Installation Issues MICE CM23 at ICST, Harbin January 13, 2009 Steve Virostek Lawrence Berkeley National Lab Topic Summary •Packaging and delivery to RAL •Moving of modules into MICE hall •Assembly work in MICE hall •Installation interfaces •End flanges and seals •Base mounting •Other connections •Utility requirements •Instrumentation MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 2 Progress Update •Shipping skid for RFCC module developed – Module axis is vertical during shipping – Skid provides for rotation to horizontal in MICE hall •RAL developing spectrometer solenoid lift beam – Four lifting points are included on the magnets – Load testing and certification is required •Two module bellows spools received at RAL – Bellows assemblies purchased from Hyspan – Spools connect spectrometer solenoid to AFC module – Apparent tolerance error being discussed w/vendor MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 3 Progress Update (cont’d) •Still need a helium-to-vacuum window design – Window separates vacuum space from tracker volume in spectrometer solenoid bore – Preliminary plan is to use AFC style window – Good opportunity to add mounting holes now •Several instrumentation readouts purchased – Thermocouple and helium level readouts for the spectrometer solenoid have been received by LBNL – Similar readouts will be needed for RFCC module – Most instrumentation only needed during initial tests MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 4 Shipping Logistics •All modules to be forklifted on/off truck •All magnet coils are shipped warm •RFCC cavities, couplers, coolers & pumps removed •Coupling coil integral with vacuum vessel •RFCC axis vertical during shipping •Concerns about shipping loads on coupling coil •Special shipping skid has been developed •Cavities, couplers packaged to prevent damage •RF, Be windows left in place w/appropriate protection •Vac vessel, cavities and couplers backfilled with N2 MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 5 RFCC Shipping Configuration Cavities removed Vacuum pumps removed Skid holds module in vertical orientation Cryocoolers removed Couplers removed MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 6 MICE Hall Access •Forklift to be used for unloading and moving through hall door •Door is tall and wide enough for spectrometer solenoids and RFCC modules •No special equipment or hardware is required MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 7 RFCC Rotation and Support Install Tilting runners installed on shipping skid MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 8 RFCC Rotation and Support Install Permanent support stand structure installed on RFCC vacuum vessel MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 9 RFCC Rotation and Support Install Module is tilted into horizontal orientation using crane MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 10 RFCC Rotation and Support Install Module is tilted into horizontal orientation using crane MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 11 RFCC Rotation and Support Install Finished tilting onto permanent support stand MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 12 RFCC Rotation and Support Install Finished tilting onto permanent support stand MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 13 Re-assembly of RFCC Module at RAL •Locate vacuum vessel/coupling coil on lateral tracks •Erect portable clean room around module •Unpack cavities, couplers, coolers, pumps •Install six tuner assemblies on each cavity •Insert cavities in vacuum vessel using special fixture •Install couplers and tuner actuators after cavity is aligned and supported by struts •Install vacuum pumps to complete module •Perform final alignment before translation MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 14 Re-assembly of Module at RAL Module ready for assembly MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 15 Re-assembly of Module at RAL Cryocooler(s) installed MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 16 Re-assembly of Module at RAL RF cavities installed from either end MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 17 Re-assembly of Module at RAL Cavity tuner actuators added MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 18 Re-assembly of Module at RAL Module vacuum pumps installed MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 19 Re-assembly of Module at RAL RF couplers installed MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 20 Module Base Mounting •RFCC module and Spectrometer Solenoid base connections to rails are similar •Six mounting plates are welded to the base of the module support stands •Location of the mounting plates will be included in an interface document (and later measured) •Magnetic loads are carried to the floor through the vacuum vessel/support stand/base mounts MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 21 Translating Platform MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 22 Spectrometer Solenoid Mounting Six mounting plates on the support stand base for installation on rails MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 23 RFCC Module Mounting •Six mounting plates to be welded to the support stand base for installation on rails •Similar to spectrometer solenoid mounting scheme MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 24 Insertion into MICE Beamline •Locate module on lateral tracks •Align and shim module to correct height •Pull back bellows on both module ends with O-rings in place •Translate module into position using rails •Release bellows and connect flanges •Lock out bellows using bridging bolts •Connect utilities and instrumentation MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 25 MICE Bellows Joints Bellows Joint Bellows Joint Bellows Joint Bellows Joint B Bellows Joint Bellows Joint MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 26 End Flanges and Seals •RFCC flanges mate with AFC module flanges •AFC flanges have no O-ring grooves or bellows •RFCC module flanges have bellows and O-ring grooves at both ends •Bellows are spec’d for >1 cm of total travel •Module relative alignment is driven by clearance in flange holes •Bellows are locked out after installation to allow transmission of forces between modules MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 27 Bellows Joint Detail Elastomer or Helicoflex allmetal O-ring Clamping bolts Bellows MICE RF and MICE Coupling Installation Coil Module Issues – Summary MICE CM23ofatthe ICST, Design Harbin, and China Fabrication Plan Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 28 Bellows Joint Detail Joint pullback for installation MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 29 Bellows Joint Detail Clamping of spectrometer solenoid joint MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 30 Bellows Joint Detail Clamping of AFC module joint MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 31 Bellows Joint Detail Fully clamped joints MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 32 Bellows Joint Detail Bridging bolts for force transmission MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 33 Module Utility Requirements •Cryomech Model PT-415 cryocoolers •3 per spectrometer solenoid, 2 per coupling coil (12 total) •50 Hz AC: 10.5 kW @ 380/420 V, 3 phase •Cooling: minimum 3 gpm of water @ 80ºF max •300 A Power Supplies – American Magnetics (5 ea total) •50-60 Hz AC: 3.5 kW @ 208 V, 3, forced air cooled, rack mnt. •60 A Power Supplies – Lake Shore Cryotronics (4 ea tot.) •50-60 Hz AC: 0.3 kW @ 208 V, 3, forced air cooled, rack mnt. •Vacuum: 10-3 torr @ startup thru 25 mm flanged ports •Cavity cooling water: ~8 lpm/per cavity •Getter pump regeneration power (100-210 VAC, 100 W) •Pressurized N2: up to 200 psi for tuner actuators MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 34 Instrumentation •Coupling coil and spectrometer solenoid •Coil voltage taps •Thermocouples •LHe level •Vacuum pressure •RF cavities •RF pickup loop •N2 pressure control for tuners (1 per cavity) •Cooling water temperature/flow •RFCC module vacuum •Getter pump power supply and controller •Pump thermocouple •Vacuum pressure MICE Installation Issues – MICE CM23 at ICST, Harbin, China Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009 Page 35