Preliminary observations from a geosynthetic reinforced piled embankment King, D. J., Bouazza, A. & Bui, H.H. Monash University, Civil Engineering, Melbourne, Australia Gniel, J Golder Associates Pty Ltd, Melbourne, Australia Rowe, R.K. Queen’s University, Department of Civil Engineering, Kingston, Canada ABSTRACT: A recent rail infrastructure project in Melbourne, Australia has seen the construction of a number of geosynthetic reinforced (GR) piled embankments to overcome the challenges associated with the local soft soil present throughout much of inner Melbourne, Coode Island Silt (CIS). To better understand the behaviour and performance of the load transfer platform (LTP), a field case study has been undertaken involving the instrumentation of one of these embankments. This paper presents data gathered during the construction and post-construction phases (approx. 9 months) as well as discussion on the LTP behaviour observed thus far. The development of arching, as seen from these preliminary results, is currently increasing with time; it is suggested that this increase is related to a coupled response between the arching mechanism and the GR/sub-soil deformation. The effects of piling works in close proximity to the LTP are also discussed and further work as part of this on-going research is described. Keywords: Load transfer platform, basal reinforcement, arching, geogrid, field study 1 INTRODUCTION A recent rail infrastructure project in Victoria, Australia, currently the largest public transport infrastructure project in Australia, saw the construction of a new rail link between regional Victoria and the Melbourne CBD. The inner city area of Melbourne, particularly the inner west and south is underlain by soft soil known as Coode Island Silt (CIS). Within the local geotechnical profession the CIS unit is well known, with a large amount of literature (both published and un-published) describing the properties and settlement performance. To meet rail performance criteria and minimise construction time, GR piled embankments supported on drilled displacement piles (DDPs) were proposed. Design commenced in 2012, construction was completed during 2013. The instrumented embankment is a widened embankment, approximately 60 m in length. The LTP is split over 2 levels (upper and lower level) along the length of the embankment to minimise the potential to induce settlement beneath the existing embankment. This paper presents instrumentation data gathered during the construction phase, as well as approximately 4 months of post-construction data. Understanding the behaviour of the LTP, in particular the load distribution which occurs due to arching, the behaviour of the GR and subsoil support, is vital in order to ensure the design is both efficient and economical. The data presented shows the arching mechanism continuing to develop with time, consistent with preliminary behaviour observed in field studies undertaken by others (Van Eekelen et al. 2008, 2010, Haring et al. 2008 and Van Deijnen et al. 2010). In addition, the effects of piling works (ground improvement for the upper level LTP) on the arching mechanism of the lower level LTP supporting the partial built embakment is described. When describing the LTP and the behaviour of the GR, the sub-soil support has an important role. In this case it is expected that the presence of approximately 2 m of fill material overlying the CIS will influence the sub-soil response. Further to this, the stress history of the CIS and the current stress levels suggest that loss of subsoil support will take a considerable period of time. The available geotechnical information, historic data and literature available on CIS will be used to support numerical modelling of sub-soil response as part of this on-going research. 2 PILED EMBANKMENT: LOAD TRANSFER When constructing embankments over soft soils, piled foundations with a geosynthetic reinforced layer at the base are commonly used to limit both total and differential embankment settlement. The geosynthetic reinforced layer, typically referred to as a load transfer platform (LTP), redistributes embankment load to the piled foundations through a combination of the arching effect, due to the differential stiffness between the piled foundations and soft sub-soil, tensile forces induced in the geosynthetic material and subsoil support. A number of methods have been developed to describe this load distribution; an understanding of the load distribution allows the design engineer to specify the type, size and spacing of the piled elements and the details of the LTP, specifically the type of geosynthetic reinforcement. Design standards, EBGEO (2010) and BS8006 (2010) are two examples of formalized design standards which have incorporated various aspects of research undertaken in this field. However, these design standards, as well as many of the methods in the published literature, produce results which often vary considerably. 