2013 Green Globes New Construction Certification Drexel University URBN Center Annex David Eldridge Grumman/Butkus Associates 6/21/2013 June 21, 2013 Page 2 of 12 June 21, 2013 Simone Pucca-Fera Pucca-Fera, Inc 3208 Denfield Place Philadelphia, PA 19145 Re: Green Globes Stage 2 Assessment for New Construction Drexel University URBN Center Annex Building G/BA #13-156.01 Dear Ms Pucca-Fera, Thank you for the opportunity to complete a Green Globes Stage 2 analysis of Drexel University’s URBN Center Annex project in Philadelphia, Pennsylvania. This second and last stage of the Green Globes assessment included on-site verification of the items that were discussed during the Stage 1 Assessment completed on 5/14/2013. I visited the site on 6/3/2013 and met you in the lobby for a morning walkthrough, primarily focusing on the occupied spaces. Ad van Hees from Drexel University’s Facilities department accompanied me during the afternoon to access the mechanical and electrical rooms. Outstanding items not verified during the Stage 1 Assessment were verified during the Stage 2 Assessment. New Construction Stage 2 Assessment Stage 2 of the new construction project included a review of additional documents provided since the Stage 1 review. These included but are not limited to construction documents, narratives, calculations, and other documents. Overall, the project has several sustainable features included in the design. The Stage 2 assessment resulted in an adjusted score of 549 out of 903 applicable points, 60.8% of the applicable total. This rating places the project at a Two Green Globes rating. The revised percentages for each category are shown below in Figure 1. The project received 97 “not applicable” points, which is less than the Green Globes limit of 100 points. ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 3 of 12 Figure 1: Green Globes Assessment Areas with Percentages “As Revised” Building achieved an overall rating of 60.8% based on the Assessor adjusted score, which may vary from the system score due to manual adjustments as detailed in the Point Summary Table. Green Globes Ratings 85-100% Demonstrates national leadership and excellence in the practice of energy, water, and environmental efficiency to reduce environmental impacts. 70-84% Demonstrates leadership in applying best practices regarding energy, water, and environmental efficiency. 55-69% Demonstrates excellent progress in the reduction of environmental impacts and use of environmental efficiency practices. 35-54% Demonstrates a commitment to environmental efficiency practices. ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 4 of 12 Figure 2: Green Globes Assessment Areas with Scores “As Revised” A recounting of the Green Globes Stage 2 evaluation for each assessment area is included in the following sections. After Stage 1, the project was submitted at a 61.6% rating; however, several instances of partial credit were identified and updated during the Stage 2 Assessment that resulted in a decrease to the awarded score. In a few instances, recommendations for improvement on future projects are identified. Of particular importance for Drexel University are items that would have sustainable impacts across the campus, including those related to minimization of off-site treatment of water, alternative fuel re-fueling facilities and increasing water efficiency through lower flow plumbing fixtures. If these were implemented, the Green Globes ratings for future projects would be improved ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 5 of 12 Point Summary Table-Comparison Green Globes® New Construction Assessor Report Drexel University URBN Annex Center, Philadelphia, PA Assessor Manual and Survey Point Adjustments Point Summary Assessor: David Eldridge Assessment Dates: 6/3/2013-6/4/2013 Date: 6/21/2013 SECTION 1: PROJECT MANAGEMENT POLICIES AND PRACTICES Description 1.1 Integrated Design Process 1.2 Environmental Purchasing 1.3 Commissioning Plan- Documentation 1.4 Emergency Response Plan Management Totals Third Party Third Party User Self- Assessed Assessor Evaluation Online Manual Survey Survey Point Scores Scores Adjustment 20 20 0 10 10 0 15 15 0 5 5 0 50 50 0 Final Third Assessed Maximum Party Points Total Third Party Points Assigned Change Applicable Assessor Available Nonfrom User Points Final without Non- Applicable Self Available Scores Applicables Points Evaluation Comments & Explanation 20 20 20 0 10 10 10 0 15 15 15 0 5 5 5 0 Emergency response plan provided 5/20/13 50 0 50 50 0 SECTION 2: SITE Description 2.1 Developed Area 2.2 Minimization of Ecological Impact 2.3 Enhancement of Watershed Features 2.4 Enhancement of Site Ecology Site Totals Third Party Third Party User Self- Assessed Assessor Evaluation Online Manual Survey Survey Point Scores Scores Adjustment 30 30 0 30 0 20 80 30 0 20 80 -8 0 -11 -19 Final Third Assessed Maximum Party Points Total Third Party Points Assigned Change Applicable Assessor Available Nonfrom User Points Final without Non- Applicable Self Available Scores Applicables Points Evaluation Comments & Explanation 30 30 30 0 (1) No calculations were provided showing 35% of impervious surfaces are shaded- but visually appears to be close so partial credit given -3 points. (2) New roofing is specified as high-albedo, but spec's call for existing roof patching to be black. Rooftop ductwork was also painted black (beneficial in heating season, but adds to heat island in summer). Stage 2 allocated partial credit 30 30 22 -8 5 points. 