SMOV3A REQUIREMENTS This is a mark-up of the SM3 SMOV Level III Requirements Document (SMO-1000, App. H, June 26, 1998), that originally addressed a single SM3 mission. The entries in purple indicate those requirements which apply to SMOV3b, only. SMOV3A. All else applies to The entries in blue indicate wording changes or typo- corrections with respect to the original document. (Note: As of 9 April 99, these changes have not yet undergone the CCB review process. ================================================================== H.11 Observatory Verification. The Servicing Mission Observatory Verification (SMOV) period starts when the HST is released from the Orbiter and encompasses those activities required to re-enable science observing with the HST. The goal of this program is to safely and quickly return HST to normal science operations with specific on-orbit checkout planned only for those subsystems and instrument packages directly affected by servicing. Those sub- systems and capabilities that are not expected to be affected by the servicing mission will be examined by the SMOV Planning Team with contingency plans developed for system level or critical path activities in the event that the assumed capabilities are not available. During the SMOV period there will be no planned, unnecessary exercising of the instruments and subsystems (i.e., activation of modes not planned for use in normal operations) which specifically precludes activities such as switching to redundant signal paths or activation of fail-safe mechanisms to verify that they work. As much as possible, engineering requirements will be verified by monitoring and trend analysis of otherwise motivated activities occurring over the course of the SMOV period to alleviate the allocation of spacecraft time to requirements that can be verified over time with routine telemetry. Science checkout and calibrations will encompass only those activities required to recommission the HST Observatory for the cycles 8 & 9 science program with the remainder of the science calibration and on-orbit verification occurring in conjunction with cycles 8 & 9 science operations. This will include verification that the new scientific instrument meets those Contract End Item (CEI) Specification performance requirements not previously verified and which are most pertinent to the science program. H.11.1 WFPC II Verification Requirements. The following two assumptions apply to WFPC II at the point of HST release: 1. WFPC II is in PROTECT-SAFE mode. 2. The WFPC II shutter is closed with the F785LP filter in place. H.11.1.1 H.11.1.1.1 Engineering Activation and Check-Out Requirements After release, the instrument shall undergo an active decontamination procedure of at least 12 hours. In the interval between release and the start of the decontamination procedure, the shutter shall remain closed and the Thermal Electric Coolers (TECs) shall remain off. H.11.1.1.2 Upon completion of the decontamination procedure, the instrument shall undergo a contamination verification phase of at least 48 hours which shall be monitored by the ST ScI. Upon the approval of ST ScI, the instrument shall be cooled to its nominal operating temperature and the AFMs shall be reset. H.11.1.1.3 Following TEC turn on, a standard UV stellar monitor shall be scheduled at least twice during the first week and, starting with the second week, at a declining frequency for the duration of SMOV as part of the WFPC II Cycle 8/9 calibration program. [The ST ScI will use the UV monitor to determine whet-her the instrument remains at its operating temperature or under-goes further decontamination.] H.11.1.1.4 A short-wavelength (approximately Lyman alpha) stellar observation shall be performed. H.11.1.2 Science Verification Requirements H.11.1.2.1 The baseline instrumental performance and optical alignment and focus of the WFPC II shall be measured from an initial set of PSF measurements, photometric calibrations and internal calibrations (dark frames, bias frames, K-spot images, and internal flat fields). Subsequent to this initial set of measurements, all WFPC II calibrations will be performed as part of the Cycle 8/9 WFPC II calibration program. H.11.1.2.2 A second PSF measurement will be performed after the NCS achieves its normal operational state. H.11.2 H.11.2.1 COSTAR Verification