REGULAR MEETING - City of Youngsville

advertisement
MINUTES OF THE REGULAR MEETING OF THE MAYOR AND CITY COUNCIL OF THE
CITY OF YOUNGSVILLE, LOUISIANA HELD ON THURSDAY, APRIL 10, 2014 AT 6:00
PM AT YOUNGSVILLE CITY HALL
PRESENT: Mayor Wilson B. Viator, Jr., Mayor Pro Tempore Brenda Burley (Div. B),
Councilman Ken Ritter (Div. A), Councilman A.J. Bernard (Div. C), Councilwoman Dianne
McClelland (Div. E)
ABSENT: Councilman Tim Barbier (Div. D)
STAFF: Rick Garner (CEO), Becky Gondron (City Clerk), Charles Langlinais (City Manager),
George Knox (City Attorney), Tim Robichaux (Director of Parks & Recreation)
GUESTS: Dax Douet, Susan Richard, Mark Lalande, Dana Martin, Gary P. Williams, Steven
O’Bryan, Paul Mier, Fire Chief Blair Rivette (YFD), Captain Ted Clark (YFD), Donald Simon,
Joyce & Gene Hamilton, Rickey Boudreaux, Larry Graffeo, Lynn Bourque, Megan Segura, Jamey
Abshire, Teresa Green, Brian West, Linda Meaux, Cyndi Smith, Dale Langlinais, Brenda
Langlinais
Mayor Viator called the meeting of April 10, 2014 to order and called on Councilwoman Dianne
McClelland to lead the prayer and pledge.
AGENDA ITEM 1. Ricky Boudreaux – Announce Candidacy for Youngsville Chief of Police.
Mr. Boudreaux said that he is officially announcing his candidacy for the Police Chief of
Youngsville. He said that he is a resident of Youngsville with 21 years of law enforcement
experience having recently served as Patrol Commander of the Iberia Parish Sheriff’s Department
as well as Commander of their Swat Team and management of a multi-million dollar budget.
AGENDA ITEM 2. 232-HELP Program Presentation. Chris Roy, thanked Mayor Pro Tem Burley
for inviting him to make this presentation. He stated that 232-HELP is a free information referral
agency founded in 1965 which connects people to resources in Acadiana. He said they serve a 10
parish area and help people meet there basic needs when they can’t get help from other resources.
Mr. Roy stated that they also have adopted the 211 service which helps out with natural disasters
and emergency situations providing information such as where to get sand bags or emergency
funding. He said that they will be having a clay shoot fund raiser on June 28th and asked for the
support of all.
AGENDA ITEM 3. Lynn Bourque – Request 10’ setback variance at 206 Oak Hill Lane. A motion
was offered by Mr. Ritter, seconded by Ms. McClelland, to approve a 5’rear setback for property
located at 206 Oak Hill Lane for the location of a 12 X 16 shed on piers provided that 8” gutters
are installed on the rear of the structure, and the vote was as follows:
YEAS: Ritter, Burley, Bernard, McClelland
NAYS: None
ABSENT: Barbier
Motion was approved.
04-10-2014 Regular Council Meeting
Page 1
Mr. Bourque stated that he is requesting a 5’ setback for a storage shed in his back yard. He said
that the shed will be on piers and not on a slab so it can be easily moved if needed.
AGENDA ITEM 4. Anthony Rogers – Address the Council pertaining to the sewer line along his
property located at 114 Smithville in Wells Landing. Mr. Rogers stated that he has a 20’ foot long
hole in his yard due to settlement along the sewer line. He said that he is afraid that the erosion
will eventually effect his home. Mr. Rogers asked for any help from the City to remove the fence
in the areas where the ground has settled and properly fill in and pack the area so no further erosion
will take place.
Upon questioning by Mr. Ritter, Mr. Garner stated that the trench that Mr. Rogers is referring to
is just inside the fence line. He said that the sewer line was put in by the developer and there is a
five (5) year warranty. He said that Shivers Construction is the developer and builder of the
subdivision and Elliot Construction was the primary contractor for the sewer line installation with
Guidry Construction as the secondary. Mr. Garner said that Elliot Construction is prepared to dig
the ditch out and repack it over the sewer line if the owner will remove the fence.
Mr. Rogers stated that he should not be responsible for the removal of the fence since it is not in
the easement.
Dax Douet stated that the sewer line is in the proper place, beyond the right of way and the property
owner had every right to have the fence on the right of way line.
