Regulating Electricity and Natural Gas in Peru: Solutions for a Sustainable Energy Sector by MASAHU Alex Cade Breekel OF TECHNOLOGY B.S. Mechanical Engineering University of Texas at Austin, 2011 MAY 2 9 2014 L LIBRARIES Submitted to the Engineering Systems Division in partial fulfillment of the requirements for the degree of Master of Science in Technology and Policy at the MASSACHUSETTS INSTITUTE OF TECHNOLOGY June 2014 © Massachusetts Institute of Technology 2014. All rights reserved. Signature redacted A u th or . . . ............................. .................... Engineering Systems Division SntMay ur rd 9, 2014 Signature redacted Certified by.... Ignacik Perez-Arriaga Visiting Professor of Engineering Systems Division Signature redacted C ertified by ... Thesis Supervisor .......................... Carlos Batile Lopez Visiting Scholar at the MIT Energy Initiative Signature A ccepted by ......... redacted Thesis Supervisor ................. Dava Newman Professor of Aeronautics and Ast onautics and Engineering Systems Director of Technology and Policy Program E 2 Regulating Electricity and Natural Gas in Peru: Solutions for a Sustainable Energy Sector by Alex Cade Breckel Submitted to the Engineering Systems Division on May 9, 2014, in partial fulfillment of the requirements for the degree of Master of Science in Technology and Policy Abstract Peru is one of the fastest growing countries in Latin America, thanks in part to industry fueled by generous endowments of hydro power capacity and natural gas reserves. However, investment in electricity generation capacity has not kept pace with the rapid increase in demand and threatens to stymie future economic growth. A flawed regulatory environment is to blame, and specific roadblocks to increased generation investments include a dysfunctional capacity payment system, low administratively determined gas prices, and structural barriers to investment in hydro. This thesis provides an overview of the design, functioning and historical context for energy regulation in Peru; identifies the key barriers to generation investment; analyzes two potential regulatory reforms; and recommends the specific reform that has the most promise for reigniting investment in hydro. Two reforms strike at the root of the current problem: The first, increasing the price of natural gas for power generators up to the economic netback value of LNG exports, would make hydro a viable investment but would hit consumers with very large increases in their electricity bills. An alternative approach, a reform to the capacity payment mechanism, could provide the same benefits in terms of drawing new generator investment but at a much lower cost to consumers. It would also offer benefits for regulatory discretion in the future evolution of the grid. Thesis Supervisor: Ignacio Perez-Arriaga Title: Visiting Professor of Engineering Systems Division Thesis Supervisor: Carlos Batlle Lopez Title: Visiting Scholar at the MIT Energy Initiative 3 Acknowledgments Many people made meaningful positive impacts on me during my time at MIT, both professionally and personally. In particular, I would like to acknowledge the contribution the following individuals made towards completion of my degree: Carlos Batlle, for offering regulatory insight throughout the thesis writing process and connecting my interest to a relevant and timely topic. Ignacio Perez-Arriaga, for instilling in me a passion for energy policy and regulation and the fundamentals for analysis thereof. Melanie Kenderdine, for providing the opportunity to work on the MIT Energy Initiative Symposium, through which I learned the fundamentals of stakeholder involvement for addressing relevant and timely energy policy issues. I would also like to thank all of my gracious hosts during my time in Lima. The learning opportunity was immensely beneficial for completion of the thesis and for understanding how regulation works in the real world. Furthermore their thoughtful time spent explaining the nuances of Peruvian regulation and policy will not be forgotten and I hope to one day return the favor. 4 Contents 1 Introduction 11 2 Evolution of the Peruvian Electricity Sector 15 2.1 Liberalization of the Electricity Sector: The Electrical Concession Law 16 2.1.1 Organization of the Market . . . . . . . . . . . . . . . . . . . 17 2.1.2 B usbar Tariffs . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 2.1.3 The Capacity Payment Mechanism . . . . . . . . . . . . . . . 19 2.1.4 The Advent of Natural Gas . . . . . . . . . . . . . . . . . . . 21 2.1.5 Electricity Sector Troubles: Energy Consumed Out of Contract 23 2.2 2.3 Elect ricity Sector Reform: Law to Ensure the Efficient Development of El ectricity G eneration . . . . . . . . . . . . . . . . . . . . . . . . . 25 2.2.1 A uctions .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 2.2.2 Transmission Planning . . . . . . . . . . . . . . . . . . . . . . 27 2.2.3 Trouble Strikes Again: Energy Shortages of 2008 . . . . . . . 28 2008 to Present: Ad Hoc Regulation . . . . . . . . . . . . . . . . . . . 30 2.3.1 The Current Geography of Supply & Demand . . . . . . . . . 30 2.3.2 Single Node Pricing . . . . . . . . . . . . . . . . . . . . . . . . 31 2.3.3 C old Reserves . . . . . . . . . . . . . . . . . . . . . . . . . . . 32 2.3.4 Promotion of Hydro Generation . . . . . . . . . . . . . . . . . 32 2.3.5 The Southern Energy Node . . . . . . . . . . . . . . . . . . . 34 2.3.6 Renewable Energy Promotion . . . . . . . . . . . . . . . . . . 36 2.3.7 Alternative Regulatory Approaches . 37 5 3 4 Methods 39 3.1 Energy Price Approach . . . . . . . . . . . . . . . . . . . . . . . . . . 39 3.2 Power Price Approach . . . . . . . . . . . . . . . . . . . . . . . . . . 42 3.3 Hydro Generation Assumptions . . . . . . . . . . . . . . . . . . . . . 43 Results and Discussion 45 4.1 Energy Price Approach . . . . . . . . . . . . . . . . . . . . . . . . . . 45 4.1.1 48 4.2 Power Price Approach 4.2.1 5 Political Costs and Economic Benefits of Higher Gas Prices . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49 Design of a Power Payment Reform . . . . . . . . . . . . . . . 50 Conclusion 55 A Economic Dispatch Model Formulation 61 B Hydro Plant Revenue Calculations 63 C Secondary Market for Pipeline Capacity 65 6 List of Figures 1-1 Generation Reserve Margin, 2004 - 2014 . . . . . . . . . . . . . . . . 12 2-1 Route of the Camisca Pipeline . . . . . . . . . . . . . . . . . . . . . . 22 2-2 Generation Investment, 1990 - 2012 . . . . . . . . . . . . . . . . . . . 23 2-3 Energy Prices and Energy Consumed Without a Contract, 2004-2012 24 2-4 Transmission Investment, 1990 - 2012 . . . . . . . . . . . . . . . . . . 28 2-5 Generation by Fuel Type and Capacity Margin, 2004 - 2009 . . . . . 29 2-6 Geography of Electricity Supply and Demand . . . . . . . . . . . . . 30 2-7 Routes of the Camisea Pipeline and Southern Peruvian Pipeline . . . 35 3-1 Generation Supply Curve, 2013 . . . . . . . . . . . . . . . . . . . . . 40 3-2 Generation Supply Curves for Model Scenarios . . . . . . . . . . . . . 41 4-1 Schematic of Supply and Demand for Electricity . . . . . . . . . . . . 46 7 8 List of Tables 2.1 Wholesale Gas Prices Around the World . . . . . . . . . . . . . . . . 23 2.2 Cold Reserve Generators . . . . . . . . . . . . . . . . . . . . . . . . . 32 3.1 Hydro Cost Assumptions . . . . . . . . . . . . . . . . . . . . . . . . . 43 3.2 Hydro Availability Factor . . . . . . . . . . . . . . . . . . . . . . . . 44 4.1 Costs and Revenue Results from Model Scenarios . . . . . . . . . . . 46 4.2 Hydro Revenue Results from Model Scenarios . . . . . . . . . . . . . 47 9 10 Chapter 1 Introduction Located on the western coast of South America, Peru is the sixth largest economy in Latin America and is one of the fastest growing. GDP has increased 6% per year over the last decade while the national poverty rate dropped from 50% to 25% (United States Central Intelligence Agency, 2014; The World Bank, 2014). Much of this remarkable growth is the result of recent private sector investment in extractive industries fueled by abundant domestic energy resources. Peru is the world's largest exporter of silver and second largest of both copper and zinc, and the extractive industry accounts for 60% of all exports (Asian-Pacific Economic Cooperation, 2013; United States Central Intelligence Agency, 2014). The success of recent commercial and industrial activity is in part attributable to Peru's generous endowments of hydro power capacity and natural gas reserves. Future growth prospects hinge largely on the ability of the government to continue to put those domestic natural resources to productive use. Investment in electricity generation capacity has not kept pace with the rapid increase in demand and threatens to stymie future economic growth. Demand has grown an average of 7% per year' though generation capacity grew at just 4.9%; demand is expected to continue to outpace supply for the next several years (Inter'Electricity demand in the United States averaged just 1% growth over the same period. 11 American Development Bank, 2013). Tremendous new generation investment will be needed in the medium to long term so that installed capacity can catch up with and sustain rapid demand growth. Creating the right environment for investment rests on prudent policy and regulation of the electricity and gas sectors in Peru. A brief look at the evolution of the reserve margin in Peru - the amount of generation capacity in excess of what is needed to just meet demand - gives the sense that there are currently several shortcomings in the regulatory system that are leading to inadequate levels of investment (Figure 1-1). Reserve margins are important to ensure adequacy of supply; if there is ever an acute system failure, like the unexpected loss of a transmission line, failure of a large power plant, or a particularly dry hydrological season, system operators can rely on reserve capacity to ensure that the lights remain on and factories continue producing. The target reserve margin in Peru for 2013 to 2016 is 33.3% (COES, 2013). This goal has only been reached less than half of time over the last decade. Figure 1-1: Generation reserve margin in Peru, 2004 - 2014. The target reserve margin is 33.3% (COES, 2013). Reserve Margin 50% Optimal 40% Margin: 33% 30% 20% 10% 2004 2006 2008 2010 2012 2014 The cause of this decline in reserve margin is due to a confluence of regulations that have undermined the government's stated electricity sector objectives. A dysfunctional capacity payment system, low administratively determined gas prices and structural barriers to investment in hydro are among the specific roadblocks to market-driven expansion of generation capacity. Recently, reactionary and ad hoc regulations in the face of a falling reserve margin have eroded investor confidence and further strained the ability of markets to ensure efficient investment in the Peruvian 12 electricity sector. In the following pages the historical context, design, and functioning of the electricity and natural gas systems in Peru are discussed, along with a detailed nature of the functioning of the regulatory scheme, some of the past sector challenges and solutions. Following, two regulatory reforms are considered that may move the electricity sector back towards a sustainable development path. 13 14 Chapter 2 Evolution of the Peruvian Electricity Sector Prior to 1992, the Peruvian electricity sector was operated as several state-owned vertically integrated utilities that bundled generation, transmission and distribution services. This era was marked by low investment rates in energy infrastructure, largely due to the absence of cost-based tariffs. Frequent power cuts, high levels of distribution loss and poor management practices were commonplace (The World Bank, 2010a). A power crisis in the 1990s revealed just how inadequate infrastructure investment was at the time: supply met a mere 74% of the total demand and losses in the distribution system were in excess of 20%, while less than half of the population had access to electricity (Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). At about this time, governments across Latin America were considering significant economic reforms and a new way to regulate their power sectors. Electricity market liberalization, it was hoped, would increase efficiency, reduce State intervention, and ultimately attract new sources of funding to maintain and expand national power systems to sustain rapidly growing economies (Batlle et al., 2010). Largely informed by the liberalized market design implemented in Chile in 1982, Peru was one of the 15 earliest adopters in Latin America, kicking off sector reforms in 1991. 