USARPAC – USARJ AWRP Briefing 2 July 2002 07/02/02 Power Projection Platform 1 of 13 Agenda BLUF: Yokohama North Dock is a “GO” • Environmental Assessment • Load Bearing Study • Equipment Procurement • Timeline (see CEB-H) • Major Issues • Spend Plan Update • Lessons Learned • What We Need from DA/AMC • Conclusion 07/02/02 Power Projection Platform 2 of 13 YND Environmental Assessment • Status. . • Issue. • • • GREEN No YND download show stoppers Discussion. • • • • • • • Issue was addressed during Aug 01 site survey at YND and USARJ IPR in Mar 02 There were no existing reports to support a FONSI JED is preparing an Environmental Report to assess the environmental impact IPR indicates no issues preventing watercraft COSIS operations at North Dock The watercraft COSIS contract will be in compliance with JEGS EDC for the ER and FONSI is 19 Jul 02 Recommendation. None LEAD: USARJ LEGEND RED POC: LTC Cromby, USARJ DCSEN Mr. Noah, JED • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 Power Projection Platform 3 of 13 YND Load Bearing Study • Status • Issue. • • AMBER 15 year old load bearing study revealed no data for Site #1 and a portion of Site #2 Discussion. • • • • Study verifying pier strength will preclude damage to watercraft and pier JED is expediting core sampling and testing Results will be used to design and build cradles with correct footprint One LCM8 from the SV to remain pierside until the AC downloads in Sep for a consolidated lift with floating and mobile cranes to permanent dry storage locations •Recommendation. • CEB-H designed cradles with the correct footprint to prevent damage to the pier LEAD: USARJ POC: LTC Cromby, USARJ DCSEN Mr. Volkman 17th ASG,DPW FE LEGEND RED • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 Power Projection Platform 4 of 13 Equipment Procurement • Status • Issue. AMBER • Several factors, including the issue of GOJ notification and DFAR compliance resulted in procurement delays •Discussion • 374th Contracting Squadron agreed to compress the solicitation period of contract award of DH equipment (EDD 23 Aug 02) •374th CONS sees no problem meeting the 15 Aug RDD for mooring/access equipment • • Recommendation. Continue to work w/ the 374th CONS to expedite procurement actions LEAD: USARJ / 374th CONS POC: Clyde Harada/Tom Blackburn LEGEND RED • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 Power Projection Platform 5 of 13 Major Issues ISSUES # LEGEND RED 1 YND Environmental Review GREEN 2 Download PAG/PA Plan AMBER 3 SV/AC Download Planning AMBER 4 YND Load Bearing Study AMBER 5 Equipment Procurement AMBER 6 Maritime (Naval) Fleet Review AMBER 7 Road Clearance Equipment Tech Data AMBER 8 COSIS Contract (Plan B – MLC Temp Hires) AMBER 9 FY03 Funding (Dredging/Upgrade/MLC) AMBER 10 MOA/ISA AMBER • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 STATUS Power Projection Platform 6 of 13 Spend Plan Update AUTHORIZATION ($000) U.S. Army Japan (Funds issued on MIPR) travel repair parts rents/utilities contracts/ISSAs office supplies,IM expendables FE project bldg 500 -71 trf to JED FE design mooring/cradle TOTAL Mar Apr weed control dehumidification access equip fuel boom storage bins/shelves life spt/safety eq HAZ compressed gas interim powr/air design interim power/air force protection -25 trf to JED Total Cumulative w/Commitments 0 0 0 700 0 0 120 0 0 100 0 0 43 0 0 55 0 0 50 0 0 0 0 0 991 0 0 975 0 0 3,803.0 0.0 0.0 07/02/02 Power Projection Platform 50 65 50 101 10 29.0 26 438 0 0 0 0 0 0 0 0 May Jun 0 4.3 0 0 0 0 0 0 10.7 0 213.3 0 158.6 38.8 404.7 