SUMMER INTERNSHIP REPORT ON 1. ANALYSIS OF REC MECHANISM 2. STUDY OF OPPORTUNITY AND OPTIONS TO SUPPLY POWER TO AN UPCOMING MEGA FOOD PARK IN THE STATE OF MADHYA PRADESH. UNDER THE GUIDANCE OF Mrs. Rachna Vats, Senior Fellow (NPTI) And Mr. Anuj Xess, Manager (REConnect Energy) Submitted by SIDDHARTH SUNDRIYAL ROLLNO: 83 MBA (POWER MANAGEMENT) Center for Advanced Management and Power Studies NATIONAL POWER TRAINING INSTITUTE (Under Ministry of Power, Govt. of India) Affiliated to MAHARSHI DAYANAND UNIVERSITY, ROTHAK AUGUST 2013 1 TRAINING COMPLETION CERTIFICATE I DECLARATION I, Siddharth Sundriyal, Roll no. 83 / Semester 3/ Class of 2012-14 of the MBA (Power Management) of the National Power Training Institute, Faridabad hereby declare that the Summer Training Report entitled 1. Analysis of REC Mechanism. 2. Study of opportunity and options to supply power to an upcoming mega food park in the state of Madhya Pradesh. is an original work and the same has not been submitted to any other Institute for the award of any other degree. A Seminar presentation of the Training Report was made on 04.09.2013 and the suggestions as approved by the faculty were duly incorporated. Presentation In charge (Faculty) Signature of the Candidate Countersigned Director/Principal of the Institute II ACKNOWLEDGEMENT I express my sincere thanks to Mr. Vibhav Nuwal (Director), REConnect Energy for giving me a great opportunity to work in such an esteem organization. I am solemnly thankful to Mr. Anuj Xess, (Manager) , REConnect Energy for his guidance and support. I also record my sincere thanks to Mr. Chetan Adhikari and Mr. Manoj Jha, REConnect Energy, for giving me valuable inputs during my tenure with the Organisation. I feel deep sense of gratitude towards Mr. S. K. Chaudhary, Principal Director, Dept. of Management Studies, Mrs. Manju Mam, Director, NPTI and Mrs. Indu Maheshwari, Dy. Director, NPTI for arranging my internship at REConnect Energy, Gurgaon and being a constant source of motivation and guidance throughout the course of my internship. I am truly indebted to Mr. Rohit Verma (Dy. Director), Mrs. Rachna Vats (Senior Fellow), Mrs. Farida Khan (Senior Fellow), Ms. Vardha Saghir (Senior Fellow), Ms. Karishma Verma (Senior Fellow) NPTI for their cooperation; and for guiding me through the course of my internship. Siddharth Sundriyal III EXECUTIVE SUMMARY The report is divided into two parts and covers two projects Project 1: Analysis of REC Mechanism. Government of India is endeavoring hard to increase share of renewable energy in electricity mix of country. As per target set under National Action Plan on Climate Change (NAPCC), government envisages renewable energy to constitute approx. 15% of total electricity consumption in the country by 2020. A number of regulatory provisions and fiscal policies like Renewable Purchase Obligation (RPO) and Accelerated Depreciation (AD) have been introduced for the same. Schemes like Feed in Tariff (FiT) has proved quite successful in providing initial thrust but it gives rise to problems such as price rigidity and rather slow cost reductions driven by mass production, and increases the financial burden on national governments. REC mechanism, launched on November 18th 2010, is market based instrument to promote RES and in cost effective manner. In India where RE sources are not evenly spread across different parts of country the mechanism seems even more promising by helping the obligated entities to meet their binding targets (RPO). But the contemporary mechanism certainly has loose ends to work upon. Uncertainty about REC price after current control period (FY 2017), non-uniform approach in RE target setting, less frequent (once in a month) trading sessions, annual compliance of RPOs making REC market skewed towards year end, piling up of REC inventory etc. are making the mechanism less attractive for developers. The project involves comprehensive study of current REC mechanism, REC pricing methodology, and trading pattern. Based on the study and discussion with several stakeholders areas of improvement in the contemporary mechanism have been identified and some recommendations have been given to make the mechanism more attractive and promising. IV Project 2: STUDY OF OPPORTUNITY AND OPTIONS TO SUPPLY POWER TO AN UPCOMING MEGA FOOD PARK IN THE STATE OF MADHYA PRADESH. This project report is meant for a developer of an upcoming mega food park in M.P. who is a potential client of m/s REConnect Energy Solutions. The Scope of this report are: I. Opportunity for taking distribution license a. Rules and regulations governing obtaining and operating as a distribution licensee b. Procedure for obtaining distribution license c. Eligibility for obtaining distribution license d. Pros and cons of operating a distribution license at the food park versus other models available II. Assessment of solar project for captive power supply at the food park a. Optimal size and model (captive, under solar park, etc) b. Cost and savings estimate for various models d. Assessment of various options available for sourcing power and potential savings on the same . e. Introduction of different EPC/ solar park providers V LIST OF TABLES Table 1: Fees and charges of REC .................................................................................................. 8 Table 2: Pricing of REC ................................................................................................................ 25 Table 3: NAPCC charges .............................................................................................................. 29 Table 4: Demand Potential of RE Power Requirement.................................................................. 29 Table 5: REC inventory ............................................................................................................... 29 Table 6: Voluntary Purchase of RE by Customer Type in USA .................................................. 31 Table 7: Benchmark costing of solar pv ....................................................................................... 31 Table 8: Comparison of RE sources ............................................................................................. 35 Table 9: Project developers……………………………………………………………………… Table 10: EPC Providers and System Integrators……………………………………………….. LIST OF FIGURES Figure 1: REC concept .................................................................................................................. 39 Figure 2: Comparison of projects with and without REC ............................................................ 52 VI ABBREVIATIONS APPC Average Power Purchase Cost CA Central Agency CEA Central Electricity Authority CER Carbon Emission Reduction CERC Central Electricity Regulatory Commission DISCOM Distribution Company FiT Feed in Tariff JNNSM Jawaharlal Nehru National Solar Mission MNRE Ministry of New and Renewable Energy NAPCC National Action Plan on Climate Change NLDC National Load Dispatch Center ORER Office of Renewable Energy Regulator O&M Operation and Maintenance PEx Power Exchange RE Renewable Energy REC Renewable Energy Certificate SLDC State Load Dispatch Center WACC Weighted Average Cost of Capital VII Table of Contents TRAINING COMPLETION CERTIFICATE............................................................................ I DECLARATION.......................................................................................................................... II ACKNOWLEDGEMENT .......................................................................................................... III EXECUTIVE SUMMARY ........................................................................................................ IV PROJECT 1: ANALYSIS OF REC MECHANISM. ............................................................................. IV PROJECT 2: STUDY OF OPPORTUNITY AND OPTIONS TO SUPPLY POWER TO AN ..... V UPCOMING MEGA FOOD PARK IN THE STATE OF MADHYA PRADESH. ................... V LIST OF TABLES ...................................................................................................................... VI LIST OF FIGURES .................................................................................................................... VI ABBREVIATIONS ................................................................................................................... VII TABLE OF CONTENTS ........................................................................................................ VIII CHAPTER 1 : RENEWABLE ENERGY CERTIFICATE MECHANISM ........................... 2 REC MECHANISM IN INDIA .......................................................................................................... 2 1.1.1 Introduction .................................................................................................................... 2 1.1.2 Drivers for REC in India ................................................................................................ 