Next steps

5/12/2012

Next

• Do we agree on the layout?

 Far detector position : ~1600m or more?

ICARUS assembly done elsewhere (i.e. b185?)

NESSIE components preassembly done elsewhere (EHN1?)

Keep the possibility to do major manipulations with a mobile crane

 Near detector position : ~460m

Order in z: ICARUS-150, NESSIE,LAGUNA

One big trench hosting everybody?

 Target layout (functionality as presented today)

 Target, decay tube, dump position (vertical and z position)

 Primary beam line (solution 1,2,3 or 4 or a different one)?

Next

• Do we agree on the presented overall schedule?

Overall Planning Proposal (nord area) activity/year

Far Detector

Near Detector

Primary beam line

Target/Dump facility

2013 2014 civil engineering

+ Infrastructure

2015

Detectors installa on + calibra on

2016 civil eng. +

Infrastruct.

Detectors installa on

+ calibra on civil engineering + components prepara on INFRA civil engineering + components prepara on

INFRA

Apr

Apr

Oct

Sep Jun

2017

Ph ys s ic

:d at a ta kin g

2018

Urgent release of resources

• To Civil engineering : GS, L.Scibile

– ~ 200K for detailed studies for the far and near facility

– ~50K for “carotage” in the target area ?

• To TE-ABT-BTP: B.Goddard

– 1 technical fellow for 2 years for all calculations and final beam layout definition ?

• Do we need a Designer now for all components integration on

CAD (primary and secondary beam lines, detectors and related infrastructure)?

• EDMS project structure

Next 40 days:

• Establish working meetings with detectors and CERN services to arrive to a final definition of the near and far facilities

– Tuesday’s afternoons at 16:00?

• Establish working meetings with everybody involved in the secondary beam facility, to converge to a reasonable CE layout

– Tuesday’s afternoons at 14:00?

• Prepare a feasibility document to be presented to the CERN directorate (15 January?)

Feasibility document for 15

th

January

• Executive summary (1p)  M.Nessi, R.Steerenberg

• Project introduction (2p)  M.Nessi, R.Steerenberg

• Project overall schedule (2p)  M.Nessi, R.Steerenberg

• Project main parameters (yellow book!) (4p)  R.Steerenberg

• Summary note on CE activities (factorized in 4 projects + cost estimation)  L.Scibile et al.

• Summary note on primary beam line and fast extraction  B.Goddard

et al.

• Summary note on target, horn, decay line, dump and muon monitors

 M.Calviani et al.

• Summary note on Fluka calculations  A.Ferrari and Fluka group

• Summary note on ICARUS detectors installation plans

• Summary note on NESSIE detectors installation plans

• Summary note on proto-laguna detector installation plans

• Facility cost estimation summary (2p) -> M.Nessi

, R.Steerenberg

Next general meeting

• Friday 11

th

January?

– Review feasibility document

– Propose a name for the new facility