Exhibit R-2, RDT&E Budget Item Justification May 2009 UNCLASSIFIED

advertisement
UNCLASSIFIED
PE NUMBER: 0401138F
PE TITLE: Joint Cargo Aircraft
DATE
Exhibit R-2, RDT&E Budget Item Justification
May 2009
BUDGET ACTIVITY
PE NUMBER AND TITLE
05 System Development and Demonstration (SDD)
0401138F Joint Cargo Aircraft
Cost ($ in Millions)
5259
Total Program Element (PE) Cost
Joint Cargo Aircraft (JCA)
FY 2008
Actual
20.283
20.283
FY 2009
Estimate
16.732
16.732
FY 2010
Estimate
9.353
9.353
FY 2011
Estimate
0.000
0.000
FY 2012
Estimate
0.000
0.000
FY 2013
Estimate
0.000
0.000
FY 2014
Estimate
0.000
0.000
FY 2015
Estimate
0.000
0.000
Cost to
Complete
0.000
0.000
Total
111.901
111.901
(U) A. Mission Description and Budget Item Justification
The Joint Cargo Aircraft, now designated the C-27J, program and the direct support airlift mission it supports has been transferred to the Air Force. The 13 aircraft
procured by the Army from FY07-09 are being transferred to the Air Force.
The C-27J program began as an Army-led, joint program to acquire a commercial derivative aircraft to support the Time Sensitive/Mission Critical resupply of Army
ground forces. A joint Army/Air Force Source Selection Team chose the C-27J in a full and open competition and awarded a firm-fixed price contract to L3
Communications on 13 June 2007.
FY10 Budget Justification: Completes Product Qualification Testing (PQT), Live Fire Test & Evaluation (LFT&E), Multi-Service Operational Test & Evaluation
(MOT&E), training and sustainment business case analyses (BCA), Depot Source of Repair, Core Logistics Analysis, and 50/50 Analysis. Funding also supports any
associated program management costs.
C-27J is in Budget Activity 05, System Development & Demonstration, because it is a new system that has not been fielded yet.
(U)
(U)
(U)
(U)
(U)
(U)
B. Program Change Summary ($ in Millions)
FY 2008
FY 2009
Previous President's Budget
42.368
26.777
Current PBR/President's Budget
20.283
16.732
Total Adjustments
-22.085
-10.045
Congressional Program Reductions
-20.782
Congressional Rescissions
-0.131
Congressional Increases
Reprogrammings
-1.758
-10.045
SBIR/STTR Transfer
0.586
Significant Program Changes:
FY08 - Congress appropriated $20.283M; ~50% of the President's Budget Request in FY08
FY09 - Congress appropriated $16.732M which represents a $10M reduction of the President's Budget Request in FY09
FY10 - Funding re-aligned to better support sustainment and training composition studies and Joint Live Fire and Operational Test programs
R-1 Line Item No. 97
Page-1 of 6
653
UNCLASSIFIED
FY 2010
11.391
9.353
Exhibit R-2 (PE 0401138F)
UNCLASSIFIED
DATE
Exhibit R-2a, RDT&E Project Justification
May 2009
BUDGET ACTIVITY
PE NUMBER AND TITLE
PROJECT NUMBER AND TITLE
05 System Development and Demonstration (SDD)
0401138F Joint Cargo Aircraft
5259 Joint Cargo Aircraft (JCA)
Cost ($ in Millions)
5259
Joint Cargo Aircraft (JCA)
Quantity of RDT&E Articles
FY 2008
Actual
20.283
0
FY 2009
Estimate
16.732
0
FY 2010
Estimate
9.353
0
FY 2011
Estimate
0.000
0
FY 2012
Estimate
0.000
0
FY 2013
Estimate
0.000
0
FY 2014
Estimate
0.000
0
FY 2015
Estimate
0.000
0
Cost to
Complete
0.000
Total
111.901
(U) A. Mission Description and Budget Item Justification
The Joint Cargo Aircraft, now designated the C-27J, program and the direct support airlift mission it supports has been transferred to the Air Force. The 13 aircraft
procured by the Army from FY07-09 are being transferred to the Air Force.
The C-27J program began as an Army-led, joint program to acquire a commercial derivative aircraft to support the Time Sensitive/Mission Critical resupply of Army
ground forces. A joint Army/Air Force Source Selection Team chose the C-27J in a full and open competition and awarded a firm-fixed price contract to L3
Communications on 13 June 2007.
FY10 Budget Justification: Completes Product Qualification Testing (PQT), Live Fire Test & Evaluation (LFT&E), Multi-Service Operational Test & Evaluation
(MOT&E), training and sustainment business case analyses (BCA), Depot Source of Repair, Core Logistics Analysis, and 50/50 Analysis. Funding also supports any
associated program management costs.
C-27J is in Budget Activity 05, System Development & Demonstration, because it is a new system that has not been fielded yet.
