UPPER GRAND DISTRICT SCHOOL BOARD "J (I • ~. I 20120508 CP: 12-02 Issued: 2012 01 01 MEMO TO: Martha Rogers, Director of Education FROM: Paul Scinocca, Manager of Capital & Renewal Projects RE: Lee Street Public School, Building Project Report Report Classification: Decision Background: At the September 27th, 2011 Board meeting, the following motions were passed: THAT, (a) (b) the report entitled "UGDSB - Full Day Kindergarden, Capital Plan", CP:11-12, dated September 27th, 2011, be received; and, the Board approve in principle the FDK Capital Plan, CP:11-12, dated September 27th, 2011. In accordance with direction from the Ministry of Education, the board is implementing the FDK Program across the district. This Program is planned to be fully implemented in East Guelph schools in September 2013, and will place significant pressure on the school facilities to house the projected number of students. The FDK Capital Plan approved in principle by the Board, included the construction of a new 498 pupil place school on the Lee Street site. Issue: To present the Lee Street Public School Building Project Report for the Board's consideration. Recommendations: 1. THAT the report entitled "Lee Street Public School, Building Project Report" dated May 8th , 2012, CP:12-02, be received. Page 2 Lee Street Public School Building Project Report CP:12-02 2. THAT the Lee Street Public School be constructed to accommodate a JK-8 program with a target opening date of September 2014. 3. THAT the "Lee Street Public School, Building Project Report" attached as Appendix "A", dated May 8th , 2012, CP:12-02, be approved. 4. THAT the Lee Street Building Committee be established and up to three (3) Trustees be appointed to the Building Committee. 5. THAT a number of Architect firms be requested to prepare and submit proposals for the design of a school building to fit the unique constraints of the site. Rationale: 1. The Building Project Report as required by Policy 309 is attached as Appendix A. 2. Based on the enrolment projections, a new school in East Guelph is required to relieve enrollment pressures particularly at Ken Danby PS. 3. The Lee Street site has some significant challenges with respect to grading and drainage. It would seem appropriate to approach experienced architects to investigate creative solutions early in the process. 4. It is suggested that the firms of Snyder & Associates, Hossack & Associates, ZAS Architects Inc., MC Architects, BJC Architects Inc., Moffet & Duncan Architects Inc. and CS&P Architects be invited to prepare presentations for review by the Building Committee in June and be paid $2,000.00 to prepare these proposals. 5. The target budget for this project is included in Appendix A. 6. The construction of the project is to be supported by a combination of NPP funds and FDK funds subject to the approval of the Ministry. PS;kz S:ICAPProjILee Street PSIBR CP-12-02.wpd Appendix A Lee Street Public School Building Project Report Capital Projects Report: CP: 12-02 May 8th , 2012 Contents: • Preliminary Space Utilization Summary • Target Budget - Expenditures • Preliminary Design Schedule In accordance with the Construction Projects Approvals and Reporting Procedures (Policy 309, Section B), a Building Project Report is to be developed for each project. For the Lee Street Public School Building Project, the size, type and scope of the project are outlined below, and are followed by a revenue summary based on the funding model, the target budget, and the preliminary timelines for the project. Lee Street Public School - Program: The Lee Street Public School will have a rated capacity of approximately 498 pupils made up of the following spaces: 5 Kindergartens 130 Will include: 1 - - - - - - - - - - - ' - - + - - - - - 1 General Office and Staff Workroom(s); 16 General Classrooms 368 General Purpose Room I Gymnasium; 1 - - - - - - - - - - - - / - - - - - - ; Library Resource Centre; Seminar Rooms; Total: 498 and Design Tech Workroom. A more detailed program which shows the preliminary allocation of space within the proposed facility follows. Upper Grand District School Board New Lee Street Public School PRELIMINARY SPACE UTILIZATION SUMMARY May 2012 Ministry Room Type Rated Capacity Qty Total Students Area I Total Room (sq.ft.) Area (sq.ft.) rJ!!·f~MtlH·~!·~i_ General Classrooms Design Tech 16 1 Kindergartens Specialty Classrooms Special Education 5 0 0 23 0 26 23 9 368 0 130 0 0 750 375 1100 1000 1000 12000 375 5500 o o o 498 Sub-Total (1) Ancillary (non-loaded) 17875 Change Rooms Sq.Ft. Per Room 1 3750 200 2 Total Area 3750 400 Gym Storage 1 400 400 Servery Seminar Rooms 1 2 250 200 250 400 Resource Room Storage Administration (General Office, Reception, Principal, Health) Staff Room, Work Room and Washrooms Library/Resource Centre, inc!. Meeting/Reading Room Washrooms Sub-Total (2) 2 2 300 200 600 400 1 1 1700 1200 2400 275 1700 1200 2400 1100 12600 Qty General Purpose / Gymnasium 1 4 Total Net Area (Academic + Ancillary) 30475 Gross Up Areas Mech. Rms, etc (11%) Corridors, etc. (22%) Walls & Partitions (12%) Gross Area = GFAlPupil Place = 1.11 1.22 1.12 46,221.6 sq.ft. 92.8 sq.ftlpupil place 33827.3 41269.2 46221.6 May 2012 Project Budget Construction/Site Development Architects/Consultants Furniture and Equipment Construction Tender $6,702,125.39 Build. Permit Site Contingency $80,425.50 $234,574.39 HST $116,952.09 Architect $507,814.86 Other Consultants Survey/Testing HST $20,000.00 $25,000.00 $9,213.58 F&E Total $280,000.00 $7,134,077.37 $562,028.44 $280,000.00 Subtotal $7,976,105.81 Project Contingency $159,522.12 Total $8,135,627.92 October 15 of Target Budget by Board Building Committee to review Architect Proposals Review of Preliminary Program and Budget Design Schematics JPrequalification of Contractors/Select Construction Mgr Concept Design, Drawings & Budget Estimate Approval of Concept Design Drawings & Budget by Board Production of Contract Drawings Submission of Site Plan Drawings for Approval Review of Working Drawings Contract Documents Period ender Analysis Board Approval and Award of Contract MILESTONE DATES Target Budget, Schedule & Plan Project to Board Building Committee (BC) Meeting & Architect Proposals Final Concept Design and Budget Presentation to BC Approval of Concept Design Drawings by Board Production of Contract Documents Submission of Site Plan Drawings for approval Tender Period Board Approval and Award of Contract Commence Construction S:\CAPProJ\Lee Street PS\Prellminary Project Design Schedule. xis May-12 June & Sept. 2012 end of October-12 1117120012 Dec to Mar-13 early Feb-13 April-May-13 Jun-13 Jul-13 June 15 15