BI-ANNUAL REGIONAL BULK PERFORMANCE EVALUATION REPORT FOR KSD PIP - MTHATHA BULK WATER SUPPLY SCHEME EASTERN CAPE CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 APRIL 2014 TO 30 SEPTEMBER 2014 2 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 TABLE OF CONTENTS 1. Introduction 2. Background 2.1 2.2 2.3 2.4 2.5 3. Progress to date 3.1 3.2 3.8 3.9 3.10 4. 4.5 The monitoring approach Data analysis and reports for implementation purposes. Data analysis and reports for performance requirements Responsible person for data analysis and report generation (financial and non-financial reports) Challenges with the monitoring and reporting tasks Project result and beneficiaries 5.1 5.2 6. Implementation of approved business plan Schedules of work and phasing of the activities 3.3 Contracts rolled out in the financial year 2013/14 and to be rolled out in 2014/15 3.4 Financial Management 3.5 Coordination with other stakeholders 3.6 Risks taken and management thereof 3.7 Management of the programme Capacities dedicated to the programme Capacity building for the staff within the programme Key challenges within the project Monitoring 4.1 4.2 4.3 4.4 5. Description of project Project History Project concept, design and plan Start date – duration of the programme Fund previously allocated to project Outcomes and outputs Beneficiaries and project results. Conclusions 6.1 6.2 6.3 Main successes and failures of the project to date Outcomes, outputs, successes and failures versus costs Ownership and sustainability of infrastructure works 7. Lessons learned 8. Recommendations ANNEXURE A: Project Implementation Photos ANNEXURE B: List of villages expected to benefit from Package 1 ANNEXURE C: Details of contracts awarded under Package 1 ANNEXURE D: Details of Job Opportunities 3 REGIONAL BULK INFRASTRUCTURE GRANT 1. SEPTEMBER 2014 INTRODUCTION In terms of Section 10(7) (b) of the Division of Revenue Act No 10 of 2014 (DORA) as promulgated in Government Gazette No 37595 dated 26 April 2014, the transferring national officer must submit a quarterly performance report for all Programmes funded by a Schedule 6 allocation within 45 days after the end of each quarter, in accordance of the relevant framework to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this report is to provide a bi-annual performance evaluation report covering the first and second quarters of RBIG funded projects, in compliance with the DoRA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering the first 6 months of the 2014/15 fiscal year, is for KSD Presidential Intervention Project (PIP) - Mthatha Bulk Water Supply Project is being implemented under the strategic objectives of the Mthatha Regional Bulk Water Supply Scheme. It is one of the Regional Bulk Infrastructure Grant projects currently being implemented by the OR Tambo District Municipality in the Eastern Cape Province, with Department of Water and Sanitation (DWS) as funder. OR Tambo DM in October 2012 finalised the appointment of Amatola Water Board as an Implementing Agent for this project. 2. BACKGROUND 2.1 Description of Project The primary focus is to augment current bulk water supply within the Mthatha Town and KSD Municipality, located in the OR Tambo District Municipality in the Eastern Cape. The project aims to increase the capacity of the water treatment works and to improve the bulk water distribution to the region thereby unlocking housing and commercial developments. The project aims at initially focusing on five corridors within a radius of 30 km from Mthatha. These corridors are Mthatha, Libode, Mqanduli, Ngqeleni and Nqadu Corridors. The targeted Local Municipality is KSD and its neighbouring Nyandeni Municipality. The area is predominantly rural in nature, with numerous villages scattered throughout the region. Mthatha is the largest town, with municipal offices, hospital, university a magistrate’s court, police station, prison, and a number of businesses and light industries. The area has been, and still is, characterised by significant backlogs in water and sanitation, as evidenced by the results of the Community Survey, Statistics South Africa, in 2007. 2.2 Project History The Mthatha Presidential Intervention Projects together with their catalyst projects have been earmarked for infrastructure development and socio economic development in the OR Tambo District. These projects include some of the projects currently being 4 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 implemented by GIBB as the Lead Consultants and some SMME’s targeted for skills transfer and empowerment. Some of the projects involve implementation of the infrastructure rehabilitation that have been identified thus far and also for the infrastructure upgrade required in order to accommodate housing developments such as the Breaking New Ground (BNG) (17,000 Units) proposed developments; and also for refurbishment of the Mthatha Water Supply as part of the Presidential intervention. Should funding be provided for the implementation phase, this would go a long way to transforming Mthatha into the economic and social power house of the OR Tambo District Municipality and the whole of Eastern Cape. It was agreed that the District and KSD Municipality work together to promote the provision of the primary bulk services for 17,000 new households, the interim focus being the targeted 6,500 new homes. Should these primary bulk services not be constructed, no new development can take place in the area. Based on studies undertaken by GIBB the capacity of Thornhill Water Treatment Works (WTW) will need to be increased by 20 Mℓ/D to cater for the proposed new BNG (approximate 6,500 units) housing project. The Thornhill WTW is currently operating at full capacity (60 Mℓ/D). The Thornhill raw water mains and raw water pump station will also require upgrade to cater for the additional 20 Mℓ/D. It is proposed by the OR Tambo DM that a new Water Treatment Works at Rosedale of 25 Mℓ/D would be required as the initial unit that would eventually be upgraded to 150 Mℓ/D. GIBB had prepared a technical report that was sent to MIG for funding application. The report contained most of the bulk work that would be required to be done in order to accommodate the development of 17,000 new houses. This appointment was for the planning, design, and construction monitoring of the bulk water supply components of the scheme, to be undertaken in a phased manner over a number of years, based on BNG Developments within the area and the availability of funding. The estimated cost of the bulk water supply scheme is approximately R600 million. Funding is being made available by DWS. In addition to the targeted BNG Developments, OR Tambo DM through Amatola and GIBB have identified four corridors within a radius of 30 km from Mthatha and these will be targeted for Bulk Water Infrastructure for the period of 5 years. The overall cost estimates for this scope of work is approximately R2.5 billion. 5 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Mthatha Dam Fig 1: Mthatha Town (KSD Local Municipality) Thornhill WTW Figure 2: Existing Raw Water Pipeline Entering Thornhill Mthatha Dam as Water Source: Mthatha Dam is the primary source of water. Mthatha Dam supplies water to the Thornhill WTW. The dam is located approximately 6 km north-west of the town. The dam was constructed in 1977 for the purpose of water supply to Mthatha Municipality and storage for the releases to Eskom hydropower stations. The Mthatha dam is a rock-fill type and has an ogee-crescent shaped concrete spillway. The catchment area for the dam is 6 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 approximately 886 km2. The mean annual runoff (MAR) for the dam is 212 million m 2. The approximate co-ordinates are: 31º 32´ 24˝ S 28º 44´ 13˝ E The dam has a 1-in-50 year yield of 145,5 million m3 per annum of which 21.9 million m3 per annum (60 Mℓ/D AADD – annual average daily demand) is allocated to Thornhill Bulk Water Supply for domestic, commercial and industrial usage. There is an additional 15.3 (41.9 Mℓ/D AADD) million m3 per annum to be allocated to the proposed Rosedale Water Supply Scheme (a supplementary for the peri-urban villages). The proposed additional supply to Thornhill Bulk of approximately 9.1 million m 3 per annum (20 Mℓ/D ) can still be supplied adequately by the Mthatha dam. Additional supply from the Mthatha Dam will also be extracted through the proposed Rosedale Regional Treatment Works. Table 1: Mthatha Dam Allocations Mthatha Dam Million m3 per annum Assured Yield (1 : 50 yr) 145.5 Thornhill Water Treatment Works 21.9 Additional requirement for upgrade 6.2 Rosedale (new supply) 12.17 TOTAL DOMESTIC DEMAND (Annual) 40.27 ESKOM (remainder) 105.23 % Allocation Table 2: Domestic Water Demand for Mthatha Town Item Thornhill Water Rosedale Water Treatment Treatment Works Works (Proposed) AADD required (Mℓ/d) 65.6 25 Design Treated Water Delivery Rate (ℓ/s) 759.3 289.35 Allowance for Reticulation Losses in whole system (Mℓ/d) – 5% AADD plus reticulation losses (Mℓ/d) Factor applied to AADD to give PWDD for whole system (1.22) Nominal Capacity of the Works (Mℓ/d) Allowance for Losses in the treatment works (Mℓld) – 5% 3.3 1.25 68.9 26.25 14.43 5.5 83.3 31.75 4.2 1.6 Nominal Capacity of the Works 87.5 33.35 15.1% 4.3% 8.36% 27.7% 72.3% Total Domestic Demand on Mthatha Dam 95.15 120.85 7 REGIONAL BULK INFRASTRUCTURE GRANT Item SEPTEMBER 2014 Thornhill Water Treatment Works Rosedale Water Treatment Works (Proposed) Total Domestic Demand on Mthatha Dam 1,012.7 386 1,398.70 3,645.7 1,389.6 5,035.3 (Mℓ/d) Design Peak Raw Water Flow Rate (ℓ/s) Design Peak Raw Water Flow Rate (m3/hr) Table 3: Proposed Sequencing of the Upgrades to the Mthatha WTW Period Thornhill Increments Rosedale WTW Increments Total Capacity 2.3 0- 1 1-2 2-3 3-5 5+ Current Short Term Medium Term Long Term Full Capacity 60 20 3 80 20 25 25 105 120 40 50 25 170 120 120 75 25 195 100 50 220 83 Project Concept, Design and Plan The projected daily demands, current and future water audit are all indicative that the Thornhill Water Supply system needs an urgent upgrade. The current bulk water distribution system and the relevant zone system reflect imbalances in terms of addressing demand and storage needs and therefore require major alterations. Other supportive factors leading to the proposed project are as follows: Shortage of current and future storage capacity Old infrastructure (90% AC pipes over 25 years old) Long pump durations (Average 20 hrs) Lack of Town Planning and Water Supply Coordination Imbalance of flow pressures Inadequate revenue collection Poor Operation and Maintenance. The design philosophy below is based on the integrated approach in order to address the key problems associated with the Thornhill Water Supply system. The purpose of the project is to ultimately supply 150 Mℓ/day of potable water to a population of 1,000,000 people (approximately 200,000 households), allowing for an increase in the average consumption per capita from 90 ℓ/c/d to 150 ℓ/c/d over a 20-year time horizon. The Medium Term