Combine_handout_ - Northern Periphery Programme

advertisement
Northern Periphery Programme 2007-2013
How to Close a Preparatory Project
Christopher Parker
20th March 2014
North Atlantic House, Copenhagen, Denmark
How to Close a Preparatory Project

Final Preparatory Report






Preparatory Project Claim



General Overview (sections 1 -6)
Contents of the Project (sections 7-8)
Financing (section 9)
Administration (sections 10-12)
http://www.northernperiphery.eu/en/documents/Downloads/Preparatoryprojects
Formal declaration of expenditure by the Lead Partner
Payments to projects will be paid out retrospectively against actual expenditure
incurred
Compiling a Preparatory Project Claim

All partners compile a Statement of Expenditure
How to Close a Preparatory Project

First level control by First Level Controllers


Project partners send materials to the Lead Partner


Project partner sends the signed Certificate of Expenditure and the signed first level
control checklist to the Lead Partner.
The Lead Partner compiles and submits the Preparatory Project Claim



A check is made to see if the expenditure is in line with the NPP 2007-2013 Common
Eligibility Rules
Lead Partner compiles the Preparatory Project Claim.
Summary of Certificates of Expenditure and partner’s Certificate of Expenditure
How to submit a Preparatory Final Report

Lead Partner submits a complete and signed Preparatory Final Report with all
supporting evidence to the Programme Secretariat
How to Close a Preparatory Project
How to Close a Preparatory Project

Assessment of the Final Report and Payment






Programme Secretariat assesses the Final Activity Report
Managing Authority assesses the Final Report
Managing Authority issues a Decision of Payment
Certifying Authority carries out final payment check
Certifying Authority makes the payment to the Lead Partner
Receipt of Grant



