CONTRACT DOCUMENTS AND SPECIFICATIONS FOR WERNER ELEMENTARY SCHOOL PARKING LOT AND PLAY AREA SITE IMPROVEMENT PROJECT FORT COLLINS, COLORADO Poudre School District R-1 February 2013 OWNER: POUDRE SCHOOL DISTRICT R-1 2407 LAPORTE AVENUE FORT COLLINS, COLORADO 80521 (970) 490-3600 JERRY GARRETSON PROJECT MANAGER ENGINEER: ANDERSON CONSULTING ENGINEERS, INC. 375 E. HORSETOOTH ROAD, BUILDING 5 FORT COLLINS, COLORADO 80525 (970) 226-0120 GREG KOCH, P.E. PRINCIPAL ENGINEER ACE PROJECT NO. COPR144 TABLE OF CONTENTS SECTION BID INFORMATION 00100 00300 00310 00320 00400 00420 00430 INSTRUCTIONS TO BIDDERS BID FORMS BID PROPOSAL FORM QUANTITY SCHEDULE SUPPLEMENTS TO BID FORMS STATEMENT OF BIDDER'S QUALIFICATIONS SCHEDULE OF SUBCONTRACTORS CONTRACT DOCUMENTS 00500 00510 00520 00530 AGREEMENT FORMS NOTICE OF AWARD AGREEMENT NOTICE TO PROCEED 00600 00610 00615 00630 00635 00640 00650 00651 00660 00670 BONDS AND CERTIFICATES PERFORMANCE BOND PAYMENT BOND CERTIFICATE OF INSURANCE CERTIFICATE OF SUBSTANTIAL COMPLETION CERTIFICATE OF FINAL ACCEPTANCE LIEN WAIVER RELEASE (CONTRACTOR) LIEN WAIVER RELEASE (SUBCONTRACTOR) CONSENT OF SURETY APPLICATION FOR EXEMPTION CERTIFICATE CONDITIONS OF THE CONTRACT 00700 00800 00900 00950 00960 GENERAL CONDITIONS SUPPLEMENTARY CONDITIONS ADDENDA, MODIFICATIONS, AND PAYMENT CONTRACT CHANGE ORDER APPLICATION FOR PAYMENT DIVISION 1 - GENERAL REQUIREMENTS 01110 01140 01180 01270 01310 01320 SUMMARY OF WORK CONTRACTOR’S USE OF PREMISES UTILITY SOURCES MEASUREMENT AND PAYMENT PROJECT MEETINGS CONSTRUCTION SCHEDULES 01330 01425 01450 01555 01635 01650 01710 01720 01745 01780 SUBMITTALS STANDARD REFRENCES MATERIALS TESTING TRAFFIC REGULATION SUBSTITUTIONS AND PRODUCT OPTIONS MATERIAL DELIVERY, STORAGE, AND HANDLING SITE CONDITIONS FIELD ENGINEERING AND SURVEYING ENVIRONMENTAL CONTROLS CONTRACT CLOSEOUT DIVISION 2 - SITE WORK 02220 02230 02315 02340 02360 02710 02740 02770 APPENDIX A REMOVAL OF STRUCTURES AND OBSTRUCTIONS CLEARING AND GRUBBING EXCAVATION AND EMBANKMENT FLY ASH STABILIZATION EROSION AND SEDIMENT CONTROL AGGREGATE BASE COURSE ASPHALT PAVEMENT SIDEWALK, CURB AND GUTTER, AND MISCELLANEOUS CONCRETE “SUBSURFACE EXPLORATION REPORT, PROPOSED PAVEMENT RECONSTRUCTION WERNER ELEMENTARY SCHOOL”, EARTH ENGINEERING CONSULTANTS SECTION 00100 INSTRUCTIONS TO BIDDERS SECTION 00100 INSTRUCTIONS TO BIDDERS 1.0 DEFINED TERMS. Terms used in these Instructions to Bidders, which are defined in the Standard General Conditions of the Construction Contract (No. 1910-8, 1990 ed. with City of Fort Collins Modifications Rev. 9.94), have the meanings assigned to them in the General Conditions. The term "Bidder" means one who submits a Bid to OWNER, as distinct from a sub-bidder, who submits a Bid to Bidder. The terms "Successful Bidder" means the lowest, qualified, responsible and responsive Bidder to whom OWNER (on basis of OWNER's evaluation as hereinafter provided) makes an award. The term "Bidding Documents" includes the Advertisement or Invitation to Bid, Instructions to Bidders, the Bid Form, and the proposed Contract Documents (including all Addenda issued prior to receipt of Bids). 2.0 COPIES OF BIDDING DOCUMENTS. 2.1. Complete sets of Bidding Documents may be obtained as stated in the Invitation to Bid. No partial sets will be issued. The Bidding Documents may be examined at the locations identified in the Invitation to Bid. 2.2. Complete sets of Bidding Documents shall be used in preparing Bids; neither OWNER nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents. 2.3. The submitted Bid proposal shall include Sections 00310, 00320, 00420, and 00430 fully executed. 2.4. OWNER and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use. 3.0 QUALIFICATION OF BIDDERS. 3.1 To demonstrate qualifications to perform the Work, each Bidder must submit at the time of the Bid opening, a written statement of qualifications including financial data, a summary of previous experience, previous commitments and evidence of authority to conduct business in the jurisdiction where the Project is located. Each Bid must contain evidence of Bidder's qualification to do business in the state where the Project is located or covenant to obtain such qualification prior to award of the contract. The Statement of Qualifications shall be prepared on the form provided in Section 00420. 3.2. In accordance with Section 8-159 of the Code of the City of Fort Collins in determining whether a bidder is responsible, the following shall be considered: (1) The ability, capacity and skill of the bidder to perform the contract or provide the services required, (2) whether the bidder can perform the contract or provide the service promptly and within the time specified without delay or interference, (3) the character, integrity, reputation, judgment, experience and efficiency of the bidder, (4) the quality of the bidder's performance of Section 00100 Page 2 previous contracts or services, (5) the previous and existing compliance by the bidder with laws and ordinances relating to the contract or service, (6) the sufficiency of the financial resources and ability of the bidder to perform the contract or provide the service, (7) the quality, availability and adaptability of the materials and services to the particular use required, (8) the ability of the bidder to provide future maintenance and service for the use of the subject of the contract, and (9) any other circumstances which will affect the bidder's performance of the contract. 3.3. Each Bidder may be required to show that he has handled former Work so that no just claims are pending against such Work. No Bid will be accepted from a Bidder who is engaged on any other Work which would impair his ability to perform or finance this Work. 3.4. No Bidder shall be in default on the performance of any other contract with Poudre School District or in the payment of any taxes, licenses or other monies due to Poudre School District. 4.0 EXAMINATION OF CONTRACT DOCUMENTS AND SITE. 4.1. It is the responsibility of each Bidder, before submitting a Bid, to (a) examine the Contract Documents thoroughly, (b) visit the site to familiarize himself with local conditions that may in any manner affect cost, progress or performance of the Work, (c) familiarize himself with federal, state and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the Work, (d) study and carefully correlate Bidder's observations with the Contract Documents, and (e) notify Engineer of all conflicts, errors or discrepancies in the Contract Documents. 4.2. Reference is made to the Supplementary Conditions for identification of: Subsurface and Physical Conditions SC-4.2. 4.3. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Contract Documents and such means, methods, techniques, sequences or procedures of construction as may be indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. 5.0 INTERPRETATIONS AND ADDENDA. 5.1. All questions about the meaning or intent of the Bidding Documents are to be submitted in writing to the Engineer and the OWNER. Interpretation or clarifications considered necessary in response to such questions will be issued only by Addenda. Questions received less than seven days prior to the date for opening of the Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. 5.2. All questions concerning the scope of this project should be directed to the Engineer. Questions regarding submittal of bids should be directed to PSD, Materials Management Department. Section 00100 Page 3 5.3. Addenda may also be issued to modify the Bidding Documents as deemed advisable by OWNER or Engineer. 5.4. Addenda will be mailed or delivered to all parties recorded by the OWNER as having received the Bidding documents. 6.0 BID SECURITY. 6.1. Each Bid must be accompanied by Bid Security made payable to OWNER in the amount stated in the Invitation to Bid. The required security must be in the form of a certified or bank cashier's check payable to OWNER or a Bid Bond on the form enclosed herewith. The Bid Bond must be executed by a surety meeting the requirements of the General Conditions for surety bonds. 6.2. The Bid Security of the successful Bidder will be retained until such Bidder has executed the Agreement and furnished the required contract security, whereupon Bid Security will be returned. If the successful Bidder fails to execute and deliver the Agreement and furnish the required contract security within 15 days of the Notice of Award, OWNER may annul the Notice of Award and the Bid Security of that Bidder will be forfeited. The Bid Security of other Bidders whom OWNER believes to have reasonable chance receiving the award may be retained by OWNER until the earlier of the seventh day after the effective date of the Agreement or the thirty-first day after the Bid Opening, whereupon Bid Security furnished by such Bidders will be returned. Bid Security with Bids which are not competitive will be returned within seven days after the Bid opening. 7.0 CONTRACT TIME. The number of days within which, or the date by which the Work is to be substantially complete and also completed and ready for Final Payment (the Contract Times) are set forth in the Agreement. 8.0 LIQUIDATED DAMAGES. Provisions for liquidated damages are set forth in the Agreement. 9.0 SUBSTITUTE ("OR EQUAL") MATERIAL AND EQUIPMENT. The Contract, if awarded, will be on the basis of material and equipment described on the Drawings or specified in the Specifications without consideration of possible substitute or "or equal" items. Whenever it is indicated on the Drawings or specified in the Specifications that a substitute or "or equal" item of material or equipment may be furnished or used by CONTRACTOR if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the "effective date of the Agreement". The procedure for submittal of any such application by CONTRACTOR and consideration by Engineer is set forth in the General Conditions which may be supplemented in the General Requirements. 10.0 SUBCONTRACTORS, SUPPLIERS AND OTHERS. 10.1. Each Bidder shall submit at the Bid opening to OWNER a list of principal subcontractors he proposes to use in the Work. Refer to Section 00430 contained within these Documents. Section 00100 Page 4 10.2. If OWNER or Engineer after due investigation has reasonable objection to any proposed Subcontractor, either may, before the Notice of Award is given, request the apparent successful Bidder to submit an acceptable substitute without an increase in Bid price. If the apparent successful Bidder declines to make any substitution, OWNER may award the contract to the next lowest responsive and responsible Bidder that proposes to use acceptable subcontractors. Subcontractors, suppliers, other persons or organization listed and to whom OWNER or Engineer does not make written objection prior to the giving of the Notice of Award will be deemed acceptable to OWNER and ENGINEER subject to revocation of such acceptance after the effective date of the Agreement as provided in the General Conditions. 10.3. CONTRACTOR shall not be required to employ any subcontractor, supplier or other persons or organizations against whom he has reasonable objection. The use of subcontractors listed by the Bidder and accepted by OWNER prior to the Notice of Award will be required in the performance of the Work. 11.0 BID FORMS 11.1. Copies of the Bid Forms are bound in the Contract Documents which may be retained by the Bidder. Separate unbound copies are enclosed for submission with the Bid. 11.2. Bid Forms must be complete in ink or typed. All lump sum prices on the form must be stated in words and numerals; in case of conflict, words will take precedence. Unit prices shall govern over extensions of sums. 11.3. Bids by corporations must be executed in the corporate name by the president or a vice-president (or other appropriate officer accompanied by evidence of authority to sign) and the corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown below the corporate name. 11.4. Bids by partnerships must be executed in the partnership name and signed by a partner, his title must appear under his signature and the official address of the partnership must be shown below the signature. 11.5. Bids by joint venture shall be signed by each participant in the joint venture or by an authorized agent of each participant. The full name of each person or company interested in the Bid shall be listed on the Bid Form. 11.6. The Bid shall contain an acknowledgment of receipt of all Addenda (the numbers of which must be filled in on the Bid Form). 11.7. No alterations in Bids, or in the printed forms therefore, by erasures, interpolations, or otherwise will be acceptable unless each such alteration is signed or initialed by the Bidder; if initialed, OWNER may require the Bidder to identify any alteration so initialed. 11.8. The address and telephone number for communications regarding the Bid shall be shown. Section 00100 Page 5 12.0 BID PRICING. Bids must be priced as set forth in the Bid Proposal Form or Forms. 13.0 SUBMISSION OF BIDS. 13.1. Bids shall be submitted at the time and place indicated in the Invitation to Bid and shall be enclosed in an opaque sealed envelope marked with the Project title, Bid No., and name and address of the Bidder and accompanied by the Bid Proposal Form, Schedule of Quantities, Statement of Bidders Qualifications, and Schedule of Subcontractors as required in Section 00430. If the Bid is sent through the mail or other delivery system, the sealed envelope shall be enclosed in a separate envelope with the notation "BID ENCLOSED" on the face of it. 13.2. Bids shall be deposited at the designated location prior to the time and date for receipt of Bids indicated in the Invitation to Bid, or any extension thereof made by addendum. Bids received after the time and date for receipt of Bids will be returned unopened. Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids. 13.3. Oral, telephonic, telegraphic, or facsimile Bids are invalid and will not receive consideration. 13.4. No Bidder may submit more than one Bid. Multiple Bids under different names will not be accepted from one firm or association. 14.0 MODIFICATION AND WITHDRAWAL OF BIDS. 14.1. Bids may be modified or withdrawn by an appropriate document duly executed (in a manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids. 14.2. Bids may also be modified or withdrawn in person by the Bidder or an authorized representative provided he can prove his identity and authority at any time prior to the opening of Bids. 14.3. Withdrawn Bids may be resubmitted up to the time designated for the receipt of Bids provided that they are then fully in conformance with these Instructions to Bidders. 15.0 OPENINGS OF BIDS. Bids will be opened and (unless obviously non-responsive) read aloud publicly as indicated in the Invitation to Bid. An abstract of the amounts of the Base Bids and major alternates (if any) will be made available after the opening of Bids. 16.0 BIDS TO REMAIN OPEN SUBJECT TO ACCEPTANCE. All Bids shall remain open for forty-five (45) days after the day of the Bid Opening, but OWNER may, in his sole discretion, release any Bid and return the Bid Security prior to that date. Section 00100 Page 6 17.0 AWARD OF CONTRACT. 17.1. OWNER reserves the right to reject any and all Bids, to waive any and all informalities not involving price, time or changes in the Work, to negotiate contract terms with the Successful Bidder, and the right to disregard all nonconforming, nonresponsive, unbalanced or conditional Bids. Also, OWNER reserves the right to reject the Bid of any Bidder if OWNER believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by OWNER. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. 17.2. In evaluating Bids, OWNER will consider the qualifications of the Bidders, whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Forms or prior to the Notice of Award. 17.3. OWNER may consider the qualification and experience of Subcontractors, Suppliers, and other persons and organizations proposed for those portions of the Work as to which the identity of Subcontractors, Suppliers, and other persons and organizations is submitted as requested by OWNER. OWNER also may consider the operating costs, maintenance requirements, performance data and guarantees of major items of materials and equipment proposed for incorporation in the Work when such data is required to be submitted prior to the Notice of Award. 17.4. OWNER may conduct such investigations as OWNER deems necessary to assist in the evaluation of any Bid and to establish the responsibility, qualifications and financial ability of the Bidder's proposed Subcontractors, Suppliers and other persons and organizations to do the Work in accordance with the Contract Documents to OWNER's satisfaction within the prescribed time. 17.5. If the Contract is to be awarded, it will be awarded to the lowest responsive and responsible Bidder whose evaluation by OWNER indicates to OWNER that the award will be in the best interest of the OWNER. Award shall be made on the evaluated lowest base bid excluding alternates. The basis for award shall be the lowest Bid total for the Bid Proposal or, in the case of more than one proposal, for sum of all proposals. Only one contract will be awarded. 17.6. If the Contract is to be awarded, OWNER will give the Successful Bidder a Notice of Award within forty-five (45) days after the date of the Bid opening. 18.0 CONTRACT SECURITY. The General Conditions and the Supplementary Conditions set forth OWNER's requirements as to performance and other Bonds. When the Successful Bidder delivers the executed Agreement to the OWNER, it shall be accompanied by the required Contract Security. 19.0 SIGNING OF AGREEMENT. When OWNER gives a Notice of Award to the Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Agreement with all other written Section 00100 Page 7 Contract Documents attached. Within fifteen (15) days thereafter, CONTRACTOR shall sign and deliver the required number of counterparts of the Agreement and attached documents to OWNER with the required Bonds. Within ten (10) days thereafter, OWNER shall deliver one fully signed counterpart to CONTRACTOR. Each counterpart is to be accompanied by a complete set of the Drawings with appropriate identification. 20.0 TAXES. OWNER is exempt from Colorado State Sales and Use Taxes on materials and equipment to be incorporated in the Work. Said taxes shall not be included in the Contract Price. Reference is made to the General and Supplementary Conditions. 21.0 RETAINAGE. Provisions concerning retainage are set forth in the Agreement. 22.0 PURCHASING RESTRICTIONS. Purchasing restrictions: The Bidder's authorized signature of this Bid assures the Bidder's compliance with the PSD’s purchasing restrictions. A copy of the resolutions are available for review in the Materials Management Department. A. 23.0 Cement Restrictions: City of Fort Collins Resolution 91-121 requires that suppliers and producers of cement or products containing cement to certify that the cement was not made in cement kilns that burn hazardous waste as a fuel. COLLUSIVE OR SHAM BIDS. Any Bid deemed by PSD in its sole discretion to be a collusive or sham Bid will be rejected and reported to authorities as such. Your authorized signature of this Bid assures that such Bid is genuine and is not a collusive or sham Bid. 24.0 BID RESULTS. For information regarding results for individual Bids send a self-addressed, self-stamped envelope and a Bid tally will be mailed to you. Bid results will be posted in the Purchasing office seven (7) days after the Bid Opening. END OF SECTION Section 00100 Page 8 SECTION 00300 BID FORMS 00310 Bid Proposal Form 00320 Quantity Schedule SECTION 00310 BID PROPOSAL FORM POUDRE SCHOOL DISTRICT BID PROPOSAL FORM TO: Board of Education Poudre School District c/o Planning, Design & Construction 2445 LaPorte Avenue Fort Collins, CO 80521 FROM: PROJECT IDENTIFICATION: Werner Elementary School Parking Lot and Play Area Site Improvement Project ACKNOWLEDGMENTS: The undersigned Bidder acknowledges examination of the following: a) Contract Documents • Drawings dated February 2013 • Contract Documents and Specifications dated February 2013 • Schedule restrictions outlined in the Instructions to Bidders, Agreement and General Conditions b) Project Sites/Existing Conditions c) Receipt of Addenda Numbers: # # # , dated , dated , dated AGREEMENTS: The undersigned Bidder agrees to the following: a) b) c) d) e) f) g) h) To hold bid open for 45 calendar days from date of Bid Opening. To enter into and execute the Construction Agreement within fifteen (15) calendar days of award, including identified Bonds of Insurance. To accomplish the Work in accordance with the Contract Documents. Poudre School District reserves the right to reject any or all bids and to waive informalities. Poudre School District reserves the right to award separate or single contracts. Poudre School District reserves the right to award the contract on the basis of either cost or schedule. The Contractor agrees to pay the Poudre School District Liquidated Damages according to the terms, amount(s) and date(s) defined in the Instructions to Bidders, Agreement and General Conditions. To reinstate or omit Alternates at the amounts submitted herein for sixty days after Contract Date. TOTAL BASE BID PRICE: Werner Elementary School Phase #1: Dollars ($ ) Dollars ($ ) Werner Elementary School Phase #2: Werner Elementary School Phase #3: Dollars ($ ) Section 00310 Page 1 UNIT PRICING: Unit Price #1: Remove Turf Sod Dollars ($ ) Per SF Unit Price #2: Remove Concrete Dollars ($ ) Per SF Unit Price #3: Remove Asphalt Speed Humps Dollars ($ ) Per SF Unit Price #4: Remove Asphalt Pavement Dollars ($ ) Per SF Unit Price #5: New Concrete Speed Humps Dollars ($ ) Per SF Unit Price #6: New Vertical Curb and Gutter Dollars ($ ) Per LF Unit Price #7: New 4-ft Concrete Drain Pans, Apron and Transition Dollars ($ ) Per SF Unit Price #8: New 3.5-ft Concrete Drain Pan Dollars ($ ) Per SF Unit Price #9: New 6-ft Concrete Drain Pan, Apron and Ramp Transition Dollars ($ ) Per SF Unit Price #10: New Concrete Sidewalk Dollars ($ ) Per SF Unit Price #11: Aggregate Base Course Dollars ($ ) Per TON Unit Price #12: Hot Bituminous Pavement Dollars ($ ) Per TON Unit Price #13: Fly Ash Stabilization Dollars ($ ) Per SY Unit Price #14: Rock Socks Dollars ($ ) Per EA Unit Price #15: Straw Wattles Dollars ($ ) Per LF Unit Price #16: Signage – Handicap Parking Signs Dollars ($ ) Per EA BID CONDITIONS: 1. , and subject to all conditions thereof, the In compliance with your Invitation to Bid dated a **(Corporation, Limited Liability Company, Partnership, Joint undersigned Venture, or Sole Proprietor)** authorized to do business in the State of Colorado hereby proposes to furnish and do everything required by the Contract Documents to which this refers for the construction of all items shown in the Drawings, listed on the following Quantity Schedule and in the Measurement and Payment Section (01270). Section 00310 Page 2 2. The undersigned Bidder does hereby declare and stipulate that this proposal is made in good faith, without collusion or connection with any other person or persons Bidding for the same Work, and that it is made in pursuance of and subject to all the terms and conditions of the Invitation to Bid and Instructions to Bidders, the Agreement, the detailed Specifications, and the Drawings pertaining to the Work to be done, all of which have been examined by the undersigned. 3. All the various phases of Work enumerated in the Drawings and Contract Documents with their individual jobs and overhead, whether specifically mentioned, included by implication or appurtenant thereto, are to be performed by the CONTRACTOR and included in the Total Bid Price. 4. The foregoing prices shall include all labor, materials, transportation, shoring, removal, dewatering, overhead, profit, insurance, etc., to cover the complete Work in place of the several kinds called for. 5. Unit Prices provided on this Bid Proposal Form will be used in conjunction with actual quantities of work performed to determine the price of additional work requested by the OWNER, in writing, that is not included in the present Drawings or Contract Documents. 6. Bidder acknowledges that the OWNER has the right to delete items of Work or change quantities at his sole discretion without affecting the Agreement or prices of any item so long as the deletion or change does not exceed twenty-five percent (25%) of the total Agreement Price. RESPECTFULLY SUBMITTED: Signature Date Title License Number (If Applicable) (Seal - if Bid is by corporation) Attest Address Telephone Section 00310 Page 3 SECTION 00320 QUANTITY SCHEDULE Project: Werner Elementary - Phase 1 Date: February 2013 Quantity Schedule Item Number Description Measurement Unit Estimated Quantity 1 Mobilization N/A -- 2 Traffic Control N/A -- 3 Surveying N/A -- 4 Removal of Turf Sod SF 5 Remove Concrete SF 6 Remove Asphalt Speed Humps SF 7 Remove Asphalt Pavement SF 8 New Concrete Speed Humps SF 9 New Vertical Curb & Gutter LF 10 New 4-foot Concrete Drain Pans, Apron and Transition SF 11 New 3.5-foot Concrete Drain Pan N/A 12 New 6-foot Concrete Drain Pan, Apron, and Ramp Transition SF 13 New Concrete Sidewalk and Transitions SF 14 Aggregate Base Course TON 15 Hot Bituminous Pavement - Grades S and SX (including striping) TON 16 Fly Ash Stabilization SY 17 Rock Socks EA Straw Wattles LF 18 19 20 Playground Equipment -- Remove and Replace Basketball and Tetherball Poles and Benches Signage - Handicap Parking Signs N/A -- -- EA Section 00320 Page 1 SECTION 00320 QUANTITY SCHEDULE Project: Werner Elementary - Phase 2 Date: February 2013 Quantity Schedule Item Number Measurement Unit Estimated Quantity Mobilization NA -- 2 Traffic Control NA -- 3 Surveying NA -- 4 Removal of Turf Sod N/A -- 5 Remove Concrete SF 6 Remove Asphalt Speed Humps N/A 1 Description -- 7 Remove Asphalt Pavement SF 8 New Concrete Speed Humps N/A -- 9 New Vertical Curb & Gutter N/A -- 10 New 4-foot Concrete Drain Pans, Apron and Transition N/A -- 11 New 3.5-foot Concrete Drain Pan N/A -- 12 New 6-foot Concrete Drain Pan, Apron, and Ramp Transition N/A -- 13 New Concrete Sidewalk and Transitions N/A -- 14 Aggregate Base Course TON 15 Hot Bituminous Pavement - Grades S and SX (including striping) TON 16 Fly Ash Stabilization 17 Rock Socks EA 18 Straw Wattles N/A -- NA -- N/A -- 19 20 Playground Equipment -- Remove and Replace Basketball and Tetherball Poles and Benches Signage - Handicap Parking Signs SY Section 00320 Page 2 SECTION 00320 QUANTITY SCHEDULE Project: Werner Elementary - Phase 3 Date: February 2013 Quantity Schedule Item Number Measurement Unit Estimated Quantity Mobilization N/A -- 2 Traffic Control N/A -- 3 Surveying N/A -- 4 Removal of Turf Sod N/A -- 1 Description 5 Remove Concrete SF 6 Remove Asphalt Speed Humps N/A -- 7 Remove Asphalt Pavement SF 8 New Concrete Speed Humps N/A -- 9 New Vertical Curb & Gutter N/A -- 10 New 4-foot Concrete Drain Pans, Apron and Transition N/A -- 11 New 3.5-foot Concrete Drain Pan SF 12 New 6-foot Concrete Drain Pan, Apron, and Ramp Transition N/A -- 13 New Concrete Sidewalk and Transitions N/A -- 14 Aggregate Base Course TON 15 Hot Bituminous Pavement - Grades S and SX (including striping) TON 16 Fly Ash Stabilization 17 Rock Socks EA 18 Straw Wattles N/A -- N/A -- N/A -- 19 20 Playground Equipment -- Remove and Replace Basketball and Tetherball Poles and Benches Signage - Handicap Parking Signs SY Section 00320 Page 3 SECTION 00400 SUPPLEMENTS TO BID FORMS 00420 Statement of Bidder's Qualifications 00430 Schedule of Subcontractors SECTION 00420 STATEMENT OF BIDDER'S QUALIFICATIONS All questions must be answered and the data given must be clear and comprehensive. This statement must be notarized. If necessary, questions may be answered on separate attached sheets. The Bidder may submit any additional information he desires. 1. Name of Bidder: 2. Permanent main office address: 3. When organized: 4. If a corporation, where incorporated: 5. How many years have you been engaged in the contracting business under your present firm or trade name? 6. Contracts on hand: (Schedule these, showing the amount of each contract and the appropriate anticipated dates of completion.) 7. General character of Work performed by your company: 8. Have you ever failed to complete any Work awarded to you? If so, where and why? 9. Have your ever defaulted on a contract? If so, where and why? 10. Are you debarred by any government agency? If yes, list agency name 11. List the more important projects recently completed by your company, stating the approximate cost of each, and the month and year completed, location and type of construction. Section 00420 Page 1 12. List your major equipment available for this contract. 13. Experience in construction Work similar in importance to this project: 14. Background and experience of the principal members of your organization, including officers: 15. Credit available: $ 16. Bank reference: 17. Will you, upon request, fill out a detailed financial statement and furnish any other information that may be required by the OWNER? 18. Are you licensed as a General CONTRACTOR? If yes, in what city, county and state? What class, license and numbers? 19. Do you anticipate subcontracting Work under this Contract? If yes, what percent of total contract? and to whom? 20. Are any lawsuits pending against you or your firm at this time? If yes, DETAIL 21. What are the limits of your public liability? DETAIL: What company? 22. What are your company's bonding limitations? 23. The undersigned hereby authorizes and requests any person, firm or corporation to furnish any information requested by the OWNER in verification of the recital comprising this Statement of Bidder's Qualifications. Section 00420 Page 2 Dated at this day of 20 . Name of Bidder By: Title: State of ) County of ) ) being duly sworn deposes and says that he is of (Name of Organization). and that the answers to the foregoing questions and all statements therein contained are true and correct. Subscribed and sworn to before me this , 20 . day of Notary Public My commission expires Section 00420 Page 3 SECTION 00430 SCHEDULE OF SUBCONTRACTORS List all subcontractors who will perform over $10,000.00 of work and state the work item they will be performing. ITEM SUBCONTRACTOR Section 00430 Page 1 SECTION 00500 AGREEMENT FORMS 00510 Notice of Award 00520 Agreement 00530 Notice to Proceed SECTION 00510 NOTICE OF AWARD Date: TO: PROJECT: OWNER: Werner Elementary School Parking Lot and Play Area Site Improvement Project Poudre School District R-1 (hereinafter referred to as "the OWNER") You are hereby notified that your Bid dated , 20 for the above project has been considered. You are the apparent successful Bidder and have been awarded an Agreement for The Price of your Agreement is Dollars ($ ). Five (5) copies of each of the proposed Contract Documents (except Drawings) accompany this Notice of Award. Five (5) sets of the Drawings will be delivered separately or otherwise made available to you immediately. You must comply with the following conditions precedent within fifteen (15) days of the date of this Notice of Award, that is by , 20 . 1. 2. You must deliver to the OWNER four (4) fully executed counterparts of the Agreement including all the Contract Documents. Each of the Contract Documents must bear your signature on the cover of the page. You must deliver with the executed Agreement the Contract Security (Bonds) as specified in the Instructions to Bidders, General Conditions (Article 5.1) and Supplementary Conditions. Failure to comply with these conditions within the time specified will entitle OWNER to consider your Bid abandoned, to annul this Notice of Award and to declare your Bid Security forfeited. Within ten (10) days after you comply with those conditions, OWNER will return to you one (1) fullysigned counterpart of the Agreement with the Contract Documents attached. Poudre School District R-1 OWNER By: Title Section 00510 Page 1 SECTION 00520 AGREEMENT THIS AGREEMENT is dated as of the day of and shall be effective on the date this AGREEMENT is signed by PSD. Poudre School District R-1 in the year of 20 (hereinafter called OWNER) and (hereinafter called CONTRACTOR) OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows: ARTICLE 1. WORK CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Project for which the Work under the Contract Documents may be the whole or only a part is defined as the construction of the Werner Elementary School Parking Lot and Play Area Site Improvement Project and is generally described in Section 01110. ARTICLE 2. ENGINEER The Project has been designed by Anderson Consulting Engineers, Inc. (ACE). ACE has not been contracted to provide Construction Management Services, nor act as the Engineer for the construction of this project. The OWNER will assume all duties and responsibilities and will have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents. ARTICLE 3. CONTRACT TIMES 3.1 The Work will be Substantially Complete within fifty-four (54) calendar days after the starting date set forth in the Notice to Proceed as defined in the General Conditions and completed and ready for Final Payment and Acceptance in accordance with the General Conditions within sixty (60) calendar days after the start date set forth in the Notice to Proceed. Work will be Substantially Complete in accordance with the following milestones at the critical locations noted below. 