3 1.1.3 Control period, operative period and sunset date .......................................................... 3 1.1.4 Objectives for REC Mechanism in India ........................................................................ 4 1.1.5 Operational Framework for RECs ................................................................................. 4 1.2 SALIENT FEATURES OF REC FRAMEWORK ............................................................................. 6 CHAPTER 2: REC CONCEPT ................................................................................................... 8 2.1 VALIDITY OF CERTIFICATES ................................................................................................... 9 2.2 DENOMINATION AND ISSUE OF CERTIFICATES ........................................................................ 9 2.3 FEES AND CHARGES ................................................................................................................ 9 2.4 FUNDING FOR CAPACITY BUILDING OF STATE AGENCY ........................................................ 10 2.5 PRICING OF CERTIFICATES: ................................................................................................... 10 CHAPTER 3: REC POTENTIAL MARKET ASSESSMENT .............................................. 11 3.1 RE POWER REQUIREMENT IN DIFFERENT STATES IN INDIA TO FULFILL RPO . ...................... 12 3.2 THE KEY DRIVING FACTORS FOR DEMAND AND SUPPLY OF RECS : ....................................... 13 CHAPTER 4: FINDINGS AND ANALYSIS ........................................................................... 14 1. LACK OF CLARITY REGARDING MINIMUM SIZE OF PROJECTS TO BE ELIGIBLE FOR REC – .... 14 2. NON-UNIFORM APPROACH IN TARGET SETTING. .................................................................... 15 3.NON AVAILABILITY OF RPO LEVELS AND PERIODIC ACCOMPLISHMENT AT SINGLE SOURCE . 16 4. PILING UP OF REC INVENTORY (CLOSING BALANCE) ............................................................ 16 5. UNCERTAINTY ABOUT LENGTH OF CONTROL PERIOD AND REC PRICE POST 2017 ................. 17 VIII 6. LITTLE PARTICIPATION OF SMALL VOLUNTARY BUYERS ....................................................... 18 7. CURRENT REC MECHANISM DOESN’T INCENTIVISE OFF-GRID INSTALLATIONS ..................... 19 CHAPTER 5: REGULATIONS FOR SPECIAL ECONOMIC ZONE IN M.P. ................. 21 CHAPTER 6: OPPORTUNITY FOR TAKING DISTRIBUTION LICENSE .................... 22 6.1 RULES AND REGULATIONS GOVERNING OBTAINING AND OPERATING AS A DISTRIBUTION LICENSEE .................................................................................................................................... 22 6.1.1 Introduction to Distribution Licensee........................................................................... 22 6.2 ELIGIBILITY FOR OBTAINING DISTRIBUTION LICENSE ............................................................ 22 6.3 PROCEDURE FOR OBTAINING DISTRIBUTION LICENSE ............................................................ 23 6.4 DOCUMENTS TO BE ACCOMPANIED WITH THE LICENSEE APPLICATION FORM. ....................... 23 6.5 PROS AND CONS OF OPERATING AS A DISTRIBUTION LICENSE AT THE FOOD PARK VERSUS OTHER MODELS AVAILABLE........................................................................................................ 26 6.6 OPTIONS FOR PROCURING OR GENERATING POWER FOR THE MEGA FOOD PARK. ................... 27 6.6.3 Assessment of solar project for captive power supply at the food park ....................... 27 6.6.2 Mechanism of Viability Gap Funding in Phase-II Batch-I of JNNSM ......................... 32 6.6.3 Criteria ........................................................................................................................ 32 6.6.4 Power projects models for the mega food park. ........................................................... 35 CHAPTER 7: SUGGESTIONS AND RECOMMENDATIONS. .......................................... 38 BIBLIOGRAPHY ....................................................................................................................... 40 IX PROJECT 1: ANALYSIS OF REC MECHANISM 1 CHAPTER 1 : RENEWABLE ENERGY CERTIFICATE MECHANISM REC Mechanism in India 1.1.1 Introduction For catalyzing the necessary development of renewable energy in India, various policy Instruments have been listed in NAPCC. Renewable Energy Certificate (REC) is one such policy instrument prescribed in the plan. It is anticipated that this mechanism would enable large number of stakeholders to purchase renewable energy in a cost effective manner. When renewable power is produced, it entails accrual of certain non-energy and societal Beneficial attributes (e.g. environmental and socioeconomic benefits). Renewable Energy Certificates (RECs) or Green tags, Renewable Energy Credits, or Tradable Renewable Certificates (TRCs) as they are at times referred to, represent an aggregation of such attributes of electricity generated from renewable energy sources. These attributes are unbundled from the physical electricity, and the two products—the attributes embodied in the certificates and the commodity electricity—may be traded separately. RECs have at times been viewed as a contractual right (property right) to the environmental attributes of electricity that is generated from renewable energy. In less than a decade RECs have become the pseudo currency of renewable energy markets, primarily because of their flexibility and the fact that they are not subject to the geographic and physical limitations of commodity electricity. In several countries RECs are being used by utilities and marketers to supply renewable energy products to end-use customers as well as to demonstrate compliance with renewable energy mandates. The Renewable Energy Certificates (RECs) have the potential to address some of the key issues preventing exploitation of renewable potential in India. Providing the generator or the buyer, an option of cost compensation through sale of such certificates will incentivize development of R.E. projects over and above the Renewable Purchase obligation set by regulatory commissions at state level. 2 1.1.2 Drivers for REC in India India has a huge RE potential- its midterm potential (till 2032) is estimated to be around 2,22,000 MW; however this potential is not distributed uniformly across the country. The Electricity Act 2003 (EA 2003) mandates State Electricity Regulatory Commissions (SERC) with the function of RE promotion within the State. The SERCs set targets for distribution companies to purchase certain percentage of their total power requirement from renewable energy sources. This target is termed as Renewable Purchase Obligation (RPO). The requirement of scheduling and prohibitive long term open access charges poses major barrier for RE abundant states to undertake inter-State sale of their surplus RE based power to the States which do not have sufficient RE based power. Consequently, the States with lower RE potential have to keep their RPO target at lower level. Besides the shortcomings of state level approach to renewable development, other inherent disadvantages of energy produced from such resources such as high unit cost of the RE based non-firm power compared to conventional power sources result in lack of motivation to produce RE based power beyond that required to satisfy the RPO mandate within the State in RE abundant States. Also RE scarce States are not able to procure RE generation from other States due to the reasons mentioned above. To overcome the challenges being faced in overall renewable development, a mechanism to enable and recognize inter- State RE transactions was critically required for further promotion and development of RE sources. The aim of introducing such a mechanism was to enable all the SERCs to raise their States‘RPO targets even if necessary resources are not available in some States. The Renewable Energy Certificate Mechanism is a mechanism which fits the bill. 1.1.3 Control period, operative period and sunset date Control period is a period during which the proposed REC Scheme will be in force while operative period is a period in which projects implemented during control period. Sunset date refers to the date on which scheme expires. It is proposed that the Scheme shall come into force 3 on April 1, 2010 and control period shall be five years i.e. March 31, 2015. And the sunset date shall be 25 years from the date on which scheme came into force i.e. March 31, 2035. 1.1.4 Objectives for REC Mechanism in India While effective implementation of inter-state transactions would be primary objective for the REC mechanism in India, some of the other objectives identified for REC mechanism are: Effective implementation of RPO regulation in all States in India Increased flexibility for participants to carry out RE transactions Overcoming geographical constraints to harness available RE sources Reduce transaction costs for RE transactions Create competition among different RE technologies Development of all-encompassing incentive mechanism Reduce risks for local distribution licensee. 