Receipt of grant by the Lead Partner
Lead Partner distributes the co-financing to the project partners
Individual share of partnership grant
How to Close a Preparatory Project
Financial Reporting Procedure
Stefan Nyström
How to Close a preparatory project
20th March 2014
Claiming procedure, financial report
Document retention
NOTE: In case of an audit, all project partners must preserve
copies of ALL supporting documents until three years have
passed after Programme closure. We recommend that
supporting documentation is preserved at least until year 2020.
Lead Partner and Partners must also consider national
legislation regarding preservation of accounting material.
Explanation of National Controllers 1 (3)
 National Controllers have one main task, to
ensure that a reliable and functional national
control system is in place in its nation
 National Controllers are responsible for
OLAF reporting, in case of any irregularities
 National Controllers designate First Level
Controllers (FLC’s) to perform the check
 Only costs certified by the FLC’s can be
eligible for ERDF or ERDF equivalent funding
 Different systems in different countries
 Current list of National Controllers and First
Level Controllers are available on our website
and annexed to our Programme Manual
Explanation of National Controllers 2 (3)
Example; National Controller Finland “Decentralised
system”:
Finnish Ministry of the Interior
Department for Development of Regions and Public
Administration
Regional Development Unit
P.O.Box 26, FI-00023 Government
(From 1.1.2008: Ministry of Employment and Economy, details
to be specified)
Finnish system
• Note that the Ministry of
Employment will not carry out
the control. It will only be the
responsible authority.
Explanation of National Controllers 3 (3)
Example; National Controller Sweden “Centralised
system”:
Swedish system
County Administrative Board of Västerbotten
Industry and Commerce Department
901 86 Umeå
• Note that listed person is the
person responsible for the unit
of Industry and Commerce at
CAV.
vasterbotten@lansstyrelsen.se
Mr Curt Hörnqvist
Head of Department
curt.hornqvist@lansstyrelsen.se
• A desk officer / FLC
responsible for the task of
certififying expenditure will be
appointed
• Currently no fee will be
charged for Swedish partners
to get their expenditure
certified.
Supporting Documents to National Controllers
National Controllers will most likely require the following
documents in order to complete a first level of control:
• Statement of Expenditure (signed by authorized person)
• Ledger for the current reporting period (every partner should
keep separate project accounts)
• Time sheets (for part time employees)
• Copies of all invoices and receipts
• Employment contracts (for full time employees)
• Model to show the office costs distributed proportional +
supporting documentation (when applicable)
• Transaction list
• Partner activity report
• Other relevant documentation
Note: It is up to each
programme partner country
to establish what
documentation they will
require.
This is only an indicative list
of required documentation
for the first level control
provided by the NPP 20072013
Statement of Expenditure by Partners to National Controller 1 (5)
Statement of Expenditure
From:
dd.mm.yyyy
To:
dd.mm.yyyy
Note: The dates
should be stated
by
[day.month.year]
, e.g.
"30.09.2008"
Project Title:
Reference number:
Partner claim no.:
Contact information
Partner organisation
(original language):
Partner organisation
(english translation):
Address:
Person responsible:
Postal code:
E-mail:
Location:
Phone:
Country:
Mobile:
Legal status:
Phone:
Contact person:
Fax:
E-mail:
E-mail:
Phone:
Website:
Mobile:
VAT-status
VAT recoverable
VAT non recoverable
Statement of Expenditure by Partners to National Controller 2 (5)
Supporting documents