2.1 Liberalization of the Electricity Sector: The Electrical Concession Law A market-based scheme for operation and investment in the Peruvian electricity sector was formally adopted in 1992 under Law No. 25844, the Electrical Concession Law (LCE)1 , which unbundled the market into generation, transmission and distribution functions; established market mechanisms for wholesale electricity transactions; established a pricing scheme for regulated electricity transactions; and opened the transmission network to free access by generators and large power users. The goals of this reform were to introduce competitive market forces to the development of the sector and relegate the State to a primarily regulatory role. In the spirit of free markets, a considerable portion of the State's electricity sector assets were transferred to private hands through the late nineties (The World Bank, 2010a). The LCE established COES 2 , the electricity system operator, and Osinergmin , the regulatory agency that sets gas and electricity tariffs and enforces compliance with energy, hydrocarbon and mining regulations. The LCE constrained the role of the Ministry of Energy and Mines (Minem)4 which formulates energy policy, grants concessions and approves regulations for the energy sector - to referential planning, relegating most future investment decisions 1 Ley de Concesiones Electricas The Committee for the Economic Operation of the System, Comiti de Operacion Economica del Sistema, is a private non-profit committee charged with operating the electricity system based on merit order generator dispatch. The committee was originally composed of generators and transmission companies, but now includes distribution companies and large free users. 3 Under the LCE, The Energy Tariff Commission was placed in charge of economic supervision of the sector. Later, an agency called Osinerg was created in 1997 to absorb some sector supervisory and oversight roles of the Ministry of Energy. In 2000, Osinerg and CTE were combined. The combined agency eventually expanded their role into the mining sector and the name was finally changed to Osinergmin (Organismo Supervisor de la Inversion en Energia y Minas) in 2007 (The World Bank, 2010a). 'Ministerio de Energia y Minas 2 16 to the private sector (The World Bank, 2010a). Organization of the Market 2.1.1 The reforms included in the LCE restructured the electricity sector of Peru based on several key principles: 1. Vertical and horizontal unbundling: Generation, transmission and distribution functions were unbundled, where distributors also serve the function of retailers 2. Least cost economic dispatch: COES manages dispatch of generation and the operation of the electricity system based on a stochastic hydrothermal economic dispatch model based on myriad assumptions of future demand, fuel prices, hydrological conditions, etc. The thermal generating units' operation costs are audited by Osinergmin. The economic dispatch for the entire system occurs on a least cost basis, independent of contractual obligations. Generators contract bilaterally with distributors and large free users 6 , and imbalances between generators' actual production with contractual obligations are bought and sold on the spot market at marginal cost 7 . COES manages the balance of payments among the generation companies. 3. Administratively determined "busbar" tariffs: Electricity prices for regulated consumers, called the busbar tariff, are determined as an administratively calculated two-part tariff for energy and power. 5 The market concentration rules were established in 1997 by Law No. 26876, The Antitrust and Anti-Oligopoly Law of the Electricity Sector, and are enforced by INDECOPI, the Peruvian antitrust market monitor. Antitrust regulations require regulatory intervention when horizontal concentration exceeds 15% of the market or vertical concentration exceeds 5%(The World Bank, 2010a). 6 Consumers with demand over 2.5 MW are classified as large free users and negotiate directly with generators for power and energy. Consumers with demands greater than 200 kW but less than 2.5 MW are called small free users and have the option to purchase power from distributors at freely negotiated prices, from distributors at regulated busbar tariffs or to freely negotiate rates with generators. 7 The marginal cost is defined as the variable cost of the last unit of power needed at any given time. 17 4. Capacity payments: Peru introduced a capacity payment scheme similar to the mechanism first introduced in Chile which remunerates generators at administratively determined prices based on their ability to provide power to cover peak demand. The power component of the busbar tariff serves as the basis of the capacity payment mechanism. 5. Monopoly regulation of transmission and distribution: Transmission assets are privately owned and receive regulated return on investment, while both public and private companies own distribution companies. All consumers pay regulated transmission and distribution rates. The intricacies of the busbar tariff and capacity payment regulations warrant further elaboration because of their immense impact on the behavior of market participants. 2.1.2 Busbar Tariffs The use of an administratively determined electricity tariff was designed to mitigate market power in the concentrated and weakly unbundled early Peruvian electricity sector. Set annually by Osinergmin, the busbar tariff was the maximum price at which distributors were allowed to sell their electricity to regulated consumers and to contract for supply with generators to serve those consumers. The tariff consists of two components: energy and power. The energy portion is determined taking the hourly marginal costs calculated by COES. The price of power, the basis of the capacity payment mechanism, is set as the annualized fixed cost and O&M of the hypothetical least cost generating unit able to cover peak demand. 18 2.1.3 The Capacity Payment Mechanism Electricity prices based on short-term marginal costs of production can rise only as high as the value of lost load, an administratively determined figure that is a rough approximation of the forgone value of consumption. During times where demand exceeds generation capacity, some load would be shed and the effective marginal prices of energy would be the value of lost load. Absent some power payment mechanism, peaker plants needed to cover the final unit of demand require that the price of energy rise to the value of lost load - while load is being shed in the system - for enough time for the generator to recover their fixed costs. The regulator has a design decision to make. In an energy-only system a tradeoff exists between amount of time blackouts occur and the value of lost load: the higher the energy price climbs during periods of unmet demand, the less time is needed to fully remunerate peak generators for their fixed costs. However, many regulators prefer to avoid both rolling blackouts and volatile prices. A payment that remunerates peaking generators for some part of their fixed costs provides additional remuneration that there are fewer hours of unmet demand and lower value of lost load to be fully remunerated on an annualized basis (Perez-Arriaga and Meseguer, 1997). In Peru, the implementation of the capacity payment mechanism devised can be conceptually divided into two distinct steps: the process of collecting the money used for capacity payments and the process of disbursements. The money designated for capacity payments is paid by regulated consumers as the base price of power that constitutes one portion of the regulated busbar tariff. Distributors pay on behalf of consumers for the total capacity of the supply contracts that they purchase to cover future demand. The collected money is then distributed to generators by COES on the basis of a generator's contribution to meeting peak demand. However, only those generators, sorted from low to high variable cost, that are just needed to meet expected peak load 19 plus the target reserve margin are awarded the capacity payment. Though generators that fall above the cutoff are free to contract their power to distributors, the base price of power portion of the busbar tariff that the distributors pay for the contract is not guaranteed to go to that specific generator. There are several aspects of the capacity payment that limit its usefulness as a tool to encourage adequate investment in generation capacity to reach the target reserve margin. Specifically, generators face a capacity payment that is too low and too uncertain to rely on as a necessary component of their returns. The inadequate size of the capacity payment is due to several strong assumptions that the regulator makes when calculating the payment, specifically assumptions (1) that they can predict the particular type of plant best suited as a peaking plant in Peru and (2) that the costs found in international references for that plant accurately reflect the cost of an investment made in Peru. Though the theoretical basis of pricing the capacity payment based on a peaking unit is sound, this method does not account for the reality of constantly evolving market conditions that would cause reality to deviate from expectation. Uncertainty manifests in the size and duration of capacity payments that investors can expect to earn. Uncertainty of the size of payments stems from the fact that the payment levels arc updated yearly using newly published prices and disbursements can change as the level of generation capacity on the system and the required margin change. Uncertainty in duration of payments comes from the fact that there is little guarantee that a generator will even be eligible for the capacity payment year to year. The payment is only granted to generators that, sorted from lowest to highest variable cost, cumulatively just meet expected demand plus the required reserve margin. That means that the high variable cost generators, those most crucial for providing supply when demand is the highest, are the least likely to receive the payment and so have diminished incentives to stay in the market. 