Wastewater - Section 2

advertisement

Improved Coordination

• MPT – 95% designed

• CHP – design in progress

• FDF – design completed

• Coordination

 Utilities

 Cranes

 Geotechnical Information

 Weekly meetings – Internal and Intra-Contractor

 CFA meetings

• Partnering – MPT/CHP

 

Coordination of design/construction and Intra-Contractor

1

Potential Innovation

• Limited in proposals

 “Prescriptive”

 30 Alternatives – developed a “No Fly Zone”

• Construction – MPT

 Schedule offer 5 months less than anticipated in RFP

• CHP Negotiation

 Better steam control with condenser

 Arrangement of equipment

  Innovation accepted if not already vetted by

Owner

2

CHP Not Part of DC Water Expertise

• CHP – different review philosophy

 Owner – smaller review group, interested in interfaces, and “were not going to operate it”

 DBO – “We have to operate it, so we want to make changes

 PM/CM – find the balance to get full contract value and understanding

 DC Water recognizing benefit of when DB is appropriate

3

Lessons Learned To Date

• Owner likes to be able to short list 3 qualified proposers

First time Design Build

 Owner and Engineers need to take time to understand process

• Design issues come to head early

Design Build Joint Venture = skin in the game

• 3D modeling understanding accelerates

• Regulatory dust should be settled

Start-up and Commissioning

– start early

• “Haz Ops” meeting very important

• Prescriptiveness can serve “mature” Owners well

• Performance guarantees force designer and contractor to work together and could be a key to being less prescriptive

4

Artist Rendering

5

Artist Rendering

6

DC CLEAN RIVERS

PROJECT

PRESENTED BY Donal Barron

7

LUZON VALLEY (SEPARATED)

GREEN INFRASTRUCTURE

(MULTIPLE SITES THROUGHOUT

DISTRICT)

DC CLEAN RIVERS

PROJECT AND

NITROGEN REMOVAL

PROGRAMS

COMBINED SEWER AREA

ROCK CREEK TUNNEL

SEPARATE CSO 031, 037, 053 AND

058

ROCK CREEK REGULATOR

ADJUSTMENTS CSO 033,

036 AND 057

F

F

NORTHEAST BOUNDARY TUNNEL

POTOMAC TUNNEL

REHAB POTOMAC P.S.

EPA HEADQUARTERS

P

F

PUMP STATION

KNOWN FLOODING AREA

• DC CLEAN RIVERS PROJECT: $2.6 BILLION

• NITROGEN REMOVAL: $950 MILLION

• TOTAL > $ 3 BILLION

• 20 YR IMPLEMENTATION (2005 – 2025)

• 96% REDUCTION IN CSO

• FLOOD RELIEF IN NORTHEAST BOUNDARY

P

WHITE HOUSE

U.S.

CAPITOL

MAIN PS

P P

P

RFK

P

ABANDON NORTHEAST

BOUNDARY SWIRL

ANACOSTIA RIVER TUNNEL

SEPARATE CSO 006

REPLACE POPLAR POINT P.S.

BLUE PLAINS TUNNEL

P

BLUE PLAINS

ENHANCED CLARIFICATION

TREATMENT & NITROGEN

REMOVAL AT BLUE PLAINS

TUNNEL DEWATERING P.S.

8

Anacostia River Projects are Being Implemented on Schedule

Project Status Legend:

Completed

Construction

Procurement

Design

Prelim Engineering

NEB Branch

Tunnels &

Diversions

($283 M)

Tingey St Diversions

($ 17M)

Main PS Diversions

($ 40 M)

Poplar Point PS

($ 31M)

JBAB Overflow & Diversion

($25 M)

Tunnel Dewatering Pump.

Station and ECF

($ 333 M)

Blue Plains Tunnel Site Prep

(Digester Demolition)

( $ 12 M)

Mt Olivet Rd Diversions

($ 41 M)

Northeast

Boundary Tunnel

($ 282 M)

LID @ DC Water

Facilities

($3 M)

M St Div. Sewer

($ 41 M)

CSO 019

($40 M)

Anacostia River Tun.

