Office of Financial Management Washington State Major Project Status Report June 1, 2009 Agency Number: Project Number: School/Campus: Project Title: Bill Reference(s): 699 Agency: State Board for Community & 08-1-315 Technical Colleges Columbia Basin College – Pasco Campus Renovation – Business Education “B” Building Chapter 520, Session 07, Section 5241, Contact Name, phone number, email: William Saraceno V.P. Administration Columbia Basin College 2600 N. 20th Avenue Pasco, WA. 99301 509-547-0511 ext. 2248 Bill.Saraceno@columbiabasin.edu Al Downs Capital Projects Columbia Basin College 2600 N. 20th Avenue Pasco, WA. 99301 509-547-0511 ext. 2356 adowns@columbiabasin.edu Project Description: This project is to renovate Columbia Basin College’s Business “B” Building originally constructed in 1958. New right sized classrooms and labs will create a more effective learning environment for the 21st century. Renovation will support growth in CBC programs that are supporting the community economic diversification efforts, support WSU-Tri-Cities transfer requirements, a new baccalaureate program in business and provide opportunities to replace failing HVAC units, incorporate electrical conservation techniques, update plumbing, and replace the roof. The building will provide classroom space, a new computer support center, two new classrooms, and specific student team project space for students in the following programs: Business Criminal Justice Digital Media / Marketing Classrooms will be equipped with appropriate technology to support effective modern teaching/learning for the above programs, as well as general-use classrooms. The architectural firm (RGU Architecture, Asotin, WA) has provided project development, design development, and has continued providing consultant services through construction completion. Square feet: 22,500 Scope Changes: Design was awarded in July of 2007. During the design phase, unforeseen conditions concerning the underground central steam system were discovered and the cost to replace the affected line sections that feed the B Building was included in the project scope of work. Early after the release of the 2007-2009 Capital Budget, the College strategized as to how best package our capital projects for the up-coming biennium. For cost effectiveness in management, construction, and bidding, it was decided to add our Facilities Repair A as an element of the project. After the bid opening, it was confirmed we received a better bid due to efficiency of scale the contractors bidding the project would get doing both at the same time. Project Total Cost: Phase Predesign Design Construction Other (Approp/Non-Approp) Total MACC Biennium 2005-2006 2007-2008 2008-2009 2008-2009 Appropriation I32 I32 Amount $ 32,000 $ 463,000 $3,681,000 $1,067,914 $4,564,500 Total Project Revenue: Phase Biennium Appropriation Leg. Allocation Leg. Allocation - Facility Repair A Total 2007-2009 2007-2009 I32 I32 Amount $5,020,000 $1,067,914 $6,087,914 Schedule: Pre-design Complete Start Design Bid Date Notice to Proceed 50% Complete Substantial Completion Final Acceptance Budget Schedule 7-1-2006 7-15-2006 3-30-2008 5-15-2008 11-15-2008 4-15-2009 6-1-2009 Actual/Forecast 7-1-2006 7-15-2006 5-21-2008 6-23-2008 11-25-2008 5-15-2009 6-15-2009 Variance (wks) 0 0 6 4* 1 4** * Project Notice to Proceed was shifted 4 weeks to allow the completion of spring quarter prior to the start of the project. This will allow time for finals to be completed and the College to remove A/V and other educational equipment and furnishings. ** Shift in date reflects 4 week shift in notice to proceed date. Project is actually only one week off of projected completion. Project Status and discussion of Critical Path for Construction: Design development for the Business Education “B” Building was completed early fall 2007. Per the project request, the project includes 4,400 sqft of new space to allow for right sizing of classroom space, adding adequate space for infrastructure, and improve circulation. Construction documents were originally scheduled to be completed by mid February, 2008 but due to unforeseen conditions were delayed 30 days. Site pot holing proved previously undocumented high voltage lines did exist and would impact the project if the building location remained as planned. This led to a decision to shift the building to the south slightly allowing the electrical lines to remain undisturbed. Value engineering started at the beginning of Construction documents and was completed prior to the issuance of comment drawings. A constructability review was conducted when the documents were at 95 percent in order to make the best use of the review team time. Project was originally slated to be advertised for bid March of 2008, with construction projected to start by June, 2008. Even with the schedule shifted by 30 days, the design team, through good project management, was able to complete the documents for bid on