15 15 0 0 40 115 0 40 115 9 61 -11 -19 Stage 2: Landscaping drawings show that only one species that will be planted at the URBN Annex bldg are native to PA. Lilyturf and fountain grass are invasive spacies. Partial credit for -11 points. SECTION 3: ENERGY Description 3.1 Building Energy Performance 3.2 Energy Demand Minimization 3.3 Energy Efficient Systems 3.4 Renewable Sources of Energy 3.5 Energy-Efficient Transportation Energy Totals Third Party Third Party User Self- Assessed Assessor Evaluation Manual Online Survey Point Survey Scores Adjustment Scores 0 0 0 60 56 0 66 182 33 56 0 76 165 0 0 0 -3 -3 Final Third Assessed Maximum Party Points Total Third Party Points Assigned Change Applicable Assessor Available Nonfrom User Points Final without Non- Applicable Self Available Scores Applicables Points Evaluation Comments & Explanation 100 100 0 0 No energy model provided Stage 1: R-values for walls and roof are not listed to check compliance with energy code. Provide ComCheck for walls and roof showing compliance with IECC '09: -2 pts. 114 66 20 80 380 35 10 4 49 79 56 20 76 331 33 56 0 73 162 -27 0 0 7 -20 Stage 2: Interior lighting is not suited for photometric sensors due to artistic functions requiring no windows, change 25 points from scored to N/A, change 10 points to N/A that were not scored originally. Chillers and elevators made N/A. Stage 1: (1) Alt. fuel refueling is not N/A: +4 to applicable (2) Changing facilities is not N/A as there is a shower and changing rooms in the Dressing Room +10 points. Stage 2: Bike racks are safe but not covered. Partial credit -3 points. SECTION 4: WATER Description 4.1 Water Performance 4.2 Water-conserving features 4.3 Minimization of off-site treatment of water Water Control Totals Third Party Third Party User Self- Assessed Assessor Evaluation Online Manual Survey Survey Point Scores Scores Adjustment 0 0 0 26 0 26 ©2013 Grumman/Butkus Associates, Ltd. 26 0 26 0 0 0 Final Third Assessed Maximum Party Points Total Third Party Points Assigned Change Applicable Assessor Available Nonfrom User Points Final without Non- Applicable Self Available Scores Applicables Points Evaluation Comments & Explanation 30 30 0 0 Stage 1: (1) Water metering is not N/A since irrigation is a high-use operation: +4 to applicable. Stage 2: (1) Water closets and lavatories are low flow. 8 points reinstated. (2) Energy Star washing machine counts for "other water conserving 45 10 35 26 0 features" 4 points reinstated. 10 10 0 0 0 85 20 65 26 0 June 21, 2013 Page 6 of 12 SECTION 5: RESOURCES, BUILDING MATERIALS AND SOLID WASTE Description Third Party Third Party User Self- Assessed Assessor Evaluation Online Manual Survey Survey Point Scores Scores Adjustment 5.1 Systems and Materials with Low Environmental Impact 5.2 Materials that Minimize Consumption of Resources 5.3 Reuse of Existing Buildings 5.4 Building Durability, Adaptability and Disassembly 5.5 Reuse and Recycling of Construction/Demolition Waste 5.6 Facilities for Recycling and Composting Resources, Building Materials and Solid Waste Totals Final Third Assessed Maximum Party Points Total Third Party Points Assigned Change Applicable Assessor Available Nonfrom User Points Final without Non- Applicable Self Available Scores Applicables Points Evaluation Comments & Explanation Stage 2: Existing structure and foundation are reused awarding credit for LCA for 20 points. 30 20 0 35 35 20 -10 6 8 0 16 16 8 2 20 8 0 20 20 8 -12 -5 14 9 0 14 14 9 5 5 0 5 5 5 0 0 0 0 10 10 0 0 75 50 0 100 100 50 -25 0 LCA for roof not provided so changed to "No". Stage 1: From documents provided, it does not appear that used materials will be included in this project (-2 points), but recycled materials will (steel is specified as recycled),+4 points. (1) No documentation provided showing that 100% of façade was reused - since it appears on the drawings to be only 50-75%. 75% credit given for -5 points (2) 50% of structure (not shell) was not kept this includes interior walls and ceiling systems. -7 points. Stage 1: Operable and pivoting walls do not qualify as "easy disassembly" - need to provide documentation about fastenings, fittings, and partition/wall/ceiling design. -5 pts. Stage 2: Packing materials for gallery artwork not recycled. SECTION 6: EMISSIONS, EFFLUENTS AND OTHER IMPACTS Description 6.1 Minimization of Air Emissions 6.2 Minimization of Ozone Depletion 6.3 Avoiding Contamination Sewers or Waterways Third Party Third Party User Self- Assessed Assessor Evaluation Manual Online Survey Point Survey Scores Adjustment Scores 15 15 0 25 25 0 6.4 Pollution Minimization Emissions, Effluents Impacts Totals Final Third Assessed Maximum Party Points Total Third Party Points Assigned Change Applicable Assessor Available Nonfrom User Points Final without Non- Applicable Self Available Scores Applicables Points Evaluation Comments & Explanation 15 15 15 0 25 25 25 0 0 0 0 5 24 64 24 64 0 0 25 70 3 3 5 0 0 22 67 24 64 0 0 Stage 1: Underground storage tanks are N/A: -2 to applicable. SECTION 7: INDOOR ENVIRONMENT Description Third Party Third Party User Self- Assessed Assessor Evaluation Online Manual Survey Survey Point Scores Scores Adjustment 7.1 Ventilation 30 19 0 7.2 Source Control of Indoor Pollutants 30 35 0 7.3 Lighting 7.4 Thermal Comfort 7.5 Acoustic Comfort Indoor Environment Totals 40 20 27 147 35 20 27 136 0 0 0 0 OVERALL TOTALS 624 571 -22 Final Third Assessed Maximum Party Points Total Third Party Points Assigned Change Applicable Assessor Available Nonfrom User Points Final without Non- Applicable Self Available Scores Applicables Points Evaluation Comments & Explanation Stage 1: Intakes and exhaust appear too close together, -6 pts Stage 2: (1) No OA monitoring stations, but CO2 sensor for RTU-1 - points remain unchanged. (2) MERV 8 filters were seen on site, 55 5 50 19 -11 5 points. Stage 1: Dedicated custodial and kitchenette exhausts would count for mitigation at source +5 50 15 35 35 5 points . Stage 1: On drawings, it appears that not all the interior offices/ticket/mtg spaces do not have views to outside and site-visit confirmed,-5 pts. Stage 2: local lighting controls made partial N/A since gallery and theaters would not want lighting controls beyond what is needed for 45 5 40 35 -5 art/performances. -5 to applicable. 20 20 20 0 30 30 27 0 200 25 175 136 -11 1000 97 903 549 -75 FINAL ASSESSMENT: 549 Points Accumulated out of 903 Available Points. Translates to 60.8% and Two Green Globes®. Project Management During the Stage 2 assessment, I was able to verify the integrated design process, verify installation of the green products specified, and confirm a team approach was used. The General Contractor’s Environmental Emergency Response Plan was provided prior to the site-visit, which reinstated five (5) points from the Stage 1 review. Precis Engineering was hired as the Commissioning Authority and a Commissioning Plan was provided. Drexel University was still expecting the completed commissioning report. ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 7 of 12 The Drexel URBN Center Annex was awarded 50 out of 50 possible Project Management points, equivalent to a 100% rating. Drexel University should continue good practices in this area. Site Considerations The project site is an existing serviced site in a dense urban area. The site is not a floodplain, a wetland, or a wildlife corridor. Erosion control measures were detailed on the civil engineering plan C701. Although no calculations were provided showing that at least 35% of the new impervious surfaces are shaded, during the Stage 2 Assessment it appeared to be a well-shaded area that included trees along the building frontage. Partial credit was given for a net reduction of three (3) points. The Stage 2 survey verified that there were few façade lights and bird strikes are not an issue, given that it is a low-rise building with no “see through” facades. Since the new roofing met high albedo specifications but the existing roofing was patched with black membrane, partial credit was awarded for a net reduction of five (5) points. Stage 1 reduced the awarded points by twenty (20) since the landscape drawings only showed one native planting, the Trumpet Creeper. It also specified Fountaingrass and Lilyturf, which are considered invasive species. During Stage 2, points for this category were broken down into three parts. Six (6) points were assigned to protection of natural corridor, six (6) points were assigned to plant species specifications, and eight (8) points were assigned to minimizing irrigated lawn areas. The UBN Center Annex was a major renovation project but it did affect the existing natural corridor by eliminating a vegetated courtyard, so six (6) points were changed to “No.” Given that at least one planting was a native plant species but two are considered invasive, two (2) points were changed to “No.” Finally, since the landscaped areas did include a small amount of lawn and were irrigated, three (3) points were changed to “No.” This resulted in a reduction of eleven (11) awarded points and an increase of six (6) notapplicable points. The Drexel URBN Center Annex is awarded an adjusted score of 61 out of 115 possible Site Considerations points, equivalent to a 53% rating. Suggestions for future projects: Future projects should look to build new construction on a remediated site, where applicable. Storm water management could be improved with a green roof and selecting pervious materials for any parking lots and hardscapes. Specify measures to minimize heat build-up on the entire roof, such as a green roof or high-albedo roofing materials. Use Energy Star compliant, high-reflectance, and high-emissivity roofing (initial reflectance of at least 0.65, a three-year-aged reflectance of at least 0.5 when tested according to ASTM E903, and an emissivity of at least 0.9 when tested according to ASTM 408). Green roofs are lightweight and easy to maintain. Green roof systems may be irrigated or not. They can be designed to be accessed by occupants. Specify a naturalized landscape utilizing native plants and trees. The number of indigenous species on a site can be increased through naturalization, whereby woodlands, meadows, and wetlands are re-created through natural regeneration or deliberate planting over time. Where possible preserve or create natural ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 8 of 12 habitat cores and corridors. If land must be cleared, specify that native plants should be salvaged for replanting on the site as part of the landscaping. Energy The Drexel URBN Center Annex has implemented some energy saving measures as well as constructed a building with high efficiency equipment. Energy performance targets were not set for this project and no energy model was provided. The majority of the walls and roof of the URBN Center Annex were existing to remain but there were new exterior walls and roofing as part of this project. The R-values for these items were not listed, so two (2) points were removed in Stage 1. The building is equipped with metal wall panels with waterproofing and a rainscreen. Air barriers specified in section 07 2700 met the requirements of local and national codes. Under the Integration of Daylighting Heading on the questionnaire, interior lighting is not suited for photometric sensors due to the artistic nature of the building’s functions. Twenty-five (25) points were changed from “Yes” to “N/A.” Additionally, another ten (10) points for window visual transmittance that were not scored originally were changed to “N/A.” Under Energy-efficient Systems, the chillers and elevators categories were manually marked “N/A,” since none exist on this project. This reduced the number of applicable points by ten (10). The Drexel URBN Center Annex incorporates energy-efficient equipment through the use of packaged rooftop units with economizer cycles and enthalpy wheels, variable speed drives on rooftop unit fans, 90% efficient motors, and point of use electric water heaters. The design strategy to serve areas with varying hours of usage and load durations from separate AHUs saves energy by not operating one central system continuously when any one area is occupied. Stage 2 confirmed that a bicycle rack was installed in a secure location but it is not covered. Partial credit was assigned for a decrease of three (3) points. Stage 1 changed alternative fuel re-fueling facilities and the changing facilities credits to applicable, which increased the applicable points by a total of fourteen (14). Stage 2 verified that a changing room is provided for ten (10) points. After making adjustments based on the Stage 2 Assessment, the Drexel URBN Center Annex is awarded 162 out of 331 possible Energy points, equivalent to a 49% rating. Suggestions for future projects: A good campus wide measure would be adding alternative-fuel re-fueling facilities throughout the campus. As alternative-fuel cars become more popular, this would present a nice addition for staff and visitors. URBN Center Annex and URBN Center could easily share one charging station due to their proximity. The use of renewable energy could be added in the way of solar water heaters for domestic water. A feasibility study could also be done for possible Photovoltaic (PV) or wind energy use at this facility. The electrical engineer should design the metering system to allow for submetering of major end uses. Sub-metering helps to motivate energy efficiency by monitoring the energy used for particular items. A ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 9 of 12 Measurement and Verification plan could also be written to track and analyze the data gathered by the submeters. An additional measure could include a monitoring system for lighting controls. Although the building was designed for efficiency with two lighting systems, one for use during exhibits and one for setup/teardown, both were observed to be on during the walkthrough. An