targets are a supply of 115 Mℓ/day of potable water to a population of 750,000 people (approximately 150,000 households) and the Short Term target is to supply 95 Mℓ/day to a population of 650,000 people (approximately 130,000 households. The targeted categories of consumers to be supplied with potable water are domestic water users throughout the KSD Local Municipality and Nyandeni Municipality, and commercial and light industrial users and institutional users mainly within the towns of 8 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Mthatha, Mqanduli, Ngqeleni and Libode. These beneficiaries and the required bulk infrastructure have been captured in a master plan report. In essence, this Master plan covers the following: Upgrading the delivery of raw water from Mthatha Dam to Thornhill Water Treatment Works; Extending the capacity of the Thornhill Waterworks by 20 Mℓ/d to 80 Mℓ/d (current) and by a further 40 Mℓ/d in the short-to-medium term; Upgrading the clear water pumping capacity to Mthatha town and Southern and Eastern surrounds out of Thornhill Waterworks; Constructing a new 25 Mℓ/d waterworks (Rosedale), upgradable in 25 Mℓ/d modules to 100 Mℓ/d, to supply the areas to the North and West of Mthatha town; Constructing a new system of bulk supply rising and gravity mains and reservoirs to transfer the clear water pumped out of the Thornhill and Rosedale Waterworks to the extended areas of supply up five (5) corridors: o o o o o Mqanduli Corridor (to the South) Ngqeleni Corridor (to the SE) Libode Corridor (to the East) Nqadu Corridor (to the North) Airport Corridor (to the West) Upgrade reticulation links to BNG areas in and around Mthatha Upgrade storage capacity where needed (particularly relevant for the BNG areas). Provide strategic links to key institutions: o o o o KD Matanzima Airport The Military Base near the airport The Bedford Hospital The Nelson Mandela Hospital Construction of the first two items above and the first stages of Libode are already underway. The methodology that was adopted in the planning stage of the project was to review the Mthatha Master Plan and technical reports for water supply by GIBB, and other professional service providers who had been working in the area, and thereafter to propose a bulk water supply scheme that complied with the guidelines and principles that have been used by Water Boards. In the context of Mthatha this involved taking into account the need for adequate, reliable water source (Mthatha Dam) that is treated in a two WTW plants (Thornhill and proposed Rosedale), feeding water into a primary and secondary bulk distribution network that is capable of supplying strategically placed bulk reservoirs that supply a number of reticulation networks, so as to provide potable water to a large number of communities. The connections from the bulk treated water supply system to the villages do not, at this stage, form part of GIBB’s current appointment. The scheme comprises a number of components, viz. the raw water supply system, the upgrade of the secondary bulk infrastructure and reservoirs as described below: 9 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Increasing Raw Water Supply System Raw water is conveyed to the Thornhill Water Treatment Works via a gravity pipeline. An emergency raw water pump station, with a capacity of 23 Mℓ/D is located on the Mthatha River, below the dam. Raw water gravitates from the Mthatha Dam into Thornhill Water Treatment Works via a short section of 1,000 mm diameter pipe through the dam embankment, and then via two steel pipes, one 600 mm diameter, and the other 800 mm diameter. Raw Water Pump Station The original system was designed using the 600 mm diameter pipeline. With low water levels and higher water demand, this was insufficient to provide adequate water, and a raw water booster pump station catered for these system requirements. It is assumed that this booster pump station delivered water to an existing 20 Mℓ balancing dam via 600 mm diameter pipes. From this elevation, the flow can gravitate to the Thornhill Water Treatment Works. To upgrade the system to provide 88 Mℓ/day, this system would require the pumps to be modified and refurbished. The pump station would then deliver the flow against a head of 10.497 m at conditions where full flow is delivered with the dam level down at 25% of the full supply level. Existing 600 mm AC Pipeline The 600 NB AC pipeline was installed to supply water from the dam to the water treatment works under gravity, but was augmented at a later date with the rising steel main to make use of the lower water levels in the dam to enable water at lower levels to be raised by means of pumping in order to get an adequate water supply to the water treatment works. However, at the time of the assessment, it was speculated that the reason for the 600 mm NB AC line being closed (sometimes) at the water treatment works was to prevent suction head problems in the common manifold upstream between the dam and the pump station during pimping. The ‘starvation’ of water to the pump sets could result in pump cavitation, which will significantly reduce the life expectancy of the pump sets. The 600 mm diameter asbestos pipeline is currently operated only as a gravity supply, and is capable of conveying a maximum of 31 Ml/d (375 l/s.) only when the Mthatha Dam is full. When the Dam level has dropped from full supply of 692.94 MSL to approximately 685.0 MSL, the gravity flow drops to only 17 Ml/d (200 l/s). Furthermore, the pressure in the pipeline must be boosted to lift the water over the highest point which has an elevation of 684.5 MSL, approximately 2 000 m from the Dam. Although the 600 mm NB AC gravity pipeline was not operational, the line is still under pressure at it has been isolated at the water treatment works. However, the steel portions of this line, where it crosses the river on the pipe bridges, have corroded badly and are in need of significant repair, but preferably replacement. Existing 800 mm diameter Steel Pipeline This pipeline has been in service for some time (over 28 years), and is reportedly in need of some rehabilitation. The 800 mm diameter steel pipeline is currently operated via the raw water booster pump station. It has been calculated that, when operated under gravity, a maximum flow of 64 Ml/d (750 l/s) can be achieved only when the Mthatha Dam is full. When the Dam level has dropped from full supply of 692.94 MSL to approximately 685.0 MSL, the gravity flow drops to only 35 Ml/d (420 l/s). The pressure in this pipeline must also be boosted to lift the water over the highest point which has an elevation of 684.5 MSL, approximately 2,000 m from the Dam. The status of the operational 800 mm NB steel rising main is in a poor condition, but not beyond repair, and with an extensive 10 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 maintenance programme the situation could be well improved. There were a number of leaks along the pipeline, mostly in the vicinity of welds. The poor status of the fittings associated with these two pipelines warrants special mention as provided below: Main air valve bolts are corroded with associated leaks and submergence of the equipment Some chambers had no access ladders for ease of maintenance, and some chamber lids necessary for the protection of the equipment were missing. The external corrosion protection of pipes over pipe bridges has deteriorated and some rust visible. As the pipeline(s) increase in size and the friction losses decrease, so the amount of power decreases. The analyses therefore compare the decrease in running cost with the increase in capital cost associated with the larger diameter pipes. This analysis is based on considering the net present value of each option over 20 years, and using a discount rate of 3%, taking capital, maintenance and running costs into account. It has been assumed that the full flow should be delivered, even when the level of water in Mthatha Dam has dropped to 25% of full supply level. It is further assumed that should the water level drop below 25%, the design flow could be reduced, as a result of water restrictions, to 80% of the design flow when the dam is 20% full. The spread of housing to the east of the Thornhill Water Treatment Works, known as Phola Park has dwellings constructed in the pipeline servitude over both raw water pipelines, and is a matter for concern, that would need to be urgently addressed. Pipe Materials Bulk water supply pipelines of this nature, require that the most durable and reliable materials have to be used. The experience of all major water supply authorities in South Africa has indicated that there are two issues – proven durability of the material of the pipe, and protection of the material from corrosion. The most durable pipe materials that are considered for this application are steel, ductile iron and GRP. Corrosion protection for steel and ductile iron will be cement mortar lining internally and possibly externally, but epoxy and tape systems will also be considered. Cathodic protection may be indicated as being required during detailed design. The design has assumed the use of cement mortar lined pipes, with the associated internal diameters used for the hydraulic calculations. Emergency Raw Water Pump Station On the site of the Thornhill water Treatment Works there is a pump station that draws water directly from the Mthatha River, and delivers to the head of works via the raw water pipeline from the Mthatha Dam (600 mm diameter). The pipe work from each emergency pump is 400 mm diameter, with two pumps delivering into a short section of 450 mm diameter pipe before the connection to the main 600mm diameter supply pipeline. Assuming a velocity of 1.5 m/s in the 450 mm diameter pipeline, an additional (or alternative to the Mthatha Dam) flow of 21.6 Mℓ/d (250 ℓ/s) can be abstracted from the river. In 2004, an additional river abstraction pump and dedicated 400 mm diameter steel rising main across the water treatment works site was planned. The design of this system allows for a further flow of 21.6 Mℓ/d (250 ℓ/s) to be abstracted from the river with this separate system. 