Welcome to Presentation on Dedicated Freight Corridors – Geotechnical Considerations in Design and Construction by – Nand Kishore, RDSO, LKO Foundation Day Celebrations of IRICEN, Pune on 20.03.2006 1 INTRODUCTION • Quantum jump in originating Railway freight traffic from 390 million ton in 2001-02 to 602 million ton in 2004-05. • Indian Railway is facing challenge to increase throughput commensurate with high growth in GDP of 8.5 %. • Railway has taken up a ‘Mission 700’ to carry 700 million ton of traffic. For this, dedicated freight corridors are to be constructed. • Dedicated Freight Corridors need to be designed and constructed for specific requirements of axle load, speed and GMT. 2 GEOTECHNICAL ASPECTS • A sound and stable formation plays a vital role in overall performance of track. • Earlier, tracks were constructed without any geo-technical considerations which served the purpose for lighter axle load & slow speed traffic. • With increase in axle load and speed of freight traffic, considerable length of track has developed weak/unstable formation in due course of time. • Permanent as well as temporary speed restrictions exist over a length of about 650 km and 2000 km respectively on account of weak formations. • With further increase of heavier axle loads, high speed & GMT, length of weak formation is likely to increase many fold. 3 LOSSES DUE TO WEAK FORMATION Direct losses: • Frequent track attention • Additional manpower • Heavy loss of ballast due to puncturing • Accelerated shallow & deep screening due to mud pumping etc. • Reduced life of track structures viz. rails, sleepers, fastenings etc. Indirect losses: • Excess fuel consumption • Safety hazard • Reduction in line capacity • Extra supervision • Wear and tear of rolling stock • Social cost: increased travel time, passenger discomfort, railway’s image, pollution. 4 COST IMPLICATIONS OF WEAK FORMATION Additional recurring expenditure on unstable formation per year /km track maintenance due to • Cost of additional maintenance : Rs. 4.00 lakh • Cost of premature track renewal : Rs. 1.50 lakh • Cost of addl. deep screening : Rs. 0.11 lakh Total Rs. 5.61 lakh • Cost on account of ballast penetration (once during life cycle of track) = 0.7 x1 .0 x 3.5 x 500 = Rs12.25 lakh/km • Cost of blanketing using Al Girder in SC Rly in 1999 - Rs 31.38 lakh/km. • Therefore, cost of rehabilitation gets recovered in about 4 to 5 years. • Rehabilitation of weak formation is costly as well as difficult. • For DFC, strong and durable formation is required from beginning to avoid rehabilitation later on. Adequate efforts are required to design and construct the formation. 5 GEOTECHNICAL REQUIREMENTS • Formation is a permanent asset and can not be replaced & difficult to upgrade. • It should be designed for traffic requirements of very long duration say 50 to 100 years. • IR decided to introduced CC+8+2 T for BOXN in selected iron ore routes. • In future, 30 t axle load is planned to be introduced. • Keeping in view of future developments, the design of formation for DFC should be done for 30 t axle load, 100 kmph speed and 35 to 50 GMT . 6 UIC DESIGN OF FORMATION FOR HIGH AXLE LOAD • Design of formation mainly include thickness of track bed layer i.e. ballast and blanket layer. • As per UIC code 719 R, 1994 minimum thickness (e) of track bed is given by e=E+a+b+c+d+f+g, 7 UIC DESIGN OF FORMATION FOR HIGH AXLE LOAD Where, • e = Total depth of ballast & blanket in meter • E= Bearing capacity factors based on class of soil • a= Factor depending on UIC group of routes based on GMT • b= Factor depending on type of sleeper • c= Factor depending on different working conditions on existing lines • d= Factor depending on axle load of hauled vehicle • f= Factor depend on speed of train • g= Factor depend on inclusion of geo-textile based on quality class of prepared sub-grade. The values of the above factors are given in the UIC-719R, 1994 code. 8 Provision of ballast & blanket thickness as per UIC code S. No Soil as per IS classificati on Quality class of the soil as per UIC code Thickness of prepared subgrade of QS3 class soil (GW, SW, GP & SP) For 22.5t For 25t For 30t (extrapolated) 1 GW QS3 NIL 8cm 15cm 35cm 2 SW QS3 NIL 8cm 15cm 35cm 3 GP QS3 NIL 8cm 15cm 35cm 4 SP QS3 NIL 8cm 15cm 35cm 5 GM QS1 0.50m 53cm 65cm 85cm 6 GM-GC QS2 0.35m 43cm 50cm 70cm 7 GC QS1 0.50m 53cm 65cm 85cm 8 SM QS1 0.50m 53cm 65cm 85cm 9 SC QS1 0.50m 53cm 65cm 85cm 10 SM-SC QS2 0.35m 43cm 50cm 70cm 11 ML-CL QS1 0.50m 53cm 65cm 85cm 12 ML QS1 0.50m 53cm 65cm 85cm 13 CL QS1 0.50m 53cm 65cm 85cm 14 MI QS1 0.50m 53cm 65cm 85cm 15 CI QS1 0.50m 53cm 65cm 85cm Note: 1. QS1 and QS2 require provision of geo-textile in addition to blanket layer. 9 2. QS3 class of soil used in prepared subgrade is almost similar to blanket material. STUDY OF FORMATION STRESSES ON TEST TRACK PANEL In January 1999, RDSO had conducted a simulated study to assess vertical stress distribution in Railway formation on full scale test track panel in TM Dte. 10 OBSERVATIONS IN TRACK PANEL STUDY Longitudinal variation of stress in formation – Effect of axle load is felt upto 4th sleepers on either side from the loading sleeper. 11 OBSERVATIONS IN TRACK PANEL STUDY Variation of stress with axle load at 60 cm depth – Vertical stresses at a depth increases linearly with axle load. 12 OBSERVATIONS IN TRACK PANEL STUDY Variation of induced stress with depth & axle load – Variation of Stress beyond 1.3 m is nominal with axle load. 13 . Conclusions of the track panel study • Induced stresses inside formation increase linearly with increase in axle load and reduce with depth. However, below one meter depth, induced stress varies only nominally with increase in axle load. • Subgrade soil in top one meter layer of railway formation truly governs its axle load carrying capacity. Therefore, to strengthen the existing formation for introduction of heavier axle loads, soil in this portion is to be replaced with proper blanket material. • Reinforcement of blanket layer with bi- axially oriented geogrid can substantially reduce stresses on subgrade soil thereby reducing depth of blanket layer required. 14 Existing Provisions in Guidelines of Earthwork for higher axle load • • • • • No blanket on rocky subgrade, GW, SW soils 45 cm thick blanket for GP, SP, GM & GM-GC soils 60 cm thick blanket for GC, SC, SM, SM-SC 100 cm CL, ML, CI, MI, CL-ML soils CH, MH soils – Unsuitable for use in top 3 m of bank • For heavier axle load traffic above 22.5t and upto 25t & above 25t upto 30t, additional blanket thickness of 30cm & 45cm respectively, over and above as given above of superior quality material, shown as upper blanket layer in enveloping curves. 15 16 GENERAL DESIGN CONSIDERATIONS • