INS News TIPS/JIM Meeting December 15, 2011 •
•
•
Please email Margaret Meixner if you are available to help with the INS Contribution (Drinks Station) to the STScI ERC Holiday Party, Tuesday, December 20 at 3:00 p.m. If you are attending the AAS meeting in January 2012, please advise Jason Kalirai (JWST) or the HST Mission Office if you are available to help out and spend some time at the STScI booth. ITSD has rolled out a new Leave Request calendaring system. See Margaret Meixner’s email from earlier this week. ITSD will present and discuss the tool at the next TIPS meeting in January. JWST Status
Massimo Stiavelli, December 15th,
2011
Space Telescope Science Institute
Agenda
 
 
Mission Progress
STScI Progress
Mission Progress
 
 
 
NGAS delivered the first release of the flight software.
Completed electronics simulator for ISIM
Installed Helium shroud floor at Johnsonʼs Chamber A
Schedule Milestones  
Completed four HQ tracked Project milestones
Milestone
Due Completed
Prototype Exposure Time
Calculators
June 2011
May 9, 2011*
WaveFront Software
Subsystem Integration
November 2011
September 27, 2011**
Proposal & Planning
Subsystem Design Review 3
November 2011
October 31- November 1
Data Management
Subsystem Design Review 1
December 2011
December 5-6
* Objective was to release in advance of the Frontier Science
Opportunities Workshop, June 6-8.
** Early completion resulted from mitigation actions to address a late
start to WAS, MCS & WEx integration. Progress at STScI
 
Data Management System
 
 
 
SODRM  
 
 
SDR review passed in early december
Built 0 completed: integration of up-the-ramp pipeline module and workflow
manager.
Ongoing work involving most of WIT staff.
Karl Gordon gave a presentation to the SWG soliciting their input.
MIRI Acceptance Review
 
 
STScI staff participated to the MIRI acceptance review kickoff meeting.
Actual delivery scheduled for April (Project Milestone)