11 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 The Emergency Raw Water Pump Station can therefore deliver up to a total of 43.2 Mℓ/d (500 ℓ/s) in this configuration. It is understood that the pumps are not currently (December 2011) fully operational. During the implementation of this project, the Emergency Raw Water Pump Station will be reinstated so that it would augment the system especially during raw water pipe installation and refurbishment. Figure 3: Existing Emergency Raw Water Pump Station at Thornhill Raw Water Pipe at Mthatha DAM Intake Tower The design of the upgrading of the raw water supply pipelines takes into account the short term high head losses and velocities in the Mthatha dam Intake tower (at 1 100 ℓ/s the velocity is some 3.3 m/s) until this pipe work is upgraded, with an associated head-loss of 5.6 m before reaching the existing raw water booster pump station. Assuming a drought condition, with a low water level in Mthatha Dam of 681.0 m (msℓ), the hydraulic grade line will drop to an absolute minimum of 675.4 m (msℓ) at the raw water pump station where the ground level is 675 m (msℓ). It is assumed that under such extreme drought conditions, however, there will be water restrictions in place, and there would not be routine abstraction at maximum flow rate, even though it will be possible. With the upgrading of the pipelines from the booster pump station to the Thornhill Water Treatment Works, it will be possible for the additional head required from the booster pumps to be reduced to a minimum – indeed, with the levels of water in the Mthatha Dam generally maintained close to full supply level as in the past, these variable speed pumps will not even be required to run for much of the time at all. The graphs below shows the ground profile along the pipeline route, and at full design flow, and the hydraulic grade lines, which are shown for both average conditions when the dam is 65% full 688.7 m (msℓ), and when the dam is close to empty: 12 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Figure 4: Hydraulic gradient under normal conditions Figure 5: Hydraulic gradient when dam is close to empty Chainage, m By increasing the pipe work diameter in the intake tower, gravity supply from Mthatha Dam to Thornhill will be possible for extended periods. It can be seen then that domestic demand, after both the upgrading of supply via the Thornhill Water Treatment Works, as well as the increase via the proposed Rosedale Water Treatment Works, this amounts to 29.8% of the assured 1 in 50 year yield of the Mthatha Dam. The strategy of increasing pipeline capacity between Mthatha Dam and the Thornhill Water Treatment Works will also resulted in a significant reduction in power required under all conditions. The project to upgrade the supply of water via the Thornhill Water Treatment Works includes the refurbishment of the existing 800 mm diameter pipeline for some 2,200 m, and the replacement of the existing 600 mm diameter pipeline which runs parallel to the existing 800 mm diameter pipeline with a second 800 mm diameter pipeline, As a result of the need to deviate the last section away from the newly established Phola Park, a new 1,200 mm diameter pipeline, 2,000 m long, will be located along a more secure route to 13 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 the Thornhill Water Treatment Works. This system is designed to convey 1,100 ℓ/s at peak. As a result of this increased demand, and noting that should the proposed Rosedale Water Treatment Works also be supplied with raw water via this intake tower, the peak demand will increase to some 1,488 ℓ/s. As a result of this requirement for increased capacity, as well as the very poor condition of the two existing 450 mm diameter manifolds in the intake tower, it is proposed that these should be replaced with larger diameter pipes and fittings. It is understood that a project is under way to replace these pipes and fittings. This is an opportunity for the size to be increased to accommodate additional future flow. Upgrade and Extension of the Thornhill Treatment Plant The existing Thornhill Water Treatment Works (WTW) in Mthatha has a treatment capacity of 60 Mℓ/day. The constraint on the option of supplying all the targeted demands from the Thornhill Water Supply system is the space limitation at the Thornhill WTW. Presently it is possible to upgrade the works to ensure supply of water to the 6,500 units however the future BNG developments (10,500 units) would require further upgrade of the Thornhill WTW by another 25 Mℓ /D. The upgrade of the Thornhill Water Treatment Works from 60 Mℓ /D to 80 M ℓ /D forms the basis of the Phase 1 Upgrading. Furthermore because of the Thornhill raw water infrastructure constraints and space constraints at the WTW site, the Thornhill WTW shall not be upgraded beyond the capacity of 120 Mℓ/D. The additional 25 Mℓ/D to cater for the remaining 10,500 BNG units will be integrated into the long term strategy and planning for the Mthatha Bulk Water Regional Supply project, or the Rosedale Bulk Water Treatment Works. The Rosedale Treatment Works is required for the BNG Phase 1A. This WTW will initially have a capacity of 25 Mℓ/D and will be increased incrementally through additions of 25 Mℓ/D units until it reaches a full capacity of 100 Mℓ/D within a 5 year horizon. It is proposed that for operation and maintenance purposes, the design of the works will be similar to the Thornhill WTW. The current water supply from the Thornhill Treatment Works is delivered in two directions, Fortgale to other regional reservoirs, and Ncambedlana (Northcrest) to other regional reservoirs. The approach to this option was based on a medium term solution which focused on improving the system’s operating efficiency from the Thornhill WTW to Signal hill and Ncambedlana. This approach can be achieved through the upgrade of the Thornhill WTW and introduction of additional storages at the key zones such as Signal hill, Ncambedlana (North crest and HL), and Zamukulungisa zones. The actions recommended for this option are as follows: Upgrade the Thornhill WTW capacity by an additional capacity of 20 Mℓ/D. Re zone the Thornhill Water supply system Increase storage in the system Replace old bulk mains and valves. The constraint on this option is the space limitation at the Thornhill WTW. Presently it is possible to upgrade the works to ensure supply of water to the 6,500 units however the future BNG developments (10,500 units) would require further upgrade of the Thornhill WTW by another 25 Mℓ /D. 14 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 The additional 25 Mℓ/D to cater for the remaining 10,500 BNG units will be integrated into the long term strategy and planning for the Mthatha Bulk Water Regional Supply project, or the Rosedale – Libode Bulk Water Supply. The upgrade of the Thornhill Water Treatment Works from 60 Mℓ /D to 80 Mℓ/D forms the basis of this upgrading. Figure 6: Thornhill Water Treatment Works The Thornhill Water Treatment works is to be designed to cater for the peak week daily demand (PWDD) which, when working in conjunction with a treated water storage capacity of 2 days of annual average daily demand (AADD) will ensure that under all conditions, the reservoirs will have a minimum of 1 day AADD available for emergencies. It is also assumed that the works would operate over 24 hours per day during peak periods to deliver the design flow of 84 Ml/d of treated water from the water treatment Evaluation of Alternatives The alternatives for increasing the capacity of the system for conveyance of raw water from the Mthatha Dam to the Thornhill Water Treatment Works have been considered. All require the use of pumps to provide an adequate service under all conditions, most particularly when the water level in the Mthatha Dam has dropped during dry periods to less than 685.0 MSL (Full supply level 692.94, and bottom water level 681.8 MSL). It has been requested by operational staff, and supported by the results of this investigation, that standby power is provided at this pump station. Continued use of the existing system comprising the raw water pump station, and 800 mm diameter steel pipeline, which requires refurbishment, has the highest running cost as a result of the electrical power needed. This cost can be reduced by using the existing 600 mm diameter AC pipe, but this is risky as it is reported to be in very poor condition. This option also does not address the concern regarding the houses in Phola Park being at risk should there be a failure of either of these pipelines. 15 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 The construction of a new 800 mm diameter steel pipeline, to be laid in parallel with the existing pipeline, but deviated along a new route to avoid Phola Park, with a new pipe bridge required was the next most attractive option. Should the philosophy be to completely replace the existing pipelines, which would be retained for emergencies, a 1,200 mm diameter steel pipeline is selected as the optimum size. However, this option is relatively expensive compared to the other options available. The combination of a new 800mm diameter steel pipeline to be built parallel to the existing 800 mm diameter pipeline, with the last section of approximately 1,000 m being rerouted around Phola Park using a 1,200 mm pipeline was then recommended. In addition Paradigm Project specialist sub contracted to Anix Trading conducted pipeline external coating integrity assessment for the existing 4.2 km of DN800 pipeline from Mthatha Dam Pump station to the Thornhill Water Treatment Works (WTW) and are to undertake Cathodic Protection (CP) from end, engineering and Design (FEED). The extent of the pipe damage caused by corrosion and other environmental factors was assessed using the Pipe Current Meter (PCM) technique. The PCM survey was conducted from 07 November 2012 to 11 November 2012 from the pump station to the WTW. A report (Pipeline Refurbishment PCM Survey – Report No PP/ORDT/PCM Report No 1) detailing the findings and recommendation from the survey was submitted to GIBB, Amatola Water and OR Tambo District Municipality (ORTDM). A copy of the report is attached for reference. From the Pipeline Refurbishment PCM Survey Report, forty five (45) defects warranting attention were identified along the pipe route. It was also highly recommended that the entire pipeline be replaced with a new pipeline equipped with a Cathodic Protection (CP) System. In light of the above, we concur with the recommendation from the PCM Survey report that there is merit in replacing the entire pipeline. However, in order to minimise disruptions to the water supply to Mthatha, we propose that new DN800 steel be laid parallel to the existing pipe. It is impossible to replace the existing pipe without disrupting the raw water supply. Proposal as a result of the detailed investigation of the existing DN800 It was against this backdrop that we propose to lay a new DN800 steel pipe to replace the existing DN800 steel pipe. The proposed pipe will be laid parallel to the new pipe currently being constructed by WK Construction under Contract No SCMU ORTDM 10-11/12A MIS 204241/1: Replacement of DN600 with DN800 Steel Pipe. The proposal therefore entails the construction of a new 2.24 km of DN800 steel pipe and the scope of works is similar to that of WK Construction. The emergency pump station located at the Thornhill Water Treatment Works could be used, but requires the existing equipment to be refurbished. The water has to be made available by releasing it from Mthatha Dam, requiring careful management so as not to result in excessive water loss. Consideration was also given to the possible upgrading of this pump station to increase its capacity. The construction cost of the various options is summarised below. The influence of running costs is reflected in the table of net present values that follows. The first column is provided only for comparison, as it is not an option that can be implemented – refurbishment of a pipeline that is fully utilised is not possible. 