Requirements After the successful installation of ACS and after re-lease, the COSTAR Deployable Optical Bench shall be retracted from the stow to launch position and then return COSTAR to Hold mode. H.11.3 ACS Verification Requirements H.11.3.1 H.11.3.1.1 Engineering Requirements ACS entry into each of four instrument states (Boot, Hold, Operate, Observe) shall be demonstrated. Operations shall be commanded via RIU commands transmitted over the Supervisory Bus. H.11.3.1.2 ACS entry into each of the defined detector states shall be demonstrated. Operations shall be commanded via RIU commands transmitted over the Supervisory Bus. H.11.3.1.3 ACS command and engineering data interface via the RIU and science data transmission via the Science Data Formatter (SDF) shall be verified by monitoring of normal configuration and science activities. H.11.3.1.4 The ability to load and dump on-board memory shall be demonstrated. H.11.3.1.5 The ability to read and write data from and to the science data buffer shall be demonstrated. H.11.3.1.6 The performance of the Cal/Coronagraph Door, M3 Fold Mechanism, IM1 and M1 Alignment and Focus Corrector Mechanisms, WFC/HRC Filter Wheels 1 and 2, SBC Filter Wheel, and WFC and HRC CCD shutters shall be verified. H.11.3.1.7 The functionality of the ACS Calibration Lamps shall be verified, either by the execution of engineering test(s) or as a result of detector performance testing. Operation of the deute-rium lamp shall be deferred for an initial outgassing period following release of the observatory, as defined in the CARD. H.11.3.1.8 Functional tests shall be executed for all three ACS detectors. Proper accumulation of signal over a specified time interval and data readout (including compressed data) shall be demonstrated. For the CCDs, readout of a single subarray and commandability of gain setting shall be demonstrated. H.11.3.1.9 The ability of the TECs to cool and stably control the CCDs shall be tested at a small number of temperature set points, in order to determine the coldest stable operating point, which is the final setting desired. that this point be at least as cold as -80C. The requirement is This test may dependent on the operation of the ASCS. H.11.3.1.10 ACS operations shall be managed to minimize risk of contamination of its optical surfaces by materials outgassed either internally or from other units installed during the SM as well as from the payload bay environment during servicing. The ACS Cal Door shall be used to provide ACS contamination protection during installation and while the OTA is viewing the bright earth for the duration of the SMOV program. A contamination moni-toring program shall be initiated as early as possible after the SM. H.11.3.1.11 High voltage operation of the ACS SBC MAMA detector shall be delayed for an initial outgassing period following re-lease of the observatory, as defined in the CARD. H.11.3.2 Target Acquisition Requirements H.11.3.2.1 The location of a reference ACS HRC camera aperture shall be determined with respect to the FGS reference frames to an accuracy of +/-1 arcsecond in V2-V3 coordinates and 10 arc minutes in aperture rotation angle. H.11.3.2.2 The relative positions of the ACS coronagraphic field masks determined during ground test shall be confirmed. H.11.3.2.3 The ability of the FSW to perform isolated point source acquisition onto the coronagraphic spots shall be demonstrated with the ACS HRC detector. Successful execution of these acquisitions will also demonstrate the ability of the FSW to cal-culate the centroid of target positions and to perform automated telescope pointing. H.11.3.3 Optical Alignment Requirements H.11.3.3.1 The encircled energy and image diameter vs. wave- length shall be measured over a grid of focus and tilt positions for both IM1 and M1 correctors. These measurements shall be used to set the nominal corrector positions. H.11.3.3.2 The camera mode image quality at the detectors over the full field shall be measured via broad and narrow band imaging of stars. The requirement for encircled energy in the WFC and HRC is 75% within a diameter of .25 arcseconds, through the F502N filter. The requirement for encircled energy in the SBC is 30% within a diameter of 0.10 arcseconds, for a star observed through the Lyman alpha filter. H.11.3.3.3 The internal stability of ACS