Piloting of Siemens PostCap™ Technology, 9,000 hours of Operational Experience including Mongstad Technology Qualification Program Michael Horn, Albert Reichl, Torsten Schliepdiek, Henning Schramm Siemens AG Germany 1/19 Table of Contents 1 Executive summary ............................................................................................................ 3 2 Introduction ........................................................................................................................ 3 2.1 Next step in CCS deployment: Scale up to full scale.................................................. 3 2.2 Requirement for technical qualification and verification ............................................ 3 3 The Siemens PostCap™ technology .................................................................................. 4 4 PostCapTM pilot plant location and set-up .......................................................................... 5 5 4.1 Pilot plant design ......................................................................................................... 6 4.2 Operational conditions of the pilot plant ..................................................................... 8 Pilot plant operation.......................................................................................................... 10 5.1 Test program ............................................................................................................. 10 5.2 Results ....................................................................................................................... 11 5.2.1 Functional performance ..................................................................................... 11 5.2.2 Operability ......................................................................................................... 13 5.2.3 Process model validation ................................................................................... 13 5.2.4 Material tests ...................................................................................................... 14 5.2.5 Emission measurements & liquid analysis ........................................................ 14 5.2.6 Verification of reclaiming technology ............................................................... 15 5.3 Summary ................................................................................................................... 16 5.3.1 Pilot plant operation with coal and gas fired flue gas ........................................ 16 5.3.2 Technology Qualification Program (TQP) for CCM project (gas fired) ........... 16 6 Scalability and constructability ........................................................................................ 17 7 References ........................................................................................................................ 17 8 Acknowledgements .......................................................................................................... 18 Permission for use .................................................................................................................... 19 Disclaimer ................................................................................................................................ 19 2/19 1 Executive summary The paper summarizes the more than 9,000 hours of operational experiences at the PostCap™ carbon capture pilot plant at E.ON’s Staudinger power plant near Hanau/Germany. The pilot plant started operation in 2009. During the first three years of operation the process was tested and its technical features were proven and further optimized, e.g. with respect to operability and energy demand, by using a slip stream from the flue gas of a coal fired power plant. In 2012 a gas burner was installed as an alternative source for CO2, and the pilot plant was operated for approx. 3.500 h on a flue gas composition equal to a gas turbine power plant. In this period of time a Technology Qualification Program (TQP) for the Carbon Capture Mongstad project in Norway was completed together with Statoil/Gassnova to prove the maturity for a full scale implementation. Key criteria for the TQP were the validation of the process model, verification of specific thermal optimization concepts and supporting technologies, reclaiming technology, materials performance and the effectiveness of the demisting technology. With the help of the results from the pilot plant operation a scale-up of the technology into a full scale application is possible. Front End Engineering Design (FEED) and concept studies were already executed for several projects. 