3 FIELD CASE STUDY 3.1 Site Conditions The subsurface conditions encountered at the site are typical of the Yarra Delta region near the Melbourne CBD and comprises Quaternary aged Yarra Delta sediments overlying the Silurian aged mudstone and sandstone of the Melbourne formation, the basement rock beneath Melbourne. The subsurface conditions vary significantly along the length of the embankment with the thickness of the Quaternary units generally increasing towards the eastern end of the embankment, adjacent to a creek. For design purposes the thickness of the CIS is the main concern and was found to vary between about 15 m at the eastern end and around 5 m at the western end where embankment widening was completed without ground improvement. Sub-surface conditions beneath instrumented area No. 2 are presented in Table 1. The base of the lower level LTP is at RL 2.0m. Figure 1 presents the nearest CPT test location, CPT30. For settlement analysis, the CIS is the dominate unit within the Yarra Delta sequence owing to its highly compressible nature. The fill will contribute to a much lesser extent depending on its thickness and Unit Fill Depth (m) (R.L. (m)) 0.0 (3.7) Coode Island Silt (CIS) 4.3 (-0.6) Fishermens Bend Silt 15.1 (-11.4) Moray St Gravel/ Werribee Formation Siltstone – Melbourne Formation 16.7 (-13.0) Description Very stiff Gravelly CLAY Soft Silty CLAY, increasing to firm with depth Stiff to very stiff, Silty CLAY and Sandy CLAY Dense, Sands, Gravel, Clay beds Not encountered (-23) Table 1: Sub-surface conditions beneath instrumented area No. 2. Figure 1: CPT30. Depth 0.0 m strength; in this case in excess of 95% of surface settlement beneath the embankment would be expected to occur in the CIS. Settlement characteristics of the CIS are well described in the published literature (Neilson 1992, Ervin 1992 and Srithar 2010). A number of geotechnical investigations were performed prior to construction. As part of detailed design the CIS thickness was determined by performing closely spaced CPTs along the length of the widened embankment. Historic information, described in Section 3.2, is also utilised. Construction records from installation of DDP (rig torque, penetration rate, etc.) provide additional information to assess the thickness of the CIS unit. 3.2 Background The existing embankment which is to be widened is approximately 8 m in height and was constructed without ground improvement. In the early 1970s an older wooden bridge crossing the adjacent creek was replaced by extending the existing embankment (without ground improvement) and constructing a reinforced concrete bridge. In the mid 1980s structural distress of the bridge abutments was attributed to settlement of the extended section of embankment. An extensive geotechnical investigation (Golder Associates 1984 - various reports) was performed with a large number of in-situ shear vane tests within the CIS and in addition, settlement monitoring over a period of 6 years from the mid 1980s onwards was recorded. Further investigation followed in the early 1990s (Consultant report 1990). This monitoring provides a detailed account of the secondary compression characteristics of the CIS and provides a useful baseline performance measure for the existing embankment performance. 3.3 Design The proposed widened embankment design had to meet more stringent rail performance criteria than the existing embankment, and in addition, the potential to cause settlement beneath the existing embankment had to be limited. A GR piled embankment was therefore seen as the most suitable option to meet these requirements and to also meet the proposed construction timeline. To minimize the impact on the existing embankment it was necessary to install DDPs from 2 levels such that the increased load acting on the CIS and the shoulder of the existing embankment was supported by a LTP. The rigid elements constructed are drilled displacement piles (DDPs), 450 mm diameter, with enlarged cast in-situ pile heads measuring 1 m by 1m. Typical centre-centre spacing varied between 2.0 m and 2.5 m. The LTP is 650 mm thick, Geosynthetic reinforcement is provided by two layers (transverse and longitudinal) of uni-axial geogrid (ACEGrid ® PET GG200 geogrid) with an ultimate tensile strength of 219 kN at 10 % strain. Transverse geogrid was placed 100 mm above the base of the LTP. A further 100 mm separates the overlying longitudinal