from coronagraphic field stop to HRC detector shall be monitored. The image shifts seen shall be compared to the specified stability of 0.12 HRC pixels RMS over 1300 s and +/- 0.20 HRC pixels over a three hour period. H.11.3.3.4 The pointing and throughput stability of the OTA- ACS combination shall be measured over several orbits. The purpose of these measurements is twofold: 1. Confirm that the typical thermal environment after SM3 does not cause unacceptable image drifts; 2. Confirm that operation of the ASCS does not degrade the ACS image quality or pointing stability. H.11.3.3.5 The ACS Point Spread Function (PSF) in normal imaging and coronagraphic modes shall be measured. H.11.3.4 H.11.3.4.1 Calibration Requirements The plate scale, orientation and geometric distortion shall be measured for each of the ACS channels by imaging an astrometric field. Relative location of each aperture in the FGS frame shall also be determined with these measurements. H.11.3.4.2 Dark rate and read noise and CTE for each CCD detec- tor shall be measured, as well as dark rate for the SBC MAMA detector. One purpose of these measurements is to confirm that the operations of the STIS, the ASCS, and the NCS do not affect the noise properties of the detectors. The hot pixel creation rate shall be assessed and the efficacy of the hot annealing cycle shall be demonstrated. H.11.3.4.3 Instrument sensitivity vs. wavelength shall be measured for a subset of ACS modes. Sensitivity measurements shall be performed using astronomical standard stars. As part of this process, UV sensitivity measurements shall be obtained as early as possible, to enable early trending of UV sensitivity. H.11.3.4.4 The instrumental polarization as function of wavelength shall be measured for both WFC and HRC channels. H.11.3.4.5 The flat field uniformity per pixel and cosmetic defect fraction shall be measured for each of the 3 ACS detectors. The ability to determine the residual response variation using the ACS internal calibration sources shall be demonstrated. The difference between sky flats and internal flats and temporal stability of the flat field correction shall be assessed. H.11.4 NICMOS Verification Requirements H.11.4.1 H.11.4.1.1 Engineering Activation Requirements The ability to command NICMOS via the RIU, science data transmission via the SDF, and the ability of NICMOS to transition between its primary operational states (HOLD, BOOT, SAA-OPER, OPERATE, and OBSERVE) shall be verified. H.11.4.1.2 The integrity of the NICMOS FSW shall be demonstrated. H.11.4.1.3 Operation of the NICMOS mechanisms (PAM, FOM, and filter wheels) shall be tested. PAM motion between -9.5 and +4.0 mm of focus travel and +/- 10 steps in X and +/-12 steps in Y tilt shall be demonstrated. The ability to reposition the field off-set mirror (FOM) to within 10 milliarcseconds over the full operational range of travel shall be demonstrated. Internal lamp exposures shall be obtained at each filter wheel position. H.11.4.1.4 The operational temperature of the detectors at their baseplate shall be maintained to within 1 degree K of the nominal operational temperature as determined by models of NCS performance. Detector temperature stability shall be charac- terized over periods of 60s, 2000s, 24 hours, and 30 days. H.11.4.1.5 The thermal stability of the Vapor Cooled Shield (VCS)shall be determined to be within +/- 5 degrees K of the nominal operating temperature as determined by models of NCS performance. H.11.4.2 H.11.4.2.1 Target Acquisition Requirements The location of each NICMOS camera aperture shall be determined with respect to the FGS reference frames to an accu-racy of +/- 2 arcseconds in V2-V3 coordinates and 7 arc minutes in aperture rotation angle for Camera 2 and 1 degree for cameras 1 and 3. H.11.4.2.2 The performance of the coronagraph shall be demon- strated by an observation of an isolated point source following an onboard acquisition (Mode 2 acq) with an autonomous location of the coronagraphic hole. H.11.4.3 Optical Requirements H.11.4.3.1 The optical plate scales at each of the detector focal planes shall be measured, with a precision of 1/4 of a Camera 2 pixel(nominally 18.8 mas). H.11.4.3.2 Optical alignment shall be restored to the level of performance achieved during Cycle 7. PAM focus setting should be measured and trended to