3.2. Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence in this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 3.1. above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expenses and difficulties involved in proving in a legal proceeding the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay but not as penalty) CONTRACTOR shall pay OWNER the amounts set forth hereafter. Section 00520 Page 1 1) Substantial Completion: Nine Hundred Fifty Dollars ($950.00) for each calendar day or fraction thereof that passes after the fifty-four (54) calendar day period for Substantial Completion of the Work has expired until the Work is Substantially Complete. 2) Final Acceptance: After Substantial Completion, Five Hundred Fifty Dollars ($550.00) for each calendar day or fraction thereof that passes after the sixty (60) calendar day period for Final Payment and Acceptance has expired until the Work is ready for Final Payment and Acceptance. ARTICLE 4. CONTRACT PRICE 4.1. OWNER shall pay CONTRACTOR for performance of the Work in accordance with the Contract Documents in current funds as follows: ($ ), Dollars, in accordance with Section 00310, attached and incorporated herein by this reference. ARTICLE 5. PAYMENT PROCEDURES CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by ENGINEER as provided in the General Conditions. 5.1. PROGRESS PAYMENTS. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Application for Payment as recommended by ENGINEER, once each month during construction as provided below. All progress payments will be on the basis of the progress of the Work measured by the schedule of values established in paragraph 2.6 of the General Conditions and in the case of Unit Price Work based on the number of units completed, and in accordance with the General Requirements concerning Unit Price Work. 5.1.1. Progress payments will be made according to the percentages below, but, in each case, less the aggregate of payments previously made and less such amounts as ENGINEER shall determine, or OWNER may withhold, in accordance with paragraph 14.7 of the General Conditions. At the time of each progress payment the OWNER will pay ninety percent (90%) of the value of the Work completed. The remaining ten percent (10%) will be paid upon Final Acceptance of the project or may be paid progressively, at the OWNER's discretion, if the character and progress of the Work have been satisfactory to OWNER and ENGINEER. Ninety percent (90%) of materials and equipment not incorporated in the Work (but delivered, suitably stored and accompanied by documentation satisfactory to OWNER as provided in paragraph 14.2 of the General Conditions) may be included in the application for payment. 5.2. FINAL PAYMENT. Upon Final Completion and Acceptance of the Work in accordance with paragraph 14.13 of the General Conditions, OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said paragraph 14.13. Section 00520 Page 2 ARTICLE 6. CONTRACTOR'S REPRESENTATION In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations: 6.1 CONTRACTOR has familiarized himself with the nature and extent of the Contract Documents, Work, site, locality, and with all local conditions and Laws and Regulations that in any manner may affect cost, progress, performance or furnishing of the Work. 6.2. CONTRACTOR has studied carefully all reports of explorations and tests of subsurface conditions and drawings of physical conditions, which are identified in the Supplementary Conditions as provided in paragraph 4.2 of the General Conditions. 6.3. CONTRACTOR has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) all such examinations, investigations, explorations, tests, reports, and studies (in addition to or to supplement those referred to in paragraph 6.2 above) which pertain to the subsurface or physical condition at or contiguous to the site or otherwise may affect the cost, progress, performance or furnishing of the Work as CONTRACTOR considers necessary for the performance or furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provisions of paragraph 4.2 of the General Conditions; and no additional examinations, investigations, explorations, tests, reports, studies or similar information or data are or will be required by CONTRACTOR for such purposes. 6.4. CONTRACTOR has reviewed and checked all information and data shown or indicated on the Contract Documents with respect to existing Underground Facilities at or contiguous to the site and assumes responsibility for the accurate location of said Underground Facilities. No additional examinations, investigations, explorations, tests, reports, studies or similar information or data in respect of said Underground Facilities are or will be required by CONTRACTOR in order to perform and furnish the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents, including specifically the provision of paragraph 4.3. of the General Conditions. 6.5. CONTRACTOR has correlated the results of all such observations, examinations, investigations, tests, reports and data with the terms and conditions of the Contract Documents. 6.6. CONTRACTOR has given ENGINEER written notice of all conflicts, errors or discrepancies that he has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR. ARTICLE 7. CONTRACT DOCUMENTS 7.1. The Contract Documents which comprise the entire Agreement between OWNER and CONTRACTOR concerning the Work consist of the General Conditions, Supplementary Conditions, those items included in the definition of “Contract Documents” in Article 1.10 of the General Conditions, and such other items as are referenced in this Article 7, all of which are incorporated herein by this reference. 7.2. Forms for use by CONTRACTOR in performing the Work and related actions in carrying out the terms of this Agreement are deemed Contract Documents and incorporated herein by this reference, and include, but are not limited to, the following: Section 00520 Page 3 7.2.1 7.2.2 7.2.3 7.2.4 7.2.5 7.2.6 Certificate of Substantial Completion Certificate of Final Acceptance Lien Waiver Releases Consent of Surety Application for Exemption Certificate Application for Payment 7.3 Drawings, consisting of sheets numbered Sheet 1 through Sheet 18, with the following general title: Werner Elementary School Parking Lot and Play Area Site Improvement Project The Contract Drawings shall be stamped "Final for Construction" and dated. Any revisions made shall be clearly identified and dated. 7.4. Addenda Numbers to , inclusive. 7.5. The Contract Documents also include all written amendments and other documents amending, modifying, or supplementing the Contract Documents pursuant to paragraphs 3.5 and 3.6 of the General Conditions. 7.6. There are no Contract Documents other than those listed or incorporated by reference in this Article 7. The Contract Documents may only be amended, modified or supplemented as provided in paragraphs 3.5 and 3.6 of the General Conditions. ARTICLE 8. MISCELLANEOUS 8.1. Terms used in this Agreement which are defined in Article I of the General Conditions shall have the meanings indicated in the General Conditions. 8.2. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and specifically but not without limitations, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge that assignor from any duty or responsibility under the Contract Document. 8.3. OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, Agreement and obligations contained in the Contract Document. Section 00520 Page 4 OWNER: POUDRE SCHOOL DISTRICT R-1 CONTRACTOR: By: By: BY: By: Title: Date: Date: (CORPORATE SEAL) Attest: Attest: Address for giving notices: Address for giving notices: 2413 Laporte Avenue Warehouse #3 Fort Collins, Colorado 80521 License No. Approved as to Form Section 00520 Page 5 SECTION 00530 NOTICE TO PROCEED Description of Work: Werner Elementary School Parking Lot and Play Area Site Improvement Project To: This notice is to advise you: That the contract covering the above described Work has been fully executed by the CONTRACTOR and the OWNER. That the required CONTRACTOR's Performance Bond and Payment Bond have been received by the OWNER. That the OWNER has approved the said Contract Documents. Therefore, as the CONTRACTOR for the above described Work, you are hereby authorized and directed to proceed within ( ) calendar days from receipt of this notice as required by the Agreement. Dated this day of , 20 . The dates for Substantial Completion and Final Acceptance shall be , 20 , respectively. , 20 and Poudre School District R-1 OWNER By: Title: ACKNOWLEDGMENT OF NOTICE Receipt of the above Notice to Proceed is hereby acknowledged this . day of , 20 CONTRACTOR By: Title: Section 00530 Page 1 SECTION 00610 PERFORMANCE BOND Bond No. KNOW ALL MEN BY THESE PRESENTS: that (Firm) (Address)____________________________ (an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and (Firm)_______________________________ (Address)____________________________ hereinafter referred to as "the Surety", are held and firmly bound unto Poudre School District R-1, 2413 West Laporte Ave, Fort Collins, Colorado 80521 hereinafter referred to as the "OWNER", in the penal sum of in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Agreement with the OWNER, dated the day of , 20 , a copy of which is hereto attached and made a part hereof for the performance of Poudre School District R-1 project, Werner Elementary School Parking Lot and Play Area Site Improvement Project. NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions and agreements of said Agreement during the original term thereof, and any extensions thereof which may be granted by the OWNER, with or without Notice to the Surety and during the life of the guaranty period, and if the Principal shall satisfy all claims and demands incurred under such Agreement, and shall fully indemnify and save harmless the OWNER from all cost and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the OWNER all outlay and expense which the OWNER may incur in making good any default then this obligation shall be void; otherwise to remain in full force and effect. PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the Work or to the Specifications. PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State of Colorado and be acceptable to the OWNER. IN WITNESS WHEREOF, this instrument is executed in four (4) counterparts, each one of which shall be deemed an original, this day of , 20 . Section 00610 Page 1 IN PRESENCE OF: Principal By: (Title) (Address) (Corporate Seal) IN PRESENCE OF: Other Partners By: By: IN PRESENCE OF: Surety (Attorney-in-Fact) (Address) (Surety Seal) NOTE: Date of Bond must not be prior to date of Agreement. If CONTRACTOR is Partnership, all partners should execute Bond. Section 00610 Page 2 SECTION 00615 PAYMENT BOND Bond No. ____ KNOW ALL MEN BY THESE PRESENTS: that (Firm) (Address) (an Individual), (a Partnership), (a Corporation), hereinafter referred to as the "Principal" and (Firm) (Address hereinafter referred to as "the Surety", are held and firmly bound unto the Poudre School District R-1, 2413 West Laporte Ave., Fort Collins, Colorado 80521 hereinafter referred to as "the OWNER", in the penal sum of in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors and assigns, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION are such that whereas the Principal entered into a certain Agreement with the OWNER, dated the day of , 20 , a copy of which is hereto attached and made a part hereof for the performance of the Poudre School District R-1 project, Werner Elementary School Parking Lot and Play Area Site Improvement Project. NOW, THEREFORE, if the Principal shall make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the Work provided for in such Agreement and any authorized extension or modification thereof, including all amounts due for materials, lubricants, repairs on machinery, equipment and tools, consumed, rented or used in connection with the construction of such Work, and all insurance premiums on said Work, and for all labor, performed in such Work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect. PROVIDED, FURTHER, that the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Agreement or to the Work to be performed thereunder or the Specifications accompanying the same shall in any way affect its obligation on this bond; and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Agreement or to the Work or to the Specifications. PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. PROVIDED, FURTHER, that the Surety Company must be authorized to transact business in the State of Colorado and be acceptable to the OWNER. Section 00615 Page 1 IN WITNESS WHEREOF, this instrument is executed in four (4) counterparts, each one of day of , 20 . which shall be deemed an original, this IN PRESENCE OF: Principal By: (Title) (Address) (Corporate Seal) IN PRESENCE OF: Other Partners By: By: IN PRESENCE OF: Surety (Attorney-in-Fact) (Address) (Surety Seal) NOTE: Date of Bond must not be prior to date of Agreement. If CONTRACTOR is Partnership, all partners should execute Bond. Section 00615 Page 2 SECTION 00630 CERTIFICATE OF INSURANCE CONTRACTOR shall insert his own standard form for Certificate of Insurance. Section 00630 Page 1 SECTION 00635 CERTIFICATE OF SUBSTANTIAL COMPLETION TO: POUDRE SCHOOL DISTRICT R-1 (OWNER) DATE OF SUBSTANTIAL COMPLETION: PROJECT OR SPECIFIED PART SHALL INCLUDE: PROJECT TITLE: Werner Elementary School Parking Lot and Play Area Site Improvement Project LOCATION: Fort Collins, Colorado OWNER: Poudre School District R-1 CONTRACTOR: CONTRACT DATE: The Work performed under this contract has been inspected by authorized representatives of the OWNER, CONTRACTOR, and the ENGINEER and the project (or specified part of the project, as indicated above) is hereby declared to be substantially completed on the above date. A tentative list of items to be completed or corrected is appended hereto. This list may not be exhaustive, and the failure to include an item on it does not alter the responsibility of the CONTRACTOR to complete all the Work in accordance with the Contract Documents. ENGINEER By: AUTHORIZED REPRESENTATIVE DATE The CONTRACTOR accepts the above Certificate of Substantial Completion and agrees to complete and correct the items on the tentative list within the time indicated. CONTRACTOR By: AUTHORIZED REPRESENTATIVE DATE The OWNER accepts the project or specified area of the project as substantially complete and will assume full possession of the project or specified area of the project at 12:01 a.m., on . The responsibility for heat, utilities, security, and insurance under the Contract Documents shall be as set forth under "Remarks" below. POUDRE SCHOOL DISTRICT R-1 OWNER By: AUTHORIZED REPRESENTATIVE DATE REMARKS: Section 00635 Page 1 SECTION 00640 CERTIFICATE OF FINAL ACCEPTANCE , 20___ TO: Gentlemen: You are hereby notified that on the day of , 20 , the Poudre School District R-1, Fort Collins, Colorado, has accepted the Work completed by for the Poudre School District R-1 project, Werner Elementary School Parking Lot and Play Area Site Improvement Project. A check is attached hereto in the amount of $ as Final Payment for all Work done, subject to the terms of the Contract Documents which are dated . In conformance with the Contract Documents for this project, your obligations and guarantees will continue for the specified time from the following date: . Sincerely, OWNER: Poudre School District R-1 By: Title: ATTEST: Title: Section 00640 Page 1 SECTION 00650 LIEN WAIVER RELEASE (CONTRACTOR) TO: Poudre School District R-1, Colorado (OWNER) FROM: PROJECT: (CONTRACTOR) Werner Elementary School Parking Lot and Play Area Site Improvement Project. 1. The CONTRACTOR acknowledges having received payment, except retainage from the OWNER for all work, labor, skill and material furnished, delivered and performed by the CONTRACTOR for the OWNER or for anyone in the construction, design, improvement, alteration, addition or repair of the above described project. 2. In consideration of such payment and other good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the CONTRACTOR voluntarily waives all rights, claims and liens, including but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A. 270 a and b), stop notices, equitable liens and labor and material bond rights which the CONTRACTOR may now or may afterward have, claim or assert for all and any work, labor, skill or materials furnished, delivered or performed for the construction, design, improvement, alteration, addition or repair of the above described project, against the OWNER or its officers, agents, employees or assigns, against any fund of or in the possession or control of the OWNER, against the project or against all land and the buildings on and appurtenances to the land improved by the project. 3. The CONTRACTOR affirms that all work, labor and materials, furnished, delivered or performed to or for the construction, design, improvement, alteration, addition or repair of the project were furnished, delivered or performed by the CONTRACTOR or its agents, employees, and servants, or by and through the CONTRACTOR by various Subcontractors or materialmen or their agents, employees and servants and further affirms the same have been paid in full and have released in full any and all existing or possible future mechanic's liens or rights or claims against the project or any funds in the OWNER'S possession or control concerning the project or against the OWNER or its officers, agents, employees or assigns arising out of the project. 4. The CONTRACTOR agrees to defend and hold harmless the OWNER, the lender, if any, and the Surety on the project against and from any claim hereinafter made by the CONTRACTOR'S Subcontractors, materialmen, Section 00650 Page 1 employees, servants, agents or assigns against the project or against the OWNER or its officers, employees, agents or assigns arising out of the project for all loss, damage and costs, including reasonable attorneys fees, incurred as a result of such claims. 5. The parties acknowledge that the description of the project set forth above constitutes and adequate description of the property and improvements to which this Lien Waiver Release pertains. It is further acknowledged that this Lien Waiver Release is for the benefit of and may be relied upon by the OWNER, the lender, if any, and Surety on any labor and material bonds for the project. Signed this day of , 20 . CONTRACTOR By: Title: ATTEST: Secretary STATE OF COLORADO COUNTY OF LARIMER 20 ) )ss. ) Subscribed and sworn to before me this , by day of Witness my hand and official seal. My Commission Expires: . Notary Public Section 00650 Page 2 SECTION 00651 LIEN WAIVER RELEASE (Subcontractor) TO: (CONTRACTOR) FROM: (Subcontractor) PROJECT: Werner Elementary School Parking Lot and Play Area Site Improvement Project. 1. The Subcontractor acknowledges having received payment, except retainage, from the CONTRACTOR for all work, labor, skill and material furnished, delivered and performed by the Subcontractor for the CONTRACTOR or for anyone in the construction, design, improvement, alteration, addition or repair of the above described project. 2. In consideration of such payment and other good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the Subcontractor voluntarily waives all rights, claims and liens, including but not limited to, mechanic's liens, Miller Act claims (40 U.S.C.A. 270 a and b), stop notices, equitable liens and labor and material bond rights which the Subcontractor may now or may afterward have, claim or assert for all and any work, labor, skill or materials furnished, delivered or performed for the construction, design, improvement, alteration, addition or repair of the above described project, against the CONTRACTOR or its officers, agents, employees or assigns, against the project or against all land and the buildings on and appurtenances to the land improved by the project. 3. The Subcontractor affirms that all work, labor and materials, furnished, delivered or performed to or for the construction, design, improvement, alteration, addition or repair of the project were furnished, delivered or performed by the Subcontractor or its' agents, employees, and servants, or by and through the Subcontractor by various subsubcontractors or materialmen or their agents, employees and servants and further affirms the same have been paid in full and have released in full any and all existing or possible future mechanic's liens or rights or claims against the project or against the CONTRACTOR or its officers, agents, employees or assigns arising out of the project. 4. The Subcontractor agrees to defend and hold harmless the CONTRACTOR, the lender, if any, and the Surety on the project against and from any claim hereinafter made by the Subcontractor's sub-subcontractors, materialmen, employees, servants agents or assigns against the project or against the CONTRACTOR or OWNER, lender or Surety or their officers, employees, agents or assigns arising out of the project for all loss, damage and costs, including reasonable attorneys fees, incurred as a result of such claims. 5. The parties acknowledge that the description of the project set forth above constitutes and adequate description of the property and improvements to which this Lien Waiver Release pertains. It is further acknowledged that this Lien Waiver Release is for the benefit of and may be relied upon by the CONTRACTOR, OWNER, the lender, if any, and Surety on any labor and material bonds for the project. Signed this day of , 20 . Section 00651 Page 1 Subcontractor By: ATTEST: Secretary STATE OF COLORADO COUNTY OF LARIMER ) )ss. ) Subscribed and sworn to before me this . day of 20 , by Witness my hand and official seal. My Commission Expires: Notary Public Section 00651 Page 2 SECTION 00660 CONSENT OF SURETY TO: Poudre School District R-1, Colorado (hereinafter referred to as the "OWNER") CONTRACTOR: PROJECT: Werner Elementary School Parking Lot and Play Area Site Improvement Project. CONTRACT DATE: In accordance with the provisions of the Contract between the OWNER and the CONTRACTOR as indicated above, for bond of (Surety) hereby approves of the Final Payment to the CONTRACTOR, and agrees that Final Payment to the CONTRACTOR shall not relieve the Surety Company of any of its obligations to the OWNER, as set forth in the said Surety Company's Bond. IN WITNESS WHEREOF, the Surety Company has hereunto set its hand this _____day of , 20 . (Surety Company) By: ATTACH: Power of Attorney and Certificate of Authority of Attorney(s)-in-Fact. Section 00660 Page 1 SECTION 00670 APPLICATION FOR EXEMPTION CERTIFICATE (Insert State certificate here.) Section 00670 Page 1 SECTION 00700 GENERAL CONDITIONS SECTION 00800 SUPPLEMENTARY CONDITIONS SECTION 00800 SUPPLEMENTARY CONDITIONS Conditions of the Contract These Supplementary Conditions amend or supplement the General Conditions of the Construction Contract (EJCDC General Conditions 1910-8, 1990 edition with City of Fort Collins modifications) and other provisions of the Contract Documents as indicated below. SC-4.2 A. Subsurface and Physical Conditions: Add the following language to paragraph 4.2.1 of the General Conditions. 4.2.1.1.1 The following report(s) of exploration and tests of subsurface conditions at the site of the Work: “Subsurface Exploration Report – Proposed Pavement Reconstruction Werner Elementary School”, 5400 Mail Creek Lane, Fort Collins, Colorado Earth Engineering Consultants, Inc. EEC Project No. 1122109, December 17, 2012 Contractor may rely upon the accuracy of the technical data contained in the geotechnical documents, but not upon non-technical data, interpretations or opinions contained therein or upon the completeness of any information in the report. B. 4.2.1.2.1 No drawing of physical conditions in or relating to existing surface or subsurface structures (except Underground Facilities referred to in Paragraph 4.3) which are at or contiguous to the site have been utilized by the Engineer in preparation of the Contract Documents, except the following: None SC-5.4.7 A. Additional Insureds Anderson Consulting Engineers, Inc. shall be included as additional insureds on the Certificate of Insurance. Section 00800 Page 1 SC-5.4.8 A. Limits of Liability Add the following language at the end of paragraph 5.4.8. The limits of liability for the insurance required by the paragraph numbers of the General Conditions listed below are as follows: 5.4.1 and 5.4.2 Coverage A - Statutory Limits Coverage B - $100,000/$100,000/$500,000 5.4.3 and 5.4.5 Commercial General Liability policy will have limits of $1,000,000 combined single limits (CSL). This policy will include coverage for Explosion, Collapse, and Underground coverage unless waived by the Owner. 5.4.6 The Comprehensive Automobile Liability Insurance policy will have limits of $1,000,000 combined single limits (CSL). 5.4.9 This policy will include completed operations coverage/product liability coverage with limits of $1,000,000 combined single limits (CSL). Section 00800 Page 2 SECTION 00900 ADDENDA, MODIFICATIONS, AND PAYMENT 00950 Contract Change Order 00960 Application for Payment CHANGE ORDER NO. PROJECT TITLE: Werner Elementary School Parking Lot and Play Area Site Improvement Project CONTRACTOR: PROJECT NUMBER: DESCRIPTION: 1. Reason for change: 2. Description of Change: 3. Change in Contract Cost: 4. Change in Contract Time: ORIGINAL CONTRACT COST TOTAL APPROVED CHANGE ORDER TOTAL PENDING CHANGE ORDER TOTAL THIS CHANGE ORDER TOTAL % OF THIS CHANGE ORDER TOTAL C.O.% OF ORIGNINAL CONTRACT ADJUSTED CONTRACT COST $ 0.00 0.00 0.00 0.00 $ 0.00 (Assuming all change orders approved) ACCEPTED BY: DATE: Contractor's Representative ACCEPTED BY: DATE: Project Manager REVIEWED BY: DATE: Title: APPROVED BY: DATE: Title: APPROVED BY: DATE: Purchasing Agent over $15,000 cc: Contractor Architect Project File Purchasing Engineer Section 00950 Page 1 Section 00960 Application for Payment Section 00960 Page 1 DIVISION 1 - GENERAL REQUIREMENTS SECTION 01110 SUMMARY OF WORK SECTION 01140 CONTRACTOR’S USE OF PREMISES SECTION 01180 UTILITY SOURCES SECTION 01270 MEASUREMENT AND PAYMENT SECTION 01310 PROJECT MEETINGS SECTION 01320 CONSTRUCTION SCHEDULES SECTION 01330 SUBMITTALS SECTION 01425 STANDARD REFERENCES SECTION 01450 MATERIALS TESTING SECTION 01555 TRAFFIC REGULATION SECTION 01635 SUBSTITUTIONS AND PRODUCT OPTIONS SECTION 01650 MATERIAL DELIVERY, STORAGE, AND HANDLING SECTION 01710 SITE CONDITIONS SECTION 01720 FIELD ENGINEERING AND SURVEYING SECTION 01745 ENVIRONMENTAL CONTROLS SECTION 01780 CONTRACT CLOSE-OUT SECTION 01110 SUMMARY OF WORK PART 1 1.01 GENERAL SECTION INCLUDES Furnish all labor and install all materials for the Werner Elementary School Parking Lot and Play Area Site Improvement Project, including but not limited to the following items: The project includes the removal of existing asphalt pavement, concrete sidewalk, curb and gutter, drain pans, and landscape materials. The project also includes the construction of new asphalt pavement, concrete driveway, concrete entrance ramp, sidewalk, curb and gutter, curb access ramp, drain pans, and bus canopy pavement; as well as the installation of bus canopy wheel stops and application of pavement markings. 1.02 WORK SEQUENCE The Work Sequence is to be submitted as part of the construction schedule required in Section 01320. Construction of the project may begin immediately on the date of Notice to Proceed. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01110-1 Summary of Work THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 01110-2 Summary of Work SECTION 01140 CONTRACTOR’S USE OF PREMISES PART 1 1.01 SECTION INCLUDES A. 1.02 The CONTRACTOR may use the OWNER’s property designated by the OWNER’s Representative for equipment and materials as long as he confines his operations to those permitted by local laws, ordinance and permits and meets the following requirements: 1. Do not unreasonably encumber site with materials or equipment. 2. Assume full responsibility for protection and safekeeping of products stored on premises. 3. Move any stored products which interfere with operations of the OWNER. 4. Obtain and pay for use of additional storage or work areas needed for operations. 5. Provide access for emergency vehicles to the site at all times. LIMITS OF CONSTRUCTION A. 1.03 GENERAL The CONTRACTOR must maintain all of his construction activities within the OWNER’s property and/or construction easements and limits of the project, or other stated areas, unless permits and/or written permission are obtained by the CONTRACTOR, from appropriate authorities or private property owners, outside of these areas. SECURITY A. The CONTRACTOR shall at all times be responsible for the security of his facilities and equipment. The OWNER will not take responsibility for missing or damaged equipment, tools, or personal belongings of the CONTRACTOR. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01140-1 Contractor’s Use of Premises THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 01140-2 Contractor’s Use of Premises SECTION 01180 UTILITY SOURCES PART 1 1.01 GENERAL SECTION INCLUDES A. Names and telephone numbers of affected agencies and utilities in the area are listed below for the CONTRACTOR’s convenience. The CONTRACTOR assumes all responsibility of contacting these agencies and verification of telephone numbers. 1. Water a. City of Fort Collins b. Fort Collins – Loveland Water District (970) 221-6700 (970) 226-3104 2. Sanitary Sewer - City of Fort Collins (970) 221-6700 3. Stormwater - City of Fort Collins (970) 221-6700 4. Park Planning – City of Fort Collins (970) 221-6366 5. Electrical a. City of Fort Collins b. Platte River Power Authority (PRPA) c. Western Area Power Administration (WAPA) d. Poudre Valley Rural Electric Association (PVREA) e. Public Service Company (PSC) / Xcel Energy (970) 224-6157 (970) 226-4000 (970) 461-7298 (970) 226-1234 (800) 895-1999 Engineering – City of Fort Collins (970) 221-6605 Engineering – Larimer County (970) 498-5700 7. Traffic – City of Fort Collins (970) 224-6062 8. Gas - Public Service Company / Xcel Energy (800) 895-2999 9. Telephone - Qwest Communications (970) 222-2414 10. Cable TV - Comcast (888) 824-4010 11. Poudre School District R-1 (970) 490-3600 12. One-Call Utility Locates 811 6. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01180-1 Utility Sources THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 01180-2 Utility Sources SECTION 01270 MEASUREMENT AND PAYMENT PART 1 1.01 SECTION INCLUDES A. 1.02 GENERAL The work performed under this Agreement shall be paid for as described in Section 500, Article 5 based on the Bid Proposal and the Total Bid Price. All costs incurred shall comply with the provisions of these Specifications and shall be included in the Total Bid Price for the project. Except as may be otherwise stipulated, no material, labor or equipment will be furnished by the OWNER. The following provides a general listing of items of Work along with a brief summary of the work and materials included. Refer to the Specifications and Drawings for additional information and all requirements for each item of Work. ITEMS OF WORK 1. Mobilization No unit measurement for payment will be made for any of the work, materials and equipment required for mobilization. This work consists of the mobilization of personnel, equipment and supplies at the project site in preparation for work on the project. This item shall include the establishment of the CONTRACTOR’S offices, buildings and other necessary facilities, and all other costs incurred or labor and operations which must be performed prior to beginning the other items under the Contract. This item shall also include temporary fencing around project work areas, and any other fencing/security items as deemed necessary by the CONTRACTOR. Removal of the CONTRACTOR’s equipment, supplies, excess materials, and cleanup of the site are also included in this item. 2. Traffic Control No unit measurement for payment shall be made for any of the materials, work, and equipment required. The payment shall be total compensation for all labor, equipment, materials, maintenance, and all incidentals necessary to prepare, implement, and maintain the approved Traffic Control Plan in accordance with the Drawings and accepted Traffic Control Plan. 3. Surveying No unit measurement shall be made for this item. Work includes providing all equipment, labor, and materials required to provide Surveying for construction of all work items for the project including: Staking of horizontal and vertical alignments; overlot grading; subgrade elevations; off-sets; temporary control points; re-establishment of land monuments; and, all appurtenance features of the work. 4. Remove Turf Sod No unit measurement for payment shall be made for this item. The Total Bid Price shall include all of the CONTRACTOR’s cost of whatsoever nature to complete the turf sod removal: furnishing and transporting all materials, labor, and equipment; Werner Elem. 01270-1 Measurement and Payment excavation, removal disposal of sod; backfilling, grading and compacting; removal and/or moving of sprinkler equipment; and, all other related and necessary materials, work, and equipment required to perform the work in accordance with the Drawings and Specifications. 