Introduction to Bolting

 The principal objective in the design of a roof support system is to help the rock mass create a selfsupporting structure.

The usage of rock bolts can be combined with wire mesh, shotcrete and concrete lining to cope with different situations encountered during mining or tunneling.

Sandvik Mining and Construction

Examples of Self Drilling Bolts

?

Hilti

Sandvik Mining and Construction

Sandvik others

Problems with Current Rib Bolting Practise

 Need to drill hole and then retract, hoping the hole does not collapse, install bolt and actuate to tension.

 Possible need to auger hole.

 Ability to reach rib with head plate.

 Safety ( Time spent on operation ).

 Potential for rib collapse.

 Manual handling.

 Mesh alignment.

 Number of consumables.

Sandvik Mining and Construction

Introduction to the SDB Bolting Concept

Sandvik Self Drilling Bolt (SDB)

 The objective – To develop a Self Drilling

Bolt for UG Soft Rock applications.

 The project started in Q4/2004 in MGT

Newcastle.

 Use hollow bar to allow flushing during drilling.

 Mechanical anchoring and post grouting (if needed).

 Drill, Tension and Grout .

Sandvik Mining and Construction

Development Cycle Simulation

MINING SYSTEM PERFORMANCE

TYPICAL COLLIERY

12

10

8

6

TWO HEADING

PANEL LAYOUT

4

2

Ove rdrive

Sh unt (S 1)

Sh uttle Car

Sh unt (S 1)

Dista nce S hunt to Boot

Sh uttle Car

Width of Pi ller

0

10 30

ABM without SDB

Sandvik Mining and Construction

50 70

DISTANCE FROM SHUNT S1 (m)

4 roof bolt, 2 rib bolt, mesh, 2 S/C only, 14t cars

90 110

ABM with SDB CM withot SDB CM with SDB

130

Technical Advantages

 Self DrillingInstallation of the bolt is quicker and simpler when it drills it’s own hole.

 Strengthaxial load capability (stiffness) is increased through the combined use of a mechanical anchor plus full encapsulation with either thixotropic or cementatious grout.

 Pretensionas the bolt is pre-tensioned by use of the mechanical anchor, the rib layers are forced together before the injection of the grout. Standard chemical capsules can be forced into cracks and fissures under the hydraulic pressure created when the bolt is inserted which results in separations being held open and a loss in encapsulation.

Sandvik Mining and Construction

Rib Bolt Data Sheet

Bolt Description

 Hollow bar OD = 19mm, ID = 9.5mm

 Frazer & Jones D10L Expansion Shell

 Nut (M20 LH) with shear pin, 36AF (optional non-shear pin for no tail bolt)

 Bolt length: typically 1.2m (any length can be supplied)

 Plate: Special SDB Butterfly Assembly

Plain Hollow Bar

Typical

 Tensile Strength (kN) 140

 Yield Strength (kN) 110

 Standard Elongation (50mm) (%) 23-38

 Bar Shear Strength (kN) 90

Sandvik Mining and Construction

Installation Procedure

 Insert self drilling rib bolt in drill chuck.

 Drill 36mm diameter hole in rib using SD Bolt & RH rotation on rig.

 On completion of drilling, anchor bolt by using reverse rotation on drill motor to set expansion shell and tension bolt.

Sandvik Mining and Construction

Sandvik Mining and Construction

Animation

Trials to Date

 Drill trials at Mandalong, West Wallsend and

Beltana

 trialling steel drill bit design

 Bolt trials at West Wallsend and Mannering

 trialling old style self drilling bolt

 SD Bolt trials at Mandalong

 current design and trials

Sandvik Mining and Construction

Pull Test – D10L Anchor in Coal

 West Wallsend - 10, 10, 12, 8, 13, 13, 12.5, 9.5,

9.5, 16 tonne

 Mannering - 16 tonne click on photo to play pull test video

Sandvik Mining and Construction

Grouting Recommendations/Options

 Rib bolt has threaded hollow centre bar allowing easy coupling of grout pump and straight clear grouting passage through centre of tube.

 Initial contacts with Specialist Site Services, with regards to post grouting the SD Bolt, have indicated no foreseeable problems.

 Currently organising trials with BASF, developing grout and resin compositions.

 Grout trial with solid bolt design proved feasibility of grouting, and new hollow bolt design should better suit grouting.

Sandvik Mining and Construction

Engineering Changes to Miner/Drill Rig

DRILL RIG:

 Triple stage bolting rig.

 SDB chuck, extension dolly.

 Reverse rotation controls.

 Pressure control on reverse rotation (95 bar = 200Nm on

ME10).

Sandvik Mining and Construction

Hazard Study & Risk Assessment

 A Hazard Study and Risk Assessment for the Installation

Procedure of the Sandvik Self Drilling Rib Bolt, has been developed in conjunction with Mandalong Colliery.

 Also a pull test SOP has been done. ( West Wallsend,

Mandalong Colliery ).

 Could use these documents as templates for your colliery.

 Will conduct a separate study to your requirements if needed.

Sandvik Mining and Construction

Customer Implementation Process

 Step 1 – Customer request, initial presentation and meeting

 Record feedback and interest

 Step 2 – UG survey of equipment and current practise

 View and measure continuous miner, drill rigs and clearances, understand the engineering issues of what will impact on the installation procedure

 Step 3 – Final proposal presentation to mine

 Fully engineered and costed proposal back to mine

Sandvik Mining and Construction

Value Proposition for Customers and Sandvik

Customer:

 Improved safety – operator is exposed 50% less time, reducing risk.

Improved productivity

– drivage rates will improve due to time savings.

 Reduced bolting costs – bolting cycle time is reduced lower total costs.

 Ability to automate – use of only one consumable, eases automation task compared with current three consumable practise (rod, sausage and bolt).

 More choices and competition.

Improved maintenance outcomes

– halves movements on drill rig.

Sandvik:

 New opportunity in more stable consumable business.

 Sandvik seen as a solution provider for rapid roadway and mine development.

 Increased customer process focus.

Sandvik Mining and Construction

Future Developments

 Roof SD Bolt.

 Cuttable Rib SD Bolt.

 Continue to develop bolt.

 Future automation.

 Total system solution.