layer. Additional material properties are presented in Section 3.4 Due to the proximity of the proposed embankment to a nearby creek, it was a requirement to minimize the embankment footprint within what is an urban flood plain. Embankment batter slopes were therefore not suitable and the construction of gabion walls was required. The DDPs on the upper level were installed at various levels between RL 4.0 m and RL 4.6 m depending on the geometry of the existing embankment. This occurred following construction of the first 2 rows of gabion wall. The embankment is shown in Figure 2 following installation of the lower level DDPs. The DDP heads are at RL 2.0 m, the existing embankment is on the left hand side and the creek can be seen in the distance. An embankment cross section at the location of instrumented area No. 2 is shown below in Figure 3. Instrumentation area No. 2 A A’ Figure 3. Embankment cross section at instrumented area No. 2. Figure 2. Instrumented embankment following installation of DDPs, facing east. 3.4 Embankment material properties The LTP comprises a 650 mm thick layer of 75 mm minus “rockfill”. Embankment material comprised “Type B” fill compacted to 95% standard compaction. 3.5 Construction timeline Due to a number of site constraints, the embankment construction and ground improvement works were performed over a number of stages. Ground improvement on the lower level occurred over a period of about 1 month between March to April 2013 (Stage 1) and a 1 week period in June 2013 (Stage 2). Figure 2 shows the site on April 17 2013 after the completion of Stage 1 ground improvement. Instrumentation (Area No. 2) was installed the following day. Due to site constraints an area near the creek end of the embankment was delayed by about 2 months, ground improvement works in this area were not completed until June 2013 (Stage 2). Additional instrumentation (Area No. 1) was installed in this area in early July, not long after completion of Stage 2. Due to the delays between Stage 1 and 2, the embankment and gabion wall construction was staggered. The upper level LTP and associated ground improvement was also undertaken in two stages. Stage 3a (adjacent to Stage 1) was completed in early July over a 1 week period. Stage 3b (adjacent to Stage 2) was completed over a 1 week period in September. Following this the third embankment lift was completed. Much of the embankment above this level is a batter slope and for this reason construction progressed rapidly to the finished height of 7.1 m (RL 9.1 m) on 24 October 2013. 3.6 Instrumentation Instrumentation was installed in 2 areas with the general aim to capture the LTP behaviour beneath the centre of the embankment in one area and its behaviour near the edge of the embankment, where lateral forces are expected to act, in the other. The instrumentation installed comprised: Area No. 1 • comprised 8 pairs of strain gauges and 2 “dummy” gauges (18 total) • 3 earth pressure cells (EPCs) • 2 horizontal inclinometers • Piezometer. Figure 4: Area No. 2 instrumentation Area No. 2 • 10 pairs of electrical resistance strain gauges, 2 “dummy” strain gauges (22 total) • 3 earth pressure cells (EPCs) • 3 tiltmeters cast-in-situ at various depths within a DDP • 1 vertical inclinometer adjacent to the instrumented DDP. Additional piezometers were planned for installation but could not be installed. This paper focuses on the area No. 2 instrumentation; the approximate location is indicated in Figure 2. Figure 4 presents the instrumentation layout. Strain gauges were installed in pairs to ensure repeatable results on both longitudinal and transverse geogrids layers. Gauges installed are Vishay – Micro Measurements® general purpose strain gauges (CEA-06-205UN350) and measure 10.5 mm by 3.1 mm. The use of these gauges to measure strain in a woven geogrid is described by Oglesby et al. (1992) and Warren et al. (2010). Gauge calibration required tensile testing in accordance with ASTM D 6637 to obtain a relationship between gauge strain (localized) and geogrid strain (global). In Area No. 2, three EPCs were installed. EPC1 was installed 100 mm above the DDP head (beneath the transverse geogrid layer); EPC2 and EPC3 are within the subsoil area. EPC2 is at the base of the LTP and EPC3 is 100 mm below the top of the LTP. Tiltmeters were installed in a DDP at RLs 1.71 m, -0.56 m and -3.0 m to measure the lateral deformation of the DDP beneath the gabion wall. A vertical inclinometer was installed 1.6 m from the centre of this DDP (700 mm from the edge of LTP) to measure the lateral deformation of the surrounding soil to provide a comparison with the DDP deformation. Automated data acquisition commenced on day 96, manual readings were taken prior to this. Day 0 is defined as 3 May 2013, when instrumentation in Area N0. 