5. 6. Remove Concrete Remove Asphalt Speed Humps No unit measurement for payment shall be made for this item. The Total Bid Price shall include full compensation for sawing, removing, hauling and disposal of such items including existing cable/conduit, pipe, concrete, asphalt, and excavation and subsequent backfill with suitable material associated with the removal of these items, and all other work necessary to remove these items in accordance with the Drawings and Specifications. Replacement of asphalt; curb, gutter and sidewalk; storm sewer and pipe outside of the pay lines due to the CONTRACTOR’s failure to protect existing, undisturbed materials shall not be paid for and shall be replaced at the CONTRACTOR’s expense. 7. Remove Asphalt Pavement No unit measurement for payment shall be made for this item. The Total Bid Price shall include full compensation for sawing, removing, hauling and disposal of such items including existing cable/conduit, pipe, concrete, asphalt, and excavation and subsequent backfill with suitable material associated with the removal of these items, and all other work necessary to remove these items in accordance with the Drawings and Specifications. Replacement of asphalt; curb, gutter and sidewalk; storm sewer and pipe outside of the pay lines due to the CONTRACTOR’s failure to protect existing, undisturbed materials shall not be paid for and shall be replaced at the CONTRACTOR’s expense. 8. Concrete Speed Humps No unit measurement for payment shall be made for this item. No payment will be made for items placed outside of the dimensions as shown on the Drawings unless directed by the ENGINEER OWNER. The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever nature associated with Concrete Speed Humps. The price bid shall include: furnishing and placing the concrete; forming; furnishing and applying curing compounds; finishing the edging the concrete surfaces; joints and joint materials; furnishing and compacting all materials required for preparation of a stable subbase; backfilling; curb painting; and all other related and necessary materials, work, and equipment required to construct the concrete curb and gutter in accordance with the Drawings and Specifications. No payment shall be made for replacement of materials damaged by the CONTRACTOR in his operations. 9. Vertical Curb and Gutter No unit measurement for payment shall be made for this item. No payment will be made for items placed outside of the dimensions as shown on the Drawings unless directed by the ENGINEER OWNER. The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever nature associated with Vertical Curb and Gutter. The price bid shall include: furnishing and placing the concrete; forming; Werner Elem. 01270-2 Measurement and Payment furnishing and applying curing compounds; finishing the edging the concrete surfaces; joints and joint materials; furnishing and compacting all materials required for preparation of a stable subbase; backfilling; curb painting; and all other related and necessary materials, work, and equipment required to construct the concrete curb and gutter in accordance with the Drawings and Specifications. No payment shall be made for replacement of materials damaged by the CONTRACTOR in his operations. 10. 11. 12. Concrete Drain Pans (4-ft wide), Apron and Transition Concrete Drain Pan (3.5-ft wide) Concrete Drain Pan (6-ft wide), Apron and Ramp Transition No unit measurement for payment shall be made for this item. No payment will be made for items placed outside of the dimensions as shown on the Drawings unless directed by the ENGINEER OWNER. The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever nature associated with Concrete Drain Pan, Apron and Ramp Transition. The price bid shall include: furnishing and placing the concrete; forming; furnishing coloring; furnishing expansion joints; furnishing and applying the curing compounds; sawcutting existing concrete as required; sawcutting control joints; finishing and edging the concrete surface; furnishing and compacting all materials required for preparation of a stable subbase; backfilling; and, all other related and necessary materials, work, and equipment required to construct the concrete pan in accordance with the Drawings and Specifications. 13. Concrete Sidewalk No unit measurement for payment shall be made for this item. Payment will be made as work progresses. No payment will be made for items placed outside of the dimensions as shown on the Drawings unless directed by the ENGINEER OWNER. The Total Bid Price shall include all of the CONTRACTOR’s costs of whatsoever nature associated with Concrete Sidewalk. The price bid shall include: furnishing and placing the concrete; forming; furnishing and applying curing compounds; finishing the edging the concrete surfaces; joints and joint materials; furnishing and compacting all materials required for preparation of a stable subbase; backfilling; and, all other related and necessary materials, work, and equipment required to construct the concrete flatwork in accordance with the Drawings and Specifications. No measurement for payment shall be made for replacement of materials damaged by the CONTRACTOR in his operations. 14. Aggregate Base Course No unit measurement for payment shall be made for this item. The Total Bid Price shall include full compensation for furnishing all labor, materials, equipment, and incidentals and for doing all work involved in Aggregate Base Course, complete-inplace, including supplying, placing and compacting aggregate base course at proper moisture in accordance with the Drawings and Specifications or as otherwise directed by the ENGINEER. 15. Hot Bituminous Pavement-Grades S and SX (including striping) No unit measurement for payment shall be made for this item. The Total Bid Price shall include full compensation for furnishing all labor, materials, equipment, and Werner Elem. 01270-3 Measurement and Payment any other incidentals to Hot Bituminous Pavement-Grade S and SX in accordance with the Contract Documents, complete-in-place; haul from the suppliers source; placement of pavement to design dimensions; subgrade preparation, excavation and embankment, including that required for Aggregate Base Course and Fly Ash installation; placement; compaction; striping; striping on concrete pavement; and, any other miscellaneous items and work shown or reasonably implied on the Drawings and in the Specifications for this work, and elsewhere in the Contract Documents. 16. Fly Ash Stabilization No unit measurement for payment shall be made for this item. The Lump Sum Bid Price for Fly Ash Stabilization shall include full compensation for furnishing all labor, materials, equipment, and incidentals and for placement, amendment, compaction, and all incidental work involved in Fly Ash Stabilization complete-inplace, including supplying and placing this item in accordance with the Drawings and Specifications or as otherwise directed by the ENGINEER OWNER. 17. 18. Rock Socks Straw Wattles No unit measurement for payment shall be made for this item. The Total Bid Price shall include all of the contractor’s costs of whatsoever nature required for supplying, installing, maintaining, removing the erosion control BMPs (filters, rock socks, wattles, etc.), and all other related and necessary materials, work, and equipment required to install erosion control BMPs in accordance with the Drawings and Specifications. 19. Playground Equipment - Remove and Replace Basketball and Tetherball Poles and Benches No unit measurement for payment shall be made for this item. The Total Bid Price shall include all of the CONTRACTOR’S costs of whatsoever nature. The bid price shall include; removal, storage, excavation; backfill; concrete pole and bench leg base; steel reinforcing; testing, asphalt patching and all other related and necessary materials, work, and equipment required to remove and reinstall playground poles and metal benches in accordance with the Drawings and Specifications. No measurement for payment shall be made for the replacement of materials damaged by the CONTRACTOR outside of this operation. Existing basketball and tetherball posts shall be reinstalled to the same height to rim and top, respectively, as they had at removal. 20. Signage – Handicap Parking Signs No unit measurement for payment shall be made for this item. The Total Bid Price shall include all of the CONTRACTOR’s cost of whatsoever nature to complete the sign installation including: furnishing and transporting all materials, labor, and equipment; furnishing and installing new signs; backfilling and compaction topsoil replacement; and, all other related and necessary materials, work, and equipment required to perform the work in accordance with the Drawings and Specifications. END OF SECTION Werner Elem. 01270-4 Measurement and Payment SECTION 01310 PROJECT MEETINGS PART 1 1.01 GENERAL SECTION INCLUDES A. Pre-Construction Conference: A Pre-Construction Conference will be held after Notice of Award and before the Notice to Proceed; the date, time and location will be determined after Notice of Award. The conference shall be attended by: 1. 2. 3. 4. CONTRACTOR and CONTRACTOR’s Superintendent CONTRACTOR’s Surveyor and Subcontractors OWNER Others as requested by the CONTRACTOR or OWNER. Unless previously submitted to the OWNER, the CONTRACTOR shall bring to the conference a tentative schedule of the construction project, include in the schedule shop drawings and other submittals. The purpose of the conference is to designate responsible personnel and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The agenda will include: 1. 2. 3. 4. 5. 6. 7. 8. 9. B. CONTRACTOR’s tentative Schedule Permit applications and submittals, including Erosion and Sediment Control Plan, and Traffic Control Plan Transmittal, review and distribution of CONTRACTOR’s submittals Processing applications for payment Maintaining record documents Critical work sequencing Field decision and change orders Use of premises, office and storage areas, staging area, security, housekeeping, and OWNER’s needs CONTRACTOR’s assignment of safety and first aid Construction Progress Meetings: Progress meetings will be conducted weekly or at the discretion of the OWNER. These meetings shall be attended by the OWNER, the CONTRACTOR’s representative and any others invited by these people. The meeting will be conducted by the OWNER and the OWNER will arrange for keeping the minutes and distributing the minutes to all persons in attendance. The agenda of these project meetings will include construction progress, the status of submittal reviews, the status of information requests, critical work sequencing, review of strategies for connections into existing facilities, status of field orders and change orders, and any general business. Werner Elem. 01310-1 Project Meetings PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01310-2 Project Meetings SECTION 01320 CONSTRUCTION SCHEDULES PART 1 1.01 GENERAL SECTION INCLUDES A. Prepare detailed schedule of all construction operations and procurements to be reviewed by parties attending the preconstruction conference. Schedule shall be approved by the OWNER prior to Notice to Proceed. 1.02 FORMAT AND SUBMISSIONS A. Prepare construction and procurement schedules in a graphic format suitable for displaying scheduled and actual progress. B. Submit four (4) copies of each schedule to the OWNER for review. The OWNER will return one copy to the CONTRACTOR with revisions suggested or necessary for coordination of the Work with the needs of the OWNER or others. 1.03 CONTENT A. Construction Progress Schedule 1. Show the complete work sequence of construction by activity and location. 2. Show the dates for the beginning and completion of major task items. At a minimum, show the following items for each phase of the project: • • • • • • • 3. B. Werner Elem. Removal of existing asphalt pavement and landscape materials; Removal of existing concrete work (sidewalks, curb and gutter, and drain pans); Preparation of subgrade and grading; Installation of new concrete work (driveway, entrance ramp, sidewalk, curb and gutter, curb access ramp, drain pans, and bus canopy pavement); Installation of new asphalt pavement; Installation of bus canopy wheel stops; and, Pavement markings. Show projected percentage of completion for each item as of the first day of the month. Report of delivery of equipment and materials. 1. Show delivery status of critical and major items of equipment and materials. 2. Include a schedule which includes the critical path for Shop Drawings, tests, and other submittal requirements for equipment and materials. 01320-1 Construction Schedules 1.04 PROGRESS REVISIONS A. Submit revised schedules and reports when changes are foreseen, when requested by OWNER, and with each application for progress payment. B. Show changes occurring since previous submission. 1. 2. C. 1.05 Actual progress of each item to date. Revised projections of progress and completion. Provide a narrative report as needed to define: 1. Anticipated problems, recommended actions, and their effects on the schedule. 2. The effect of changes on schedules of others. OWNER'S RESPONSIBILITY A. OWNER's review is only for the purpose of checking conformity with the Contract Documents and assisting CONTRACTOR in coordinating the Work with the needs of the Project. B. It is not to be construed as relieving CONTRACTOR from any responsibility to determine the means, methods, techniques, sequences and procedures of construction as provided in the General Conditions. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01320-2 Construction Schedules SECTION 01330 SUBMITTALS PART 1 1.01 GENERAL SECTION INCLUDES A. B. Werner Elem. Requirements 1. Where required by the Specifications, the CONTRACTOR shall submit descriptive information that will enable the ENGINEER OWNER to determine whether the CONTRACTOR’s proposed materials, equipment and methods of work are in general conformance to the design concept and in accordance with the Drawings and Specifications. The information submitted may consist of drawings, specifications, descriptive data, certificates, samples, test results, product data, and such other information, all as specifically required in the Specifications. In some instances, specified submittal information describes some, but not all features of the material, equipment, or method of work. 2. The CONTRACTOR shall be responsible for the accuracy and completeness of the information contained in each submittal and shall assure that the material, equipment, or method of work shall be as described in the submittal. The CONTRACTOR shall verify that all features of all products conform to the requirements of the Drawings and Specifications. The CONTRACTOR shall ensure that there is no conflict with other submittals and notify the ENGINEER OWNER in each case where its submittal may affect the work of another CONTRACTOR or the OWNER. The CONTRACTOR shall ensure coordination of submittals among the related crafts and subcontractors. 3. Submittals will be reviewed for overall design intent and returned to CONTRACTOR with action to be indicated by the ENGINEER OWNER. It shall be the CONTRACTOR’s responsibility to assure that previously accepted documents are destroyed when they are superseded by a resubmittal as such. 4. It shall be the CONTRACTOR’s responsibility to ensure that required items are corrected and resubmitted. Any work done before approval shall be at the CONTRACTOR’s own risk. Submittal Procedure 1. Unless a different number is called for in the individual sections, six (6) copies of each submittal and sample are required, four (4) of which will be retained by the ENGINEER OWNER. The CONTRACTOR shall receive two (2) copies in return. Faxed submittals will not be accepted. 2. Submittals that are related to or affect each other shall be forwarded simultaneously as a package to facilitate coordinated review. Uncoordinated submittals will be rejected. 01330-1 Submittals C. Werner Elem. 3. If the items or system proposed are acceptable but the major part of the individual drawings or documents are incomplete or require revision, the submittal will be returned with requirements for completion. 4. The right is reserved for the ENGINEER OWNER to require submittals in addition to those called for in individual sections. 5. Submittals regarding material and equipment shall be submitted directly to the ENGINEER OWNER and will be accompanied by a transmittal form. A separate form shall be used for each specific item, class of material, equipment, and items specified in separate discrete sections for which the submittal is required. Submittals for various items shall be made with a single form when the items taken together constitute a manufacturer’s package or are so functionally related that expediency indicates checking or review of the group or package as a whole. 6. A unique number, sequentially assigned, shall be noted on the transmittal form accompanying each item submitted. Original submittal numbers shall have the following format: “XXX-Y;” where “XXX” is the originally assigned submittal number and “Y” is a sequential letter assigned for resubmittals (i.e., A, B, or C being the first, second and third resubmittals, respectively). Submittal 25B, for example, is the second resubmittal of Submittal 25. 7. If the CONTRACTOR proposes to provide material, equipment, or method of work that deviates from the Contract Documents, it shall indicate so under “deviations” on the transmittal form accompanying the submittal copies. 8. Submittals that do not have all the information required to be submitted, including deviations, are not acceptable and will be returned without review. Review Procedure: 1. Submittals are specified for those features and characteristics of materials, equipment, and methods of operation that can be selected based on the CONTRACTOR’s judgment of their conformance to the requirements of the Drawing and Specifications. Other features and characteristics are specified in a matter that enables the CONTRACTOR to determine acceptable options without submittals. The review procedure is based on the CONTRACTOR’s guarantee that all features and characteristics not requiring submittals conform to the Drawings and Specifications. Review shall not extend to means, methods, techniques, sequences, or procedures of construction or to verifying quantities, dimensions, weights or gages, or fabrication processes (except where specifically indicated or required by the Specifications) of separate items, and as such, will not indicate approval of the assembly in which the item functions. 2. Unless otherwise specified, within twenty-one (21) calendar days after receipt of the submittal, the ENGINEER OWNER will review the submittal and return copies. The returned submittal will indicate one of the following actions: 01330-2 Submittals a. If the review indicates that the material, equipment, or work method complies with the Specifications, submittal copies will be marked “NO EXCEPTIONS TAKEN”. In this event, the CONTRACTOR may begin to implement the work method or incorporate the material or equipment covered by the submittal. b. If the review indicates limited corrections are required, copies will be marked “FURNISH AS NOTED”. The CONTRACTOR may begin implementing the work method or incorporating the material and equipment covered by the submittal in accordance with the noted corrections. Where submittal information will be incorporated in Operation and Maintenance data, a corrected copy shall be provided. c. If the review indicates that the submittal is insufficient or contains incorrect data, copies will be marked “REVISE AND RESUBMIT”. Except at its own risk, the CONTRACTOR shall not undertake work covered by this submittal until it has been revised, resubmitted and returned marked either “NO EXCEPTIONS TAKEN” or “FURNISH AS NOTED”. d. D. If the review indicates that the material, equipment, or work method do not comply with the Specifications, copies of the submittal will be marked “REJECTED”. Submittals with deviations that have not been identified clearly may be rejected. Except at its own risk, the CONTRACTOR shall not undertake the work covered by such submittals until a new submittal is made and returned marked either ”NO EXCEPTIONS TAKEN” or “FURNISH AS NOTED”. Drawings 1. The term “shop drawings” includes drawings, diagrams, layouts, schematic, descriptive literature, illustrations schedules performance and test data, and similar materials furnished by CONTRACTOR to explain in detail specific portions of the work required by the Contract 2. CONTRACTOR shall coordinate all such drawings, and review them for legibility, accuracy, completeness and compliance with contract requirements and shall indicate this approval thereon as evidence of such coordination and review. Shop drawing submitted to the ENGINEER OWNER without evidence of CONTRACTOR’s approval will be returned for resubmission. 3. Shop drawing shall be clearly identified with the name and project number of this contract, and references to applicable specification paragraphs and contract drawings. When catalog pages are submitted, applicable items shall be clearly identified. 4. CONTRACTOR shall stamp his approval on shop drawings prior to submission to the ENGINEER OWNER as indication of his checking and verification of dimensions and coordination with interrelated items. Stamp shall read: “(CONTRACTOR’s Name) represents that we have determined and verified all field dimensions and measurements, field construction Werner Elem. 01330-3 Submittals criteria, materials, catalog numbers and similar data, and that we have checked with the requirements of the Specifications and Drawings, the Contract Documents, and General Conditions”. Marks on drawings by CONTRACTOR shall not be in red. Any marks by CONTRACTOR shall be duplicated on all copies submitted. E. 5. If shop drawings show variations from contract requirements, CONTRACTOR shall describe such variations in writing, separate from the drawings, at time of submission. All such variations must be approved by the ENGINEER OWNER. If ENGINEER OWNER approves any such variations, he shall issue an appropriate contract modification, except that, if the variation is minor and does not involve a change in price or in time of performance, a modification need not be issued. 6. Should the CONTRACTOR propose any item on his shop drawings or incorporate an item into the work, and that item should subsequently prove to be defective or otherwise unsatisfactory, (regardless of the ENGINEER’s OWNER’s preliminary review), the CONTRACTOR shall, at his own expense, replace the item with another item that will perform satisfactorily. Certificates For those items called for in individual sections, furnish six (6) certificates of compliance from manufacturers or suppliers certifying that materials or equipment being furnished under the Contract comply with the requirements of these Specifications. F. Samples Samples shall be sufficient in size to clearly illustrate functional characteristics and full range of color, texture, and pattern. G. Effect of Review of CONTRACTOR’s Submittals Review of drawings, data, methods of work, or information regarding materials or equipment the CONTRACTOR proposes to provide, shall not relieve the contractor of its responsibility for errors therein and shall not be regarded as an assumption of risks or liability by the ENGINEER or the OWNER, or by any officer or employee thereof, and the CONTRACTOR shall have no claim under the Contract on account of the failure or partial failure, of the method of work, material, or equipment so reviewed. A mark of “NO EXCEPTIONS TAKEN” or “FURNISH AS NOTED” shall mean that the OWNER has no objection to the CONTRACTOR, upon its own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01330-4 Submittals SECTION 01425 STANDARD REFERENCES PART 1 1.01 GENERAL SECTION INCLUDES A. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to the laws or regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard specification, manual, code, or laws or regulations in effect at the time of opening of Bids, except as may be otherwise specifically stated. However, no provision of any referenced standard, specifications manual or code (whether or not specially incorporated by reference in the Contact Documents) shall be effective to change the duties and responsibilities of OWNER, CONTRACTOR, or ENGINEER, or any of their consultants, agents or employees from those set forth in the Contract Documents, nor shall it be effective to assign to ENGINEER, or any of ENGINEER’s Consultants, agents, or employees, any duty or authority to supervise or direct the furnishing or performance of the Work. Whenever used in the Contract Documents, the following abbreviations will have the meanings listed: AASHTO American Association of State Highway and Transportation Officials 444 North Capital Street, N.W., Suite 225 Washington, DC 20001 ACI American Concrete Institute P. O. Box 19150 Detroit, MI ACPA American Concrete Pipe Association AISC American Iron and Steel Institute 150 East 42nd Street New York, NY 10017 American Iron and Steel Institute 150 East 42nd Street New York, NY 10017 AISI Werner Elem. ANSI American National Standards Institute, Inc. 1430 Broadway New York, NY 10017 AREMA American Railway Engineering and Maintenance-of-Way Association 8201 Corporate Drive, Suite 1125 Landover, MD 20785 01425-1 Standard References Werner Elem. ASCE American Society of Civil Engineers 345 East 47th Street New York, NY 10017 ASTM American Society of Testing and Materials 1916 Race Street Philadelphia, PA 19103 BOCA Building Officials and Code Administrators 17926 Halstead Homewood, IL 60430 CISPI Cast Iron Soil Pipe Institute CRSI Concrete Reinforcing Steel Institute 180 North LaSalle Street Chicago, IL 60601 CSI Construction Specifications Institute DIPRA Ductile Iron Pipe Research Associations EPA Environmental Protection Agency FEDSPEC Federal Specifications General Services Administration Specification and Consumer Information Distribution Branch Washington Navy Yard, Building 197 Washington, DC 20407 FEDSTDS Federal Standards (see FEDSPEC) ICBO International Conference of Building Officials 5360 South Workman Mill Road Whittier, CA 90601 MILSPEC Military Specifications Naval Publications and Forms Center 5801 Tabor Avenue Philadelphia, PA 19120 NIST National Institute of Standards and Technology NPC National Plumbing Code NSC National Safety Council 01425-2 Standard References OSHA Occupational Safety and Health Act U.S. Department of Labor Occupational and Health Administration San Francisco Regional Office 450 Golden Gate Avenue, Box 30617 PCA Portland Cement Association PCI Prestressed Concrete Institute PS Products Standards Section - U.S. Depart. of Commerce SSPC Steel Structures Painting Council SSPWC Standard Specifications for Public Works Construction Building News, Inc. 3055 Overhead Avenue Los Angeles, CA 90034 TCA Title Council of America UBC Uniform Building Code Published by ICBO UL Underwriter’s Laboratory 207 East Ohio Street Chicago, IL 60611 UMC Uniform Mechanical Code Published by ICBO UPC Uniform Plumbing Code Published by IAPMO PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01425-3 Standard References THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 01425-4 Standard References SECTION 01450 MATERIALS TESTING PART 1 1.01 1.02 SECTION INCLUDES A. Provide such equipment and facilities as are required for conducting field tests and for collecting and forwarding samples. Do not use any materials or equipment represented by samples until tests, if required, have been made and the materials or equipment found to be acceptable. Any product which becomes unfit for use after approval thereof shall not be incorporated into the work. B. Tests shall be made by an accredited testing laboratory selected by the OWNER. Except as otherwise provided, sampling and testing of all materials and the laboratory methods and testing equipment shall be in accordance with the latest standards and tentative methods of the American Society for Testing Materials (ASTM), and the American Association of Highway and Transportation Officials (AASHTO). C. Where additional or specific information concerning testing methods, sample sizes, etc., is required, such information is included under the applicable sections of the Specifications. Any modification of, or elaboration on, these test procedures which may be included for specific materials under their respective sections in the Specifications shall take precedence over these procedures. OWNER’S RESPONSIBILITIES A. 1.03 GENERAL The OWNER shall be responsible for and shall pay all costs in connection with the following materials testing: 1. Soils compaction tests. 2. Trench backfill. 3. Pipe and structural bedding. 4. Tests not called for by the Specifications of materials delivered to the site. 5. Concrete tests. 6. Asphalt pavement tests. CONTRACTOR’S RESPONSIBILITIES A. In addition to those inspections and tests called for in the General Conditions, CONTRACTOR shall also be responsible for preparing and submitting to OWNER a materials testing schedule for the project and coordinating all materials testing required for the following: 1. All retesting for work or materials found defective or unsatisfactory, including tests covered under 1.02 above. Werner Elem. 01450-1 Materials Testing 1.04 TRANSMITTAL OF TEST REPORTS Written reports of tests and engineering data furnished by CONTRACTOR for ENGINEER’s OWNER’s review of materials and equipment proposed to be used in the work shall be submitted as specified for Shop Drawings. The testing laboratory retained by the OWNER will furnish three (3) copies of a written report of each test performed by laboratory personnel in the field or laboratory. Two (2) copies of each test report will be transmitted to the ENGINEER OWNER and one (1) copy to the CONTRACTOR within seven (7) days after each test is completed. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01450-2 Materials Testing SECTION 01555 TRAFFIC REGULATION PART 1 1.01 1.02 SECTION INCLUDES A. Conformance: City of Fort Collins Traffic Control Regulations, Manual of Uniform Traffic Control Devices (U.S. Department of Transportation), or applicable statutory requirements of authority having jurisdiction. Fort Collins regulations take precedence over Manual of Uniform Traffic Control Devices. B. Operations on or about traffic areas and provisions for regulating traffic will be subject to the regulation of governmental agencies having jurisdiction over the affected areas. C. Keep traffic areas free of excavated material, construction equipment, pipe, and other materials and equipment. D. Keep fire hydrants and water control valves free from obstruction and available for use at all times. E. Conduct operations in a manner to avoid unnecessary interference with public and private roads and drives. TRAFFIC CONTROL PLAN A. 1.03 1.04 GENERAL If a Traffic Control Plan is provided in the Contract Documents, it is to be used as a guideline for the CONTRACTOR. The CONTRACTOR shall submit his own Traffic Control Plan for approval by the OWNER. Adjustments to the approved plan may be required by the OWNER based on actual traffic operation. FLAGMEN A. Required where necessary to provide for public safety, or the regulation of traffic, or by jurisdictional authorities. B. Shall be properly equipped and certified by ATSSA. WARNING SIGNS AND LIGHTS A. Provide barricades and warning signs for: 1. Open trenches and other excavations. 