2 Introduction 2.1 Next step in CCS deployment: Scale up to full scale While fossil power is still one of the main sources for electrical energy generation for the coming decades, one of the biggest challenges to the fossil energy industry in the 21st century is the development of economically feasible carbon capture technologies to mitigate climate change and also co-generate CO2 for usage e.g. in enhanced oil recovery (EOR). Several technologies for CO2 reduction have been developed – pre-combustion, oxyfuel and post combustion. The latter usually employs a chemical absorption – desorption process, but with different solvents. Siemens has chosen amino acid salt as solvent for the development of a post combustion capture process (details see chapter 3). Regardless of the specific technology, transfer to full scale is challenging, since the dimensions are huge. A step in between (demonstration plant) would be feasible, but these projects are also capital intensive. Thus transfer from pilot to full scale is one alternative, meaning that pilot experiments have to be thoroughly executed, monitored and evaluated [1] [2] [3]. 2.2 Requirement for technical qualification and verification To gain security for the scale up of the carbon capture technology to full scale and resulting operational requirements it is necessary to validate the technology in pilot scale projects in an industrial environment. Laboratory experiments have to be performed beforehand and also as parallel supporting activities but they are limited in their significance, mainly with regards to size and synthetic conditions. The resulting focus during pilot plant operation can be summarized as follows: - Prove of concept: the selected process of carbon capture is validated with authentic industrial flue gas in a stable operation mode 3/19 - Prove of performance: the performance of the carbon capture process is measured (e.g. capture rate, long-term solvent stability and degradation, heat rate, power consumption, emissions) - Prove of operability (e.g. plugging, foaming) - Prove of construction material concept - Optimization of function and design of mechanical equipment - Validation of simulation models to ensure reliable process design results for upscaling - Validation of control concept 3 The Siemens PostCap™ technology Siemens has developed a post combustion carbon capture process, the Siemens PostCap™ process based on an amino acid salt (AAS) solvent (aqueous solution). The process is capable of separating at least 90% of the CO2 contained in the flue gas from coal, oil or gas fired power plants as well as from industrial sources. Figure 1 shows the PostCapTM process configuration in general. Decarbonized flue gas Solvent reclaiming CO2 compression CO2 absorption CO2 desorption Flue gas inlet Figure 1: Siemens PostCapTM process configuration The raw flue gas is cooled in a flue gas cooler and then conveyed by a blower through the absorber. The gas leaves the top of the absorber as decarbonized flue gas. The solvent meets the flue gas in the countercurrent absorber, where CO2 is selectively absorbed by a chemical reaction. The “rich” solvent (loaded with CO2) is pumped from the absorber bottom and heated up in a “rich/lean solvent heat exchanger”, before it enters the top of the desorber column. At the desorber bottom, the chemical bonding of CO2 is reversed at a higher temperature (which is provided by steam in a reboiler). Thus a mixture of CO2 and water is stripped out. The water is condensed at the desorber top condensor, whereas the remaining CO2 is compressed (and if applicable purified) for transport, such as by pipeline, and further use. The “lean” solvent (which has been relieved of most of its CO2) is pumped from the desorber bottom, cooled in two steps (“rich/lean solvent heat exchanger” and “lean solvent 4/19 cooler”) and then fed to the absorber top. A small slipstream of cold solvent is taken downstream of the lean solvent cooler for reclaiming. The purified solvent is fed back upstream of the lean solvent cooler. The particular advantages of using an Amino Acid Salt as solvent are: Application of an environmentally friendly, biodegradable, non-toxic solvent Minimal solvent emissions due to a very low vapor pressure Good solvent stability against various degradation mechanisms, particularly against oxidation and - as a result - low solvent refill need Ease of handling by power station operators and personnel (inflammable, nonexplosive, no inhalation risk). During process operation amino acid salt solvents (as well as amines) form degradation products by thermal stress or reactions with SOx, NOx and oxygen contained in the flue gas. To offset this degradation, the Siemens PostCapTM process applies a proprietary two-step reclaiming process to minimize solvent losses, hence operation costs. SOx contaminated solvent is fully recovered, the blocking of the solvent is fully reversed, and a sellable sulfur product is generated. In principle any SOx content in the flue gas is feasible for PostCapTM, however in practice a reasonable level has to be determined based on economic considerations (cost of conventional flue gas desulphurization vs. cost of reclaiming). Furthermore a highly selective separation of the amino acid salt solvent from other byproducts is applied in the second reclaiming step and thus a high recyclability assured. Each step of the reclaimer can be operated independently (either continuously or batch-wise), which allows tailor-made solutions for client’s needs. 