Note: The documents listed below is an indicative list of supporting documentation recommended by the Managing Authority.
It is up to each nation to decide on what documentation they will require.
Ledger
Time sheets (part time employees)
Copies of invoices and receipts
Employment contracts (full time employees)
Model to show the proportional distribution of office costs (if applicable)
Currency convertion sheet
Statement of Expenditure, 10% area partner + underlying documentation, see indicative list above (if applicable)
Other relevant documents (such as contracts, vat-documents etc.)
Other funding and information measures
Yes
No
Yes
No
Has any other EU funding been received?
Has the project received any eligible co-financing that was not stated in the budget?
Has the project fulfilled its information duties in accordance with Commission Regulation (EC) No 1828/2006?
Has the project undergone any substantial modification affecting the nature of implementation?
Expenditure
All expenditure has been incurred during the project period
All expenditure included has been paid during current reporting period
All expenditure concerns the project
All expenditure concerns activities that were stated in enclosure 1 to the decision
Signature
I hereby certify that all information in this Statement of Expenditure is complete and correct and that project net costs
for this reporting period amounts to:
0,00
euro
Place and date
Authorized signature for partner organisation
Name in clear
Statement of Expenditure by Partners to National Controller 3 (5)
Project Title:
0
Project partner:
0
Partner country:
0
Reference no:
0
MS Partner from 20% area:
NMS Partner from 20% area:
NMS Partner from 10% area:
Lead Partner responsible:
Other partner:
Note: If 10% partner, please fill in information of responsible Lead Partner below
Country:
Partner no:
Statement of Expenditure by Partners to National Controller 4 (5)
Cost and co-financing statement for Northern Periphery projects
This statement refers to the period from:
Partner claim no.:
dd.mm.yyyy
0
to:
dd.mm.yyyy
Certified cost,
earlier reporting
periods
Claimed cost,
current period
Project cost,
accumulated
20.000,00
20.000,00
200.000,00
200.000,00
200.000,00
200.000,00
200.000,00
200.000,00
20.000,00
20.000,00
200.000,00
200.000,00
20.000,00
20.000,00
20.000,00
20.000,00
20.000,00
20.000,00
200.000,00
200.000,00
1.100.000,00
1.100.000,00
PROJECT COSTS INCURRED (all amounts in euro)
Types of Expenditure
Approved budget
1. Staff costs incl. social contributions
2. Travel and accomodation
3. External experts
4. Office costs (directly allocated)
5. Office costs (distributed proportionally)
6. Promotion / publications, Seminars / conferences,
Meetings
7. Equipment and supplies
st
8. Other (including 1 level control)
9. In kind costs
10. Share of common costs
Total expenditure
0,00
0,00
Deducted: Received common cost payments
0,00
Deducted: Project revenue
0,00
Deducted: In kind costs
0,00
0,00
20.000,00
20.000,00
0,00
0,00
1.080.000,00
1.080.000,00
Project net cost
#DIV/0!
Statement of Expenditure by Partners to National Controller 5 (5)
PUBLIC MATCH FUNDING RECEIVED (all amounts in
euro)
Public match funding, In kind (source, type)
Budgeted match
funding
Certified funding,
earlier reporting
periods
Claimed received
funding,
current period
Actual funding,
accumulated
0,00
0,00
Totally received In kind contribution
Public match funding, cash (source)
0,00
0,00
0,00
0,00
Budgeted match
funding
Certified funding,
earlier reporting
periods
Claimed received
funding,
current period
Actual funding,
accumulated
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
Totally received public cash contribution
Total public financial contribution
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
#DIV/0!
Supporting document to Statement of expenditure