1.1.5 Operational Framework for RECs Step-1 Accreditation: The proposed REC mechanism requires a procedure for accrediting generation plants which are eligible to receive RECs. Accreditation is done to assess and establish eligibility of renewable energy plants to receive RECs. The process of accreditation is largely one time activity where in plants are validated on its renewable nature and other pre-requisites to be eligible for issuance of REC. The State agency appointed by the State Electricity Regulatory Commission (SERC) shall be responsible for Accreditation. Accreditation process involves processing of application, verification of projects, transfer of information, creation and operation of accounts etc. The process of accreditation of eligible renewable energy projects would also involve verification of applications (projects) and sites and hence the accreditation agencies at state level would need to have adequate monitoring capability. 4 Step-2 Registration Every eligible entity shall apply for registration at central level. Only one central agency at national level will be authorized to recognize attributes from renewable generation to avoid double counting. Registration will result in creation of an account for all the entities participating in the mechanism. Step-3 Information of RE generation Central agency would receive information about injection of RE power by the accredited RE generators through State Load Dispatch Centre (SLDC) via Regional Load Dispatch Centre (RLDC) and local distribution licensee. Step-4 Issuance of REC by REC registry The eligible entity shall receive a certificate for a specified quantity of electricity generated and injected into the grid. One REC will be issued for each 1 MWh of electricity generated from renewable energy plants. RECs will be created as electronic records in a register (because electronic documents are easier to track than paper documents). The issued certificates will be credited to the registered account of the plant operator/owner. Step-5 Exchange of REC RE generators with REC certificates can exchange their certificate at a common platform viz. the power exchange approved by CERC. Obligated entities (as defined by the SERCs in their regulations for RPO obligations) shall buy REC through power exchange. The price discovery of REC will be based on the demand and supply of the RECs in the market, subject to a forbearance price (ceiling price) determined by CERC. REC exchange will be connected to the central agency to keep record of all the transaction in the REC exchange. Step-6 Monitoring Mechanism It is proposed that a panel of auditors shall be empanelled by CERC at the central level. The remuneration charges for such panel of auditors will be met out of the funds which Central Agency may collect from eligible entities. 5 Step-7 Compliance by Obligated Entities Central registry will furnish details of REC purchase and redemption to respective SERCs to enable them to assess compliance by obligated entities and impose penalties on them, if applicable. As evolved by the Forum of Regulators, there is a provision for enforcement mechanism in the draft model regulation for SERCs under section 86 (1) (e) of the Act. As per this provision, in the event of default, obligated entities would be directed to deposit the amount required for purchase shortfall of REC at forbearance price (i.e. maximum price) of REC in a separate fund, which cannot be utilized without approval of the concerned State Commission. In addition to this enforcement mechanism the penalty under Section 142 of the Electricity Act 2003 would also be applicable to the obligated entity. The concerned State Commission can empower an officer of the State Agency to procure required shortfall of REC at the cost and expense of Distribution licensee. 1.2 Salient Features of REC Framework ● Cost of electricity generation from renewable energy sources is classified as cost of electricity generation equivalent to conventional energy sources and the cost for environmental attributes. ● RE generators will have two options: a. either to sell the renewable energy at preferential tariff , or b. to sell electricity generation and environmental attributes associated with RE generation in the form of REC separately. Grid connected RE Technologies approved by MNRE would be eligible under this scheme. ● Existing projects having firm PPA would not be eligible till the end of the contract period or a period of three years from the date of premature termination of the agreement, whichever is earlier. 6 ● Captive Generators (including their self-consumption) shall be eligible for REC if they do not avail promotional / concessional Wheeling Charges, Banking Facility and enjoy Electricity Duty Waiver. However, if they forgo such benefits, they will not be eligible to access the market for 3 years. Provided that the 3 year limit does not apply if the concessions are withdrawn by the state or state commission. ● Under REC Mechanism, RE generating company sells the electricity generated either a. to the distribution licensee at a price not exceeding the pooled cost of power purchase of such distribution licensee, or b. to any other licensee or to an open access consumer at a mutually agreed price, or through power exchange at market determined price. ● Central Agency- NLDC would issue REC to RE generators. ● One REC will be issued to the RE generators for 1 MWh of electricity injected into the grid from renewable energy sources. ● Categories of Certificates: Solar and Non-solar. ● CERC may, in consultation with the Central Agency, appoint from time to time compliance auditors to inquire into and report on the compliance of these Regulations by the person applying for registration, or on the compliance by the renewable energy generators in regard to the eligibility of the Certificates and all matters connected thereto. 7 CHAPTER 2: REC CONCEPT As shown in the figure RE generation either can be sale at feed in tariff or it can be utilized by selling it for REC benefits. So electricity shall have to be sold to a licensee equal or less than APPC.RE generator can sell REC as a green attributes through power exchanges. FIGURE 1: REC Concept RENEWABLE ENERGY GENERATION ELECTRICITY + REC BENEFITS SALE AT FIT ELECTRICITY GENERATED WILL BE SOLD TO DISCOM AT A REGULATED TARIFF ELECTRICITY SOLD TO OPEN MARKET AT MARKET PRICE GREEN ATTRIBUTE SOLAR REC DISCOMS AT PRICE LESS THAN /EQUAL TO APPC NON SOLAR REC SALE OF RECS AT EXCHANGE 8 2.1 Validity of Certificates Eligible entity should apply for Certificates within three months after corresponding generation from the eligible RE projects. Also the certificate would be valid for 2 years from the date of issuance of such certificate. 2.2 Denomination and issue of Certificates The detailed procedure for issuance of REC would be covered under the detailed procedure to be issued by the Central Agency later. Each certificate would represent one megawatt hour of electricity generated from renewable energy sources and injected into the grid. 2.3 Fees and charges Fees and Charges payable under this mechanism would include onetime registration fee and charges, annual fee and charges, the transaction fee and charges for issue of certificate and charges for dealing in the certificate. The details of fees and charges for different procedures of REC are as under: Table 1 : Fee& Charges for REC Fee and Charges towards Accreditation Amount in Rs Processing Fees (One Time) 5,000 Accreditation Charges (One Time) 30,000 Annual Charges Revalidation Charge at the end of five (5) years 15,000 Fee and Charges towards Registration 10,000 15,000 Processing Fees (One Time) 1, 000 Registration Charges (One Time) 5, 000 Annual Charges 1,000 Revalidation Charge at the end of five (5) years Fee and Charges towards Issuance of REC Fees per Certificate 5,000 Amount in Rs Amount in Rs 10 9 The fees and charges under this mechanism would be collected by the Central Agency and utilized for the purpose of meeting the cost and expense under the mechanism including the remuneration payable to the compliance auditors, the officers, employees, consultants and representatives engaged to perform the functions under these regulations. 2.4 Funding for capacity building of State Agency State Agency is an important institution in the process of effective implementation of REC mechanism. Considering the role envisaged for such an agency, it is necessary to build up capacity for the agency. Hence certain percentage of the proceeds from the sale of Certificates would be provided for the purpose of training and capacity building of the State Agency as designated by the concerned State Commission and for other facilitative mechanism required as per the detailed procedure by the Central Agency. 