20 2.1.4 The Advent of Natural Gas In the early 1980s, when Royal Dutch Shell first discovered vast deposits of natural gas in jungles of Camisea, the government of Peru was unable to finalize an agreement that allowed the company to continue explore and produce the gas fields. A renewed interest in a domestic energy supply emerged in the late 1990s as international oil prices began to rise. After another attempt to reach an agreement with Shell' broke down 1998, the government finally signed a concession contract in 2000 with a consortium led by Argentina's Pluspetrol to explore and produce the largest portion of the fields, Block 88. At around 10 trillion cubic feet (Tcf), Block 88 is by far the largest natural gas deposit in Peru. The same consortium won a contract for development of neighboring Block 56, devoting its 3 Tcf of gas to LNG export from the outset (Reinstein et al., 2010). Had the currently known reserves supplied only the domestic market, the gas was expected to last 35 years; factoring in LNG exports reduces this estimate to 20 years (The World Bank, 2010a). Over the course of the two 40 year contracts for Blocks 88 and 56, Peru is estimated to receive $1.9 billion in taxes and $3.5 billion in royalties (Reinstein et al., 2010). Gas from Block 88 is transported through the Camisea Pipeline that brings the gas from the East Peru to the central part of the country near Lima (Figure 2-1). Favorable transportation tariffs were made possible in the first years of pipeline operation through the Garantade la Red Principal (GRP), a financing scheme designed to keep transportation tariffs low for early pipeline customers and to guarantee revenues for Transportadora de Gas del Peru (TGP), the concessionaire for the Camisea pipeline. The GRP scheme 9 computed a per-unit-shipped transportation tariff by dividing the total annualized cost of the pipeline by its total capacity, calculated as if the 8 This time partnered with Mobil. 'The details of the GRP program are laid out in Law No. 27133, Law for the Promotion of the Development of the Natural Gas Industry (1999). 21 Figure 2-1: Route of the Camisea Pipeline. Camisea Gas Fields Lima Camisea Pipeline pipeline was fully subscribed. Each customer paid this common price for each unit of gas that they shipped, and the remaining operations and debt financing costs were socialized to consumers in a surcharge added to electricity transmission tolls. This scheme remained in place until the pipeline was fully subscribed just four years after commencement, at which point the shipping tariffs remained unchanged but the electricity surcharge was eliminated (Reinstein et al., 2010). Prices for pipeline transportation into the Lima area are at about $1 per million British Thermal Units (mmBtu) for power generators (Osinergmin, 2014). Natural gas prices for Block 88 were set through negotiation between the government and producer. Prices are not linked to international prices and the concession contract stipulates the evolution of future prices based on a basket of liquid fuels. The prices for gas from other blocks are not stipulated in the concession contracts and producers are free to charge any price they wish (Reinstein et al., 2010). Prices for Camisea gas as of January 2014 have floated to about $1.83/mmBtu, among the lowest gas prices in the region (Table 2.1). 22 Table 2.1: Wholesale gas prices in 2012 compared to price for Camisea gas (International Gas Union, 2013; Osinergmin, 2014). Price Country (US$/mmBtu) Brazil Colombia USA Mexico Argentina Peru (2014) 2.1.5 10.0 5.0 2.4 2.3 2.2 1.83 Electricity Sector Troubles: Energy Consumed Out of Contract The framework established by the LCE had several underlying structural deficiencies that only became apparent several years after reform. The flaws in the capacity payment mechanism and reliance on the regulated busbar tariff had led to an unsus10 tainable level of generation investment (Figure 2-2). The resulting reduction in the reserve margin, rising global prices of oil and a particularly dry period due to the El Nifio weather phenomenon caused marginal electricity prices to climb starting in 2004 (The World Bank, 2010a). Osinergmin's models failed to reflect these rapidly rising costs, and the busbar tariff remained essentially unchanged (Figure 2-3). Figure 2-2: Evolution of investments in generation in Peru, 1990 - 2012 (Minem, 2012). Investment ($Million) 2000 1500 - 1000 - 500 0 1990 1995 2000 2005 2010 1()Though there was a small surge of investment in the late nineties, investment in much needed generation capacity in Peru didn't materialize. It is worth noting that only generators with the very lowest capital costs - inefficient, unreliable and dirty oil and diesel generators - likely constituted this momentary influx of investment (Putnam Hayes and Bartlett Inc. and Mercados Energeticos S.A., 1998). 23 The decoupling of the average marginal prices and the busbar tariff led to a total breakdown in the normal contractual framework established by the LCE. Distributors who were legally required to purchase all of their energy needs through long term contracts but whose income from selling energy was capped by the busbar tariff could not afford to purchase energy at a price higher than they were legally allowed to recover. Instead, distributors simply continued to supply their customers electricity without the commensurate supply contracts. Around this time there was a strong correlation between the spot price and the amount of energy that was consumed without a contract (Figure 2-3). Figure 2-3: Spot price, busbar tariff and energy consumed without a contract in Peru, 2004-2012. Price (US$/kWh) 25 Energy Consumed Without Contract Energy Consumed (GWh) 500 20 Price - -Spot - -Busbar Tariff - 400 15 - - 300 10 - 200 100 5 0 0 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 The breakdown of contractual trust that resulted from inadequate generation investment and reliance on the busbar tariff scheme was a major failing of the regulatory system. As distributors continued to eschew reliance on bilateral contracts, generators were left with an uncertain revenue future and even further reduced incentives to invest in more capacity. In response the energy ministry proposed a reformed regulatory paradigm. The issue of capacity payments was left unaddressed, but the new regulations significantly changed the way distributors contract for electricity supply and how costs of those contracts are reflected in regulated tariffs. 24 2.2 Electricity Sector Reform: Law to Ensure the Efficient Development of Electricity Genera- tion Minem, hoping to improve the investment climate for generation companies and bring much needed generation capacity into the market, proposed a revised regulatory framework in 2006: Law No. 28832 - the Law to Ensure the Efficient Development of Electricity Generation" (Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). The new law introduced an auction mechanism for distributors to contract for a portion of their future demand; changed the way prices for regulated consumers are determined; changed several aspects of the transmission system; and introduced distribution companies and large free users onto the management board of COES (Gacon, 2013). Though changes to the way the busbar tariff is calculated were certainly needed, this reform attacked the symptoms (divergence of short-term marginal costs and busbar tariffs) instead of the causes (flawed capacity payment scheme) of the electricity sector problems. 2.2.1 Auctions The government, recognizing the need to allow electricity prices to better reflect the true costs of generation, devised an auction mechanism for distributors to contract for their energy and power needs. Cautious of the incumbent companies' ability to exert market power over the captured customers they serve due to weak unbundling between generation companies and regulated distributors, the new contracting framework was designed to be transparent but it is still characterized by close regulatory oversight. Distributors are responsible for initiating auctions to contract for the full demand " Ley para Asegurar el Desarrollo Eficiente de la Generaci6n E16ctrica 25 of regulated consumers at least three years in advance of the contract commencement dates, and the duration of the contracts must be at least five years. Distributors and free users can combine their future demands and participate in joint auctions to encourage economies of scale (Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). In this way the objective of the auctions is two-folded: first, from the tariff design point of view, it is expected that the pressure of potential new entrants on incumbents could drive prices towards what would exist in a fully competitive market; second, the auctions are expected to serve as a tool to reduce the entry barriers for these new entrants, through the provision of long-term contracts and sufficient lead times to allow for the construction of the new plants. Osinergmin establishes a hidden price cap for energy that generators offer in the auctions based on power demand models. The cap is kept secret unless a distributor is unable to fulfill its entire request without exceeding the cap. If the cap is exceeded a new auction round is called and is open to any generators who wish to participate. The price that generators bid is only for energy, and generators are remunerated at their bid price (pay-as-bid). Determination and payment of the price of power remains as it was before (Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). The auction mechanism does not replace administratively set regulated rates, but is rather a supplemental way of contracting for supply. Distributors are free to choose to contract for supply bilaterally at or below the busbar tariff, or through the auction mechanism (Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). Electricity prices for regulated consumers are a weighted average of the auction prices and the busbar tariff set through modeling as before (Cangalaya, 2013). Though the auction mechanism had significant advantages in how busbar tariffs arc determined, it was ultimately designed to encourage adoption of newly available natural gas in the power sector. Investment in hydro generation, which up to 2006 had represented the lion's share of capacity and generation in Peru, was severely limited due to contract timing and scale of the auction contracts. 26 The three year lag between when the contracts are signed until the contractual obligations begin is simply too short for large scale hydro power investments. Additionally the five year contract duration does not ensure a sustained cash flow for a period long enough to mitigate significant capital risk. The scale of the auctions is too small to capture the benefits that economies of scale can provide for large projects. Currently, any individual distributor can request an auction to be held to meet their demand. The regulations also allow distributors to call simultaneous auctions to encourage economies of scale in generation, but there are no requirements to do so. A large hydro or thermal plant would need to contract a significant portion of their capacity to garner financing. Low natural gas prices have helped diversify Peru's energy mix, decrease its reliance on imported oil and provide domestic industries with seemingly low cost energy. However, the success of low gas prices was at the cost of investment in hydro power. The share of natural gas as a fuel for generation from 6% in 2003 to over 30% in 2008, completely inundating the new pipeline by 2008, just four years after it was first put into service. This quick adoption of low priced natural gas lowered the average spot price and made it even harder for new generation in other technologies to be financially viable. 