16 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Bulk Supply to Fort Gale – Signal hill Zone Water is pumped from Thornhill Water Treatment Works to Fort Gale reservoirs through tow (2) No. 600 mm diameter pipes, one is an AC pipe and the other one is a Steel pipe. The water supply to Fort Gale reservoirs (6 Mℓ, 8 Mℓ and 2 Mℓ) is pumped at the water treatment plant by four sets of horizontally split centrifugal pumps. The pumps are currently pumping for 20 hrs. The design duty for the pump (6 & 7 alternating) that pumps water through the AC pipe is 230 ℓ/s of flow at 127 m head. The pump rated power is 400 kW and pump model is EME 200/250. The design duty for the pump (3 & 5 in parallel) that pumps water through the Steel pipe is 11 7 ℓ/s of flow at 110m head. The pump rated power is 225 kW and pump model is 6/8-STGMM. The pumps will need to be upgraded to cater for future demand to a proposed design duty pump. Water is pumped from the Fort Gale reservoirs to the Signal hill reservoirs to cater for the demand. Here two rising mains of 450 mm and 350 mm diameter are used. The 350 mm diameter pipeline is also used as gravity main when the pumps at Fort Gale are not running. The approximate lengths of these pipes are 1.60 km and 1.80 km respectively. These two pipes are connected to a 600 mm diameter steel pipe at the inlet of the reservoirs. This system supplies, Zamukulungisa, Zimbane, Town Owen Dam, Ngangelizwe, and Kwezi zones. The BNG development project would require that Zamukulungisa, Zimbane, Signal hill zones reservoir and mains be upgraded. Bulk Supply to Ncambedlana/Northcrest Zone The water supply to Ncambedlana/Northcrest reservoir (8 Mℓ) is pumped at the water treatment plant by horizontally split centrifugal pumps. The pumps are currently pumping for 20 hrs. The maximum operation discharge for the pumps is 140 ℓ/s and the maximum operation head is 125 m. The design duty for the pumps is 117 ℓ/s of flow at 106 m head. The pump rated power is 225 kW and pump model is 6/8-STGMM. The pump will need to be upgraded for future demand to a proposed design duty pump. The bulk clear water supply from the Thornhill Water Treatment Works is pumped through a 450 mm diameter rising main to the 8 Mℓ Ncambedlana (Northcrest) reservoir. There are two supply pipelines from the Ncambedlana reservoir. The first is a 350 mm diameter gravity pipeline which supplies the Maydene 3 Mℓ reservoir. A further 200 mm diameter rising main is used to supply the 3 Mℓ Ncambedlana high-level reservoir. The pump station at Ncambedlana/Northcrest supplying Ncambedlana HL reservoir (3 Mℓ) has two KSB model WRLN 75 centrifugal pumps. The pump station works on a single duty and single standby pump system. The design duty for the pumps is 40 ℓ/s of flow at 112 m head. This system supplies, Northcrest, Hillcrest, Norwood, Ncambedlana, Maydene Farm and Lower Corana. In order to cater for the proposed BNG development units within this zone, the infrastructure such as the reservoirs in Ncambedlana HL, Ncambedlana and Maydene farm together with the 450 mm diameter ThornhillNcambedlana pumping main and the Ncambedlana – Ncambedlana HL pumping main will require an upgrade. The challenge and constraint as already stated above was the Raw Water bulk infrastructure from the Mthatha Dam to the Thornhill WTW and also the availability of space for the upgrade at the Water Treatment Works. Another limitation was also the availability of the way leaves for all the proposed upgrades of the existing system. The optimum option strategically linked to future water resource planning was that of taking advantage of the proposed bulk pipeline from Rosedale to Libode (Ø=700 mm and Ø=600 mm) sized to allow for off takes into the existing reservoirs and proposed reservoirs within the Ncambedlana zone. The resulted in the split of Mthatha supply into two bulk supply 17 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 systems divided in their supply zones by the Mthatha River. This option therefore requires a second Water Treatment works at Rosedale which would supply all the supply areas in west of Mthatha and also be used for future extensions to other Towns such as Libode, Mqanduli, Ngqeleni etc. Planned Bulk Water Infrastructure Upgrade The planned new project involves the upgrades of Thornhill Water Supply scheme that was originally designed to cater for 60 Mℓ/D and is now required to cater for 80 Mℓ/D. These upgrades includes the raw water infrastructure upgrade, the water treatment works upgrade and the secondary infrastructure such as supply mains and reservoirs that would be affected by the increase in demand due to the earmarked BNG developments in Mthatha. The Thornhill water treatment works upgrade will only accommodate the 6500 BNG units and the informal settlement (Joe Slovo, Chris Hani and Nelson Mandela) as these are currently supplied through the strained Mhlahlane WTW. It should be noted that there is need for a rollout of the proposed Mthatha Regional Scheme in order to cater for the remaining 10,500 BNG units and also allow for a split of Mthatha Water Supply into two systems (Thornhill Water Supply and Rosedale Water Supply). This rollout would include the detailed design and construction of the new abstraction point, raw water mains and the Rosedale Water Treatment Works. This particular Mthatha Regional Water Supply Scheme rollout will form a separate phase to the proposed Thornhill Bulk Water Supply Scheme Upgrade. The existing infrastructure and proposed Thornhill Bulk Water Supply Upgrade is shown in Fig. 7 Figure 2.7: Proposed bulk Infrastructure Upgrade Fig 7: Proposed Thornhill Bulk Water Supply Upgrade 19 REGIONAL BULK INFRASTRUCTURE GRANT 2.3 SEPTEMBER 2014 Funding Updates The two main funding streams for the project are the MIG and RBIG. The Table 5.0 below gives a summary of the funding required for the various corridors targeted for the supply of bulk water from Mthatha Dam. Table 5: Funding for the various corridors for the KSD Bulk Water PI Project. Description Mthata Outlet Modifications Dam Outlet Raw Water Thornhill Water Rosedale Project Cost R 120 000 000 R 180 306 752 Thornhill WTW Mthatha South Mqanduli Corridor Signal Hill Strategic Linkages Raw Water R 101 251 107 R 450 075 103 R 411 259 590 Rosedale WTW Mthatha North Nqadu Corridor Libode & Ngqeleni Corridor R 407 420 953 R 180 478 428 R 79 851 250 R 1 335 402 348 R 72 509 795 R 2 577 387 566 R 67 339 460 R 1 241 985 217 R 506 895 127 The Table 5.1 below indicates the funding split between MIG and RBIG for the various strategic corridors for the project. Table 5.1: The MIG and RBIG Funding for the various corridors for the KSD Bulk Water PI Project. Description Mthata Dam Outlet Raw Water Thornhill Water Rosedale Project Cost MIG RBIG R 120 000 000 R0 R 120 000 000 R 180 306 752 R0 R 180 306 752 Thornhill WTW Mthatha South Mqanduli Corridor Signal Hill Strategic Linkages Raw Water R 101 251 107 R 450 075 103 R 411 259 590 R 20 869 565 R 213 496 145 R 307 041 184 R 80 381 542 R 236 578 958 R 104 218 406 R 72 509 795 R 57 869 795 R 14 640 000 R 67 339 460 R0 R 67 339 460 Rosedale WTW Mthatha North Nqadu Corridor Libode & Ngqeleni Corridor Sub-Total R 407 420 953 R 180 478 428 R 79 851 250 R0 R 72 157 324 R 27 361 675 R 407 420 953 R 108 321 104 R 52 489 575 R 506 895 127 R 145 910 178 R 360 984 949 R 2 577 387 566 R 844 705 866 R 1 732 681 700 Funds required for the project 20 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 5.2 below indicates the funding that is required for the entire bulk water project. This excludes the reticulation for the supply areas. Table 5.2: Funding for the entire water project MIG RBIG Required Available Shortfall Required Available Shortfall R 844 705 866 R 266 000 000 R 578 705 866 R 1 732 681 700 R 897 483 846 R 835 197 854 Funds previously allocated to project Table 5.3 below indicates the funding that was made available to the project. Table 5.3: Funding for the project YR 2012/2013 to YR 2014/15 2012/13 MIG R120,000,000 RBIG Budget allocation R48,048,614 2013/14 2014/15 R113,518,937 R 150,000,000 Table 5.4 below indicates the funding is required for the next financial years up to FY 2016/17. The corridors have been sub divided into packages to enable better management of the procurement process. PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE MARCH 2014 Table 5.3: Funding for the project YR 2013/2014 to YR 2016/17 Cash flow Requirements Water Packages Package 1 Package 2 Package 3 Package 4 Package 5 Package 6 Package 7 Package 8 Package 9 Water Total FY 13/14 FY 14/15 RBIG 102 972 10 680 0 0 0 0 0 0 0 113 652 MIG 20 870 19 493 44 962 13 781 0 0 0 0 0 99 105 FY 15/16 RBIG 41 537 72 239 80 357 65 767 111 680 46 657 53 186 0 3 500 474 924 MIG 36 522 34 075 79 865 51 554 56 367 65 718 20 087 0 0 344 188 FY 16/17 RBIG MIG 0 6 286 28 129 33 247 113 757 44 577 59 096 111 792 100 211 497 096 RBIG 17 802 30 960 68 304 28 186 55 022 43 328 22 794 27 362 1 500 295 256 0 0 33 865 0 7 159 23 332 0 27 362 0 91 717 MIG 15 652 14 604 34 228 22 094 24 157 28 165 8 609 0 0 147 509 Table 5.4: Funding split per package Packages No of Tender Contracts Packages Values Tender Date MIG contracts RBIG contracts Package 1 10 R 610 596 898 Apr-12 1 9 10 R 235 229 826 R 375 367 072 R 610 596 898 Package 2 7 R 188 336 714 Oct-13 3 4 7 R 68 171 867 R 120 164 848 R 188 336 714 Package 3 10 R 335 843 810 Dec-13 4 6 10 R 192 919 120 R 142 924 691 R 335 843 810 Package 4 6 R 214 629 088 Feb-14 4 2 6 R 87 429 088 R 127 200 000 R 214 629 088 Package 5 10 R 360 984 012 Apr-14 5 5 10 R 87 684 113 R 273 299 899 R 360 984 012 Package 6 8 R 228 443 945 May-14 4 4 8 R 117 213 868 R 111 230 077 R 228 443 945 Package 7 8 R 163 772 405 Jun-14 3 5 8 R 28 696 310 R 135 076 095 R 163 772 405 Package 8 9 R 195 762 484 Jul-14 2 7 9 R 27 361 675 R 168 400 810 R 195 762 484 Package 9 5 R 279 018 209 Aug-14 0 5 5 R 279 018 209 R 279 018 209 73 R 2 577 387 566 26 47 73 R 1 732 681 700 R 2 577 387 566 Total MIG R 844 705 866 RBIG Total PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE 2.4 MARCH 2014 Start date – Duration of the Programme GIBB was appointed as Lead Consultant in November 2011 in by OR Tambo DM. In April 2012, GIBB conducted the Procurement process for the Construction Contracts. Six Contracts were put to open tender for the First Package of the Mthatha Thornhill Bulk Water Upgrade. Package 1 will be completed in December 2014. The progress on the corridor infrastructure showing Packages 1-9 is shown on Tables 6.16.9 below. PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE MARCH 2014 Table 6.1: Status on Package 1 Package Package 1 Thornhill Project Name & Masterplan Contract Number Thornhill Raw Water & WTW Sub Project Project Description Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Construction Commission Comment Start Duration Finish Start Finish On progress or Why Behind? R 8 356 765 Sep-12 26 months Sep-14 Sep-14 Oct-14 Linked to Raw water line contracts