2.5 Pricing of Certificates: The price of REC will be as discovered in the power exchange, subject to a floor and forbearance price determined by CERC. The forbearance price will not only ensure optimum incentive for the RE technologies but also save the obligated entities purchasing RECs at unrealistic high price. It is should be noted that the REC purchase expense for meeting compliance by distribution licensees should be treated as pass through‘ expense in the Annual Revenue Requirement. CERC, declares the floor and forbearance prices for the solar and non-solar RECs. Forbearance Price: The forbearance price has been derived based on the highest difference between cost of generation of RE technologies / RE tariff and the average power purchase cost of 2011-12 for the respective states. Floor Price: The floor price has been determined keeping in view the basic minimum requirements for ensuring the viability of RE projects set up to meet the RE targets. This viability requirement shall cover loan repayment & interest charges, O&M expenses and fuel expenses in case of Biomass and Cogeneration. Table 2: REC Price for Period 2012-17 Non Solar REC (Rs/MWh) 3,300 Forbearance Price Floor Price 1,500 Solar REC ( Rs/MWh) 13,400 9,300 10 CHAPTER 3: REC POTENTIAL MARKET ASSESSMENT To analyze the potential REC market in India, Renewable energy generation thus available has been compared with the current scenario (RE capacity addition as planned) to quantify incremental RE generation due to target set out in NAPCC. Table 3 : NAPCC target implementation NAPCC Target implementation Scenario Energy Requirement Unit 2009-10 2010-11 2010-11 2011-12 2012-13 2013-14 2014-15 BU 848.39 906.32 968.32 12.7567 15.8205 19.6201 NAPCC Target RE Energy % BU 5% 42.4195 6% 54.3792 7% 67.7824 8% 81.3672 9% 96.1146 10% 112.134 Incremental Energy BU - 11.9597 13.4032 13.5848 14.7474 16.0194 MW 15765.9 19553.1 24250 30075 37299. 46258 % 25% 25% 25% 25% 25% 25% RE Energy Availability BU 34.5273 42.8213 53.1075 65.8642 81.6848 101.305 RE Energy Availability % 4.07% 4.72% 5.48% 6.48% 7.65% 9.0% Incremental Renewable Energy Availability BU - 8.29397 10.2862 12.7567 15.8205 19.6201 Current Scenario Renewable Installed Capacity CUF At estimated CUF of 25% on aggregate basis, total renewable energy generation is expected to increase from 34.53BU (2009-10) to 101.305BU units (2014-15), which translate to share of RE quantum in overall energy mix to increase from 4.07% to 9.03%, which is marginally lower than the RPO trajectory outlined under NAPCC. Thus, incremental RE generation varies from 8.29BU to 19.6201BU. If RECS are proposed to be introduced for new RE projects, this translates to REC market potential of around 8 to 20BU per annum. 11 3.1 RE Power Requirement in different states in India to Fulfill RPO . As discussed above that 21 states have declared their RPO. It is interesting to see how much electricity these states need to procure from RE sources in order to fulfill their RPO? Table 4: Demand Potential of RE Power Requirement (in MUs) State 2010-11 2011-12 2012-13 4190 4793 5483 Assam 65 139 224 Delhi 227 241 254 Gujarat 2514 2949 3425 Haryana 3787 4557 5484 Himachal Pradesh 662 776 902 Jammu & Kashmir 101 317 554 Jharkhand 287 308 330 Karnataka 4924 5465 6066 Madhya Pradesh 2247 2288 2330 Maharashtra 5889 7460 8602 Manipur 15 26 48 Mizoram 18 23 29 Orissa 1098 1222 1418 Punjab 1722 1794 1869 Rajasthan 3688 4161 5159 Tamil Nadu 6609 6518 6934 10 22 24 Uttar Pradesh 2497 3201 3800 Uttarakhand 723 845 889 Andhra Pradesh Tripura West Bengal 663 1146 2199 As shown above, a large amount of Renewable Energy generation is required by obligated entities to fulfill their RPO condition as defined by their respective states and but as shown in Table 4, as per the projection of Renewable Energy generation in future is not going to be sufficient for obligated entities to fulfill their RPO criteria. 12 So in order to complete their RPO these obligated entities should have to purchase REC. 3.2 The key driving factors for demand and supply of RECs : a) Demand for RECs: The demand for the RECs will be mainly driven by the states which are not able to meet their RPO targets by purchase of RE power. A review of RPO target and actual achievement shows that very few states have been able to meet their RPO targets. In long term, factors like RPO targets, total electricity consumption of the states and the gap between targets & achievement will vary, which will eventually change the demand for RECs. b) Supply for RECs: The supply of RECs will depend upon the new renewable energy capacity addition, RE projects getting eligible for issuance of RECs, players participating in the REC market etc . 13 CHAPTER 4: FINDINGS AND ANALYSIS 1. Lack of Clarity Regarding Minimum Size of Projects to be Eligible for REC – CERC doesn’t specify minimum installed capacity for projects to avail RECs, though in Draft document issued by CERC on March 17, 2010, it was mentioned as 250 KWp.30 Only three state agencies, (viz. Jammu and Kashmir, Maharashtra and Orissa), have specifically notified the minimum size allowed for REC projects. The table shows the detailsSTATE REC cap Andhra Pradesh No Cap Assam No Cap Bihar No Cap Chattishgarh No Cap Delhi No Cap Gujarat No Cap Haryana No Cap Himachal Pradesh No Cap Jammu & Kashmir 250 kW Goa & UT No Cap Jharkhand No Cap Kerala NA Madhya Pradesh No Cap Maharashtra 250 kW Manipur and Mizoram No Cap Meghalaya No Cap Nagaland NA Orissa 250 kW Punjab No Cap Rajasthan No Cap Tamil Nadu No Cap Tripura No Cap Uttar Pradesh No Cap Uttrakhand No Cap 30Source: MODEL PROCEDURE / GUIDELINES FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR REC MECHANISM BY STATE AGENCY (Draft dated March 17, 2010) 14 MERC specifies minimum installed capacity for availing REC benefit to be 250 kwp.31However, there are cases in Maharashtra where projects lower than the specified capacity (250 kWp) have been accredited. Energy Project No. Capacity (MW) OO1 0.225 29-06-2012 N/A OO1 0.225 6/6/2012 N/A Maharastra Wind M-Tech Innovations Ltd M/s KOTHARI AGRITECH PVT. LIMITED M/s KOTHARI AGRITECH PVT. LIMITED OO2 0.225 6/6/2012 N/A Maharastra Wind BotharaFoundary& Machine Works OO1 0.225 29-03-2012 23-05-2012 Maharastra Wind Deegee Orchards Pvt Ltd OO1 0.23 17-02-2012 23-03-2012 Maharastra Wind Sanjay D. Ghodawat HUF OO1 0.23 17-02-2012 N/A Maharastra Wind NarendraSolvexPvt Ltd Narendra Vegetable Products Pvt Ltd OO1 0.23 17-02-2012 23-03-2012 OO1 0.23 17-02-2012 23-03-2012 STATE Source Maharastra Wind Maharastra Wind Maharastra Wind RE Generator Date of Accrediation Date of Registration *Source:https://www.recregistryindia.in/index.php/general/publics/accredited_regens There should be uniformity among states agencies while setting eligibility criteria for Accreditation. Again, the states which have specifically laid out criteria should follow them strictly. More clarity regarding minimum installed capacity for REC eligibility is desired. 2. Non-Uniform Approach in target setting. The target for RE generation (year 2012-13) has been taken as average of renewable energy requirement as per the NAPCC and as per the MNRE Report on “Renewable Energy in India: progress, Vision and Strategy. Therefore, the Commission has, for computing floor price, settled on a figure which is around 70000 MUs. In the last order dated 1st June 2010 for calculating REC prices the respective RE (MU) for 6% of DMRPS it was considered on the basis of 17th Electric Power Survey (EPS) data. A uniform approach should be adopted for setting the targetas it directly affectsthe floor price. Higher the target higher is the floor price.And subsequently it affects the cash flow for project developers. 15 3.Non Availability of RPO levels and Periodic Accomplishment at Single Source Information about RPO levels of various states is not available at single source (website). Again, information about periodic accomplishment of RPO target by various obligated entities are also not available on public domain. Once rational RPO targets have been set for various states, the information about it and its accomplishment should be available on website maintained by central agency (NLDC). The Central Agency (CA) from time to time, after each trading session (of RECs) or fortnightly, update the RPO achievement section and should intimate the utilities falling short of target. The regular updating of target achieved will give an idea of REC market to the RE generators and they can thus eventually anticipate the REC demand in months ahead. 