2.2.2 Transmission Planning Prior to the electricity sector reform there was no formal role for the State in planning transmission investments. New lines were built in response to market demand and remuneration to transmission owners fluctuated yearly based on the concept of an Adapted Economic System. The lack of market demand to spur investments and uncertain yearly revenues for investors led to chronically low investment rates in transmission assets in the years following sector liberalization (Figure 2-4). Responding to the failure of the regulatory regime to garner adequate transmission investments, 27 Proinversi6n 2 - the private investment promotion agency - tendered several projects under Build, Operate, Own and Transfer (BOOT) contracts between 2000 and 2002 (Ruiz and Rosell6n, 2012). Figure 2-4: Evolution of transmission investment in Peru, 1990 - 2012 (Minem, 2012). Investment ($Million) 600 500 400 - 300 - 200 100 0 1990 1995 2000 2005 2010 In an attempt to rectify the conditions that led to such low levels of transmission investment in the years since the LCE, Law No. 28832 established a mandatory transmission planning responsibility for COES and a system of guaranteed future revenues for asset investors (The World Bank, 2010a). Once per year COES publishes a transmission system diagnostic report that details transmission network issues such as congestion or voltage problems. Private agents and stakeholders submit proposed transmission additions to COES, who assembles these proposals into a four year transmission expansion plan. After approval from Osinergmin and Minem, Proinversi6n holds public auctions for concession contracts where transmission investors offer their lowest monthly payment needed to invest. Electricity consumers pay postage stamp tariffs that remunerate the winners of such auctions based on total energy consumption. 2.2.3 Trouble Strikes Again: Energy Shortages of 2008 During two consecutive days in drought stricken August of 2008 the main electricity system in Peru suffered from a shortage of generation that led to significant power The Agency for the Promotion of Private Investment (Agencia de Promoci6n de la Inversi6n Privada - Proinversi6n), which was created to foster private participation in strategic infrastructure investment. At the time of the tenders the agency existed under a different name but for purposes of this discussion was functionally the same. 12 28 cuts. The 2006 reforms had come too late to stem the tides of the sustained period of underinvestment in generation capacity and transmission lines that preceded the sector restructuring (Figure 2-5). The subsequent lack in generation investment, combined with acute constraints in the Camisea gas pipeline and power transmission lines, left the system in dire straits (The World Bank, 2010a). Figure 2-5: Total generation by fuel type in Peru and capacity margin, 2004 to 2009. Note that the target capacity margin in Peru is 33.3%. Generation (GWh) 3000 Reserve Margin 50% 2500 40% 2000 30% 1500 - 20% 1000 10% 500 0 0% 2004 Natural Gas 2005 Hydro 2006 2007 Diesel =Residual 2008 wCoal -Reserve 2009 Margin The Camisea pipeline operator was only required to expand capacity of the pipeline commensurate with the amount of firm capacity contracts that were signed by customers. Early in the life of the pipeline some generators were reluctant to sign these contracts despite relying on the pipeline to fuel their power plants. The pipeline had enough capacity to serve those customers with and without firm capacity on most days, but not during the particularly high demand days in August, thus leaving some generation capacity unable to contribute to meeting peak demand (The World Bank, 2010a). The shortage of generation capacity and strained transmission lines led to extremely high spot prices and divergence of prices between different regions of Peru. High and geographically disparate prices along with acute shortage events brought the health of the electricity sector to the forefront of the political agenda. Scrambling to find a quick fix to the highly visible problems in the sector the government enacted several minor sector reforms in quick succession. 29 2.3 2008 to Present: Ad Hoc Regulation Much has changed since the 2008 power shortages. However, unlike previous iterations of sector reform, the most recent changes have largely been reactionary and without a coherent guiding framework. A series of quick reforms in 2008 were largely meant to be temporary fixes, but the lack of sustainable solutions have left many of the changes in place today with no clear picture of what comes next. 2.3.1 The Current Geography of Supply & Demand In 2013 demand in Peru peaked at 5.6 GW, and installed generation of 7.3 GW comprises roughly 45% natural gas, 45% hydro, 10% oil, 1% coal and less than 1% renewable (COES, 2014). The electricity system is radial, with a central zone that has the majority of supply and demand, connected to northern and southern zones transmission lines. The geographic distribution of capacity, demand and generation are displayed graphically in Figure 2-6. Figure 2-6: Geography of electricity supply and demand in Peru (Osinergmin, 2012). The value in the arrows are the total electrical energy that is exported from the center of the country to meet demand in the north and south in 2013. North Demand: 15% Capacity: 12% Generation: 9% isu Centra Demand: 65% Capacity: 76% Generation: 82% South Demand: 20% Capacity: 12% seneration: 9% The concentration of generation in the center of the country is largely a result of investment in gas generation that relies on the inexpensive Camisea Gas (Table 2.1), which powered 37% of total electricity generated in 2013. As a result, the power lines 30 extending to the north and south of the country are congested about 40% of the year, transmitting 17% of the total energy generated in the country out of the central zone and into the northern and southern regions (Barco, 2012). 2.3.2 Single Node Pricing Emergency Decree 049-2008 changed the way electricity prices are set and generators are remunerated in order to make wholesale prices lower and uniform across the country. Instead of relying on the locational marginal prices that determine unique costs at each busbar on the system, COES now calculates the marginal price of electricity for the entire country using a single-node model that ignores electricity and gas transmission constraints. Generators that are dispatched for security of supply but cost more than the single node marginal price are paid the difference between their actual costs and the idealized marginal price. Using a single node price lowers average wholesale prices in security constrained locations and dulls incentives for efficient generation investment. Locational marginal prices are efficient at sending locational signals because in places where a very expensive generator is needed to produce electricity during peak demand, prevailing high electricity prices encouraged new and more efficient generators to invest in these areas, thereby lowering the cost of electricity in the long term. Transitioning towards a single price eliminates these locational signals and discourages generation investment in the areas where it is most needed. Furthermore, generating units that consistently provide the last few units of power are foregoing the ability to capture economic rents for their fixed investments, discouraging them from participating in the market in real time and discouraging new investments in the future. In addition to the acute problems caused by ignoring transmission constraints in pricing electricity in the wholesale market, the problem of regulatory risk looms large. Emergency Decree 049-2008 was put in force in 2008 with the intended expiration of 2011. Subsequent decrees extended the date first to 2013 and again to 2016. 31 This constantly shifting goal post further steers risk averse investors away from the Peruvian market (EDEGEL S.A.A., 2014). Cold Reserves 2.3.3 Due to a chronic lack of investment in new generation capacity under the normal capacity payment scheme, a new strategic reserve mechanism was devised to ensure that there was sufficient generation capacity to meet peak demand in emergency situations. Cold reserves are procured outside of the capacity payment scheme established under the LCE. Generators that are procured through this mechanism are meant to only run in times of system emergency (Tudela and Paredes, 2013). A series of government decrees, culminating in Urgent Decree No. 001-2011, established the role of Proinversi6n to hold a reverse bid auctions for predetermined capacities in specific locations in the country. Only new generators are eligible to participate in the auctions and must have a certain amount of on-site fuel storage capability. The generators awarded cold reserve status consistently garner payments for power in excess of the standard capacity payment (Table 2.2). Table 2.2: Basic information regarding cold reserve generators. Note that normal payment for power is 6,190 US$/MW-month in 2013 (Osinergmin, 2010; Cangalaya, 2013). Plant Ilb Talara Pucallpa Puerto Maldonado Eten 2.3.4 Capacity (MW) Power Price (US$/MW-mth) Investment ($ Million) Completion Date 564 200 40 18 214 7,190 7,815 9,147 11,719 7,627 220 106 40 23 145 June 2013 July 2013 Feb 2015 Feb 2015 June 2015 Promotion of Hydro Generation Development of hydro resources is once again of major interest to the government of Peru. 32 Three of the nine guiding principles for the development of the energy sector 3 and three of the seven electricity sector goals" directly or indirectly mention an increased reliance on hydro power in the country. Estimates of the hydrological resource base in Peru are enormous. The technical potential is a staggering 60 GW, nearly ten times the entire installed capacity in 2013 (The World Bank, 2010b). However, due to many institutional and financial barriers hydro development has come to a near complete halt in recent years. Total generation from hydro dropped from 85% of total in 2003 to just 54% in 2013, with reliance on natural gas increasing at a rate of over 30% year on year (COES, 2014). In an attempt to overcome some of the structural barriers to hydro development inherent in the auction mechanism and low natural gas prices, new rules15 were introduced in 2008 that discounted all hydro bids for the supply auctions by an amount of the regulator's choosing, so far 15% (The World Bank, 2010b). If the hydro developer wins the auction at their discounted bid, they are guaranteed to be remunerated at their actual bid price (Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). Yet another 2008 change' 6 applied accelerated depreciation to the capital cost of new investments hydro, and the maximum duration of auction contracts was extended from 10 to 20 years (Batlle et al., 2012). Even with these 2008 changes there has been very little recent hydro investment in the country (Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). Following these 2008 changes to the auction mechanism introduced by Law No. 28832, Proinversi6n conducted two auctions exclusively for hydro technologies. Auctions in 2009 and 2010 secured slightly over 650 MW of hydro capacity investment. 13 To develop a diversified energy matrix focused on renewable sources and energy efficiency; To develop a self-sufficient infrastructure for energy production; To develop an energy sector with a minimum environmental impact and low carbon emissions as part of sustainable development (Tafur et al., 2012). 14 Promote projects and investments to achieve a diversified energy matrix based on conventional and non-conventional renewable, hydrocarbon, geothermal and nuclear energies that ensure power supply in the country; Prioritize construction of efficient hydro power plants for national electricity generation; Promote an intensive and efficient use of conventional and non-conventional renewable energies as well as distributed generation (Tafur et al., 2012). 15 Legislative Decree 1041 6 Legislative Decree 1058 33 Though the auctions were successful in garnering investment in hydro generation capacity, there was uncertainty regarding who would ultimately bear the cost of the projects procured by the state outside of the formal distributor supply auctions. In the end the contracts were shouldered by Electroperu, the state owned electricity company. 