4 PostCapTM pilot plant location and set-up During the process development for PostCap™, Siemens got the opportunity to build a pilot plant with a CO2 capacity of up to 40 kg/h at E.ON’s coal fired power plant Staudinger near Frankfurt/Main in Germany. The location close to the Siemens R&D and chemical engineering group in Frankfurt Industrial Park Hoechst is of great advantage because a transfer of people and material between both sites is possible on short notice, and the knowledge and experience of the Siemens PostCap™ and chemical process experts can be used to a maximum extent. Also the laboratory scale carbon capture plant and the reclaimer designed for the Pilot Plant operation are located at the Siemens premises in Frankfurt. Figure 2: Location of the pilot plant at E.ON’s Staudinger Power Plant (red marker) and Siemens laboratory in Frankfurt/Hoechst (blue marker) (Source: OpenStreetMap) 5/19 4.1 Pilot plant design The predominant target for the design of a pilot plant is to choose the dimensions in a way that the achieved results are reproducible and can be used to set up and verify a process calculation model. On the other hand, the pilot plant should not be too large in order to save cost and construction time. Examples for the main equipment are given below. A simplified process flow diagram (PFD) is shown in Figure 3. The pilot plant features more than 150 measuring points for monitoring, control and optimization. Furthermore, gas samples (both online and isokinetic) and liquid samples can be drawn from several locations. Since compression is a well-known technology, it does not have to be studied, thus the CO2 from downstream the desorber condenser is fed back to the power plant. Condensate Separator Decarbonized Flue Gas CO2 Gas Lean Solvent Cooler Solvent for Reclaimer treatment Desorber Absorber Desorber Top Condenser Fresh Solvent Rich/Lean Solvent Heat Exchanger Flue Gas FG cooler Make-Up Water Flue Gas Blower Gas Return to Power Plant FG Cooler Water Cycle Solvent Buffer Tank LSF Compressor Flash Vessel Rich Solvent Pump Reboiler Steam Condensate Lean Solvent Pump Cooling Water Cooling Water Return to Power Plant Figure 3: Simplified process flow diagram (PFD) for the pilot plant configuration Another design target was the operation of the pilot plant by remote control, which is possible from the computers of the process experts via Internet, e.g. from their offices in Frankfurt. Flue gas cooler The flue gas cooler is designed to cool the flue gas from approx. 100 °C to approx. 40 °C. In addition the flue gas cooler washes out some particulate matter and other contaminants in the flue gas, and it can also be operated with potassium hydroxide in order to reduce SOx. At the pilot plant the cooler is integrated in the lower part of the absorber column. The cooling section has a height of 2.6 m and is equipped with a structured packing. Absorber column design To reflect the above mentioned targets of pilot plant operation the main design parameters of the absorber are the diameter and the height. The diameter has to be chosen to achieve reliable results for up-scaling. Under this aspect wall effects have to be considered, however they will be of less influence in full scale. In addition literature [4] considers a scale-up factor in the range of 1,000 to 50,000 as feasible for absorbers. As shown in table 1 the chosen diameter of 200 mm is in a conservative range of the tolerable scale-up factors. To investigate the flow and reaction behavior the height of the structured packing beds has to be set similar to a full scale application. Thus the full height of 25 m was chosen for the sum of the beds of 6/19 the structured packing. Injection points for lean solvent were placed at different heights of the absorber, so that the impact of packing heights could be investigated. Flue gas Absorber Laboratory scale Pilot-scale Staudinger Full-scale (gas fired) Nm³/h 3 230 2.3 Mio. kg/h 4 300 3 Mio. 50 mm DN 200 2 x > 15 m Structured (gauze) Structured (metal sheet) Structured (metal sheet) 0.01 0.4 4 000 - 16 x 5 625 x pilot scale Staudinger (for one absorber) Diameter Packing type Solvent holdup Scale-up factor m³ Cross-section area absorber lab scale Table 1: Scale-up factors from Siemens laboratory plant to Staudinger pilot plant and to a possible full scale application In amine-based Post Carbon Capture processes there is normally an additional washing step installed on top of the absorber column to clean the emitted flue gas from solvent vapor and by-products. This step was not considered necessary for the AAS solution used by Siemens based on the fact that salts have very low vapor pressure. For possible droplet emissions a demister was implemented and successfully verified during the pilot plant operation. Desorber column design The selection criteria for the dimensional requirements of the desorber were similar as for the absorber. The desorber diameter was chosen with 200 mm at the bottom part and 150 mm at the main section and the top part. The chosen height of the structured packing beds is 15 m which is assumed to be conservative. This packing height would in a first approach be transferred to full-scale plants, but could be further optimized. In addition the pilot plant desorber was designed for pressurized operation up to 3 bar(a) to increase the flexibility in operation. Layout The pilot plant equipment is arranged on two floors installed in a steel structure based container building with cladding (see Figure 4). 