PROJECT MANAGEMENT CM 321 Mechanical Systems February 1st & 6th,

advertisement

PROJECT MANAGEMENT

CM 321

Mechanical Systems

February 1st & 6th,

2007

Introduction

Maria Boyer

Construction Manager

University Mechanical Contractors, Inc

Experience

• 17 years in Mechanical Industry

• 3 years in General Contracting

WHAT IS SPECIALTY CONTRACTING?

z “The BIG THREE”

M - Mechanical

E - Electrical

P - Plumbing

M

Mechanical Systems z Mechanical system can represent 15% - 40% of the overall cost of a project.

z HVAC - Heating, Ventilation & Air Conditioning z Temperature Control Systems z Building Automation Systems z Fire & Life Safety Systems z Plumbing Systems

E Electrical Systems z Power Wiring z Lights z UPS Systems (Uninterrupted Power Supply) z Communication Wiring z Data Wiring z Fire & Life Safety Systems

P Plumbing Systems z Sanitary Waste z Domestic Water z Storm Drainage z Medical Gases z Natural Gas z Lab Waste

What is Project Management?

Management of:

Scope

Time / Schedule

$Resources (People, Material, Finance$)

Project Management for Mechanical Contractors:

--

How it is Unique

-- How is it Unique… z z z z z z

Diversity of Projects

System Integration with Building

Components (Structural & Arch)

Expanded Responsibilities

Self Perform Work – Labor Relations

Technical Component

Owner/Developer Relationships

Project Management

Responsibilities z z z z z z z z z

Risk Management

Financial Management

Document Management

Resource Management

Coordination / Scheduling

Estimating

Scope Control

Quality Control

Customer Relations

Primary Responsibility..

Risk Manager

“Manage the Project by effectively communicating the contract with all parties and mitigating risks throughout the construction and closeout process.”

The Big C’s

“Communicate..

Clarify..

Confirm”

ACTIVITY

Project Management Cycle z Pre-Construction z Construction z Close-Out

Three Primary

Project Delivery Approaches z Plan / Spec z Design Assist z Design Build

Delivery Method

Timeline Distinctions

TIMELINE

DELIVERY METHOD 1st Qrt 2nd Qrt 3rd Qrt 4th Qrt 1st Qrt 2nd Qrt 3rd Qrt 4th Qrt

Plan / Spec Design Design Design

Bid

Build Build Build Build

Design Design Design

Bid

Build Build Build Build

Design Build Design Design Design

Bid

Build Build Build Build

Scope Management

“Provide what you committed to provide within the parameters of the bidding documents and submitted bid proposal.”

PM Required Tools z Bid Proposal Letter z z

Bid Plans and Specifications

Bid Budget Estimate z z z

Schedule

Contract

1 st Tier Contract From

Owner

Contract Review

Review upon Receipt

Bid Scope Proposal Letter

Bid Documents: Plans; Specifications; Schedule

Post Bid – “Clarifications”

Review for Discrepancies Between Bid & Contract

Contract scope defined

Schedule

Plans and Specification Documents Listed

Terms and Conditions

(“ The Small Print” )

Contract Terms & Conditions

Important to Mechanical Contractors z Notice Requirements (Sample) z Change criteria z Change of schedule or delay by others z Dispute resolution z Payment z Schedule of Values z Retainage

Notice

Protecting the Rights of Your Company z Event Occurrence z Rough Order of Magnitude $Price (ROM) z Final Price with Back-Up

ACTIVITY

Review Sample

Notice Requirement Matrix

End of this segment

Review Feb. 1st

Key Discussion Points z z z z z z

What does MEP stand for?

What type of structure do you have if there is no MEP?

What percentage range of a projects total cost can the

Mechanical system represent?

What is the primary responsibility of a Project Manager?

What are the three project delivery approaches ?

What is the most significant difference between the three

Project delivery approaches?

z z z z z

Conceptual; Schematic; Design

Development; Permit and

Construction represent the five typical stages of what?

The Project Management Cycle is comprised of what three phases?

Name a key review item that a

Project Manager must make upon receipt of the contract ?

What are notice requirements and what is their impact?

What is ‘ flow-down of contract terms’ ?

Schedule Management z z z

Know your Scope

Proposal; Plans; Specifications;

Contract

Understand General

Contractor’s Schedule

Is it complete? Is it feasible?

Does it adequately allow for completion of mechanical activities?

Identify milestones for mechanical activities

Project start date and completion date

Integrated activities of other trades

Scheduling Benefits z Communication tool z Record document of contractor’s intent z Assists in estimating project costs z Develops framework for planning phases z Risk management tool z Maximizes construction sequencing z Productivity measurement tool.

z Resource management both at the project & corporate levels

Resource Management

“Successful Project Managers have a keen insight and ability to manage people, material and financial ‘resources’.”

Turnover Meetings z What is a Turnover

Meeting?

z Stages Turnover

Meetings Occur?

Keys to Successful Turnover

Between Team Members.

Communicate the Overall Intent of the Project: z z z z z z z

Scope

Documents – Plans / Specs / Addendums

Estimate / Budget

Schedule

Team Players

Commitments

Materials / Methods

Material / Equipment Management z Purchase Orders / Subcontracts

Subcontract: Labor Service

Purchase Order: Product

Submittals z What do they mean?

Impact as a contract documents z What are they for?

Engineer

Crew

Purchasing

Owner z What do good ones look like?

ACTIVITY

Review Submittal Document

Financial Cost Management z Work In Progress Schedule (WIP)

Forecast cost to complete z What Type of Costs?

z Why Is It Important?

Cost Codes

“Breaking the project down into manageable parts”

Labor

Equipment / Material

Subcontractors

Committed Costs

Forecasting

Labor Management z Labor Budgets z Cost Codes

By Area

By Type z Crew Schedules z Labor Forecasting

Project Management

Project Cycle

Identifying and Resolving

Risks Throughout the

Project Cycle.

Pre-Construction

Construction

Close-Out

Project Cycles

PM Roles &

Responsibilities

Pre-Construction Construction

Contract

Turn-Over

Meeting

Scope / Terms

Conditions

Estimating / Sales

T.O

PM

Notice

Requirements

PM T.O

Field

Production

Material /

Equipment

Submittals

Close-Out

Retainage / Lien

Detailing Shop

Drawings /

Installation / Startup

PM / Field T.O

Estimating / Sales

Operation &

Maintenance /

Owner Training

Financial Cost

Management

Budgets – Labor /

Material / Equipment

Forecasting /

Labor Productivity

+/- $Profit

End of this segment

Download