time frames Reservoirs (Res), Pipelines(PL) & Pumpstation (PS) Raw water pump station upgrade (RJN) Upgrading of raw water pump station R 40 000 000 800mm gravity main (WK Construction) 2.2km 800mm dia gravity main R 48 000 000 Nov-12 27 months Dec-14 Jan-15 Jan-15 Additional scope of work R 45 878 414 1200mm gravity main (Mbokhoto) 2.0km 1200mm dia gravity main R 55 054 096 Oct-12 25 months Nov-14 Dec-14 Dec-14 Contract no 1 terminated, awaiting appointment of new Contractor R 36 137 288 Refurbishing of existing 800mm dia gravity main (Anix Trading) Refurbishment of 2.2km 800mm dia gravity main R 43 364 746 Aug-12 24 months Oct-14 Oct-14 Nov-14 Scope change R 34 643 764 Upgrade 60 to 80 Ml/day Civils (Norland) Upgrade 60 to 80 Ml/day Civils R 41 572 517 Aug-12 25 months May-14 Nov-14 Dec-14 Additional scope of work R 32 340 855 Upgrade 60 to 80 Ml/day M&E (Zanamanzi) Upgrade 60 to 80 Ml/day M&E R 38 809 025 Aug-12 24months Sep-14 Nov-14 Dec-14 Attached to Civil Contract time frame, Additional budget to allow for pumps Lalini gravity main (UMSO) 3.2km 315mm dia gravity main from 3Ml reservoir to Lalini booster pump station R 59 618 951 Jun-12 20 months Dec-13 Jan-14 Feb-14 Construction is complete. Defects liability period Misty Mount gravity main and 2 X 1ML reservoirs (Xesibe) 11.4km 315mm dia rising main from Lalini booster pumpstation to 1ML Misty Mount reservoir R 32 854 230 Aug-12 24 months Sep-14 Oct-14 Oct-14 Granted Extension of time but on penalties now Libode Town gravity main 1 X 250Kl reservoirs (Dokose) 12.2km 250mm dia gravity main from Misty Mount reservoir to 250kl Libode Town reservoir R 22 205 596 Nov-12 13 months Nov-13 TBA TBA Contract no 1 terminated, awaiting appointment of new Contractor Pipeline Replacement Mthatha CBD pipeline replacement R 73 043 478 Mar-14 14 months Apr-15 Apr-15 May-15 Delay on awarding of contracts Raw water steel pipes (Hall Longmore) 4.2km gravity main to WTW R 25 531 145 Jan-13 12 months Dec-13 Delivery of pipes is complete Potable water steel pipes (Hall Longmore) 40km pipeline from Thornill WTW to Mqanduli via Viedgisville R 104 316 553 Jul-13 12 months Jun-14 Delivery of pipes is in progress Potable water GRP (APS) pipeline to airport corridor and surrounding new developments R 57 869 795 Jul-13 12 months Jun-14 Some pipes delivered and some pipes stored at factory Libode & Ngqeleni Bulk Conveyance Pipe Supply Contracts Total package 1 R 610 596 898 24 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 6.2: Status on Package 2 Package Project Name & Masterplan Contract Number Mthatha Central & Airport Corridor Sub Project Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Construction Commission Start Duration Finish Start Finish Comment Res, PL & PS 11 Signal Hill rising main (Cerimele) 3.8km 900mm dia rising main from Thornhill PS to Signal Hill Reservoir R 29 165 968 Sep-14 8 months May-14 May-14 June-14 Construction is underway 13 Zamukulungisa gravity main (Cerimele) 4.1km 600mm dia gravity main from Signal Hill reservoir to Zamukulungisa R 37 013 357 May-14 11 months Mar-15 Mar-15 Mar-15 Construction is underway Fairfield gravity main (Mpumalanga) 10.7km 400mm dia gravity main from Signal Hill reservoir to Fairfield reservoir R 14 730 554 Aug-14 14 months Dec-15 Dec-15 Dec-15 Construction is underway Gravity Main to Link Reservoir (Zanamanzi) 1,9km 250mm dia mPVC gravity main from 400mm Fairfield Gravity Main to existing Link Reservoir R 24 021 232.80 Aug-14 9 months June-15 Jun-15 Jun-15 Construction is underway R 17 008 458.00 July-14 9 months May-15 May-15 May-15 Construction is underway 15 16B Sheshegu village gravity main (Zanamanzi) Kaplan village gravity main (Zanamanzi) Package 2 Project Description Fairfield gravity supply (Zanamanzi) 16A 12 18A Total package 2 2.4km 250mm dia mPVC gravity main offtake to Sheshegu village from 400mm Fairfield pipeline 3.7km 300mm dia gravity main from new 400mm GRP main coming from Fairfield Reservoir 2.6km 400mm GRP gravity main from Fairfield reservoir to start of Kaplan 300mm Gravity main Area 8 gravity main BNG 2a,b,c,e (Lejamo) 0.7km 200mm dia gravity main from Vulindela heights to Area 8 Area 8 gravity main BNG 2a,b,c,e (Lejamo) 0.1km 200mm gravity main to BNG 2A Area 8 gravity main BNG 2a,b,c,e (Lejamo) 0.2km 200mm gravity main to BNG 2C Area 8 gravity main BNG 2a,b,c,e (Lejamo) 1.4km 250mm dia gravity main from Zimbane reservoir to Area 8 Area 7 gravity main BNG 3a,b,c,d,e (Lejamo) 3.3km 300mm dia gravity main in Area 7 Area 7 gravity main BNG 3a,b,c,d,e (Lejamo) 0.4km 150mm gravity main to BNG 3B Area 7 gravity main BNG 3a,b,c,d,e (Lejamo) 0.2km 200mm gravity main to BNG 3D Signal Hill (Mamlambo) 15Ml Signal Hill reservoir R 39 254 969 Mar-14 15 months May-15 May-15 May-15 Construction is underway Fairfield (Norland) 10Ml Fairfield reservoir R 27 142 176 Jul-14 14 months Oct-15 Oct-15 Oct-15 Construction is underway R 188 336 714 25 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 6.3: Status on Package 3 BULK WATER Thornhill Project Name & Masterplan Contract Number Signall Hill Strategic Linkages & Mqanduli Bulk Conveyance Sub Project Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Construction Commission Start Duration Finish Start Finish Comment Res, PL & PS 14B Zamukulungisa (Ruwacon) 13.5Ml Zamukulungisa reservoir R 32 414 111 Sep-14 13 months Sep-15 Sep-15 Sep-15 14A Zimbane (Lijamo) 6 Ml Zimbane reservoir R 24 135 600 Sep-14 7 months May-15 May-15 May-15 19 Area 6 (Anix) 6Ml Area 6 reservoir R 24 145 200 Sep-14 13 months Sep-15 Sep-15 Sep-15 17 Area 1 gravity main Ph2 (Radee) 4.3km 400mm dia GRP gravity main from Signal Hill reservoir to Area 1 R 24 000 000.00 Jul-14 9 months May-15 May-15 May-15 3.9km 300mm dia GRP gravity main from Signal Hill reservoir to Area 6 8.3km 600mm dia rising main from Zamukulungisa booster pumpstation to Viedgesville reservoir 19.9km 500mm dia gravity main from Viedgeville reservoir to Mqanduli CRS R 52 931 119 Aug-14 19 months Dec-15 Dec-15 Dec-15 R 84 661 860 Sep-14 25 months Sep-16 Sep-16 Sep-16 Area 6 gravity main BNG Ph2 (Radee) Package 3 Project Description Waiting for Eskom pole to be relocated thereafter construction will commence Construction is underway Construction is underway Construction is underway Construction is underway 21 Viedgesville rising main (Anix) 22 Mqanduli CRS gravity main (Cerimele) 25 Viedgesville (Ruwacon) 20Ml Viedgesville reservoir R 42 939 461 Sep-14 13 months Oct-15 Oct-15 Oct-15 Waiting for Eskom pole to be relocated thereafter construction will commence 29 Connection to Bedford Hospital (Zamisanani) Connection to Bedford Hospital R 14 640 000 Sep-14 10 months Aug-15 Aug-15 Aug-15 Construction will start mid Sep Waiting for Eskom poles to be relocated thereafter construction will commence Connection to Airport (Zamisanani) Connection to Military Base (Zamisanani) 37 Maydene (Xesibe) 43 BNG 1A gravity main (Penninsula) BNG 1A gravity main (Penninsula) Total package 3 Construction is underway Connection to Airport Connection to Military Base 10Ml Maydene reservoir 2.4km 250mm dia gravity main from Maydene reservoir to BNG 1A 2km 200mm dia gravity main from Maydene reservoir to BNG 1A R 26 376 460 Sep-14 13 months Sep-15 Sep-15 Sep-15 R 9 600 000 Jul-14 6 months Feb-15 Feb-15 Feb-15 Construction is underway R 335 843 810 26 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 6.4: Status on Package 4 . Project Name & Masterplan Contract Number Sub Project Project Description Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Package 4 Thornhill Mthatha to Mqanduli Bulk Conveyance Construction Commission Start Duration Finish Start Finish Comment Res, PL & PS 23 Kwamkhulu gravity main (Bluroca) 11.7km 400mm dia gravity main from Mqanduli CRS to Kwamkhulu booster pumpstation R 20 085 000 Oct-14 14 months Dec-15 Dec-15 Dec-15 Contract awarded. Awaiting environmental Authorisation. 24 KuGxwalibomvu village gravity main (Kwena Mukoni) 7km 250mm dia gravity main KuGxwalibomvu reservoir to KuGxwalibomvu village R 10 944 088 Oct-14 14 months Dec-15 Dec-15 Dec-15 Contract awarded. Awaiting environmental Authorisation. Kwamkhulu rising main (Kwena Mukoni) 2.8km 250mm dia rising main from Kwamkhulu booster pump to Mahlathini reservoir 26 Mqanduli CRS (Icon) 12Ml Mqanduli CRS reservoir R 32 400 000 Oct-14 13 months Nov-15 Nov-15 Nov-15 Contract awarded. Awaiting environmental Authorisation. 27 Kwamkhulu (Lijamo) 50kl Kwamkhulu reservoir & booster pumpstation (civils) R 24 000 000 Oct-11 14 months Oct-15 Oct-15 Oct-15 Contract awarded. Awaiting environmental Authorisation. Zamukulungisa (Lijamo) Zamukulungisa pstn (civils) Mahlathini (Lijamo) 3Ml Mahlathini reservoir KuGxwalibomvu (Lijamo) 2Ml KuGxwalibomvu reservoir Rosedale (WK) 20 Ml Rosedale command reservoir R 43 200 000 Oct-14 17 months May-16 May-16 May-16 Contract awarded. Awaiting environmental Authorisation. 35 Total package 4 R 130 629 088 27 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 6.5: Status on Package 5 BULK WATER Project Name & Masterplan Contract Number Sub Project Project Description Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Package 5 Thornhill Signall Hill Strategic Linkages Construction Commission Start Duration Finish Start Finish Res, PL & PS 10A Thornhill Pumpstation Construction of Thornhill Clear Water Pumpstation: Mechanical & Electrical R 84 000 000 Jan-15 14 months Feb-16 Feb-16 Mar-16 10B Thornhill Buildings & Refurbishment - Civil Refubishment of WTW & construct new genset/MV & MCC switchgear buildings R 20 869 565 Jan-15 8 months Sep-15 Sep-14 Oct-15 20 Zamukulungisa & Kwamkhulu Pstns - M&E Mech & Elec equipment for pstns R 8 347 826 Jan-15 8 months Sep-15 Sep-14 Oct-15 28 Refurbisment at Mqanduli WTW Refurbisment at Mqanduli WTW R 19 870 497 Jan-15 14 months Feb-16 Feb-16 Mar-16 Refurbishment of Mqanduli raw water abstration Refurbishment of Mqanduli raw water abstration R 10 763 186 Jan-15 14 months Feb-16 Feb-16 Mar-16 30 Rosedale raw water rising main (Ph 1) 3.2km 600mm dia rising main from Mthatha Dam to Raw Water reservoir (Ph 1) R 25 964 117 Jan-15 9 months Oct-15 Oct-15 Nov-15 38a 25 Ml/day WTW & clear water pstn - Civils (Ph 1) 25 Ml/day WTW & clear water pstn -Civils (Ph 1) R 104 320 111 Jan-15 17 months May-16 May-16 May-16 38b 25 Ml/day WTW & clear water pstn - M&E (Ph 1) 25 Ml/day WTW & clear water pstn -M&E (Ph 1) R 69 546 741 Jan-15 24 months Jan-17 Jan-17 Feb-17 38c 12ML Rosedale Raw Water Reservoir 12ML Rosedale Raw Water Reservoir R 30 000 000 Jan-15 17 months May-16 May-16 May-16 44 Area 2 gravity main 2.4km 300mm dia gravity main from Ncambedlana HL reservoir to Area 2 R 7 749 494 Jan-15 13 months Feb-16 Feb-16 Feb-16 36 Ncambedlane HL 10 Ml Ncambedlane HL reservoir R 35 121 104 Jan-15 13 months Feb-16 Feb-16 Feb-16 Ncambedlane 8Ml Ncambedlane reservoir R 28 431 370 Jan-15 13 months Feb-16 Feb-16 Feb-16 Total package 5 Comment R 360 984 012 Tender stage Tender stage Tender stage Tender stage Tender stage Tender stage Tender stage Tender stage Tender stage Tender stage Tender stage Tender stage 28 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 