DIAGRAM #1
CUT-IN REGLETS 1" MIN. DEEP SEALED
WITH M-BOND ADHESIVE ON BOTH SIDES.
PRESATURATE EDGE OF TOPCOAT R
FLASHING FABRIC IN MAJORSEALTM LIQUID
FLASHING AND TUCK INTO JOINT
COUNTERFLASHINGS BY OTHERS
TOPCOAT R FLASHING FABRIC
TARGET APPLIED OVER SCUPPER
FABRIC ON BOTH SIDES. SEE
DIAGRAM 1
OVERLAP TOPCOAT R FLASHING
FABRIC 2" MIN. INSIDE SCUPPER
TOPCOAT R FLASHING FABRIC
INSIDE SCUPPER TO EXTEND OUT
OPENINGS ON BOTH SIDES. SEE
DIAGRAM 1
SURFACE GRANULES APPLIED TO
TOP LAYER OF MAJORSEALTM
LIQUID FLASHING
TOPCOAT R
FLASHING FABRIC
BASE LAYER OF
MAJORSEAL TMLIQUID
FLASHING
GAF SBS MODIFIED BITUMEN
OR BUILT-UP GRANULE
SHEET.
2" MIN.
2" MIN.
NOTE:
1. IF GAF GRANULE MEMBRANE IS LEFT EXPOSED OVERNIGHT BEFORE INSTALLING MAJORSEAL TMLIQUID
FLASHING, A TEMPORARY NIGHT SEAL MUST BE INSTALLED. THE NIGHT SEAL MUST BE COMPLETELY
REMOVED BEFORE INSTALLING THE FLASHING.
R
FIELD FABRICATED THRU WALL
MAJORSEAL
LIQUID FLASHING
OVERFLOW SCUPPER FLASHING DETAIL
TM
1 Campus Drive.
Parsippany, NJ 07054
WALL & CURB
SERIES
DRAWING #
SYSTEM
322
MM
SCALE
N.T.S.