169.4 999.8 (Cmtmt) Jul Aug Sep * Commitments 0 0 ($32.4 PRC) (34.93 PRC) (206.7 PRC) fender Mooring chain fender/shakle/line 0 (402.64 PRC) 0 (29.9 +$31.1 PRC) 0 0 0 (274 PRC, 10.3 PRC 36.7 (28.27 + 6.92 +3.5 PRC) 36.7 (1,064.2) $2,100.7 dehum/maint kit PVC & gangway outlets/distrib sys barriers, uniforms, truck 0.0 0.0 7 of 13 Lessons Learned • Political Sensitivity Analysis • Identify Total Requirements • Establish a Working Group • AMC LNO is Critical • • 07/02/02 DODAAC/UIC Environmental Assessment • Port Site Survey • Funding • GFE • Equipment Tech Data Power Projection Platform 8 of 13 What We Need from DA/AMC • Full Court Press to refine SV/AC Download Plan • Assistance/AMC POC for development of Download PA Plan • Assistance/POC for Equipment Tech Data (Road Clearances) • Discussion/Definition of DA FY 03/Phase 2 Funding Plan 07/02/02 Power Projection Platform 9 of 13 Conclusion • Ready to accept the SV download at YND • Working hard to provide near turnkey operations with facilities, equipment, service support in record time • Appreciate the outstanding DA and AMC support 07/02/02 Power Projection Platform 10 of 13 Back Up Charts 07/02/02 Power Projection Platform 11 of 13 Timeline AWRP MASTER EVENTS CALENDAR FY 2002 JAN WEEK 1 2 3 RESOURCES FEB 4 5 FY02 Spend Plan 6 7 MAR 8 9 10 11 12 13 DA Funding FE Design MIPR FACILITIES ID FE Req FE Design CONTRACTS Contracting C2 Decision Develop COSIS SOW PEOPLE Submitt TDA Develop PDs EQUIPMENT ID EQUIP Req EQUIP SPECs WATERCRAFT / GRD EQUIP TRANSFER DA / AMC / FORSCOM Watercraft Transfer MTG ID Watercraft / Ground EQUIP Storage Locations FORCE PROTECTION AT / FP Assessment PROCESSES & PROCEDURES 07/02/02 Power Projection Platform ID MOA / ISA Requirements Survey(s) - CCTV - Lighting - Barrier Draft MOA USARPAC / AMC 12 of 13 Timeline AWRP MASTER EVENTS CALENDAR FY 2002 APR WEEK 14 15 MAY 16 17 18 19 20 JUN 21 22 23 24 25 26 RESOURCES USARJ / CEB-H MIPRs OSC MIPR (COSIS) 78th SIG BN MIPR 28 Jun FACILITIES Project Installation / Construction Environ Assessment FE Design CONTRACTS Submit FE PR&Cs Finalize GFP/CFP FE Project Solicitation Period Load Bearing Study Pre Prop YND Bidder visit Issue Synopsis IGCE Issue RFP Develop COSIS SOW PEOPLE Conf Amend RFP 14 Jun 21 Jun COSIS Solicitation Period Selection Panels Submitt RPAs Publish Job Annoucements LNO on-site EQUIPMENT Finalize CTA Procure CTA / GFP EQUIP SPECs WATERCRAFT / GRD EQUIP TRANSFER Draft AMC / FORSCOM EQUIP Transfer MOA ST 901 / 909 FORCE PROTECTION Survey(s) - CCTV - Lighting - Barrier PROCESSES & PROCEDURES Procure AT/FP EQUIP (Barriers, etc) MLC Guard Recruitment (5) Draft MOA USARPAC / AMC Draft ISA 17th ASG / CEG-A Draft ISA 78th SIG BN / CEB-H 07/02/02 Power Projection Platform Final 78th SIG ISA 24 June 13 of 13 Timeline Strong Virginian AWRP MASTER EVENTS CALENDAR FY 2002 JUL WEEK 27 28 29 American Cormorant Contractor on-site 26 Aug AUG 30 31 32 33 SEP 34 35 36 37 38 39 RESOURCES Temp MLC MIPR 11 Jul FACILITIES Project Installation / Construction YND Opening Ceremony 12 Sep Enviromental Review 19July Load Bearing Study CONTRACTS COSIS Solicitation 30 Aug COSIS Contract Evaluations (26 Jul-13 Sep) SSA Decision Evaluation Proposals Due (rev) 25 Jul PEOPLE Initiate Temp MLC Recruitment (12) 3 x DACs on-site YND 16 Aug 2 Jul Temp MLCs on-site YND 16 Sep TEMP MLC Selection Panels 16 Aug EQUIPMENT Install EQUIP Procure CTA / GFP WATERCRAFT / GRD EQUIP TRANSFER FORCE PROTECTION LCU 2013 / 2016 Arrive 22 July MLC Guard Recruit (5) MLCs Guards on-site YND 16 July PROCESSES & PROCEDURES Final MOA USARPAC / AMC 1 July Final 17th ASG ISA 1July 07/02/02 Power Projection Platform 16-20 Sep COSIS Contract Award (rev) 23 Sep YND Bidder Visit (2nd) 9 Jul S i t e R e a d y YND Complete 16 Aug S V A C A C D o w n l o a d D o w n l o a d D o w n l o a d SV DL 20-26 Aug AC DL 10-15 Sep 14 of 13 Spend Plan Update REQ CEB Hythe APR Plan Actual PACOM AWRP FY02 Spend Plan Roll-Up MAY JUN JUL AUG Plan Actual Plan Actual Plan Plan SEP Plan CUMULATIVE TOTAL THRU JUN Plan Actual Delta 844.0 107.0 91.3 35.1 31.3 78.8 11.3 364.8 119.0 84.3 220.9 133.9 87.0 OSC 2955.5 18.4 18.4 10.0 25.7 0.0 0.0 2840.0 0.0 0.0 28.4 44.1 -15.7 USARJ 3334.6 0.0 52.8 1097.0 948.2 1872.7 0.0 594.1 357.1 187.1 2969.7 1001.0 1968.7 78th Signal 16.0 2.2 2.2 8.3 8.3 10.5 10.5 0.0 CORP ENG 96.0 96.0 96.0 0.0 0.0 3325.5 0.0 1285.5 0.0 2040.0 Excess TOTAL 170.4 7416.5 127.6 164.7 1150.4 1013.5 5.5 96.0 96.0 2047.5 107.3 Surplus Funds (as of 30 Jun 02): • $170.4K 07/02/02 Power Projection Platform 3804.4 170.4 646.5 271.4 UFRs (as of 30 Jun 02): • $ TBD – Potential Impacts of Load Bearing Study 15 of 13 Dredging at Site 4 • Status • Issue • • AMBER Dredging at Site 4 Required for permanent mooring of 10 x LCU2000s Discussion • Relooking required dredging depth at Site#4 (Permanent LCU berths) and potential requirement to resample sediment at greater depth • Temporary site for ten LCU 2000s constrains vessel operations • Will execute dredging as early in JFY03 as practicable • 1391 completed • LEGEND RED Recommendation • Proceed based on resolution of required vessel depth LEAD: USARPAC POC: LTC Blanchard • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 Power Projection Platform 16 of 13 Strong Virginian / American Cormorant Download Planning • Status • Issue. AMBER • Activities in Japan require advance lead times to coordinate download, reception, staging, onward movement and storage. • • Discussion • Activities in Japan do not have implementing instructions Recommendation. • Conduct download meetings ASAP LEAD: AMC(CEB-H) POC: Chris Gill, Operations LEGEND RED • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 Power Projection Platform 17 of 13 YND Rock Drill • Status • Issue. • • • AMBER Planning meeting/forum with key players is required to prep for Rock Drill Discussion • MSC, MTMC, USARJ, 17th ASG, 35th S&S Bn require implementing instructions Recommendation. • Conduct a meeting ASAP to develop/validate IPR and Rock Drill support requirements and responsible activities LEAD: AMC (CEB-H) POC: Ivor Edwards, Operations LEGEND RED • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 Power Projection Platform 18 of 13 MOA (AMC / USARPAC) • Status • Issue. • • • AMBER Will provide same outstanding service with or without a completed MOA Discussion. • • • USARPAC provided signed MOA to HQAMC 12 Jun FSC staffing of draft MOA complete 27 Jun Timeline’s MAY NOT meet requirements prior to personnel / equipment on-site Recommendation. LEAD: USARPAC POC: Mr. D.R. Brown, USARPAC Mr. Butch Boyett, AMC LEGEND RED • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 Power Projection Platform 19 of 13 17th ASG ISA • Status • Issue. • • • AMBER ISA needed to address 17 ASG support to AMC and AMC reimbursement to 17th ASG Discussion • The 17th ASG ISA draft is completed Recommendation. • Sign ISA LEAD: USARJ (17th ASG) POC: Mr. Blackburn, DCSLOG Mr. Brown, 17th ASG LEGEND RED • Will not meet the final objective AMBER • May miss intermediate objective / event but will meet final objective GREEN • Will meet final objective 07/02/02 Power Projection Platform 20 of 13