2.3.5 The Southern Energy Node Passed in late 2012, Law No. 29970 - designed to strengthen energy security by diversifying electricity sources, reduce dependence on imported fuels and increase reliability of the natural gas supply chain - gave increased authority and a statutory mandate to Minem to prioritize projects that increase the reliability of the energy supply chain in Peru, especially to the south. The demands for gas from the Camisea gas pipeline far exceeded expectations, and had reached the full capacity of the line by 201117. More pipeline infrastructure was needed to continue to increase reliance on the abundant Camisea gas. The Southern Peruvian Pipeline, a project that falls within the legal framework of Law No. 29970, will be a 1,200 km line that will bring Camisea natural gas to the southern part of the country to serve industrial and power sector consumers, with the long term goal of establishing "The Southern Energy Node" and creating a petrochemical industry based in that region (Figure 2-7). Originally planned as a private construction project that was delayed by several financial and technical problems, the government now plans on offering a concession for the pipeline that includes guaranteed income over the life of the contract, using a financing scheme similar to the GRP. The selection process for the concessionaire is now underway with plans on finalizing the deal, after four consecutive delays in a year and a half, in late June 2014. The total cost is estimated to be $2.5 billion, it 17 Though, as discussed before, there were acute pipeline constraints in 2008, these constraints occurred before the pipeline was operating at maximum throughput capacity as it is now 34 Figure 2-7: Routes of the current Camisea Pipeline and the proposed Southern Peruvian Pipeline. Camisea Gas Fields Lima Camisea Pipeline Southern Peruvian Pipeline will be the largest project ever undertaken in Peru (No Author, 2014b). Proinversi6n, in order to create an anchor demand for the pipeline and to quickly provide electricity generation assets in the south of the country, held a concession auction for two 500 MW power plants, one in Ilo and the other in Mollendo 8 . Both plants will have a simple cycle diesel turbine generators. When the pipeline arrives, both generators will convert to gas fired combined cycle and will have a combined output of 1,500 MW (No Author, 2014a). Another anchor demand project promoted by the government is a smaller dieselthen-gas 200 MW power plant located in Quillabamba, south of Camisea but much closer to the fields than the Ilo and Mollendo plants (Electroperu, 2013). Instead of again relying on Proinversi6n, this time the government required Electoperu, the state owned electricity generation company, to invest in the power plant as the sole owner 19 In an effort to encourage a market-driven decentralization of power production 18 The Mollendo plant was awarded $5,899 /MW-month and is set to start up on a May 2016, and the Ilo plant was awarded 5,750 /MW-month and will start generating in March of 2017 (No Author, 2014a). 19 Set to be completed in 2016, this 200 MW open cycle turbine will cost around $150 million (Electroperu, 2013). 35 in the country, Law No. 29970 subsidizes the cost of Camisea gas from Field 88 for generators in the north and south of the country so that all generators will pay the same price per unit of delivered natural gas. The cost of this mechanism is funded through electricity consumers by a transmission toll. 2.3.6 Renewable Energy Promotion The primary mechanism for promoting investment in renewable energy in Peru is technology-specific auctions, governed by Legislative Decree 100220. Every two years Minem determines the need to call an auction for renewable generation, specifying the desired amount of energy for each type of generation technology 21 The auction process for renewable energy proceeds much like the conventional supply auctions. Investors offer price-quantity pairs, declaring the total amount of energy they expect to generate over a year in MWh and the price that they require for that generation in $/MWh (Gacon, 2012). Osinergmin calculates a price cap and awards are made to all generators that comprise the portfolio of generation assets that meets the technology quotas of the ministry at the least cost. Renewable energy generators that win the auction sell energy to the national grid at system marginal costs. Periodic financial settlements occur whereby the government can offer additional remuneration to the generator if their market earnings fall short of their bid, or where the government can impose penalties on a generator that produces less energy than offered in its bid (Gacon, 2012). 20 Published in May of 2008. Generation technologies that are eligible for the renewable technology auctions are wind, solar, tidal, biomass, geothermal and hydro under 20 MW. Hydro facilities larger than 20 MW are regulated as conventional generation technologies. 21 36 2.3.7 Alternative Regulatory Approaches Despite the myriad small regulatory changes instituted since 2008, the electricity system still faces significant underinvestment in generation. The government's response has been to increasingly rely on frequent and unpredictable involvement of Proinversi6n to bring in new investment. This type of government intervention has been a messy affair: hydro auctions have been cleared with unidentified buyers; cold reserves have been solicited with expensive out-of-market procurement; generators serving as the anchor demands for the southern energy node rely on expensive fuel until low cost natural gas arrives. These regulatory interventions crowd out efficient generation investment and diminish the impetus for new and comprehensive regulatory restructuring. It is imperative that policy makers in Peru address the three fundamental market flaws moving forward: the dysfunctional capacity payment system, the low administratively determined natural gas prices and structural barriers to investment in hydro. The following analysis considers the impacts of explicitly addressing each of the first two fundamental reforms in terms of economics and increased levels of hydro investment. Because of the nature of the reforms, their impact on the market can be abstracted to consider the mechanism through which they send efficient market signals to generators. Energy prices are determined by the variable costs of generators on the system. Controlling the price of natural gas, which fuels 45% of the generation capacity in Peru, would have a direct impact on the average energy prices and therefore an impact on generator revenues. Allowing the price of natural gas to rise to its economic value would result in a more efficient allocation of the scarce resource and perhaps to an increase in hydro capacity investment that is so desperately needed in Peru. Power prices for generators in the Peruvian market stem directly from the capacity payment, which currently does not reflect the actual cost of generation investment and has failed to garner the level of investment sought by Osinergmin. Fundamental 37 reform of this system of power payments must be considered if the regulator wishes to increase generation investments without continuing to rely on the costly ad hoc methods pursued recently, such as the cold reserves and Proinversi6n hydro auctions. Attempting any structural reform of regulations that improve the efficiency of market signals for generators in Peru must be undoubtedly be coupled with the removal of the structural barriers to investment in hydro. Specific strategies for pursuing these reforms and the relative impacts on the market are explored in the following analysis. 38 Chapter 3 Methods At the root of the problem of generation underinvestment, especially in hydro power, is that efficient electricity market signals are stymied by flaws in the design of regulations. Because more efficient market signals can come from either energy payment remuneration - through economically priced natural gas - or from power payment remuneration, reforms to both sources of generator revenue are explored separately below. However, generator revenue comprises the sum of energy and power payments, and in both cases of reform considered here, reform is made on each of these revenue sources independently, while the functioning of other remains as it is today. Explicit changes needed to address barriers to hydro investment are addressed in both cases. 3.1 Energy Price Approach The impacts of a change in energy prices in Peru are explored using a simple unit commitment model, for which a complete description can be found in Appendix A. For computational efficiency, a simplified mix of generators was used that reflects the actual supply curve in Peru for December 2013. Both the simplified and actual supply curves can be seen in Figure 3-1. 39 Figure 3-1: Actual 2013 and idealized (Base) generation supply curves at current natural gas prices. The shaded area represents the installed capacity relying on Camisea natural gas (COES, 2013, 2014). Variable Cost ($/MWh) 500 400 - 300 - Actual -Base 200 100 0 2000 3000 7000 6000 5000 4000 Cumlative Generation Capacty (MW) 8000 The model is run for one scenario that reflects the current prices - the Base Case - and two scenarios that consider the economic opportunity cost of the fuel: 1) the LNG Case where natural gas is priced at the value of LNG exports and 2) the Alternative Fuel Case where gas is priced at the highest it could rise before a generation technology relying on an alternative fuel has an equal variable cost. A study by The World Bank (2010b) found an economic value of natural gas by calculating the netback price for exported LNG as a function of international oil prices1 . They found that, with a barrel of oil at $100, the netback value of natural gas at the wellhead is approximately $4.6/mmBtu. Adding the Camisea pipeline tariff brings the LNG-based netback value of natural gas to $5.6/mmBtu at the point of generation. To estimate the opportunity cost of natural gas as a fuel for the power sector we can consider the variable cost of generators operating on the next most expensive fuel. Oil is the second hydrocarbon fuel of choice in Peru, and the least expensive generator relying on oil has a variable cost of $147/MWh, far more expensive than the highest variable cost generator relying on Camisea natural gas at $30/MWh. Assuming a 'The economic netback value of a fuel is the potential revenues from sales to a specific market minus the cost of delivering the gas to that market. In this case it would be the price that a hypothetical LNG exporter would pay to just break even on sales to the international market. 40 heat rate of 10 mmBtu/MWh, the price of natural gas that brings the Camiscareliant generator to the same variable cost as the oil generator is $14.7/mmBtu. The three scenarios will thus be defined as: the Base Case with natural gas at $1.2 - $2.8/mmBtu; the LNG Case with natural gas at $5.6/mmBtu; and the Alternative Fuel Case with natural gas at $14.7/mmBtu 2 . The impact that these gas prices has on the generation supply curve can be observed in Figure 3-2. Figure 3-2: Generation supply curves for Base, LNG and Alternative Fuel Cases. Variable Cost ($/MWh) 500 Fuel 400 - -Alt. -LNG 300 - =Base 200 - 100 - 02000 3000 7000 6000 5000 4000 (MW) Cumlative Generation Capacty 8000 An alternative method for allowing gas prices paid by generators to reflect the scarcity value of the natural gas is to allow a secondary market for pipeline capacity on the Camisea Pipeline, and on any future gas pipelines. In such a market consumers openly buy and sell capacity contracts that give the holder the right to move gas through a pipeline. In this way those consumers that value fuel delivery the most at a given time are willing to reflect that value in a market, presumably leading to an increase in effective fuel price. As the marginal cost of generation rises to reflect the cost of generators with higher variable costs than those that rely on Camisea gas, generators should be willing to pay for gas up to the point where their variable cost approaches that of the next highest generator. In the likely case where the next 2 The range of gas prices for the Base Case are an artifact of the generators' reported costs for fuel. Generators in the Peruvian electricity system that rely on Camisea gas self-report their costs, which are not audited like all other generation units. This gives generators the opportunity to price in fixed costs associated with pipeline capacity contracts or bid strategically for other reasons. For simplicity, this analysis relies on the reported values of natural gas prices. 