2 was first installed. 4 PRELIMINARY RESULTS AND OBSERVATIONS 4.1 Load Transfer Platform – EPC data Figure 5 presents the EPC data which is plotted against days elapsed since installation (i.e., days since 3 May 2013). The embankment height, described in Section 3.5, is also plotted. The two periods of ground improvement for the upper level LTP, Stage 3a and 3b, occurred between days 63 and 71 and days 131 and 137 respectively. The gap in data is due to power loss and EPC2 did not respond for a period due to a wiring issue. Embankment construction was completed with the placement of track formation on Day 176 (24 October 2013). This arching behaviour, as observed based on the EPC data, is described in choronological order. The LTP (650 mm thick) was placed on Day 1, EPC pressure matched closely the overburden stress, arching does not occur at this point. Note that all EPCs show an initial spike in pressure immediately following placement of the LTP and Lift No. 1. This is due to an increase in overburden stress and the effects of dynamic compaction, compaction induced stresses dissipated over the days following. Embankment lift No. 1 was completed on day 34 (embankment height 1.95 m). At this point the cell pressure observed in EPC2 (base of LTP, 2.05 m of overburden) reduces to a value less than EPC3 (top of LTP, 1.35 m of overburden) cell pressure despite having a much larger overburden stress. This behaviour indicates that partial arching formed at this point, although the expected stress increase in EPC1 is not as obvious. This is likely offset by the initial dynamic compaction induced stresses. The arching continues to develop after embankment lift No. 2, however the development of arching is now more pronounced. The arching is affected by the Stage 3a piling works, as observed by the Lift Nos. 3-7 Lift No. 2 (some earthworks) Lift No. 1 LTP Refer to Fig. 6 Stage 3a Piling Figure 5: EPC data and embankment height. Stage 3b Piling significant increase in EPC2 cell pressure, suggesting partial arching collapse. The effect of these two periods of ground improvement works (day 63 to 71 and 131 to 137) is more clearly evident during the second phase were the data acquisition hardware was in operation. This is discussed in Section 4.2. During an extended period midway through construction (day 71 to day 132) and the period postconstruction it can be seen that arching is increasing with time at constant overburden stress. This is not expected to occur indefinately; a point of maximum arching is expected to occur. To date the observed behaviour suggests that maximum arching has not yet been reached. This is similar to the preliminary arching behaviour observed in a series of Dutch field studies, including; Van Eekelen et al. (2008, 2010) where arching took around 9 months post-construction to fully develop. Similar behaviour was observed in both a shallow and a full height test embankment (Haring et al. 2008) and a piled railway embankment (Van Deijnen at al. 2010). It is thought that the development of the arching is related to the coupled behaviour between the arching mechanism and the GR/sub-soil deformation. Conceptually, this observation is similar to the arching described in 2D trapdoor arching tests by Iglesia et al. (1999, 2013) and observed more recently in 3D laboratory experiments by Van Eekelen et al. (2012a,b). The time dependent behaviour observed arises due to the nature of the sub-soil deformation occuring, more specifically, time dependent consolidation of the CIS. 4.2 Ground improvement works and arching Installation of the upper level DDPs during both Stages 3a and 3b had an effect on the performance of the lower level LTP on both occasions. However, this can be observed best during Stage 3b when data acquisition was automated on a 4 hr time step. EPC data gathered during Stage 3b ground improvement works, days 131 and 137, is shown in Figure 6. The DDP layout in shown in Figure 7. Three separate spikes in the data can be seen, the general response of the 3 EPCs in each case is the same. The magnitude of the response does however vary and it can be seen that this is related to the proximity of the DDP to the instrumented area. In each case, the general response saw the stress acting on EPC1 reduce and a corresponding increase in EPC2 and EPC3. EPC3 at the base of the LTP shows a larger increase than EPC2 in each case. The three events (Day 136 is 2 timesteps) are described below: • Day 133 – Midday to 4pm. 3 DDPs installed in the vicinity of instrumented area No. 2. F11 (11.4 m), G12 (10.2 