4. Piling Up of REC Inventory (Closing Balance) Since the first trading session in March 2011, in last 30 trading sessions, only four times number of RECs issued have exceeded number of RECs redeemed. This has led to huge surge of REC inventory (non-redeemed). Again, RECs are valid for only two years (from date of issuance) and eventually lapsed if not traded in two years. This leaves the RE developers with skepticism about the popularity of certificate market as their cash inflows are at stake. Table 5: REC Inventory Month, Year Opening Balance Solar REC Issued Total Solar 0 REC Redeemed Total Solar 0 Non Solar 532 532 Closing Balance March, 2011 0 Non Solar 0 Total Solar 0 Non Solar 424 Total 0 Non Solar 108 424 April, 2011 0 108 108 0 4503 4503 0 260 260 0 4351 4351 May, 2011 0 4351 4351 0 28270 28270 0 18502 18502 0 14119 14119 June, 2011 0 14119 14119 0 27090 27090 0 16385 16385 0 24824 24824 108 July, 2011 0 24824 24824 0 30224 30224 0 18568 18568 0 36480 36480 Aug, 2011 0 36480 36480 0 31813 31813 0 25096 25096 0 43197 43197 Sept, 2011 0 43197 43197 0 74612 74612 0 46362 46362 0 71447 71447 Oct, 2011 0 71447 71447 0 126544 126544 0 95504 95504 0 102487 102487 Nov, 2011 0 102487 102487 0 135697 135697 0 105527 105527 0 132657 132657 Dec, 2011 0 132657 132657 0 88055 88055 0 111621 111621 0 109091 109091 Jan, 2012 0 109091 109091 0 102348 102348 0 171524 171524 0 39915 39915 Feb, 2012 0 39915 39915 0 200736 200736 0 206188 206188 0 34463 34463 March, 2012 0 34463 34463 0 203819 203819 0 199737 199737 0 38545 38545 16 April, 2012 0 38545 38545 0 122369 122369 0 71226 71226 0 89688 89688 May, 2012 0 89688 89688 249 230448 230697 10 168675 168685 239 151461 151700 June, 2012 239 151461 151700 324 258801 259125 342 236485 236827 221 173777 173998 July, 2012 221 173777 173998 328 382384 382712 179 158220 158399 370 397941 398311 Aug, 2012 370 397941 398311 190 474594 474784 379 273893 274272 181 598642 598823 Sept, 2012 181 598642 598823 1443 568124 569567 1160 264446 265606 464 902320 902784 Oct, 2012 464 902320 902784 1412 614478 615890 1791 222700 224491 85 1294098 1294183 Nov, 2012 85 1294098 1294183 1603 392485 394088 1219 132352 133571 469 1554231 1554700 Dec, 2012 469 1554231 1554700 992 382391 383383 1208 273644 274852 253 1662978 1663231 Jan, 2013 253 1662978 1663231 3306 304238 307544 2308 193337 195645 1251 1773879 1775130 Feb, 2013 1251 1773879 1775130 1882 314917 316799 2234 152952 155186 899 1935844 1936743 March, 2013 899 1935844 1936743 2917 268323 271240 3183 427871 431054 633 1776296 1776929 April, 2013 633 1776296 1776929 2444 259299 261743 2217 44459 46676 860 1991136 1991996 May, 2013 860 1991136 1991996 3973 249221 253194 1703 52968 54671 3130 2187389 2190519 June, 2013 3130 2187389 2190519 2802 292928 295730 1479 72486 73965 4453 2407831 2412284 July, 2013 4453 2407831 2412284 17227 462962 480189 2029 161402 163431 19651 2709391 2729042 Aug, 2013 19651 2709391 2729042 12890 488824 501714 2359 40889 43248 30182 3157326 3187508 53982 7121029 7175011 23800 3963703 3987503 Total : Stricter compliance of RPO is recommended. Otherwise the balance between demand and supply is disturbed. Laxity in compliance leads to piling up of REC inventory. This again leads to skepticism in minds of RE project developers who are pondering about setting up plants under RE mechanism. 5. Uncertainty about Length of Control Period and REC price post 2017 A great deal of confusion and wide range of opinions persists when it comes to length of control period. A longer control period will give a sense of security and certainty to developers but at the same time this won’t reflect the reduction in cost due to change in technology. A longer control period should be set, with floor price kept constant over the control period. This will ensure minimum returns to the RE generators, giving certainty. But the forbearance price should be revised from time to time (yearly or once in two years) reflecting the reduction in cost due to improvement in technology. While anticipating his cash flows, the developer should take into account the floor price fixed. Anything above floor price he gets by selling RECs on PEx will be his premium for the risk he has taken. 17 6. Little Participation of Small Voluntary Buyers While the primary goal of the RECs is to address the needs of the compliance market, it can also serve as a useful tool for meeting the ‘green electricity’ needs of the voluntary market. Such applications include participation by corporate as a part of their Corporate Social Responsibility (CSR) and by philanthropic organizations as well as individuals. In 2004, voluntary market in the USA was estimated to account for about 3 million MWh of green electricity with an estimated market value of $ 15–45 million. This is projected to go up to 20 million MWh of green electricity with an estimated market value of $ 100–300 million by 201032. The increase in voluntary demand for RE by residential and commercial consumers in the US is driven by green products offered by utilities and competitive electricity suppliers, and RECs.Refer Table 6. Table 6: Voluntary Purchase of RE by Customer Type in USA S. No. 1 2 3 4 Year Residential (GWh) Commercial (GWh) Total (GWh) Share of Commercial (in %) 2005 3,000 5,500 8,500 65 2006 3,200 8,700 11,900 73 2007 4,500 13,600 18,100 75 2008 5,500 18,8000 24,300 77 Source33 In India REC has found little popularity among voluntary buyers. Only two corporates viz. (POSOCO and Manikaran Power Trading Ltd.) have voluntarily bought RECs from IEX so far.34 Recommendation: Steps should be taken to encourage participation of voluntary buyers. A smaller denomination of REC would enhance market participation and would improve liquidity in the market for RECs. Smaller denominationwill facilitate participation of small buyers as well as small projects across the country.While the compliance market may remain the primary driver for the RECs in India in the initial stage, the scope for voluntary market purchases would remain promising in future. 32 Holt, Ed and Lori Bird (2005).“Emerging Markets for Renewable Energy Certificates: Opportunities and Challenges", Technical Report, NREL/TP-620-37388, National Renewable Energy Laboratory, Colorado. 33 Cook, O. and A. Karelas (2009). Insights into the Renewable Energy Market: A Brief Overview of Procurement Trends, Drivers, and Impacts of Voluntary Commercial Purchasers, Center for Resource Solutions. Francisco, California. 34 Source: List of REC Voluntary Buyers from IEX http://www.iexindia.com/RECApp/RECVoluntaryBuyers.aspx 18 7. Current REC Mechanism doesn’t Incentivise Off-grid installations The present REC mechanism doesn’t benefit off-grid application. As per current CERC REC Regulation the mechanism is only for grid connected plants. Thus the off-grid and small applications like rooftop solar PV cannot avail the benefit from REC mechanism. By leveraging the REC mechanism, solar becomes cost competitive with conventional power production from commercial and industrial segments. REC represents critical source of cash flows for project owners. In several countries like Australia small RE installations are also included in beneficiary list of similar certificate trading schemes. The following figure 2. shows how REC can substantially reduce payback period of small installations. (Source: BRIDGE TO INDIA Financial Model) 19 PROJECT 2: STUDY OF OPPORTUNITY AND OPTIONS TO SUPPLY POWER TO AN UPCOMING MEGA FOOD PARK IN THE STATE OF MADHYA PRADESH. 20 CHAPTER 5: REGULATIONS FOR SPECIAL ECONOMIC ZONE IN M.P. The MADHYA PRADESH ACT No. 23 of 2003 - THE INDORE SPECIAL ECONOMIC ZONE (SPECIAL PROVISIONS) ACT, 2003 gives the following guidelines regarding generation, transmission, distribution, supply, sale and use of electricity in the special economic zones in the state of Madhya Pradesh. The Developer or Co-developer or any other person designated as such by the Development Commissioner shall be deemed to be the Licensee to undertake in the Zone, the activities of transmission, distribution, supply and sale of electricity, with authority to purchase the energy requirements in the Zone from such sources as may be considered appropriate and conducive to the development of the Zone. The Developer or the Co-developer or any other person designated as such by the Development Commissioner shall be deemed to be permitted to generate electricity for the purpose of supplying it within the Zone. The Unit established in the Zone shall be entitled to generate electricity either individually or in association with other Units in the Zone for captive use and consumption of such Unit or Units or sell and supply electricity to other units in the Zone. The tariff terms and conditions of the generation, transmission, distribution, sale, supply and use of electrical energy in the Zone shall be subject to such regulations as may be made by the Development Commissioner. The provisions of levying electricity duty and cess under the Madhya Pradesh Electricity Duty Act 1949 (9 of 1949) and Madhya Pradesh Upkar Adhiniyam 1981 (1 of 1982) shall not be applicable to sale or supply of electricity to the Zone and generation, transmission, distribution and consumption within the Zone. 21 CHAPTER 6: OPPORTUNITY FOR TAKING DISTRIBUTION LICENSE 6.1 Rules and regulations governing obtaining and operating as a distribution licensee 6.1.1 Introduction to Distribution Licensee. According to Electricity act 2003:- "distribution licensee" means a licensee authorized to operate and maintain a distribution system for supplying electricity to the consumers in his area of supply; “ licensee” means a person who has been granted a licensee under section 14; The Appropriate Commission may, on an application made to it under section 15, grant any person license: I. II. to distribute electricity as a distribution licensee; or to undertake trading in electricity as an electricity trader, in any area as may be specified in the license 6.2 Eligibility for obtaining distribution license Section14. (Grant of licensee): The Appropriate Commission may grant a licensee to two or more persons for distribution of electricity through their own distribution system within the same area. Provided also that a distribution licensee shall not require a licensee to undertake trading in electricity. 