7/19 Figure 4: Equipment arrangement on two levels and outside view of the PostCap™ pilot plant Reclaimer The reclaimer was constructed and commissioned for semi-continuous operation in the Siemens laboratory in Frankfurt/Main for solvent loaded with by-products, which was taken batch-wise from the pilot plant and re-fed into the pilot plant after treatment (see Figure 5). A detailed description of the reclaiming process and steps was published in 2014 [5] Figure 5: Reclaimer view in the laboratory in Frankfurt/Main. 4.2 Operational conditions of the pilot plant The original design of the pilot plant was based on a slip stream from the flue gas of the Staudinger coal fired power plant. The pilot plant was operated on this basis until summer 2010. During this period of time flue gas compositions in a range as shown in Table 2 occurred. Composition vol % CO2 N2 O2 Ar H2O 11.6-14.3 Not measured 4.9-6.7 Not measured Not measured 3 mg/Nm (dry) at 6% O by-products 2 concentration 120-200 NOx 0.5 – 1,5 % NO2/NOx 20-60 SOx Table 2: Composition of flue gas at pilot plant inlet (coal fired operation) In 2012 the Staudinger CCS Pilot Plant was nominated as Verification Plant (VP) for the PostCap™ process within the Carbon Capture Mongstad (CCM) project of Statoil and Gassnova. The goal of this project was the CO2 capture from a gas fired combined heat and 8/19 power plant (CHP). For simulation of the CHP flue gas a gas burner was installed as a new flue gas source (see Figures 6 and 7) Figure 6: Gas burner (in container) for simulation of gas fired power plant flue gas conditions. Stack close to desulfurisation system of power plant Flue gas to stack Emission source 2 pilot plant Flue gas back to power plant CO2-product Power Plant Treated flue gas Flue gas feed from power plant Rich solvent Flue gas Flue gas blower Flue gas Flue gas cooler Flue gas Desorption Absorption (incl. condensation) Lean solvent Flue gas feed from gas burner New gas burner Flue gas to stack New natural gas feed to gas burner new existing Existing natural gas pipeline Figure 7: Adaption of pilot plant to gas fired application. During the gas fired application the flue gas was specified as shown in Table 3. 9/19 Stack close to gas burner Emission source 1 pilot plant Table 3: Composition of flue gas at carbon capture plant inlet (gas fired operation, reference case taken from CCM project, simulated by gas burner operation in verification plant) 5 Pilot plant operation 5.1 Test program After two months of commissioning the Siemens PostCap™ pilot plant was taken into operation in October 2009. A very short duration of installation and commissioning was achieved by successfully using fast track engineering. As described in the following, pilot plant operation involved several test and reconstruction phases. Most important parameter variations comprised: • Lean solvent inlet temperature to absorber • Solvent pump-around • Flue gas inlet • Heat duty • Amino acid salt concentration in solvent (aqueous solution) October 2009 – July 2010 The pilot plant was adjusted and optimized to operate at the given environmental conditions and with the defined interfaces to the power plant. Process parameter variations were executed and respective operational data was obtained to validate the process model. Solvent stability evaluation including SOx long-term experiments was executed as well as tests on construction materials. Results of this first operational period were also shown in [6] and [7]. The first pilot plant operation phase was followed by a reconstruction period in July 2010. The lean solvent flash equipment and some features for pressurized desorber mode were installed, before the pilot plant was taken into operation again. August 2010 – December 2010 After the pilot plant upgrade, experiments focused on pilot plant operation including the lean solvent flash approach and other advanced process features. The target of the operation was to confirm the expected reduction of energy demand due to the lean solvent flash and to revalidate the process model in accordance. The solvent stability evaluation and construction material tests were extended. 10/19 January 2011 – September 2011 Within the first three quarters of 2011, activities focused on the reclaimer development. In order to ensure realistic boundary conditions, reclaimer tests had to be carried out with used solvent. Therefore, the Staudinger pilot plant was operated under standard conditions in order to produce several batches of used solvent. The solvent was then transported to Frankfurt/Hoechst and treated within the pilot reclaimer in order to verify the solvent regeneration process. October 2011 – March 2012 During the first years of PostCap™ process development, laboratory and pilot plant experiments had been carried out with an amino acid salt solution which is referred to as “solvent type I”. In order to enlarge delivery options, the qualification of an alternative solvent which is based on the same amino acid salt, but supplied by a different