University of Wisconsin-Stout Physical Plant To: Phil Lyons From: Shirley Klebesadel Date: July 16, 2014 RE: Annual Report 2013-2014 Enclosed are the 2013-2014 Physical Plant Department Annual Report and highlights by each department within Physical Plant. Copy: G. Gust, B. Lorenz, B. Weisenbeck, Z. Smolarek, C. Zimmerman, J. Paulus, M. Eickstaedt, M. Smith, T Biasi, J. Janiak, J. Fults, C. Lacombe, PP web page Director’s Comments Physical Plant began the year in crisis mode in our efforts to keep the campus functioning while conducting the required cleanup, repairs and replacement of the campuses facilities, infrastructure and equipment damaged by the multi-million dollar rain event on June 21, 2014. The campus damages were concentrated to three facilities; Jarvis Science building and Science Addition, Memorial Student Center and the Administration basement and associated grounds near these facilities. Our staff immediately responded and began water remediation to minimize the damages to the various facilities eliminating thousands of dollars in repair and minimized the displacement of faculty and staff caused by this event. All facilities were ready for the start of the fall semester. Physical Plant relocated the contents and the occupants of Harvey Hall to JTC along with McCalmont Residence Hall. It also planned and designed two major projects; Harvey Hall Phase 2 and North Hall. Designed all agency projects of Bowman Hall clock tower repair and the North campus development plan and replaced the baseball dugouts with new storage areas with field turf upgrades and the multi – purpose fields had new sod installed. MPR flooring replacement and main gym bleacher upgrades providing ADA seating. Developed and issued the six year development plan for the campus. We provided comfortable safe facilities and grounds through a severely cold snowy winter. Collaborated with the City’s 13th Avenue street project, including new safety islands at second and fourth street east respectively, a bike turning lane at Broadway street intersection, and side walk lighting on the north side of the street. Physical Plant continued to be a leader in energy savings through projects; pilot projects on HVAC filter replacement, DDC upgraded, General Service and Tainter Hall roof replacements( adding roof insulation), and numerous lighting upgrades as a part of normal maintenance activities. Began the implication of a dash board software to share electrical usage by building. Physical Plant experienced and celebrated numerous retirements and employees changing occupations. Five key management positions; Business Manager, Craft worker supervisor, Campus planner, Campus engineer and Custodial Supervisor along with several Custodial Services, Building Maintenance and Administrative office staff are being recruiting new position’s respectively. The entire Physical Plant staff continues to display outstanding work and coverage through the currant vacancies with timely and efficient service during our many planned and unplanned events throughout the year. We continue to provide the back drop for campus to perform our mission. Shirley J. Klebesadel Physical Plant Department Annual Report 2013-2014 General The following are areas that we will track and benchmark as we compile data 1 2 3 4 5 6 Task 2009-2010 Work Orders Processed Small Projects Approved Small Project Dollar Amount Hours Spent on Training Kilowatts of Electricity Used Cost of Electricity Used 19,511 7 Total Fleet Mileage 20 $1,020,775 2,541 2010-2011 2011-2012 2012-2013 2013-2014 21,626 25,754 23,355 21,948 23 18 20 26 $2,015,544 $1,994,604 750 669 $1,421,566 2,481 $1,416,895 1,452 21,281,612 22,497,193 22,395,078 23,011,523 23,064,591 $1,432,602 $1,550,056 $1,658,822 $1,751,932 $1,801,560 289,736 263,031 255,237 240,565 272,772 Operating Cost per Gross Square Foot of Building Space APPA Facilities Performance Indicators Report Operating Costs Report – Fiscal Year 2013-2014 All Functions Significant Supporting Data Custodial Service Level UW-Stout Ordinary Tidiness Admin Total Cost/ Custodial GSF UW-Stout Ratio & Measures Total Cost/ Landscape Maintenance Level ModerateLevel Maintenance Energy Total Cost/ Maintenance Service Level Reactive Management Energy Total Cost/ Total