2. Obstructions, such as material piles, equipment (moving or parked), piled embankment. B. Illuminate by means of warning lights all barricades and obstructions from sunset to sunrise. C. Protect roads and driveways by effective barricades on which are placed acceptable warning signs. Werner Elem. 01555-1 Traffic Regulation D. 1.05 PARKING A. 1.06 Barricades and warning signs must be acceptable to the ENGINEER OWNER. The CONTRACTOR shall designate parking areas with the approval of the OWNER for the use of all construction workers and others performing work or furnishing services in connection with the project so as avoid interference with public traffic, OWNER's operations, or construction activities. ROADWAY USAGE BETWEEN OPERATIONS A. At all times when work is not actually in progress, CONTRACTOR shall make passable and shall open to traffic such portions of the project and temporary roadways or portions thereof as may be agreed upon between CONTRACTOR and OWNER and all authorities having jurisdiction over any properties involved. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01555-2 Traffic Regulation SECTION 01635 SUBSTITUTIONS AND PRODUCT OPTIONS PART 1 1.01 GENERAL SECTION INCLUDES A. Description 1. This section describes the procedure required by the CONTRACTOR for product substitutions. 2. Requests for Substitution 3. a. Base all bids on materials, equipment and procedures specified. b. Certain types of equipment and kinds of material are described in specifications by means of trade names and catalog numbers, and/or manufacturer’s names. Where this occurs, it is not intended to exclude from consideration such types of equipment and kinds of material bearing other trade names, catalog numbers and/or manufacturer’s names, capable of accomplishing purpose of types of equipment or kinds of material specifically indicated. c. Other types of equipment and kinds of material may be acceptable to the OWNER and ENGINEER. d. Types of equipment, kinds of material and methods of construction, if not specifically indicated must be approved in writing by ENGINEER and the OWNER. Submission of Requests for Substitution a. After Notice to Proceed, the OWNER/ENGINEER will consider written requests for substitutions of products, materials, systems or other items. b. The ENGINEER OWNER reserves the right to require substitute items to comply color and pattern-wise with base specified items, if necessary to secure “design intent”. c. Submit six (6) copies of request for substitution. Include in request: 1) Complete data substantiating compliance of proposed substitute with Contract Documents. 2) For products: i. Werner Elem. Product identification, including manufacturer’s name. 01635-1 Substitutions and Product Options 3) d. 4. Manufacturer’s literature, marked to indicate specific model, type, size, and options to be considered: Product description; performance and test data; reference standards; difference in power demand; dimensional differences for specified unit. iii. Name and address of similar projects on which product was used, date of installation, and field performance data. For construction methods: i. Detailed description of proposed method. ii. Drawings illustrating methods. 4) Itemized comparison of proposed substitution with product or method specified. 5) Data relating to changes in construction schedule. 6) Relation to separate contracts. 7) Accurate cost data on proposed substitution in comparison with product or method specified. In making request for substitution, or in using an approved substitute item, Supplier/Manufacturer represents. 1) He has personally investigated proposed product or method, and has determined that it is equal or superior in all respects to that specified and that it will perform function for which it is intended. 2) He will provide same guarantee for substitute item as for product or method specified. 3) He will coordinate installation of accepted substitution into work, to include building modifications if necessary, making such changes as may be required for work to be complete in all aspects. 4) He waives all claims for additional costs related to substitution which subsequently become apparent. Substitutions a. Werner Elem. ii. Request sufficiently in advance to avoid delay in construction. 01635-2 Substitutions and Product Options 5. 6. CONTRACTOR’s Option a. For products specified only by reference standards, select any product meeting standards by any manufacturer, indicate selected type in submission. b. For products specified by naming several products or manufacturers, select any product and manufacturer named, indicate selected type in submission. c. For products specified by naming one or more products, but indicating option of selecting equivalent products by stating “or equivalent” after specified product, CONTRACTOR must submit request, as required for substitution, for any product not specifically named. Rejection of Substitution or Optional Item a. Substitutions and/or options will not be considered if: 1) They are indicated or implied on shop drawings, or project data submittals, without formal request submitted in accordance with this section. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01635-3 Substitutions and Product Options THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 01635-4 Substitutions and Product Options SECTION 01650 MATERIAL DELIVERY, STORAGE, AND HANDLING PART 1 1.01 GENERAL SECTION INCLUDES A. Equipment, products and materials shall be shipped, handled, stored, and installed in ways which will prevent damage to the items. Damaged items will not be permitted as part of the work except in cases of minor damage that have been satisfactorily repaired and are acceptable to the ENGINEER OWNER. B. Pipe: Pipe and appurtenances shall be handled, stored, and installed as recommended by the manufacturer. Pipes with paint, tape coatings, linings or the like shall be stored to protect the coating or lining from physical damage or other deterioration. Pipe shipped with interior bracing shall have the bracing removed only when recommended by the pipe manufacturer. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01650-1 Material Delivery Storage, and Handling THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 01650-2 Material Delivery Storage, and Handling SECTION 01710 SITE CONDITIONS PART 1 1.01 GENERAL SECTION INCLUDES A. General 1. The CONTRACTOR acknowledges that he has satisfied himself as to the nature and location of the work, the general and local conditions, particularly those bearing upon access to the site; handling, storage, and disposal of materials; availability of water, electricity and roads; uncertainties of weather, river stages, or similar physical conditions at the site; the conformation and conditions of the ground; the equipment and facilities needed preliminary to and during the execution of the work; and all other matters which can in any way affect the work or the cost thereof under this Contract. 2. The CONTRACTOR further acknowledges that he has satisfied himself as to the character, quality and quantity of surface and subsurface materials to be encountered from his inspection of the site and from reviewing any available records of exploratory work furnished by the OWNER or included in these Documents. Failure by the CONTRACTOR to acquaint himself with the physical conditions of the site and all the available information will not relieve him from responsibility for properly estimating the difficulty or cost of successfully performing the work. 3. PART 2 2.01 The CONTRACTOR warrants that as a result of his examination and investigation of all the aforesaid data that he can perform the work in a good and workmanlike manner and to the satisfaction of the OWNER. The OWNER assumes no responsibility for any representations made by any of its officers or agents during or prior to the execution of this Contract, unless (1) such representations are expressly stated in the Contract, and (2) the Contract expressly provides that the responsibility therefore is assumed by the OWNER. PRODUCTS INFORMATION ON SITE CONDITIONS A. Werner Elem. Any information obtained by the ENGINEER regarding site conditions, subsurface information, groundwater elevations, existing construction of site facilities, and similar data will be available for inspection, as applicable, at the office of the ENGINEER upon request. Such information is offered as supplementary information only. Neither the ENGINEER nor the OWNER assumes any responsibility for the completeness or interpretation of such supplementary information. 01710-1 Site Conditions 1. 2. Differing Subsurface Conditions: a. In the event that the subsurface or latent physical conditions are found materially different from those indicated in these Documents, and differing materially from those ordinarily encountered and generally recognized as inherent in the character of work covered in these Contract Documents, the CONTRACTOR shall promptly, and before such conditions are disturbed, notify the ENGINEER OWNER in writing of such changed conditions. b. The ENGINEER OWNER will investigate such conditions promptly and following this investigation, the CONTRACTOR shall proceed with the work, unless otherwise instructed by the ENGINEER OWNER. If the ENGINEER OWNER finds that such conditions do so materially differ and cause an increase or decrease in the cost of or in the time required for performing the work, the ENGINEER OWNER will recommend to the OWNER the amount of adjustment in cost and time he considers reasonable. The OWNER will make the final decision on all Change Orders to the Contract regarding any adjustment in cost or time for completion. Underground Utilities: a. PART 3 3.01 Known utilities and structures adjacent to or encountered in the work are shown on the Drawings. The locations shown are taken from existing records and the best information available from existing utility plans, however, it is expected that there may be some discrepancies and omissions in the locations and quantities of utilities and structures shown. Those shown are for the convenience of the CONTRACTOR only, and no responsibility is assumed by either the OWNER or the ENGINEER OWNER for their accuracy or completeness. EXECUTION GENERAL A. Where the CONTRACTOR's operations could cause damage or inconvenience to railway, telegraph, telephone, television, oil, gas, electricity, water, sewer, or irrigation systems, the operations shall be suspended until all arrangements necessary for the protection of these utilities and services have been made by the CONTRACTOR. B. Notify all utility offices which are affected by the construction operation at least 48 hours in advance. Under no circumstances expose any utility without first obtaining permission from the appropriate agency. Once permission has been granted, locate, expose, and provide temporary support for all existing underground utilities. C. The CONTRACTOR shall protect all utility poles from damage. If interfering power poles, telephone poles, guy wires, or anchors are encountered, notify the ENGINEER OWNER and the appropriate utility company at least 48 hours in advance of construction operations to permit the necessary arrangements for protection or relocation of the interfering structure. D. The CONTRACTOR shall be solely and directly responsible to the owner and operators Werner Elem. 01710-2 Site Conditions of such properties for any damage, injury, expense, loss, inconvenience, delay, suits, actions, or claims of any character brought because of any injuries or damage which may result from the construction operations under this Contract. 3.02 E. Neither the OWNER nor its officers or agents shall be responsible to the CONTRACTOR for damages as a result of the CONTRACTOR's failure to protect utilities encountered in the work. F. If the CONTRACTOR while performing the Contract discovers utility facilities not identified in the Drawings or Specifications, he shall immediately notify the OWNER, utility, and the ENGINEER in writing. G. In the event of interruption to domestic water, sewer, storm drain, or other utility services as a result of accidental breakage due to construction operations, promptly notify the proper authority. Cooperate with said authority in the restoration of service as promptly as possible and bear all costs of repair. H. The CONTRACTOR shall replace, at his own expense, any and all other existing utilities or structures removed or damaged during construction, unless otherwise provided for in these Contract Documents or ordered by the ENGINEER OWNER. INTERFERING STRUCTURES A. 3.03 FIELD RELOCATION A. 3.04 The CONTRACTOR shall take necessary precautions to prevent damage to existing structures whether on the surface, aboveground, or underground. An attempt has been made to show major structures on the Drawings. The completeness and accuracy cannot be guaranteed, and it is presented simply as a guide to avoid known possible difficulties. During the progress of construction, it is expected that minor relocations of the work will be necessary. Such relocations shall be made only by direction of the ENGINEER OWNER. If existing structures are encountered that prevent the construction, and that are not properly shown on the Drawings, notify the ENGINEER OWNER before continuing with the construction in order that the ENGINEER OWNER may make such field revision as necessary to avoid conflict with the existing structures. If the CONTRACTOR shall fail to so notify the ENGINEER OWNER when an existing structure is encountered, and shall proceed with the construction despite the interference, he shall do so at his own risk. EASEMENTS A. Werner Elem. Where portions of the work are located on public or private property, easements and permits will be obtained by the OWNER. Easements will provide for the use of the property for construction purposes to the extent indicated on the easements. Copies of these easements and permits are available upon request to the OWNER. It shall be the CONTRACTOR's responsibility to determine the adequacy of the easement obtained in every case and to abide by all requirements and provisions of the easement. The CONTRACTOR shall confine his construction operations to within the easement limits or make special arrangements with the property owners or appropriate public agency for the additional area required. Any damage to property, either inside or outside the limits of the easements provided by the OWNER, shall be the responsibility of the CONTRACTOR as specified herein. The CONTRACTOR shall remove, protect, and 01710-3 Site Conditions replace all fences or other items encountered on public or private property. Before final payment will be authorized by the ENGINEER OWNER, the CONTRACTOR will be required to furnish the OWNER with written releases from property owners or public agencies where side agreements or special easements have been made by the CONTRACTOR or where the CONTRACTOR's operations, for any reason, have not been kept within the construction right-of-way obtained by the OWNER. B. 3.05 It is anticipated that the required easements and permits will be obtained before construction is started. However, should the procurement of any easement or permit be delayed, the CONTRACTOR shall schedule and perform the work around these areas until such a time as the easement or permit has been secured. LAND MONUMENTS A. The CONTRACTOR shall notify the ENGINEER OWNER of any existing Federal, State, Town, County, and private land monuments encountered. Private monuments shall be preserved, or replaced by a licensed surveyor at the CONTRACTOR's expense. When Government monuments are encountered, the CONTRACTOR shall notify the ENGINEER OWNER at least two (2) weeks in advance of the proposed construction in order that the ENGINEER OWNER will have ample opportunity to notify the proper authority and reference these monuments for later replacement. END OF SECTION Werner Elem. 01710-4 Site Conditions SECTION 01720 FIELD ENGINEERING AND SURVEYING PART 1 1.01 GENERAL SECTION INCLUDES A. Surveying: It shall be the responsibility of the CONTRACTOR to provide construction staking for horizontal and vertical alignment of the centerline, grading, and all appurtenant features of the work including all offset lines necessary for construction. The CONTRACTOR shall be responsible for staking the limits of construction. All construction surveying provided by the CONTRACTOR shall be completed under the supervision of a Colorado Registered Land Surveyor. The OWNER will provide the elevations and descriptions of the original and temporary project benchmarks. The OWNER will also provide two (2) additional benchmarks in a location within the limits of construction at the request of the CONTRACTOR. B. Supervision: The CONTRACTOR shall have supervision, knowledge of the project requirements and proper installation, and construction procedures, available in the field at all times that work is progressing. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01720-1 Field Engineering and Surveying THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 01720-2 Field Engineering and Surveying SECTION 01745 ENVIRONMENTAL CONTROLS PART 1 1.01 SECTION INCLUDES A. PART 2 2.01 GENERAL The work of this section consists of obtaining permits and providing environmental controls consistent with regulatory permits through the duration of the work required under this project. PRODUCTS MATERIALS A. Dust Control Dust control agents may be necessary in addition to wetting down with water. Dust control agents may be used only after prior approval by the OWNER. PART 3 3.01 3.02 DUST CONTROL APPLICATION A. The CONTRACTOR shall execute work by methods to minimize raising dust from construction operations. B. The CONTRACTOR shall provide and apply dust control at all times, including evenings, holidays and weekends, as required to abate dust nuisance on and about the site that is a direct result of construction activities. The use of non-approved chemicals, oil, or similar palliatives will not be allowed. Dust control agents may be used only after prior approval of the OWNER. The CONTRACTOR shall be required to provide sufficient quantities of equipment and personnel for dust control sufficient to prevent dust nuisance on and about the site. C. The OWNER will have authority to order dust control work whenever in its opinion it is required, and there shall be no additional cost to the OWNER. The CONTRACTOR shall be expected to maintain dust control measures effectively whether the OWNER or ENGINEER OWNER specifically orders such Work. PRESERVATION OF NATURAL FEATURES A. 3.03 EXECUTION Confine operations as much as possible. Exercise special care to maintain natural surroundings in an undamaged condition. Within the work limits, barricade trees, rock outcroppings, and natural features to be preserved. HOUSEKEEPING A. Werner Elem. Keep project neat, orderly, and in a safe condition at all times. Store and use equipment, tools, and materials in a manner that does not present a hazard. Immediately remove all rubbish. Do not allow rubbish to accumulate. Provide on- 01745-1 Environmental Controls site containers for collection of rubbish and dispose of it at frequent intervals during progress of work. 3.04 DISPOSAL A. Disposal of Waste (Unsuitable) Materials All material determined by the ENGINEER OWNER to be waste will be disposed of in approved landfill in a manner meeting all regulations. Dispose of waste materials, legally, at public or private dumping areas. Do not bury wastes inside of the limits of construction. All costs for dump fees, permits, etc., to be borne by the CONTRACTOR. B. Disposal of Garbage and Other Construction Materials Provide sanitary containers/dumpsters and haul away contents such that no overflow exists. 3.05 C. Excess excavation shall become the property of the CONTRACTOR and shall be legally disposed of by him outside the limits of construction to an approved disposal site. Excess excavated material suitable for backfill shall not be disposed of until all backfill operations are complete. D. The CONTRACTOR is to immediately inform ENGINEER OWNER of any hazardous materials encountered during construction. Dispose of waste materials legally at private or public facilities. BURNING A. 3.06 WATER CONTROL A. 3.07 No burning of debris will be permitted. The project work is subject to periodic flooding due to rainfall and snowmelt, flows from adjacent developed areas and storm water pipes and ground water flows from saturated soils or other ground water sources. The CONTRACTOR shall take all necessary steps to remove these flows from the work site. NOISE CONTROL A. Werner Elem. All mechanical equipment shall be equipped with the best available mufflers to reduce noise. The CONTRACTOR shall be responsible for obtaining any necessary permits and shall limit noise to the permitted levels. Noise level monitoring shall be performed by the CONTRACTOR as necessary to show that the permitted levels are not being exceeded. 01745-2 Environmental Controls 3.08 PERMITS A. All work must be performed in accordance with all applicable regulatory permits. 1. It shall be the responsibility of the CONTRACTOR to obtain a Construction Dewatering Permit from the Colorado State Health Department for any dewatering operations that will be discharged into any drainageways, open channels, or irrigation ditches. The CONTRACTOR shall be responsible for any testing required under the Construction Dewatering Permit. 2. It shall be the responsibility of the CONTRACTOR to submit a general permit application to the Colorado State Health Department for stormwater discharges associated with construction activity and to comply with all conditions of the permit. The CONTRACTOR shall also submit a Stormwater Management Plan for review by the OWNER. B. The OWNER Will Obtain the Following Permits, if applicable 1. Floodplain Use Permit 2. Larimer County Right-of-Way Permit 3. All Applicable Railroad Permits 4. Applicable 404 Permits It shall be the responsibility of the CONTRACTOR to prepare and obtain an approved Erosion and Sediment Control Plan from the OWNER. The CONTRACTOR must obtain all other applicable permits. END OF SECTION Werner Elem. 01745-3 Environmental Controls THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 01745-4 Environmental Controls SECTION 01780 CONTRACT CLOSEOUT PART 1 1.01 GENERAL SECTION INCLUDES A. The following project closeout procedure defines the responsibilities of the CONTRACTOR, OWNER, and ENGINEER in closing the project. Step 1: CONTRACTOR advises the ENGINEER OWNER in writing that he has reached "Substantial Completion" and provides a list of items to be completed or corrected. Closeout may be conducted by areas or portions of the work if requested by the OWNER. Step 2: ENGINEER OWNER inspects the work to determine if it is substantially complete, and issues a Certificate of Substantial Completion plus a "Punch List" of items to be completed or corrected. Substantial Completion - Definition 1. Reference General Conditions, Substantial Completion Step 3: CONTRACTOR completes and/or corrects all punch list items and notifies the ENGINEER in writing that his work is ready for final inspection. At this time, a final application for payment is submitted. Step 4: ENGINEER OWNER makes final inspection. When the work is found to be acceptable under the Contract Documents, and the Contract fully performed, the Engineer will issue a final Certificate for Payment. B. Final Paperwork: Prior to Final Payment and Acceptance, the CONTRACTOR shall deliver the following items to the ENGINEER OWNER: CONTRACTOR's Two Year Guarantee of Materials and Workmanship. All Guarantees, Warranties and Submittals, as specified. Receipts for Extra Materials Delivered to the OWNER. Final Application for Payment. Consent of Surety to Final Payment. CONTRACTOR's Affidavit of Release of Liens. Releases from Property Owners for Special Easements. Project Record Documents. Red-lined as-built drawings. Werner Elem. 01780-1 Contract Closeout C. Definitions 1. Substantial Completion for South Bus Maintenance Facility Parking/Driving Surface and Site Improvement Project shall be defined as the completion of all asphalt pavement, concrete driveway, concrete entrance ramp, pans, curb and gutter, sidewalk, bus canopy pavement, bus canopy wheel stops, and pavement striping. The parking lots, driveways, and bus canopies must be open to all vehicular traffic. 2. Final Completion shall be defined as the completion of all Work including cleanup, Project Record Documents shall be turned over to the OWNER, all punch list items completed, and all processing of all change orders. The Work must be ready for final payment and acceptance. PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION (Not Applicable) END OF SECTION Werner Elem. 01780-2 Contract Closeout DIVISION 2 – SITE WORK SECTION 02220 REMOVAL OF STRUCTURES AND OBSTRUCTIONS SECTION 02315 EXCAVATION AND EMBANKMENT SECTION 02340 FLY ASH STABILIZATION SECTION 02360 EROSION AND SEDIMENT CONTROL SECTION 02710 AGGREGATE BASE COURSE SECTION 02740 ASPHALT PAVEMENT SECTION 02770 SIDEWALK, CURB AND GUTTER, AND MISCELLANEOUS CONCRETE SECTION 02220 REMOVAL OF STRUCTURES AND OBSTRUCTIONS PART 1 1.01 GENERAL SECTION INCLUDES A. This work consists of the removal and disposal of trees, slope and ditch protection, abandoned utility services, curb, gutter, pipes, sidewalk, appurtenances, fences, signs, foundations, pavements, pavement markings, and any other obstructions that are not designated or permitted to remain. It shall also include salvaging, stockpiling and loading salvable materials, sandblasting, plugging structures, cleaning culverts, and sawing and cutting to facilitate controlled breaking and removal of concrete and asphalt to a neat line. Except in areas to be excavated, the resulting trenches, holes, and pits shall be backfilled. Materials removed and not designated to be salvaged or incorporated into the work shall become the property of the CONTRACTOR. 1.02 RELATED SECTIONS A. Section 02315 – Excavation and Embankment PART 2 PRODUCTS (Not Applicable) PART 3 EXECUTION 3.01 CONSTRUCTION REQUIREMENTS A. General: The CONTRACTOR shall raze, remove, and dispose of all structures and obstructions which are identified on the project, except utilities, structures and obstructions removed under other contractual agreements or as otherwise provided for in the Contract Documents, and salvable material designed to remain the property of the OWNER. B. Salvable Material: All salvable material designated in the Contract or by the ENGINEER OWNER to remain the property of the OWNER shall be removed without damage, in sections or pieces which may be readily transported, and shall be stockpiled by the CONTRACTOR at specified locations within the project limits. The CONTRACTOR shall safeguard salvable materials and shall be responsible for the expense of repairing or replacing damaged or missing material until it is incorporated into the work, or is loaded onto the OWNER’s equipment by the CONTRACTOR. C. Signs and Traffic Signals: Removal of signs shall include removal of posts, footings, pedestals, sign panels, and brackets. Concrete adhering to salvable sign posts shall be removed. Removal of sign panel shall include removal of the panel and its attachment hardware from the existing installation and adjusting the spacing of the remaining panels. Werner Elem. 02220-1 Removal of Structures and Obstructions The removal of traffic signal items shall include poles, mast arms, signal heads, span wires, footings, all attachment hardware, and other incidental materials. Removal of signal pole or pedestal pole shall include pole, span wire, cable, signal heads, overhead sign support wire, footings, and pedestrian push buttons. Removal of traffic signal controller and cabinet shall include removal of the footing and all auxiliary equipment contained within the cabinet. D. Pavements, Sidewalks, and Curbs: All concrete pavements, sidewalks, structures, curbs, gutters, etc., designated for removal, shall be disposed of off-site by the CONTRACTOR at his expense. Sawing of concrete and asphalt shall be done to a true line, with a vertical face, unless otherwise specified. The minimum depth of a saw cut shall be 2 inches. For reinforced concrete, the minimum depth shall be 2 inches, or to the depth of the reinforcing steel, whichever occurs first. END OF SECTION Werner Elem. 02220-2 Removal of Structures and Obstructions SECTION 02315 EXCAVATION AND EMBANKMENT PART 1 1.01 SECTION INCLUDES A. 1.02 1.03 This work shall consist of excavation, embankment fill, disposal of excess material, shaping, and compaction of all material encountered within the limits of work, including excavation and fill for structures. The excavation shall include, but is not limited to, the native soils which must be excavated for the project work. All work shall be completed in accordance with these Specifications and the lines and grades on the Drawings. DEFINITIONS A. Unclassified Excavation shall consist of the excavation of all materials of whatever character required of the work, obtained within the right-of-way. B. Muck Excavation shall consist of the removal of mixtures of soils and organic matter not suitable for foundation material and replacement with approved material. C. Rock Excavation shall consist of igneous, metamorphic and sedimentary rock which cannot be excavated without the use of rippers, and all boulders or other detached stones each having a volume of 1/2 cubic yard or more, as determined by physical or visual measurement. It shall also include replacement with approved material as required. D. Embankment Material shall consist of approved material acquired from excavation or from outside sources, hauled and placed in embankments. DESCRIPTION A. 1.04 GENERAL This work shall consist of excavation, disposal, placement, and compaction of all material encountered within the limits of the work, and not being completed under some other item, necessary for the construction of the project in accordance with the Specifications and the lines, grades, and typical cross-sections shown on the Drawings. All excavation will be classified, “unclassified excavation”, or “muck excavation” or “rock excavation”, as hereafter described. All embankment will be classified “embankment material” as hereafter described. QUALITY ASSURANCE A. Werner Elem. Final topography and/or cross-sections will be surveyed of areas that are to finished grade and compared to the design section for accuracy. Final grade shall match design grades within the tolerances discussed in PART 3 EXECUTION. 