41 generator is running on oil, there is a lot of room for prices to rise. Creating such a market is within the regulatory purview of Osinergmin and would have similar consequences for energy prices as the Alternative Fuel Case and will not be analyzed in full here. For a more in-depth discussion of the impact that a secondary market for pipeline capacity might have on the Peruvian market, see Appendix C. 3.2 Power Price Approach To consider how reforming the current capacity payment mechanism would impact remuneration for a hydro generator, we must first define the type of power payment scheme to analyze. The hypothetical concept considered here will be a quantity-based approach that relies on reverse auctions for defined generation capacities where generators offer the minimum yearly payment they would need to enter the market, and in the case of greenfield investments the duration of the contracts are commensurate with the lifetime of a power plant. The power payments that are awarded through the auction, if we assume that the auctions are fully competitive, will reflect the supplementary revenue that a generator would require in addition to their expected energy payment remuneration to enter or remain in the Peruvian electricity market. This scheme would compliment energy portion of the electricity supply auctions that currently exist. The specific details of how best to design this new quantity-based power payment approach are discussed later. For purposes of the financial analysis we will assume that the expected energy revenues for a hydro generator are equivalent to the time-average marginal cost of generation, and that any power payment would simply supplement energy revenues. To understand the costs of this new scheme, a simple calculation is conducted that considers the average marginal cost of electricity, the availability of the hydro as discussed above, and hydro variable costs. A complete description of these calculations can be found in Appendix B. 42 Hydro Generation Assumptions 3.3 To study how the alternative regulatory scenarios affect the financial viability of hydro generators, a better understanding of their financial and operational characteristics is needed. The question we would like to ask is how high electricity sector remuneration would need to rise to offer "enough" revenue for new hydro investors. However there is no simple invariable answer to this question. Physical characteristics such as reservoir size, estimated inflows and susceptibility to changing hydrological cycles define the operational - and thus the cost and revenue profile - of any particular hydro generator, and capital and financing costs change with time and at the whim of international markets. For this simple analysis, however, a single cost metric is used to evaluate the various regulatory scenarios and is considered a threshold value rather than the true cost of investment for all hydro generators in the Peruvian market. Considering the necessary simplification to the cost profile of hydro generators, we can define adequate remuneration as the amount of revenue that would cover the annualized fixed and variable costs of a new hypothetical generator. Table 3.1 contains some basic information on the cost of hydro investment in Peru. Table 3.1: Hydro cost assumptions for scenario analysis. All hydro assumptions except fixed O&M are from The World Bank (2010b). Fixed O&M is from Gacon (2013). The annualized capital cost was computed considering a thirty year recovery period and 15% rate of return. All costs are normalized on a per-kW basis. Variable O&M ($/MWh) Fixed O&M ($/kW-yr) Overnight Capital Cost ($/kW) Annualized Capital Cost ($/kW-yr) 0.30 30 2000 304 Considering the costs in Table 3.1, our particular hypothetical hydro generator would need a net revenue of at least $304/kW-yr to just break even with a 15% rate of return. This value will be used as the threshold net income that would encourage hydro capacity investment. Note that this is strictly financial in nature and that any structural barriers that remain would still prevent investment, even when the 43 expected financial returns are high. Peru has an energy-constrained hydrothermal electricity system: hydro generation is subject to variable hydrological cycles that places an effective cap on the amount of energy that can be generated using hydro. For the purpose of the analytic model, the monthly average capacity factors for hydro over the last ten years are used to adjust available generation capacity and remuneration for hydro generators in the scenarios (Table 3.2). Though this is a crude approximation of the availability of hydro through the hydrological cycle, it will suffice to gain an understanding of the impacts of scaling the availability of the generator commensurate with reasonable inflow assumptions. Table 3.2: Hydro availability factor, taken as monthly hydro generation as a fraction of firm capacity from 2008 to 2013 (COES, 2014). The average availability over this period is 0.65. Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec. 0.74 0.68 0.75 0.72 0.67 0.58 0.57 0.57 0.55 0.62 0.64 0.71 Defining the meaning of firm capacity for the purposes of capacity payment eligibility is a design decision of the regulator. In Peru, the firm capacity of a hydro generator is defined as the amount of power that they could produce during the lowest hydrological inflow month for a thirty year duration (The World Bank, 2010b). For many hydro generators on the system, their firm capacity is commensurate with their effective capacity, though some are discounted heavily. For this analysis we assume that firm capacity is equivalent to installed capacity. 44 Chapter 4 Results and Discussion The following section discusses the results of the analysis scenarios in terms of costs to consumers and revenues to generators. More detail regarding the design and implementation of either of these approaches is also discussed here. 4.1 Energy Price Approach Figure 4-1 gives a simplified schematic view of supply and demand curves for electricity. Price is on the vertical axis and quantity is on the horizontal. The supply curve represents cumulative generation capacity, stacked from low to high variable cost, and the demand curve is vertical and represents total consumer demand for electricity. It is represented vertically because consumers have little ability to change their demand in real time based on prices, so demand is said to be inelastic. The conditions that define supply and demand change on an hourly basis'. In every hour, the most expensive generator that is needed to meet demand establishes the marginal cost, or the cost of supplying one more increment of power for that 'In reality conditions change on an infinitesimal time horizon: the supply curve and precise level of demand are never exactly the same twice. However, for simplicity this analysis simplifies the time variance of supply and demand into discreet hourly periods. 45 Figure 4-1: Schematic of supply and demand for electricity. Consumer costs are the sum of marginal cost times demand for every hour. Demand Supply Marginal Cost ($/MWh) Generator Surplus Generation Cost Quantity (MW) hour. Consumers pay - and generators receive - the marginal cost of energy for each hour for every unit of energy consumed 2 . Below the supply curve is the true cost of generation that accounts for fuel and O&M. The area between supply curve and the marginal cost is called generator surplus and goes towards paying the fixed investments of generators. Any generator surplus in excess of fixed investments are maintained as profits. Table 4.1 summarizes total consumer cost and total generator surplus for the economic dispatch modeling scenarios. The average marginal cost is time-averaged, meaning that the marginal cost in each our is averaged over time, irrespective of demand. Note that the time-average marginal cost in 2013 was about $25/MWh, quite close to the Base Case scenario. Table 4.1: Consumer costs and generator revenues for the economic dispatch modeling scenarios. Case Base LNG Alt. Fuel Gas Price Avg. Marginal Cost Consumer Cost Generator Surplus ($/mmBtu) $/MWh ($ million) ($ million) 0 - 2.9 30 1222 1191 5.6 14.7 52 130 2076 5101 1974 4871 Evaluating the magnitude change in total consumer costs, it is worth noting that though natural gas prices are a large driver of energy costs, costs to consumers do 2 Though consumers do not pay in real time, the average marginal cost is an approximation of the cost of electricity to consumers over the long term because generators internalize their expectations for average marginal costs in supply contracts. 46 not rise one-to-one with an increase in gas prices: an 400% increase in the price of natural gas between the Base and LNG Cases results in a 70% increase in consumer energy costs 3 . A 1200% increase in gas price increases consumer costs just over 300%. This fact reveals that natural gas generators are not always the marginal generator, but rather prices are sometimes set from generators not relying on Camisea natural gas. Nearly all of the increase in consumer costs for energy is directed towards generator surplus as opposed to paying for the added cost of the natural gas. This is largely an artifact of the large hydro capacity on the system, which operates at a nearzero variable cost. For this type of generator, any energy payments that result from marginal cost pricing is nearly all surplus. Table 4.2 shows these revenues and generation costs on a per-kW capacity basis for the hypothetical hydro generator on this system 4 . Table 4.2: Results from economic dispatch model in terms of hydro generator revenues. Case Base LNG Alt. Fuel Net Revenue Costs Gas Price Energy Revenue Power Revenue ($/kW-yr) ($/kW-yr) ($/kW-yr) ($/kW-yr) ($/mmBtu) 0 - 2.9 5.6 14.7 173 294 723 74 74 74 -32 -32 -32 216 337 765 This analysis shows that under the Base Case scenario hydro is not competitive, with net revenues falling far short of the $304/kW-yr target calculated above. Bringing gas prices up to the opportunity value of LNG on the world market would just surpass the revenue requirements while increasing consumer costs and generator surplus 70%. Increasing the price of gas commensurate with its opportunity cost in the power sector increases net revenues for hydro generation dramatically but increases consumer costs and generator surplus by over 300%. 3 Though the price of gas for the base case ranges from 0 - 2.9 $/mmBtu, a capacity-weighted average of 1.12 $/mmBtu was used for calculating comparisons. The capacity-weighted average was found by multiplying the price of natural gas times the capacity of the generator, and dividing by total generation capacity relying on gas. 4 Note that the power payment for capacity from 2013 was used, 6,190 US$/MW-month. 47 This analysis shows that increasing the price of natural gas to a value near the opportunity cost of the fuel for LNG export would be nearly ideal for encouraging new hydro investment in the system. However, these increases in natural gas prices result in large associated increases in consumer costs. This is a political challenge that may prove untenable. Complicating the politics of increasing energy prices is the fact that many of the generators that would benefit from the increase in surplus are owned by large multinational corporations. Much of the additional consumer costs would leave the country as increased corporate profits, a political challenge nearly as great as increased costs. 