Optimizing Operations of Finished Water Pumps and Protecting the Distribution System with Transient Modeling 95TH Annual Conference | November 2015 | Raleigh Convention Center, Raleigh, NC Authors Crystal Broadbent, Hazen and Sawyer Kelvin Creech, Town of Cary Michael Wang, Hazen and Sawyer Outline Project Background Surge Modeling Field Work Model Calibration Air Release Valve Analysis Economic Analysis Recommendations Summary Purpose Surge Model used to identify problems affecting operations of finished water pumps, WTP, and distribution system • Optimize operations • Reduce O&M cost • Protect critical infrastructure Background Background Staff suspect finished water pumps were adversely affected by entrained air left in the transmission main • • The WTP: • 40 mgd WTP • 9 finished water pumps • 42-inch transmission main The challenges: • After maintenance, unable to purge all air out of transmission main • High-pitch sound emanating from existing air release valves Surge Model Surge Model 2010 MDD Pumps Operating at MDD • Two 1000 hp Q= 24.3 mgd Pressure = 161.4 psi • One 450 hp High Service Pump Detail High Service Pumps in Surge Model Surge Relief Valve ADAMS Control Valve, typ. FWP-7 FWP-6 FWP-5 FWP-4 FWP-3 FWP-8 42-inch Transmission Line Profile System Profile 500 480 460 Elevation (feet) 440 420 400 380 360 CPZ Zone 340 320 300 0 Pipeline HSP 2000 4000 6000 8000 Distance (feet) 1.0E+4 1.2E+4 1.4E+4 Field Test Field Test – Logger Location Jenks & Apex Hwy 55 Between pumps and ADAMS valves Venturi Vault Green Level Church Rd Field Test • Work performed April 18th, 2013 • Evaluated a series of pump on and off configurations • Pump 6 start • Pump 5 start while Pump 6 operating • Pump 6 off while Pump 5 operating • Pump 3 on while Pump 4 operating • Pump 3 off while Pump 4 operating • Measured pressures at hydrants Pump 6 WTP Meter - Upstream Green Level Hydrant Jenks & 55 Hydrant CPZ Pressure Green Level Vault Pressure Jenks/55 Pressure Jenks/55 Flow CPZ Flow Green Level Vault Flow Pump 6 Start 200 150 100 50 SCADA does not capture the pressure wave 0 25 20 SCADA does not capture the pump start up 15 10 5 0 11:26:01 11:26:44 11:27:27 11:28:11 Time (h:m:s) 11:28:54 11:29:37 Fow (mgd) Pressure (psi) 250 Pump 5 Pump 6 WTP Meter - Upstream Green Level Hydrant Jenks & 55 Hydrant CPZ Pressure Green Level Vault Pressure Jenks/55 Pressure Jenks/55 Flow CPZ Flow Green Level Vault Flow 250 Pump 5 Start Pump 6 Operating 25 psi difference 150 100 A 25 psi difference between Pump 5 and Pump 6 & WTP Meter. This indicates that the ADAMS valve in front of Pump 5 is throttling flow and energy is being consumed. 50 0 25 20 15 10 5 11:40:25 11:40:42 11:41:00 11:41:17 11:41:34 Time (h:m:s) 11:41:51 11:42:09 11:42:26 0 11:42:43 Fow (mgd) Pressure (psi) 200 Pump 5 Pump 6 WTP Meter - Upstream Green Level Hydrant Jenks & 55 Hydrant CPZ Pressure Green Level Vault Pressure Jenks/55 Pressure Jenks/55 Flow CPZ Flow Green Level Vault Flow Pump 6 Off Pump 5 Operating 250 150 100 50 0 25 20 15 10 5 0 11:58:51 11:59:34 12:00:17 12:01:00 Time (h:m:s) 12:01:44 12:02:27 Fow (mgd) Pressure (psi) 200 Pump 3 Pump 4 WTP Meter - Upstream Green Level Hydrant Jenks & 55 Hydrant CPZ Pressure Green Level Vault Pressure Jenks/55 Pressure Jenks/55 Flow CPZ Flow Green Level Vault Flow 250 Pump 3 On Pump 4 Operating 150 100 50 Pressures are the same for Pump 4, Pump 3 and WTP Meter, as would be expected 0 25 20 15 10 5 0 12:27:22 12:28:05 12:28:48 12:29:31 Time (h:m:s) 12:30:14 12:30:58 Fow (mgd) Pressure (psi) 200 Pump 3 Pump 4 WTP Meter - Upstream Green Level Hydrant Jenks & 55 Hydrant CPZ Pressure Green Level Vault Pressure Jenks/55 Pressure Jenks/55 Flow CPZ Flow Green Level Vault Flow 200 150 100 50 0 25 20 29 second closing: 62 psi pressure increase SCADA does not capture the pressure wave 15 10 5 0 12:45:48 12:46:31 12:47:14 12:47:57 Time (h:m:s) 12:48:40 12:49:24 Fow (mgd) Pressure (psi) 250 Pump 3 Off Pump 4 Operating Model Calibration Surge Model Calibration to Field Test Results Analyzed two scenarios Pump 6 on Pump 6 turns off while Pump 5 remains