22 6.3 Procedure for obtaining distribution license Procedure for Grant of License a. Every application under section 14 shall be made in such form and in such manner as may be specified by the Appropriate Commission and shall be accompanied by such fee as may be prescribed. b. Any person who has made an application for grant of licensee shall, within seven days after making such application, publish a notice of his application with such particulars and in such manner as may be specified. c. a licensee shall not be granted until the objections, if any, received by the Appropriate Commission in response to publication before the expiration of thirty days from the date of the publication of the application have been considered by it; d. Where a person makes an application under sub-section (1) of section 14 to act as a licensee, the Appropriate Commission shall, as far as practicable, within ninety days after receipt of such application, I. issue a licensee subject to the provisions of this Act and the rules and regulations made thereunder ; or II. reject the application for reasons to be recorded in writing if such application does not conform to the provisions of this Act or the rules and regulations made thereunder or the provisions of any other law for the time being in force: Provided that no application shall be rejected unless the applicant has been given an opportunity of being heard. e. A licensee shall continue to be in force for a period of twenty- five years unless such licensee is revoked. 6.4 Documents to be accompanied with the licensee application form. 1. Affidavit of the authorized person on non judicial stamp paper of appropriate value. 2. Information relating to existing licensee. 3. Prior experience ( preceding 3 years details for related business) 23 4. Documents related to the status of the applicant:a. Copies of the company’s memorandum /articles of association/ partnership deed/ constitution of society etc. b. Copies of the certificate of registration of company/ society and certificate of commencement of the business. c. Relevant resolution of company / society/ local authority. d. Letter of authority of the board of directors in favor of person applying and signing the application. e. Names and address of the directors with share holding/ financial stake. f. Names of principal share holders/ partners/ members. g. Income tax clearance certificate. 5. Data relating to management and financial capability. A licensee must have sufficient and financial capability to function as a transmission or distribution licensee on a sustainable basis. Documents demonstrating these capabilities shall include: a. Managerial capability 1. Senior management’s CV. 2. Cadre strength for different categories, technical and non technical. b. Financial capability 1. Bank references regarding applicant’s solvency. 2. Most recent balance sheet. 3. Audited accounts of the applicant and it’s holding company, subsidiary or affiliated company for each of the three preceding financial years. 4. Any accompanying notes and certification on the above statements from a reputed chartered accountant. c. Any other document/ evidence to substantiate applicant’s ability to perform functions of distribution of electricity in a sustainable manner. d. Financial details of other business ventures of the applicant. 6. Map of the area of supply. a. Detailed map showing the area of the supply/ transmission as mentioned in the regulation. 24 b. Detailed electrical distribution map (including information on substations and configuration of the system) and geographical map of the proposed area of distribution, drawn to scale. c. The map shall clearly distinguish between the existing and new facilities that shall be required for meeting the obligation to supply. d. The map shall include the streets and roads in which the electricity is distributed. 7. A list of all local authorities vested with the administration of any portion of the area of distribution. 8. A list of protected / reserved forests, sanctuaries and monuments of archeological importance in the proposed area of supply. 9. A list of cantonment, aerodrome, fortress, arsenal, dockyard, or camp or any building or place in occupation of the government for the defense purpose in the proposed area of supply. 10. An appropriate statement describing any lands, which the applicant proposes to acquire for the purpose of the license and the means of such acquisition. 11. Data relating to the applicant’s future business: a. Five year business plan for the distribution of electricity for which the application is being made and funding arrangements for meeting its obligations under proposed license for maintenance, operation, improvement and expansion for future load growth. b. Five year annual forecast of costs, sales and revenues and project financing stating the assumptions underlying the figures provided. c. Details of approach and methodology for setting up the proposed distribution system. 12. Statement of exclusion desired of the general conditions of the license specified by the commission and justification thereof. 13. Proof of payment of application fee. 14. Proof of compliance with such additional requirements as may be prescribed by the central government u/s 14 of the act if license of distribution of electricity has been granted to any other person in the proposed area of supply. a. Capital adequacy 25 b. Credit worthiness c. Code of contact d. Others 15. Copies of agreement for purchase of power, if executed. 16. No objection certificates to distribute or supply in an area from the central government as per section 15(2)(ii) of the electricity act or acknowledgement or the filing of the application with the central government seeking such approvals. 17. Acknowledgement of service of a copy of transmission application to the state transmission utility. 18. Details of assets and facilities required for the business in appropriate format. a. Is the applicant acquiring existing assets or creating new assets? b. For applicants employing other contractors 6.5 Pros and cons of operating as a distribution license at the food park versus other models available The Madhya Pradesh government provides several concessions to the SEZ including the mega food parks as per its SEZ Policy 2003 and Agro and Food Processing Policy 2012. Assistance on power consumption with subsidized rate of INR 1.50 per unit for 5 years subject to a ceiling of 25% of the electric units consumed to Cold Storage, Cold Chamber, Ripening Chamber and Individual Quick Freezing Enterprise -Agro and Food Processing Policy 2012 GoMP through its Ministry of Power will allocate 5MW Power for the SEZ units. A 33KV/11KV sub-station will be constructed to provide uninterrupted & quality power at cheaper rates in the area. - Jabalpur mega food park Other pros and cons for a distribution licensee of a mega food park can be as stated below- 26 Pros: 1. Easy load forecasting. Since a mega food park will consist mostly of industrial and commercial setups, with well known load and time of operation, load forecasting will be easy. Also, seasonal fluctuations in power demand can be predicted according to the harvesting seasons. 2. Easy energy accounting. Fixed number of consumers within the food park will make the energy accounting easy. 3. Less risk of default. Industrial and commercial users pay their bills on time to continue getting uninterrupted power for their processing and other units. Cons: 1. Restriction to load shedding. Industrial and commercial users will expect uninterrupted power supply for their plant machineries to work efficiently. 6.6 Options for procuring or generating power for the mega food park. The options available for the developer of the food park to procure or generate power for the food park can be 1. Generate own power ( coal based, solar, wind or biomass). 2. Purchase from open access/third party/bilateral/power exchange. 3. Combination of the above. 4. PPA(power purchase agreement). 6.6.3 Assessment of solar project for captive power supply at the food park Madhya Pradesh is endowed with high solar radiation with around 300 days of clear sun. Madhya Pradesh offers good sites having potential of more than 5.5 to 5.8kWh/sq m for installation of solar based power projects. 