Mr. Ritter stated that this development has been in existence for a short amount of time and the
City needs to be more aggressive with developers when it comes to compacting lines. He said the
developer installed the fencing not the property owner and feels that the City should fix this.
Mayor Viator explained that if a utility fails, the City is responsible to repair it but not to remove
any structures if they are in the easement. He said that Shivers Construction should bear the full
cost of packing the soil, raising it to the proper level and removing and replacing the fence since
there is a five (5) year warranty and the City should mandate that this be done. The property owner
should not be responsible for any of the cost.
A motion was offered by Mr. Ritter, seconded by Ms. Burley, to send a certified letter to Shivers
Construction Company demanding that they fix the problem on the property located at 114
Smithfield and the adjacent lot, including the fencing and any landscaping, and the Council will
take no legal action if fixed within 30 days, and the vote was as follows:
YEAS: Ritter, Burley, Bernard, McClelland
NAYS: None
ABSENT: Barbier
Motion was approved.
AGENDA ITEM 5. Chemin Metairie Phase I – Roundabout & Road Emergency Repairs. This
item was deleted from the agenda. A motion was offered by Mr. Ritter, seconded by Ms.
McClelland to go into executive session due to potential litigation pertaining to the Chemin
04-10-2014 Regular Council Meeting
Page 2
Metairie Phase I Roundabout and Road Repairs; session to include the Mayor, Council, City CEO,
City Clerk, City Attorney and Pam Granger, and the vote was as follows:
YEAS: Ritter, Burley, Bernard, McClelland
NAYS: None
ABSENT: Barbier
Motion was approved.
Ms. Burley left the meeting after the executive session.
A motion was offered by Ms. McClelland, seconded by Mr. Ritter, to resume regular session, and
the vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
ABSENT: Burley, Barbier
Motion was approved.
Mayor Viator announced that the Council had declared the road repairs an emergency at a prior
meeting and he and the Council feel that additional borings are needed to make sure the roadway
is fixed correctly.
PLATS/SUBDIVISIONS
AGENDA ITEM 6. Preliminary Plat approval of Chemet Park Residential Development, 18.1
Acres – 36 Lots; Developer Guidry Land Development, Owner – Britt Paul Melancon (Dax
Douet). A motion was offered by Mr. Ritter, seconded by Ms. McClelland, to give preliminary
plat approval of Chemet Park Residential Development subject to the following: a) acceptance of
City Engineer Dax Douet's recommendations in a letter dated April 3, 2014 with the following
changes: 1) add item S - providing for an expiration of preliminary plat approval 2 years from
April 10, 2014; 2) add item T – requiring Home Owners Association to be in place with documents
filed at the Court House prior to the sale of the first lot; 3) Lafayette Areawide Development
Review Committee Comprehensive Report dated March 19, 2014 in No. 8 – change 25 year design
storm event to 10 year design storm event, and the vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
ABSENT: Burley, Barbier
Motion was approved.
ORDINANCES FOR INTRODUCTION
AGENDA ITEM 7. Ordinance No. 368-2014 – An ordinance to ban the use of all tobacco products
within the Youngsville Sports Complex and Parking Areas. A motion was offered by Ms.
McClelland, seconded by Mr. Ritter, to introduce Ordinance No. 368-2014, an ordinance to ban
the use of all tobacco products within the Youngsville Sports Complex and Parking Areas, and the
vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
04-10-2014 Regular Council Meeting
Page 3
ABSENT: Burley, Barbier
Motion was approved.
ORDINANCES FOR FINAL ADOPTION
AGENDA ITEM 8. Ordinance No. 358.1-2014 – An ordinance amending and re-enacting
Ordinance No. 358-2013 establishing quality standards for the design, construction, and warranty
of public streets within privately developed subdivisions within the incorporated limits of the City
of Youngsville. (Amendment to Section 7). A motion was offered by Mr. Ritter, seconded by Ms.
McClelland, to adopt Ordinance No. 358.1-2014, an ordinance amending and re-enacting
Ordinance No. 358-2013 establishing quality standards for the design, construction, and warranty
of public streets within privately developed subdivisions within the incorporated limits of the City
of Youngsville, and the vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
ABSENT: Burley, Barbier
Motion was approved.
UPDATES
AGENDA ITEM 9. Sewer Project Updates. Susan Richard, Engineer with Domingue, Szabo
and Associates reported the following:

Détente Road Sewer System Project – Contractor: C-D Utilities: The pump station start up
and testing were successful. The contractor is installing walks and handrails and dress
work. Once complete, a final inspection will be held.