6.6: Status on Package 6 BULK WATER Project Name & Masterplan Contract Number Sub Project Project Description Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Libode & Ngqeleni Corridors Bulk Conveyance Commission Start Duration Finish Start Finish Comment Res, PL & PS Design and Tender stage 41 Lalini gravity main 5.2km 450mm dia gravity main connecting from 600mm dia to Lalini booster pumpstation R 26 436 041 Oct-14 10 months Jun-15 Nov-14 Dec-15 40 Misty Mount rising main 11.4km 400mm dia rising main from Lalini booster pump station to a 10Ml Misty Mount reservoir R 51 345 365 Oct-14 12 months Oct-15 Oct-15 Nov-15 45 Megacom gravity main 13.8km 300mm dia gravity main from 10Ml Misty Mount command reservoir to Megacom HL reservoir R 44 559 590 Oct-14 12 months Oct-15 Oct-15 Nov-15 46 Mandovini gravity main 0.5km 300mm dia gravity main from Megacom HL reservoir to Mandovini reservoir R 34 069 624 Oct-14 13 months Nov-15 Nov-15 Dec-15 Mandovini grarvity main 13.5km 200mm gravity main from Megacom reservoir to Mandovini reservoir Enjiveni gravity main 11km 200mm dia gravity main from 300mm dia pipeline connecting from Megacom reservoir to Enjiveni reservoir 47 Lalini 1Ml Lalini reservoir R 5 298 799 Oct-14 9 months May-15 May-15 May-15 49 Misty command 10ML Misty command reservoir R 28 149 871 Oct-14 14 months Dec-15 Dec-15 Dec-15 50 Hegacom HL 10Ml Megacom HL reservoir R 28 149 871 Oct-14 14 months Dec-15 Dec-15 Dec-15 51 Mandovini 1ML Mandovini reservoir R 10 434 783 Oct-14 9 months May-15 May-15 May-15 Enjiveni 1ML Enjivini reservoir Package 6 Rosedale Construction Design and Tender stage Design and Tender stage Design and Tender stage Design and Tender stage Design and Tender stage Design and Tender stage Design and Tender stage Total package 6 R 228 443 945 29 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 6.7: Status on Package 7 BULK WATER Project Name & Masterplan Contract Number Sub Project Project Description Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Package 7 Rosedale Libode & Ngqeleni Corridors Bulk Conveyance Construction Commission Start Duration Finish Start Finish Comment Res, PL & PS Design and Tender stage Lalini Booster pump station at Lalini to Misty Mount R 7 603 543 Nov-14 8 months Jun-15 Jun-15 Jun-15 Mdoni Booster pump station at Mdoni to Polini R 1 443 923 Nov-14 8 months Jun-15 Jun-15 Jun-15 42 Mdoni rising main 13.5km 400mm dia rising main from Lalini booster pump station to Mdoni booster pump station R 83 158 032 Nov-14 8 months Jun-15 Feb-15 Mar-15 43 Palini rising main 2.4km 300mm dia rising main from Mdoni booster pump station to Palini reservoir R 7 749 494 Nov-14 8 months Jun-15 Feb-15 Mar-15 43 Nqgeleni gravity main 6.9km 300mm dia gravity main from Palini reservoir to Nqgeleni reservoir 42 Mdoni 48 48 Design and Tender stage Design and Tender stage Design and Tender stage Design and Tender stage R 19 373 735 Nov-14 8 months Jun-15 Feb-15 Mar-15 500kl Mdoni reservoir R 3 361 426 Nov-14 8 months Jun-15 Feb-15 Mar-15 Polini 10Ml Polini reservoir R 35 121 104 Nov-14 13 months Nov-15 Dec-15 Dec-15 Nqgeleni 1.5 Ml Ngqeleni reservoir R 5 961 149 Nov-14 8 months Jun-15 Feb-15 Mar-15 Design and Tender stage Design and Tender stage Design and Tender stage Total package 7 R 163 772 405 30 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 6.8: Status on Package 8 BULK WATER Project Name & Masterplan Contract Number Sub Project Project Description Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Rosedale Rosedale Ph2 & Nqadu Corridor Package 8 31 33 34 Total package 8 Construction Commission Start Duration Finish Start Finish Comment Res, PL & PS Rosedale WTW 25 to 50 Ml/day Civils (Ph 2) 25 to 50 Ml/day Civils (Ph 2) R 69 546 741 Aug-15 16 months Nov-16 Dec-16 Feb-17 Rosedale WTW 25 to 50 Ml/day M&E (Ph 2) 25 to 50 Ml/day M&E(Ph 2) R 46 364 494 Aug-15 10 months May-16 Dec-16 Feb-17 Soyini 2Ml Soyini reservoir R 7 815 729 Aug-15 13 months Aug-16 May-16 Jun-16 Soyini rising main 5.2km 300mm dia rising main from Rosedale Command Reservoir to 2Ml Soyini Reservoir Ngungululu 1 Ml Ngungululu reservoir R 5 298 799 Aug-15 9 months Apr-16 Apr-16 Apr-16 Soyini Soyini reservoir to Gungulu reservoir R 1 273 368 Ngungulu rising main 6.6km 300mm dia rising main from Soyini resrvoir to Ngungulu 1Ml reservoir R 21 311 108 Nqadu 3.5 Ml Nqadu reservoir R 14 406 111 Aug-15 9 months Apr-16 Apr-16 Apr-16 Nqadu gravity main 9.8km 200mm dia gravity main from Ngungulu reservoir to 3.5Ml Nqadu reservoir R 12 955 564 Design stage Design stage Design stage R 16 790 570 R 195 762 484 Design stage Design stage 31 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Table 6.9: Status on Package 9 BULK WATER Project Name & Masterplan Contract Number Sub Project Project Description Comments Project Cost (15% indirect costs added to construction contract) incl VAT excl supplied pipes incl elsewhere Package 9 Mthatha Dam Mthatha Dam Modifications Mthatha Dam Modifications Mthatha Dam Outlet Upgrade Upgrading of Mthatha Dam outlet to at least 150 Ml/day 32 Rosedale raw water pump station Rosedale raw water pump station R 15 411 227 30b Rosedale raw water rising main (Ph 2) 3.2km 600mm dia rising main from Mthatha Dam to Raw Water reservoir (Ph 2) R 25 964 117 39b 25 Ml/day WTW & clear water pstn - M&E (Ph 2) 25 Ml/day WTW & clear water pstn - M&E (Ph 2) R 71 729 822 38b 25 Ml/day WTW & clear water pstn - Civil (Ph 2) 25 Ml/day WTW & clear water pstn - Civil (Ph 2) R 45 913 043 52 Upgrade 80 to 115 Ml/day (M&E and civils) Thornhill Upgrade 80 to 115 Ml/day Total package 9 R0 R 120 000 000 R 279 018 209 Design Stage Design Stage Design Stage Design Stage Design Stage Design Stage 32 REGIONAL BULK INFRASTRUCTURE GRANT 3. SEPTEMBER 2014 PROGRESS TO DATE The performance evaluation meeting was conducted on 3 September 2014 by a team consisting out of the following people (for the water supply component): 3.1 A. Gidana T. Dlulane T. Maposa M. Vonco A. Dabula T. Gumede H. Lwenje C. Khumbula M. Hlwele DWS Regional Office EC DWS DWS DWS GIBB Engineering & Architecture GIBB Engineering & Architecture GIBB Engineering & Architecture ORTDM MISA Support Amatola Water Implementation of the approved business plan In its capacity as Lead Consultant, GIBB has employed its own staff and is also utilising the SMME Consultants to manage the project and to provide specialized professional services, financial management and administrative support to the project. Amatola in its capacity as the Implementing Agent is providing guidance and also monitoring progress on behalf of OR Tambo DM. OR Tambo DM has also appointed external professional service providers and contractors in terms of its supply chain management policies and procedures. 3.2 Schedules of work and phasing of the activities The Mthatha Regional Bulk Infrastructure Presidential Intervention project comprises a number of components, viz. the raw water refurbishment and upgrade, the upgrade and extension of the Thornhill Water Treatment Plant, and the proposed bulk New Rosedale Water Treatment works and the Secondary bulk water infrastructure upgrade as described in Section 3.1 above. Construction work on the first contracts awarded under Phase 1 commenced in September 2012, and the last contract is expected to be completed in October 2015. 3.3 Contracts rolled out in the financial year 2013/14 and to be rolled out in 2014/15 Below is a list of some of the contracts that have been/will be implemented during the 2013/14 and 2014/15 financial years. Tables 6.1-6.9 show the status on all contracts. 3.4 Financial Management Consulting Engineers report monthly on progress and submit invoices to GIBB, appointed as Lead Consultant then submits an equally valued claim and progress report to the Amatola Water Board who also submit to the Department of Water and Sanitation’s regional office in King William’s Town where the necessary approvals and signatures are obtained for the payment of the invoices and funds into the municipality’s account. 3.5 Co-ordination with other Stakeholders From a programme management perspective, regular liaison meetings are held between OR Tambo DM, Amatola Water and GIBB in Mthatha. All relevant stakeholders are invited to attend, including Councillors. 33 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 In order to co-ordinate all the activities that take place at project level, and to ensure that effective communication takes place amongst project team members (both internal and external to OR Tambo DM) and between DWS (in its role as Implementing Agent) and the officials and councillors of the local and district municipalities, the traditional authority in the project area, and government officials, two committees have been established, viz: (i) (ii) Project Management Committee (PMC) that deals primarily with technical and contractual matters, and Project Steering Committee (PSC) that deals more with institutional and policy issues. Sub-PSCs and contract-specific liaison committees have also been established to provide for good communication and dissemination of project-related information. Three Community Liaison Officers (CLOs) have been appointed by the civil contractors involved with upgrade of Raw Water Bulk mains and Phase 1 of the Thornhill bulk water treatment works. Other technical co-ordination and ad hoc meetings will also take place, either on a needs basis, or in terms of generally accepted contract administration practice. 3.6 Risks taken and Management thereof Due diligence should be practised in ensuring that there is minimum disruption of water during construction. 3.7 Management of the Programme The project is managed by a team formed by OR Tambo DM and its team of Professional Service Providers. The Department of Water and Sanitation (DWS) undertakes the function of the regulator and funder. 3.8 Capacities Dedicated to the Programme The capacities dedicated to the programme are as follows: 3.9 Water Services Authority – OR Tambo District Municipality. Water Services Provider – OR Tambo District Municipality. Funding – DWS – Regional Bulk Infrastructure Grant (RBIG) Implementing Agent – Amatola Water Board Regulator – DWS. Overall Programme and Project Management – GIBB as Lead Consultant for OR Tambo DM. Specialized professional services, financial management and administrative support – DWS. Design, contract administration and construction monitoring – various professional service providers appointed by OR Tambo DM: GIBB (Pty) Ltd, SMME’s Capacity Building for the Staff within the Programme The labourers are receiving “in-service” training by the contractors in terms of Health and Safety, pipe laying, bedding and backfilling. During implementation, people will be identified that show potential for development and these people will be given accredited training in the skills for which they show an aptitude. 