02315-1 Excavation and Embankment PART 2 2.01 MATERIALS A. Embankment material may consist of approved material acquired from excavations or material hauled from outside the project limits. Suitable material identified on-site shall be used first for embankments and backfill. Excess excavated native soils which are not used as embankment or backfill shall become the property of the CONTRACTOR and shall be disposed of off-site by the CONTRACTOR, in a location acceptable to the ENGINEER OWNER. B. Muck excavation shall also include the replacement of excavated muck with uniformly graded rock, riprap, on-site or imported soils, or other material whichever is most suitable for the specific situation encountered. The ENGINEER OWNER will determine which type of aggregate or other material which shall be used after observing the specific site conditions. PART 3 3.01 PRODUCTS EXECUTION GENERAL EXCAVATION/EMBANKMENT A. General: The excavation and embankment for the project work should be finished to reasonably smooth and uniform surfaces. Variation from the subgrade plane shall not be more than .08 feet in soil or more than .08 feet above or .50 below in rock. Where bituminous or concrete surfacing materials are to be placed directly on the subgrade, the subgrade plane shall not vary more than 0.04 feet. Materials shall not be wasted without permission of the ENGINEER OWNER. Excavation operations shall be conducted so that material outside of the limits of slopes will not be disturbed. Prior to beginning grading operations in any area, all necessary clearing and grubbing in that area shall have been performed in accordance with Section 02230 of these Specifications. The CONTRACTOR shall notify the ENGINEER OWNER in sufficient time before beginning excavation or embankment such that the necessary topography and/or cross-sections may be taken. The CONTRACTOR shall not excavate beyond the dimensions and elevations established, and material shall not be removed prior to surveying the site. When the CONTRACTOR’s excavating operations encounter remains of pre-historic people’s dwelling sites or artifacts of historical or archaeological significance, the operations, shall be temporarily discontinued. The ENGINEER OWNER will contact archaeological authorities to determine the disposition thereof. When directed, the CONTRACTOR shall excavate the site in such a manner as to preserve the artifacts encountered and shall remove them for delivery to the custody of the proper state authorities. Such excavation will be considered and paid for as extra work. Werner Elem. 02315-2 Excavation and Embankment B. Excavation: 1. Unclassified: All excess suitable material excavated from the project site and not used for embankment shall be removed from the project site and become the property of the CONTRACTOR. Where material encountered within the limit of the work is considered unsuitable for embankment (fills) on any portion of this project work, such material shall be excavated as directed by the ENGINEER OWNER and replaced with suitable fill material. All unsuitable excavated material from excavation consisting of any type of debris (surface or buried), excavated rock, bedrock or rocks larger than 6 inches in diameter and boulders shall be hauled from the project site and disposed of by the CONTRACTOR at his expense. Debris is defined as “anything that is not earth which exists at the job site”. 2. Muck: Where excavation to the finished grade section results in a subgrade or slopes of unsuitable soil, the ENGINEER OWNER may require the CONTRACTOR to remove the unsuitable materials and backfill to the finished graded section with approved material. Disposal of the material shall be at the CONTRACTOR’s expense. Good surface drainage shall be provided around all permanent cuts to direct surface runoff away from the cut face. 3. C. Rock: Unless otherwise specified, rock shall be excavated to a minimum depth of 0.5 feet below subgrade within the limits of the channel area, and the excavation shall be backfilled with material shown on the Drawings or as designated by the ENGINEER OWNER. Disposal of material and replacement with suitable approved material shall be at the CONTRACTOR’s expense. Embankment Construction: Embankment construction shall consist of constructing all fill areas, including preparation of the areas upon which they are to be placed, the placing and compacting of approved material within areas where unsuitable materials have been removed, the preparation of subgrade for pavement, and the placing and compacting of embankment material in holes, pits and other depressions within the project area. Only approved materials shall be used in the construction of embankments and backfills. Approved materials shall consist of clean on-site cohesive soils or approved imported soils. On-site materials should not be used without the approval of the ENGINEER OWNER if select material is called for in the Drawings. On-site cohesive soils are suitable for use as compacted fill provided the following recommendations are met: Percent Finer by Weight (ASTM C136) Gradation ½-Inch 3/8-Inch No. 4 Sieve No. 200 Sieve Werner Elem. 02315-3 100 70 – 100 50 – 100 60 (min) Excavation and Embankment • • • Liquid Limit Plasticity Index In-Situ Coefficient of Permeability 35 (max) 20 (max) 1x10-6 cm/sec (min) On-site cohesive soils or imported soils should be placed and compacted in horizontal lifts, using equipment and procedures that will produce recommended moisture contents and densities throughout the lift and embankment height. On-site or imported cohesive soils should be compacted within a moisture content range of 2% below, to 2% above optimum moisture content and compacted to 95% of the Maximum Standard Proctor Density (ASTM D698). When embankment is to be placed and compacted on hillsides, or when new embankment is to be compacted against existing embankments, or when embankment is built 1/2 width at a time, the slopes that are steeper than 4:1 when measured longitudinally or at right angles to the adjacent ground shall be continuously benched over those areas where it is required as the work is brought up in layers. Benching shall be well keyed and where practical a minimum of 8 feet. Each horizontal cut shall begin at the intersection of the original ground and the vertical sides of the previous cuts. Material thus cut out shall be recompacted along with the new embankment material at the CONTRACTOR’s expense. The ground surface underlying all fills shall be carefully prepared by removing all organic matter, scarification to a depth of 8 inches and recompacting to 95% of the Maximum Standard Proctor Density (ASTM D698) at optimum moisture content + or - 2% prior to fill placement. Embankment material shall be placed in horizontal layers not exceeding 8 inches (loose measurement) and shall be compacted to 95% of the Maximum Standard Proctor Density (ASTM D698) at optimum moisture content + or - 2%. Effective spreading equipment shall be used on each lift to obtain uniform thickness prior to compacting. As the compaction of each layer progresses, continuous leveling and manipulating will be required to assure uniform density. For embankments which serve as berms, the downstream portion shall be “keyed” into the subsurface soils a minimum of 3 feet to enhance the stability of the slope. Materials which are removed from excavations beneath the water table may be over the optimum moisture content and will require that they be dried out prior to reusing them. Cross hauling or other action as appropriate will be ordered when necessary to insure that the best available material is placed in critical areas of embankments, including the top 2 feet of all embankments. No additional payment will be made for cross hauling ordered by the ENGINEER OWNER. Frozen materials shall not be used in construction of embankments. During the construction of the channels, the channel bottom shall be maintained in such condition that it will be well drained at all times. Excavation or Embankment (Fill), and Structural Backfill work either completed or in a stage of completion that is either eroded or washed away or becomes unstable Werner Elem. 02315-4 Excavation and Embankment due to either rains, snow, snow melt, channel flows or lack of proper water control shall be either removed and replaced, recompacted or reshaped as directed by the ENGINEER OWNER and in accordance with the Drawings and Specifications at the CONTRACTOR’s sole expense. Removed unsuitable materials shall be hauled away and disposed of at the CONTRACTOR’s expense. Placing of replacement materials for removed unsuitable materials shall be purchased, placed and compacted at the CONTRACTOR’s expense. D. Proof rolling with a heavy rubber tired roller will be required, if designated on the Drawings or when ordered by the ENGINEER OWNER. Proof rolling shall be done after specified compaction has been obtained. Areas found to be weak and those areas which failed shall be ripped, scarified, wetted if necessary, and recompacted to the requirements for density and moisture at the CONTRACTOR’s expense. Proof rolling shall be done with equipment and in a manner acceptable to the ENGINEER OWNER. Proof rolling as shown on the Drawings or as ordered by the ENGINEER OWNER shall not be measured and paid for separately, but shall be included in the unit prices bid for the work. 3.02 EXCAVATION AND BACKFILL FOR STRUCTURES A. Poor foundation material for any of the work shall be removed, by the CONTRACTOR, as directed by the ENGINEER OWNER. The CONTRACTOR will be compensated for removal and replacement of such materials in accordance with Muck Excavation. The CONTRACTOR is cautioned that construction equipment may cause the natural soils to pump or deform while performing excavation work inside and on footings, structural floor slabs, or other structure foundation areas. Foundation materials which are: a) saturated by either surface or subsurface flows due to the lack of adequate water control or dewatering work by the CONTRACTOR; b) frozen for any reason; or, c) that are disturbed by the CONTRACTOR’s work or caused to become unacceptable for foundation material purposes by means of the CONTRACTOR’s equipment, manpower, or methods of work shall be removed and replaced by the CONTRACTOR at his expense. Dewatering should not be conducted by pumping from inside footing, structural floor slab, or other structure foundation limits. This may decrease the supporting capacity of the soils. Care should be taken when excavating the foundations to avoid disturbing the supporting materials. Excavation by either hand or careful backhoe soil removal, may be required in excavating the last few inches of material to obtain the subgrade of any item of the concrete work. Any over-excavated subgrades that are due to the CONTRACTOR’s actions, shall be brought back to subgrade elevations by the CONTRACTOR and at his expense in the following manner: 1. Werner Elem. For over-excavations of 2 inches or less, either: Backfill and compact with an approved granular materials; backfill with 1/2 inch crushed rock; or fill within concrete at the time of the appurtenant structure concrete pour. 02315-5 Excavation and Embankment 2. For over-excavations greater than 2 inches, backfill and compact with an approved granular material. All granular footings, structural floor slabs, or other structure areas shall be compacted with a vibratory plate compactor prior to placement of concrete, reinforcing, or bedding materials. Backfill, and fill within 3 feet of, or adjacent to, all structures and for full height of the walls, shall be selected non-swelling material. It shall be granular, well graded, and free from stones larger than 2 inches. Material may be job excavated, but selectivity will be required as determined by the ENGINEER OWNER. Stockpiled material, other than topsoil from the excavation shall be used for backfilling unless an impervious structural backfill is specified. The backfill material shall consist of either clean on-site granular materials free of stones larger than 2 inches in diameter with no more than 20% passing the No. 200 sieve, or equivalent imported materials. All backfill around the structures shall be consolidated by mechanical tamping. The material shall be placed in 6-inch loose lifts within a range of 2% above to 2% below the optimum moisture content and compacted to 95% of Maximum Standard Proctor Density (ASTM D698) for cohesive soils, or to 75% relative density for pervious material as determined by the relative density of cohesionless soils test, ASTM D4253. When specified on the Drawings or as required by the ENGINEER OWNER, Class I structural backfill shall meet the following gradation requirements: % by Weight Passing Square Mesh Sieves Sieve Size 2-Inch No. 4 No. 50 No. 200 100 30 - 100 10 – 60 5 – 20 In addition, this material shall have a liquid limit not exceeding 35 and a plasticity index of not over 6. Impervious structural backfill, where shown or specified, shall consist of material having 100% finer than 2 inches in diameter and a minimum of 30% passing a No. 200 U.S. Standard Sieve. The material shall be placed in 6-inch loose lifts within a range of 2% above to 2% below the optimum moisture content and compacted to 95% of Maximum Standard Proctor Density for cohesive soils as determined by ASTM D698. END OF SECTION Werner Elem. 02315-6 Excavation and Embankment SECTION 02340 FLY ASH STABILIZATION PART 1 1.01 GENERAL SECTION INCLUDES This section covers treating the subgrade, existing subbase or existing base by pulverization, adding Class "C" fly ash, mixing and compacting of the mixed material to the required density. This item applies to natural ground or embankment and shall be constructed as specified herein and in conformity with the typical sections, lines and grades as shown on the plans or as established by the Engineer. 1.02 RELATED SECTIONS A. 1.03 SUBMITTALS A. PART 2 2.01 Section 02740 – Asphalt Pavement The CONTRACTOR shall cooperate with the ENGINEER OWNER in obtaining and providing samples of all specified materials. The CONTRACTOR shall submit certified laboratory test certificates for all items required in this section. PRODUCTS MATERIALS A. Fly Ash Fly ash shall meet ASTM Specification 618, Section 3.2, when sampled and tested in accordance with Sections 4, 6 and 8, unless otherwise shown on the plans. Fly ash shall be of the Class "C" designation containing a minimum of 25 percent CaO. B. Water The water used in the stabilized mixture shall be clean, clear, free of sewage, vegetable matter, oil, acid and alkali. Water known to be potable may be used without testing. All other sources shall be tested in accordance with AASHTO T-26 and approved by the ENGINEER OWNER. 2.02 EQUIPMENT A. The machinery, tools and equipment necessary for proper prosecution of the work shall be on the project site and approved by the ENGINEER OWNER prior to the beginning of construction operations. All machinery, tools and equipment used shall be maintained in a satisfactory and workmanlike manner. B. Fly ash shall be stored and handled in closed weatherproof containers until immediately before distribution on the road. If storage bins are used, they shall be completely enclosed. Werner Elem. 02340-1 Fly Ash Stabilization C. If fly ash is furnished in trucks, each truck shall have the weight of fly ash certified on public scales or the Contractor shall place a set of standard platform truck scales or hopper scales at a location approved by the ENGINEER OWNER. PART 3 3.01 GENERAL A. 3.02 EXECUTION It is the primary purpose of this specification to secure a completed course of treated material which contains a uniform fly ash/soil mixture with no loose or segregated areas; has a uniform density and moisture content; is well bound for its full depth; and, has a smooth surface suitable for placing subsequent courses. It shall be the responsibility of the Contractor to regulate the sequence of his work; to process a sufficient quantity of material to provide full depth as shown on plans; to use the proper amounts of fly ash; to maintain the work; and, to rework the courses as necessary to meet the above requirements. PREPARATION OF SUBGRADE A. Before other construction operations are begun, the subgrade shall be graded and shaped to enable the fly ash treatment of materials in place, in conformance with the lines, grades, and thickness shown on the plans. Unsuitable soil or materials shall be removed and replaced with acceptable material. The subgrade shall be firm and able to support, without displacement, the construction equipment and the compaction hereinafter specified. Soft or yielding subgrade shall be corrected and made stable by scarifying, adding fly ash, and compacting until it is of uniform stability. If the Contractor elects to use a cutting and pulverizing machine that will remove the subgrade material accurately to the secondary grade and pulverize the material at the same time, he will not be required to expose the secondary grade nor windrow the material. However, the Contractor shall be required to roll the subgrade, as directed by the ENGINEER OWNER, before using the pulverizing machine and correct any soft areas that this rolling may reveal. This method will be permitted only where a machine is provided which will ensure that the material is cut uniformly to the proper depth and which has cutters that will plane the secondary grade to a smooth surface over the entire width of the cut. The machine shall be of such design that visible indication is given at all times that the machine is cutting to the proper depth. 3.03 APPLICATION A. Werner Elem. The fly ash shall be spread by an approved spreader at the rates shown on the plans or as directed by the ENGINEER OWNER. A motor grader shall not be used to spread the fly ash. The fly ash shall be distributed at a uniform rate and in such manner as to reduce the scattering of fly ash by wind to a minimum. Fly ash shall not be applied when wind conditions, in the opinion of the ENGINEER OWNER, are such that blowing fly ash becomes objectionable to traffic or adjacent property owners. 02340-2 Fly Ash Stabilization 3.04 MIXING A. The soil and fly ash shall be thoroughly mixed by approved rotary mixers or other approved equipment, and the mixing continued until, in the opinion of the ENGINEER OWNER, a homogeneous, friable mixture of soil and fly ash is obtained, free from all clods or lumps. Initial mixing after the addition of fly ash will be accomplished dry or with a minimum of water to prevent fly ash balls. Water required to achieve the specified moisture content for the mixture should be added after initial mixing. If the soil fly ash mixture contains clods, they shall be reduced in size by raking, blading, disking, harrowing, scarifying or the use of other approved pulverization methods so that when all nonslaking aggregates retained on the No. 4 sieve are removed, the remainder of the material shall meet the following requirements when tested at the field moisture condition or dry by laboratory sieves: Minimum Passing 1-3/4 inch sieve Minimum Passing No. 4 sieve 100 percent 60 percent During final mixing, water shall be added to the materials as directed by the ENGINEER OWNER, until the proper moisture content has been secured. Water shall be added through the pulverizing machine or other method acceptable to the ENGINEER OWNER to develop a uniform, controlled rate addition of the needed moisture. Final moisture content of the mix, prior to compaction, shall not exceed the optimum moisture content of the mix by more than 2 percent nor by less than the optimum by more than 4 percent. Should the natural moisture content of the soil be above the specified range, aeration of the soil may be required prior to addition of the fly ash. 3.05 COMPACTION A. Compaction of the mixture shall begin immediately after final mixing of the fly ash and be completed within one hour following addition of fly ash and water. The material shall be sprinkled as necessary to maintain the optimum moisture. Compaction of the mixture shall begin at the bottom and shall continue until the entire depth of mixture is uniformly compacted to a specified density. All non-uniform (too-wet, too dry or insufficiently treated) areas which appear shall be corrected immediately by scarifying the areas affected, adding or removing material as required and reshaping the recompacting by sprinkling and rolling. The surface of the course shall be maintained in a smooth condition, free from undulations and ruts, until other work is placed thereon or the work is accepted. The stabilized section shall be compacted to the extent necessary to provide the density specified below: Description For fly ash treated subgrade, existing subbase or existing base that will receive subsequent subbase or base courses Werner Elem. 02340-3 Not less than 95 percent maximum dry density (ASTM D-698) Fly Ash Stabilization For fly ash treated subbase or base that will receive surface course Not less than 98 percent maximum dry density (ASTM D-698) In addition to the requirements specified for density, the full depth of the material shown on the plans shall be compacted to the extent necessary to remain firm and stable under construction equipment. After each section is completed, the ENGINEER OWNER will make tests as necessary. If the material fails to meet the density requirements, the ENGINEER OWNER may require it to be reworked as necessary to meet those requirements or require the Contractor to change his construction methods to obtain required density on the next section. Throughout this entire operation the shape of the course shall be maintained by blading, and the surface, upon completion, shall be smooth and in conformity with the typical section shown on the plans and to the established lines and grades. Blading should be terminated within two hours after blending of the fly ash. Should the material, due to any reason or cause, lose the required stability, density and finish before the next course is placed or the work is accepted, it shall be reprocessed, recompacted and refinished at the sole expense of the Contractor. Reprocessing shall follow the same pattern as the initial stabilization, including the addition of fly ash. 3.06 FINISHING, CURING AND PREPARATION FOR SURFACING A. After the final layer or course of the treated subgrade, subbase or base has been compacted, it shall be brought to the required lines and grades in accordance with the typical sections. 1. The resulting base surface shall be thoroughly rolled with a pneumatic tire roller and "clipped", "skinned" or "tight bladed" by a power grader to a depth of approximately 1/4 inch, removing all loosened stabilized material from the section. Recompaction of the loose material should not be attempted. The surface shall then be thoroughly compacted with the pneumatic roller, adding small increments of moisture as needed during rolling. If plus No. 4 aggregate is present in the mixture, one complete coverage of the section with the fat wheel roller shall be made immediately after the "clipping" operation. When directed by the ENGINEER OWNER, surface finishing methods may be varied from this procedure provided a dense, uniform surface, is produced. The moisture content of the surface material must be maintained within the specified range during all finishing operations. Surface compaction and finishing shall proceed in such a manner as to produce, in not more than two hours, a smooth, closely knit surface, free of cracks, ridges or loose material conforming to the crown, grade and line shown on the plans. 2. After the fly ash treated course has been finished as specified herein, the surface shall be protected against rapid drying by either of the following curing methods for a period of not less than three days or until the surface or subsequent courses are placed: a. Werner Elem. Maintain in a thorough and continuously moist condition by sprinkling. 02340-4 Fly Ash Stabilization Werner Elem. b. Apply a two-inch layer of earth on the completed course and maintain in a moist condition. c. Apply an asphalt membrane to the treated course, immediately after same is completed. The quantity and type of asphalt approved for use by the ENGINEER OWNER shall be sufficient to completely cover and seal the total surface of the base between crown lines and all voids. If the Contractor elects to use this method, it shall be the responsibility of the contractor to protect the asphalt membrane from being picked up by traffic by either sanding or dusting the surface of same. The asphalt membrane may remain in place when the proposed surface or other base courses are placed. Asphaltic emulsions are not acceptable for the asphaltic membrane. 02340-5 Fly Ash Stabilization THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 02340-6 Fly Ash Stabilization SECTION 02360 EROSION AND SEDIMENT CONTROL PART 1 1.01 1.02 SECTION INCLUDES A. This work shall consist of temporary measures needed to control erosion and water pollution. These temporary measures shall include, but not be limited to, berms, dikes, dams, sediment basins, fiber mats, netting, gravel, mulches, grasses, slope drains and other erosion control devices or methods. These temporary measures shall be installed at the locations where needed to control erosion and water pollution during the construction of the project, and as directed by the ENGINEER OWNER, and as shown on the Drawings. B. The Erosion Control Plan presented in the Drawings were reviewed and approved by the OWNER and serves as a minimum for the requirements of erosion control during construction. The CONTRACTOR has the ultimate responsibility for providing adequate erosion control and water quality throughout the duration of the project. Therefore, if the provided plan is not working sufficiently to protect the project areas, then the CONTRACTOR shall provide additional measures as required to obtain the required protection. The CONTRACTOR shall include in his bid price for erosion control a minimum of all items shown on the Erosion Control Plan and any additional items that may be needed to control erosion and water pollution. SUBMITTALS A. Construction schedule for Erosion Control per subsection 3.01 B. Sequencing Plan per subsection 3.12 PART 2 2.01 GENERAL PRODUCTS MATERIALS A. Materials may include hay bales, straw, fiber mats, fiber netting, wood cellulose, fiber fabric, gravel and other suitable materials, and shall be reasonably clean, free of deleterious materials, and certified weed free. All materials shall be submitted for approval prior to installation. B. Temporary grass cover (if required) shall be a quick growing species suitable to the area, which will provide temporary cover and will not later compete with the grasses sown for permanent cover. All grass seed shall be approved by the ENGINEER OWNER prior to installation. C. Fertilizer and soil conditioners shall be approved by the ENGINEER OWNER prior to installation. Werner Elem. 02360-1 Erosion and Sediment Control PART 3 3.01 3.02 EXECUTION CONSTRUCTION REQUIREMENTS A. When so indicated in the Contract Documents, or when directed by the ENGINEER OWNER, the CONTRACTOR shall prepare construction schedules for accomplishing temporary erosion control work. These schedules shall be applicable to clearing and grubbing, grading, structural work, construction, etc. He shall also submit for acceptance his proposed method of erosion control on haul roads and borrow pits and his plan for disposal of waste material. Work shall not be started until the erosion control schedules and methods of operations have been accepted. B. The CONTRACTOR will be required to incorporate all permanent erosion control features into the project at the earliest practicable time as outlined in his accepted schedule. Temporary erosion control measures will then be used to correct conditions that develop during construction. C. The erosion control features installed by the CONTRACTOR shall be adequately maintained by him until the project is accepted. D. In the event of conflict between these requirements and erosion and pollution control laws, rules, or regulations of other Federal, State or local agencies, the more restrictive laws, rules, or regulations shall apply. PERMITS AND COMPLIANCE A. If necessary, the CONTRACTOR must apply for and obtain a Construction Dewatering Permit from the Colorado Department of Health. All costs for this permit shall be the responsibility of the CONTRACTOR. This permit requires that specific actions be performed at designated times. The CONTRACTOR is legally obligated to comply with all terms and conditions of the permit including testing for effluent limitations. The CONTRACTOR shall also apply for and obtain a stormwater discharge permit for construction activities, if applicable. The CONTRACTOR shall comply with and pay for any and all requirements set forth in the permit. The CONTRACTOR shall allow the Colorado Department of Health or other representatives to enter the site to test for compliance with the permit. Non compliance with the permit can result in stoppage of all work. In addition to permit requirements, the OWNER shall also monitor the CONTRACTOR’s erosion control and work methods. If the overall function and intent of erosion control is not being met, then the OWNER shall require the CONTRACTOR to provide additional measures as required to obtain the desired results. Costs for any additional erosion control measures shall be the responsibility of the CONTRACTOR, since he has the ultimate responsibility for providing adequate erosion control and water quality for the duration of the project. Werner Elem. 02360-2 Erosion and Sediment Control 3.03 STABILIZATION OF DISTURBED AREAS A. 3.04 PROTECTION OF ADJACENT PROPERTIES A. 3.05 OF SEDMENT AND EROSION CONTROL Sediment barriers, perimeter dikes, and other measures intended to either trap sediment or prevent runoff from flowing over disturbed areas must be constructed as a first step in grading and be made functional before land disturbance takes place. Earthen structures such as dams, dikes, and diversions must be stabilized within 5 days of installation. Stormwater outlets must also be stabilized prior to any upstream land disturbing activities. All on-site stormwater conveyance channels used by the CONTRACTOR for temporary erosion control purposes shall be designed and constructed with adequate capacity and protection to prevent erosion during storm and runoff events. Stabilization adequate to prevent erosion shall also be provided at the outlets of all pipes and channels. STORM SEWER INLET PROTECTION A. 3.08 STABILIZATION STABILIZATION OF WATERWAYS AND OUTLETS A. 3.07 Properties adjacent to the site of a land disturbance shall be protected from sediment deposition. In addition to the erosion control measures required on the Drawings, perimeter controls may be required if damage to adjacent properties is likely. Perimeter controls include, but are not limited to, a vegetated buffer strip around the lower perimeter of the land disturbance, sediment barriers such as straw bales and silt fences; sediment basins; or a combination of such measures. Vegetated buffer strips may be used only where runoff in sheet flow is expected and should be at least 20 feet in width. TIMING AND MEASURES A. 3.06 Temporary sediment control measures shall be established within 5 days from time of exposure/disturbance. Permanent erosion protection measures shall be established within 5 days after final grading of areas. All storm sewer inlets which are made operable during construction or which drain stormwater runoff from a construction site shall be protected from sediment deposition by the use of filters. WORKING IN OR CROSSING WATERCOURSES AND WETLANDS A. Construction vehicles should be kept out of watercourses to the extent possible. Where in-channel work is necessary, precautions must be taken to stabilize the work area during construction to minimize erosion. The channel (including bed and banks) must always be restabilized immediately after in-channel work is completed. B. Where a live (wet) watercourse must be crossed by construction vehicles during construction, a Temporary Stream Crossing must be provided for this purpose. Werner Elem. 02360-3 Erosion and Sediment Control 3.09 CONSTRUCTION ACCESS ROUTES A. 3.10 DISPOSITION OF TEMPORARY MEASURES A. 3.11 At the time specified in the Contract Documents, and subject to compliance with specified materials and installation requirements, the CONTRACTOR will receive a Substantial Completion Certificate for temporary erosion control measures. MAINTENANCE OF EROSION CONTROL MEASURES AFTER SUBSTANTIAL COMPLETION A. 3.15 The CONTRACTOR shall submit a sequencing plan for approval for erosion control in conformance with his overall Construction Plan for approval by the OWNER. Changes to the Erosion Control Sequencing Plan may be considered by the OWNER only if presented in writing by the CONTRACTOR. SUBSTANTIAL COMPLETION OF EROSION CONTROL MEASURES A. 3.14 All temporary and permanent erosion and sediment control practices must be maintained and repaired as needed to assure continued performance of their intended function. SEQUENCING A. 3.13 All temporary erosion and sediment control measures shall be disposed of within 30 days after final site stabilization is achieved or after the temporary measures are no longer needed as determined by the OWNER. Trapped sediment and other disturbed soil areas resulting from the disposition of temporary measures shall be permanently stabilized to prevent further erosion. MAINTENANCE A. 3.12 Wherever construction vehicles enter or leave a construction site, a Stabilized Construction Entrance is required. Where sediment is transported onto a public road surface, the roads shall be cleaned thoroughly at the end of each day. Sediment shall be removed from roads by shoveling or sweeping and be transported to a sediment controlled disposal area. Street washing shall be allowed only after sediment is removed in this manner. The CONTRACTOR will be responsible for maintaining temporary erosion control measures as specified in the Drawings and Contract Documents until such time as the disturbed drainage area has stabilized as determined by the ENGINEER and the OWNER. FINAL COMPLETION AND ACCEPTANCE