4.1.1 Political Costs and Economic Benefits of Higher Gas Prices If raising costs to consumers is completely untenable, mechanisms can be devised that transfer the additional revenues that generators might capture back to consumers through taxes on installed capacity or lowering the capacity payment. However, the long term efficiency gains that would result from having natural gas reflect market price are nontrivial. Another consideration when thinking about the costs to consumers is that the large increase in marginal cost of energy production reflected in these modeling simulations would be short term and transitory and would be relieved as more hydro generation enters the market, providing sustainable low carbon energy generation to meet future demand while preserving the natural gas endowment to its highest value use. Another driver for transient reductions in energy prices that are not reflected in the model is the move to combined cycle power plants that rely on Camisea gas. Combined cycle power plants are about 30% more efficient than open cycle, and therefore more economical at a given gas price. To alleviate the price shock to consumers and allow the system to remain closer to equilibrium through the transition to higher gas price, a set schedule of price increases should be published ahead of time to allow market 48 participants to react economically to the new generation cost reality. Lastly, under this reform scenario, it is imperative that current barriers to hydro investment - including the lag and duration of energy supply contracts - be addressed with haste. Without eliminating these barriers, increasing the cost of natural gas in the power sector will simply increase energy costs, since the market efficiency gains will only be realized if both the gas prices are brought to their economical value and hydro investors are allowed to compete on a level playing field. 4.2 Power Price Approach How large would a power payment need to be for our hypothetical hydro generator, assuming that their energy remuneration is unchanged? Considering the Base Case model run, a hydro investor, net of operational costs, can expect to earn $142/kWyr from energy payment revenues. Therefore, to meet the $304/kW-yr threshold, a hydro investor would need an additional $162/kW-yr to be fully remunerated. To consider the costs to consumers that such a payment would entail, imagine that hydro investment met the total future capacity needs of Peruvian electricity demand, which has averaged 7% growth per year for the last several years, and that 5 energy prices remained the same as the average marginal cost from the Base Case . If all new demand growth for the next decade was met with hydro paid a power price of $162/kW-yr, the total additional cost to consumers over the current capacity payment would be $140 Million, 80% less expensive to consumers than bringing natural gas costs up to the LNG Case price for just one year. When the future costs of the discriminatory power payment are discounted to present value using a 10% discount rate, consumer savings come to a staggering 90% over the LNG Case gas price increase. 5 Peak demand in 2013 was 5,565 MW 49 4.2.1 Design of a Power Payment Reform With such a seemingly positive return for this method, what would such a power payment scheme look like in practice? There is still much debate on what an effective power payment system should look like in practice but a few guiding principles should be at the forefront of a reform. One way to operationalize good regulatory principles is to consider four regulatory decisions that must be addressed adequately under a new power payment scheme (Rodilla and Batlle, 2013): 1. Identification of counterparties (buyers and sellers) 2. The precise definition of the power product to be sold 3. Determination of the type of mechanism (price or quantity) 4. The design of the process The Counterparties Currently, the counterparties for the capacity payment mechanism are regulated users and generators. Under a new power payment scheme, the buyers should be all users of the network, both regulated and free, to avoid the implicit cross subsidy that exists in the current power payments'. Osinergmin could look at the centralized Brazilian energy auctions as an example of a centralized auction procedure that encourages economies of scale and assigns the cost of power contracts to all consumers (Mastropietro et al., 2013; Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). One way to distribute the costs fairly is to add the new security of supply mechanism to an additional charge to the transmission tariffs that all consumers are subject to. The sellers that would participate in the new capacity auctions would be all of those generators that the regulator saw fit, depending on the regulatory objective. 'The cross subsidy manifests from regulated consumers bearing the entire power payment that is meant to encourage investment that benefits all consumers, both regulated and free. 50 Perhaps the first-best option from an economic point of view is to allow all generators to participate in the auctions. Physical realities of market concentration, fuel price distortions and inherent differences between generation technologies may compel the regulator to prefer discretionary auctions, choosing between thermal and hydro generation, or incumbents and new entrants. This would give Osinergmin increased discretion and control of who enters the market and when, while consumers only bear additional costs for those generators that are deemed necessary by the regulator. The Product The precise definition of the power product is crucial in determining the success of the power payment scheme. The duration and lag period of the power contracts that result from the auctions is of critical importance for the promotion of hydro power generation. Lag times for new generation investment should be longer than the current supply auction lag to account for the inelasticity of demand for capacity in the short term inherent with long lead-time generation investments (Rodilla and Batlle, 2013). A distinction between new investments and incumbents may also be warranted. Greenfield investments need long contract durations to secure financing, though incumbent generators should be offered power contract durations of shorter lengths to maintain market flexibility for both the generators and suppliers who contract their power 7 Perhaps most critically for the success of the entire power payment design is the incorporation of reliability incentives into the product that is auctioned. An important distinction should be made between a power payment system that pays generators to simply deliver power and a payment that ensures that power is delivered when the grid needs it. The current design in Peru is the latter: it pays generators for their contribution to peak through relying on proxy calculations such as forced 7This distinction is iade in the Brazilian power sector (Putnam Hayes and Bartlett Inc and Mercados Energ6ticos S.A., 2011). 51 outage rates or lowest monthly water inflows for hydro. However, the power payment design fails to account for system need. For example, if the lowest hydro inflow that is used to determine the firm capacity for a hydro plant coincides with the lowest period of demand, yet the hydro facility consistently contributes to meeting peak demand during high demand periods, that facility is not being remunerated on the basis of the power it can provide when the grid needs it the most. The same goes for thermal power plants. If an average forced outage rate is used to establish firm capacity of Camisea natural gas plants, yet the only times forced outages occur is when demand is highest - and the Camisea Pipeline is overburdened - those generators are being over-compensated for their supply. Simple changes to the way payments are disbursed, no matter if the current payment concept is maintained or if a new one is designed, can make the payments better suited to encouraging generation when the grid needs it the most. Calculating the forced outage rates based on periods of high demand, relying on ex post payments based on generator availability during grid contingency events, or levying strong noncompliance penalties will all force generators to internalize the timing and cost of nonavailability when they are most needed and encourage more grid reliability than simple transfers that do not account for grid need. The Mechanism The main problem with the price-based security of supply mechanism that Peru has now is that the regulator has to hope that the ideal amount of generation investment follows from the administratively set price, something that has yet to come to bear8 . Though a capacity payment mechanism is not inherently flawed, changes must be made to the mechanism if the results that are sought never manifest. 8 The capacity payment system in Peru, like many others, adjusts generator remuneration based on availability factors. Therefore in practice not all generators receive exactly the same payment for their capacity, but rather they receive the same payment for their effective capacity and will for the purposes of this analysis be considered a single price system. 52 A quantity-based approach, as considered here, has the advantage that the regulator can set a desired quantity and allows the market mechanism - here the auction clearing price - to set the correct price, avoiding the Goldilocks challenge of setting the ideal price for power based on a sought level of system reliability. Though a fixed-quantity mechanism would be an improvement over the status quo, precaution does need to be taken to avoid manipulation of the market by incumbents. The Process A design imperative for the process of conducting the power supply auctions should include aggregated demands of all consumers, not simply individual distributors. The economies of scale that are so important in reducing the cost of hydro cannot be realized without large power supply needs being met through aggregated demand. The current supply auctions fail to meet this design criteria. It is notable that several of the aforementioned design considerations are present in the current cold reserve solicitation scheme. Cold reserve generators, auctioning their power under conditions similar to the design described here have consistently fetched power payments higher than the regulated rate (Table 2.2). This price discrepancy, the relative success at the ease of clearing those auctions, and the reliance on this ad hoc method of securing generation capacity are all cause to reconsider the current capacity payment mechanisms. One feature of the cold reserve auction designs not explicitly discussed here is that decisions are made on a geographic basis. The regulator knows that not all potential investment locations are equally beneficial for the system. If the estimated avoided costs of a certain power line exceed the additional power payment needed to encourage investors to build in a place that would eliminate the need for that transmission line, then the economically prudent decision by the regulator would be to pay a higher power price, up to the avoided costs, to the generator that eliminates the constraint. This type of design feature, though not advocated in full here, might be suitable for 53 the Peruvian system if the signal nodal price for energy prevails. 