establish and maintain focus within +/1mm of nominal (best) focus for each Camera. After pupil adjustment, the combined effect of all NICMOS internal optics shall add a wavefront error, at the FPA, of no greater than lambda/20 (rms) at wavelength of 1.083 microns. The encircled energy within a 100 mas (200 mas for Camera 3) radius of an unresolved point-source shall be measured. H.11.4.3.3 H.11.4.4 H.11.4.4.1 Root mean square image motion shall be characterized. Calibration Requirements The ability to determine residual pixel-to-pixel variation using the internal flat-field calibration source shall be demonstrated. The stability of the instrumental flat-fields will be characterized over timescales of orbits, days, and one month. H.11.4.4.2 The ability to calibrate spectral throughput shall be demonstrated. The goal is the calibration of the absolute flux level to an accuracy of approximately 10%. Total instrument throughput shall be determined and compared to that measured previously during Cycle 7. H.11.4.4.3 The ability to do differential photometry with a residual measurement error no greater than 3%, and a temporal stability of 3% over a month shall be demonstrated. The consequences of detector temperature stability will be assessed. H.11.4.4.4 NICMOS geometric stability will be characterized as a function of orbital elements, vehicle orientation, and dewar temperatures by measuring the lateral motion of the image in the Camera 2 focal plane. H.11.4.4.5 Detector read noise and dark current shall be measured and compared to Cycle 7 values. mean read noise is <35 electrons. The expectation for The goal for mean dark current is TBD electrons/second. H.11.4.4.6 The cosmic ray background will be measured and confirmed to be comparable to the Cycle 7 levels. H.11.4.4.7 HST and NICMOS thermal emission will be charac- terized as a function of spectral element and time. H.11.4.4.8 The decay timescale for image persistence will be determined for both images from external sources of light and from cosmic rays. H.11.4.4.9 The photometric and wavelength solutions for the G096 and G141 grisms will be remeasured. H.11.4.4.10 During the initial cooldown phase, NICMOS detector dark current and flat-field performance in all three cameras shall be measured in 5-degree steps starting at 100 degrees K. H.11.4.5 NICMOS Cooling System (NCS) Engineering Verification Requirements H.11.4.5.1 Configure the NCS to re-cool NICMOS detectors and verify NICMOS background noise is reduced to scientifically useful levels. The goal during SMOV is to verify the capability to maintain the NICMOS Cooling Coil temperature less than or equal to 70 +/- 0.1K. H.11.4.5.2 Verify the capability of the NCS to achieve and maintain a NICMOS Cold Well temperature of 72 Kelvin. H.11.4.5.3 Verify the NCS capability to provide adequate level of thermal stability and repeatability for NICMOS science operations. H.11.4.6 H.11.4.6.1 NICMOS/NCS Calibration and Performance Requirements The temperatures of each NICMOS detector, along with its range of variation and the timescales for variation, shall be determined. H.11.4.6.2 The temperature of the VCS (and hence the filter elements), along with its range of variation and the timescales for variation, shall be determined. H.11.4.6.3 The absence of spurious signal or noise in the NICMOS detectors due to NCS operation shall be verified. H.11.4.6.4 If the NCS transitions into IDLE Mode, the magnitude and repeatability of changes in NICMOS focus shall be determined. H.11.4.6.5 If the NCS transitions into IDLE Mode, the repeatability and settling timescale for the VCS temperature shall be determined. H.11.4.6.6 If the NCS transitions into IDLE Mode, changes in detector pixel behavior and the positioning and quantity of detector focal plane contamination ("grot") shall be determined. H.11.5 STIS Verification Requirements H.11.5.1 H.11.5.1.1 Engineering Requirements STIS entry into each of four instrument states (Boot, Hold, Operate, Observe) shall be demonstrated. Operations shall be commanded via RIU commands transmitted over the Supervisory Bus. H.11.5.1.2 STIS command and engineering data interface via the RIU and science data transmission via the Science Data Formatter (SDF) shall be verified by monitoring of normal configuration and science activities. H.11.5.1.3 The performance of the