Power System Operation Corporation Limited (a wholly owned subsidiary of POWERGRID) National Load Despatch Centre New Delhi 1st August 2012 Sub: Loading of Extra High Voltage (EHV) transmission elements on the network and its impact on the grid security 1.0 Background: Two grid disturbances occurred on two consecutive days on 30th and 31st July 2012. In the first disturbance at 0233 hours on 30th July 2012, nearly the entire Northern Grid was affected while in the second disturbance, the Northern, Eastern and North Eastern grids were affected to a large extent. In both the disturbances, in the antecedent grid conditions there was heavy power flow on the 400 kV Bina-Gwalior-Agra single circuit section crossing 1000 MW on the single circuit available. (The second circuit was under outage since 28th July 2012 for up-gradation to 765 kV level). A similar incident at 1510 hours on 29th July 2012 had also led to a near miss situation. This section has Quad Bersimis conductor which has a Surge Impedance Loading (SIL) of 691 MW but loaded much above the SIL. Likewise, the loading on many circuits in the Eastern region was also of the order of 550 MW and above against the SIL of 515 MW for a twin Moose configuration line. 1.0 Safe loading limits for the transmission system: The Planning Criteria issued by Central Electricity Authority in June 1994 stipulates that the permissible loading on transmission lines would either be the stability limit evaluated from St Clair’s curve or thermal limit depending on the line length. It states that while Surge Impedance Loading (SIL) gives a general idea of the loading capability of the line, it is usual to load the short lines above SIL and long lines below SIL (because of stability considerations). The thermal limit of a Quad Bersimis line at 40 degree centigrade ambient temperature is of the order of 3200 amps which correspond close to 2200 MVA at 400 kV voltage level in contrast to the SIL of 691 MW. NLDC, POSOCO Page 1 In several incidents over the past few years, the following concerns have come to the fore in several disturbances involving high antecedent line loadings in the system. 1. Surprises in the form of protective relaying mis-operations either due to incorrect settings, load encroachment or use of distance relays for power swing blocking. These have led to cascading failures in the past. 2. Sustained high loading for a period of ten minutes or more in daytime high ambient temperature conditions have led to line tripping on transient faults possibly due to increase in sag. 3. High reactive power consumption by the transmission line under heavy loading conditions which lead to voltage dips in the system. Lack of dynamic reactive power consumption adds to the constraint. Till the incidents of 30th and 31st July 2012 is analyzed in detail and any shortcomings in different regions identified, the following action plan is being implemented with immediate effect. • NLDC/RLDCs in consultation with CEA and CTU shall review transfer capability of inter-regional and any other critical links keeping in view CERC regulations and the experience during the two grid collapses. • The Short Term Open Access (STOA) approvals by RLDCs/NLDC would be considered based on the transfer limits worked out above. However if at any time due to an emergency in the system, RLDCs would take all actions necessary to ensure system security including curtailment of transactions. • NLDC/RLDCs to review and impose congestion charges as per CERC regulation for inter-regional links for any drawal beyond the limits to be specified as mentioned above. • The transfer limits considering SIL limits (indicated at Annexe-1) on each trunk transmission lines in the inter-regional corridor and intra-regional systems have been worked out by NLDC and the same is enclosed at Annexe-II. x----x----x NLDC, POSOCO Page 2 Annexe-1 NLDC, POSOCO Page 3 Annexe-2 Power System Operation Corporation Limited National Load Despatch Centre Dated: 1st August 2012 Interregional Corridor Total Transfer Capability (TTC) MW Reliability Margin (RM) MW Available Transfer Capability (ATC) MW LTA/ MTOA MW Available Margin for STOA MW West to North* 1250 200 1050 260 790 400 kV Bina-Gwalior East to North 3850 200 3650 1158 2492 400 kV KahalgaonBiharsharif West to East 850 300 550 0 550 220 kV BudhipadarTarkera East-North East 440 35 405 135 270 220 kV BTPS-Agia East-South 900 0 900 170 730 400 kV Rourkela-Talcher West to South 1000 0 1000 992 8 Limiting Element HVDC Bhadrawati link capacity *only one circuit is available presently on 400 kV Bina-Gwalior-Agra. The other line is under upgradation to 765 kV level. 400 kV Zerda-Kankroli and 400 kV Kankroli-Bhinmal lines are under forced outage. x----x----x NLDC, POSOCO Page 4