OF EROSION CONTROL MEASURES A. After the ENGINEER OWNER has determined that the drainage area has stabilized, the CONTRACTOR shall remove all remaining temporary erosion control measures. Any damage to the site shall be repaired to the satisfaction of the ENGINEER OWNER and at no cost to the OWNER. END OF SECTION Werner Elem. 02360-4 Erosion and Sediment Control SECTION 02710 AGGREGATE BASE COURSE PART 1 1.01 GENERAL SECTION INCLUDES A. 1.02 The worked to be performed includes the preparation of the aggregate base course foundation; the production, stockpiling, hauling, placing and compacting aggregate base course. RELATED SECTIONS A. 1.04 Section 02315 – Excavation and Embankment SUBMITTALS A. PART 2 2.01 The CONTRACTOR shall cooperate with the ENGINEER in obtaining and providing samples of all specified materials. The CONTRACTOR shall submit certified laboratory test certificates for all items required in this section. PRODUCTS MATERIALS A. Aggregates: Aggregates for bases shall be crushed stone, crushed slag, crushed gravel or natural gravel that conforms to the quality requirements of AASHTO M 147 except that the requirements for the ratio for the minus No. 200 sieve fraction to the minus No. 40 sieve fraction shall not apply. The requirements for the Los Angeles wear test shall not apply to Class 1, 2 and 3. Aggregates for bases shall meet the grading requirements as called out in the Drawings. The liquid limit shall be as shown in the table and the plasticity index shall be ≤ 6. B. Gradations: Werner Elem. 02710-1 Aggregate Base Course Sieve Designation 4 inch 3 inch 2 1/2 inch 2 inch 1 1/2 inch Note: 2.02 Percentage by Weight Passing Square Mesh Sieves LL < 35 Class 1 Class 2 Class 3 --100 ----95 --100 100 ----95 ----100 ------- 1 inch --- --- --- 3/4 inch No. 4 No. 8 No. 200 --30 - 65 --3 - 15 ------3 - 15 ------20 max. Class 4 ----- LL < 30 Class 5 Class 6 --------- 100 100 ----- ----- ----- 90 100 --- 100 --- --- 95 100 --30 - 70 --3 - 15 --- 100 100 30 - 65 25 - 55 3 - 12 ----20 - 85 5 – 15 50 - 90 30 - 50 --3 - 12 Class 3 materials shall consist of bank or pit run material. EQUIPMENT A. General: Equipment shall be capable of legally performing the work as described in this Specification. Equipment that is inadequate to obtain the results specified shall be replaced or supplemented as required to meet the requirements of this Specification. Any equipment that is used in an improper manner may be cause for rejection of the work if in the opinion of the ENGINEER the work fails to meet the requirements of this specification. Equipment used for compaction shall be the rolling type, vibratory type, or combination of both types, and shall be of sufficient capacity to meet the compaction requirements herein. PART 3 3.01 EXECUTION PREPARATION OF FOUNDATION A. The foundation shall be considered to be the finished earth subgrade, subbase course, or base course, as the case may be, upon which any subbase, base or surface course is to be constructed. Preparation of foundation for construction of a subbase, base, or surface course shall consist of the work necessary to restore, correct, strengthen or prepare the foundation to a condition suitable for applying and supporting the intended course. For aggregate base course roads and parking areas, the top six-inches of topsoil shall be stripped within the area to be aggregate surfaced. Following stripping of the topsoil, the upper 12 inches of the subgrade shall be scarified and compacted to a minimum of 95% of the Maximum Standard Proctor Density (ASTM D698). Werner Elem. 02710-2 Class 7 ----- Aggregate Base Course On-site material may be used as accepted by the ENGINEER, for compacted fill for the aggregate base course. Fill shall be placed within 2% of optimum moisture content and compacted to a minimum of 95% of the Maximum Standard Proctor Density (ASTM D698). Aggregate base course used as a foundation for pavements shall be placed on the subgrade within two percent of optimum moisture and compacted to a minimum of 95% of the Maximum Standard Proctor Density (ASTM D698). The top six inches of topsoil shall be stripped within the area to be aggregate surfaced. Following stripping of the topsoil, the upper 12 inches of the subgrade shall be scarified and compacted to a minimum of 95% of the Maximum Standard Proctor Density (ASTM D698). On-site material may be used, as accepted by the ENGINEER, for compacted fill for the aggregate base course. Fill shall be placed within 2% of optimum moisture content and compacted to a minimum of 95% of the Maximum Standard Proctor Density (ASTM D698). Deviations in aggregate base course under pavements of more than 1/4 inch in 10 feet, measured with a 10-foot straight edge, shall be corrected prior to pavement construction. The foundation shall be prepared and constructed such that it will have a uniform density throughout. It shall be brought to the required alignment and cross section with equipment and methods adapted for the purpose. Upon completion of the shaping and compacting operations, the foundation shall be smooth, at the required density, and at the proper elevation and contour to receive the aggregate base course. After the specified compaction has been obtained, the subgrade under the curb, gutter, sidewalk and pavement shall be proof-rolled with a heavily loaded rubber tire roller, fully loaded water truck, or other approved equipment. Those areas which produce a rut depth of over ½ inch or which crack the subgrade after pumping and rebounding shall be ripped, scarified, wetted or dried if necessary, and recompacted to the requirements for density and moisture at the CONTRACTOR’S expense. Where unsuitable material is encountered, the ENGINEER may require the CONTRACTOR to remove the unsuitable materials and backfill to the finished grade with approved material. The completed subgrade shall be proof-rolled again after placement of approved material. Unless otherwise provided, all holes, ruts and other depressions in the foundation shall be filled with materials similar to those existing in the foundation. High places shall be excavated and removed to the required lines, grade and section. Base course material shall not be placed on a foundation that is soft, spongy, or one that is covered by ice or snow. Base course shall not be placed on a dry or dusty foundation where the existing condition would cause rapid dissipation of moisture from the base course material and hinder or preclude its proper compaction. Dry foundations shall have water applied and reworked and compacted as necessary. The ENGINEER shall direct the CONTRACTOR to make minor adjustments in the finish grade from that shown in the Drawings as may be necessary or desirable to maintain the characteristics of a stabilized foundation by minimizing the amount of cutting into or filling. Werner Elem. 02710-3 Aggregate Base Course 3.02 EARTH SUBGRADE A. 3.03 When the foundation is an earth subgrade it shall be prepared by removing all vegetation, excavating and removing materials, filling depressions, scarifying, shaping, smoothing and compacting to meet the required grade, section and density. Stones over six inches in greatest dimension shall be removed. PLACEMENT A. The aggregate base course shall be constructed to the width and section shown in the Drawings. If the required compacted depth of base coarse exceeds six inches, the base shall be constructed in two or more layers of approximate equal thickness. The maximum compacted thickness of any one layer shall not exceed six inches. Each layer shall be constructed as far in advance of the succeeding layer as the ENGINEER may direct. The work shall, in general, proceed from the point on the project nearest the point of supply of the aggregate in order that the hauling equipment may travel over the previously placed material, and the hauling equipment shall be routed as uniformly as possible over all portions of the previously constructed courses or layers of the base course. The material shall be deposited on the soil foundation, or previously placed layer in a manner to minimize segregation and to facilitate spreading to a uniform layer of the required section. In the event that blending of materials is necessary to provide required gradation and properties of the material, and is done in the roadway, the same shall be accomplished by mixing the aggregate and blending material by means of blade graders, discs, harrows or other equipment to effect a uniform distribution and gradation throughout the finished mixture. Excessive mixing and grading that will cause segregation between the coarse and fine materials is prohibited. 3.04 COMPACTION A. After a layer or course has been placed and spread to the required thickness, width and contour, it shall be compacted. If the material is too dry to readily attain the required density, it shall be uniformly moistened to the degree necessary during compaction operations for proper compaction. B. Compaction of each layer shall continue until the required density of Section 3.01 is reached. The surface of each layer shall be maintained during compaction operations in such a manner that a uniform texture is produced and aggregates firmly keyed. All areas where proper compaction is not obtainable due to segregation of materials, excess fines, or other deficiencies in the aggregate, shall be reworked as necessary or the material removed and replaced with aggregates that will meet this specification. The surface of each layer shall be kept true and smooth at all times. 3.05 MIXING Werner Elem. 02710-4 Aggregate Base Course A. General: Unless otherwise specified, the CONTRACTOR shall mix the aggregate by any one of the three following methods. 1. Stationary Plant Method: Aggregate base course and water shall be mixed in an approved mixer. After mixing the aggregate shall be transported to the project site while it contains the proper moisture content and shall be placed on the roadbed by means of an approved spreader. 2. Travel Plant Method After the material for each layer has been placed through an aggregate spreader or windrow sizing device, it shall be uniformly mixed by a traveling mixing plant. 3. Road Mix Method After material for each layer has been placed, the materials shall be mixed while at an optimum moisture content by motor graders or other approved equipment until the mixture is uniform throughout. 3.06 SHOULDER CONSTRUCTION A. Shoulders shall be constructed with base course material to conform to the elevation and section shown in the Drawings. No equipment shall be used which by its design or through its manner of operation that will damage the pavement or curbs. Insofar as practicable, the base course material shall be placed directly on the shoulder area. Materials that are deposited outside the shoulder area, if not contaminated, shall be recovered and placed within the required limits. The CONTRACTOR will not be compensated for materials not recovered as determined by the ENGINEER. Materials shall not be deposited on the pavement or surfacing during placing unless specifically permitted by the ENGINEER. Werner Elem. 02710-5 Aggregate Base Course The base course material as placed shall be spread and compacted to the required density in layers not exceeding six inches in compacted thickness. Any material inadvertently placed on the pavement shall be broomed from the pavement. The result shall not effect a change in the gradation of the shoulder material. END OF SECTION Werner Elem. 02710-6 Aggregate Base Course SECTION 02740 ASPHALT PAVEMENT PART 1 1.01 SECTION INCLUDES A. 1.02 Section 02340 – Fly Ash Stabilization QUALITY ASSURANCE A. Test samples will be taken in the field by the OWNER’s independent testing service. Mix designs and material samples are to be submitted for review at least 4 weeks prior to material placement. All sampling and testing shall be done in accordance with the latest methods of AASHTO, unless otherwise specified. B. When placing the asphalt trench patch, saw cutting of the existing asphalt will not be permitted within the wheel path of a travel lane. All asphalt patches shall conform to the specifications outlined in the City of Fort Collins Design and Construction Standards for Streets of Public Right-of-way, “Construction Details” section. PART 2 2.01 This section covers paving of all new and existing asphalt surfaces. Existing pavement is to be replaced with similar material as herein set forth. RELATED SECTIONS A. 1.03 GENERAL PRODUCTS MATERIALS A. Cationic Emulsified Asphalt: The cationic emulsified asphalt for the tack coat shall be CSS-1h and shall meet the requirements of AASHTO M 208 (ASTM C 2397). B. Aggregate for Hot Plant Mix Bituminous Pavement: 1. Description – The asphaltic concrete surface shall consist of a mineral aggregate, uniformly mixed with asphalt cement. 2. Materials: a. Crushed Gravel: The crushed gravel shall consist of clean, hard, durable particles which have been crushed to the gradations shown in Table 1 (in accordance with the Colorado Department of Transportation Standard Specifications for Road and Bridge Construction). Aggregates for hot plant mix bituminous pavement shall be of uniform quality, composed of clean, hard, durable particles of crushed stone, crushed gravel, natural gravel, or crushed slag. Excess of fine material shall be wasted before crushing. For Gradings S, SX, and SG, a percentage of the aggregate retained on the 4.75 mm. (No. 4) sieve shall have at least two mechanically induced fractured Werner Elem. 02740-1 Asphalt Pavement faces when tested in accordance with Colorado Procedure 45. This percentage will be provided by the ENGINEER OWNER. The angularity of the fine aggregate shall be a minimum of 45.0% when determined according to CP L-5113, Method A. Aggregate samples representing each aggregate stockpile shall be non-plastic if the percent of aggregate passing the Number 4 sieve is greater than or equal to 10 percent by weight of the individual aggregate sample. Plasticity will be determined in accordance with AASHTO 90. Reclaimed material shall be of uniform quality. The maximum size of the reclaimed asphalt pavement shall be 38 mm (1 1/2 inches) prior to introduction into the mixer. The maximum aggregate size contained in the combination of reclaimed asphalt pavement and new aggregate shall not exceed the maximum specified in Table 1. The hot bituminous pavement shall not contain more than 15 percent reclaimed asphalt pavement. The material shall not contain clay balls, vegetable matter, or other deleterious substances. The aggregate for Gradings S, SX, and SG shall have a percentage of wear of 45 or less when tested in accordance with AASHTO T 96. TABLE 1 MASTER RANGE TABLE FOR HOT BITUMINOUS PAVEMENT Sieve Size Percent by Weight Passing Square Mesh Sieves Grading S Grading SG Grading SX 100 100 90 – 100 90 – 100 100 * * 90 – 100 * * * * * * 23 – 49 19 – 45 28 – 58 37.5 mm (1 1/2”) 25.0 mm (1”) 19.0 mm (3/4”) 12.5 mm (1/2”) 9.5 mm (3/8”) 4.75 mm (#4) 2.36 mm (#8) 1.18 mm (#16) * * * 600 μm (#30) 300 μm (#50) 150 μm (#100) 2–8 1–7 2 –10 75 μm (#200) * These additional Form 43 Screens will initially be established for the Contractor’s Quality Control Testing using values from the As Used Gradation shown on the Design Mix. The crushed gravel shall show no detrimental amount of stripping when tested as follows: A test sample consisting of the aggregate and bitumen to be used in the paving mixture shall be mixed at the temperature specified herein. The sample shall then be spread in a loose, thin layer and allowed to air-season for 24 hours before testing. A portion of the sample, not over ½ of the capacity of the Werner Elem. 02740-2 Asphalt Pavement jar, shall be placed in a glass jar and completely covered with distilled water. The jar shall be fitted with a tight screw cap and allowed to stand for a period of 24 hours. The jar shall be vigorously shaken for a period of 15 minutes and the sample of the mixture shall then be examined for stripping. If stripping occurs, the aggregate shall be rejected or an approved method of treating shall be specified to change the material from a hydrophilic to a hydrophobic state as directed by the ENGINEER OWNER. Superpave Performance Graded Binders. Superpave Performance Graded Binders shall conform to the requirements listed in Table 2. The oil to be used shall be Performance Graded Binder 64-22. TABLE 2 SUPERPAVE PERFORMANCE GRADED BINDERS Requirement for PG Binder 58-22 58-28 58-34 64-22 64-28 70-28 76-28 AASHTO Test No. 230 230 230 230 230 230 230 T 28 3 3 3 3 3 3 3 TP 48 58 58 58 64 64 70 76 TP 5 - - - - 50 - - T 51 Toughness, joules (inch-lbs) - - - - - - Tenacity, joules (inch-lbs) - - - - - - *CP L2210 *CP L2210 T 240 1.00 1.00 1.00 1.00 1.00 1.00 1.00 T 240 58 58 58 64 64 70 76 TP 5 - - - - - 50 50 *CP L2211 Method A - - - - 20*** - - T 51 Property Original Binder Properties Flash Point Temp., °C, minimum Viscosity at 135 °C, Pa●s, maximum Dynamic Shear, Temp. °C, where G*/Sin δ @ 10 rad/s ≥ 1.00 kPa Ductility, 4 °C (5 cm/min.), cm minimum 12.4 (110) 8.5 (75) RTFO Residue Properties Mass Loss, percent maximum Dynamic Shear, Temp. °C, where G*/Sin δ @ 10 rad/s ≥ 2.20 kPa Elastic Recovery, 25 °C, percent min. Ductility, 4 °C (5 cm/min.), cm minimum PAV Residue Properties, Aging Temperature 100 °C Dynamic Shear, Temp. °C, where G*●Sin δ @ 10 rad/s ≤ 5000 kPa Creep Stiffness, @ 60 s, Test Temperature in °C S, maximum, MPa m-value, minimum **Direct Tension, Temperature in °C, @ 1 mm/min., where failure strain ≥ 1.0 % PP 1 22 19 16 25 22 25 28 TP 5 -12 -18 -24 -12 -18 -18 -18 300 300 300 300 300 300 300 TP 1 0.300 0.300 0.300 0.300 0.300 0.300 0.300 TP 1 -12 -18 -24 -12 -18 -18 -18 TP 3 *Colorado Procedure **Direct tension measurements are required when needed to show conformance to AASHTO MP 1. ***If the PG 64-28 RTFO residue fails the ductility test, the binder will be accepted if the TFO residue (AASHTO T 179) has a ductility of 25 cm or more. Werner Elem. 02740-3 Asphalt Pavement 2.02 PAVING PLANT REQUIREMENT A. Werner Elem. General Requirements: 1. Uniformity: The plants shall be so designed, coordinated and operated as to produce a mixture within the job mix tolerances as covered in paragraph 2.03C under “Preparation and Composition of the Mixture.” 2. Equipment for Preparation of Asphalt: Tanks for storage of asphalt shall be capable of heating the material, under effective and positive control at all times, to temperature requirements set forth in the Specifications. Heating shall be accomplished by steam coils, electricity, or other means such that no flame shall come in contact with the heating tank. A circulating system for the asphalt shall be provided of adequate size to ensure the property and continuous circulation between storage tank and mixer during the entire operating period. All pipelines and fittings shall be steam jacketed or other properly insulated to prevent heat loss. Storage tank capacity shall be sufficient for at least one day’s run. 3. Dryer: A rotary dryer of any satisfactory design for drying and heating the mineral aggregates shall be provided. The dryer shall be capable of drying and heating the mineral aggregate to the temperature requirements set forth in the Specifications. 4. Screens: Plant screens, capable of screening all aggregates to the size required for proportioning, and having normal capacities slightly in excess of the full capacity of the mixer, shall be provided. The mesh of the screens shall be approved by the ENGINEER OWNER before paving operations. 5. Bins: The plant shall include a minimum of 3 dry aggregate storage bins with the total capacity of not less than 3 times the dead load capacity of the mixer. Each bin shall be provided with an overflow pipe that shall be of such size and at such locations as to prevent any backing up of material into other bins. Each bin shall have a suitable convenient means for sampling. The sampling openings shall be subject to the approval of the ENGINEER OWNER. 6. Thermometric Equipment: An armored thermometer reading from 200F to 500F shall be fixed in the asphalt feed line at a suitable location from the discharge valve at the mixer unit. The plant shall be further equipped with an approved dial scale mercury actuated thermometer, an electric pyrometer, or other approved thermometric instrument so placed at the discharge chute of the dryer as to register automatically or indicate the temperature of the heated aggregate. 7. Dust Collectors: When plants are located in any vicinity where dust may be objectionable, or when dust interferes with the efficient operation of the plant, proper housing, mixer covers, dust collecting systems shall be installed. Provision shall be made to waste the material so collected or to return it uniformly to the mixture as the ENGINEER OWNER may direct. 02740-4 Asphalt Pavement 8. B. Safety Equipment: Adequate and safe stairways to the mixer platform and guarded ladders to other plant units shall be placed at all points required for accessibility to all plant operations. All gears, pulleys, chains, sprockets, and other dangerous moving parts shall be thoroughly guarded and protected. Ample and unobstructed passage shall be maintained at all times in and around the truck loading space. This space shall be kept free from drippings from the mixing platform. Special Requirements of Batch Plants: 1. Plant Scale: Scales for any weight box or hopper may be either of the beam or springless dial type and shall be a standard make and design, sensitive to ½ of 1% of the maximum load that may be required. When of the beam type, there shall be a separate beam with telltale indicator for each size aggregate and a tare beam for balancing the hopper. 2. Control of Mixing Time: The plant shall be equipped with an approved means to govern the time of mixing and to maintain it. 3. Weight Box or Hopper: The equipment shall include a means for accurately weighing each bin size to hold a full batch without hand raking or running over. The weight box or hopper shall be supported on fulcrums and knife edges so constructed that they will not be easily thrown out of alignment or adjustment. Gates on both bins and hopper shall be so constructed as to prevent leakage when they are closed. 4. Asphalt Bucket: The asphalt bucket which is used for weighing the asphalt cement shall have sufficient capacity to hold not less than 10% of the weight of aggregate required for one batch. It shall be steam jacketed or equipped with properly insulated electric heat units and shall be suspended on dial scales or beam scales equipped with a telltale indicator so that the tare weight of asphalt cement can be measured accurately to within 2% above or below the weight required. The bucket shall be so arranged that it will deliver the molten asphalt cement in a thin uniform sheet or in multiple streams the full width of the mixer. 5. Mixer Unit: The plant shall include a batch mixer of an approved twin pugmill type or rotary drum type and shall be capable of producing a uniform mixture within the job mix tolerances fixed by these Specifications. It shall have a batch capacity of not less than 2,000 pounds. If of the pugmill type, worn or improper pugmill paddles will not be permitted. A mechanical batch counter shall be installed and shall be so designed as to register upon only the actuation of the asphalt bucket release and to preclude the register of any material through the operation of pulling bins. Werner Elem. 02740-5 Asphalt Pavement C. Special Requirements for Continuous Mixing Plants: 1. Gradation Control Unit: The plant shall include a means of accurately proportioning each bin size of aggregate either by weighing or by volumetric measurement. When gradation control is by volume, the unit shall have an accurately controlled individual gate to form an orifice for volumetrically measuring the material drawn from each respective bin compartment. Indicators shall be provided on each gate to show the gate opening in inches. 2. Weight Calibration or Aggregate Feed: The plant shall include a means for calibration of gate openings by means of weight test samples. The materials fed out of the bins through individual orifices shall be bypassed to a suitable test box, each compartment material confined in a separate box section. The plant shall be equipped to handle conveniently such test samples weighting up to 800 pounds and to weigh them on accurate scales. 3. Synchronization of Aggregate and Asphalt Feed: Satisfactory means shall be provided to afford positive interlocking control between the flow of aggregate from the bins and the flow of asphalt from the meter or other proportioning sources. This control shall be accomplished by interlocking mechanical means or any positive method under the control of the ENGINEER OWNER. 4. Mixer Unit for Continuous Method: The plant shall include a continuous mixer of an approved twin pugmill type, and shall be capable of producing a uniform mixture within the job mix tolerance fixed by these Specifications. The paddles shall be of a type adjustable for angular position on the shafts and reversible to retard the flow of the mix. The mixer shall carry a manufacturer’s plate giving the net volumetric contents of the mixer at the several heights inscribed on a permanent gauge and also giving the rate of feed of aggregate per minute at plant operating speed. Unless otherwise required, determination of mixing time shall be by weight methods under the following formula. The weights shall be determined for the job by tests made by the ENGINEER OWNER. Mixing time in seconds = Pugmill dead capacity in pounds Pugmill output in pounds/seconds The mixing time shall be approved by the ENGINEER OWNER. 2.03 PREPARATION OF MATERIAL A. Preparation of Asphalt Cement: The asphalt cement shall be heated at the paving plant to a temperature not exceeding 325F. The penetration of the asphalt cement shall be maintained within the limits of penetration specified through the period of use. B. Preparation of Mineral Aggregates: The mineral aggregates shall be dried and heated at the paving plant so that when delivered to the mixer, they shall be at as Werner Elem. 02740-6 Asphalt Pavement low a temperature as is consistent with proper mixing and laying, and in no case to exceed 350F. They may be fed simultaneously into the same drier but in all cases, immediately after heating, they shall be screened into three or more bins. The screen sizes shall be approved by the ENGINEER OWNER prior to the start of construction. C. Preparation and Composition of the Mixture: Each size of hot aggregate, the mineral filler and the asphalt cement shall be measured separately and accurately to the proportions in which they are to be mixed. After the hot aggregate and mineral filler have been charged into the mixer and thoroughly mixed as directed by the ENGINEER OWNER, the asphalt cement shall be added and the mixing continued for a period of at least 20 seconds, or longer if necessary, to produce a homogeneous mixture, in which all particles of the mineral aggregates are coated uniformly. The constituents of the surface course shall be combined in such proportions to produce a mixture conforming to the gradations shown in Table 1. All mix furnished for the project shall conform to within the range of tolerances shown in Table 3. TABLE 3 MIX TOLERANCES Bitumen Content Asphalt Recycling Agent Temperature of Mixture When Discharged from Mixer ±0.3% ±0.2% ±10°C 1 Hot Bituminous Pavement Passing the 9.5 mm (3/8 inch) and larger sievers ±6% 2 Passing the 4.75 mm (No. 4 and 2.36 mm (No. 8 sieves) ±5% 2 Passing the 600 μm (No. 30) sieve ±4% 2 Passing the 75 μm (No. 200) sieve ±2% 1 When 100% passing is designated, there shall be no tolerance. When 90-100% passing is designated, 90% shall be the minimum; no tolerance shall be used. 2 These tolerances apply to the Contractor’s Quality Control Testing. 