manufacturer was carried out. “Solvent type II” qualification was successfully finalized by means of experiments in the Staudinger pilot plant. April 2012 – September 2012 From April to September 2012 the Staudinger pilot plant was reconstructed in order to demonstrate PostCap™ process applicability to flue gases emitted from gas-fired power plants by use of a gas burner. October 2012 – November 2012 Restart of Carbon Capture plant after adjustment to gas burner operation. Start of the technical qualification program (TQP) as agreed with Statoil/Gassnova. The first phase of the heat and mass balance verification was conducted. Several measurement campaigns took place where solvent and emissions behavior was analyzed. December 2012 – March 2013 During that period of time the second phase of the heat and mass balance evaluation took place. The configuration and function of the absorber and desorber demisters were tested and validated. Further measurement campaigns were conducted. In parallel the operation and verification of the reclaimer was executed. In March 2013 the 3,000 h test phase of the CCM TQP was concluded successfully. August 2013 – September 2013 An additional measuring campaign with the gas burner as flue gas source was conducted to get a broader data base with regards to emissions and to evaluate the influence of Fe-Ions on solvent degradation, especially on the creation of ammonia (NH3). Further detailed investigations on the topic took place in the laboratory plant in Frankfurt Hoechst from April to August 2014. 5.2 Results 5.2.1 Functional performance The Capture Rate of 90% within the defined ranges was maintained at a constant steam input. The overall and component mass balances could be closed for the whole operation period. No shut downs related to solvent or process specific issues (e.g. plugging, precipitation) occurred. Occasional unplanned shut downs were caused e.g. by external reasons such as missing power, cooling water supply or flue gas from the coal fired boiler as well as problems with the gas burner package unit used to synthesize flue gas. 11/19 During the gas burner operation the “in-spec” availability was monitored as part of the technical qualification program (TQP). An overall result of > 93 % was achieved (Figure 8). The process parameters - like flue gas amount and composition (including SOx and NOx byproducts), capture rate, steam input, solvent pump-around, temperature and pressure at desorber - were kept within the comparably narrow pre-agreed ranges. 32 40 96 36 60 33 24 30 88 26 52 23 16 20 80 16 44 13 08 10 2 67 33 6 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 0 In-Spec Availability % % Total "in Spec" VP Availability relative to operating hours with flue gas Calendar Hours Figure 8: “In-spec” availability of the pilot plant with gas burner during TQP The lean solvent flash (LSF) gas compression approach was successfully validated. Based on process information derived from recorded data a conclusion about the use of LSF approach can be drawn. By applying the LSF approach the thermal energy demand in the pilot plant can be reduced by more than 40 % related to steam input, thus a level of < 2.7 GJ/t of captured CO2 could be achieved under the conditions given at the pilot plant. This value was confirmed in several testing phases and different set ups also with both flue gas types. The quality of the CO2 product was specified for the gas based flue gas operation related to possible storage requirements. Excluding a very short period with LSF compressor air leakages, the O2 concentration in the CO2 product was considerably lower than the requirement specification. Hence it was possible to conclude that the originally planned deoxygenation unit is not required in the full-scale plant. It has to be stated that the reason for the LSF compressor leakage could not occur in a full scale plant based on constructional and control differences between pilot scale and full scale equipment. Project specific discussions of the N2 limit showed that values of < 0.2 mole % are expected for full scale projects, see Table 4 as an example. In analogy to O2, the measured values were considerably lower. Sulphur components were below detection limit. Thus it can be concluded that the required CO2 purity was outbalanced in the pilot plant. Specification / Product CO2 CO2 Purity [mole %] O2 [ppmwt] (max) N2 [mole %] H2O [ppmwt] (max) H2S [ppmwt] (max) Others > 99.6 (balance) < 200 < 0.2 to be agreed prior to contract award < 100 to be agreed prior to contract award Table 4: CO2 product quality specified for CCM project, license package agreement The installed measuring devices for steam and electrical power consumption posed some challenges during operation. For steam measurement an equivalent alternative was found and 12/19 witnessed by an independent third party to provide accurate information about steam input. As a countermeasure for the recording approach of electrical power consumption, measured data taken from frequency converters were extracted manually. The investigation on performance of PostCapTM solvent from different suppliers (referred to as solvent type I and type II) showed following results: • Absorption-desorption experiments gave similar results for both solvents. No significant difference in carbon capture performance could be detected. • Emission measurements showed that there are no relevant differences in solvent emission behavior. • The results of further analyses, especially on solvent composition, indicate similar degradation behavior for both solvents. 