27 Solar project in Madhya Pradesh are governed by Madhya Pradesh Solar Power Policy – 2010. The Madhya Pradesh Urja Vikas Nigam (MPUVN) Limited is the nodal agency for implementation of the Madhya Pradesh Solar Power Policy – 2010. Only new plant and machinery shall be eligible for installation under this policy. Hybrid system shall be allowed as per guidelines of MNRE. Any enterprise willing to establish solar PV/solar thermal projects in MP shall be eligible for incentives under this policy. Eligibility for availing benefits under this scheme shall be based on techno-economical viability and available resources. Captive units will be eligible to get benefits under this policy as an investor/consumer. State Policy Minimum capacity of a grid connected Solar Power Generator (SPG) should be 1 MW each. This project will come under the state policy of Small Solar Power Plants of capacity up to 2MW connected to distribution network (below 33 kV). Evacuation For Solar PV sources, connectivity may be allowed at Low Voltage or 11/33 kV as considered technically suitable by the Distribution Licensee. Generation Generation of the State depends upon the Irradiance at the specific site selected for project. In MP it varies from 5 – 6 kWh / m2 / day. Even if the most conservative approach is chosen 1.5 MUs of Electricity can be generated by a 1 MW Power Project. Tariff 28 The MPERC determines the levelised tariff of Rs. 10.70 per unit for 25 years for sale of electricity from Rooftop PV and other small Solar Power Projects with capacity limited to 2 MW CDM Benefits There is sharing of Clean Development Mechanism benefits and this will be as per the provisions in CERC (Tariff for Renewable Energy Sources) Regulations, 2009 which is mentioned as follows “The CDM benefits should be shared on a gross basis, starting from 100% to developers in the first year after commissioning and thereafter reducing by 10% every year till the sharing becomes equal (50:50) between the developers and the consumers, in the sixth year. Thereafter, the sharing of CDM benefits should remain equal till the time that benefit accrues.” Sale to third party / Captive use. Open Access for Renewable Sources of Energy Renewable Sources of Energy will have Open Access, subject to availability of adequate transmission capacity in Transmission Licensee’s system within the State as per Open Access Regulations The project developer is required to obtain Short / Long Term Open Access permission in case of captive use / third party sale. The open access charges, as applicable and will be levied. In case of sale of power to the Distribution Licensee, such permission is not applicable and is not required to be obtained. In case the point of injection and drawl fall within the jurisdiction of any of the Distribution Licensees involving the transmission network, permission for bulk power transmission is required to be obtained from M.P. Power Transmission Co. by the developer before executing the agreement with M.P. Power Trading Co. and the developer will not be required to execute a separate agreement with M.P. Power Transmission Company Limited. 29 The Distribution Company in whose area the energy is consumed (irrespective of the point of injection) will deduct 2% of the energy injected towards wheeling charges in terms of units. Wheeling charges are not applicable where generation and consumption of energy are at the same premises without involving the licensees system network. Reactive Power Charges The MPERC orders for the charges for KVARh consumption from the grid as 27 paise/unit. Table 7.Benchmark Capital Cost Norm for Solar PV Power Projects for the FY 2013-14 Sr.No. Particulars Capital Cost Norm for % of total cost Solar PV project (Rs. Lakh/MW) 1. PV Modules 344.50 43% 2. Land Cost 16.80 2% 3. Civil and General Works 094.50 12% 4. Mounting Structures 105.00 13% 5. Power Conditioning Unit 060.00 7% 6. Evacuation Cost up to Inter‐ connection 105.00 13% 080.00 10% 805.80 100% Point (Cables and Transformers) 7. Preliminary and Pre‐ Operative Expenses including IDC and contingency 8. Total Capital Cost Benchmark Capital Cost for solar Thermal Power Projects. Considering the expected reduction in cost of thermal power projects globally as well as the tariff quoted by the bidders selected under JNNSM, the Commission proposes the benchmark capital cost of solar thermal project as 1200 Lakh/MW for FY 2013-14. 30 Solar Technology Parks Solar technology parks for generation and manufacturing units in equipment & related ancillaries for solar systems shall be promoted and established at appropriate locations in the state of Madhya Pradesh. The MPUVN shall be the nodal agency for establishing the Solar technology parks. The SME sector will be promoted for manufacture of various components and systems for solar systems. The Solar technology parks will be given preference in land allocation and creating of essential facilities by the state government. Advantages and disadvantages of setting your solar plant in a solar park . Advantages of a solar park 1. Ready to move & start facility for any solar power developer with clear title land. 2. Proper North-South oriented plots to be allotted so as to reduce land wastage, which are ideal for solar plant designing 3. Reduction in time to both start and execute the project. 4. No ROW (right of way) issue will be there for laying of transmission line, which will be done only once and common to all. 5. Ease of work execution and management will be there. 6. Relief from local issues which again will result into time and money saving in project execution. 7. Evacuation from individual project will be done right from the individual plot to the discom’s substation at 132KV level. 8. Reduced transmission losses to the tune of 1/16th of the normal at 33KV. 9. Individual plant metering at pooling substation for ease of billing. 10. Security, preventive maintenance of approach roads & transmission line etc. will be done on periodic basis. 11. Grid down time is also minimum for 132 kV sub-station, which means higher revenue generation. 12. Better financials than in your own lands. 13. Good for High Networth individuals with tax liability. 31 Disadvantages of a solar park - Your project is not in your area or land. 6.6.2 Mechanism of Viability Gap Funding in Phase-II Batch-I of JNNSM The mechanism of operation of Viability Gap Funding shall be as enumerated below: 1) The tariff to be paid to the developer is fixed at Rs.5.45 per kWh. This tariff will remain firm for 25 years project period. In case benefit of accelerated depreciation is availed for a project, the tariff will get reduced by 10% to Rs.4.95 per kWh in line with CERC regulations. 2) The developer will be provided a viability gap fund based on his bid. The upper limit for VGF is 30% of the project cost or Rs.2.5 Cr./MW, whichever is lower. 3) The developer has to put his own equity of at least Rs.1.5 Cr./MW. 4) The remaining amount can be raised as loan from any source by the developer. 5) The VGF when paid by the SECI may be used to return part of the loan or developer contribution (in excess of Rs.1.5 Cr./MW) or a combination thereof as the case may be, in case investments have already been made. SECI will issue a letter confirming release of VGF so that bidder is able to achieve financial closure for full amount if required at the time of signing of PPA. Registration fee For large grid connected solar power projects, along with application, developer shall have to pay @ Rs. 50,000/- per megawatt as non-refundable registration fee. The maximum limit for registration fee shall be Rs 50 lakhs per project. The Board of MPUVN may change the registration fee from time to time. 6.6.3 Criteria a. Financial Criteria :Net Worth:- The Net Worth of the company should be equal to or greater than the value calculated at the rate of Rs 2 Crore or equivalent US$ per MW of the project capacity upto 20 MW. For every MW 32 additional capacity, beyond 20 MW, additional net worth of Rs. 1 crore would need to be demonstrated. The computation of Net Worth shall be based on unconsolidated audited annual accounts of the company. The Company would be required to submit annual audited accounts for the last four financial years However, the Net Worth criteria should be met not more than seven days prior to the date of submission of RfS by the bidding Companies. To demonstrate fulfilment of this criteria, the Company shall submit a certificate from a Chartered Accountant certifying the availability of Net Worth on the date not more than seven days prior to submission of RfS along with a Certified copy of Balance Sheet, Profit & Loss Account, Schedules and cash flow statement supported with bank statement. b. Technical Criteria Under the VGF scheme in Phase II Batch-I of the JNNSM, it is proposed to promote only commercially established and operational technologies to minimize the technology risk and to achieve the commissioning of the Projects. c. Connectivity with the Grid (i) The plant should be designed for inter-connection with the transmission network of STU/CTU or any other transmission utility at voltage level of 33 KV or above. (ii) The responsibility of getting connectivity and open access with the transmission system owned by the STU / CTU or any other transmission utility, as may be required, will lie with the Project Developer. This arrangement would be subject to arrangement