The principal objective in the design of a roof support system is to help the rock mass create a selfsupporting structure.
The usage of rock bolts can be combined with wire mesh, shotcrete and concrete lining to cope with different situations encountered during mining or tunneling.
Sandvik Mining and Construction
?
Hilti
Sandvik Mining and Construction
Sandvik others
Need to drill hole and then retract, hoping the hole does not collapse, install bolt and actuate to tension.
Possible need to auger hole.
Ability to reach rib with head plate.
Safety ( Time spent on operation ).
Potential for rib collapse.
Manual handling.
Mesh alignment.
Number of consumables.
Sandvik Mining and Construction
Sandvik Self Drilling Bolt (SDB)
The objective – To develop a Self Drilling
Bolt for UG Soft Rock applications.
The project started in Q4/2004 in MGT
Newcastle.
Use hollow bar to allow flushing during drilling.
Mechanical anchoring and post grouting (if needed).
Drill, Tension and Grout .
Sandvik Mining and Construction
MINING SYSTEM PERFORMANCE
TYPICAL COLLIERY
12
10
8
6
TWO HEADING
PANEL LAYOUT
4
2
Ove rdrive
Sh unt (S 1)
Sh uttle Car
Sh unt (S 1)
Dista nce S hunt to Boot
Sh uttle Car
Width of Pi ller
0
10 30
ABM without SDB
Sandvik Mining and Construction
50 70
DISTANCE FROM SHUNT S1 (m)
4 roof bolt, 2 rib bolt, mesh, 2 S/C only, 14t cars
90 110
ABM with SDB CM withot SDB CM with SDB
130
Self DrillingInstallation of the bolt is quicker and simpler when it drills it’s own hole.
Strengthaxial load capability (stiffness) is increased through the combined use of a mechanical anchor plus full encapsulation with either thixotropic or cementatious grout.
Pretensionas the bolt is pre-tensioned by use of the mechanical anchor, the rib layers are forced together before the injection of the grout. Standard chemical capsules can be forced into cracks and fissures under the hydraulic pressure created when the bolt is inserted which results in separations being held open and a loss in encapsulation.
Sandvik Mining and Construction
Bolt Description
Hollow bar OD = 19mm, ID = 9.5mm
Frazer & Jones D10L Expansion Shell
Nut (M20 LH) with shear pin, 36AF (optional non-shear pin for no tail bolt)
Bolt length: typically 1.2m (any length can be supplied)
Plate: Special SDB Butterfly Assembly
Plain Hollow Bar
Typical
Tensile Strength (kN) 140
Yield Strength (kN) 110
Standard Elongation (50mm) (%) 23-38
Bar Shear Strength (kN) 90
Sandvik Mining and Construction
Insert self drilling rib bolt in drill chuck.
Drill 36mm diameter hole in rib using SD Bolt & RH rotation on rig.
On completion of drilling, anchor bolt by using reverse rotation on drill motor to set expansion shell and tension bolt.
Sandvik Mining and Construction
Sandvik Mining and Construction
Drill trials at Mandalong, West Wallsend and
Beltana
trialling steel drill bit design
Bolt trials at West Wallsend and Mannering
trialling old style self drilling bolt
SD Bolt trials at Mandalong
current design and trials
Sandvik Mining and Construction
West Wallsend - 10, 10, 12, 8, 13, 13, 12.5, 9.5,
9.5, 16 tonne
Mannering - 16 tonne click on photo to play pull test video
Sandvik Mining and Construction
Rib bolt has threaded hollow centre bar allowing easy coupling of grout pump and straight clear grouting passage through centre of tube.
Initial contacts with Specialist Site Services, with regards to post grouting the SD Bolt, have indicated no foreseeable problems.
Currently organising trials with BASF, developing grout and resin compositions.
Grout trial with solid bolt design proved feasibility of grouting, and new hollow bolt design should better suit grouting.
Sandvik Mining and Construction
DRILL RIG:
Triple stage bolting rig.
SDB chuck, extension dolly.
Reverse rotation controls.
Pressure control on reverse rotation (95 bar = 200Nm on
ME10).
Sandvik Mining and Construction
A Hazard Study and Risk Assessment for the Installation
Procedure of the Sandvik Self Drilling Rib Bolt, has been developed in conjunction with Mandalong Colliery.
Also a pull test SOP has been done. ( West Wallsend,
Mandalong Colliery ).
Could use these documents as templates for your colliery.
Will conduct a separate study to your requirements if needed.
Sandvik Mining and Construction
Step 1 – Customer request, initial presentation and meeting
Record feedback and interest
Step 2 – UG survey of equipment and current practise
View and measure continuous miner, drill rigs and clearances, understand the engineering issues of what will impact on the installation procedure
Step 3 – Final proposal presentation to mine
Fully engineered and costed proposal back to mine
Sandvik Mining and Construction
Customer:
Improved safety – operator is exposed 50% less time, reducing risk.
Improved productivity
– drivage rates will improve due to time savings.
Reduced bolting costs – bolting cycle time is reduced lower total costs.
Ability to automate – use of only one consumable, eases automation task compared with current three consumable practise (rod, sausage and bolt).
More choices and competition.
Improved maintenance outcomes
– halves movements on drill rig.
Sandvik:
New opportunity in more stable consumable business.
Sandvik seen as a solution provider for rapid roadway and mine development.
Increased customer process focus.