m) and H13 (11.2 m). This distance in brackets is the distance from DDP to EPC2/3 which is close to the center of a soil arch (E14,E15,D14 and D15). • Day 136a - 8am to Midday. G12 (8.2m) • Day 136b –Midday to 4pm. G14 (5.6 m), G13 (9.0 m) and J14 (9.2 m) • Day 137 – 8am to Midday. F13 (6.8 m) and H14 (7.4 m) The response of the EPC suggests that partial collapse of the soil arch has occured on each occasion. Given the strong correlation with the timing of the installation of the DDPs it is suggested that this response is primarily due to lateral deformation of the LTP and the embankment material overlying it from the installation of these full displacement piles. It is possible that dynamic loading from the piling rig tracking across the upper level hardstand may contribute, however this doesn’t correlate with the data and is considered unlikely. It is likely that the day to day fluctuation in the EPC data observed in Figure 5 are due to dynamic loading from earth moving eqiupment, however the response of the EPCs during Stage 3a piling is of much larger order of magnitude and a different mechanism is required to explain this behaviour. Numerical simulation of drilled displacement piles by Pucker and Grabe (2012) showed that bulk density modelled increased adjacent to the DDP and reduced exponentially at a distance from the DDP. For the single DDP modelled in dense sands, approximately six pile diameters (6D) was suggested as the maximum zone of influence and 8D for the loose sand modelled. The zone of influence observed here is 12.4D (G12) and increases to over 20D for DDPs installed on Day 133. This perhaps gives some insight into the sensitivity of the soil arch to external loading/deformation. Based on the EPC data, the response to the piling installation is consistent in each case; partial collapse of the arching mechanism. Equally consistent is the response following the partial arching collapse, in each case the arching mechanism trends towards its previous state. This is consistent with the general trend (Figure 5) observed between Day 71 to 132 and post construction. In all cases the arching mechanism trends towards a state of increased arching. It should be noted that this would be expected to occur up until some maximum sub-soil/GR deformation. Irreversible, complete collapse of the arching mechanism would be expected at very large sub-soil/GR deformation. Day 133 Day 136a,b Day 137 Stage 3a - Piling Figure 6. EPC data and embankment height. Figure 7. DDP layout. 4.3 Geogrid performance and sub-soil support. In order to describe the behaviour of the sub-soil support beneath the LTP it is necessary to understand the stress history of the CIS, which for this site is not an easy task given the site history. Approximately 2 m of fill has overlain the CIS historically (likely greater than 50 years), the existing rail embankment has been constructed and more recently site surcharging occurred as part of construction activities. The current vertical stress acting on the sub-soil (as measured from EPC3) has for the large part been less than 40 kPa; at present it is less than 25 kPa and reducing further. We consider that the current vertical stress is less than, or about equal to, the effective overburden pressure associated with the historic fill. Given the significant period of time in which the historic fill has been in place it is considered that primary consolidation is complete and that ongoing settlement is largely related to secondary consolidation. If the stress levels acting on the CIS remain as they are, or continue to reduce as expected, then loss of sub-soil support is expected to also occur primarily as a function of the secondary consolidation of the CIS. It should be noted that the ground improvement performed will further reduce the rate of settlement; the effect on the CIS due to the ground improvement requires further work to quantify. With these factors in mind it is apparent that loss of sub-soil support (and hence development of tensile load in the GR) will take a considerable period of time. Assessing the rate of subsoil settlement, and in turn the development of GR tensile load, will be part of this ongoing research. The initial strain gauge readings, which are typically very small, therefore seem quite reasonable given the expected slow rate of sub-soil settlement. Strain gauge readings at present are generally less than about 0.2%, which is considered within the error range for this type of strain measurement. In addition, it is likely that some initial slack in the geogrid is being taken up. 5 CONCLUSIONS AND ONGOING RESEARCH Based on the preliminary results from this instrumented embankment, the