($ 291 M)

Blue Plains Tunnel

($ 397 M)

CSO 007

($ 5 M)

A Blue Plains Tunnel

C CSO 019 Overflow and Diversion Structures

D JBAB Overflow and Potomac Outfall Sewer Diversion

E M Street Diversion Sewer (CSOs 015, 016 and 017)

G CSO 007 Diversion Structure and Diversion Sewer

H Anacostia River Tunnel

I Main Pumping Station and Tingey Street Diversions

J Northeast Boundary Tunnel

K Northeast Boundary Branch Tunnels

L Northeast Boundary Diversions

M Mt. Olivet Road Diversions

Y 9

Z Poplar Point Pumping Station Replacement

Anacostia River Tunnel

Overview

 23-foot diameter TBM tunnel

 Soft ground

 100 ± feet deep and 12,500 feet long

 Mining from CSO-019 south to PP-

JS

 6 shafts (15 to 75-foot I.D.)

 3 Adits (4.5 to 10-foot I.D.)

 2 Diversions

 6 Odor Control and Venting

Facilities

 Instrumentation & Data Collection

System

 System Start-up

 Design-Build contract value:

$200 – $250 million

PP-JS

CSO-019

CSO-018

M Street

CSO-007

CSO-005

10

ART Estimated Schedule

Event

Issue RFQ

Pre-SOQ meeting

Last day to submit RFQ questions

SOQ Due

Shortlist Notification

Issue RFP

Collaboration period

Proposals Due

Notice to proceed

Occupy site at CSO 019

Substantial Completion

Final Completion

Date

 October 16, 2011 

November 16, 2011 

 December 1, 2011 

 December 16, 2011 

February 10, 2012 

 April 13, 2012 

 April 2012 – December 2012

 December 12, 2012

June 3, 2013

 November 2013

 June 2017

 September 2017

11

Vision

Anacostia River Projects

DC Water is

Implementing Tunnels

Most severely impacted by CSOs

GI will provide additional

CSO control

Green

Potomac & Rock

Creek Projects

There is a brief window of time to consider new approaches

Gray Hybrid

12

Why is a Multi Million Dollar Demonstration

Project Necessary?

 Need it to be a large scale demonstration

– address entire subsewersheds

 Representative sites not “cherry picked” so scale-up is realistic

 Sound technical basis

 Potential for innovative solutions and creative alliances

 Targeted performance is high degree of

CSO control

 Resolution of institutional issues

 Analysis of other factors

• Triple bottom line benefits

Public acceptability

Testing over several meteorological / climate cycles

O&M impacts

The magnitude of investment by

DC ratepayers to control Potomac and Rock Creek CSOs requires a sound technical and institutional basis for making decisions

13

Demonstration Project (6 sites)

 Completed evaluation of sites for GI demonstration projects in

Potomac River and Rock Creek sewer sheds.

 After construction, monitor for 2 years

 Use results to design Potomac River and Rock Creek projects using combination of tunnels and GI

14

Lessons Learned

1.

Verify Financial Capabilities

• Evaluate need to compare proposers’ financial capabilities with respect to estimated cash flow needs

2.

Process Projects

• Designer needs a “skin in the game,” possibly as a JV partner

15

Lessons Learned

3.

RFQ Content/Solicitation

• Set a realistic page count; identify what pages do/do not count

Avoid requests requiring subjectivity or similar responses among proposers

Include standard forms in RFQ for simpler organization/evaluation

When answering questions, send responses to all proposers

4.

RFQ Evaluation

• Have technical staff at selection panel discussions to answer questions

• Obtain completed score sheets before selection panel adjourns

16

Lessons Learned

5.

Contents of Technical Proposal

Resist requesting more items; identify points that differentiate better schedule, better quality, less risk

Avoid asking for identical things in different sections

Ask key personnel to list only what contributes to project success

6.

Confidentiality

Emphasize confidentiality among all teams; require signed agreements

Don’t put confidential evaluations/comments on shared computer drives

Don’t meet with individual proposers after release of RFQ; exceptions are official proprietary meetings

Be careful what is printed to shared printers

17

TUNNEL DEWATERING PUMPING STATION

AND ENHANCED CLARIFICATION FACILITY

PRESENTED BY Bo Bodniewicz

18

Long Term Control Plan

Overview

20-year program with a goal of reducing CSO events

19

Controlling Combined

Sewer Overflows (CSOs)

TDPS & ECF Project furthers control & treatment of CSOs

Capture Uncontrolled CSO Discharges

• Potomac and Anacostia Rivers

• Rock Creek

Relieve flooding in Northeast Boundary Area

Implemented under a Federal

Consent Decree

• U.S. EPA / U.S. DOJ

• District of Columbia

• DC Water

20

Download