(U)
(U)
(U)
(U)
(U)
(U)
(U)
FY 2008
4.285
1.495
7.987
1.930
4.586
20.283
B. Accomplishments/Planned Program ($ in Millions)
Multi-Service Test (PQT, LFT&E and MOT&E) & Airworthiness Certification
Mission Planning System Development
Sustainment, Training, and Technical Studies
Program Office Mission Support
Internal Air Force Reprogramming Action
Total Cost
(U) C. Other Program Funding Summary ($ in Millions)
FY 2008
FY 2009
Actual
Estimate
(U) Air Force Aircraft
Procurement
(U) Army RDT&E
6.495
3.017
(U) Army Aircraft Procurement
155.982
263.381
FY 2010
Estimate
FY 2011
Estimate
FY 2012
Estimate
319.050
FY 2013
Estimate
FY 2014
Estimate
FY 2015
Estimate
FY 2009
10.045
FY 2010
6.840
4.362
2.325
1.380
1.133
16.732
9.353
Cost to
Total Cost
Complete
0.000
319.050
(U) D. Acquisition Strategy
- Multi-Service Test Program: Airworthiness, Product Qualification Testing (PQT), Live Fire Test and Evaluation (LFT&E) and Multi-Service Operational Test &
Project 5259
R-1 Line Item No. 97
Page-2 of 6
654
UNCLASSIFIED
Exhibit R-2a (PE 0401138F)
UNCLASSIFIED
Exhibit R-2a, RDT&E Project Justification
DATE
May 2009
BUDGET ACTIVITY
PE NUMBER AND TITLE
PROJECT NUMBER AND TITLE
05 System Development and Demonstration (SDD)
0401138F Joint Cargo Aircraft
5259 Joint Cargo Aircraft (JCA)
Evaluation (MOT&E). The program provides funds to the FAA and other government offices/agencies supporting aircraft airworthiness certification, procures
hardware to support the LFT&E and provides funds to the Army Test & Evaluation Center, the Air Force Operational Test & Evaluation Center, and other test
organizations to conduct PQT, LFT&E and OT&E. The program will exercise existing prime contract options to provide needed data and other support required to
assess any retrofits needed based on test results.
- Sustainment and Training Studies: The program has established an independent contract to conduct the Sustainment and Training business case analyses, Depot
Source of Repair, and Core Logistics Analysis.
- Training Systems Requirements Analysis (TSRA): The program has exercised existing options within the prime contract to conduct TSRAs to help determine future
training system requirements.
Project 5259
R-1 Line Item No. 97
Page-3 of 6
655
UNCLASSIFIED
Exhibit R-2a (PE 0401138F)
UNCLASSIFIED
DATE
Exhibit R-3, RDT&E Project Cost Analysis
May 2009
BUDGET ACTIVITY
PE NUMBER AND TITLE
PROJECT NUMBER AND TITLE
05 System Development and Demonstration (SDD)
0401138F Joint Cargo Aircraft
5259 Joint Cargo Aircraft (JCA)
(U) Cost Categories
(Tailor to WBS, or System/Item Requirements)
($ in Millions)
(U) Product Development
Mission Planning System Development
Subtotal Product Development
Remarks:
(U) Support
Sustainment, Training and Technical Studies
Subtotal Support
Remarks:
(U) Test & Evaluation
Multi-Service Test Program
C FFP
C FFP
Performing
Activity &
Location
Total
Prior to FY
2008
Cost
L3 Comm
L3 Comm
(Greenville
TX), Belzon
(Huntsville
AL)
FY 2008
Cost
FY 2008
Award
Date
MIPR
N/A
Various
Locations
N/A
FY 2009
Cost
FY 2009
Award
Date
FY 2010
Cost
0.000
1.495
1.495
0.000
0.000
3.770
7.987
4.362
1.380
4.362
1.380
3.770
7.987
FY08: Acquire Data Reports from aircraft contractor in support of Training and Support BCAs
Subtotal Test & Evaluation
Remarks:
(U) Management
Program Office Mission Support
Internal AF Reprogramming Action
Subtotal Management
Remarks:
(U) Total Cost
Project 5259
Contract
Method &
Type
FY 2010
Award
Date
Cost to
Complete
Total Cost Target Value
of Contract
1.495
1.495
5.994
5.994
17.499
21.473
0.000
17.499
21.473
0.000
24.496
0.000
0.000
27.467
0.000
3.326
4.285
10.045
6.840
3.326
4.285
10.045
6.840
2.085
2.325
1.133
2.085
1.930
4.586
6.516
2.325
1.133
0.000
7.473
4.586
12.059
9.181
20.283
16.732
9.353
0.000
55.549
R-1 Line Item No. 97
Page-4 of 6
656
UNCLASSIFIED
24.496
Exhibit R-3 (PE 0401138F)
UNCLASSIFIED
Exhibit R-4, RDT&E Schedule Profile
DATE
May 2009
BUDGET ACTIVITY
PE NUMBER AND TITLE
PROJECT NUMBER AND TITLE
05 System Development and Demonstration (SDD)
0401138F Joint Cargo Aircraft
5259 Joint Cargo Aircraft (JCA)
Project 5259
R-1 Line Item No. 97
Page-5 of 6
657
UNCLASSIFIED
Exhibit R-4 (PE 0401138F)
UNCLASSIFIED
DATE
Exhibit R-4a, RDT&E Schedule Detail
May 2009
BUDGET ACTIVITY
PE NUMBER AND TITLE
PROJECT NUMBER AND TITLE
05 System Development and Demonstration (SDD)
0401138F Joint Cargo Aircraft
5259 Joint Cargo Aircraft (JCA)
(U)
(U)
(U)
(U)
Schedule Profile
Mission Planning System Development
Test Program: Airworthiness, LFT&E and OT&E
DSOR/TSRA/BCA
Project 5259
FY 2008
2-4Q
2-4Q
1-4Q
R-1 Line Item No. 97
Page-6 of 6
658
UNCLASSIFIED
FY 2009
1Q
1-4Q
1-4Q
FY 2010
1-3Q
1-3Q
Exhibit R-4a (PE 0401138F)