Mode Select Mechanism, Slit Wheel, Calibration Insert Mechanism, Mode Isolation Shutter, Echelle Blocker, CCD Shutter and Focus Adjust and Corrector Alignment Mechanism shall be verified, as part of normal operations. H.11.5.1.4 Minifunctional tests shall be executed for all three STIS detectors. The high voltage for the STIS MAMA detectors will not be activated until the ambient pressure is below TBD. H.11.5.1.5 The ability of the TEC to cool and stably control the CCD shall be tested at a small number of temperature set points, in order to determine the coldest stable operating point, which is the final setting desired. The requirement is that this point be at least as cold as -80 degrees C. This test may be dependent on the operation of the ASCS and the NCS. H.11.5.1.6 Contamination plan: 1. The STIS shutter shall be used to provide STIS contamination protection in addition to the contamination management plan defined in H.11.16. 2. The STIS Deuterium and Krypton lamps will not be operated until TBD weeks after release. 3. STIS sensitivity will be monitored periodically. H.11.5.2 H.11.5.2.1 Target Acquisition Requirements The location of a reference STIS camera aperture shall be determined with respect to the FGS reference frames to an accuracy of 11 arcsecond in V2-V3 coordinates and 10 arc minutes in aperture rotation angle. H.11.5.3 H.11.5.3.1 Optical Alignment Requirements The slit plane encircled energy vs. wavelength and image diameter shall be measured for the nominal corrector focus and tilt positions. If the throughput is significantly lower than pre-SM3 measurements, further corrector alignment and testing will be performed. The requirements at center of field are 36% energy within the 0.1x0.09 slit at 145 nm and 48% energy within the 0.1x0.09 slit at 633 nm. This test is dependent on the setting of the HST secondary mirror position, which must be set to nominal focus prior to the throughput test. H.11.5.3.2 The nominal values for Slit Wheel positions, based on slit/aperture choice, and Mode Select Mechanism positions, based on detector/grating/wavelength (or order) choice, shall be verified. Determination of shifts of nominal positions shall result in modification of the on-board mechanism calibration tables. H.11.5.3.3 MSM and Slit wheel positions will be checked at a few settings at off-nominal cooler temperatures to check operations during planned cooler excursions. H.11.5.3.4 The slit-to-detector internal stability of STIS shall be monitored. The spectral shifts seen shall be compared to the specified stability of 0.2 low resolution MAMA pixels over a one hour period. The purpose of this measurement is twofold: 1. Confirm that the typical thermal environment after SM3 does change the requirements for frequency of wavelength calibration for typical astronomical observations. 2. Confirm that operation of the NCS and ASCS do not degrade the STIS spectral image quality. H.11.5.3.5 The pointing and throughput stability of the OTA- STIS combination shall be measured over several orbits. The purpose of this measurement is threefold: 1. Confirm that the typical thermal environment after SM3 does not cause unacceptable image drifts. 2. Confirm that operation of the NCS and ASCS do not degrade the STIS image quality or pointing stability. 3. Confirm that the STIK installation has not induced forces that are deforming the optical bench. H.11.5.4 Calibration Requirements H.11.5.4.1 Dark rate and read noise for each detector shall be measured at the nominal operating temperatures, and will be periodically monitored to track variations with time and temperature. The goals are: 1. To confirm that operation of ACS, the ASCS, and the NCS do not affect the noise properties of the detectors. 