Operating Costs w/o Purch Util Total Operating Costs w/Purch Util $10.1 M $12.1 M Grounds Total Cost/ Maint Acre GSF Total Cost/ Total Cost/ GSF w/o Purch Util Total Op Cost/ GSF w/ Purch Util GSF GSF w/o Purch Util GSF w/Purch Util $.31 $1.51 $.23 $1.01 $4,427 $1.61 $4.00 $4.77 Overall Averages $.55 $1.37 $.40 $2.15 $5,114 $1.63 $5.24 $7.45 Enrollment 5,00011,999 $.48 $1.56 $.31 $2.15 $5,890 $1.89 $5.54 $7.47 MAPPA $.49 $1.40 $.37 $1.45 $4,115 $1.49 $4.43 $5.84 Physical Plant Front Office, Purchasing, Fleet and Stores This year the administrative office has gone through the most change in Physical Plant due to changing of personnel. After serving for five years Jeanine Rossow, the Business Manager, transferred to UWEC. Recruitment was held and Mark Williams accepted the position and resigned after three months of service. Recruitment is process for this position. Dave Cutsforth is providing accounting assistance during the recruitment process. Kim Fisher, Office Associate was hired and after six months of service transferred to UWRF in May. This position has now been filled Kristin Bunch who will begin employment July 7, 2014. Our inventory control coordinator Mark Wenzel provided his retirement notice on June 26th and left the same day. He has completed 30 years of State service. The existing staff has done a marvelous job picking up the slack due to the various vacancies. The 2014-2015 budget for the department was developed. Developed and managed the DFD project related services for the year. Jacky Olson along with TMA team is developing the web based version of TMA. The team is working on an implementation plan to “go live” in January 2015 to the campus. IT continued to update all equipment records in TMA with accurate information, correct labels and location by having individual maintenance technician review TMA list and make updates as needed. TMA labels are being created for equipment without a label. Equipment that exists that is not in TMA is being added and labels. Equipment no longer in use is being removed from TMA. All the campus buildings will be reviewed. Key request forms, fleet authorization and fleet non-availability forms are now processed through Image Now. Electronic login records for all MSDS sheets for the department have been developed. Safety Smart “bata testing” has also been completed for Risk Management. Record keeping coverage for the campus key control inventory will be handing off these duties back to the locksmith. These duties were performed by the front office for the last two years as the locksmith position was vacant The locksmith, Kevin Moen just fulfilled his probation. These duties are slowly being transferred back as the Locksmith is trained in his new duties. Central Heating Plant This past fiscal year numerous contracts were awarded again. Fremont Ind. received the boiler water treatment contract. Robindale Energy Services received the coal contract. Pember received the ash removal contract. Ameripride Linen received our uniform contract. The 13-14 heating season had use switching to coal a few days earlier due to a natural gas line rupture in Canada. We burned 799 tons of coal in a very short period of time from January 26thFebruary 11th due to being one of the coldest winters on record. The amount of natural gas consumed during this fiscal year was 200,665 mcf. We used 145 gallons of fuel oil only for our emergency generator due to strict EPA regulations. In October the two superintendents and director traveled to Wisconsin Rapids for the annual state power plant conference. DOA provided us with information pertaining to our emergency generators, and also heating plant compliance and strategy updates. Fremont Ind. also provided a great seminar on boiler water treatment. On February 3rd and 7th Airtech Environmental Services performed carbon monoxide testing on our two coal boilers. This was done to be in compliance with the new EPA regulations being enforced. Both boilers performed extremely well operating <10% of the approved limits. On February 25th we had a one-time energy assessment done on the entire university. In general, the assessor found the facility to be well-designed and operated from an energy-efficiency standpoint. On May 13th Wisconsin DNR