Math 126-104 Spring 2013 Quiz 8, Feb. 15 Carter Name A bag of sand originally weighing 144 lb was lifted at a constant rate. As it rose, sand also leaked out at a constant rate. The sand was half gone by the time the bag had been lifted to 18 ft. How much work was done lifting the bag this far? (Neglect the weight of the bag and the lifting equipment.) Solution. Since the weight of the bag is a linear function of its height, we compute the changes ∆x = (x1 − x0 ) = 18 and ∆y = (y1 − y0 ) = −72 for (x0 , y0 ) = (0, 144) and = (x1 , y1 ) = (18, 72). Thus the weight as a function of height is w = 144 − 4x. To compute the work, we use the integral Z W = 0 18 18 2 (144 − 4x) dx = 144x − 2x = 144 · 18 − 2 · 182 0 = 8 · 182 − 2 · 182 = 182 [8 − 2] = 6 · 324 = 36 · 54 = 2025 − 81 = 1944 ft.lbs.