2. To calibrate NUVMAMA dark rate vs. temperature and time from SAA in the post-SM3 operating environment. H.11.5.4.2 Instrument sensitivity vs. science mode and wave- length, shall be measured for the low-resolution spectroscopic modes for contamination monitoring. Sensitivity measurements shall be performed using astronomical standard stars. Sensitivity shall be measured at different values of the MAMA temperatures. H.11.5.4.3 NUVMAMA dark current reduction afforded by the ASCS shall be demonstrated. H.11.6 Early Release Observations H.11.6.1 SMOV activities shall include early release observations with at least the WFPC2 science instrument. The resulting science data products shall be released into the public domain to demonstrate the improved HST capabilities. H.11.7 Optical Telescope Assembly/Fine Guidance Sensor Verification Requirements The following is a preliminary list of OTA/FGS verification requirements for the Third Servicing Mission SMOV. They these requirements have been based on the referenced documents. H.11.7.1 H.11.7.1.1 Optical Interfaces HST's secondary mirror shall only be moved to com- pensate for desorption in the graphite epoxy structure. H.11.7.2 FGS S-Curve Restoration Activities (applicable if an FGS is replaced). The FGS shall be peaked up by the vendor and then turned over to operations and science to optimize the location of the articulated FGS fold flat #3. H.11.7.2.1 The FGS vendor will be given an opportunity to peak up the S-Curves in the central and off-axis locations. Both the Central Position Modulation Index (CPMI)and the Off-Axis Modulation Index (OAMI) shall be determined in this operation for a fold flat #3 position which maximizes both values. The deter- mination of these values may be done using a mixture of both analysis and on-orbit test data. The precise star used for evaluating performance shall be determined by the agreement between the vendor and the HST operations. At any time, the government may elect to use the analysis in the incentive fee evaluation and may require no further fold flat #3 moves. H.11.7.2.2 The pupil centering with respect to the face of the Koester's prism shall be accomplished by articulating FGS fold flat #3 (FF3). The modulation of the X and Y S-curves shall be optimized at a particular field location that is chosen to produce an acceptable set of S-curves over the entire FGS FOV. Performance at the selected field location shall be deemed adequate if the S-curve modulation in each axis is within 10% of the maximum value achieved during the final laboratory optimization procedures. The wavelength characteristics of the S Curve at the relevant central location in the FOV will be baselined using F583W, PUPIL, and the red filter. H.11.7.2.3 A test to determine whether the optimal orientation of FF3 is affected by desorption shall be performed two to six months after the baseline alignment of FF3 is completed. It will consist of obtaining an S-curve near the FGS FOV location used for the baseline alignment. H.11.7.2.4 After the orientation of FF3 has been optimized the position of the Internal Test Source (ITS) shall be measured. This result together with a prediction of the Optical Control Subsystem (OCS) obscuration zone shall be used to update PDB cone 5, which describes the FOV avoidance zone about the OCS center where guide stars can neither be acquired nor moved. H.11.7.3 H.11.7.3.1 FGS Calibration Mini-OFAD/Plate Scale calibrations for operational use shall be executed in all three FGSs. Onboard flight software table updates and PDB updates incorporating the new calibrations shall be made. H.11.7.3.2 FGS-to-FGS alignment calibration shall be performed and resulting alignment matrices computed. Onboard tables and the PDB shall be updated with the new calibration parameters. H.11.7.3.3 A check on the stability of the Mini-OFAD and FGS- to-FGS Alignment parameters, and on the stability of the S- curve restoration, shall be made two to six months after the calibra-tions. ITS measurements shall be obtained to verify positional stability of the FF3. These data will be used to verify and change (if necessary) the operational K parameters for the new FGS. H.11.7.3.4 A PMT calibration for a replacement FGS shall be derived from brightness measurements of stars acquired while conducting other FGS and non-FGS SMOV activities. H.11.7.3.5 If an FGS is replaced, dark count data will have been obtained in all FGSs during the replacement FGS functional checkout. If no FGS is replaced, dark counts shall be acquired on a target of opportunity basis. H.11.7.3.6 The operational performance of the replacement FGS will be verified in an operational environment. Standard guide star acquisition and tracking of bright and faint guide stars will be exercised. The jitter and noise characteristics during slews and fine lock pointing will be compared to nominal tolerances. H.11.7.3.7 FGS pointing stability will be verified to be