Contract Time and Claims Construction Engineering 380 Contract Time and Claims • Time is not usually part of consideration (like money), and delayed performance is common in construction • Hard for owner to press termination and breach claims for delays • Also hard to get relief from delay unless clear and specific damages can be shown or unless there are express contractual terms (must not be unconscionable) Contract Time and Claims • Commencement usually denoted by a Notice to Proceed order from owner (a letter along with necessary permits) • There can also be contractor notification clause in the contract stipulating that the contractor send written notice that work has begun Contract Time and Claims • Constructive acceleration claim is generated by owner’s refusal to grant a time extension for changes in scope or condition • Contractor must then spend more money to stay on original schedule, justifying the claim for recovery • Can also have a request for early completion, handled like a standard (contract) change order • Sometimes contractors can be prevented from early finish because of hardship on owner Contract Time and Claims • Project Schedule is often required under contract terms and can have legal standing in the case of a litigated claim • Advent of CPM schedules, which establish relationships in activities, have made claims more complex but also probably made relief more realistic Contract Time and Claims • • • • • Start with activities and durations on WBS Determine relationships between activities Longest path through network is critical Key is to understand the relationships Must be able to re-run schedule as certain activity durations change. If activity is on critical path, delay is automatic, if it is not critical, then must examine if activity falls within float or creates a new critical path Lowest element O r g a n i z a t i o U n i t s WBS/Work Packages to Network Circuit board Design cost account Production cost account Test cost account Software cost account B P-10-1 Design WP D-1-1 Specifications WP D-1-2 Documentation A D-1-1 D-1-2 D P-10-2 F S-22-2 K T-13-1 C S-22-1 Production WP P-10-1 Proto 1 WP P-10-2 Final Proto 2 B Proto 1 5 Test systems WP T-13-1 Test Software WP S-22-1 Software preliminary WP S-22-1 Software final version Irwin/McGraw-Hill D Final proto 2 4 A Specifications and documentation 2 F Final software 2 K Test 3 C Preliminary software 3 ©The McGraw-Hill Companies, 2000 Activity-on-Node Network Fundamentals B E Construction plans Staff report 15 15 H Occupancy A C Application approval 5 F Traffic study 10 Commission approval 10 G 35 Wait for construction 170 D ES ID EF SL Description LS Dur Service check 5 KOLL BUSINESS CENTER County Engineers Design Department LF EF Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Activity-on-Node Network Forward Pass 5 B 20 20 20 Construction plans E 35 Staff report 15 15 15 H 35 Occupancy A Application approval 0 5 20 C 5 Traffic study 10 10 F Commission approval 15 20 10 20 10 200 G 30 200 35 235 Wait for construction 30 170 200 D ES ID SL Description LS Dur Service check EF 15 5 20 KOLL BUSINESS CENTER County Engineers Design Department LF EF Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Activity-on-Node Network Backward Pass B E Construction plans 5 15 185 Staff report 20 185 15 200 20 H 185 Occupancy 5 A Application approval 0 5 5 C Traffic study 10 15 F 10 10 Commission approval 20 20 G 20 10 30 200 35 235 Wait for construction 30 170 200 20 D ES ID SL Description LS Dur Service check EF 15 5 20 KOLL BUSINESS CENTER County Engineers Design Department LF LS Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Activity-on-Node Network with Slack 5 0 5 B 20 Construction plans 15 20 185 20 E 35 165 Staff report 185 15 15 20 200 20 200 H 235 185 0 0 5 5 5 Application approval 10 5 A 0 0 5 5 15 C 15 Traffic study 20 20 15 20 10 10 20 5 D 10 10 0 20 F 30 Commission approval 10 30 30 0 30 G 200 200 Occupancy 35 235 Wait for construction 170 200 20 ES ID EF 10 SL Description 15 LS Dur LS EF Service check 5 20 KOLL BUSINESS CENTER County Engineers Design Department LF Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Example of Laddering Using Finish-to-Start Relationship Trench 1/3 Irwin/McGraw-Hill Trench 1/3 Trench 1/3 Lay pipe 1/3 Lay pipe 1/3 Lay pipe 1/3 Refill 1/3 Refill 1/3 AON network Refill 1/3 ©The McGraw-Hill Companies, 2000 