on Graph Field test results: dashed lines Surge model results: solid lines Different color for each location Pump 6 Start Model: WTP Meter Field: WTP Meter Model: Pump 6 Field: Pump 6 Model: Green Level Field: Green Level Model: Jenks & Apex Field: Jenks & Apex 250 Model Matches Loggers 200 Pressure (psi) 150 100 50 0 350 370 390 410 430 450 Time (sec) 470 490 510 530 550 Pump 6 Off Model: WTP Meter Field: WTP Meter Model: Pump 6 Field: Pump 6 Model: Green Level Field: Green Level Model: Jenks & Apex Field: Jenks & Apex 250 Model Matches Loggers 200 Pressure (psi) 150 100 50 0 20 40 60 80 100 120 Time (sec) 140 160 180 200 Air Valve Evaluation Basic Purposes of Air Valves The Basic Premise Allow air and gases to be released from a pipe Allow air into a pipe under negative pressure conditions Behavior of Air “Air & Its Impact on a Water and Wastewater System”, Val-Matic; Air Valves Bulletin 1500; issue 3 volume 52 p 37-44 Installation Guidelines Air valve connection to the pipe needs to be correctly sized and located to capture the small air bubbles as well as larger pockets. For air-release valves this is particularly important, since their function is to release these small bubbles and pockets. Ideal (but not generally practiced in the U.S.): Connection to Pipe (d) Ratio to Pipe Diameter (D): d = D for D ≤ 12 inch d = 0.6D for D inch < D ≤ 60 inch d = 0.35D for > 60 inch Orifice Sizing: Air-release Valve Difficult to predict quantity of air/gases that will come out of solution Assume 2% solubility of air in water under standard conditions Less is known about dissolved air properties in wastewater “Choked orifice,” or “sonic flow” occurs when the ratio of low pressure (absolute) to high pressure (absolute) < 0.528 (for vacuum, avoid internal pressures below -5 psi gauge) Orifice Sizing: Air/Vacuum Valve Pipeline Filling Fill rate 1ft./sec. Exhaust air at a rate = pumping rate or the design fill rate Air enters Orifice (3), travels through the annular space between the cylindrical floats (4), (5), and (6) and the valve Chamber Barrel (2) and discharges from the Large Orifice (1) into atmosphere Typically vented to atmosphere a differential pressure of < 2 psi. Valves with anti-slam or slow-closing may have a differential pressure of 5 psi Orifice Sizing: Air/Vacuum Valve, cont. Pipeline Draining Gravity flow based on pipe slope or drain valve Determine maximum allowable negative pressure (usually -5 psi) Caution Improper design of orifice size for an air/vacuum valve = Release air too fast “air slam” Single stage 2 stage 31 Air Valves for Burst and Draining Each manufacturer uses its own set of calculations and some provide free sizing programs 4” 3” 4” 4” 8” 8” 4” 4” 3” 4” Existing Air Valves are 2 times too Small Velocity: 3-3.3 fps For 42 inch pipe Air Valve size is between a 4 and 6 inch Current Size Air Valves would be for ONLY a 16 to 24 inch pipe Economic Analysis Economic Analysis 1. Evaluated current operations for taking 42” offline and returning it to service 2. Determined effectiveness of existing air valves 3. Using model and field test • Determined existing restrictions in 42” transmission main • Energy cost due to restrictions in 42” transmission main Current 42” Operation Normally: 42” feeds CPZ (641’); 30” feeds WPZ (540’) Taking out of service Operate valves to switch 30” from WPZ to CPZ Drain 42” through blow off valves Supply WPZ through PRVs from CPZ Supply CPZ using 3 WPZ pumps 400hp; 5.5 mgd @ 305 ft 1 Swing pump 1000 hp; 9 mgd @ 450 ft Supplement with Durham water Placing back into service 24-72 hrs to refill 42” Main Refill from NC 55 & Old Jenks Rd 30” Main still providing supply to CPZ Operate valves to switch 30” from CPZ to WPZ Flush through hydrants Return 42” Main to service Hydraulic Model Analysis* Evaluating 30” TM Supplying WPZ (typical operation) Supplying CPZ (when 42” offline) Average Day Demand for WPZ: 3.4 mgd Average Day Demand CPZ: 16.2 mgd 1 WPZ Pump: 3 hrs a day 6.3 MGD @ 271 ft; 78% Calculated HP: 384 Davis Drive & Waldo Rood Blvd PRV between CPZ and WPZ 2.7 mgd Setting 