Currency conversion sheet
All project partners have to state their expenditure in Euro, only programme partner
countries using Euro are Finland and Ireland. All other partners except for Finnish
and Irish partners have to convert their currency into Euros. This is made by applying
the Currency conversion sheet, and its principles:
Currency conversion sheet (for non Euro partners) The currency used in the
Northern Periphery Programme 2007-2013 is Euro (EUR). Consequently all non Euro
partners must convert their expenses from national currency into Euro. All costs
should be converted using the monthly Commission rate for the last month in the
current reporting period. The Commission exchange rates is found on the official
website:
http://ec.europa.eu/budget/inforeuro/index.cfm?fuseaction=countries&Language=en
Currency Conversion Sheet 1 (2)
Project Title:
0
Project partner: 0
Partner country: 0
Reference no:
0
Currency convertion sheet (for non Euro partners)
The currency used in the Northern Periphery Programme 2007-2013 is Euro (EUR). Consequently all non Euro partners must
convert their expenses from national currency into Euro. All costs should be converted using the monthly Commission rate for
the last month in the current reporting period. The Commission exchange rates are found on the official website:
http://ec.europa.eu/budget/inforeuro/index.cfm?fuseaction=countries&Language=en
Last month of current reporting period:
month
This statement refers to the period from
Partner claim no.:
dd.mm.yyyy
0
to
dd.mm.yyyy
Claimed cost,
current period
National currency
Exchange rate
Claimed cost,
current period
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
Corresponding exchange rate:
PROJECT COSTS INCURRED
Types of Expenditure
Euro
1. Staff costs incl. social contributions
2. Travel and accomodation
3. External experts
4. Office costs (directly allocated)
5. Office costs (distributed proportionally)
6. Promotion / publications, Seminars / conferences,
Meetings
7. Equipment and supplies
8. Other (including 1st level control)
9. In kind costs
10. Share of common costs
Total expenditure
0,00
#DIV/0!
Deducted: Received common cost payments
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
Deducted: Project revenue
Deducted: In kind costs
Total project net cost
0,00
#DIV/0!
rate
Currency Conversion Sheet 2 (2)
Project Title:
0
Project partner: 0
Partner country: 0
Reference no:
0
PUBLIC MATCH FUNDING RECEIVED
Public match funding, In kind (source, type)
Claimed received
funding,
current period
National currency
Exchange rate
Claimed received
funding, current
period
Euro
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
Totally received In kind contribution
0,00
Public match funding, cash (source)
Claimed received
funding,
current period
National currency
#DIV/0!
Exchange rate
Claimed received
funding, current
period
Euro
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
0,00
0,00000
#DIV/0!
Totally received public cash contribution
0,00
#DIV/0!
Supporting documents from National Controllers
National/First Level Controllers will send two main
document to the project partner:
• Certificate of Expenditure
• Checklist of First Level Control
Certificate of Expenditure 1 (4)
Project Title:
Project partner:
Partner country:
Reference no:
Partner from flexibility rule area:
Choose
Certificate of Expenditure
This certificate refers to the period from
Partner claim no.:
dd.mm.yyyy
to
I / We hereby certify that the financial statement for the period stated above has been checked,
according to Art. 16 of Regulation (EC) No 1080/2006, for accuracy and compliance with the
Grant Letter including its enclosures and the Northern Periphery Programme Common Eligibility
Rules, as well as all applicable National legislation and Community rules and regulations
I / We also certify that the control has been conducted independently from project implementation
dd.mm.yyyy
Note: The dates should be stated by [day.month.year ], e.g. "30.09.2008"
Certificate of Expenditure 2 (4)
Types of Expenditure
Approved budget
Certified cost,
earlier reporting
periods
Claimed cost,
current period
Certified cost,
current period
Certified cost,
accumulated
1. Staff costs incl. social contributions
0,00
2. Travel and accomodation
0,00
3. External experts
0,00
4. Office costs (directly allocated)
0,00
5. Office costs (distributed proportionally)
0,00
6. Promotion / publications, Seminars / conferences,
Meetings
0,00
7. Equipment and supplies
0,00
8. Other (including 1st level control)
0,00
9. In kind costs
0,00
10. Share of common costs
0,00
Total expenditure (NPP area)
0,00
0,00
0,00
0,00
0,00
Deducted: Received common cost payments
0,00
Deducted: Project revenue
0,00
Deducted: In kind costs
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
Total project net cost (NPP area)
#DIV/0!
Certificate of Expenditure 3 (4)
Project Title:
Project partner:
Partner country:
Reference no:
Partner claim no.:
0
0
0
0
0
PUBLIC MATCH FUNDING RECEIVED (all amounts in euro)
Public match funding, In kind (source, type)
Budgeted match
funding
Certified funding,
earlier reporting
periods
Stated financial
contribution,
current period
Certified financial
contribution,
current period
Certified funding,
accumulated
0,00
0,00
Totally received In kind contribution
Public match funding, cash (source)
0,00
0,00
0,00
0,00
0,00
Budgeted match
funding
Certified funding,
earlier reporting
periods
Stated financial
contribution,
current period
Certified financial
contribution,
current period
Certified funding,
accumulated
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
Totally received public cash contribution
Total public financial contribution
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
Certificate of Expenditure 4 (4)
DEDUCTIONS
List of cost deductions made for the current reporting period
Note: The total deduction amount should equal the difference between "Claimed cost current period" and "Certified cost current period", see above.
Budget Line
Type of Cost
Supplier
Deductions, total
Deducted amount
0,00
Supporting documents
The following documents should be sent back to the project partner
Certificate of Expenditure
First level control checklist
Certificate of Expenditure, 10% area partner (if applicable)
First level control checklist, 10% area partner (if applicable)
Signature
Place and date
Verification no.
Authorized signature
Name in clear
Stamp
Comments
Documents from Partner to Lead Partner
All partners have to submit the following documents to the
Lead Partner:
• Certificate of Expenditure (blue ink version)
•Additional documents which may be part of the Partnership
Agreement:
• Partner Activity Report (as part of the aggregated final
report)
• FLC checklist
• Transaction list of all expenditures
• Other documents agreed within
the project partnership
Lead Partner Principle