and DOA arrived on site to review our air operating permit and various records. All are in compliance and up to date. The yearly steam shutdown took place in May of 2013. It was from May 16th-28th. The operators performed maintenance on numerous valves and other equipment, including our emergency generator. As in the past all plant personnel attended general safety training as well as asbestos training. Lisa Pederson of Security trained everyone to be CPR/AED certified. Current project on the list with DOA is to install to oxygen monitors and Data Acquisition Systems on our two coal boilers. These will be installed in late 2014. In May we had our front end loader overhauled for the upcoming coal season. Overall the plant is in great shape and operating reliably as well efficiently. Custodial Services Mission: Custodial Services provides and maintains an environment conducive to higher education learning while servicing students, faculty, staff and external customers on the UW-Stout campus. Purpose: Custodial Services Group primarily provides cleaning services, office/equipment/building relocation services, recycling services and event setup services to customers located on 2.54 million square feet of floor space in 55 buildings across campus. By category, the Group services 22 Academic and Research buildings, 21 University Housing residence halls, 10 service buildings and 2 University Center buildings. Overview: The Custodial Service Group consists of 78 permanent positions and peaks at approximately 122 FTE, seasonally. Three Custodial Service Supervisors operate geographic portions of campus custodial operations with the entire custodial operation managed by one superintendent. The FTE quantity also includes student employees, University Dining Service employees who generally work 75% through the academic year and University Dining Service employees who generally work the entire academic year but encounter occasional schedule reductions during low cover business periods. Custodial vacancies are generally filled with limited term employees (LTE) until the Civil Service recruitment process can be completed. Our supervisors, with recruitment assistance from Human Resources staff, continue to interview multiple candidates for vacancies that occur regularly. Custodial Services is an experienced and dedicated group who serves the campus through continuous shifts seven days per week. Daily tasks include opening and closing of buildings and classrooms, cleaning of restrooms, showers, classrooms, laboratories, offices, public areas and gymnasiums. For our internal and external customers, the Group completes event set-ups and breakdowns, serves camps and conferences attendees, provides laundry service, recycling services, commencement services for UW-Stout and Menomonie High School, as well as relocation services for office, equipment and complete building furniture, fixture and equipment (FFE) inventories requested by faculty and staff throughout campus. Seasonal work, such as deep cleaning, carpet extraction and major floor refinishing occur during semester breaks. Custodial management serves as administrator for the waste removal, pest control and window/blind cleaning contracts. The Custodial Service staff consists of 41 team members who clean academic buildings, 14 team members who clean residence halls, 5 team members who clean University Centers, 14 lead workers who oversee specific groups of buildings and/or operate recycling activities, three custodial service supervisors and one superintendent. Custodial Services provides employment to approximately 60 student employees at various times throughout the year. Those students complete custodial duties, office relocations and full building relocations in academic (GPR) and SLS (PR) facilities across campus. Training: All staff members have opportunities to attend training and refresher programs provided on campus. Various safety awareness training sessions are held during the year. Among the training topics are asbestos awareness, personal protective equipment, blood borne pathogens, ladders, hazardous communications and chemicals, fall protection, slips, trips, hearing conservation, accident reporting, workers compensation, back care, ergonomics, heat