54 Chapter 5 Conclusion Peru's remarkable economic growth is in jeopardy. Its electricity sector is facing immense challenges in the coming months and years as rapid demand continues to outpace generation investment, while hydro investment in particular has slowed to a trickle. Appropriate policies and regulations in the electricity and natural gas sectors of Peru are critical to create a sustainable investment climate that benefits investors and consumers. Fundamental problems exist in the energy markets due to the low price of natural gas, and the power markets through the flawed capacity payment system. Addressing one or both of these issues could direct the sector back on the road to prosperity, but each reform poses unique challenges from political and regulatory perspectives. Increasing the price of energy, by raising the price of natural gas for power generators up to the economic netback value of the fuel would again make hydro a viable investment, but structural barriers in the supply auctions would still pose a problem and consumers would be hit with very large increases in their electricity bills. An alternative approach, a reform to the capacity payment mechanism, could provide the same benefits in terms of drawing new generator investment at a much lower cost to consumers. It would also have the additional advantage of allowing the 55 regulator more leeway in deciding which generation technologies should be included in the system whether it be for policy, technical or cost reasons. This regulatory discretion is akin to Brazil's successful market structure, where the regulator determines some socially optimal mix of generation capacity and allows generators to compete for the market, not in the market (Putnam Hayes and Bartlett Inc and Mercados Energeticos S.A., 2011). If Peru undergoes these particular reforms, the power system will be able to sustain impending and much needed economic growth, maintaining the countrys status as a beacon of prosperity in Latin America. 56 Bibliography Asian-Pacific Economic Cooperation, 2013. Peru, in: APEC Energy Demand and Supply Outlook 5th Edition. Asian-Pacific Economic Cooperation. Barco, D., 2012. Observatorio Econ6mico: Sector electrico peruano. Technical Report. BBVA. Batlle, C., Barroso, L., Echevarria, C., 2012. Evaluaci6n del marco normativo e institucional del Perul para la promoci6n de energia electrica a partir de recursos renovables. Technical Report. Inter-American Development Bank. Batlle, C., Barroso, L.a., Perez-Arriaga, I.J., 2010. The changing role of the State in the expansion of electricity supply in Latin America. icy 38, 7152-7160. Energy Pol- URL: http: //linkinghub . elsevier. com/retrieve/pii/ S0301421510005677, doi:10.1016/j .enpol.2010.07.037. Cangalaya, S.B., 2013. Fijaci6n de Precios en Barra Mayo 2013 - Abril 2014. COES, 2013. Estudio de Verificacion del Margen de Reserva Firme Objetivo (MRFO) del SEIN, Periodo 2013-2016. Technical Report. COES, 2014. Sistema de Informaci6n del COES. EDEGEL S.A.A., 2014. Estados Financieros Separados 31 de diciembre de 2013 y de 2012 (Con el Dictamen de los Auditores Independientes). Electroperu, 2013. Proyectos de Inversi6n en Electroperu S.A - ler trimestre 2013. Gacon, J.R.M., 2012. Marco Legal de las Energias Renovables en el Per' . 57 Gacon, J.R.M., 2013. Aspectos Econ6micos de la Generaci6n Electrica. Technical Report. Gerente de Generaci6n y Transmisi6n Electrica - OSINERGMIN. Inter-American Development Bank, 2013. Enhancement of the Implementation System for Electrical Generation Planning Terms of Reference. International Gas Union, 2013. Wholesale Gas Price Survey - 2013 Edition. Technical Report. International Gas Union. Mastropietro, P., Batlle, C., Barroso, L.A., Rodilla, P., 2013. Electricity Auctions in South America: Towards Convergence of System Adequacy and RES-E Support. Technical Report September. IIT Working Paper. Minem, 2012. Evoluci6n de las Inversiones de las Empresas Generadoras. No Author, 2010. "MEM aprueba reglamento de mercado secundario de pro- ducci6n y capacidad de transporte de gas natural". August 5. Andina. Available: http://www.andina.com.pe/Espanol/Noticia.aspx?id=Cj+JqiDtoLo=#.Ugqq2ZLBhpO [Last Accessed: 23 January 2014]. No Author, 2014a. "C6mo sera el Nodo Energetico del Sur?". February 28. Gestion. Available: http://gestion.pe/economia/como-nodo-energetico-sur-2090320 [Last accessed: 24 April 2014]. No Author, 2014b. "Gasoducto Sur Peruano postergado para el tercer trimestre". January 21. Peru2l. Available: http://peru21.pe/economia/gasoducto-sur-peruanopostergado-tercer-trimestre-2166585 [Last accessed: January 29, 2014]. Osinergmin, 2010. Ficha Tecnica de Proyectos Buscador. Osinergmin, 2012. Compendio de Centrales de Generaci6n Eh6ctrica del Sistema Interconectado Nacional. Osinergmin, 2014. Precios y Tarifas. P rez-Arriaga, I.J., Meseguer, C., 1997. Wholesale.Marginal Prices in Competitive Generation Markets. IEEE Trans 12. 58 Putnam Hayes and Bartlett Inc., Mercados Energ6ticos S.A., 1998. Payment for Generating Capacity in Peru. Technical Report March. Comisi6n de Tarifas Ek6ctricas. Putnam Hayes and Bartlett Inc, Mercados Energeticos S.A., 2011. Electricity Auctions - An Overview of Efficient Practices. Reinstein, D., Benitez, D.A., Johnson, T.M., 2010. Peru's Downstream Natural Gas Sector: A Preliminary Assessment. Technical Report. Energy Unit, Sustainable Development Department, Latin America and the Caribbean Region, World Bank. Washington DC. Rodilla, P., Batlle, C., 2013. Chapter 12. Security of Generation Supply in Electricity Markets, in: P6rez-Arriaga, I.J. (Ed.), Regulation of the Power Sector. SpringerVerlag, London. Ruiz, E., Rosell6n, J., 2012. Transmission investment in the Peruvian electricity market: Theory and applications. Energy Policy 47, 238-245. URL: http:// linkinghub. elsevier. com/retrieve/pii/S301421512003679, doi:10. 1016/j. enpol.2012.04. 062. Tafur, H.J.M., Cuneo, L.E.O., Pereyra, R.C.T., 2012. Peru Subsector Electrico Doc- umento Promotor. Technical Report. Peru Ministerio de Energyia y Minas. The World Bank, 2010a. Peru - Recent Economic Development in Infrastructure (REDI) - (vol. 2) - Investing in Infrastructure as an Engine for Growth: Spending More, Faster, and Spending Better. The World Bank, 2010b. Peru: Overcoming the Barriers to Hydropower. Technical Report. The World Bank, 2014. World Bank Country Data: Peru. Tudela, R.V., Paredes, C.E., 2013. Mercado electrico en el Peru: Balance de corto plazo y agenda pendiente. Technical Report. Instituto del Peru. United States Central Intelligence Agency, 2014. The World Factbook. 59 60 Appendix A Economic Dispatch Model Formulation The economic dispatch model used in this analysis is programmed in the General Algebraic Modeling System (GAMS) as a relaxed mixed integer program. A full algebraic representation of the economic dispatch model is included here. Indices: h Hours m Months t Generation technologies renew(t) Hydro generator subset Parameters: Ctv Variable cost excluding fuel for generation type t ($/MWh) Ht Heat rate for generation type t ([unit]/MWh) Ft Fuel price for generation type t ($/[unit]) Ptax Maximum power and installation size for generation type t (MW) AM Monthly hydro availability (%) Lh Demand in hour h (MW) Variables: 61 Z Objective function ($) GCt,h Generation cost of technology t for hour h ($) Positive Variables: Pt,h Power output of technology t for hour h (MW) Model: Minimize: Minimize the sum of all variable costs for all technologies for all hours: Z GC ,h =3 (A.1) t,h Where: Generation cost is the sum of the non-fuel and fuel costs of each generator in each hour: GCth = P,h * (Cv + H, * F) (A.2) Subject to: Total power produced by generation technologies must be less than or equal to their maximum installed capacity: Pt,h Pt (A.3) Supply must meet demand: (A.4) EPt,h = Lh Total energy produced by hydro units must be less than or equal to their monthly availability factor: > h'N 62 Phydro(t),h < 730 * Am * P"yfo(t) y (A.5) Appendix B Hydro Plant Revenue Calculations Potential revenues for a hypothetical hydro generator were calculated using the output of the economic dispatch model, normalized for generation capacity. Total energy market revenues are the sum of all energy payments received per year: R EM = MC * CF * 8760 (B.1) Power payment revenue is the sum of monthly regulated power payments for generators: RP' = PP* 12 (B.2) The total cost of hydro energy generation is the fixed and variable costs of generation: C = VC * CF * 8760 + FC (B.3) The net revenue of the generator, which is used to consider investment viability, is the sum of revenues and costs: Rnet REM + RPP - C (B.4) 63 Where: 64 REM Annual energy market revenue ($/kW-yr) RPP Annual power payment revenue ($/kW-yr) Rnet Annual net revenue ($/kW-yr) MC Average marginal cost ($/kWh) CF Hydro capacity factor (%) PP Monthly power payment ($/kW-mth) C Annual generation costs ($/kW-yr) VC Variable O&M costs ($/kWh) FC Fixed O&M ($/kW-yr) Appendix C Secondary Market for Pipeline Capacity An alternative way that prices could increase to reflect the opportunity cost of natural gas is to implement a secondary capacity market for transmission on the Camisea pipeline. Supreme Decree No. 046-2010-EM allows Osinergmin to create an electronic auction board where owners of pipeline capacity can sell in an open and transparent marketplace. Still the regulations governing such a market have yet to be finalized, and for the foreseeable future gas capacity tariffs are unlikely to reflect the scarce supply and growing demand in the market. Current transportation tariffs are structured as a flat postage stamp fee. (No Author, 2010). Such an approach would give the generators that signed the first capacity contracts the economic right to the scarcity rents that manifest from a secondary release market. An alternative approach would be for the government or some other entity to hold the capacity on the pipeline and have regular auctions for the right to use the capacity on the line. In this way incumbent generators who currently have the first right of refusal to the pipeline capacity would not reap the economic benefits of scarcity, but it would rather be the government that collected the additional revenue - above the cost of operating the pipeline - to do with that revenue whatever they wish. 65 Under the government-held capacity concept, the added cost of electricity that results from increased costs to generators could be subsidized by the earnings that the government makes from selling the capacity. Then this begs the question of why bothering to let the tariffs for pipeline transmission reflect scarcity in the first place, and if so why not let the current holders of capacity capture the economic rents? If the first mover advantage that is currently bestowed to those generators that have capacity contracts is removed, the door will be opened to more efficient new generation to invest in natural gas plants that rely on the Camisea Pipeline. The more efficient the generator produces electricity for a given volume of gas, the more money the generator can pay for the natural gas and remain profitable in the electricity market. This would spur a "race to the top" as incumbents and new generators alike rush to become the most efficient, and thus operate profitably for the greatest amount of time. This increase in fleet efficiency would minimize the cost increases to the energy market that result from the higher costs for generators. A secondary release market would also allow industrial consumers to reflect their interests in gas capacity and increase the utilization of the pipeline. Generators are required to hold firm capacity contracts to receive capacity payments from the system operator (Reinstein et al., 2010). These firm contracts effectively exclude other consumers from accessing the pipeline even when the generator is not using it. Providing the ability of industrial users and generators to reflect their time-varying value of consuming natural gas would increase the utilization factor of the pipeline and ensure that the maximum economic benefits that could accrue from using the natural gas for productive purposes. 66