TIPS Meeting 20 March 2003, 10am, Auditorium 1. JWST Status Peter Stockman 2. STIS Status Paul Goudfrooij 3. Slitless Spectroscopy* Jeremy Walsh * No hardcopy provided Next TIPS Meeting will be held on 17 April 2003. Space Telescope Science Institute JWST S&OC JWST S&OC Contract Peter Stockman TIPS March 20, 2003 1 S&OC Proposal Space Telescope Science Institute JWST S&OC • Original Proposal submitted November 2001 − Proposed cost comparable to unsolicited proposal, (330M w fee over 10 years) − Project internal estimate: 140M (based largely on SMEX & MIDEX PI missions, inexpensive flight ops systems) − Extended review of proposal assumptions with Project in spring • Revised proposal submitted on schedule (16 Sept.) to meet 176M target. Reductions achieved by the following assumptions: • Govt. provides groundstations -- probably DSN • Govt. provides I&T test system as basis of flight operations ground system (STScI was to provide originally) • Govt. provides SI, OTE, S/C flight ops analysts for launch + 1 yr • Just-in-time development schedule (no phased development to support SI, OTE, S/C dev.) • No operations or science I&T support for SI, OTE, S/C. • Reduced support to Project and SIs but w. overguides 2 Status of negotiations (began Jan. 15) Space Telescope Science Institute JWST S&OC • Contract negotiations began in mid January − Project puts back: management oversight, Project support, special studies, PRD Ops. (~ 5M) and fenced these costs off. − Project poses a new Target of 159.5 (without fee) − AURA can meet new Project target: • • STScI roles are reduced significantly compared to HST (and Chandra and SIRTF experience) » SI support » Commissioning planning for SIs and spacecraft. » Calibration software » Calibration analysis • • Assumes TRW develops I&T system near that needed for flight ops. Reduced planning system capabilities: no linked observations, routine scheduling of parallel calibrations, manual planning of the weekly calendar • Late GO funding for Cycle 1 (Grants office startup delayed) Contract will be revised after results of replan: reduced instrument complement?, delayed schedule. 3 Key Assumptions Space Telescope Science Institute JWST S&OC • SI s: The three JWST instruments will have the capabilities and complexity outlined in the ASWG and Project Scientists recommendations. In particular: - The NIRCam will be a wide field, infrared camera with a limited set of fixed-band filter combinations (<20) and several elements used exclusively for wavefront-sensing. - The NIRSpec will be a multi-object, single-order spectrograph with addressable apertures and a small number of fixedposition gratings (< 6). The MIRI will have two elements: a camera with a small number gratings and potentially a fixed pupil mask and Lyot stop for coronagraphy; a slit spectrograph with R ~1500 and a small number of fixed-position gratings. All three instruments will have a single target acquisition mode (including PEAKUP and/or PEAKDOWN). All three instruments will have a small number of common readout schemes (<3) and a common data format. - - 4 More Key Assumptions Space Telescope Science Institute JWST S&OC • The S&OC systems will not support parallel activities. These include parallel calibration, pure parallel or coordinated parallel observations and parallel modes within instruments. Level 2 requirement 3.2.15.4 is applicable to the Observatory. • The Fine Guidance Sensor will be sufficiently capable to enable guide star availability and selection to be done in an automated fashion by the S&OC. This assumes a wide field, highly capable guider that can satisfy the Level II requirement (3.2.15.2.2) for the 95% probability of guide star acquisition. 