78 psi * hydraulic model received from CH2M’s Swing Pump: operates 2 to 3 times a day: ~ 14hrs each day 9.6 MGD @ 424 ft; 85% Calculated HP: 840 WPZ Pumps operating: 1, 2 and 9 – operates continuously Each: 4.2 mgd @ 380 ft; 78% Calculated HP: 359 per pump Together, the WPZ pumps and swing pump can continue to meet average day demands WPZ Pump Pumping to CPZ Pumping to WPZ Cost Difference Between Supplying CPZ with 42” vs. 30”: Average Day Demand 42” Supply CPZ Pump 3: 384 hp, 8.4hrs/day, 30days/month Pump 5: 835 hp, 9.4hrs/day, 30days/month; 827 hp, 14.6hrs/day, 30days/month Pump 6: 835 hp, 9.4hrs/day, 30days/month Total : 720,000 kwh/month 30” Supply CPZ 3 WPZ pumps each: 359hp, 24hrs/day, 30days/month Swing Pump: 840 hp, 14hrs/day, 30days/month Total : 841,000 kwh/month Difference 121,000 kwh/month kWh cost $0.0535/kwh for all over 140,000 kWh per month, per kWh (duke energy) Cost for using 30” verses 42” to supply CPZ $1,600 cost/week $6,500 cost/month Effectiveness of Existing Air Valves Cumulative Volume from Air Valves: Power Loss Simulation 90 Proposed Air Valves Existing Air Valves 80 70 Positive slope: The rate air is entering air valves 60 Volume (cf) Surge model power loss result: Existing valves let in a greater volume of air and take longer to expel it than the proposed valves. Negative slope: The rate air is being expelled through the air valves 50 40 30 Larger volume of air is directly proportional to the headloss. 20 10 0 0 10 20 30 40 50 60 70 80 Time (seconds) 90 100 110 120 130 140 Comparing Field Test to Model Field – Pump 6 ModelWithout Restrictions Flow, mgd 10.75 10.75* Discharge Pressure, psi 148 140 Discharge HGL, ft 656 637 Suction HGL Range, ft 290 290 TDH, ft 366 347 Efficiency, % 80 80 Calculated HP 862 818 * Forcing the model to provide the exact flow as the field test Pumps are operating below the 20.2 inch impeller curve (shown in the next slides) Pump 6 Field Test Model 42" Transmission Main - HGL Field Test at 10.75mgd Pump at 10.75mgd 660 Model with Restrictions Elevation Possible Restrictions: Throttled valve Air pocket Corrosion buildup* Biofilm* *City staff confirmed this is not the case HGL, ft 650 640 630 450 350 250 0 1000 2000 3000 4000 5000 6000 7000 8000 Distance, ft 9000 10000 11000 12000 13000 14000 15000 Ground Elevation, ft 550 Reduction of Pump Capacity – Air Pocket Air pockets in the pipeline add additional head loss and restrict flow Head loss is directly proportional to the size of air pocket As high as 16% additional head loss Extremely difficult to predict exact head loss Determine entrained air by comparing the design capacity and actual capacity Another way is to determine the actual friction value through field work and then recalculate capacity with new friction value to see if entrained air is an issue S J van Vuuren, M van Dijka and J N Steenkamp, Quantifying the Influence of Air on the Capacity of Large Diameter Water Pipelines and Developing Provisional Guidelines for Effective De-aeration. WRC Report No. 1177/2/03 Potential Energy Savings: One Pump Evaluation 862 hp, 24hrs/day, 30days/month 818 hp, 24hrs/day, 30days/month 24,000 kwh/month difference 463,000 kwh/month 439,000 kwh/month Savings Field Test Model with No Restrictions $15,400 saving/yr Difference Recommendation Suggested Sizing for 15 and 20 MGD from Manufacture Software 3”/6” & 3” 4” 4” 4” 8” 8” 4” 4” 4” 3” New Locations Hazen Recommendation Remains the same 4” 4” 4” 6” 6” 4” 3” 4” 3” New Locations Various Construction Cost Estimate for Valve Upgrade Item Description Total Cost Tee Connection (42”x20”) $110,000 Tapping Saddle (42” x 12”) $18,000 Existing Tapping Saddle (42”x8”) $13,000 Air Valve New Manhole Tee (42”x20”) $120,000 New Manhole Tapping Saddle (42” x 12”) $29,000 Recommended Modifying Pump Control Valves Replace Actuators More control of open/close times Reduce operational cost by removing headloss through malfunctioning valve ADAMS Valve 50 Summary Summary Calibrated Surge Model Optimized Operations Improved Air Release Protected Critical Infrastructure Reduces O&M Cost 52