Finish-to-Start Relationship Figure 4-16 Lag 2 X Irwin/McGraw-Hill Y ©The McGraw-Hill Companies, 2000 Start-to-Start Relationship Figure 4-17 A B Activity M Activity P Activity N Irwin/McGraw-Hill Lag 5 Activity Q ©The McGraw-Hill Companies, 2000 Use of Lags to Reduce Detail Figure 4-18 Trench 1 mile Lag 3 Lay pipe 1 mile Lag 3 Irwin/McGraw-Hill Refill 1 mile ©The McGraw-Hill Companies, 2000 Finish-to-Finish Relationship Figure 4-19 Prototype Lag 4 Testing Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Network Using Lags Figure 4-22 15 5 Lag 10 20 0 A 0 0 5 5 5 0 0 5 5 C B 5 5 Lag 5 25 15 15 E 0 0 10 20 15 30 30 5 10 45 30 F 0 30 40 5 10 45 40 H 5 45 50 0 5 50 Lag 10 10 Legend D 25 25 G 40 Lag 5 ES ID SL LS Dur Lag 10 EF 11 SL 21 11 15 36 11 36 0 4 40 LF Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Hammock Activity Example Figure 4-23 6 C 11 11 0 0 A 5 0 5 B 6 0 0 5 5 5 6 6 5 11 11 10 21 6 D 10 10 F 13 14 8 4 18 5 Legend ES ID EF SL Description LS Dur. 21 0 8 1 E 18 G 21 F 25 4 25 0 3 21 21 13 Hammock 8 LF Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Network Plans • • • • • Activity- unit of work requiring time Merge activity- dependent on prior activity Burst activity- dependent on post activity Parallel activities- can occur simultaneous Path- sequence of connected, dependent activities • Event- zero duration activity (start, end) Network Plans • • • • Node marks activity (Activity-On-Node) Every activity has a node Arrow marks relationships 3 relationships must be known – predecessor activities – successor activities – parallel activities Network Plans • When relationships and activities are known, add durations • Make forward pass for ES and EF days – add activity times starting from zero – always choose longest EF number • Make backward pass for LS and LF days – set EF to LF or use contractual completion – subtract durations starting with end node – always choose smallest LS number Network Plans • Calculate slack (float) times – LS-ES – LF-EF – nodes with positive number can have delayed start without impacting overall project end – nodes with zero are on the critical path – negative slack means a prior node has delay – on average, 10% of activities are critical Network Plans • Check for logic loops and number errors • Create ES Gantt chart (easier to read) • Add calendar dates w/ weekends & holidays • Use ladder activities when starts are dependent but finishes aren’t • Note lag activities (conc. cures, shipping) • Start-to-start lags are like laddering Contract Time and Claims • Causation can be by: – contractor (owner can file claim or liquidated damages allowed), – Owner (contractor can file claim for delay or acceleration) – No-cause (accidental fire)- no claims – Mutual cause- no claims Contract Time and Claims • Risk allocation and sharing applies to time similarly to money (as in earlier lecture) • Force majeure clauses list specific events for which the contractor will be granted an extension • Liquidated damages, no-damage-for-delay clauses, and excusable/inexcusable delay were covered in previous lecture Contract Time and Claims • Claims (Chapter 27) are largely two-phase process – Is the claim legitimate under the contract and conditions (what are the facts) – If yes- how much should the damaged party receive (determination of award) – The determination of award is largely a measurement problem, as outlined in the book Contract Time and Claims • Eichleay formula allows contractors to add standard overhead costs to actual costs incurred. Overhead is calculated on a prorated daily basis- if your light and heat bill is $100 per day, and you had to stop work for 5 days, you would be entitled to the $500 (oversimplified case) Contract Time and Claims • Certainty principle precludes speculative claim (I would be a starting pitcher for the Yankees if I hadn’t hurt my back) • Certainty principle makes documentation and record keeping critically important in providing support for a claim • Consequential damages must be foreseeable at the time of the contract Contract Time and Claims • Both parties have a duty to mitigatecannot exploit, cannot recover damages that you could have avoided- moving capital equipment onto the job • Collateral source rule tries to keep costs and benefits in line • Non-economic losses, punitive damages generally not awarded in construction, but issue of contorts is developing