exhaustion, violence prevention, snow blower safety awareness and other safety techniques and procedures. The annual State of Wisconsin Hazardous Materials and Waste Disposal Awareness Training, presented by Advance-Veolia, was held at UW-Stout on March 11, 2014. All custodial employees were trained to use our new MSDS Online Explorer program during the first and second quarters of 2014. The custodial superintendent successfully passed the State of Wisconsin license recertification tests for Asbestos Supervisor and Asbestos Inspector in November 2013. All custodial service supervisors were recertified as State of Wisconsin licensed Asbestos Supervisors in November of 2013. Projects: A major move-out and substantial cleaning activity occurred in Jeter-Tainter-Callahan (JTC) residence halls began in May of 2013, to accommodate Harvey Hall office relocations. Furniture, fixtures and equipment, belonging to University Housing, were removed. Some FFE were delivered to surplus, some were redistributed to other residence halls and some were placed into storage. Once Callahan Hall was emptied, FFE from Louise Smith Tainter House offices were moved into Callahan Hall to accommodate their building renovation. Office and classroom relocations from Harvey Hall began in June and continued to be moved into the JTC complex and other academic buildings through first quarter of 2014. To accommodate Chancellor-candidate presentations, the search committee requested that portions of Harvey Hall, including Harvey Hall Theater, be reopened in May of 2014. The custodial team revitalized Harvey Hall for that purpose. Upon conclusion of the candidate presentations, Harvey Hall was closed again. Major event setup activities in FY 2013-2014 included numerous athletic events at Sports and Fitness Center and Williams Stadium, five UW-Stout commencement ceremonies, one Menomonie High School Commencement ceremony, multiple Camps and Conference functions, STEPS, DECA, UW-Stout Career Conferences, the annual Menomonie Chamber of Commerce “Meet Menomonie” Event, University Center seminars, receptions and conferences as well as other events. Several new pieces of major custodial equipment were ordered and received. These items replaced older, high maintenance equipment and improved operational efficiency. To update equipment and minimize back injuries, Custodial Services purchased 130 new lightweight plastic-topped tables for academic functions (GPR) to replace the heavier wood compositetopped tables. A new 2015 cargo van has been ordered for the academic custodial group (GPR) and is expected to arrive early in FY2014-2015. Summary: We will provide first class service to our university while focusing on the overall mission statement, vision and goals of the Physical Plant. The services we provide will promote an environment that aligns itself with our student’s educational and cultural goals. Crafts Workers Mission: The UW-Stout Building Maintenance Department provides and maintains a safe and comfortable working environment for students and staff in all University Buildings. Overview: The building trades group offers an expertise to the department that is pivotal to maintaining a campus of this size. Over the past year the trades have completed and number of projects to improve facilities need for a state of the art learning environment. The group shows a great deal of pride in their work and that is reflected in the various projects around campus. We hired a new Craftsworker Supervisor and Locksmith and saw the retirement of a Facilities Repair Worker during the past 12 months. Safety: Safety is always a top priority within the group. The safety toe shoe program gives money to employees to aid in the purchase of shoes. Members of the group received asbestos O & M refresher courses. All staff attended the annual Safety Training sessions for 2 days. Purpose: Here in the Building Maintenance and Crafts area we continue to provide service and support to all aspects of the campus. These include: 1. Provide proper heating, cooling and ventilation 2. Service and maintain all electrical, plumbing and steam systems 3. Provide services for remodeling projects in Academic as well as Student Life Services buildings 4. Provide services and support