of energy accounting with the SLDC. The maintenance of Transmission system upto the inter-connection point shall be the responsibility of the Project Developer. d.Bank Guarantees The Project Developer shall provide the following Bank Guarantees to SECI in a phased manner as follows: • Earnest Money Deposit (EMD) of Rs. 10 Lakh/MW in the form of Bank Guarantee along with RfS. • Performance Bank Guarantee of Rs. 20 Lakh/MW at the time of signing of PPA. 33 In addition to the Performance Bank Guarantee of Rs. 20 Lakh/MW to be provided at the time of signing of PPA, the Bank Guarantee towards EMD will also be converted into Performance Bank Guarantee. The Project Developers are required to sign PPA with State Utilities/Discoms in line with the Timeline given in the guidelines. In case, the Project Developer refuses to execute the PPA within the stipulated time period, the Bank Guarantees towards EMD shall be encashed by SECI as penalty. In case the Project is not selected, SECI shall release the Bank Guarantees within 15 days of the issue of LoI to selected Projects. All the Bank Guarantees shall be valid for a period of 16 months from the date of signing of PPA for the Projects. e.Permits and Licensing Permit and licensing requirements vary, depending on the location of the project but the key permits, licences and agreements typically required for renewable energy projects include: • Land lease contract. • Environmental impact assessment. • Building permit/planning consent. • Grid connection contract. • Power purchase agreement. The authorities, statutory bodies and stakeholders that should be consulted also vary from country to country but will usually include the following organisation types: • Local and/or regional planning authority. • Environmental agencies/departments. • Archaeological agencies/departments. • Civil aviation authorities (if located near an airport). 34 6.6.4 Power projects models for the mega food park. 1. Solar plant models. A solar generator can opt the following models for generation and consumption of solar power within its own area. 1. Solar captive. 2. Pseudo captive solar project. 3. Solar rooftop. 4. Solar thermal plant. 1 mw of solar power plant will need about 5 acres of land. Ideally the land has to be very close to a substation. For a 1 mw plant 11 kva is ok. For each km the substation is away from land, one has to incur about Rs 10 /12 lakhs for laying the transmission lines. Better than that is to buy up the land between your land and the substation. A simple way to determine the approximate ceiling for the solar PV system capacity for all electricity needs is as follows: a. Find out your total monthly electricity consumption. Let’s say it is 100000 kWh b. Divide it by 30 to get an approximate daily consumption. In the example, it is about 3300 kWh. c. Using the thumb rule that 1 W of solar PV can approximately produce 4 Wh of electricity per day, you can determine the approximate maximum solar PV capacity you will require to power all your systems using solar PV. In this case, if the total daily consumption of electricity is 3300 kWh, you will require a maximum of 3300/4 = 825 kw. d. 1 MW can generate approx 1.5- 1.7million units per year. 35 2. APPC plus REC. Solar power can be sold to the state discoms at APPC and RECs can be claimed for the same, which can be traded in the exchange at a price between rs.9.3-12 per unit. The power required can be purchased from the exchange or through a PPA at generally lower rate. Another option for bulk user is to procure power through a power purchase agreement i.e. PPA at preferential tariff as decided by the SERC. 3. Third Party PPA Third Party PPA is a power purchase agreement which a developer can use and claim REC. Third party PPA rec is normally got by government authorized power trading companies. Companies that set up large solar plants of size 10MW and above, can approach these companies to avail the 3rd party PPA for their solar project in Madhya Pradesh. The current third party PPA for solar power doing the rounds in Madhya Pradesh is Rs 4.50 - 5 per unit with 5% escalation once or twice a year. This third party PPA is available for 5 and 10 years tenure. Companies that avail 3rd Party PPA for their solar project in Madhya Pradesh can also avail REC benefit. For small use or to overcome the deficit of power, the power distributor can purchase power through open market i.e. IEX or PXIL at the exchange rate. 4. Biogas. Also since a mega food park have several food processing plants, and they generate huge amount of biodegradable waste, a mega food park can also establish a biogas plant with capacity depending upon the amount of waste generated per day. The biogas plant can be used to generate electricity or can be used as a source of cooking gas for the food processing plants themselves. 36 The table below shows a comparison of different RE sources as per the Madhya Pradesh SERC. Table 8. Solar PV Solar Biogas Wind Exchange 5.64 5.92 2.4(average)-IEX thermal Price/unit 1)10.44 for 2MW and 12.65 (Levelised above 2.0- PXIL tariff) 2)10.70 for less than 2 As on 8.8.13 MW Capital cost 1)8 cr/ MW, (cr/MW) 2)For rooftop and others 13.25 4.63 5.96 Given in table 1. less than 2 MW-10.5 Requirements Registration with IEX and PXIL. 37 CHAPTER 7: SUGGESTIONS AND RECOMMENDATIONS. 1. Solar plant cannot supply power fully to the mega food park. It can only be used as a backup power source during daytime. Therefore for long term procurement of power at a comparatively lower price, a long term PPA is suggested. 2. If the mega food park developer wants to invest in solar power, he can do so in form of captive solar plant. Rooftop installation will make optimum utilization of space. In case of Rooftop PV, cost of land, water facilities, land development, roads, security, illumination, civil structures, initial infrastructure for supply etc. will not be needed , which would results in lower costs in upfront investment. 3. The solar power generated can be sold to the state discoms at tariff decided by the SERC. The generator can get the RECs for the power thus sold and can trade the power in the IEX or PXIL. 4. Pseudo captive solar plant.- available space and rooftops can be leased to a developer for setting up of solar plant. In this case, the food park developer need not require to invest in solar installation and will get the benefit from the rent of land and rooftops. The details of some solar project developers and EPC providers is given below. Table 9:Project Developers s. no. Name of developer Phone no. Email 1. Adani power ltd. 079-25555101 ajaypratap.singh@adanipower.com 2. Azure power 011-49409800 inderpreet@azurepower.com 3. Dalmia solar power ltd. 011-23457100 ramkr.yadav@dalmiacement.com 4. Electrotherm India ltd. 079-66186500 renewable@electrotherm.com 5. Essel Infraprojects ltd. 022-66012323 6. Gadawari Power and Ispat ltd. 0771-40820000 info@gpilindia.in 7. Green infra ltd. 011-49190500 info@greeninfralimited.in 38 8. Inspira projects ltd. 022-67733600 contact@inspiraprojects.com 9. Kishore electro infra private ltd. 040-65440559 Balraj.khatri@kishoreindustries.in 10. Lanco solar private ltd. 0124-4691000 saibaba@lancogroup.com 11. Maharashtra seamless ltd. 0124-4624000 contact@jindalpipe.com 12. Mahindra solar 022-24901441 epc@mahindraepc.com 13. Moser baer solar ltd. 0120-24658001 pvinfo@moserbaer.in 14. Punj Lloyd infrastructure ltd. 0124-2620123 rajatseksaria@punjlloyd.com 15. Tata BP solar india ltd. 080-40702000 amitk@tatabp.com Table 10: EPC Providers and System Integrators s. no. Name of developer Phone no. Email 1. Abener engineering private ltd. 022-66889600 abener@abener.abengoa.com 2. CG Power solutions 022-24237777 info@cgpowersolutions.com 3. Eversun energy private ltd. 080-41209110 marketing@eversunenergy.com 4. Harsha Abacus Solar pvt ltd. 02717-391208 info@harsha-abakus.com 5. Kirloskar brothers ltd. 020-27214444 Sandra.pinto@kbl.co.in 6. Larson & Toubro ltd. 044-22526000 info@lntecc.com 7. Meru energy india pvt ltd. 9711918415 info@meruenergy.com 8. Samved energy systems pvt. Ltd. 020-20270231 samvedenergy@gmail.com 9. Siemens ltd. 022-39677000 10. Solarsis india pvt. Ltd. 040-40484444 info@solarsis.in 39 BIBLIOGRAPHY Reports and Publications 1. “Guide to ELECTRICITY LAWS in India” by Raj Singh Niranjan. 2. “Taxes and incentives for renewable energy” published in June 2012 by KPMG International. 3. “ Solar yearbook and Directory 2013” by India Infrastructure. 4. “RENEWABLES 2012 – Global Status Report” by REN21 5. Solar Radiation Hand Book-2008 of Indian metrology department Websites 1. Ministry Of Power.- http://www.powermin.nic.in/ 2. Ministry of New and Renewable energy.- http://www.mnre.gov.in/ 3. Central Electricity Regulatory Commission.- http://www.cercind.gov.in/ 4. Central Electricity Authority.- http://www.cea.nic.in/ 5. Renewable Energy Certificate Registry of India.- https://www.recregistryindia.in/ 6. Power System Operation Corporation India Ltd.- http://www.nldc.in/ 7. Indian Renewable Agency Development Agency. - http://www.ireda.gov.in/ 40