5.2.2 Operability Several operation modes were successfully tested, such as start-up, shut-down and automatic stand-by (with minimum solvent circulation at a well-defined heat input). The latter is advantageous with respect to short reaction times to process interruptions upstream of the capture plant. Solvent behaviour with regards to foaming and plugging was no issue at all. Foaming, which was observed at the desorber only, could be easily handled by respective counter-measures. An antifoam agent was identified and tested successfully. 5.2.3 Process model validation Coal fired: Several parameter variations have been performed and the simulation model was successfully validated. Good accordance between the measured and predicted temperature profiles in the absorber and desorber was obtained by adjusting the interfacial area factor (IAF) and the heat transfer factor (HTF) in the simulation model. The IAF expresses the ratio of the effective and the geometric mass transfer area and has to be adjusted, since the hydrodynamic correlations within the used process simulation software Aspen Plus ® are based on the reference system CO2 ↔ NaOH. With respect to the HTF, Aspen Plus ® advises to set it to be reciprocal to the IAF. Gas fired: The validated process model for coal fired operation was used as starting point for the investigations of CCM Full Scale Design. Based on the comparison of selected pilot plant operational data during 3000 hrs operation and the simulation results it was confirmed that a further adaption / tuning of the process model was not necessary to reliably model the real process behaviour. For comparison of measured and simulated temperature profiles and mass balance an acceptable good accordance has been achieved for all evaluated operation periods. Comparison of measured and simulated solvent cycle capacities (ΔRich/Lean CO2 Loading) led to good conformity. Pilot plant process data were used to validate the process model energy balance. Besides considering the pure energy balance, the process model further considers mass balance as well as temperature profiles, solvent concentration and loadings. By comparison of measured and simulated specific energy demand it can be seen that a good accordance has been achieved. This additionally confirms the process model validation. A further process model adaption was not necessary to reliably model the real process behaviour. For a design capture rate of 90 % the measured specific energy demand was below the simulated energy demand, hence process model results can be understood to be conservative (Figure 9). 13/19 05 .0 2. 20 13 13 .1 2. 20 12 29 .0 1. 20 13 04 .1 2. 20 12 09 .1 2. 20 12 20 .1 1. 20 12 26 .1 1. 20 12 06 .1 1. 20 12 14 .1 1. 20 12 3.50 3.00 2.50 2.00 1.50 1.00 0.50 0.00 24 .1 0. 20 12 01 .1 1. 20 12 GJ/ t CO2 Measured and Simulated specific energy demand excluding heat loss Specific Energy Demand Desorption excl. Experimental Heat Losses of 2.4. KW Simulated Specific Energy Demand Desorption excl. Heat Losses Figure 9: Measured energy demand versa simulated energy demand during TQP 5.2.4 Material tests Coal based flue gas: AISI 316Ti (AISI = American Iron and Steel Institute) is used as main construction material in the pilot plant. Corrosion tests showed that AISI 316Ti as well as AISI 316L can be used as construction material for parts in contact with solvent under the typical process conditions. Based on these results AISI 316L is now selected as the standard material for PostCap™ plants with flue gas from coal fired power plants due to expected better availability on the world market and lower costs. Natural gas based flue gas: Long term tests (1000 h + 2000 h) were executed. All tested materials were confirmed to be corrosion resistant (see Figure 10). Both AISI316L and AISI304L showed a uniform attack, which is however very minimal. Quantification figures would in the worst case lead to 17 µm loss after the design lifetime of 25 years. This is tolerable even for the structured packing, which consists of metal sheets of 100 µm. For FG cooler condensate section (acidic CO2 Product condensate), both AISI 904L and titanium can be used; no corrosion is detected. Originally AISI 316L was foreseen as construction material for full-scale plants with gas based flue gas as well. As AISI 304L showed comparable stability in all tests, it is now selected as the standard material for PostCap™ plants with flue gas from natural gas combustion. This results in a considerable saving in capital expenses (CAPEX). Figure 10: Material test samples before and after test 5.2.5 Emission measurements & liquid analysis Nine high standard campaigns for emission measurements, nine liquid analyses of solvent and five reclaimer analyses were successfully executed by Siemens