for all campus departments Training: Department-wide training issues completed during the last fiscal cycle included: 1. Asbestos Operations & Maintenance- All full time & LTE staff 2. Asbestos Supervisor Refresher- Facilities Repair Worker – Adv. & Supervisor 3. National Electrical Code Update – Electricians 4. Continuing education credits - Plumber Project Summary: Some of the larger projects that were completed this year include: 1. Curran Hall 11 Remodel 2. Began fire door inspection in all buildings 3. Inspected and repaired steam piping in many steam pits 4. Removed many items out of Harvey Hall for salvage and surplus 5. LIT front entrance upgrade in Millennium Hall 6. Baseball field dug out replacement and expansion 7. JTC fit-up for Harvey Faculty 8. Harvey Hall move-out WORK ORDER SUMMARY Fiscal Year 2013/2014 Total hours captured in work orders Total Charge-backs Actual work orders completed Quantity 17,050 $1,310,914 3605 Physical Plant Building Maintenance Mission Statement: The UW-Stout Physical Plant Building Maintenance Department will: Maintain University Academic facilities and Equipment Maintain University Housing facilities and equipment Maintain University Dining service facilities and equipment Maintain University Centers facilities and equipment Initiate timely response to service requests and emergencies Completed prescribed Preventive Maintenance Ensure minimal disruption to the learning Environment Maintain a safe and comfortable working environment for students and staff in all University buildings. Overview: The Physical Plant Building Maintenance Department provides direct or indirect service to all 67 buildings consisting of approximately 2,500,000 square feet. Residence hall ages range from Tainter Hall, built in 1955, to Hovlid Hall remodeled in 2010. Fleming Hall, built in 1962, renovation in 2012. Currently McCalmont Hall built in 1963 is receiving substantial electrical, mechanical, environmental and FF&E renovation in 2013. Physical Plant Building Maintenance is staffed by 5 full time Facilities Maintenance Specialists-Advanced, 6 Full time Maintenance Specialists, 1 fulltime HVAC/Refrig Specialists-Advanced, 1 Electronic Technician – Senior( LTE), 2- I.S. Business Automation Specialist – Senior, 1- Buildings & Grounds Supervisor – HVAC, 1 Buildings & Grounds Assistant Superintendent- Building Maintenance. Student workers ranging from 6 to 50+students are hired for maintenance & painter employees, depending upon the season and workloads. SAFETY: Safety continues to be the most important aspect in our jobs. Whether it is student, faculty/staff or personal safety, we strive for perfection. Continuously respond to the 24/7 emergency maintenance phone Respond to Campus Police as requested Accompany state and local authorities on all mandatory inspection of regulated equipment and correct deficiencies found. Attend all mandatory safety training provided by risk management annually Provide all Personal Protection Equipment /training for all Department members Additional Goals: Here in Building Maintenance area we continue to provide service and support to all aspects of the campus. These include: 1. 2. 3. 4. 5. 6. Provide proper heating, cooling and ventilation. Service and maintain fire alarm systems. Respond to campus elevator emergencies. Maintain academic building in a safe and comfortable state. Maintain Housing and Dining facilities in a safe and comfortable state. Provide services and support where needed on campus. TRAINING: Department-wide training issues completed during the last fiscal cycle included: 1. Asbestos Operations & Maintenance- All full time, LTE and Supervisor members. 2. Asbestos Inspector Superintendent of Buildings and Grounds (BGS). 3. Asbestos Supervisor/Contractor - Superintendent of Buildings and Grounds (BGS) & Buildings & Grounds Supervisor-Hvac. 4. DDC Controls Training - (BGS-HVAC & IS Business Automation -Senior) Individual training requirements to upgrade personnel skills and knowledge relating to job function: 1. 2. 3. 4. 5. Pool Operators Certification (FMS-Adv) Asbestos Supervisor/Contractor – Facilities Maintenance Specialist (FMS). Allerton Controls Training (Hovlid /NPT.) HVAC/Refg.-Spec. Adv. Refrigeration & Air Conditioning Training HVAC/Refg.