Winding Down the Cost of Offshore Wind Offshore Wind Power Conventional Grid Access New AC Grid Access The cost of offshore wind energy is decreasing, thanks in part to two innovations from ­Siemens: a smaller AC substation called the Offshore Transformer Module and a highercapacity wind turbine. Text: Charles Murray Illustrations: Jochen Stuhrmann 32 Living Energy · No. 12 | July 2015 Offshore Wind Power C utting costs by one-third is a tall order in any line of business. But it’s one that the offshore wind power industry has promised to deliver: to push down the price per kilowatt-hour of wind energy by 2020 from €0.14 to 0.15 to under €0.10. With five years to go, the contours of how this will happen are starting to emerge, and two innovations are expected to be standouts in capturing wind offshore. One is a substation that has been simplified, standardized, and shrunk – called the Offshore Transformer Module (OTM). The other is an uprated version of the wind turbine itself. A Pioneer’s Progress Both innovations fit ­Siemens’ profile as a trusted, stable partner to its customers, with over 23 years of experience in delivering offshore projects on time and on budget. These factors, alongside a firm commitment to invest in renewable energy such as wind power, makes S ­ iemens’ offshore wind turbines the most bankable solution in the market. This careful balance of innovation with reliability and low risk is the source of ­Siemens’ global reputation. Going forward, ­Siemens aims to maintain its leading position in the offshore market and drive it to long-term sustainability. To that end, the levelized cost of energy needs to be reduced significantly in an increasingly heterogeneous market. Wind power first went to sea a quartercentury ago. That step-out was typified by the first in-water installation ever, at Vindeby, Denmark, delivered in 1991 by ­Siemens. Still operated ­today by Dong Energy, its eleven turbines’ 5 megawatts of output was a milestone for the industry. Moreover, Vindeby is located relatively close (1.5 to 3 kilometers) to land and in shallow water (2 to 6 meters). In subsequent years, as the push toward renewable energy surged ahead, there was also a drive to reach greater distances, depths, and capacities. As 34 Living Energy · No. 12 | July 2015 Offshore Wind Power all the easily accessible sites on shore and near the coastline filled up, and in some areas, due to environmental concerns, wind power plants had to be placed further out and deeper in the sea. Today, offshore wind is one of the most advanced emerging technologies. A steep technological development has taken place since Vindeby was installed in Danish waters. As for the wind turbines, there is a clear trend toward larger machines and larger rotors. In the decades since offshore wind power took off, the capacity of the wind turbines has multiplied by more than 200, while blade length has multiplied by 15. After nearly a quartercentury, offshore wind is one of the most ­advanced emerging technologies today. Projects also have grown considerably. The trend in offshore wind is toward larger parks that are further ­offshore. This ultimately gives way to more complex projects exposed to ­severe sea and wind conditions. At the moment, the world’s largest offshore wind farm is the London Array of 175 wind turbines with a combined capacity of 630 megawatts that matches many state-of-the-art conventional gas or coal power plants. Inaugurated in 2013, this project was successfully de­ livered by S ­ iemens with its ­SWT-3.6-120 turbines that sit 20–25 kilometers offshore in the Thames Estuary at depths of up to 25 meters. Even as the London Array was being built, generators and suppliers were recognizing their next challenge. While hurdles of distance, depth, and size had been cleared, newer projects would have to achieve the same at significantly lower cost. Slimline Substation One key cost target, recalls ­Siemens Transmission Solutions CEO Tim ­Dawidowsky, was the AC substation that connects the majority of offshore wind parks to the onshore power grid. Thanks to S ­ iemens’ pioneering efforts in the industry, the company has already innovated and reduced costs in offshore grid access. By introducing new developments based on actual experience and standardizing around this best practice, ­Siemens has been at the forefront of the drive to reduce costs. Since ­Siemens delivered its first AC offshore platform for the Thanet project in the UK, there has been a steady evolution of designs in the marketplace. During this evolution, the trend has moved toward ever-increasing specifications, increased functionality, and higher power ratings – and a ­resultant increase in costs. Starting in 2014, a task force with representatives of all relevant ­Siemens divisions came together, drawing on their extensive offshore wind experience as well as the best ideas from a broad cross-section of customers, partners, suppliers, and other key industry stakeholders. Within eleven months, the group had generated a design for future AC platforms – one that Dawidowsky hails as the vanguard of the third generation. Four key features set the third generation apart from the conventional, more bespoke offshore substation platforms currently in the market: A simple design with no moving parts; a more environmentally friendly design, with the elimination of mineral oil; overall weight is three times lighter than that of a typical conventional AC offshore substation platform; and cost is reduced by up to 40 percent across the offshore scope. A more compact AC substation, the Offshore Transformer Module helps cut operational and maintenance costs. Plug-and-Play Principles Other, more mature industries have already noted and leveraged the advantages of a standardized, modular approach in traditionally complex engineering projects. Rather than building major equipment directly on the deck of an offshore platform, resulting in increased interfaces and critical paths, these are instead built into standard-sized containers. Such containers can then be mounted on a simple platform deck at the fabrication yard. The process is analogous to “plug and play” within the consumer electronics industry. Modular assembly cuts out an enormous amount of cost, Dawidowsky points out, and it means S ­ iemens can leverage a true standardized approach across multiple projects at all levels of the supply chain. Maintenance is also simplified. Rather than bringing specialists to malfunctioning equipment, a modular approach allows the