La Hwy 89/Fortune Road Pump Station and Force Main Project – Contractor: MP
Dumesnil Construction Co.: The 45-day lien period expired and a clear lien certificate has
been submitted and retainage requested.

La Hwy 89 South Pump Station and Force Main Project – MP Dumesnil Construction Co.:
The pump station and force main are complete with a few remaining items. A problem
with the delivery of the control panel occurred but the Contractor is hoping to be able to
finish the work and perform start up in mid-May.

Sewer System Improvements Project – LCDBG FY 2013 (Church Street Pump Station
Upgrade and Crepe Myrtle Trailer Park Pump Station) – Contractor: E.B. Feucht & Sons,
Inc.: The Notice to Proceed was issued effective February 10, 2014. With 180 calendar
days in the contract, the expected completion date is August 9, 2014. Submittals for
materials and equipment are being reviewed. The contractor expects to begin installing the
force main in the next two weeks.

Griffin Road Sewer Extension: M.P. Dumesnil Construction Company has begun this work
and the project should be completed in approximately three weeks. Mayor Viator approved
a change order to add another sewer connect to accommodate another machine shop.
04-10-2014 Regular Council Meeting
Page 4
AGENDA ITEM 10. Sports Complex Activities. Tim Robichaux, Director, thanked the Council
for introducing the Tobacco ban ordinance and thanked Rick Garner for drafting it. He reported
the following:
 Equipment for the complex is being ordered.
 Working on signage for complex and sponsors.
 Website will be live by the end of the month.
 Contracts are being finalized with BYYA and LYSA and SSYS.
 Negotiations are going on with Steve and Pat O’Brien of Bon Temps Grill for the
concessions.
AGENDA ITEM 11. Savoy Road Improvements Project. Mayor Viator read an update prepared
by Andre Montagnet, Engineer for the Project which stated: Trahan Construction, has completed
the curbing and storm drainage work and the soil cement base will be installed over the next 3
weeks. The following item will be the asphalt roadway placement, and this will take approximately
2 weeks. Based on this schedule, the roadway surface should be in place by May 15, 2014 and
then the striping, seeding and final dressing will need to be completed after that time.
Mayor Viator stated that Trahan Construction, the contractor, has exceeded the time limits on the
contract. He said that he met with the Contractor and they said they were delayed by SLEMCO,
the Charter School, Al Lanie harvesting cane and change orders but guaranteed that the road would
be complete by April 24, 2014. Mayor Viator recommended that liquidated damages not be
charged until April 25, 2014 for Savoy Road and the Sports Complex.
A motion was offered by Mr. Bernard, seconded by Ms. McClelland, to extend the time for
substantial completion for the Savoy Road Improvements Project and the Sports Complex to April
24, 2014, and the vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
ABSENT: Burley, Barbier
Motion was approved
AGENDA ITEM 12. Youngsville Recreation Center – Bid Award. A motion was offered by Ms.
McClelland, seconded by Mr. Bernard, to award the bid for the Youngsville Recreation Center to
the apparent low bidder, Ratcliff Construction Company in the amount of $3,449,000.00 which
includes the Base Bid and Alternates No. 1 & 2, all to be funded with $3,165,000 from Louisiana
State Facility Planning and bond funds, and the vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
ABSENT: Burley, Barbier
Motion was approved.
Prior to the motion, Mark Lalande reported that five (5) bids were received and Ratcliff
Construction Company out of Alexandria, LA was the apparent low bidder with a bid price of
$3,449,000.00 which includes the Base Bid, Alternate No. 1 and Alternate No. 2. He said that the
Opinion of Probable Cost for construction was $4,167,000.00 so the bids came in under budget.
04-10-2014 Regular Council Meeting
Page 5
He said that the Architectural Fees through construction, which are not included in that cost, are
$356,629.00 and $172,400.00 for testing, inspection and construction contingencies. He said that
if additional funding becomes available to do the parking lot or other upgrades this can be done
with a changeorder. Mr. Lalande also stated that he would like to upgrade the ceiling but any extras
would have to be approved by Facility Planning.
Upon questioning by Mr. Bernard, Mayor Viator stated that the City is required to budget a 25%
match to the funding coming from the State. He said that the engineering fees are not being
reimbursed by Facility Planning so that will be part of the 25% and this will come out of the current
bond funds. Mayor Viator stated that everything has to be approved by Mr. Bill Eskew with the
Office of Facility Planning before anything can be started.
