Integrated Financial Management System (FMS) Rollout to Subs (Publishing) Project Steercom Meeting November 14, 2007 Presentation Outline Project Scope & Approach Project Methodology Project Implementation Timeline Project Status Issues and Concerns Conversion Assumptions Project Team’s Pending Decision Points Next Steps Project Scope – Modules Subsidiary ABS-CBN Publishing SAP Modules to be Implemented Order Mgmt To Collection (Circulation, Subscription, Ads Booking, Prepress Job Order, Billing & Collection), Journal Entry & Reporting (GL), Margin Analysis (Mgmt Reporting), Requisition-to-Payment (Purchasing & AP), Fixed Asset Mgmt, Treasury Mgmt Legend: Pure SAP Project Scope – Modules Publishing / Films Allocation System CPI ABS-CBN Japan Logistics (OTC/RTP) SD/MM Financials (BMA/JER/AMT) FI/CO/AM LN Forms LN Databases Planning & Consolidation Payroll ABS-CBN Australia Pty. Ltd. ABS-CBN Europe - Milan ABS-CBN Europe - London ABS-CBN Middle East SDD ABS-CBN Middle East LLC ABS-CBN Middle East FZ LLC ABS-CBN Telecoms ABS-CBN North America TV Food Chefs, Inc ABS-CBN News Channel Studio 23 AMCARA Broadcasting Network ABS-CBN Broadcasting Corp. Project Approach Use parent company’s template for common processes Requisition to Payment Journal Entry and Reporting Budgeting Asset Management Treasury/ Bank SAP Workflow Capture unique processes and determine integration and implementation requirements with SAP Order to Cash (allocation process.) Inventory Management (inclusion of distribution requirements e.g. zoning, etc.) Margin Analysis (per issue reporting) Project Methodology Project Preparation Blueprinting Realization Final Preparation Go Live Project Implem Timeline Mar Apr May Jun Jul Aug Sep Oct Go-live Nov Dec Jan Feb ABS-CBN Publishing Project Preparation Blueprinting Realization Project Preparation Final Preparation Go-live Support Blueprinting Realization - Planned - Actual Project Status Tasks Period Remarks Blueprinting Process System Formal Sign-off Completed (except 7 forms) Completed Completed (except portion on organization) Realization (QAS) Design, Construct, Unit Test 8/2 – 11/20 On-going: 90% External System Interface 8/6 – 11/20 On-going: 70% Authorization and Security 9/10 – 11/23 QA config completed on 11/6; Ongoing volume assessment & org design Workflow Configuration and Testing 9/10 – 12/03 CA & MR Completed; Ongoing PR/PO Project Status Tasks Period Remarks 10/3 – 11/20 Ongoing but delayed Realization (QAS) System Testing (Prototyping) Integration Testing (Prototyping) Systems Overview Training for Process Owners Mock Data Conversion 11/20 – 11/26 11/15 12/03 – 12/07 Delayed; due to delay in design & rework during testing Project Status Tasks Period Remarks Final Preparation UAT / Process and Systems Training for EndUsers 11/27 – 12/14 Data Conversion (Cut Over and Go Live) to Prod Master Data – 12/17 – 12/21, 2007 Balances (Jan - Nov 07) – 12/17 – 12/21 AR/AP SL (as of 11/30) – 12/17 – 12/21 Trans-List (Dec 2007) – Jan Wk 2 Migration to Prod 12/17 – 31 Stress Test 12/17 – 31 Go Live Support 01/03 – 31 / 08 For confirmation based on volume assessment Issues and Concerns Delay in Systems / Integration Testing Certain scenarios were revisited and changed as a result of the blueprint review More detailed scenario documentation Interface requirements were also affected OTC forms design not yet finalized Delay in the submission of Master Data (process owners requested for an extension in the deadline for 90% data: end of Oct. instead of Oct. 15, 2007) Data for Conversion Make sure that all master data are 100% complete and cleansed by Nov. 30, 2007 (moved from Nov. 12, 2007 as a result of the request from users) Conversion Assumptions Profit and Loss Accounts Balance Sheet Accounts Receipts and payments will be completed in the legacy system (encoding to SAP) Open Sales Orders Use of Translist conversion template to facilitate loading in SAP Open PO conversion Conversion of Subsidiary Ledgers with open balances only Current Transactions on Soft Live Conversion of prior year for historical data will be at Cost object level (PC/CC/IO) Re-create all in SAP Subsidiary Process Owners shall be responsible for the accuracy of their conversion balances Project Team’s Pending Decision Points Shared service for operating supplies procurement and warehouse/asset management Common stocks for sign-off by parent’s process owners ITS – ongoing BPR to determine fit CM concerns related to Shared Services Next Steps TASKS RESPONSIBLE Competency Tests for Process Team Finance/Acctg personnel Volume Assessment and Process Team Organization Design Complete realization phase Construction & Process Team Final Preparation phase Project Team TARGET DATE 11/19/07 11/23/07 12/07/07 12/31/07 End of Presentation