customer to decide whether to rectify faults offshore in minor cases or to bring the equipment onshore, replacing it with an immediately available spare unit. Repairs done on land, Dawidowsky notes, “are about ten times less expensive than doing the same on the u Living Energy · No. 12 | July 2015 35 Offshore Wind Power The ­Siemens SWT-7.0-154 delivers nearly 10 percent more energy than its predecessor, while retaining its proven reliability. that are almost identical to those used for the wind turbines themselves, thus eliminating the need for a large bespoke foundation. The smaller ­OTMs also allow utilization of a much broader, potentially more local supply chain for construction, something that many customers find valuable. siemens.com/swt-7-0-154 Combined Savings “Repairs done on land are about ten times less expensive than doing the same on the platform itself.” Tim Dawidowsky, CEO, ­Siemens ­Transmission Solutions 36 Living Energy · No. 12 | July 2015 platform itself.” Downtime is nearly eliminated, because units can be exchanged altogether with replacement units held as spares, another case of “plug and play.” Smaller Switchgear Both high- and medium-voltage transformers have been optimized, increasing capacity whilst minimizing bulk. Fans and pumps have been completely eliminated. “No moving parts!” Dawidowsky enthuses, noting the inherent reduction in maintenance costs. Neither do the transformers require any mineral oil. Instead, they employ a nonflammable, highly biodegradable fluid called ester liquid. This brings two benefits over oil: It allows an elimination of the fire-suppression system and it is a much lower risk for marine life. Gas-insulation technology – already applied on ­Siemens AC offshore platforms – has been refined and improved, based on accumulated experience. Shedding Pounds The 2014 task force was also set a clear goal to reduce the weight of the offshore substation and significantly bring down overall costs. The realization that cutting total mass below 1,000 tonnes could bring about a step change in cost reduction became a key factor in the development of the concept. Below 1,000 tonnes, the OTM can be installed by conventional ships and cranes already deployed on the wind farm for wind turbine and foundation installation, as opposed to using large specialized vessels that are much more costly, much less available, and subject to greater weather restrictions in their operations. The solution, not obvious at first but brilliant in retrospect, was to split the substation into two smaller ones, each of which can be mounted on separate foundations By eliminating the need for its own, separate foundation, the new, smaller design can also be added to an existing wind turbine foundation while hosting the wind turbine itself. This delivers even greater cost savings, as it eliminates the need for any additional foundation to support the two modules. Typically, Dawidowsky estimates, all this requires is adding 15 percent to the turbine foundation’s structural steel to ensure that it can handle the increased loading requirement. In addition, by thinking holistically across the whole wind farm, considering both the turbines and the grid connection, with the new solution one can avoid the need to use dedicated compensation reactors for the transformer. By using this capability to cancel out the capacitance of the cables, it eliminates the need for another large piece of equipment offshore with a resulting further optimization of the platform structure. All told, each new substation module weighs in considerably lighter, at around 630 tonnes (generating 250 mega­watts each), a reduction of nearly 60 percent from conventional designs. For larger capacities, multiple modules can be used. Given that typically, two-thirds of offshore capital costs are expended on building and installing platforms, this can result in a serious reduction of future project budgets. “This is a real cost-saving opportunity for AC grid connections,” summarizes Dawidowsky, adding that ­Siemens is working on cost improvements in the DC sector as well. The company is well versed in both types Tail Winds for Turbines A380 79.8 meters 154 meters SWT-6.0-154 SWT-7.0-154 IEC class IA Nominal power 6,000 kW IB Rotor diameter 154 m Blade length 75 m 7,000 kW Swept area 18,600 m2 Hub height Site-specific Power regulation Pitch regulated, variable speed of current. In addition to its AC grid connections, where S ­ iemens has delivered about 3 gigawatts of transmission capacity, ­Siemens also has delivered four DC substations with a combined rating of 2.9 gigawatts. A fifth connection with a capacity of an additional 900 megawatts was ordered in 2014 and is scheduled to go into operation in 2019. Natural Progression to 7 Megawatts As offshore capacities continue to grow, so do those of wind turbines themselves. ­Siemens’ flagship offshore wind turbine, the SWT-6.0-154, has already set new standards in gearless turbine design. In early 2015, ­Siemens raised the bar yet again by introducing a generator upgrade to 7 megawatts. The S ­ iemens ­SWT-7.0-154 delivers nearly 10 percent more energy than its predecessor, while retaining its proven reliability. Development engineers have refined only those turbine components needed to increase electrical output. The new model is set to go into serial production by 2017. Stronger permanent magnets and generator segments in the permanent magnet generator provide the key to harvesting a higher yield. Additionally, the converter and transformer have been upgraded, in line with the higher electrical output. All other components share the proven engineering of the 6.0-megawatt wind turbine, giving ­Siemens customers the assurance of relying on proven technology and an established supply chain while significantly increasing energy generation. “Our new wind turbine offers customers an investment as reliable as our proven G4 and D6 product platforms,” notes Offshore CEO Michael Hannibal of ­Siemens Wind Power and Renewables. “However, it also answers market demands to achieve greater energy yield at lower cost and effort.” Cost reduction through innovation is the key factor of the new turbine and ­also of new ­Siemens grid access solutions. The turbine’s long structural design lifetime of 25 years and increased power rating create a remarkable cost of energy benefit. p Charles Murray is a science journalist who writes about technology and sustainability ­issues. He is based in Zurich, Switzerland. Living Energy · No. 12 | July 2015 37