Before the motion was made, Mayor Viator said that he wanted to make the Council aware that
there was one sub-contractor that is threatening to file legal action if the bid is awarded because
he was upset when his flooring did not meet the bid specs and he requested an addendum to delay
the bids.
Mayor Viator concluded by stating that an application was made for an additional $1,525,000 from
the State for the project and we should know by June, 2014 after the legislative session.
ENGINEERING UPDATES – C. H. FENSTERMAKER – DAX DOUET
AGENDA ITEM 13. Chemin Metairie Parkway Phase II. 100% complete. Contractor has now
fixed all concrete panels at US 90 that needed repair.
AGENDA ITEM 14. Chemin Metairie Parkway, Phase II Waterline. Bihm Construction is the
contractor. All borings are complete on project.
AGENDA ITEM 15. Reconstruction of Bonin Road and Chemin Metairie – 2011 Road
Improvements (Project No. 2043981.4CC). The project is complete and Mr. Douet requested that
the Council approve the Act of Acceptance for recordation to begin the 45 day lien period.
A motion was offered by Ms. McClelland, seconded by Mr. Ritter, to adopt Resolution No. 201407 authorizing and directing the Mayor to execute for and on behalf of the City of Youngsville of
the Parish of Lafayette, Louisiana, an act of acceptance from Cecil Perry Construction, LLC
Contractor, pertaining to the completion of a contract for 2011 Road and Intersection Improvement
Program, Phase II, Chemin Metairie Road and Bonin Road, and the vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
ABSENT: Barbier, Burley
Motion was approved
AGENDA ITEM 16. Sports Complex Construction Project (Project No. 2043981.3YC)
(estimated 85% complete) – Contractor has completed laying asphalt on all parking lots and is
working on finishing the asphalt jogging trail. All project trees have been planted with final dirt
work grading being performed to spray grass hydro-seeding throughout the entire site. Contractor
04-10-2014 Regular Council Meeting
Page 6
has completed construction of the fishing pier with all bridge wood work. All plumbing work in
both soccer and tennis buildings are complete and flooring is being installed. All structural steel
finishing is complete and the perimeter fencing around the project is being installed.
a) Sports Complex Changeorder No. 7. Mr. Douet presented Change Order No. 7 in the amount
of $52,110.00 which includes the installation of the structural supports to mount scoreboards on
all playing fields and to add field shade structures over the softball bleachers. A motion was
offered by Mr. Ritter, seconded by Mr. Bernard, to approve changeorder No. 7 in the amount of
$52,110.00 for the Youngsville Sports Complex Project, and the vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
ABSENT: Burley, Barbier
Motion was approved.
Mr. Douet concluded by stating that he feels that the entire project will come in very close to the
actual budget.
AGENDA ITEM 17. Water Storage Tank (Project No. 2043891.4WC) (CHF). The design is
finished for the 300,000 gallon base bid and the 500,000 gallon alternate bid and ready to proceed
with advertising for bids.
AGENDA ITEM 18. Roundabout at LA 89 and Fortune Road (Project No. 2043981.4IC) (CHF).
Mr. Douet stated that he spoke with DOTD and they indicated that the project will not be let out
until sometime in the fall.
FINANCIAL REPORTS
AGENDA ITEM 20. March, 2014 Finance Report Approval. A motion was offered by Mr.
Bernard, seconded by Mr. Ritter, to approve the March, 2014 Finance Report, and the vote was as
follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
ABSENT: Burley, Barbier
Motion was approved.
Ms. McClelland questioned the high cost of the electricity bill at the sewer plant. Mayor Viator
said that he would get Charles Langlinais to check in to this.
APPROVAL OF MINUTES
AGENDA ITEM 21. Minutes of Regular Meeting of March 13, 2014 and Special Meeting of
March 25, 2014. A motion was offered by Ms. McClelland, seconded by Mr. Ritter, to approve
the minutes of the regular meeting of March 13, 2014 and special meeting of March 25, 2014 and
the vote was as follows:
YEAS: Ritter, Bernard, McClelland
NAYS: None
04-10-2014 Regular Council Meeting
Page 7
ABSENT: Burley, Barbier
Motion was approved.
AGENDA COMMENTS, ANNOUNCEMENTS
A motion to adjourn was offered by Ms. McClelland, seconded by Mr. Bernard, and unanimously
carried.
There being no further business to come before the Council, Mayor Viator adjourned the meeting.
/s/ Wilson B. Viator, Jr.
Wilson B. Viator, Jr., Mayor
/s/ Rebecca L. Gondron
Rebecca L. Gondron, City Clerk