com- patible with ASCS/NCS operation. H.11.7.4 H.11.7.4.1 FGS Astrometry Science Re-Commissioning The decision to re-enable the astrometry FGS for science will be partly based on the repeatability and stability of the S Curve. Performance shall be deemed adequate if the S Curve exhibits small amplitude and morphology changes that are consistent with the temporal variations seen in time. S Curves over These data will be also be used to assess the operational performance of the FGS1R across the FOV and to determine if contingency FGS1R FF3 re-optimization is necessary to preserve operational integrity. H.11.7.4.2 The re-enabling of astrometry science will also depend on the repeatability of the optical field angle distortion calibration. An LTSTAB orbit will be obtained and compared to the pre-servicing mission standards. If the LTSTAB adjustments can remove all differences introduced by servicing mission activities, the integrity of the astrometer is established. H.11.7.4.3 Serendipitous photometric observations from the LTSTAB verification orbit will be used to verify the photometric stability of the astrometry FGS. H.11.8 Pointing Control Subsystem Verification Requirements H.11.8.1 The initial attitude shall be determined to an accuracy within .2 degrees using Fixed Head Star Tracker (FHST) data. H.11.8.2 The gyro drift rate bias shall be calibrated to within 0.05 arcseconds per second prior to the first guide star acquisi-tion. H.11.8.3 The FHST/FHST alignment matrices shall be computed, using FHST observations at the initial attitude, to an accuracy of 5 arcseconds (1s). The FHST/FHST alignment matrices shall be updated if the change in the pitch or yaw alignment exceeds 20 arcseconds. The alignment computations will be further refined during normal operations to achieve accuracy comparable to the pre-Servicing Mission level. H.11.8.4 If gyros are changed out, the gyro to FHST alignment matrices shall be updated to an accuracy that reduces the attitude error following a vehicle maneuver to less than one arcsecond per degree of slew. H.11.8.5 The PCS shall acquire guide stars in fine lock. H.11.8.6 The vehicle jitter during periods of fine lock shall be measured. H.11.8.7 Perform a post SM3 HST Modal Test to properly charac- terize the on-orbit system modes and jitter. H.11.9 HST 486 Verification Requirements H.11.9.1 HST486 Thermisters shall be configured for appropriate temperature monitoring. H.11.9.2 DMS (SSM486 flight software) shall be configured to provide nominal operation of the safemode tests and software safemodes. H.11.9.3 After transition to normal mode, HST 486 performance shall be verified by observing the following: 1. Vehicle slews 2. Science maneuvers 3. Solar Array slews 4. HGA slews and TDRSS track 5. FGS acquisitions 6. FGS diagnostics 7. Events Status Buffer management 8. Telemetry and recorder management 9. SPC processing 10. BMIC management 11. FGS observer performance 12. VT and/or KR software charge control 13. SPAR performance 14. Gyro bias estimation/extrapolation performance H.11.9.4 The SSM flight software shall maintain the position vectors for up to four TDRSS spacecraft, and calculate the following position and velocity vectors from a flight tested analytical model at a 1 Hz rate. 1. Solar 2. Lunar 3. Magnetic field H.11.10 Instrumentation & Communications Subsystem Verification Requirements No applicable requirements. H.11.11 H.11.11.1 SI C&DH Verification Requirements Verify that the NSSC-I interface with the HST486 shall support spacecraft operations and commanding of the post SM-3 complement of SIs. H.11.11.2 A NSSC-1 load supporting the post SM3 SI configura- tion shall be loaded during SMOV. The NSSC-1 load will be required to remove FOC memory for additional command storage. Load and verification activities shall include pre- and postinstallation dump of the NSSC-1 and regression testing of NSSC-1 functionality. H.11.12 Structures and Mechanisms Subsystem Verification No applicable requirements. H.11.13 Thermal Control Subsystem Verification Requirements H.11.13.1 All active thermally controlled SSM systems status shall be verified by analysis of neighboring telemetry parameters [i.e., SSM ES Bay 1: Computer baseplate heater, Bays 2 & 3: Battery heaters, Bay 4: Door heaters, Bay 5: Comm tray & Recorders (2) heaters, Bays 6 & 9: RWA heaters, Bays 