following conclusions are made: • Arching within a piled embankment can be clearly observed through the variation of vertical stress in the LTP as is expected. • The development of the arching mechanism is observed to develop with time. It is suggested that this occurs due to sub-soil/GR deformation; initially this deformation is largely a function of sub-soil behaviour. The time dependent nature arises in this case due to primary consolidation of CIS. • The response of the soil arch to external loading would appear to be fairly sensitive. The effect of piling installation (full displacement piles) on the arching mechanism at a range of up to 20D is noticeable and measurable. • The response of the arching mechanism to the piling installation is a short term response only. The arching mechanism in the piling installation cases, and in general, trends towards a state of increased arching. 6 ACKNOWLEDGEMENTS The authors would like to thank both Golder Associates (through a “Innovation and Excellence” (i2x) award) and Monash University for their financial assistance and support as well as the Regional Rail Link – City to Maribyrnong River (RRLCMR) Alliance for supporting and providing the opportunity to undertaken this field case study. In addition, the design support provided by the RRLCMR Alliance to obtain the necessary approvals and their assistance during both the construction and instrumentation installation phases is greatly appreciated. REFERENCES British Standard, BS8006-1, 2010. Code of practice for strengthened/reinforced soils and other fills. Consultant report (1990) – Bridge Investigation, North Melbourne. Dated August 1990. Duijnen, P.G. van, Eekelen, S.J.M van & Stoel, A.E.C. van der 2010. Monitoring of a railway piled embankment. Proc. 9th International Conference on Geosynthetics, Guaruja, Brazil, p. 1961-1964. EBGEO, 2010. Recommendations for design and analysis of earth structures using geosynthetic reinforcements – EBGEO. German Geotechnical Society. Translated English version of 2nd edition of EBGEO. Ernst & Sohn. Eekelen, S.J.M van, Bezuijen, A. & Dimiter, A. 2008. Piled embankments in the Netherlands, a full-scale test, comparing 2 years of measurements with design calculations. 4th European Geosynthetics Conference (EuroGeo4), Edinburgh, Scotland. Paper no. 264. Eekelen, S.J.M van, Bezuijen, A. & Dimiter, A. 2010. The Kyoto Road, monitoring of a piled embankment, comparing 3½ years of measurements with design calculations. Proc. 9th International Conference on Geosynthetics, Guaruja, Brazil, p. 1941-1944. Eekelen, S.J.M van, Bezuijen, A., Lodder, H.J. and Tol, A.F. van 2012a. Model experiments on piled embankments. Part 1. Geotextiles and Geomembranes Journal, 32, p. 69-81 Eekelen, S.J.M van, Bezuijen, A., Lodder, H.J. and Tol, A.F. van 2012b. Model experiments on piled embankments. Part 2. Geotextiles and Geomembranes Journal, 32, p. 82-91 Ervin, M.C. 1992. Engineering properties of Quaternary aged sediments of the Yarra Delta. Engineering Geology of Melbourne, Olds and Seddon (editors). Golder Associates 1984 – Bridge Investigation, North Melbourne. 4 reports dated April 1984 to September 1987. Haring, W. Profittlich, M. & Hangen, H. 2010. Reconstruction of the national road N210 Bergambacht to Krimpen a.d. Ijssel, NL: design approach, construction experiences and measuring results. Proc. 4th European Geosynthetics Conference (EuroGeo4), Edinburgh, Scotland. Paper no. 259. Iglesia, G. R., H. H. Einstein and R. V. Whitman 1999. Determination of vertical loading on underground structures based on an arching evolution concept. Geo-Engineering for Underground Facilities, ASCE. Iglesia, G. R., H. H. Einstein and R. V. Whitman 2013. Investigation of Soil Arching with Centrifuge Tests. Journal of Geotechnical and Geoenvironmental Engineering. Neilson, J.L. 1992. Geology of the Yarra Delta. Engineering Geology of Melbourne, Olds and Seddon (editors). Oglesby, J. W., Mahmoodzadegan, B. and Griffin, P. M. 1992. Evaluation of methods and materials used to attach strain gauges to polymer grids for high strain conditions. Report No. FHWA/LA-92/265, US Department of Transport ation, Federal Highway Administration, Washington, D.C., 54 pages. Pucker, T. and Grabe, J. 2012. Numerical simulation of the installation process of full displacement piles. Computers and Geotechnics 45 , p. 93-106. Srithar, S.T. 2010. Settlement characteristics of Coode Island Silt. Australian Geomechanics, Vol. 45 no. 1 p. 55-64 Warren K.A., Christopher, B. and Howard, I.L. 2010. Geosynthetic strain gage installation procedures and alternative strain measurement methods for roadway applications. Geosynthetics International, 2010, 17, No. 6, p. 403-430.