GENERAL NOTES General Contractor's General Responsibilities 1. General contractor is responsible for all materials, construction methods and craftsmanship. 2. Do not scale drawings. 3. All new work is to be plumb, level and square. 4. All new work is to comply with UCCS design and construction standards. 5. The Contractor is responsible to bring discrepancies or conflicts between various construction documents, including drawings and specifications, to the immediate attention of the architect before bid opening for resolution. Do not assume correctness of one document or the other. 6. Existing site utilities are to remain unless noted otherwise. 7. Contractors are responsible for coordinating work with other trades, and owner's self-performed work wherever and whenever they overlap. 8. General Contractor is responsible to coordinate inspection services provided by a State Inspector. Fees for inspections and required permits to be by General Contractor. Code Compliance 1. Comply with all local, state and federal codes, laws and regulations. 2. Comply with OSHA's standard requirement for excavating and trenching. Parking, Trash Removal, Temporary Facilities, Deliveries 1. Contractor is responsible to pay for parking on campus. PROJECT LOCATION 2. This project will make available to the General Contractor (1) Facilities services parking stall for use during construction behind Engineering building, west of the patio. 3. General Contractor is responsible for trash and recycling removal. Coordinate dumpster locations with UCCS Project Manager. Schedule, Work Hours & Building Access 1. Work to be started and completed as stated in the bid forms. 2. Hours of construction are between 7:00am - 10:00pm or as otherwise arranged with the Project Manager. 3. Coordinate construction activities with UCCS Project Manager to meet owner's schedule. Project Location Plan - Engineering Building 4. Activities causing noise, vibration, odors and activities which require closure of part of the building, parking areas or interruption of utility services must be coordinated with owner's schedule. 5. Arrange building access with UCCS Project Manager. Scale: Engineering Patio Facilities Services ENGINEERING AND APPLIED SCIENCE (ENGR) CS Not To Scale Date: 06/19/2015 Drawn by: MQF SCOPE OF WORK 1 SOLID PIPE END 3 4" Ø PERFORATED PIPE FF=36.5 FIELD VERIFY SOLID PIPE DRAIN TO DAYLIGHT FF=36.5 FIELD VERIFY Excavate soil above and about 12" deep along perimeter of existing concrete storage vault shown hatched. Field verify top of existing concrete vault. (Approx. T.O.V. =36.75) 3 Remove any existing membrane and protection board on top of existing concrete storage vault and along perimeter foundation walls below patio to a depth of 5' max. See detail 1 and 2/A2 . New waterproofing and protection board should be compatible with existing waterproofing system. See attached existing waterproofing and protection board specification. Provide submittals for approval. 1 3 4 Provide new 4" perforated drain pipe with filter fabric on top of existing concrete storage vault deck. Drain to daylight. See detail 1/A2. 5 Backfill affected area and reinstall sod to original condition. Coordinate landscape work with Facilities Outdoor Services. 3 3'-0" 4 SLOPE 1/4"/FT NEW STONE PAVER TO PROTECT DRAIN PIPE UNDERNEATH GRADE 1 A2 ALL WORK SHALL BE IN STRICT COMPLIANCE WITH CURRENT BUILDING CODES AND OTHER STATE AND LOCAL CODES AND BUILDING REQUIREMENTS THAT APPLY. CONTRACTOR AND SUBCONTRACTORS SHALL PROVIDE ALL LABOR, MATERIAL AND EQUIPMENT TO COMPLETE ALL WORK SHOWN ON PLANS, CALLED FOR IN SPECIFICATIONS, OR REASONABLY IMPLIED FOR A COMPLETE INSTALLATION EVEN THOUGH NEITHER SHOWN ON PLANS OR CALLED OUT IN SPECIFICATIONS. EXISTING SITE UTILITIES ARE TO REMAIN UNLESS NOTED OTHERWISE. CONTRACTOR TO COORDINATE WITH FACILITIES ON SCHEDULES AND ACTIVITIES AT LEAST 2 DAYS PRIOR TO ANY DEMOLITION OR NEW WORK TYP. WORK TO BE COMPLETED BETWEEN XXXXXXX AND XXXXXXXXXXXXX. A)HOURS OF CONSTRUCTION ARE BETWEEN 7:00AM - 10:00PM OR AS OTHERWISE ARRANGED WITH THE CAMPUS SECURITY. CONTRACTOR WILL BE RESPONSIBLE FOR PARKING FEES. 1 3 5 SLOPE 3 240 240 SLOPE 30X16 CONCRETE SPLASH BLOCK THE INTENT OF THE DRAWINGS IS TO PROVIDE INFORMATION FOR THE CONSTRUCTION. IT IS IMPORTANT FOR THE CONTRACTOR TO VERIFY FIELD DIMENSIONS AND CONDITIONS BEFORE EXECUTION OF THE WORK. CONTACT OWNER SHOULD ANY DISCREPANCIES EXIST. EXISTING SITE UTILITIES ARE TO REMAIN UNLESS NOTED OTHERWISE. FF=41.0 FF=41.0 2 A2 2 2 5 Excavate along perimeter of concrete patio shown hatched 3' wide and a depth of 5 feet. Salvage existing sod for reinstallation. Provide protective systems per OSHA standard requirement. GENERAL NOTES GENERAL CONTRACTOR TO EMAIL FINAL BIDS TO MFALCON@UCCS.EDU BY 2:00PM ON XXXXXXXX. GENERAL CONTRACTOR IS RESPONSIBLE TO COORDINATE INSPECTION SERVICES PROVIDED BY A STATE INSPECTOR. INSPECTIONS AND REQUIRED PERMITS TO BE BY GENERAL CONTRACTOR. 45° 45° 2 A1 Construction Plan Scale: 1/8"=1'-0" 1 A1 Demolition Plan Scale: 1/8"=1'-0" Scale: Engineering Patio Facilities Services ENGINEERING AND APPLIED SCIENCE (ENGR) A1 Not To Scale Date: 06/19/2015 Drawn by: MQF EXISTING CONCRETE PATIO FF=41.0 (V.I.F) 6" GRADE TO SLOPE 5% MIN. (6" OF FALL IN 10') 4'-3" NEW WATERPROOFING WITH MIRA-DRAIN PROTECTION BOARD FILTER FABRIC 4" Ø PERFORATED PIPE IN GRAVEL FILL FF=36.75 (V.I.F.) 1'-0" EXISTING CONCRETE VAULT FF=35.75 1 A2 Detail Scale: 3/8"=1'-0" EXISTING CONCRETE PATIO GRADE TO SLOPE 5% MIN. (6" OF FALL IN 10') EXISTING CONCRETE PATIO FF=41.0 (V.I.F) NEW 4" PERFORATED DRAIN PIPE WITH SOLID END ON TOP OF EXISTING STORAGE VAULT 5'-0" BACK FILL NEW COLD APPLIED RUBBERIZED WATERPROOFING WITH PROTECTION BOARD 4" SOLID PIPE, SLOPE 1/4"/FT NEW STONE PAVER MIN. 2" THK. POLYSTYRENE FOUNDATION INSULATION TERMINATION BAR EXISTING CONCRETE STORAGE VAULT EXISTING FOUNDATION WALL 3 A2 Elevation Scale: 1/8"=1'-0" 2 A2 Detail Scale: 3/8"=1'-0" Scale: Engineering Patio Facilities Services ENGINEERING AND APPLIED SCIENCE (ENGR) A2 Not To Scale Date: 06/19/2015 Drawn by: MQF