Lean Aircraft Initiative Plenary Workshop Factory Operations Focus Team March 5, 1997 Presented by: Tom Shields MIT LEAN AIRCRAFT INITIATIVE l l l l Outline Phase I research Phase II research direction Research activities Next steps FO030597-2 FO030597-2 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE l Phase I Research Report Inventory survey and case studies – Baseline for the industry – Front end loading of inventory – Two recommendations for improvement l l Benchmarking nonsponsor companies Comparative case studies – Flow optimization – Variability reduction l l l Focused case studies Lean implementation considerations Member flow benchmarking FO030597-3 FO030597-3 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE l l l l l l Phase II Research Considerations Identifiable and practical deliverables Meaningful to senior management LEM used as a guide for research Extendible to the enterprise level Balanced breadth and depth of research Linked to Implementation IPT FO030597-4 FO030597-4 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE l l l l l Strategic Approach Build on the LEM Conduct on-site field research Drill down to prioritized metrics/enabling practices (using “Order to point of use delivery cycle time” as initial metric) Use appropriate models to analyze interactions of key factors Use models as decision tools FO030597-5 FO030597-5 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE Example Deliverables l Production system benchmarking l Models for analysis and decision FO030597-6 FO030597-6 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE l l l l Phase II Factory Operations Research Better understanding of assembly stage Identification of appropriate metrics Identification of causes for deviation in assembly cycle time Recommendations for leaner systems FO030597-7 FO030597-7 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE l Research Activities Starting September 1996 Visits to member assembly facility – Weekly visits (234 person hrs) – 2 week stay in January (28 person days) l l l Development of process maps Detailed tracking of specific serial numbers for product types during build Analysis of archival data of recent builds FO030597-8 FO030597-8 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE l l l On-site Visits Collection of module build status documentation at assembly areas Identification of delay causes, if any, with Cell Leaders, Lead Persons, Operators, Schedulers, etc. Identification of waste FO030597-9 FO030597-9 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE Process Maps Sub Assembly 1 Sub Assembly 6 Sub Assembly 2 Sub Assembly 7 Sub Assembly 3 Sub Assembly 8 Sub Assembly 4 Sub Assembly 9 Sub Assembly 5 Sub Assembly 10 Storage Transportation Test Assembly Operation FO030597-10 FO030597-10 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE Subassembly Process Maps Flow operation 1 operation 2 operation 9 operation 16 operation 10 operation 3 operation 4 operation 11 operation 18 operation 12 operation 5 Storage operation 13 operation 6 operation 20 operation 14 Flow operation 15 Transportation Value-Adding Operation Inspection Non-Value-Adding Operation FO030597-11 FO030597-11 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE l l l l l Reasons for Increment in Cycle Time Part shortages (outside source) Part not found but ‘available’ People not available Built awaiting inspection Quality problem – part quality – work quality l l Tooling availability Station availability FO030597-12 FO030597-12 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE Lean Changes Vs. Reality Several lean changes are readily understood, but barriers exist ... l External Conditions Contract conditions v v l with customer with supplier l l Suppliers are limited v v v business reasons there aren’t that many capacity l Internal Conditions Performance measurement system Need to work with upper management to meet requirements for lean transition Workforce issues v v much overtime flexibility FO030597-13 FO030597-13 ©1997 Massachusetts Institute of Technology LEAN AIRCRAFT INITIATIVE l Next Steps Continue research at field sites – Multiple sites in same sector – Multiple sectors – Engine sector in 1997 – Airframe and Electronic sector in 1998 l l l Propose experiments and monitor results Develop models or decision tools Product transition to production study starting in 1998 FO030597-14 FO030597-14 ©1997 Massachusetts Institute of Technology