Expressway Authority of Thailand Ministry of Transport Market Sounding Documentation For Udonratthaya-Ayutthaya Expressway Project April 2015 -๒- 1. Introduction Expressway Authority of Thailand (EXAT) realizes great benefits of Udonratthaya-Ayutthaya Expressway Project as the infrastructure development for transportation of Thailand. The beginning of the project is started at the end route of the existing Udonratthaya Expressway and the end of the project connects to highway No. 32 at Bang Pahan District in Ayutthaya Province. Total distance of project is 42 kilometer. The objective of the project is to develop the expressway network for the linkage of travelling and goods transportation between Bangkok and Ayutthaya Province and also including the provinces in the North of Thailand. According to the Act on Private Investment in State Undertaking B.E. 2556 (2013), EXAT would like to invite private sectors to participate in giving suggestions and opinions on the project investment forms. Market sounding of Udonratthaya-Ayutthaya Expressway Project is conducted to obtain suggestions and opinions in order to implement this project efficiently. The information obtained from investors will used for this project only. 2. Objectives -1- The purpose of this market sounding is for market testing on private sectors’ interest of Udonratthaya-Ayutthaya Expressway Project’s investments. The suggestions and recommendations from private investors will enhance successful implementation of the project. 3. Target Groups 3.1 Thai or international company that operate and maintain expressway projects 3.2 Thai or international private investors 3.3 Any financial institutions that are interested in expressway projects 4. Project Details 4.1 Reason and Necessity The demand volume of cargo and passenger between Bangkok and Ayutthaya province has rapidly increased -2- because of the development of land use such as Real Estate and Industrial Estate sections. At present there are very high traffic volumes on highway No. 32 which is the main road to service the demand volume and the traffic characteristic is not in good condition. Apart from that, Ayutthaya province is also the location of much tourist attraction such as Ayutthaya Historical Park, Bang Sai Arts and Crafts Centre, Bang Pa-In Palace etc. and every year there are a lot of tourists come to visit. So the expansion of transportation network is critical to serve that demand. 4.2 Alignment of Project (1) Main line The beginning of the main line of UdonratthayaAyutthaya Expressway Project is started at the end route of the existing Udonratthaya Expressway at Bang Pa-in District. The main line moves forward to the North and parallels with highway No. 347 in the west side. The main line is across Chaophaya River at Kao Koet District and after that it passes through the area of Ayutthaya Province. The main line will connect to the highway in Ayutthaya Province, such as highway No. 3442 highway No. 347 highway No. -3- 356 highway No. 3263 highway No. 309 highway No. 329. The end of the main line will connects to highway No. 32 at Bang Pahan District and total distance of Udonratthaya-Ayutthaya Project is 42 km. as Figure 1. -4- Expressway Figure 1 Alignment of Udonratthaya-Ayutthaya Expressway Project -3- (2) Typical Section of Viaduct Structure The viaduct structure of Udonratthaya-Ayutthaya Expressway Project is design T-shaped column and I-Girder shape. It has 4-lane, (2-lane each direction). Each traffic lane is 3.50 meters wide with outer shoulder of 2.00 meters wide and inner shoulder of 0.50 meters wide as shown in Figure 2. Figure 2 Typical Cross Section of UdonratthayaAyutthaya Expressway Project (3) On-off ramp -4- There are 8 locations of on-off ramp as shown in Figure 3, as followed: 1) On-off ramp Bang Pa-in 2) On-off ramp Kanchanaphisek Road 3) On-off ramp Bang Sai Royal Folk Arts and Crafts Center 4) On-off ramp Kao Koet Royal Folk Arts and Crafts Center 5) On-off ramp Ban Klueng 6) On-off ramp Worrachet 7) On-off ramp Phut Lao 8) On-off ramp Bang Pahan -5- Figure 3 On-off Ramps of Udonratthaya-Ayutthaya Expressway Project -5- 4.3 Traffic Volume The traffic volume forecasting of Udonratthaya- Ayutthaya Expressway Project show as follows: Year Traffic on the expressway (PCU/day) 2022 (Opening Year) 27,026 2026 31,153 2031 43,083 2036 55,176 2041 69,014 2046 78,906 2051 93,186 4.4 The toll collection Toll collection of the Udonratthaya-Ayutthaya Expressway Project is a close system based on 42 kilometers distance. In the year 2022 (The opening year to the traffic), the toll rate of each vehicles are as follows: Types of vehicle Entry Distance Maximum rate rate toll rate -6- (Baht) (Baht/km.) (Baht) 4 wheels vehicle 35 0.50 55 6 to 10 wheels 70 1.00 110 105 1.50 165 vehicle More than 10 wheels vehicle -7- Project - Feasibility Study Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep 4.5 Project Implementation Plan Udonratthaya-Ayutthaya Expressway Project has a plan to implement during fiscal year 2014-2022 and opens to the traffic in 2022 as follows: 2014 2015 2016 2017 - Land acquisition - Construction (include detail design) -7- 2018 2019 2020 9months 8months 36months 2021 2022 2023 4.6 Project Investment Costs An investment budget for Udonratthaya-Ayutthaya Expressway project is approximately 3 1 ,432.51 Million Baht consisting of: - Land acquisition cost - Construction cost 2,766.51Million Baht 28,666.00Million Baht (Including detailed design and consultants cost) 4.7 The Economic Feasibility Study Shows that the project will be worthwhile economically as follows: - Net Present Value (NPV) = 24,850.25 Million Baht (at the discount rate of 12%) - Economic Internal Rate of Return (EIRR) = 19.81 - Benefit Cost Ratio (B/C) = 2.22 -8- 5. Scopes of Investment The private sector who has been appointed by the EXAT as a concessionaire of Udonratthaya-Ayutthaya Expressway Project is obliged to carry out the following scopes of project investment and the EXAT is obliged to perform the following scopes of project investment: 5.1 The private sector who has been granted for a concession is committed to project investment and operation in 2 phases as follows: Phase 1 Expressway Design and Construction The concessionaire will be responsible for the design and construction costs of Udonratthaya-Ayutthaya Expressway Project and make it complied with the concession agreement as well as provide installation of Mechanical and Electrical system, toll collection system, communication system, traffic control system and any other systems as considered necessary. Phase 2 Expressway Operations and Maintenance The concessionaire will be responsible for the operation cost of the expressway so that it can render service to public in an effective way with safety according to the international standard and the expressway can be -9- maintained in good condition throughout the concession period of the project. 