during TQP. Furthermore five measurement campaigns were conducted by third parties. The degradation products in 14/19 the solvent and their behaviour were observed, and the main reaction pathways are well understood. The main degradation compounds accumulated in the solvent were formates/acetate, oxalate and – to a smaller extent – alkyl amines, as well as the non-volatile nitrosamines. After starting the reclaimer operation the concentration of non-volatile nitrosamine in the liquid solvent pump around was successfully kept constant at a desired level (see Chapter 5.2.6, Figure 11). Amines, ammonia and aldehydes originating from decomposed solvent were emitted to the atmosphere as volatile compounds. The concentration of amines and acetaldehyde at the absorber outlet were approximately constant after starting the reclaiming. The detected values were within the limits that are expected for full scale applications. During the additional measurements in August/September 2013 the level of ammonia concentration could be linked to the concentration of metals which act as a catalyst for the degradation. During the laboratory tests between April and August 2014 this relation could be further quantified. The emission of droplets was in all but two campaigns, even during the verification of demisting technology with increased gas load, below the very low detection limit. In the two campaigns where droplets were detected, the concentration of the solvent in the droplets was very low, resulting in a solvent content in decarbonized flue gas of 20 to 50 µg/m3. As a consequence the demisting technology can be seen as sufficient to avoid droplet emissions. 5.2.6 Verification of reclaiming technology During the coal fired operation of the pilot plant the reclaimer technology was thoroughly tested for both modules (SOx and NOx). The functionality was successfully proven and the performance was validated. As a result of these tests the reclaimer design could be further optimised, e.g. the crystallization process in both modules was reduced from two steps to one step. The Siemens reclaiming technology at gas fired operation of the pilot plant was successfully verified by operation of the reclaimer pilot plant as shown in Figure 11. No unexpected deviation compared to the full scale reclaiming concept appeared. Operability was satisfying. No blocking by solid particles, no reclaimer pilot plant shut down and no malfunctions occurred within reclaimer pilot plant operation. The scale-up tests for the full scale use of a belt filter and a centrifuge within the Reclaimer were successfully executed together with corresponding suppliers. The suppliers stated the suitability of their equipment for the desired solid-liquid separation and they determined the necessary process and product property data for a reliable equipment design. The reclaimer operation and the scale up test during the TQP were witnessed by the Customer and a third party. 15/19 Figure 11: Reclaimer effect on non-volatile nitrosamine concentration in solvent A robust performance of the NOx reclaimer based on conservative assumptions was confirmed. It should be emphasized that the NO2 input at the pilot plant flue gas at gas fired operation was much higher than given by the design base, however the observed waste stream was even lower than expected. The very low (but in-spec) SOx-concentrations in the flue gas of the pilot plant under gas fired operation lead to a very low accumulation of potassium sulphate in the solvent. Nevertheless this low uptake was separated by the SOx-reclaimer and the sulphate level in the solvent was also kept constant. Applying the washing step in the centrifuge a clean potassium sulphate product was gained, that meets the specifications of e.g. fertilizer manufactures for a further utilization. 5.3 Summary 5.3.1 Pilot plant operation with coal and gas fired flue gas A total of more than 9,000 hours of operation was successfully conducted at the PostCap™ pilot plant located at the Staudinger power plant : - - 5.3.2 The targets in focus as listed in chapter 2.2 of this paper were achieved for both flue gas sources - coal fired and gas fired. The performance of the amino acid salt based solvent and the chosen process and mechanical features as well as the simulation model and the control concept were validated under realistic industrial conditions. The Reclaimer operation was successfully tested for both modules (SOx and NOx) with different flue gas compositions/by-products as they are specific for coal fired and gas turbine power plants. Technology Qualification Program (TQP) for CCM project (gas fired) The proposed TQP was executed as agreed with Statoil/Gassnova. More than 3000 hours of “in-spec” operation were successfully accomplished on 2013-03-27 by 24/7 operation. The total "in-spec" availability of the carbon capture plant relative to operating hours with flue 16/19 gas, results in 93 %. Pilot plant operation in combination with the Reclaimer was very stable. All performance parameters such as liquid hold ups, temperature profiles, capture rate, steam input, flue gas composition (with regards to O2 and CO2) showed stable behaviour during the 3000 “in-spec” operating hours. 