-Spec Adv. Cooling Water Management – all new employees. PROJECT SUMMARY: The recently completed and in process projects include: 1. Complete the upgrade of all pneumatic controls for AHU’s in South Hall to DDC for the fall/spring of 2014/2015 2. Chilled repairs are in process for #3 chiller at the Central chiller plant. 3. Continuing all repairs for Emergency Generator on campus due to issues found during last summer outage. 4. The replacement and installation a new style 3M filter in Jarvis Science Addition’s two large AHU’s has shown exceptional result. After a 10 month trial we had to replace the filters installed last Sept. 6th. Air Quality is very good and the energy savings thus far is $5,680 between both AHU’s. This does not include material or labor cost savings due to filter changes for the 12 month period. Have advanced this program to other unit on campus. 5. Project has been completed for Phase 1 of Campus DDC upgrade to eliminate all FPU’s 6. Moving forward with plans and ideas for Phase 2 of Campus DDC upgrade to eliminate all NUC’s. This will now allow us to look to the future for DDC upgrades to AHU’s and building automation and energy efficiency. Also looking at future projects for BTU meters for Condensate and chilled water for future building monitoring of heating and cooling costs. This will allow us to feed additional information into the campus Dashboard. 7. Campus Dashboard is up and running with some minor issues. 8. Campus facilities are being upgraded to a graphical view of the unit and current running status on the computer system. We are about 80% completed with upgrades of the programs from numerical information to graphical. GROUNDS MISSION The UW-Stout Grounds Department provides services that provide a functionally aesthetic campus that meets the needs of the university. SAFETY Safety to all university faculty, staff and students is at the forefront of the Grounds Department. We provide and attend safety training to all staff. We look for problem areas around campus on a continual basis, and prioritize projects accordingly. TRAINING Training our department has completed during the last fiscal year include: 1. Asbestos Supervisor Update- Supervisor of Buildings and Grounds (SBG) 2. Asbestos Inspector Update- - Supervisor of Buildings and Grounds (SBG) 3. Safety Training 4. Professional Grounds Management Society Conference PROJECT HIGHLIGHTS 1. The Multi-purpose field had new sod installed. The project totaled 22 semi loads of sod. 2. Upgrades to the irrigation systems to a new central control ET system. 3. Finished repairs to the baseball infield The Grounds Department has an excellent hard working staff, which strives to achieve our objectives of safety, function and aesthetics. Facilities Planning and Engineering MISSION: To provide the University and Community with the highest quality facilities and physical environment for learning, living and working, by maximizing the available resources To fulfill our mission and established strategies and objectives, the following have been completed this past fiscal year. 1. Completed and managed construction on 21 projects valued at $2,999,604. Refer to tables on following pages for a list of projects. 2. Received funding approval for 26 small projects totaling $1,994,432. Refer to tables on following pages for a list of projects. 3. Managing 4 major and/or all agency projects in progress, valued at $47,190,000, as of July 1, 2014. Refer to table on following pages for a list of projects. 4. Campus Planning a. Lead UW-Stout design team for Harvey Hall Renovation including A/E design review meetings, coordination with UW-System and DSF. Constructions to start fall of 2014. b. Planning and completion with UW-System for the 2015-2021 Campus Physical Development (6-year) plan. c. Facilitated laboratory modification requests and funding. Six projects funded. d. Lead design team for the master plan study for the North Campus Site Development. Obtain approval from the City of Menomonie to vacate 3rd Street West. With UW System selected BWBR and Rettler for its design services. e. Successful acquire one residential property within the campus boundary. 