5.2 The government will support for land acquisition cost in relation to the expressway construction project while the EXAT will assist in coordination with government sectors as well as give all the possible supports to the investor. So, it can be provided with maximum benefits according to the law of investment promotion. 5.3 Concession Period: The concession period of this project is 30 years beginning from the construction period. The concession holder obtains the right to receive the toll revenues generated from UdonratthayaAyutthaya Expressway Project and will have to pay a portion of the toll revenues to the government as mutually agreed in the concession agreement. 5.4 Project Operation Rules Udonratthaya-Ayutthaya and Regulations Expressway for Project, Ayutthaya Province will be according to the Private Investment in State Undertakings Policy Committee Act, B.E. 2556 (2013), the EXAT Act, B.E. 2550 (2007) and all the concerned rules, regulations and agreements. - 10 - 6. Private Partner Selection Criteria A selection of the private partner for UdonratthayaAyutthaya Expressway Project will follow the Public Private Partnership Act, B.E. 2556 (2013), while a Selection Committee will be nominated by the EXAT to set up initial selection criteria, as followed: 6.1 Qualifications of the Investor The concession holder must possess business management skill and a good financial status with at least 500 Million Baht paid-up registered capital. He/she should has experiences and records of the design– construction, project management as well as operation and maintenance of the expressways. 6.2 Proposal Preparation The interesting private partners will prepare proposals in accordance with the requirements stipulated in the proposal preparation documentation, arranged by the Selection Committee of Udonratthaya-Ayutthaya Expressway Project, Ayutthaya Province. 6.3 Private Partner Selection Process for Build-TransferOperate (BTO) Concession This is a concession given to private partner to operate the expressway which will be in compliance with the - 11 - Public Private Partnership Act, B.E. 2556 and the Expressway Authority of Thailand Act, B.E. 2550 (2007). - 12 - 7. Procedure in Market Sounding The questionnaire responders are kindly requested to fill in their ideas or suggestions and returned to the following address, from 16th April to 24th April, 2015, between 8.30 a.m. to 4.30 p.m. or send E-mail to eta_planing@exat.co.th or returned to the following address from 16th April to 24th April 2015. The Governor of The Expressway Authority of Thailand Expressway Authority of Thailand 2380 Phahonyothin Road Senanikom Chatuchak Bangkok 10900. With a word on the envelop corner “(Market Sounding)” For more information, Please contact Tel. +66 2 558 9800 Ext. 2540 Fax +66 2 940 1226 EXAT will neither be responsible for the expenses incurred from questionnaire responses nor committed to taking actions according to the suggestions information provided by the responders. - 13 - or 8. Questions 8.1 What form of investments are you interested in? _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______ 8.2 Are you in interested in the investment of UdonratthayaAyutthaya Expressway Project? Please specify the scope of your investment that you are interested in. As a company that operates and maintains an expressway As a private sector As a financial institution Others; please specify _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ - 14 - _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ ______________________________________ _______________________________________________ ___________________ 8.3 Considering allocation of project funding, do you have any suggestions, opinions, or requests for financial supports from the government? _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________ - 15 - 8.4 As Thai government is responsible for providing land and cooperating with facility agencies, do you have suggestions and/or opinions in order to implement this project efficiently? _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _ _______________________________________________ ___________________ _______________________________________________ ___________________ _______________________________________________ _______________________________________________ ______________________________________ _______________________________________________ ___________________ - 16 - 8.5 As Udonratthaya-Ayutthaya Expressway Project is a megaproject which requires tremendous amount of investment, do you have any suggestions and/or opinions in order to implement this project efficiently? _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________ - 17 - 8.6 Considering operation and maintenance of the project, do you have any suggestions, opinions, and/or requests for financial supports from the government? _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ ____________________ 8.7 As this project shall follow Build - Transfer - Operate (BTO), do you have any suggestions and/or opinions concerning - 18 - reasonable financial return to the Thai government and private sector? _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ ____________________ - 19 - 8.8 As Udonratthaya-Ayutthaya Expressway Project is a megaproject, in order to implement this project efficiently, do you think you should be offered some supports from the government? If yes, please specify: 1) Privilege Tax/Account 2) Co-operations & supports from government agencies 3) Public concerns 4) Others _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ - 20 - _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________ 8.9 Do you have any opinions and/or suggestions concerning investors’ cost of capital and the proper figure for the rate of return of this project? _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _____________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ - 21 - _______________________________________________ ____________________ - 22 - 8.10 Do you have any opinions and/or suggestions on the implementation plan of Udonratthaya-Ayutthaya Expressway Project? _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _____________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ ____________________ 8.11 Other suggestions _______________________________________________ _______________________________________________ _______________________________________________ - 23 - _______________________________________________ _______________________________________________ _____________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ _______________________________________________ ____________________ 9. Contact Details Contact Name : Position : Company : Name Company : Address : Telephone : Number - 24 - Fax Number : E-mail Address : - 25 -