time and we were able to award the project in sufficient time to stay on our planned construction start of June, 2008. The critical path for this project started June 23, 2008 with the completion of the College removing A/V and other valuable equipment from the building. The Contractor then took possession of the building and the project critical path. Chervenell Construction Co. from Kennewick, WA was the successful low bid on the project. All elements of the project were accepted. Since the notice to proceed (June 23, 2008) the Contractor has consistently met deadlines and objectives. As a whole, the project is on schedule. An unusually wet winter and frequent snow on both sides of the State contributed to approximately an 8 day lag in the project schedule. Some tasks were early started and others were pushed out from the original schedule to compensate for the weather. The critical path has remained intact. Contract Award History A/E Agreement Original Agreement Amendments Pending Changes Total Current Design Contingency $ $ $ $ 261,194 11,500 272,694 $ 39,613 Construction Contract (excl. sales tax) Bid Award Amount $4,559,600 Change Orders $55,248 Pending Changes $8,000 Total $4,559,600 Current Construction Contingency $ 335,291 Potential for Project Cost Overruns/Claims During design development, this project benefited from having business education faculty involved with the process. The design team obtained a clear understanding of what is needed for the building and was able to translate the needs into construction bid documents that were easily understandable by the contractors who bid the project. Bid results indicate only eight percent between high and low bid. Prior to the start of the project construction stage, the College and design team with C/R agreement did not believe there exists a basis for any major changes or impacts to the project. Follow up to the preceding statement: To date there have been no major changes. Minor unforeseen conditions were dealt with early and at minimal cost. The bulk of changes have been to better meet the long term usage requirements of the programs to be housed in the building, specifically the new baccalaureate business program. The Contractor is a well known local contractor with a very good reputation who has worked with the College previously on projects more complicated than this project. Although market driven costs were a concern at the start of the project, we believed the risks have been identified and our plan would address any potential impacts. To date we have not seen an impact to the project caused by the market. Sustainability efforts for LEED Silver did add some initial cost, but the budget was able to accommodate those costs and long term payback will offset the initial costs. Discussion of Project Quality This project incorporates design standards developed for CBC facilities on the Pasco Campus that are based on previous experience and design team input. Each building system component or product was reviewed and discussed prior to project inclusion and will reflect the quality and design of all buildings constructed within the College’s service district. Building design incorporates lessons learned from other community college projects throughout the state, as well as, the College’s own recent projects. The design code followed for the project was the International Building Code in conjunction with current City of Pasco and state code and practice. Project quality will be at or above state standards for life and energy conservation. This project is designed as a LEED Silver and will be presented for certification at the end of the project. Through careful attention to sustainable design elements and incorporation into the project and the contractor’s efforts to comply with the LEED requirements, this project will be submitted for Gold certification. Quality of construction is evident in the ownership the General Contractor and major sub contractors have taken in the project. It is reflected in each trade's workmanship. The renovation of this building will continue the facility plan started in 1999 and reviewed in 2005 with the ultimate goal of all buildings providing a quality supportive learning environment for the current and future students. Project Photographs The Office of Fiscal Management and SBCTC Capital Office have concept floor plans and graphics available for review as a part of the project request package. Photographs, imbedded below, show current project condition. At the end of the project a CD of the project from start to finish will be available upon request from the College’s Administrative Services office. 90 days after NTP new roof sheeted and ready for ice shield. 130 days work proceeding rapidly throughout interior. December start of the first extended snow period. Project moving at acceptable schedule rate. Main Hall in January Main Hall at start of May Photos that follow depict current project status: