Calculate Spending and Efficiency Variances

advertisement
Calculate Spending And
Efficiency Variances
Principles of Cost Analysis and
Management
© Dale R. Geiger 2011
1
Why So Much?
© Dale R. Geiger 2011
2
Terminal Learning Objective
• Task: Calculate Spending And Efficiency Variances
• Condition: You are a cost advisor technician with
access to all regulations/course handouts, and
awareness of Operational Environment
(OE)/Contemporary Operational Environment (COE)
variables and actors.
• Standard: with at least 80% accuracy
• Identify and enter relevant scenario data into macro
enabled templates to calculate Spending and Efficiency
Variances
• Identify root causes of Spending and Efficiency Variances
© Dale R. Geiger 2011
3
Why So Much?
• The gas pump is a calculator that charges based on
number of gallons * price per gallon
• Higher gas bills are caused by an increase in one or
both of these variables
• If you are using more gallons than you should be you
have an unfavorable efficiency variance
• If you are paying more per gallon then you have an
unfavorable spending variance
• These are common situations where we dig deeper
into the root cause of variable cost changes
© Dale R. Geiger 2011
4
Getting to the Root Cause
• Imagine that in a
normal week of driving
you expect to use 20
gallons and you planned
on spending $4 per
gallon
Projected
Cost
Planned
Resource
Usage
20 gallons
*
Planned Price
$4/gallon
$80
© Dale R. Geiger 2011
5
You Actually Spent
• You cut down on driving
last week and the pump
registered only 18
gallons, but the cost per
gallon went up to $5
• Note that your total
variance is $10
unfavorable
© Dale R. Geiger 2011
Actual
Cost
Actual
Resource
Usage
18 gallons
*
Actual Price
$5/gallon
$90
6
What if No Price Change?
• If the price were still
$4 per gallon your
more efficient driving
would have spent $72.
• This is an Efficiency
Variance of $8
favorable
Projected Cost
Efficiency Intermediate
Variance
Product
Planned
Resource
Usage
Actual
Resource
Usage
20 gallons
18 gallons
*
Planned Price
*
Planned
Price
$4/gallon
$4/gallon
$80
© Dale R. Geiger 2011
$8
$72
7
How Did Price Impact?
Intermediate
Product
Spending
Variance
Actual
Cost
Actual
Resource
Usage
Actual
Resource
Usage
18 gallons
18 gallons
Planned Price
Actual Price
$4/gallon
$5/gallon
$72
($18)
$90
• However, instead you
paid $5 per gallon for
the 18 gallons: a total
of $18 more
• This is a Spending
Variance of $18
Unfavorable
© Dale R. Geiger 2011
8
Putting it All Together
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
20 gallons
18 gallons
18 gallons
*
Planned Price
*
Planned Price
*
Actual Price
$4/gallon
$4/gallon
$5/gallon
$80
$8
$72
($18)
$90
note that the net of efficiency and spending variance equals the total variance
9
© Dale R. Geiger 2011
Relating to Volume Variance
plan
sales volume
variance
=
=
=
flexible
plan
actual
fcst
=
performance
variance
=
=
=
actual
results
actual
actual
actual
=
=
=
actual
actual
actual
units
price/unit
sales
fcst
fcst
fcst
variable/unit
variable cost
fixed cost
fcst
fcst
fcst
=
=
=
fcst
=
fcst
profit
fcst
=
=
=
actual
flex budget
variable cost
efficiency
variance
intermediate
product
spending
variance
actual results
variable cost
=
∆
=
∆
=
Efficiency and
Spending Variances
are going one level
deeper in trying to
understand the root
cause of the variable
cost change
resource quantity
should have used
X
price per
resource
should have paid
resource quantity
actually used
X
resource quantity
actually used
X
price per resource
should have paid
price per resource
actually paid
10
© Dale R. Geiger 2011
Other Applications
• There are many, many application of spending
and efficiency variances
• People cost is hours*rate/hour
• Material cost is parts*cost/part
• Tank Maintenance is miles*cost/mile
• There are many other types of variance
• Some of which are useful in certain circumstances
• All of which follow the same logic you have
learned here
© Dale R. Geiger 2011
11
Check on Learning
• What does the efficiency variance reveal?
• The spending variance is favorable but the
efficiency variance is unfavorable. How would
you describe the situation?
© Dale R. Geiger 2011
12
Exercises
• Evaluate Efficiency and Spending Variances for
each of the scenarios below:
Gas
Staff
Maint
Edits
Elect
Tele
Food
Planned
Resource
Usage
1000
gal
500
hrs
600
miles
200
pages
150
kw
400
min
2000
cal
Planned
price
$4 /
gal
$50 /
hr
$20 /
mile
$5 /
page
$.3 /
kw
$.2 /
min
$.05 /
cal
Actual
resource
usage
1200
gal
400
hrs
600
miles
350
pages
120
kw
550
min
2500
cal
$3.9 /
gal
$50 /
hr
$25 /
mile
$6 /
page
$.5 /
kw
Actual price
© Dale R. Geiger 2011
$.15 / $.04 /
min
cal
13
Gasoline Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
*
Planned Price
*
Planned Price
*
Actual Price
© Dale R. Geiger 2011
14
Gasoline Example
Projected Cost
Planned
Resource Usage
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Actual
Resource
Usage
Actual
Resource
Usage
*
Planned Price
*
Actual Price
1000 gallons
*
Planned Price
$4/gallon
$4000
© Dale R. Geiger 2011
15
Gasoline Example
Projected Cost
Planned
Resource Usage
Efficiency
Variance
Intermediate
Product
Actual
Resource
Usage
1000 gallons
*
Planned Price
Spending
Variance
Actual
Cost
Actual
Resource
Usage
1200 gallons
*
Planned Price
*
Actual Price
$4/gallon
$3.9/gallon
$4000
$4680
© Dale R. Geiger 2011
16
Gasoline Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
1000 gallons
1200 gallons
1200 gallons
*
Planned Price
*
Planned Price
*
Actual Price
$4/gallon
$4/gallon
$3.9/gallon
$4000
($800)
$4800
© Dale R. Geiger 2011
$120
$4680
17
Staff Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
*
Planned Price
*
Planned Price
*
Actual Price
© Dale R. Geiger 2011
18
Staff Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
500
400
400
*
Planned Price
*
Planned Price
*
Actual Price
$50
$50
$50
$25,000
$5,000
$20,000
© Dale R. Geiger 2011
0
$20,000
19
Maintenance Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
*
Planned Price
*
Planned Price
*
Actual Price
© Dale R. Geiger 2011
20
Maintenance Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
600 miles
600 miles
600 miles
*
Planned Price
*
Planned Price
*
Actual Price
$20/mile
$20/mile
$25/mile
$12,000
0
$12,000
© Dale R. Geiger 2011
($3000)
$15,000
21
Editing Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
*
Planned Price
*
Planned Price
*
Actual Price
© Dale R. Geiger 2011
22
Editing Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
200 pages
350 pages
350 pages
*
Planned Price
*
Planned Price
*
Actual Price
$5/page
$5/page
$6/page
$1000
($750)
$1,750
© Dale R. Geiger 2011
($350)
$2100
23
Electricity Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
*
Planned Price
*
Planned Price
*
Actual Price
© Dale R. Geiger 2011
24
Electricity Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
150 kw
120 kw
120 kw
*
Planned Price
*
Planned Price
*
Actual Price
$.3/kw
$.3/kw
$.5/kw
$45
$9
$36
© Dale R. Geiger 2011
($24)
$60
25
Telephone Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
*
Planned Price
*
Planned Price
*
Actual Price
© Dale R. Geiger 2011
26
Telephone Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
400 min
550 min
550 min
*
Planned Price
*
Planned Price
*
Actual Price
$.2/min
$.2/min
$.15/min
$80
($30)
$110
© Dale R. Geiger 2011
$27.50
$82.50
27
Food Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
*
Planned Price
*
Planned Price
*
Actual Price
© Dale R. Geiger 2011
28
Food Example
Projected Cost
Efficiency
Variance
Intermediate
Product
Spending
Variance
Actual
Cost
Planned
Resource Usage
Actual
Resource
Usage
Actual
Resource
Usage
2000 cal
2500 cal
2500 cal
*
Planned Price
*
Planned Price
*
Actual Price
$.05/cal
$.05/cal
$.04/cal
$100
($25)
$125
© Dale R. Geiger 2011
$25
$100
29
Spreadsheet Exercises
© Dale R. Geiger 2011
30
Download