5 Many Miscellaneous Space Telescope Science Institute JWST S&OC • The peak flight to ground data rate will be 25 GB/day. • Level 1 data products will be available at L+3 months. Level 2 data products will be available at L+6 months. • Targets of Opportunity are not supported within the time period of this contract. • Etc. (about 70 such assumptions) 6 Current Status Space Telescope Science Institute JWST S&OC • Technical aspects of contract appear to be satisfactory to NASA • 2-3 week period to acquire needed signatures 7 Replan Status Space Telescope Science Institute JWST S&OC • Challenge was to meet: − Stringent budget limits in FY04-07 − Launch date as close as possible to 2010 − Overall cost of 1.6B • NASA HQ has settled on Option 4i − Launch in August 2011 − About 110M cut in US instruments (down from ~ 160M) • No MIRI • 1/4 of NIRCam FOV, 1/8 NIRSpect FOV − Reduced primary mirror area (but meets spec) − Reduced testing plan − Challenged Project to save 40-50M in other areas to help restore instruments. 8 SWG & Project Studies Space Telescope Science Institute JWST S&OC • SWG considering merging NIRCam and Canadian FGS: − Potential saving of accommodations (mass, computer) − Elimination of short wavelength tunable filter − Shared electronic and detector procurement • Project finding it difficult to achieve matching savings • Other possibilities: − Loss or reduced short wavelength performance. − Increased role for ESA in MIRI • Emergency meeting for SWG in April 10,11 9 SPACE TELESCOPE SCIENCE INSTITUTE Operated for NASA by AURA STIS Status Report Paul Goudfrooij • Group News / Reorganization • Unusual Target ACQ Failure • Items for upcoming Phase II Update – Planned New Apertures – Corrections for CTE loss Group Reorganization • Two IS’es on well-deserved sabbatical: – • Jeff Valenti reassigned to JWST / NIRspec (Jan 03) – • But will finish a few STIS assignments Scott Friedman (COS) helping out with a few tasks – – – • Nolan Walborn (Sep 02) and Kailash Sahu (Mar 03) CCD Dispersion Solutions CCD & MAMA Spectroscopic Sensitivity Monitors SM4 Backup to Tom Brown Claus Leitherer (COS) to help out with – Phase-2 reviews of Cycle 12 MAMA programs (if more than we can reasonably handle in Spectrographs Branch) TIPS Presentation March 20, 2003 Paul Goudfrooij 2 Group Reorganization • “New” ESA Instrument Scientist: Jesús Maíz-Appelániz – – • • • User Support Lead IS ETC & APT oversight New Pipeline Lead IS: Charles Proffitt New Calibration Lead IS: Linda Dressel New Information Lead IS: Bahram Mobasher TIPS Presentation March 20, 2003 Paul Goudfrooij 3 Unusual Target ACQ Failure • Target ACQ of Spectroscopic Sensitivity Monitor Visit on March 6 failed: No Flux in the Lamp Image 1 2 1 2 3 3 Π • Ο ∃ direct measurement to measure current across lamp Hint of lower OCLP30VC, but not statistically significant Slit wheel / MSM resolver counts identical to other ACQs Shutter ajmqcb+mncl+ajmqcb sequence occurred nominally All other mechanisms in their nominal positions Preliminary conclusion: Lamp did not fire (HSTAR closed) ACQs after the problematic one were all OK to date – • • • • • TIPS Presentation March 20, 2003 Paul Goudfrooij 4 New “Pseudo-Apertures” • • • • FUV-MAMA first-order spectroscopy at detector location with low dark – ~ 2’’ above bottom of detector – Reduction of dark current by factor of 5 – 52x0.05D1, …, F25QTZD1 Improvement of Fringe Flats at E1 positions – Important to align fringes in flat with those in target spectrum – 52x0.1 slit (best for defringing) location is offset in dispersion direction from wider slits – New ‘E2’ positions will place target slightly off-center in slits ≥ 0.2 arcsec wide New WEDGEA0.6 position for 50CORON Will provide POS TARGs to GOs for cycle 12; Apertures to be implemented in next APT build. TIPS Presentation March 20, 2003 nominal new Paul Goudfrooij 5 Correcting CCD Spectroscopy for CTE Loss Amp C STIS CCD: Nominal Readout Direction Amp D • 4 Readout Amps (1 / corner) Nominal Clocking Direction • Bi-directional Clocking yields CTI ≡ 1 – CTE: 1 δ(fluxD / fluxB) CTI = δY 2 Measured using “Sparse Field Tests” TIPS Presentation Axis2 (Y) • Nominal Amp: D (lowest RN) Parallel (virtual) overscan Amp A Serial overscan March 20, 2003 Axis1 (X) Serial overscan Paul Goudfrooij Amp B 6 “Sparse Field” Tests • • Sparse fields to ensure that sources do not overlap, in which case (e.g.) PSF wings could fill traps for sources along the readout direction Two varieties: (i) “Internal” Sparse Field Test – – Annual series of lamp images through narrow slits, projected at 5 positions along columns (or rows) Designed to represent “worst–case” point source spectroscopy (should be no background to fill traps) TIPS Presentation March 20, 2003 Paul Goudfrooij 7 “Sparse Field” Tests • (ii) “External” sparse field test (annually) – A. Imaging: ¬ ¬ ¬ – Sparse outer field in NGC 6752 CVZ target (‘cheap’ observing time; yields range of backgrounds) 3 exposure times; 50CCD mode B. Spectroscopy: ¬ ¬ ¬ ¬ Young open cluster NGC 346, in nebulosity CVZ target Slitless; 3 exp. times; G430L [O II] λ3727, Hβ, [O III] λ5007 lines in nebulosity provide three convenient, ~constant “sky” levels per spectrum TIPS Presentation March 20, 2003 Paul Goudfrooij 8 External Sparse Field Test: Imaging CTI Analysis Clear dependence on background level (“sky”) • Slope systematically flatter with increasing flux • “Sky” presumably fills traps in bottoms of potential wells, mostly affecting transfer of small charge packets. • Suggests CTI bck α ∝ exp – signal TIPS Presentation March 20, 2003 Paul Goudfrooij 9 The Strong Effect of Background: Gain=1 vs. Gain=4 • Background level in spectroscopy mode typically low, dominated by dark current – Need to account for spurious charge of the STIS CCD CC DR ead CC TIPS Presentation March 20, 2003 out sh D flu Paul Goudfrooij 10 Functional Dependence on Signal and Background Levels • To be done separately for imaging and spectroscopy Spectroscopy Imaging CCD Column Number • • CCD Row Number Spectroscopy: – ISF; ESF in slitless mode – CCD Sensitivity monitor data Imaging (cf. Cal. Workshop ‘02): – ESF & Full-field sens. monitor TIPS Presentation March 20, 2003 Paul Goudfrooij 11 Functional Dependence on Signal and Background Levels • Iterative Process for Spectroscopy – Parameter space covered by ESF test at a given epoch is limited – Sensitivity monitor: good coverage of signal levels, but not of sky ¬ G230LB data allow suitable cross-comparison with MAMA G230L AGK+81D266, G230LB TIPS Presentation March 20, 2003 Paul Goudfrooij 12 Time Constant of CTI Evolution • • Need several datasets, each with same signal & background level Need datasets covering long baseline in time ⇒ ISF data – Have to correct for signal & background dependence prior to fitting 60 e– CTI = CTI0 + { 1 + 0.243 [± 0.016] (t – t0) } 120 180 500 3400 TIPS Presentation (with t in yr) CTI data from Tom Brown March 20, 2003 Paul Goudfrooij 13 Final CTI Correction Formula (For Point-Source Spectroscopy) • Define background (sky) and epoch parameters: yr = (MJD – 51765.25) / 365.25 (i.e., relative to 2000.6) bg = max(BACKGROUND,0) + 0.5 for CCD Gain = 1 + 5.0 for CCD Gain = 4 • Functional form producing best fit to the data: ( CTI = 0.0467 GROSS – 0.720 ∗ exp –3.85 • bg GROSS 0.17 )∗ (1 + 0.243 yr) Implementation into the pipeline: ¬ ¬ Formula parameters into CCD table reference file (new columns) 1-D extraction step (x1d) to correct for CTE by default for CCD data (CTE correction step switchable) • For Cycle 12 Phase II, provide downloadable IRAF script to calculate correction factor for a given net & background level. TIPS Presentation March 20, 2003 Paul Goudfrooij 14 Quality of CTI fit CTI Correction good to ≤ 7% ⇒ Spectrophotometry good to ≤ 1% @ 2000.6 TIPS Presentation March 20, 2003 Paul Goudfrooij 15 The Strong Effect of Background: Gain=1 vs. Gain=4 Complex behavior at low signal levels – – – CTE-like behavior obvious, but details not quite understood Notice somewhat different behavior for B vs. D amps Renders low-signal CTI values somewhat uncertain TIPS Presentation March 20, 2003 Paul Goudfrooij 16