Role Lead Partner:

Be the policeman of the project, ensure that all certified costs can be connected
to eligible/approved project activities (Letter distributed)
Northern Periphery Programme recommends that all partner Certificates of
Expenditures (CoEs) to the LP are supported by a partner activity report, clearly
outlining the individual partner activities, and a transaction list to demonstrate
which costs are related to what activities.
AND
It is vital that the Lead Partner can extract the individual partner activities from the
overall Work Package activity plan, potentially outline individual partner activities
in the partnership agreement.
Lead Partner Principle

Role Lead Partner:

Note
The NPP does not require the first level controller of the Lead Partner to check
the complete claim. However, according to EC guidelines this is within the scope
of the Lead Partner’s FLC.
Lead Partner Principle

Role Lead Partner:





Acting as link between the project partners and the programme
Submitting the project progress report
Overall responsibility for project coordination
Formal beneficiary of ERDF and ERDF equivalent funding
Lead Partner has the responsibility to distribute the funding received from the
NPP 2007-2013 among the project partnership in accordance with the spending
by the partners.
The complete Lead Partner responsibilities are stipulated in Regulation:
(EC) 1080/2006, Art 20
Documents from Lead Partner to the Secretariat
In order to make a complete progress
report the Lead Partner has to submitt the
following documents to the Secretariat:
•Final preparatory project report
• Project claim
• Summary of Certificates of Expenditure
• Certificate of Expenditure
(blue ink version) from all partners
• FLC checklists from all partners
Note that the Activity Report and the Summery
of COE have to be submitted both in blue ink
version, by post, as well as an electronic
version by e-mail.
Project Claim 1 (4)
Project Claim is the formal decleration of spending by the Lead Partner in order to
receive ERDF or ERDF equivalent co-financing, 2 page document:
Project claim
1 (2)
page 1
Note: The dates should be stated by [day.month.year ], e.g. "30.09.2008"
Reporting period:
Project claim No.:
Project Title:
Reference number:
Priority:
From:
Priority 1:
dd.mm.yyyy
To:
Priority 2:
Contact information
Lead partner organisation (original language):
Lead Partner organisation (english translation):
Address:
Postal code:
Location:
Country:
Person responsible:
E-mail:
Phone:
Mobile:
Phone:
Fax:
E-mail:
Website:
Contact person:
E-mail:
Phone:
Mobile:
Bank information
Name of bank:
Address:
IBAN number:
BIC code:
dd.mm.yyyy
Project Claim 2 (4)
Supporting documents
Project Claim (page 1 and 2)
Summary of CoE
Certificates of Expenditure (for all claiming
project partners)
First level control checklists (for all claiming
project partners)
Activity Report
Other funding and information measures
Yes
No
Yes
No
Has any other EU funding been received?
Has the project received any eligible cofinancing that was not stated in the budget?
Has the project fulfilled its information duties in
accordance with Commission Regulation (EC)
No 1828/2006?
Expenditure
All expenditure has been incurred during the
project period
All expenditure included has been paid during
current reporting period
All expenditure concerns the project
All expenditure concerns activities that were
stated in enclosure 1 to the decision
Has the project undergone any substantial
modification affecting the nature of
implementation?
Signature
I hereby certify that all information in this Project claim is complete and correct. By signing this Project claim I also apply for
payment in accordance with the Northern Periphery Programme 2007-2013 decision for project funding.
Place and date
Authorized signature
for the Lead Partner
organisation
Name in clear
Summary of Certificates of Expenditures 3 (4)
Summary of CoE is the ”calculator” to ensure that the
project claim has been compiled correctly:
1. Fill in the reported period for the project, and the claim
number
Summary of CoE
Summary of certified costs and financial contributions
From:
Claim No.
dd.mm.yyyy
To:
dd.mm.yyyy
0
Project Partners
The Summary of CoE template is a summary of all Certificates of Expenditure (CoE).
PLEASE NOTE: All yellow fields together with the scroll lists must be filled in!
C e r t i f i e d e x p e n d i t u r e, c u r r e n t r e p or t i n g p e r i o d
Type of Expenditure
Lead partner
Partner 2
Partner 3
Partner 4
Partner 5
Partner 6
Partner 7
Partner 8
Partner 9
Partner 10
Partner 11
Partner 12
Partner 13
Partner 14
Partner 15
Partner 16
Partner 17
Partner 18
Partner 19
Partner 20
Fill in LP name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Approved budget
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Choose
Country
Total
expenditure
Choose
Country
0,00
0,00
0,00
0,00
0,00
1. Staff costs