7 & 8: Door heaters, ESTR-2 heater, Bay 10: SI C&DH Tray heaters, AS shelf: RSU(3) and FHST(3) heaters, External: CSS(5), AD drive/latch heaters, Latch/ Drive heaters, MSS heaters, Retr/Depl heaters, and SADM heaters]. H.11.14 Aft Shroud Cooling System (ASCS) Engineering Verification Requirements H.11.14.1 Verify the heat rejection capability of the ASCS to maintain ACS and STIS subsystems at temperatures supporting achievement of each instrument’s science performance for Cycles 8 and 9 operations. The goal during SMOV is to verify the capabi-lity to maintain the following interface plate temperatures: 1. Less than or equal -2 degrees C for ACS 2. Less than or equal 4 degrees C for STIS 3. Less than or equal -5 degrees C for STIS (dark) 4. Greater than or equal 25 degrees C for STIS (boil) H.11.14.2 Verify the ASCS capability to provide adequate level of thermal stability and repeatability for ACS and STIS science operations. H.11.15 Solar Array III (SAIII) Verification Requirements H.11.15.1 SAIII drive system performance shall be characterized during the SMOV period and the following requirements verified. 1. the sensed position is within +/- 3.5 degrees of the commanded position when operating within the range 0 to 130 degrees, 2. the sensed position is within +/- 5.0 degrees of the commanded position when operating within the remainder of the range, 3. the maximum command profile error shall be less than the safemode test threshold. H.11.15.2 SAIII power generation performance shall be assessed and compared to Beginning of Life (BOL) predictions that account for expected degradation. To the extent possible, measurements shall be recorded when HST is at orbit noon, when the Sun vector is within +/-10 deg of the -V1 axis, when the SA/Sun incidence angle is less than 5 deg, and when all the CCC K-relays are closed. H.11.16 General Verification Requirements H.11.16.1 The HST optics shall be protected from contaminants being polymerized by the solar UV light reflected by the earth in the early stage of outgassing following SM3. The following con-tamination management plan shall be carried out to provide the protection described below. 1. Avoid pointing the +V1 axis within 15 degrees of bright earth limb from the time HST is released by the Orbiter through release +3 days. 2. Avoid pointing the +V1 axis within two degrees of the bright earth Limb from release +3 days through release +12 days. 3. From release +12 days through release +42 days the cumulative exposure of the focal plane to the earth (+V1 axis within two degrees of the bright-earth surface) is not to exceed the total bright earth exposure (approximately six days) experienced by HST during the first six weeks following the Second Servicing Mission. H.11.16.2 Parallel operation of NICMOS, STIS, and WFPC2, and ACS shall be demonstrated, with an allowance, if necessary, of several weeks of response time between the first parallel test and subsequent operations requiring parallel capabilities. H.11.17 H.11.17.1 Electrical Power Subsystem Verification Requirements With the Voltage Improvement Kit (VIK) installed, the battery charge control performance shall be characterized by recording a statistically significant data set of individual battery charge-on and charge-off cutoff voltages. This data shall be recorded over the nominal temperature range following SM3. The average charge-on and charge-off voltages shall be compared to the expected values based on VIK specifications and past performance of the CCC(s). H.11.17.2 With the K10 bypass relay closed, the SPA Recovery (SPAR)modifications (relays in the SA3 D-Boxes and associated flight software)shall control charging of Battery 1 and maintain thermal stability when operating in conjunction with both hardware and software charge control modes. H.11.17.3 A software charge control mode, either Voltage/ Temperature SoftWare Charge Control (VTSWCC) or K-Relay SoftWare Charge Control (KRSWCC) shall perform charge control and maintain battery thermal stability while operating in conjunction with the SPAR modifications. This shall be verified for periods of high suntime, low solar array incidence angles, and at a minimum HST load power for the expected load range following SM3. H.11.17.4 A minimum of three batteries shall be capacity tested at one-month intervals following SM3.