3.10 Key Challenges within the Project Key risk areas include the following: 34 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 General: Future – Possible compensation payable to those dispossessed of their land due to the construction of the proposed Rosedale WTW. OR Tambo DM will engage with the relevant affected parties through the Social Facilitator. The details of who will be funding the compensation and the mechanisms of how and to whom payment will be made are still uncertain (compensation amounts will be determined for each corridor first before engagement with funding stakeholders) Current Contracts: Rosedale to Libode Pipeline – Slow progress on last 12 km section of pipeline to Libode under the Dokose Contract. A number of contractual letters in line with GCC 2010 were issued by the engineer to the contractor and the client. Contractual processes were followed and in February 2014 a letter of termination was issued to the contractor. (We are waiting for Amatola Water to advise about the way forward for this project) Libode Bulk Supply Pipeline - Contract No: MIS 200542/2- Eskom connections date remains unresolved. Eskom reportedly stuck on contractor procurement. Raw Water Pipeline – Slow progress on the DN 1200 Contract under Mbokotho Investments. A number of contractual letters in line with GCC 2010 were issued by the engineer to the contractor and the client. Contractual processes were followed and in February 2014 a letter of termination was issued to the contractor. (We are waiting for Amatola Water to advise about the way forward for this project). Raw Water Pipeline – We still await Eskom to move an old power line and pole that is affecting the works at Pipe Bridge 2. Payment for the work was done in August 2013. Raw Water Pump station – Existing pumps cannot be replaced with new pumps until 3 No pipe bridges and 1200mm and 800mm pipelines are complete (fasttracking completion of pipelines) New Contracts: Awaiting ESKOM to relocate their services for construction to proceed for 3 No Package 3 contracts. Awaiting Environmental Authorisations for construction to proceed for 4 corridors. Client involvement at higher level is required to resolve Land issues DWS, AW and GIBB need to resolve the Mthatha Dam Water use Licence misinterpretation. 35 REGIONAL BULK INFRASTRUCTURE GRANT 4 MONITORING 4.1 The Monitoring Approach SEPTEMBER 2014 Primary monitoring and supervision is conducted by the GIBB and other SMME Consulting Engineers appointed by OR Tambo DM. In addition the Implementing Agent Amatola Water also conducts. This is done by conducting regular site visits, compiling monthly progress reports and measurement of quantities of work conducted by the Contractor. Each contract is controlled by having formal site meetings on a monthly basis. In addition, contract progress is monitored against the official construction programme submitted by the Contractor. The data collected from these actions is then formally recorded and discussed with all stakeholders on a regular basis in order to take corrective measure when deviations occur. 4.2 Data Analysis and Reports for Implementation Purposes Reports indicating progress and expenditure are submitted by GIBB to OR Tambo DM and to DWS. 4.3 Data analysis and reports for performance requirements Reports are submitted by GIBB to DWS, Amatola Water and OR Tambo DM as required. 4.4 Responsible Person for Data Analysis and Report Generation (financial and nonfinancial reports) Casper Brink, is the Programme Manager for the Implementing Agent - Amatola Water Board | Head Office Mobile: +27 (83) 232 0011 | Office: +27 (43) 707 3700 | Fax: +27 (43) 707 3701 www.amatolawater.co.za Mr N (Phums) Mkhwanazi, is the Programme Manager for Lead Consultant GIBB Ltd (Pty) for the KSD PI projects being implemented on behalf of OR Tambo DM (Tel: (031) 267-8570; Cell: 072-442-6541; E-mail: nmkhwanazi@gibb.co.za ). Reports and other information are submitted to Mrs N Msebi for OR Tambo DM, Mthatha, and/or Mrs A. Gidana of DWS, King William’s Town, Email: gidanaa@DWS.gov.za as required. 4.5 Challenges with the Monitoring and Reporting Tasks No real challenges are experienced regarding the monitoring and reporting tasks for this project. Once the project has been completed, Record Drawings and all related documentation will be forwarded to DWS for record-keeping. 5 PROJECT RESULTS AND BENEFICIARIES 5.1 Outcomes and Outputs Currently the expected outcomes and outputs are on track for the phase under construction. Planning for further phases has also commenced through the Mthatha Bulk Master plan. 5.2 Beneficiaries and Project Results As stated in Section 2.3 above, the purpose of the project is to ultimately supply 150 Mℓ/day of potable water to a population of 1,000,000 people (approximately 200,000 households), allowing for an increase in the average consumption per capita from 90 ℓ/c/d to 150 ℓ/c/d over a 20-year time horizon. The Medium Term targets are a supply of 115 36 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 Mℓ/day of potable water to a population of 750,000 people (approximately 150,000 households) and the Short Term target is to supply 95 Mℓ/day to a population of 650,000 people (approximately 130,000 households. The targeted categories of consumers to be supplied with potable water are domestic water users throughout the KSD Local Municipality and Nyandeni Municipality, and commercial and light industrial users and institutional users mainly within the towns of Mthatha, Mqanduli, Ngqeleni and Libode. It should be noted that GIBB’s Water’s current appointment excludes the connections between the bulk water supply scheme and the village reticulation systems and any aspect of the village reticulation systems themselves. Jobs Created More than 440 jobs were created to date since construction commenced. 6 CONCLUSION 6.1 Main Successes and Failures of the Project to Date 6.2 The main challenge has been the delay in the award of contracts that has significantly affected the targeted delivery of the implementation of the bulk water provision. However there has been a great participative engagement by stakeholders and the Lead Consultant to drive the implementation of Phase 1 of the Scheme. The role-players maintain regular contact with each other, and the project team, under the direction of DWS, and Amatola Water provides the necessary professional input. The extensions of time due to technical difficulties and labour strike have also added to the delays, but construction work is under way, and Phase 1 of the project is due for completion by the third quarter of 2014. The success or failure of the project is likely to depend more on social and political factors than on technical ones. It is strongly recommended that OR Tambo DM and KSD LM become more actively involved in resolving ISD issues that have escalated in frequency and magnitude since March 2012. The proactive and energetic involvement of both senior officials and politicians is required as a matter of urgency. Master planning for the five main corridors for the KSD PI for the next 5 years has been completed. To date, a total of 22 contracts falling under Packages 2, 3& 4 have been awarded. Draft Tender documents for Package 6&7 have been submitted to Amatola Water for approval. Outcomes, Outputs, Successes and Failures versus the Costs There has been evidence of competitive tendering on all components of Phase 1 of the Scheme, as indicated by the interest shown by tenderers and generally keen pricing. The lowest bidder for the construction of the bulk water mains were approximately 30% less than the Engineer’s estimate. Most awards were based on contractors that had prices close to the Engineer’s Estimate so as to discourage large discount that are counter-productive to service delivery as contractors end up failing to deliver within their tender price. Local contractors, suppliers and general labour have benefited from this project. In the Bulk Treated Water Supply System (Phase 1) tender, the target for local joint venture 37 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 participation is 15%, and a minimum contract participation goal of 5% for local labour, 5% for local enterprises, and 5% for local plant hire. 6.3 Ownership and Sustainability of Infrastructure Works Ownership of all the assets included in the bulk water supply system is to vest in OR Tambo DM, in its capacity as the Water Services Authority. Operation and maintenance arrangements for the bulk water supply system are still required to be finalized by OR Tambo DM especially for the proposed Rosedale WTW and for the de-sludge process. Currently Amatola Water Board is also offering its support to the Operation and maintenance of water and sanitation infrastructure for OR Tambo DM as means of ensuring capacity build up and mentorship development for the operators. 7 LESSONS LEARNED Stakeholder engagement at conceptual level where all parties including DWS, OR Tambo DM, KSD LD and the Professional Team share their views in shaping the project goals and objects should be encouraged. It is essential that a fully-functioning Project Steering Committee be in place at the earliest possible opportunity during the planning stage of the project, and continues throughout the design and construction stages, with all relevant stakeholders taking an active part in discussions and conveying project-related decisions to the community at large. A greater amount of involvement by officials and politicians in local government is especially required to avoid unnecessary delays due to social resistance to such developments. The active participation of the Department of Rural Development and Land Reform is essential in all land-related issues. 8 RECOMMENDATIONS It is recommended that urgent attention be paid to the key challenges listed under Section 3.10 above GIBB & SMME’s consultants, after approval has been obtained from DWS and its Implementing Agent, need their fee budgets in the appointment letters to be adjusted to the scope of work that includes future Phases of the bulk distribution system, together with the necessary financial allocations. OR Tambo District Municipality has to ensure sufficient RBIG and MIG funding is available in order to ensure the bulk water infrastructure is upgraded within the planned time of implementation. DWS to support and expedite the water licence approvals Funding for the full KSD PI (for five corridors within 30km radius of Mthatha) be made available (approximately R2.5 Billion) through DWS RBIG and MIG. It is recommended that, after the two DN800 Steel pipes (WK and Anix) have been commissioned, the existing DN800 Steel pipe be shut down for analysis of the internal pipe condition. 