2. Travel and accomodation
3. External experts
4. Office costs (directly allocated)
5. Office costs (distributed proportionally)
6. Promotion / publications, Seminars /
conferences, Meetings
7. Equipment and supplies
8. Other (including 1st level control)
9. In kind costs
10. Share of common costs
0,00
Total expenditure
0,00
Deducted: Received common cost payments
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
Lead partner
Partner 2
Partner 3
Partner 4
Partner 5
Partner 6
Partner 7
Partner 8
Partner 9
Partner 10
Partner 11
Partner 12
Partner 13
Partner 14
Partner 15
Partner 16
Partner 17
Partner 18
Partner 19
Partner 20
Fill in LP name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
Fill in partner
name
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
FALSE
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
Deducted: Project revenue
Deducted: In kind costs
0,00
Total net cost
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
C e r t i f i e d f i n a n c i a l c o n t r i b u t i o n, c u r r e n t r e p o r t i n g p e r i o d
Public financial contribution
Public match funding, in kind
Budgeted public
match
funding
Public match funding, cash
Total public financial contribution
Total
contribution,
current period
0,00
0,00
0,00
Project Claim 4 (4)
NOTE: Self generated table after completing the Summary of Certificates of Expenditures
Project claim
page 2
Reporting period:
Project Claim No.:
Project Title:
Reference number:
Priority:
From:
0
dd.mm.yyyy
0
0
Priority 1:
To:
dd.mm.yyyy
Priority 2:
Project Expenditure and Financial contributions
Expenditure and financial contributions sorted by source of finance
This table is self generated from the "Summary of CoE" sheet.
C e r t i f i e d e x p e n d i t u r e, c u r r e n t r e p or t i n g p e r i o d
Type of Expenditure
Approved budget
Member States
MS+NMS
1. Staff costs
2. Travel and accomodation
3. External experts
4. Office costs (directly allocated)
5. Office costs (distributed proportionally)
6. Promotion / publications, Seminars /
conferences, Meetings
7. Equipment and supplies
8. Other (including 1st level control)
9. In kind costs
10. Share of common costs
Total project expenditure
Deducted: Received common cost payments
Deducted: Project revenue
Deducted: In kind costs
Total project net cost
Member State
Non Member
State
10% area
Faroe
Islands
20% area
Greenland
Iceland
Norway
Norway
Total
expenditure
20% area
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
Budgeted match
funding
Member States
Norway
Total financial
contribution,
current period
C e r t i f i e d f i n a n c i a l c o n t r i b u t i o n, c u r r e n t r e p o r t i n g p e r i o d
Member State
Non Member
State
20% area
10% area
0,00
0,00
0,00
0,00
0,00
0,00
Faroe
Islands
Greenland
Iceland
Norway
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
0,00
Financial contribution
MS+NMS
Public match funding, in kind
Public match funding, cash
Total public financial contribution
0,00
0,00
0,00
0,00
0,00
0,00
20% area
0,00
0,00
0,00
0,00
0,00
0,00
Documents from Lead Partner to the Secretariat
Changes in project implementation
All changes in project implementation have to be communicated to the Secretariat and need
preapproval before becoming eligible (this includes changes in project end date, budget changes and
changes in the activity plan). The degree of the change (major or minor) will be determined by the
Secretariat:
Rule of thumb:
1. Please describe the change in the budget, activity plan, partnership, project co-ordinator
staff, project time period, indicators or other changes to the Secretariat in an e-mail.
2. Justify the need for change
3. Describe the impact on project implementation.
Maximum number requests two per year.
Documents from Lead Partner to the Secretariat
Changes in project implementation
Minor changes are:
• A change with no major impact on project implementation and less than 40 000 Euro increase in
one project budgetline
• A change of a minor impact is approved in regular correspondence between the Lead Partner and
the Secretariat, i.e request and answer by e-mail.
• All changes are to be listed in the project activity report and should confirm the picture that the
changes are of a minor degree when being described in its full context.
Major changes are:
• A change with a major impact on the projects implementation or more than 40 000 Euro increase in
one project budgetline
• A change with a major impact normally requires a formal request in a specific template and the
Secretariat will provide information on how to make that request.
• Different bodies can be responsible for approving the change (Managing Authority and Programme
Monitoring Committee)
Major changes on the overall project can normally only be allowed once during the project lifetime.
What happens after your project submission
Thank You for Listening!
www.northernperiphery.eu
Download