6 Scalability and constructability Based on the results of the pilot plant operation, a scale-up of the PostCap™ technology to large-scale demonstration and full-scale projects is possible. The technology had been chosen as a basis of project development by several large-scale projects globally for the design of CO2 capture plants to be optimally integrated into either new-build power plants or to be retrofitted to existing ones. Figure 12 shows the layout of a full scale plant that was developed during the concept study for the Carbon Capture Mongstad (CCM) project. Details on the scale-up procedure and results can be found in [8]. In addition a detailed constructability study was conducted by Siemens for the CCM project to prove that a full scale plant and the respective large and heavy equipment can be manufactured, transported and assembled on site. Figure 12: PostCap™ full scale plant, layout for CCM project 7 References [1] Stoffregen, Torsten, et al: Pilot-scale demonstration of an advanced aqueous aminebased post-combustion capture technology for CO2 capture from power plant flue gases, Energy Procedia 63 ( 2014 ) 1456 – 1469 [2] Radgen, Peter, et al: Lessons Learned from the Operation of a 70 Tonne per Day Post Combustion Pilot Plant at the Coal Fired Power Plant in Wilhelmshaven, Germany, Energy Procedia 63 ( 2014 ) 1585 – 1594 [3] Kay, John P., et al: Pilot-scale evaluations of advanced solvents for post combustion CO2 capture, Energy Procedia 63 ( 2014 ) 1903 – 1910 [4] Goedecke, Ralf: Fluidverfahrenstechnik, Wiley-VCH Verlag GmbH & Co. KGaA; Auflage: 1. Auflage (2006) [5] Melcher, Berthold, et al: Validation, operation and smart full-scale design of an efficient reclaiming system for carbon capture solvents based on amino acid salt, Energy Procedia 63 ( 2014 ) 676 – 686 17/19 [6] Jockenhövel, Tobias, et al: Validation of a second-generation post-combustion capture technology – Results from POSTCAP pilot plant operation, PowerGen Europe 2010 [7] Jockenhövel, Tobias, et al: Towards Commercial Application of a Second-Generation Post-Combustion Capture Technology – Pilot Plant Validation of the Siemens Capture Process and Implementation of First Demonstration Case, Energy Procedia 4 (2011) 1451– 1458 [8] Reichl, Albert, et al: Process development and scale-up for post combustion carbon capture - validation with pilot plant operation, Energy Procedia 63 ( 2014 ) 6379 – 6392 8 Acknowledgements Siemens gratefully acknowledges the following for their support and collaborative development of projects mentioned in this paper. In chronological order: • The BMWi (Bundesministerium für Wirtschaft und Energie – German Federal Ministry for Economic Affairs and Energy) for funding of the Siemens POSTCAP development project • E.ON SE for co-funding of the Siemens POSTCAP development project and providing facilities for erection and operation of the pilot plant • The Norwegian Government and Gassnova, funders of the carbon capture project Mongstad (CCM) 18/19 Permission for use The content of this paper is copyrighted by Siemens and is licensed to PennWell for publication and distribution only. Any inquiries regarding permission to use the content of this paper, in whole or in part, for any purpose must be addressed to Siemens directly. Disclaimer These documents contain forward-looking statements and information – that is, statements related to future, not past, events. These statements may be identified either orally or in writing by words as “expects”, “anticipates”, “intends”, “plans”, “believes”, “seeks”, “estimates”, “will” or words of similar meaning. Such statements are based on our current expectations and certain assumptions, and are, therefore, subject to certain risks and uncertainties. A variety of factors, many of which are beyond Siemens’ control, affect its operations, performance, business strategy and results and could cause the actual results, performance or achievements of Siemens worldwide to be materially different from any future results, performance or achievements that may be expressed or implied by such forward-looking statements. For us, particular uncertainties arise, among others, from changes in general economic and business conditions, changes in currency exchange rates and interest rates, introduction of competing products or technologies by other companies, lack of acceptance of new products or services by customers targeted by Siemens worldwide, changes in business strategy and various other factors. More detailed information about certain of these factors is contained in Siemens’ filings with the SEC, which are available on the Siemens website, www.siemens.com and on the SEC’s website, www.sec.gov. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in the relevant forward-looking statement as anticipated, believed, estimated, expected, intended, planned or projected. Siemens does not intend or assume any obligation to update or revise these forward-looking statements in light of developments which differ from those anticipated. Trademarks mentioned in these documents are the property of Siemens AG, its affiliates or their respective owners. 19/19