2 Superpave Performance Graded Binders shall conform to the requirements listed in Table 4 at 75 gyrations. Werner Elem. 02740-7 Asphalt Pavement TABLE 4 MIX DESIGN CRITERIA AT OPTIMUM OIL Property Asphalt Content (%) Voids @ N (INI) Voids @ N (DES) Voids @ N (MAX) V.M.A. (%) % Voids Filled Tensile Strength Retention Dry Tensile Strength (psi) Mixing Temperature Compaction Temperature D. PART 3 3.01 3.02 Specification +/-0.3% 11 Min. 3%-5% 2 Min. 14 Min. 65%-78% 80 Min. 30 Min. 325 Deg. F 300 Deg. F Paving Plant Inspection: For the verification of weights or proportions and character of materials and determination of temperatures used in the preparation of the mixture, the ENGINEER OWNER or his authorized representative shall have access at any time to all parts of the paving plant. EXECUTION SURFACE PREPARATION A. All final pavement cuts shall be made in straight lines using saw cut. Initial pavement cuts may be made using wheel cut or other suitable method. B. Prior to placing the prime coat, the base course shall be thoroughly cleaned. Loose material shall be removed from the existing surface as directed by the ENGINEER OWNER. PRIME COAT A. Werner Elem. All previously prepared bases or existing surface shall be primed with a cationic emulsified asphalt in accordance with the requirements of these Specifications, and at the locations that are shown on the Plans or as directed by the ENGINEER OWNER. The prime coat shall be placed by means of an approved pressure distributor. Before application, the asphaltic oil shall be heated as directed by the ENGINEER OWNER. However, it shall not be heated to more than 180F. In general, the rate of application shall be from 0.25 to 0.35 gallons per square yard as directed by the ENGINEER OWNER. The prime coat shall be carefully applied, particularly around curbs and sidewalks. If excessive amounts of curb, sidewalks, or other structures are sprayed with asphaltic oil, they shall be cleaned as directed by the ENGINEER OWNER at the CONTRACTOR’s expense. All vertical contact faces shall be primed by painting with cationic emulsified asphaltic oil. 02740-8 Asphalt Pavement 3.03 ASPHALTIC CONCRETE SURFACE A. Transportation of Mixture: The mixture shall be transported from the paving plant to the work in vehicles equipped with tight metal compartments previously cleaned of all foreign materials. When directed by the ENGINEER OWNER, the compartments shall be sufficiently insulated and each load shall be covered with canvas or other suitable materials of sufficient size to protect it from weather conditions. The inside surface of all vehicle compartments used for hauling mixture must be lightly lubricated with a tin oil or soap solution just before loading, but excess lubricant will not be permitted. No load shall be sent out so late in the day as to interfere with spreading and compacting the mixture during daylight unless artificial light, satisfactory to the ENGINEER, is provided. B. General Conditions: The mixture shall be laid only when the base is dry and only when weather conditions are suitable. The mixture shall be laid when atmospheric temperatures are consistent with the placement temperature limitations as outlined in Table 5. Asphalt shall not be placed when frost exists in the subgrade. Any material laid shall be rolled with pneumatic rollers in addition to the specified rolling, as directed by the ENGINEER OWNER. C. Placing Asphalt Mixture: If traffic is allowed to use the prepared subgrade or sub-base, the subgrade or sub-base shall be checked and corrected as needed immediately ahead of placing bituminous materials. Prior to placement of the bituminous surface, the base shall be cleaned of all dirt or other foreign matter. When the new pavement abuts the old pavement, the Contractor shall cut the old pavement as directed by the Engineer and paint the edge of the pavement with a tack coat. TABLE 5 PLACEMENT TEMPERATURE LIMITATIONS Compacted Layer Thickness, in mm (inches) Minimum Air and Surface Temperature, °C(°F) Top Layer of Payment Note (1) 15 (60) 10 (50) Note (2) 20 (70) 15 (60) Layers Below Top Layer Note (1) 10 (50) 5 (40) Note (2) 15 (60) 10 (50) 25(1) or less >25 to 75 (1 to 3) >75 (3) --0 (30) 5 (40) Notes: Air Temperature is taken in the shade. Surface is defined as the existing base on which the new pavement is to be placed. (1) Temperatures to be used when mix contains unmodified asphalt cement (PG 5828, PG 58-22, PG 64-22). Temperatures to be used with PG 76-28, PG 70-34, PG 64-28 and Pg 58-40. (2) Temperature to be used when mix contains AC-20R [AC-20 (Rubberized)]. The asphaltic pavement shall be placed only when the base is stable and weather conditions are suitable. The asphaltic pavement shall have a density of ninetytwo percent (92%) to ninety-six percent (96%) of the maximum theoretical Werner Elem. 02740-9 Asphalt Pavement density, determined according to Colorado Procedure 51. Field density determinations will be made in accordance with Colorado Procedure 44 or 81. While the surface is being compacted and finished, the Contractor shall carefully trim the outside edges of the pavement to the proper alignment. Unless otherwise permitted by the ENGINEER OWNER, the mixture shall be spread by means of a mechanical self-powered paver, capable of spreading the mixture true to the line, grade, and crown set by the ENGINEER OWNER. Pavers shall be equipped with hoppers and distributing screws of the reversing type to place the mixture evenly in front of adjustable screeds. The mixture shall be dumped in the center of the hoppers and care exercised to avoid overloading and spilling over of the mixture upon the base. Pavers shall operate when laying mixtures at such speed between 10 feet and 20 feet per minute, as may be decided by the ENGINEER OWNER. Pavers shall be equipped with a quick and efficient steering device and shall have forward and reverse speeds of not less than 100 feet per minute. Unless operating on fixed side forms, pavers shall employ mechanical devices such as equalizing runners, straightedge runners, evener arms, or other compensating devices to adjust the grade and confine the edges of the mixture to true lines within the use of stationary side forms. The pavers shall be capable of spreading the mixtures, without segregation, in thickness of from ½ inch to 3 inches, to a maximum width of 10 feet in increments of 1 foot or less and to a minimum width of 8 feet. They shall be equipped with blending or joint leveling devices for smoothing and adjusting all longitudinal joints between adjacent strips of courses of the same thickness. When asphalt concrete pavement thickness in excess of 2 inches is called for, they shall be laid in separate courses of not less than 1 inch or more than 2 inches or as directed by the ENGINEER OWNER. The term “screed” includes a “strike-off” device operating by cutting, crawling, or other practical action which is effective on the mixture at a workable temperature without tearing, shoving, or gouging and which produces a finished surface of the evenness and texture specified. The screed shall be adjustable as to level and shall have an indicating level attached. Longitudinal and transverse joints shall be made in a careful manner. Well bonded and sealed joints are required. If necessary to obtain this result, joints shall be painted with cationic emulsified asphaltic cement. In making the joint along any adjoining edges such as curb, gutter, or an adjoining pavement and after the hot mixture is placed by the finished machine, just enough of the hot material shall be carried back to fill any space left open. This joint shall be properly “set” up with the back of rake at proper height and level to receive the maximum compression under rolling. The work of “setting up” this joint shall be performed always by competent workmen who are capable of making correct, clean, and neat joints. Immediately after any course is screeded, and before roller compaction is started, the surface shall be checked, any inequalities adjusted, all fat, sandy accumulations from the screed removed by a rake or hoe, and all fat spots in any Werner Elem. 02740-10 Asphalt Pavement course removed and replaced with satisfactory material. Irregularities in alignment and grade along the outside edge shall also be corrected by the addition or removal of mixture before the edge is rolled. In narrow, deep, or irregular sections, intersections, turnouts, or driveways where it is impractical to spread and finish the mixtures by machine methods, the CONTRACTOR may used approved spreading equipment or acceptable hand methods as directed by the ENGINEER OWNER. When the mixture is to be spread by hand, upon arrival on the work it shall be dumped upon a steel dump board outside the area on which it is to be spread. Immediately thereafter it shall be distributed into place by means of hot shovels and spread with hot rakes in a loose layer of uniform density and correct depth. Tines of the rakes shall not be less than ½ inch longer than the loose depth of the mixture, and spaces between tines shall not be less than the maximum diameter of aggregate particle except that in no case should the spaces be less than 1 inch. Loads shall not be dumped any faster than can be properly handled by the shovelers. The shovelers shall not distribute the dumped load faster than it can be properly handled by the rakers. The rakers will not be permitted to stand in the hot mixture while raking it, except where necessary to correct errors in the first raking. The raking must be carefully and skillfully done in such a manner that after the first passage of the roller over the raked mixture, a minimum amount of back patching will be required. Placing mixtures shall be as continuous as possible and the roller shall pass over the unprotected edge of the freshly laid mixture only when the laying of this course is to be discontinued for such intervals of time as to permit the mixture to become chilled. D. Joints: Joints between old and new pavements, or between successive days’ work, shall be carefully made in such a manner as to insure a thorough and continuous bond between the old and new surfaces. The edge of the previously laid course shall be cut back to its full depth so as to expose a fresh surface, after which the hot surface mixture shall be placed in contact with it and raked to a proper depth and grade. Hot smoothers or tampers shall be carefully used in such a manner as to heat up the old pavement sufficiently (without burning it) to insure a proper bond. Before placing mixture against them, all contact surfaces of curbs, gutters, headers, manholes, etc., shall be painted with a thin uniform coating of cationic emulsified asphaltic cement. E. Compaction of the Mixture: After spreading, the mixture shall be thoroughly and uniformly compressed by a power-driven roller or rollers, weighing not less than 8 tons, as soon after being spread as it will bear the roller without undue displacement. Delays in rolling freshly spread mixture will not be tolerated. Rolling shall start longitudinally at the sides and shall proceed toward the center of the pavement overlapping on successive trips by at least ½ the width of a rear wheel. Alternate trips of the roller shall be of slightly different lengths. If the width of the pavement permits, it shall, in addition, be rolled at right angles to the center line. Werner Elem. 02740-11 Asphalt Pavement The speed of the roller shall not exceed 3 miles per hour and shall, at all times, be slow enough to avoid displacements of the hot mixture, and any displacement occurring as a result of reversing the direction of the roller, or from any other cause, shall at once be corrected by the use of rakes and of fresh mixture where required. Rolling shall proceed continuously until all roller marks are eliminated. To prevent adhesion of the mixture to the roller, the wheels shall be kept properly moistened, but excess water will not be permitted. The rollers shall be in good condition, capable of reversing without back-lash and shall weight not less than 200 pounds to the inch of tread. They shall be operated by competent and experienced rollermen and must be kept in continuous operation as nearly as practicable in such a manner that all parts of the pavements shall receive substantially equal compression. Along curbs, headers, manholes, and similar structures, and all places not accessible to the roller, thorough compactions must be secured by means of hot tampers and at all contacts of this character, the joints between these structures and the surface mixture must be effectively sealed. The course, after final compaction, shall conform to the following requirements: It shall be smooth and true to the established crown and grade. It shall have the average thickness specified and shall at no point vary more than ¼ inch from the thickness shown on the typical cross-section in the Plans. Any low or defective places shall immediately be remedied by cutting out the course at such spots and replacing it with fresh, hot mixture which shall be immediately compacted to conform with the surrounding area and shall be free from depressions exceeding ¼-inch as measured with a 10-foot straightedge paralleling the centerline of the roadway. After final compaction, the finished surface course shall at no point have a density less than 92% of the maximum density possible to be obtained in a voidless pavement composed of the same materials in like proportions. Density shall be determined from specimens cut from the finished pavement as directed by the ENGINEER OWNER. 3.04 TEMPORARY ASPHALT COLD-PATCH In the event the CONTRACTOR cannot install hot bituminous pavement, for whatever reason, pursuant to the requirements of these documents, he shall install a temporary asphalt cold-patch pursuant to said requirement and subsequently remove said cold-patch and replace with hot bituminous pavement at the earliest possible date. A. Place suitably prepared base course. B. Minimum thickness: 2 inches on 6-1/2 inches of aggregate base course. C. The CONTRACTOR is responsible for maintaining cold-patch. Werner Elem. 02740-12 Asphalt Pavement 3.05 MANHOLE FRAMES AND VALVE BOXES A. Manhole frames and water valve vaults can be completed after paving operation by using “plates.” B. Foreign matter which is introduced into manholes and valve vaults shall be removed immediately to provide free access to the facilities. C. Valve vaults and manhole rings shall be straight and properly aligned. Adjustments to be made with concrete rings and mortar only (maximum tolerance is ¼”). Valve boxes shall be inspected by placing a valve key on the operating nut to assure a proper alignment. END OF SECTION Werner Elem. 02740-13 Asphalt Pavement THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 02740-14 Asphalt Pavement SECTION 02770 SIDEWALK, CURB AND GUTTER, AND MISCELLANEOUS CONCRETE PART 1 1.01 SECTION INCLUDES A. 1.02 Section 02315 – Excavation and Embankment SUBMITTALS A. 1.04 Concrete work shall consist of air entrained Portland Cement concrete constructed on a prepared subgrade in accordance with these Specifications. The completed work shall conform to the thicknesses and typical cross-sections shown on the Drawings. The completed work shall conform to the lines and grades shown on the Drawings or to those established by the ENGINEER OWNER at the job site. RELATED SECTIONS A. 1.03 GENERAL The CONTRACTOR shall cooperate with the ENGINEER OWNER in obtaining and providing samples of all specified materials. The CONTRACTOR shall submit certified laboratory test certificates for all items required in this section, including a mix design for concrete. PROJECT REQUIREMENTS The CONTRACTOR shall submit batch tickets for each load of concrete. Tickets shall show weight of all materials and additives used in each batch. PART 2 2.01 PRODUCTS MATERIALS A. Concrete shall conform to the following requirements: 28-Day Field Compressive Strength Cement/Fly Ash Max. Water/Cement Ratio Air Content % Range Maximum Slump Fine Aggregate (max. % of total Aggregate) 3500 psi 600 lbs./cu. yd. 0.53 5-8 4" 50% This material shall consist of a mixture of coarse and fine aggregates, Portland cement, water and other materials or admixtures as required. The type of cement shall be Type I, II, or I/II unless sulfate conditions dictate otherwise. If sulfate conditions exist, Type V cement shall be used. Werner Elem. 02770-1 Sidewalk, Curb and Gutter, and Miscellaneous Concrete B. Concrete Aggregates: The grading and composition requirements for coarse and fine aggregates for concrete shall conform to the following tables. COARSE AGGREGATES FOR PORTLAND CEMENT CONCRETE Sieve Size or Test Procedure 1 Inch ¾ Inch 3 ⁄8 Inch No. 4 No. 8 % Wear Clay Lumps * Friable Particles, % Coal & Lignites, % Sodium Sulfate Soundness % % Passing or Test Requirement 100 90-100 20-55 0-10 0-5 45, Max. 2.0, Max. 0.5, Max. 12, Max. FINE AGGREGATES FOR PORTLAND CEMENT CONCRETE Sieve Size or Test Procedure 3 ⁄8 Inch No. 4 No. 16 No. 50 No. 100 No. 200 Friable Particles, % Coal & Lignite, % Deleterious Material (AASHTO T 112),% Sand Equivalent (AASHTO T 176),% Fineness Modules Sodium Sulfate Soundness, % C. Percent Passing or Test Requirement 100 95 - 100 45 - 80 10 - 30 2 - 10 3, Max. 1.0, Max. 1.0, Max. 3, Max. 80, Min. 2.50 - 3.50 20.0, Max. Coarse Aggregate for Concrete: Coarse aggregates shall conform to the requirements of AASHTO M 80, except that the percentage of wear shall not exceed 45 when tested in accordance with AASHTO T 96. Coarse aggregate shall conform to the grading in above table. D. Fine Aggregate for Concrete: Fine aggregates shall meet Colorado Department of Highways Section 703.01 requirements and gradation as shown above. Fine aggregate for concrete shall conform to the requirements of AASHTO M 6. The amount of deleterious substances removable by elutriation shall not exceed 3% by dry weight of fine aggregate when tested in accordance with AASHTO T 11, unless otherwise specified. The minimum Sand Equivalent, as tested in accordance with AASHTO T 176 shall be 80, unless otherwise Werner Elem. 02770-2 Sidewalk, Curb and Gutter, and Miscellaneous Concrete specified. The Fineness Modules shall not be less than 2.50 nor greater than 3.50, unless otherwise approved. E. Fly Ash and Water: Upon approval based on a satisfactory trail mix, the CONTRACTOR shall have the option of substituting approved fly ash for portland cement, up to a maximum of 20 percent by weight. The total weight of cement and fly ash shall not be less than the specified mix design. 1. Fly ash for concrete shall conform to the requirements of ASTM C 618, Class C or Class F. All chemical requirements of ASTM C 618 Table 1-A shall apply with the exception of footnote A. Class C fly ash will not be permitted where sulfate resistant cement is required. The CONTRACTOR shall submit certified laboratory test results for the fly ash. Test results that do not meet the physical and chemical requirements may result in the suspension of the use of fly ash until the corrections necessary have been taken to insure that the material meets the specifications. 2. F. Water used in mixing or curing shall be clean and free of oil, salt, acid, alkali, sugar, vegetable, or other substance injurious to the finished product. Water will be tested in accordance with, and shall meet the suggested requirements of AASHTO T 26. Water known to be of potable quality may be used without test. Where the source of water is relatively shallow, the intake shall be so enclosed as to exclude silt, mud, grass, or other foreign materials. Concrete Curing Materials and Admixtures 1. Curing Materials: Curing Materials shall conform to the following requirements as specified: Burlap Cloth made from Jute or Kenaf: AASHTO M 182 Liquid Membrane-Forming Compounds Curing Concrete: AASHTO M Sheet Materials for Curing Concrete: AASHTO M 171 Straw shall not be used for curing unless approved by the ENGINEER OWNER. Werner Elem. 2. Air-Entraining Admixture: Air-entraining admixtures shall conform to the requirements of AASHTO M 154. Admixtures which have been frozen will be rejected. No chloride containing additives shall be permitted. 3. Chemical Admixtures: Chemical admixtures for concrete shall conform to the requirements of AASHTO M 194. Admixtures which have been frozen will be rejected. 4. Joint Fillers: The joint fillers shall meet the requirements of one or more of the references listed in paragraph 1.03. 02770-3 Sidewalk, Curb and Gutter, and Miscellaneous Concrete PART 3 3.01 EXECUTION SUBGRADE PREPARATION A. The subgrade shall be excavated or filled to the required grades and lines. All soft, yielding, or otherwise unsuitable material shall be removed and replaced with suitable material with the ENGINEER's OWNER's approval. Filled sections shall be compacted and compaction shall extend a minimum of six inches outside the form lines. The moisture content of the subgrade shall be brought within +/- 2% of optimum moisture content and compacted to 95% of the maximum standard Proctor density (ASTM D698) for subgrade materials classified as A-4 through A-7 or 95% of modified proctor density for materials classified as A-1 through A-3. 3.02 CONCRETE PLACEMENT A. 3.03 MACHINE PLACEMENT A. 3.04 Concrete transported in truck mixers or truck agitators shall be delivered to the site of the work and completely discharged within a period of ninety (90) minutes after the cement comes in contact with the mixing water or with the combined aggregates containing free moisture in excess of 2% by weight. The concrete shall be placed either by an approved slip form/extrusion machine, by the formed method, or by a combination of these methods. The subgrade shall be conditioned to provide a uniformly moist surface when concrete is placed. The slip form/extrusion machine shall be so designed to place, spread, consolidate, screed, and finish the concrete in one complete pass in such a manner that a minimum of hand finishing will be necessary to provide a dense and homogenous concrete section. The machine shall shape, vibrate, and/or extrude the concrete for the full width and depth of the concrete section being placed. It shall be operated with as nearly a continuous forward movement as possible. All operations of mixing, delivery, and spreading concrete shall be so coordinated as to provide uniform progress, with stopping and starting of the machine held to a minimum. FORMED METHOD A. The vertical face of previously sawed and adjacent asphalt pavement may NOT be used as a forming surface. The CONTRACTOR shall use forms on front and back of all curb and gutter, sidewalks and crosspans. The forms shall be of metal or other suitable material that is straight and free from warp, having sufficient strength to resist the pressure of the concrete without displacement and sufficient tightness to prevent the leakage of mortar. Flexible or rigid forms of proper curvature may be used for curves having a radius of 100 feet or less. Division plates shall be metal. Where directed by the ENGINEER OWNER the CONTRACTOR shall use a thin metal back form to preserve landscaping, sprinklers, etc. Form must be straight and rigid and must be approved by the ENGINEER OWNER prior to use on project. The front and back forms shall extend for the full depth of the concrete. All of the forms shall be braced and staked so that they remain in both horizontal and vertical alignment until their removal. No wooden stakes will be allowed. They shall be cleaned and Werner Elem. 02770-4 Sidewalk, Curb and Gutter, and Miscellaneous Concrete coated with an approved form-release agent before concrete is placed against them. The concrete shall be deposited into the forms without segregation and then it shall be tamped and spaded or mechanically vibrated for thorough consolidation. Low roll or mountable curbs may be formed without the use of a face form by using a straight edge and template to form the curb face. When used, face forms shall be removed as soon as possible to permit finishing. Front and back forms shall be removed without damage to the concrete after it has set. Should the removal of adjacent asphalt pavement be required beyond that shown in the asphalt patch detail to properly correct failed concrete sections, the CONTRACTOR shall remove and replace said asphalt pavement to such an extent as to provide a smooth repair. The ENGINEER OWNER shall be notified prior to commencing any additional asphalt removal. 3.05 FINISHING A. 3.06 The plastic concrete shall be finished smooth by means of a wood float and then it shall be given final surface texture using a light broom or burlap drag. Concrete that is adjacent to forms and formed joints shall be edged with a suitable edging tool to the dimensions shown on the Drawings. JOINTING A. Contraction Joints: Transverse weakened-plane contraction joints shall be constructed at right angles to the curb line at intervals not exceeding 10 feet for curb and gutter or 5 feet for sidewalk. Joint depth shall average at least one-fourth of the cross-section of the concrete. Contraction joints may be sawed, hand-formed, or made by 1/8 inch thick division plates in the form work. Sawing shall be done early after the concrete has set to prevent the formation of uncontrolled cracking. The joints may be hand-formed either by (1) using a narrow or triangular jointing tool or a thin metal blade to impress a plane of weakness into the plastic concrete, or (2) inserting 1/8 inch thick steel strips into the plastic concrete temporarily. Steel strips shall be withdrawn before final finishing of the concrete. Where division plates are used to make contraction joints, the plates shall be removed after the concrete has set and while the forms are still in place. B. Expansion Joints: Expansion joints shall be constructed at right angles to the curb line at immovable structures and at points of curvature for short radius curves. Filler material for expansion joints shall conform to requirements of one or more of the references defined in Section 1.03 and shall be furnished in a single 1/2 inch thick piece for the full depth and width of the joint. Expansion joints in a slip formed curb or curb-and-gutter shall be constructed with an appropriate hand tool by raking or sawing through partially set concrete for the full depth and width of the section. The cut shall be only wide enough to permit a snug fit for the joint filler. After the filler is placed, open areas adjacent to the filler shall be filled with concrete and then troweled and edged. The CONTRACTOR may choose to place the filler and pour the concrete around it. Alternately, an expansion joint may be installed by removing a short section of freshly extruded curb-and-gutter immediately, installing temporary holding forms, placing the Werner Elem. 02770-5 Sidewalk, Curb and Gutter, and Miscellaneous Concrete expansion joint filler, and replacing and reconsolidating the concrete that was removed. Contaminated concrete shall be discarded. Construction joints may be either butt or expansion-type joints. Curbs or combined curbs and gutters constructed adjacent to existing concrete shall have the same type of joints as in the existing concrete, with similar spacing; however, contraction joint spacing shall not exceed 10 feet. 3.07 PROTECTION A. The CONTRACTOR shall always have materials available to protect the surface of the plastic concrete against rain. These materials shall consist of waterproof paper or plastic sheeting. For slip form construction, materials such as wood planks or forms to protect the edges shall also be required. Concrete damaged by rain shall be required to be removed and replaced at the CONTRACTOR’s expense. Concrete being placed in cold weather during which the temperature may be expected to drop below 35 degrees F., shall be suitably protected to keep the concrete from freezing until it is at least 10 days old. Concrete injured by frost action shall be required to be removed and replaced at the CONTRACTOR’s expense. The CONTRACTOR will be responsible for correcting any vandalism or defacement (graffiti) that occurs on the concrete prior to final acceptance. 3.08 CURING A. 3.09 BACKFILLING A. 3.10 The spaces in front and back of curbs shall be refilled with suitable material to the required elevations after the concrete has set sufficiently. The fill material shall be thoroughly tamped in layers. SEALING A. 3.11 Concrete shall be cured for at least 7 days after placement to protect against loss of moisture, rapid temperature change, and mechanical injury prior to any overlay or reconstruction work. Moist burlap, waterproof paper, white polyethylene sheeting, white liquid membrane compound, or a combination thereof may be used as the curing material. Membrane curing shall not be permitted in frost-affected areas when the concrete will be exposed to deicing chemicals within 30 days after completion of the curing period. Where required, concrete shall be sealed with a mixture of 1/2 linseed oil and 1/2 diesel fuel, unless otherwise specified by ENGINEER OWNER. TOLERANCE A. Forms shall not deviate from true line by more than ¼-inch at any point. B. Mixed concrete shall be not less than 50°F, nor more than 80°F at the time of placing it in forms unless otherwise directed. Werner Elem. 02770-6 Sidewalk, Curb and Gutter, and Miscellaneous Concrete C. If air temperature is 35°F or less at the time of placing, the ENGINEER OWNER will require water and/or aggregate heated to not less than 70°F, or more than 150°F. D. Finished joints shall not deviate more than ¼-inch in the horizontal alignment from a straight line. E. Any localized humps and or depressions greater than ¼-inch will require removal and replacement of the work in question. F. No ponding of water greater than 3/8-inch shall be allowed. G. Combination curb, gutter and walk and/or vertical curb and gutter flowline depth shall not vary from adopted standards by more than +1/2-inch, measured vertically from the top of curb to the gutter invert. H. Pedestrian walks shall have a minimum of 2.0% and a maximum of 2.5% slope toward the roadway. I. Contraction and construction joints shall be placed at the standard spacing of 10 feet in curb, gutter, sidewalks, crosspans, trickle channel, etc. A minimum spacing of 5 feet will be allowed for repairs. J. Heave or settlement of sidewalk, relative to separate curb pour, greater than ½-inch shall be cause for corrective action. This provision shall not apply to transverse sidewalk joints. K. At the time of final acceptance inspection, the repair of all cracks will be completed. 1. Cracks that are less than ¼-inch wide, exhibit no horizontal or vertical shifting, and do not meet the conditions in 2, 3, and 4 below may, at the discretion of the OWNER, be sealed by routing approximately ¾-inch to 1-inch deep by ¼-inch wide and filling with Sikaflex 1-A or equivalent. 2. Any crack that extends through a joint shall require removal and replacement of the entire cracked area. 3. Any longitudinal cracked section of concrete will require complete removal and replacement of that section between joints. 4. Repair action for hairline cracks as determined in 1 above may be waived at the discretion of the OWNER. For the purpose of this section, a hairline crack is one that is reasonably immeasurable and without separation as determined by the ENGINEER OWNER. 3.12 QUALITY CONTROL A. Concrete testing and testing laboratory services required shall conform to the following unless otherwise determined by the ENGINEER OWNER. Procedures Section Type of Test Werner Elem. Project Acceptance Frequency 02770-7 Test Sampling Project Testing Sidewalk, Curb and Gutter, and Miscellaneous Concrete GRADATION Sidewalks: 1/1000 sq yds or fraction thereof for each size aggregate of concrete placed CP 30 CP 31 CP 30 CP 60 MOISTURE CONTENT (COARSE AGGREGATE) 1 per day min. where CP 30 moisture content is greater than +0.5% from SSD condition CP 60 SLUMP The slump, air content and unit weight tests shall be carried out on the first truck of concrete for the daily placement and thereafter in conformance with the following table: T 141 T 119 AIR CONTENT 1 set of tests for every 1000 square yards or fraction thereof of concrete placed T 141 T 199 T 152 YIELD AND CEMENT 4 tests for every 2000 lineal feet or fraction thereof or nomograph of curb and gutter graph placed T 141 T 121 SIDEWALKS (CONCRETE) CURBING (CONCRETE) Curbing: 1/2000 lineal feet or fraction thereof for each size aggregate of concrete placed MOISTURE CONTENT (FINE AGGREGATE) 1 per day and as often as needed for quality control COMPRESSIVE Sidewalks: 1 set (4) of T 141 cylinders per 1000 square yards or fraction thereof or concrete placed per day T 22 T 23 Curbing: 1 set (4) of cylinders per 2000 lineal feet or fraction thereof of concrete placed per day Point of Acceptance: Gradation - Stockpile, belt, or bin Air Content - Mixer Discharge Werner Elem. 02770-8 Sidewalk, Curb and Gutter, and Miscellaneous Concrete Prior to backfilling and after forms are removed, honeycombed, defective or damaged areas of concrete shall be repaired. Repairs shall be made within 7 days after the forms are removed. 3.13 CLEAN-UP A. The surface of the concrete shall be thoroughly cleaned upon completion of the work and prior to the substantial completion walk through, and the site left in a neat and orderly condition. END OF SECTION Werner Elem. 02770-9 Sidewalk, Curb and Gutter, and Miscellaneous Concrete THIS PAGE INTENTIONALLY LEFT BLANK. Werner Elem. 02770-10 Sidewalk, Curb and Gutter, and Miscellaneous Concrete APPENDIX A SUBSURFACE EXPLORATION REPORT PROPOSED PAVEMENT RECONSTRUCTION WERNER ELEMENTARY SCHOOL EARTH ENGINEERING CONSULTANTS SUBSURFACE EXPLORATION REPORT PROPOSED PAVEMENT RECONSTRUCTION WERNER ELEMENTARY SCHOOL 5400 MAIL CREEK LANE FORT COLLINS, COLORADO EEC PROJECT NO. 1122109 Prepared for: Poudre School District c/o Anderson Consulting Engineers, Inc. 375 East Horsetooth Road, Building 5 Fort Collins, Colorado 80525 Attn: Mr. Scott Parker, P.E. Prepared by: Earth Engineering Consultants, Inc. 4396 Greenfield Drive Windsor, Colorado 80550 December 17, 2012 Poudre School District c/o Anderson Consulting Engineers, Inc. 375 East Horsetooth Road, Building 5 Fort Collins, Colorado 80525 Attn: Mr. Scott R. Parker, P.E. (srparker@acewater.com) Re: Subsurface Exploration Report Proposed Pavement Reconstruction Werner Elementary School 5400 Mail Creek Lane Fort Collins, Colorado EEC Project No. 1122109 Mr. Parker: Enclosed, herewith, are the results of the geotechnical subsurface exploration completed by Earth Engineering Consultants, Inc. (EEC) personnel for the proposed pavement reconstruction project for Werner Elementary School located at 5400 Mail Creek Lane in Fort Collins, Colorado. As a part of this exploration, ten (10) soil borings extending to depths of approximately 10 feet below existing site grades were advanced within the proposed pavement reconstruction areas to develop information on existing pavement and subsurface conditions. This exploration was completed in general accordance with our proposal dated November 27, 2012. In summary, the existing surface pavement and aggregate base thicknesses were relatively thin. The subgrade soils encountered beneath the existing pavement section generally consisted of sandy lean clay with clayey sand observed in two (2) borings. The cohesive subgrade soils extended to the depths explored, approximately 10 feet below current surface grading. Free water was not encountered in any of the test borings at the time of our exploration. The cohesive subgrade soils were generally medium stiff to stiff and exhibited relatively low swell potential. The subgrade soils where in-situ moisture contents appeared elevated would be expected to be unstable under construction traffic after removal of the existing pavement structure. Recommendations for subgrade/ground stabilization measures are provided within the text portion of this report. 4396 GREENFIELD DRIVE WINDSOR, COLORADO 80550 (970) 545-3908 FAX (970) 663-0282 www.earth-engineering.com SUBSURFACE EXPLORATION REPORT PROPOSED PAVEMENT RECONSTRUCTION WERNER ELEMENTARY SCHOOL 5400 MAIL CREEK LANE FORT COLLINS, COLORADO EEC PROJECT NO. 1122109 December 17, 2012 INTRODUCTION The subsurface exploration for the proposed pavement reconstruction/improvements at the existing Werner Elementary School located at 5400 Mail Creek Lane in Fort Collins, Colorado, has been completed. The field exploration for this project included drilling ten (10) soil borings to depths of approximately 10 feet below present site grades within proposed pavement improvement areas to obtain information on existing pavement thicknesses and in-situ subsurface conditions. Individual boring logs and a site diagram indicating the approximate boring locations are included with this report. We understand this project involves the improvement/reconstruction of existing pavement areas at the existing Werner Elementary School as outlined on the attached boring location diagram. We understand the layout of the pavement areas will remain essentially the same as the existing configuration after the reconstruction efforts are completed although a small area of new pavement will be added in Phase II in the general vicinity of boring B-9. The main pavement corridors are anticipated to receive moderate to heavy traffic flow. The parking areas are expected to receive low volumes of light vehicle/automobile traffic. Based on the information we received from Anderson Consulting Engineers, the project’s civil engineering consultant, minor vertical realignment may be necessary in some areas to accommodate drainage improvements; however, essentially no horizontal realignment or expansion is expected. The purpose of this report is to describe the existing pavement thickness and subsurface conditions encountered in the borings, analyze and evaluate the test data and provide geotechnical recommendations concerning design and construction of new pavements after removal of the existing pavement sections. EXPLORATION AND TESTING PROCEDURES The boring locations were established in the field by Earth Engineering Consultants, Inc. (EEC) personnel by pacing and estimating angles from identifiable site references. The approximate boring locations are indicated on the attached boring location diagram. The locations of the borings should be considered accurate only to the degree implied by the methods used to make the field measurements. Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 2 The borings were performed using a truck mounted, CME-45 drill rig, equipped with a hydraulic head employed in drilling and sampling operations. The boreholes were advanced using 4-inch nominal diameter continuous flight augers and samples of the subsurface materials encountered were obtained using split-barrel and California sampling techniques in general accordance with ASTM Specifications D1586 and D3550, respectively. Additional “bulk” samples of the subgrade materials were obtained from the auger cuttings. In the split-barrel and California barrel sampling procedures, standard sampling spoons are driven into the ground by means of a 140-pound hammer falling a distance of 30 inches. The number of blows required to advance the split barrel and California barrel samplers is recorded and is used to estimate the in-situ relative density of cohesionless materials and, to a lesser degree of accuracy, the consistency of cohesive soils. All samples obtained in the field were sealed and returned to the laboratory for further examination, classification and testing. Moisture content tests were completed on each of the recovered samples. Washed sieve analysis and Atterberg limits tests were performed on selected samples to help establish the percentage of fines and plasticity of the subgrade soils. Swell/consolidation tests were performed on selected samples to evaluate the potential for the subgrade soils to change volume with variation in moisture content and loading conditions. A Hveem stabilometer (R-Value) test was completed on a composite sample of the subgrade materials to evaluate the remolded subgrade strength characteristics for the pavement design. Results of the outlined tests are indicated on the attached boring logs and summary sheets. As a part of the testing program, all samples were examined in the laboratory and classified in accordance with the attached General Notes and the Unified Soil Classification System, based on the soil's texture and plasticity. The estimated group symbol for the Unified Soil Classification System is shown on the boring logs and a brief description of that classification system is included with this report. SITE AND SUBSURFACE CONDITIONS The pavement improvement areas generally surround the existing Werner Elementary School building. The improvement areas are indicated on the attached “Boring Location” diagram. The existing pavements appeared to be in relatively poor condition. Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 3 An EEC representative was on-site during drilling to evaluate the subsurface materials encountered and direct the drilling activities. Field logs prepared by EEC site personnel were based on visual and tactual observation of disturbed samples and auger cuttings. Final boring logs included with this report may include modifications to those field logs based on the results of laboratory testing and engineering evaluation. Based on the results of the field boring and laboratory testing, subsurface conditions can be generalized as follows. The existing pavement sections generally included 2 to 3½ inches of hot bituminous pavement (HBP) over aggregate base ranging in the thickness from approximately 2 to 9 inches. At boring location B-9, the surfacing material generally included about 6 inches of a gravel surface. The subgrade soils encountered beneath the existing pavement sections generally consisted of materials classified sandy lean clay although the near surface soils in borings B-1 and B-2 were classified as clayey sand. The native cohesive soils were generally medium stiff to stiff and exhibited relatively low swell potential with increase in moisture and load at current moisture and density conditions. The in-place soils appeared to be relatively moist with measured moisture contents generally in the 15 to 20% range. The sandy lean clay extended to the bottom of the borings at depths of approximately 10 feet below current site grades. The stratification boundaries indicated on the boring logs represent the approximate locations of changes in soil types; in-situ, the transition of materials may be gradual and indistinct. GROUNDWATER LEVEL OBSERVATION Observations were made while drilling and after completion of the borings to detect the presence and depth to hydrostatic groundwater. No free water was observed in the borings either during or immediately after completion of drilling. The boreholes were backfilled upon completion so that longer term monitoring for groundwater depth was not possible. Longer-term observations in cased holes sealed from the influence of surface water would be required to more accurately evaluate groundwater levels. Fluctuations in groundwater levels can occur overtime depending on variation in hydrologic conditions and other conditions not apparent at the time of this report. Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 4 ANALYSIS AND RECOMMENDATIONS Visual Evaluation of Existing Pavement Structure As illustrated on the enclosed site photographs and based on the initial site visit/walk-through on November 20, 2012, various areas of the asphaltic concrete surface material/hot mix asphalt (HMA) pavement materials, across the site exhibited longitudinal, transverse and/or alligator cracking. The majority of the longitudinal and transverse cracks were “crack-sealed”. The existing pavement section for the site, as previously presented, was relatively thin ranging from 2 to 3½ inches of HMA, underlain by 2 to 9 inches of ABC; however, variations may exist across the site. These varying thicknesses across the site would correlate to overall structural numbers ranging from about 0.98 to 1.84, or an average of about 1.55. As further discussed in this report we have estimated structural numbers for the reconstruction efforts to be approximately 2.59 for the automobile parking areas and approximately 3.57 for the heavy duty pavement sections; thus indicating that the existing pavement section in general are deficient for the anticipated traffic conditions. For cohesive subgrade soils, it is typically suggested to place a zone of aggregate base course (ABC) between the hot mix asphalt (HMA) section and the underlying subgrade to reduce the potential for trapped moisture. The ABC section acts as a capillary break mechanism, a load distribution, and a leveling course. For the rehabilitation/reconstruction of the on-site pavement areas we would recommend the use of a composite section over a stabilized subgrade section. Swell – Consolidation Test Results The swell-consolidation test is performed to evaluate the swell or collapse potential of soils. In this test, relatively undisturbed samples obtained directly from the California barrel sampler are placed in a laboratory apparatus and inundated with water under a predetermined load. The swell-index is the resulting amount of swell or collapse expressed as a percent of the sample’s initial thickness. After the initial movement appears completed, additional incremental loads are applied to evaluate swell pressure and possible consolidation. Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 5 For this assessment, we conducted five (5) swell-consolidation tests on samples obtained at approximate depths of 1 to 2 feet below site grades. The swell index values for the soil samples tested at 150-psf inundation pressure generally revealed relatively low swell potential ranging from (+) 0.0 to (+) 3.1%. The (+) test results indicate the swell potential characteristics of the soil upon inundation with water. The laboratory test results for the swell-consolidation testing procedures are included with this report. Subgrade Preparation Recommendations We understand all existing pavements will be removed from the proposed pavement replacement areas. Existing aggregate base and/or gravel surfacing materials, where encountered, could remain in-place beneath the new pavement sections or incorporated into the pavement subgrades. Areas of the subgrades appear to be moist to very moist beneath the existing pavements. Those areas of high moisture content will likely show instability with pumping and rutting under construction traffic loads. After removal of existing pavements and completing any required cuts and prior to placement of any fill, or pavement materials, we recommend the in-place soils be scarified to a minimum depth of 12 inches, adjusted in moisture content and compacted to at least 95% of the material's maximum dry density as determined in accordance with ASTM Specification D-698, the standard Proctor procedure. The moisture content of the scarified soils should be adjusted to be within the range of 2% of standard Proctor optimum moisture at the time of compaction. If soft or loose zones are observed during the scarification/compaction process, additional reworking of the subgrades may be required. The subgrades should be closely observed to evaluate the suitability of the in-situ soils. If the subgrades will be stabilized with the addition of Class “C” fly ash as subsequently outlined in this report, the scarification and compaction could be accomplished in conjunction with the stabilization process. Due to the slightly elevated in-situ moisture contents in various areas across the site, after removal of the existing pavement section during the reconstruction phase, soft/compressible subgrade conditions may exist in which ground stabilization may be necessary to create a working platform for construction equipment and/or placement of additional fill, where applicable. Placement of a granular material, such as a 3-inch minus recycled concrete or Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 6 equivalent, may be necessary as a subgrade enhancement layer embedded into the soft soils, prior to placement of additional fill material or operating heavy earth-moving equipment. Supplemental recommendations can be provided upon request. If any fill soils are required to develop pavement subgrades, those fill materials should consist of approved, low-volume change materials which are free from organic matter and debris. It is our opinion the near surface sandy lean clay or clayey sand material could be used as fill in these areas. Fill soils should be placed in loose lifts with a maximum thickness of 9 inches, adjusted in moisture content and compacted to at least 95% of the material’s standard Proctor maximum dry density. The moisture content of the fill soils should be adjusted to be within ±2% of the material’s standard Proctor optimum moisture content. We expect the subgrades exposed after removal of the existing pavements will show areas of instability, pumping and possible rutting. We recommend stabilization of the subgrades with the addition of Class “C” fly ash be considered to allow for construction of the pavement section atop a stable platform. Based on prior experience with similar materials, we recommend 13% Class “C” fly ash, based on dry weights, be incorporated with the subgrade soils for the stabilization. The stabilized zone should be 12-inches thick with compaction to at least 95% of the standard Proctor maximum dry density. The moisture content should be adjusted to -3 to +1% of standard Proctor optimum moisture at the time of compaction. Care should be taken after preparation of the subgrades to avoid disturbing the subgrade materials. Materials which are loosened or disturbed by the construction activities or materials which become dry and desiccated or wet and softened should be removed and replaced prior to placement of the overlying fill or pavement structure. Care should be taken to maintain proper moisture contents in the subgrade soils prior to placement of any overlying improvements. Pavement Sections Pavement section designs are based on subgrade conditions and anticipated traffic volumes. Based on the subsurface conditions encountered across the site and the laboratory test results, we are providing the pavement thicknesses herein using a Hveem Stabilometer/R-Value of 11 as determined in laboratory testing. The traffic volumes and estimated 18 kip equivalent single axle Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 7 loads (18-kip ESAL’s) are based on our experience with similar projects and current LCUASS pavement design guidelines. For a total reconstruction of the on-site pavement areas, we recommend that at least the upper 1foot of subgrade material beneath the final pavement section be stabilized with fly ash to enhance the integrity of the subgrade section and increase the life of the pavement section. Recommended pavement sections are provided in Table 1 below. Pavement design methods are intended to provide structural sections with adequate thickness over a particular subgrade such that wheel loads are reduced to a level the subgrade can support. The support characteristics of the subgrade for pavement design do not account for shrink/swell movements of a soft/compressible clay subgrade. Thus, the pavement may be adequate from a structural standpoint, yet still experience cracking and deformation due to shrink/swell related movement of the subgrade. It is, therefore, important to minimize moisture changes in the subgrade to reduce shrink/swell movements. Recommended alternatives for the on-site pavement improvements are as follows: TABLE 1 –Minimum Pavement Thicknesses for On-Site Pavement Improvement Areas Light Duty / Automobile Parking Areas Heavy Duty/Bus Lanes and Main Traffic Corridors 10 50 18 kip Equivalent Single Axle Loads (ESAL’s) 20-year 73,000 365,000 Resilient Modulus (R = 11) Reliability Serviceability Loss (Terminal Service=2.2 and 2.5) Design Structural Number – 20-year design life 3681 75% 2.3 2.59 3681 85 2.0 3.57 3-1/2″ @ 0.44 = 1.54 6″ @ 0.11 = 0.66 12″ @ 0.05 = 0.60 2.80 5″ @ 0.44 = 2.20 8″ @ 0.11 = 0.88 12″ @ 0.05 = 0.60 3.68 6″ Minimum 8″ Minimum 18 kip Equivalent Daily Load Axles (EDLA) Composite Section: – with Fly Ash Stabilized Subgrade Hot Mix Asphalt Pavement Aggregate Base Fly Ash treated subgrade (13% Class C Fly ash – 12”) Structural Number Portland Cement Concrete Pavement – PCCP Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 8 Asphaltic concrete for use in the hot bituminous pavements (HBP) should consist of grading S (75) or SX (75) with PG 58-28 performance graded binder. The pavement materials should be compacted to within 92 to 96% of maximum theoretical density (Rice value). The aggregate base should be either Class 5 or Class 6 base consistent with LUCASS Standards. Portland cement concrete pavements should be constructed of exterior pavement mix concrete with a 28 day compressive strength of at least 4,200 psi. The concrete should be air entrained. The recommended pavement sections are based on non-reinforced concrete although woven wire mesh or fiber mesh should be considered to help control shrinkage cracking. Pavement Considerations The collection and diversion of surface drainage away from paved areas is critical to the satisfactory performance of the pavement. Drainage design should provide for the removal of water from paved areas in order to reduce the potential for wetting of the subgrade soils. Long-term pavement performance will be dependent upon several factors, including maintaining subgrade moisture levels and providing for preventive maintenance. The following recommendations should be considered the minimum if a total reconstruction is planned for the site: The subgrade and the pavement surface should be adequately sloped to promote proper surface drainage. Install pavement drainage surrounding areas anticipated for frequent wetting (e.g. along curb and gutter alignments, islands, and any potential areas where surface water intrusion may occur), Install joint sealant and seal cracks immediately, especially between HMA and concrete curbs, sidewalks, etc. Seal all landscaped areas in, or adjacent to pavements to minimize or prevent moisture migration to subgrade soils. Place compacted, low permeability backfill against the exterior side of curb and gutter. Place curb, gutter, and/or sidewalk directly on approved moisture conditioned and compacted, proof rolled soils without the use of base course material. Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 9 Preventive maintenance should be planned and provided for with an on-going pavement management program. Preventive maintenance activities are intended to slow the rate of pavement deterioration, and to preserve the pavement investment. Preventive maintenance consists of both localized maintenance (e.g. crack and joint sealing and patching) and global maintenance (e.g. surface sealing). Preventive maintenance is usually the first priority when implementing a planned pavement maintenance program and provides the highest return on investment for pavements. Prior to implementing any maintenance, additional engineering observation is recommended to determine the type and extent of preventive maintenance. Zones of perched and/or trapped water may be encountered at different times throughout the year in more permeable zones in the subgrades. The location and amount of perched and/or trapped water and the depth to the hydrostatic groundwater can vary over time depending on hydrologic conditions and other conditions not apparent at the time of this report. Please note that if during or after placement of the stabilization or initial lift of pavement, the area is observed to be yielding under vehicle traffic or construction equipment, it is recommended that EEC be contacted for additional alternative methods of stabilization, or a change in the pavement section. Water Soluble Sulfates – (SO4) The water soluble sulfate (SO4) testing of the on-site subgrade materials were less than 20 ppm. Sulfate contents less than 0.1% (1,000 ppm) is considered negligible risk of sulfate attack on Portland cement concrete. The laboratory results indicate that ASTM Type I Portland cement is useable for site concrete on and below grade. However, if there is no, or minimal significant cost differential, use of ASTM Type I-II Portland cement is recommended for additional sulfate resistance of construction concrete. Foundation concrete should be designed in accordance with the provisions of the ACI Design Manual, Section 318, Chapter 4. Earth Engineering Consultants, Inc. EEC Project No. 1122109 December 17, 2012 Page 10 GENERAL COMMENTS The analysis and recommendations presented in this report are based upon the data obtained from the soil boring performed at the indicated locations and from any other information discussed in this report. This report does not reflect any variations which may occur between boring or across the site. The nature and extent of such variations may not become evident until construction. If variations appear evident, it will be necessary to re-evaluate the recommendations of this report. It is recommended that the geotechnical engineer be retained to review the plans and specifications so that comments can be made regarding the interpretation and implementation of our geotechnical recommendations in the design and specifications. It is further recommended that the geotechnical engineer be retained for testing and observations during earthwork and foundation construction phases to help determine that the design requirements are fulfilled. This report has been prepared for the exclusive use of Poudre School District/Anderson Consulting Engineers, Inc. for specific application to the project discussed and has been prepared in accordance with generally accepted geotechnical engineering practices. No warranty, express or implied, is made. In the event that any changes in the nature, design or location of the project as outlined in this report are planned, the conclusions and recommendations contained in this report shall not be considered valid unless the changes are reviewed and the conclusions of this report modified or verified in writing by the geotechnical engineer. DRILLING AND EXPLORATION DRILLING & SAMPLING SYMBOLS: SS: Split Spoon - 13/8" I.D., 2" O.D., unless otherwise noted ST: Thin-Walled Tube - 2" O.D., unless otherwise noted R: Ring Barrel Sampler - 2.42" I.D., 3" O.D. unless otherwise noted PA: Power Auger HA: Hand Auger DB: Diamond Bit = 4", N, B AS: Auger Sample HS: Hollow Stem Auger PS: Piston Sample WS: Wash Sample FT: Fish Tail Bit RB: Rock Bit BS: Bulk Sample PM: Pressure Meter WB: Wash Bore Standard "N" Penetration: Blows per foot of a 140 pound hammer falling 30 inches on a 2-inch O.D. split spoon, except where noted. WATER LEVEL MEASUREMENT SYMBOLS: WL : Water Level WCI: Wet Cave in DCI: Dry Cave in AB : After Boring WS : WD : BCR: ACR: While Sampling While Drilling Before Casing Removal After Casting Removal Water levels indicated on the boring logs are the levels measured in the borings at the time indicated. In pervious soils, the indicated levels may reflect the location of ground water. In low permeability soils, the accurate determination of ground water levels is not possible with only short term observations. DESCRIPTIVE SOIL CLASSIFICATION Soil Classification is based on the Unified Soil Classification system and the ASTM Designations D-2488. Coarse Grained Soils have move than 50% of their dry weight retained on a #200 sieve; they are described as: boulders, cobbles, gravel or sand. Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are described as : clays, if they are plastic, and silts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents may be added according to the relative proportions based on grain size. In addition to gradation, coarse grained soils are defined on the basis of their relative in-place density and fine grained soils on the basis of their consistency. Example: Lean clay with sand, trace gravel, stiff (CL); silty sand, trace gravel, medium dense (SM). CONSISTENCY OF FINE-GRAINED SOILS Unconfined Compressive Strength, Qu, psf Consistency < 500 500 - 1,000 1,001 - 2,000 2,001 - 4,000 4,001 - 8,000 8,001 - 16,000 Very Soft Soft Medium Stiff Very Stiff Very Hard RELATIVE DENSITY OF COARSE-GRAINED SOILS: N-Blows/ft Relative Density 0-3 Very Loose 4-9 Loose 10-29 Medium Dense 30-49 Dense 50-80 Very Dense 80 + Extremely Dense PHYSICAL PROPERTIES OF BEDROCK DEGREE OF WEATHERING: Slight Slight decomposition of parent material on joints. May be color change. Moderate Some decomposition and color change throughout. High Rock highly decomposed, may be extremely broken. HARDNESS AND DEGREE OF CEMENTATION: Limestone and Dolomite: Hard Difficult to scratch with knife. Moderately Can be scratched easily with knife. Hard Cannot be scratched with fingernail. Soft Can be scratched with fingernail. Shale, Siltstone and Claystone: Hard Can be scratched easily with knife, cannot be scratched with fingernail. Moderately Can be scratched with fingernail. Hard Soft Can be easily dented but not molded with fingers. Sandstone and Conglomerate: Well Capable of scratching a knife blade. Cemented Cemented Can be scratched with knife. Poorly Cemented Can be broken apart easily with fingers. WERNER ELEMENTARY FORT COLLINS, COLORADO EEC PROJECT NO. 1122109 DECEMBER 2012 WERNER ELEMENTARY FORT COLLINS, COLORADO EEC PROJECT NO. 1122109 DECEMBER 2012 WERNER ELEMENTARY FORT COLLINS, COLORADO EEC PROJECT NO. 1122109 DECEMBER 2012 WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-1 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 3" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR A-LIMITS None N/A N/A D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) LL PI -200 (%) PRESSURE SWELL % @ 500 PSF 10 6000 11.3 113.1 39 23 38.7 600 psf 0.1% 7 3000 22.3 8 4000 24.1 _ _ BASE 2" 1 _ _ SANDY LEAN CLAY (CL) / CLAYEY SAND (SC) 2 dark brown very stiff to stiff _ _ CS 3 _ _ 4 brown _ _ SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-2 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 2" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) 9 7000 9.0 109.5 5 3000 13.1 7 1000 19.3 A-LIMITS LL None N/A N/A -200 PI (%) SWELL PRESSURE % @ 500 PSF _ _ BASE 3" 1 _ _ CLAYEY SAND (SC) 2 brown _ _ loose to medium dense CS 3 with light gravels _ _ sandy seam _ _ 4 SS 5 _ _ SANDY LEAN CLAY (CL) 6 brown _ _ medium stiff 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-3 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 3.5" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR A-LIMITS None N/A N/A D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) LL PI -200 (%) PRESSURE SWELL 11 5000 15.7 109.6 42 26 62.7 2000 psf 11 5000 22.7 3 1000 21.9 % @ 500 PSF _ _ BASE 6.5" 1 _ _ SANDY LEAN CLAY (CL) 2 brown / grey very stiff to medium stiff _ _ CS 3 % @ 150 psf 2.0% _ _ 4 _ _ SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-4 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 3" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) 8 3000 18.0 103.9 10 6000 19.4 7 1000 17.5 A-LIMITS LL None N/A N/A -200 PI (%) SWELL PRESSURE % @ 500 PSF _ _ BASE 6" 1 _ _ SANDY LEAN CLAY (CL) 2 brown _ _ stiff to very stiff CS 3 _ _ 4 _ _ brown / grey with calcareous deposits SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ traces of gravel SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-5 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 2.5" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR A-LIMITS None N/A N/A D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) LL PI -200 (%) PRESSURE SWELL 9 5000 20.5 103.6 43 27 71.4 750 psf 12 4000 19.7 7 2000 24.2 % @ 500 PSF _ _ BASE 5" 1 _ _ LEAN CLAY with SAND (CL) 2 brown _ _ very stiff to stiff CS 3 % @ 150 psf 1.1% _ _ 4 _ _ SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-6 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 3" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) 9 5000 19.1 105.6 5 3000 20.7 8 6000 18.6 A-LIMITS LL None N/A N/A -200 PI (%) SWELL PRESSURE % @ 500 PSF _ _ BASE 8.5" 1 _ _ SANDY LEAN CLAY (CL) 2 brown _ _ very stiff to stiff CS 3 _ _ 4 _ _ SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-7 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 2.5" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR A-LIMITS None N/A N/A D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) LL PI -200 (%) PRESSURE SWELL 10 5000 17.4 107.3 40 26 74.0 1700 psf 9 5000 18.9 8 6000 17.6 % @ 500 PSF _ _ BASE 7.5" 1 _ _ LEAN CLAY with SAND (CL) 2 brown _ _ very stiff CS 3 % @ 150 psf 3.1% _ _ 4 _ _ SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-8 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 2.5" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) 11 5000 19.1 108.3 9 5000 19.5 7 6000 17.5 A-LIMITS LL None N/A N/A -200 PI (%) SWELL PRESSURE % @ 500 PSF _ _ BASE 8" 1 _ _ SANDY LEAN CLAY (CL) 2 brown _ _ very stiff CS 3 _ _ 4 _ _ SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-9 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) LL PI (%) PRESSURE 7 4000 20.1 106.7 43 27 81.6 <150 psf 11 7000 18.8 8 6000 16.3 SAND & GRAVEL 6" _ _ LEAN CLAY with SAND (CL) _ _ A-LIMITS None N/A N/A -200 SWELL % @ 500 PSF 1 brown / grey 2 very stiff _ _ CS 3 % @ 150 psf None _ _ 4 _ _ SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants WERNER ELEMENTARY SCHOOL - PAVEMENT EVALUATION FORT COLLINS, COLORADO PROJECT NO: 1122109 DATE: DECEMBER 2012 LOG OF BORING B-10 RIG TYPE: CME45 SHEET 1 OF 1 FOREMAN: DG AUGER TYPE: 4" CFA SPT HAMMER: MANUAL START DATE FINISH DATE SURFACE ELEV SOIL DESCRIPTION TYPE ASPHALT 2.5" WATER DEPTH 12/1/2012 12/1/2012 N/A WHILE DRILLING AFTER DRILLING 24 HOUR D N QU MC DD (FEET) (BLOWS/FT) (PSF) (%) (PCF) 9 3000 21.1 101.8 7 5000 22.2 10 5000 21.5 A-LIMITS LL None N/A N/A -200 PI (%) SWELL PRESSURE % @ 500 PSF _ _ BASE 9" 1 _ _ SANDY LEAN CLAY (CL) 2 brown / grey very stiff _ _ CS 3 _ _ 4 _ _ SS 5 _ _ 6 _ _ 7 _ _ 8 _ _ 9 _ _ SS 10 _ _ BOTTOM OF BORING DEPTH 10.5' 11 _ _ 12 _ _ 13 _ _ 14 _ _ 15 _ _ 16 _ _ 17 _ _ 18 _ _ 19 _ _ 20 _ _ 21 _ _ 22 _ _ 23 _ _ 24 _ _ 25 _ _ Earth Engineering Consultants SWELL / CONSOLIDATION TEST RESULTS Material Description: Dark Brown SANDY LEAN CLAY (CL) / CLAYEY SAND (SC) Sample Location: Boring 1, Sample 1, Depth 2' Liquid Limit: 39 Beginning Moisture: 11.3% Plasticity Index: 23 % Passing #200: Dry Density: 116.2 pcf Swell Pressure: 600 psf 38.7% Ending Moisture: 19.6% % Swell @ 500: 0.1% 10.0 8.0 Swell 6.0 4.0 Percent Movement 2.0 0.0 -2.0 Water Added Consolidatio -4.0 -6.0 -8.0 -10.0 0.01 0.1 Load (TSF) Project: Werner Elementary School - Pavement Evaluation Location: Fort Collins, Colorado Project #: Date: 1122109 December 2012 1 10 SWELL / CONSOLIDATION TEST RESULTS Material Description: Brown / Grey Sandy Lean Clay (CL) Sample Location: Boring 3, Sample 1, Depth 2' Liquid Limit: 42 Plasticity Index: Beginning Moisture: 15.7% 26 % Passing #200: Dry Density: 107.4 pcf Swell Pressure: 2000 psf 62.7% Ending Moisture: 21.7% % Swell @ 150: 2.0% 10.0 8.0 Swell 6.0 4.0 Percent Movement 2.0 0.0 Water Added -2.0 Consolidatio -4.0 -6.0 -8.0 -10.0 0.01 0.1 Load (TSF) Project: Werner Elementary School - Pavement Evaluation Location: Fort Collins, Colorado Project #: Date: 1122109 December 2012 1 10 SWELL / CONSOLIDATION TEST RESULTS Material Description: Brown LEAN CLAY with SAND (CL) Sample Location: Boring 5, Sample 1, Depth 2' Liquid Limit: 43 Plasticity Index: Beginning Moisture: 20.5% 27 % Passing #200: Dry Density: 110.9 pcf Swell Pressure: 750 psf 71.4% Ending Moisture: 20.9% % Swell @ 150: 1.1% 10.0 8.0 Swell 6.0 4.0 Percent Movement 2.0 0.0 Water Added -2.0 Consolidatio -4.0 -6.0 -8.0 -10.0 0.01 0.1 Load (TSF) Project: Werner Elementary School - Pavement Evaluation Location: Fort Collins, Colorado Project #: Date: 1122109 December 2012 1 10 SWELL / CONSOLIDATION TEST RESULTS Material Description: Brown LEAN CLAY with SAND (CL) Sample Location: Boring 7, Sample 1, Depth 2' Liquid Limit: 40 Plasticity Index: Beginning Moisture: 17.4% 26 % Passing #200: Dry Density: 116.5 pcf Swell Pressure: 1700 psf 74.0% Ending Moisture: 20.6% % Swell @ 150: 3.1% 10.0 8.0 Swell 6.0 4.0 Percent Movement 2.0 0.0 Water Added -2.0 Consolidatio -4.0 -6.0 -8.0 -10.0 0.01 0.1 Load (TSF) Project: Werner Elementary School - Pavement Evaluation Location: Fort Collins, Colorado Project #: Date: 1122109 December 2012 1 10 SWELL / CONSOLIDATION TEST RESULTS Material Description: Brown / Grey LEAN CLAY with SAND (CL) Sample Location: Boring 9, Sample 1, Depth 2' Liquid Limit: 43 Plasticity Index: Beginning Moisture: 20.1% 27 % Passing #200: Dry Density: 107.7 pcf Swell Pressure: <150 psf 81.6% Ending Moisture: 22.5% % Swell @ 150: None 10.0 8.0 Swell 6.0 4.0 Percent Movement 2.0 0.0 Water Added -2.0 Consolidatio -4.0 -6.0 -8.0 -10.0 0.01 0.1 Load (TSF) Project: Werner Elementary School - Pavement Evaluation Location: Fort Collins, Colorado Project #: Date: 1122109 December 2012 1 10 RESISTANCE R-VALUE & EXPANSION PRESSURE OF COMPACTED SOIL - ASTM D2844 Werner Elementary School - Pavement Evaluation PROJECT: PROJECT NO. 1122109 5400 Mail Creek Lane - Fort Collins, Colorado LOCATION: DATE Dec. 2012 SANDY LEAN CLAY (CL) - AASHTO: A-6 MATERIAL DESCRIPTION: Composite Subgrade Sample - Borings B-1 thru B-6 @ 1 - 4-feet SAMPLE LOCATION: 39 17 PLASTICITY INDEX: %PASSING #200: R-VALUE LABORATORY TEST RESULTS 2 TEST SPECIMEN NO. 1 100 150 COMPACTION PRESSURE (PSI) 110.8 112.0 DENSITY (PCF) 18.5 17.0 MOISTURE CONTENT (%) 0.00 0.00 EXPANSION PRESSURE (PSI) 135 133 HORIZONTAL PRESSURE @ 160 PSI 2.53 2.52 SAMPLE HEIGHT (INCHES) 229.3 363.4 EXUDATION PRESSURE (PSI) 10.6 12.3 UNCORRECTED R-VALUE 10.6 12.3 CORRECTED R-VALUE LIQUID LIMIT: R-VALUE @ 300 PSI EXUDATION PRESSURE = 11 61.5 3 150 112.9 16.5 0.00 128 2.52 507.7 15.4 15.4 RESILIENT MODULUS, PSI = 3,681 100 90 80 70 R-Value 60 50 40 30 20 10 0 0 50 100 150 200 250 300 350 Exudation Pressure, PSF 400 450 500 550 600 Poudre School District