interlock control should be installed to ensure only one lighting system is in use at a given time. Exterior fixtures were also observed to be illuminated during the survey. This may have been due to electrical work taking place next to the building. The control system for the exterior lights should be verified as returned to normal operating sequence when the contractor’s work is complete. These fixtures are not part of the URBN Center Annex’s electrical system but were located in front of the facility. Water Daily water consumption targets were not established for this building, though some water savings is realized through low flow water closets and lavatories. Additional points could be added by providing water usage calculations. However, the likely result would remain at Two Green Globes level of achievement. Stage 1 removed twelve (12) points for specifying non-low-flow water closets, sinks, lavatories and other water savings appliances. Stage 2 reinstated eight (8) points since the lavatories were seen to have 0.5 gallons/minute aerators and the water closets were 1.28 gallons per flush. Also, the clothes washer machines were verified to be ENERGY STAR® rated, which reinstated four (4) points under “other water-saving appliances.” Stage 1 changed water sub-metering to applicable, for four (4) additional applicable points. The irrigation system for the Annex building is water-efficient with rain sensors installed. Based on the Stage 2 Assessment, the URBN Center Annex is awarded 26 out of 65 possible Water points, equivalent to a 40% rating. Suggestions for future projects: Graywater collection or recovered condensate for non-potable water reuse (e.g. flushing toilets, HVAC system make-up) in the building could be considered for future building projects to improve sustainability in relation to water use resources. Completion of the water usage calculation spreadsheet will aid Drexel University in determining a suitable target for water usage. Resources, Building Materials, and Solid Waste Overall, the strengths of the Drexel URBN Center Annex project for this category lie in building adaptability, the use of materials with low-VOC, and recycled content. Although no Life Cycle Assessment data was calculated, the discussions during Stage 2 confirmed that thought was given to reduce life-cycle impact by utilizing the existing foundation/flooring assemblies as well as the majority of the structural elements. However, since no LCA was performed for the added new roof, this was changed to “No” for a decrease of ten (10) points. Stage 2 confirmed that 50% of the structure (not shell) was not reused and so seven (7) points were removed from this question. ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 10 of 12 Used materials were not incorporated into the project, so Stage 1 deducted two (2) points. Also, Stage 1 awarded four (4) additional points for use of recycled steel. The sheathing was specified as Forestry Stewardship Council certified. The original questionnaire claimed that 100% of the façade was reused. Stage 2 confirmed that only about 75% of the façade was reused, this deducted five (5) points. Stage 2 also confirmed that 50% of the building elements (not shell elements) were not kept, so seven (7) points were deducted. Stage 1 removed five (5) points since “operable and pivoting walls” do not qualify under for easy disassembly but do qualify for building adaptability. In order to qualify for these points, the project would have to include a narrative describing fastenings, fittings, and partition/wall/ceiling design and how they allow for easy disassembly. Construction Waste Management plan was included in the specifications and included a 75% reduction goal. The Drexel URBN Center Annex received a final score of 50 out of 100 possible Resources points, equivalent to a 50% rating. Suggestions for future projects: The main area for improvement on future projects is to perform detailed life-cycle assessments on building materials and assemblies. Additionally, future projects should ensure that materials and assemblies allow for easy disassembly. Components should be used that can be assembled or fastened in a manner that reduces deconstruction waste and facilitates reassembly into new construction. Detail the facility's waste handling and recycling facilities. Include the locations for the collection and storage of materials separated for recycling. To comply with Green Globes criteria, the recycling area should be equal to 20 ft2 for each 10,000 ft2 of building area, or 100 ft2 for buildings over 54,000 ft2. Emissions, Effluents, and Other Impacts This project did well in this category by the use of environmentally preferable refrigerants, low NOX furnaces on the packaged rooftop units, and localized exhaust for custodial closets and bathrooms. Pest minimization practices were specified in section 01 1000. Stage 2 confirmed low NOx furnaces, with less than 20 ppm emissions. Stage 1 reduced the applicable points in this category by two (2), since there are no underground storage tanks. The project utilized refrigerants with zero ozone depletion potential. The Drexel URBN Center Annex project is awarded 64 out of 67 points under the Emissions category, equivalent to a 96% rating. Indoor Environment Indoor air quality is enhanced through the use of an ASHRAE compliant ventilation rate and localized exhaust to mitigate pollution at source. ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 11 of 12 Stage 1 reduced awarded points by six (6) in the air entrainment question, since the air intakes for roof mounted equipment are located closer than 30 feet from exhausts and closer than 60 feet from other sources of pollution. Stage 2 reduced awarded points by five (5), since the filters installed in the rooftop units were MERV 8, not MERV 13. The original questionnaire stated that outdoor airflow monitoring would be provided but Stage 2 confirmed there was no airflow measuring stations installed. However, there are CO2 sensors, so the points for this criterion remain unchanged. The ventilation rate procedure was used to determine minimum compliance to ASHRAE 62.1 and the CFM/person rate was revised in the questionnaire to accurately state 6 cfm/person. Stage 1 reduced awarded points by five since not all interior spaces (office/ticketing/meeting area) have views to outside. Stage 2 confirmed this. Low-VOC materials in the design included adhesives and sealants. Legionella risk is mitigated by ensuring the domestic water heaters are set between 120-140°F. Local lighting controls was changed to partial “N/A,” since the gallery and theater spaces do not need lighting controls beyond what is needed for the artwork or performances. This reduced the applicable points by five (5). The Stage 2 walk-through demonstrated that indoor NC levels were acceptable and protection was provided from undesirable outside noise. Stage 2 also verified thermal comfort conditions of all primary spaces. During the Stage 2 site visit, two operational conditions were noticed that Drexel should address in order to receive the benefits of their original design: 1. The cafe exhaust fan was giving off a noticeable amount of noise. Drexel should consider controlling this fan via a switch so the fan can be easily turned off when not in use or configured with a VFD to allow the fan to operate at a slower speed during times of low usage. 2. The gallery area is equipped with two different lighting systems (a lower wattage system when artwork is displayed and a higher wattage, fluorescent system for when the space is used for functions and needs more light). The intent of this design is to only use one system at a time. However, during the site-visit both of the lighting systems were on. Drexel should communicate the proper procedure to staff to ensure that the high-wattage fluorescent lights should only be utilized during special events/theater functions when the additional light output is needed. Additionally, an interlock could be installed so that only one system may operate at a time. After making adjustments based on the Stage 2 Assessment, the Drexel URBN Center Annex is awarded 136 of 175 available points in the Indoor Environment category, equivalent to a 78% rating. ©2013 Grumman/Butkus Associates, Ltd. June 21, 2013 Page 12 of 12 Suggestions for future projects: Future projects should try and incorporate natural or hybrid ventilation. These strategies can be used to promote thermal comfort and lower utility bills by allowing more individual control over ventilation rates and lessening the demands on the HVAC system. This strategy is not applicable in all building types in a university setting but can be used in administrative areas if these areas do not connect with the areas with pressure differential requirements. High efficiency filters can be integrated into the AHU design, making sure that the fan motors can accommodate any additional static pressure from the higher efficiency filter. Summary The project has incorporated a number of significant sustainable practices into the design. The project is recommended for a Two Green Globes level of performance. For additional information about the Green Globes Assessment, please see the attached documents. APPENDIX A: Client’s Self-Evaluation / Original Verifier Worksheet APPENDIX B: System Generated Assessors Evaluation / Final Report APPENDIX C: Updated Verifier Worksheet Including Adjustments APPENDIX D: Site Visit Photos/Supporting Documentation Very truly yours, David S. Eldridge, Jr., P.E., BEMP, BEAP, HBDP Project Manager p:\13 projects\13156gbi.r01\wp\urbn center annex_stage 2 assessment report.docx Enclosures c: Dianne Elliott, GBI ©2013 Grumman/Butkus Associates, Ltd.