38 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 ANNEXURE A: PROJECT IMPLEMENTATION PHOTOS ANIX TRADING: DN 800 – PIPE LAYING WK CONSTRUCTION SA: - SCOUR VALVE CHAMBER WITH EROSION PROTECTION 39 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 NORLAND CONSTRUCTION: - CRARIFIER 8 CONCRETE WORK COMPLETE WITH M&E EQUIPMENT RJN PROJECTS: - PUMP AND FITTINGS INSTALLATION 40 REGIONAL BULK INFRASTRUCTURE GRANT ZANAMANZI SERVICES: - MATERIALS STORAGE MAMLAMBO: CONSTRUCTION OF 15ML RESERVOIR SEPTEMBER 2014 41 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 ANNEXURE B: LIST OF AREAS EXPECTED TO BENEFIT FROM PACKAGE 1 (Extract from Technical Report dated January 2011) No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Township Name Zone Sidwadwa Signal Hill South Ridge Signal Hill Zimbane Valley Signal Hill Kuyasa Signal Hill Southernwood Signal Hill Southernwood (LL) Signal Hill Vulindlela Heights Signal Hill/Fort Gale Ministrial Complex Signal Hill Nkululekweni Signal Hill Myezo Signal Hill Fort Gale Fort Gale Norwood ncambedlana North Crest & North Crest Northncambedlana Ncanbedlana (HL) ncambedlana (HL) Ncambedlana (Agriculture) ncambedlana Police Band Fort Gale Hill Crest ncambedlana Maydene Farm Maydene Kilowatt Garden Signal Hill Ilitha Zimbane Zimbane Zimbane Mbuqe Zimbane Kwezi and Kwezi ext Kwezi Ngangelizwe Ngangalizwe Waterfall Farm Ngangalizwe CBD Fort Gale Owen Dam Nduli Cresent (Fort Gale Flats) Fort Gale The Hill New Briton Zamukulungisa Informal Zamukulungisa Zamukulungisa Industrial Zamukulungisa Prison Zamukulungisa Parameters No. Units erven size m2 Demand (Mℓ/D) Demand (ℓ/s) PEAK FACTOR SPDD (ℓ/S) SPDD (Mℓ/D) 6 5,000 800 4.50 52.08 1.5 78.13 6.75 1 2,000 550 1.40 16.20 1.5 24.31 2.10 3 1,500 300 0.90 10.42 1.5 15.63 1.35 Income Type Middle Income High Income Low Income Middle Income High Income Middle Income Industrial High Income High Income High Income High Income Middle Income Low Income Middle Income Middle Income Middle Income Middle Income Middle Income Middle Income Low Income Low Income Low Income Middle Income Middle Income Low Income High Income Middle Income Low Income Middle Income Low Income Middle Income Middle Income TOTAL 7 4,500 300 2.70 31.25 1.5 46.88 4.05 Population 2007 1084 1534 804 3509 2896 609 228 61 183 610 4130 6995 7485 4271 0 560 1708 6382 201 0 804 2983 20880 6960 134 1462 229 1584 138 2680 853 560 82519 8 2,500 200 1.50 17.36 1.5 26.04 2.25 Average Size 2 (m ) 900 1000 300 320 1100 800 1500 10000 10000 1600 1000 1030 700 500 40000 700 450 350 1500 300 350 375 450 600 325 900 900 300 300 300 900 500 2 2,500 700 2.00 23.15 1.5 34.72 3.00 4 2,800 500 1.96 22.69 1.5 34.03 2.94 No. of Households 217 307 161 702 579 122 46 12 37 122 826 1399 1497 854 0 112 342 1276 40 0 161 597 4176 1392 27 292 46 317 28 536 171 112 16504 5 2,000 900 2.40 27.78 1.5 41.67 3.60 TOTAL 22,800.00 11.00 127.31 190.97 16.50 PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 ANNEXURE C: DETAILS OF CONTRACTS AWARDED UNDER PACKAGE 1 DELIVERABLES PROGRAMME TARGETS CONTRACT 1: Mbokotho TOTAL PROJECT Thornhill Raw Water Main Rehabilitation Phase 1 Thornhill Raw Water Main Refurbishment of Raw Rehabilitation Phase 1 and Water Pipeline from Mthatha Thornhill Water Treatment Dam to Thornhill Water Works Upgrade Treatment Works Construction of new DN 1200 Steel Pipe a) Physical Progress on Project 75% CONTRACT 2: Anix CONTRACT 3: RJN CONTRACT 4: WK CONTRACT 5: Norland CONTRACT 6: Zanamanzi Thornhill Raw Water Main Rehabilitation Phase 1 Refurbishment of Existing DN 800 Steel Pipe Thornhill Raw Water Main Rehabilitation Phase 1 : Design, Supply and Installation of Mechanical and Electrical Equipment Thornhill Raw Water Main Rehabilitation Phase 1 : New DN 800 Raw Water Main Steel Pipe Thornhill Bulk Water Supply: Thornhill Water Treatment Works - Civil Works: MIS204248/1 Thornhill Bulk Water Supply: Thornhill Water Treatment Works Electrical and Mechanical Works: MIS204248/2 90% 90% 65% 92% 70% 40% 2. Overall Project Progress (vis-a-vis Programme Deliverables) ITEM STATUS a) Contract amount R 175 998 497 R 39 878 413.62 R 30 137 287.95 R 6 963 971.20 R 38 201 292.84 R 34 176 676.70 R 26 640 854.50 DWA funding: R 90 717 420 R 21 933 127.49 R 16 575 508.37 R 3 830 184.16 R 21 010 711.06 R 15 379 504.52 R 11 988 384.53 OTHER funding: R 85 281 077 R 17 945 286.13 R 13 561 779.58 R 3 133 787.04 R 17 190 581.78 R 18 797 172.19 R b) Contract Start date c) Contract Duration 1 September 2012 18 Months d) Percentage time elapsed to date e) Cumulative spending to date Percentage spent of contract amount j) Contract status 94% R 105 532 102.09 14 652 469.98 8 October 2012 17 October 2012 12 September 2012 1st November 2012 18 September 2012 1 September 2012 18 months 22 months (Revised) 23 months 22 months (Revised) 24 Months (Revised) 16 months 111.1% 95.5% 82.6% 86.4% 87.5% 100.0% R 21 528 614.91 60% 54% All civil contractors are working on-site and the M&E contractors are fabricang equiqment off-site. Only 805m of pipe has been laid to date. Contract has been terminated, Amatola Water has issued a termination letter, dated 03 March 2014. Contract has been terminated by the Client R 16 680 873.09 55% R 4 550 587.62 65% R 21 259 406.38 56% The Contractor has finished laying all Contractor has finished laying and the pipes except on the bridges. The welding 1600m of pipes. The contractor pilling works are now complete except has also completed the concrete piers Contractor is busy fabricating for Bridge 3 South Abutment and the on the crossing and is now laying the mechanical and Electrical Equipment Contractor has startted working on the pipes over this area and also working pile caps, abutments and piers. Bridge on the valve chambers 3 South abutment piling is delayed due to unforeseen geological conditions R 29 585 236.21 87% R 11 927 383.88 45% Contractor has completed all concrete works for the two clarifiers and installation of M&E equipement is also complete. Contractor is now working Contractor is busy fabricating on the Concrete pouring for filter mechanical and Electrical Equipment building roof slab is on-going. The M&E installation on the fillter building is also expected to start soon. PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 DELIVERABLES PROGRAMME TARGETS TOTAL PROJECT Libode Bulk Supply Pipeline a) Physical Progress on Project CONTRACT 1: UMSO CONTRACT 2: XESIBE CONTRACT 3: DOKOSE Libode Bulk Supply Pipeline (Gravity Gravity Main from 1st Command Reservoir Main from Existing 3ML Reservoir to Libode Bulk Supply Pipeline - Contract to Libode Town - Contract No: MIS Booster Pump) - Contract No: MIS No: MIS 200542/2 200542/3 200542/1 86% 100% 99.6% 59% 2. Overall Project Progress (vis-a-vis Programme Deliverables) ITEM a) Contract amount DWA funding: OTHER funding: b) Contract Start date c) Contract Duration d) Percentage time elapsed to date e) Cumulative spending to date Percentage spent of contract amount j) Contract status STATUS R 95 565 648 R 49 682 459.58 R R - 27 378 524.94 R R - R R - R 18 504 663.48 - 29 June 2012 31 August 2012 11 November 2012 12 Months 12 Months 12 months 12 months 149% 100.0% 166.7% R 79 275 809.17 78% R 43 795 192.51 88% R 180.0% 25 872 908.75 95% The contract is complete. Umso was instructed by Pipe excavation, bedding, backfill done except 55m the Engineer to do emergency health and safety from pump station delevery side. Command and Contract 1 is complete, Contract 2 is at water backfill for terminated contract MIS200542/3. Work Pump sump resevoirs are 100% complete with only leak testing stage and Contract 3 has been done in August and Septemebr 2014 was pipe testings outstanding. Pump station done but not yet abandoned by the contractor. laying of ductile iron up to the R61 bridge tested, also outstanding is power supply pipe underside. connection to delivery pipeline. R 9 607 707.91 52% Outstanding work is about 6.2km still needs to be done. Umso is construction of 250kl reservoir at snails pace emanating to failure to construct RDP standard house hearby the resevoir which is a pre-requisite for continuing with resevoir. For the rest of the project, there is no new Contractor appointment issued yet. PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE SEPTEMBER 2014 ANNEXURE D: DETAILS OF CONTRACTS AWARDED UNDER KSD PI MTHATHA SOUTH DELIVERABLES PROGRAMME TARGETS TOTAL PROJECT CONTRACT 1: Cerimele CONTRACT 2: Mamlambo CONTRACT 3: Cerimele CONTRACT 4: Ruwacon CONTRACT 5: Anix CONTRACT 6: Ruwacon CONTRACT 7: WK AW 2013/14/14 : AW 2013/14/15 : AW 2013/14/16 : AW 2013/14/32 : AW 2013/14/28 : AW 2013/14/27 : AW 2013/14/39 : KSD PI Bulk Water Phase 2 - KSD PI Bulk Water Phase 2 - KSD PI Bulk Water Phase 2 - KSD PI Bulk Water Phase 2 - KSD PI Bulk Water Phase 2 - KSD PI Bulk Water Phase 2 - KSD PI Bulk Water Phase 4 Construction of 3.7km Construction of 15ML Construction of DN600 steel Construction of Construction o8.3km 600 dia Construction of 13.5 ML Construction of 20Ml KSD PI - BULK WATER Viedgesville Reservoir Steel rising main from Zamukulungisa Resevoir Rosedale reservoir Main PHASE 2 : Central & Airport DN900 plus 2No 1km long Signall Hill Reservoir - C12A Zamukulungisa Gravity Main DN600 continuously welded - C13 Zamukulungisa booster Main Corridor steel pipelines from pumpstation to Viedgesville Thornhill Water treatment resevoir Works to Signall Hill Reservoir - C11 a) Physical Progress on Project 15% 5% 20% 20% 3% 0% 0% 0% 2. Overall Project Progress (vis-a-vis Programme Deliverables) ITEM STATUS a) Contract amount R 303 339 471 R 61 824 857.27 R 32 712 473.55 R 39 978 713.97 R 35 782 884.13 R 66 365 567.40 R 30 074 975.03 R 36 600 000.00 DWA funding: R 303 339 471 R 61 824 857.27 R 32 712 473.55 R 39 978 713.97 R 35 782 884.13 R 66 365 567.40 R 30 074 975.03 R 36 600 000.00 OTHER funding: R b) Contract Start date c) Contract Duration d) Percentage time elapsed to date 4 March 2014 5 March 2014 2 July 2014 5 May 2014 1 October 2014 1 September 2014 1 October 2014 1 October 2014 15 Months 7.8 months (34 weeks) 13 months (52 weeks) 6.5 months (26 weeks) 13 months (52 weeks) 13 months (52 weeks) 13 months (52 weeks) 15 months (60 weeks) 40% 44.1% 19.2% 57.7% 0.0% 0.0% 0.0% 0.0% e) Cumulative spending to R date Percentage spent of contract amount j) Contract status 14 988 134.70 5% The awarded Contractors are mobilising to start with the site establishment R 549 816.30 1% R 7 101 270.18 22% The Contractor has completed site The Contractor has started with the establishment, bulk earthworks, site establishment. Sections of the subsoil drainage and no fines under the pipeline still await RoD and may be reservoir. The Contractor has also cast delayed. The contractor has submitted three quarters of the wall footing. They a programme reflecting a slow start. are working on the wall panel first lift R 7 082 641.55 18% R - 0% The Contractor has started with the The Contractor has completed with the RDP house (90% complete). Thereafter site establishment. The Contractor is the land owner will be relocated to the working on the deep drainage pipes new house and construction will from the Zamukulungisa reservoir and commence. Reservoir construction the progress is slow due to hard rock cannot start until Eskom poles are that lead to blasting. moved. R - 0% The Contractor is mobilizing to start. R 254 406.67 1% R - 0% Construction can not start as there are Site camp establishment and setting is ESKOM poles which need to be re now complete. Contractor is relacating routed existng services affecting the works. PROGRAMME MANAGEMENT: REGIONAL BULK INFRASTRUCTURE ANNEXURE E: DETAILS OF JOB OPPORTUNITIES To be updated towards the end of September 2014. SEPTEMBER 2014