Pre-Commencement Checklist

advertisement
Domestic Construction – Pre-Commencement
Checklist
Owner:
Builder :
Project :
Site Address:
Supervisor:
Date:
Component
QBCC Licence:
Phone:
Job No:
/
Action/Comment
Plastering commencement date
Sub-contract agreement in place
Construction Safety Plan received from
builder
Approved plans on site
Electricity available
Water available
Toilet on site and stocked
Site sign clear and visible
Car parking arrangements
Car parking and materials storage
Requirements for rubbish removal
Work Method Statements for hazards
Check plans and contract documents
for extent of work, any special
requirements and any variations
Check for any special design loads and
thermal and acoustic performance
requirements
Check level of finish required
Determine extent of water resistant
plasterboard
Check if there are any fire separating
walls
Building sufficiently water resistant to
permit installation of plasterboard
Timber frame plumb and correctly
aligned
Internal walls sufficiently set down at
This example is a guide
only and not a QBCC
recommendation
Current as at: 21 Feb 2012
Domestic Construction – Pre-Commencement
Checklist
Owner:
Builder :
Project :
Site Address:
Supervisor:
Date:
Component
QBCC Licence:
Phone:
Job No:
/
Action/Comment
least the thickness of the ceiling batten
+ 10mm below the underside of the
bottom chord of the truss.
Check ceiling battens installed level
and at the correct height.
Trimmer battens provided to ceiling at
change of direction of roof frame
Plumbing, gas, electrical, air
conditioning and telecommunication
rough in complete
Plasterboard supply
Plan for reduced manual handling of
plasterboard
Cornice supply
Supply of adhesive and accessories
Wall insulation installed
Check any requirements for movement
joints in walls and ceilings in contract
documents and with supervisor.
Sub-Contractor :
QBCC Licence:
This example is a guide
only and not a QBCC
recommendation
Current as at: 21 Feb 2012