Installation Issues

advertisement
Installation Issues
MICE CM23 at ICST, Harbin
January 13, 2009
Steve Virostek
Lawrence Berkeley National Lab
Topic Summary
•Packaging and delivery to RAL
•Moving of modules into MICE hall
•Assembly work in MICE hall
•Installation interfaces
•End flanges and seals
•Base mounting
•Other connections
•Utility requirements
•Instrumentation
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 2
Progress Update
•Shipping skid for RFCC module developed
– Module axis is vertical during shipping
– Skid provides for rotation to horizontal in MICE hall
•RAL developing spectrometer solenoid lift beam
– Four lifting points are included on the magnets
– Load testing and certification is required
•Two module bellows spools received at RAL
– Bellows assemblies purchased from Hyspan
– Spools connect spectrometer solenoid to AFC module
– Apparent tolerance error being discussed w/vendor
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 3
Progress Update (cont’d)
•Still need a helium-to-vacuum window design
– Window separates vacuum space from tracker
volume in spectrometer solenoid bore
– Preliminary plan is to use AFC style window
– Good opportunity to add mounting holes now
•Several instrumentation readouts purchased
– Thermocouple and helium level readouts for the
spectrometer solenoid have been received by LBNL
– Similar readouts will be needed for RFCC module
– Most instrumentation only needed during initial tests
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 4
Shipping Logistics
•All modules to be forklifted on/off truck
•All magnet coils are shipped warm
•RFCC cavities, couplers, coolers & pumps removed
•Coupling coil integral with vacuum vessel
•RFCC axis vertical during shipping
•Concerns about shipping loads on coupling coil
•Special shipping skid has been developed
•Cavities, couplers packaged to prevent damage
•RF, Be windows left in place w/appropriate protection
•Vac vessel, cavities and couplers backfilled with N2
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 5
RFCC Shipping Configuration
Cavities removed
Vacuum pumps
removed
Skid holds
module in
vertical
orientation
Cryocoolers removed
Couplers removed
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 6
MICE Hall Access
•Forklift to be used for
unloading and moving
through hall door
•Door is tall and wide enough
for spectrometer solenoids
and RFCC modules
•No special equipment or
hardware is required
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 7
RFCC Rotation and Support Install
Tilting runners installed
on shipping skid
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 8
RFCC Rotation and Support Install
Permanent support stand
structure installed on
RFCC vacuum vessel
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 9
RFCC Rotation and Support Install
Module is tilted into
horizontal orientation
using crane
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 10
RFCC Rotation and Support Install
Module is tilted into
horizontal orientation
using crane
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 11
RFCC Rotation and Support Install
Finished tilting onto
permanent support stand
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 12
RFCC Rotation and Support Install
Finished tilting onto
permanent support stand
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 13
Re-assembly of RFCC Module at RAL
•Locate vacuum vessel/coupling coil on lateral tracks
•Erect portable clean room around module
•Unpack cavities, couplers, coolers, pumps
•Install six tuner assemblies on each cavity
•Insert cavities in vacuum vessel using special fixture
•Install couplers and tuner actuators after cavity is
aligned and supported by struts
•Install vacuum pumps to complete module
•Perform final alignment before translation
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 14
Re-assembly of Module at RAL
Module ready
for assembly
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 15
Re-assembly of Module at RAL
Cryocooler(s)
installed
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 16
Re-assembly of Module at RAL
RF cavities
installed from
either end
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 17
Re-assembly of Module at RAL
Cavity tuner
actuators added
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 18
Re-assembly of Module at RAL
Module vacuum
pumps installed
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 19
Re-assembly of Module at RAL
RF couplers
installed
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 20
Module Base Mounting
•RFCC module and Spectrometer Solenoid base
connections to rails are similar
•Six mounting plates are welded to the base of
the module support stands
•Location of the mounting plates will be included
in an interface document (and later measured)
•Magnetic loads are carried to the floor through
the vacuum vessel/support stand/base mounts
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 21
Translating Platform
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 22
Spectrometer Solenoid Mounting
Six mounting plates on
the support stand base
for installation on rails
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 23
RFCC Module Mounting
•Six mounting plates to be
welded to the support stand
base for installation on rails
•Similar to spectrometer
solenoid mounting scheme
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 24
Insertion into MICE Beamline
•Locate module on lateral tracks
•Align and shim module to correct height
•Pull back bellows on both module ends with
O-rings in place
•Translate module into position using rails
•Release bellows and connect flanges
•Lock out bellows using bridging bolts
•Connect utilities and instrumentation
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 25
MICE Bellows Joints
Bellows Joint
Bellows Joint
Bellows Joint
Bellows Joint
B
Bellows Joint
Bellows Joint
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 26
End Flanges and Seals
•RFCC flanges mate with AFC module flanges
•AFC flanges have no O-ring grooves or bellows
•RFCC module flanges have bellows and O-ring
grooves at both ends
•Bellows are spec’d for >1 cm of total travel
•Module relative alignment is driven by
clearance in flange holes
•Bellows are locked out after installation to
allow transmission of forces between modules
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 27
Bellows Joint Detail
Elastomer or
Helicoflex allmetal O-ring
Clamping bolts
Bellows
MICE RF and
MICE
Coupling
Installation
Coil Module
Issues – Summary
MICE CM23ofatthe
ICST,
Design
Harbin,
and China
Fabrication Plan
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 28
Bellows Joint Detail
Joint pullback for installation
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 29
Bellows Joint Detail
Clamping of spectrometer solenoid joint
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 30
Bellows Joint Detail
Clamping of AFC module joint
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 31
Bellows Joint Detail
Fully clamped joints
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 32
Bellows Joint Detail
Bridging bolts for force transmission
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 33
Module Utility Requirements
•Cryomech Model PT-415 cryocoolers
•3 per spectrometer solenoid, 2 per coupling coil (12 total)
•50 Hz AC: 10.5 kW @ 380/420 V, 3 phase
•Cooling: minimum 3 gpm of water @ 80ºF max
•300 A Power Supplies – American Magnetics (5 ea total)
•50-60 Hz AC: 3.5 kW @ 208 V, 3, forced air cooled, rack mnt.
•60 A Power Supplies – Lake Shore Cryotronics (4 ea tot.)
•50-60 Hz AC: 0.3 kW @ 208 V, 3, forced air cooled, rack mnt.
•Vacuum: 10-3 torr @ startup thru 25 mm flanged ports
•Cavity cooling water: ~8 lpm/per cavity
•Getter pump regeneration power (100-210 VAC, 100 W)
•Pressurized N2: up to 200 psi for tuner actuators
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 34
Instrumentation
•Coupling coil and spectrometer solenoid
•Coil voltage taps
•Thermocouples
•LHe level
•Vacuum pressure
•RF cavities
•RF pickup loop
•N2 pressure control for tuners (1 per cavity)
•Cooling water temperature/flow
•RFCC module vacuum
•Getter pump power supply and controller
•Pump thermocouple
•Vacuum pressure
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Page 35
Download