5. Continued implementation of the Residence Hall Renewal Plan for the next 12 years valued proposed at $78,060,000 at today’s cost. a. The third building under the renewal plan, McCalmont Hall Renovation is scheduled to be August 2014. b. North Hall A/E request was revised in June 2014 as the next renewal hall project. 6. Managed the construction phase of: a. $385,000 13th Ave. Improvement completed August 2013. b. $8,400,000 McCalmont Hall Renovation. To be completed August 2014. 7. Facilities Data and Recordkeeping a. Updated FacMan data for all General Purpose Revenue (GPR) buildings and Program Revenue (PR) buildings. b. Updated campus floor plans for new and renovated buildings. c. Updated the campus Central Data Request (CDR) records. d. Submitted reports to UW-System, and or DSF on the following topics: • Building Inventories • Energy Cost Reduction Plans • Municipalities Services Payments e. Provided annual report for the WPDES Municipal Separate Storm Sewer System General Permit- storm water management plan. 8. Project Summary Tables: Projects Completed in 2013-2014 Small Projects Submitted and Funding Approved in 2013-2014 Major and All Agency Projects in Progress as of July 2014 Projects Completed in 2013-14 Project No. All Agency & Major Projects Budget Project Name Submitted Budget Projects Closed 13I1M Tainter Hall Roof Repl areas A1a & b 39,600 Sep-13 13H3K Tainter Hall Roof Repl areas A1a & b 39,000 Sep-13 13E3T Child Study Center Fence 17,000 Aug-13 13E3N Heritage Hall Fire Door replacement 95,000 Jan-14 13E2O Comm. Tech. 2013 Office Remodel 148,000 Aug-13 13C2S 13h Ave. Improvement Assessment 12K1A Heritage Hall rm 240 Renovation 180,352 Aug-13 12I3N G.S. Roof Repl Areas B1-B3 175,700 Aug-13 12I1T 2012 Multi-Bldg. Exterior Repairs 78,000 Jun-14 385,500 Aug-13 12H4O Johnson Fieldhouse Sound System 182,652 Sep-13 12H4L Campus DDC Upgrade 164,300 Apr-14 12H4K Administration Window Replacement 181,040 Oct-13 12H1U LST House HVAC Replacement 149,200 Oct-13 12G3C A/E On Call 180,500 Apr-14 12D3Z.1 S&FC MPR Floor Replacement 421,000 Jun-14 12D3Z Johnson Fieldhouse Bleacher Repair 117,000 Sep-13 12B1B Asbestos Abatement for Maint. 41,500 Nov-13 12A2D LST House Elect. Distrib. Replacement 152,000 Oct-13 11J1M Williams Stadium Constr. Repairs 149,760 Aug-13 11E1D Sports & Fitness Pool Cover 24,500 Jul-13 11D2D Stormwater Erosion Materials 78,000 Oct-13 3 of 20 Subtotals 923,500 2,076,104 Small Projects Submitted and Funding Approved 2013-14 Project No. Project Name Submitted Budget 14F1Q Primary Elect. Feeder 704 repl. Pit 4 to McCal 14E5P Price Commons Special Diet Pantry rm 224 14E5K LLC - Fluid resurface (south 1/2) 124,400 14E1Q LLC - EDPM roof repl. (north 1/2) 104,600 14E1I Bowman Hall rm 304 Veterans Center 49,000 14D1X 2014 Sidewalk Safety Improvements 45,000 14D1P Heritage Hall 419 Renov (Weidner Center) 49,972 14C3H Antrim Hall Conversion to Triple Beds 49,280 14C2N GPR Multi Bldg. Exterior Repair 78,000 14B1X Chiller #3 Vibration Repair Projects Closed 105,800 48,700 49,500 13L2E LLC Group Study Center 54,500 13L1L MPR Athletic Curttain Replacement 176,000 13L1F Child Family Center Ramp Removal 53,230 13K3P System Wide H.P. Oxygen Monitors/DAS 80,000 13K30 Fryklund Hall - Tech Lab 214 136,400 13K2J AA Exh Fan Disconnects & VFD's 48,900 13K2O Asbestos Abatement for Maint. 41,500 13K2N Bowman Hall Remodel Rm 105, 106, & 107 45,150 13K2G HP #4 Boiler Blow Down Piping 16,900 13J1N Library Entrance Replacement 97,000 13I4N Voc Rehab Classroom 332 13I4H Jarvis Tech. & U.S. Equip. Platform 13I4G Jarvis Tech. 157 Flooring Repl. 151,000 170,000 110,000 31,000 13I3O Comm Tech Curtain Wall Replacement 13I1M Tainter Hall Roof Repl areas A1c & d 39,600 Sep-13 13H3K Tainter Hall Roof Repl areas A1a & b 39,000 Sep-13 Total 26 1,994,432 Major and All Agency Projects in Progress (July 2014) Project No. Project Name Approved Budget Project Status $28,000,000 Awaiting Contract, Construction est. to start Sept 2014 thru Dec 2015. 11I1X Harvey Hall Renovation: Phase 2 12E1H Bowman Hall Bell Tower Renovation $8,900,000 Changed to a Major Project, Construction est. summer 2015. 12G3K McCalmont Hall Renovation $8,400,000 Construction underway, Completion Aug 2014 14B1X North Campus Site Development $1,890,000 Design underway, Construction est. summer 2015. Total 47,190,000