV GSU transformer, shared with combustion turbines 11 11 10 MW Warrior Run BESS is a 5,000 square foot building, and has a 138kV transmission connection, COD 2015 12 12 CUSTOMER/GRID BENEFIT – FREQUENCY REGULATION • Frequency Regulation insures that supply and load of MWh match on realtime basis • The first picture shows the traditional way to provide frequency regulation • A generator is sent an AGC signal (green dotted line) to match load (red line) • Close, but not perfect match • Not ideal • Energy Storage is a superior way to provide for frequency regulation since it can instantaneously add or remove energy from the grid • As noted on the second picture where the green and red lines are in sync • Pictures provided by PJM 13 13 Continuously on Continuously charge 14 14 Can Provide Energy at the Peak Example is a 4 hour battery 15 15 CUSTOMER/GRID BENEFIT – 5MW CAPACITY VALUE • 20MW BESS can provide 20MW for 1 hour or 5MW for 4 Hours • IPL is working within the MISO process to receive 5MW of capacity value for the project for 2016/17 PY • Batteries as a source of capacity will be an increasingly important resource to meet peaking capacity in the US • Over 30 GW or simple cycle gas turbines expected in next 10 years in US alone, 3X globallly • AES has aggressive goals to build BESS to met this capacity need 16 16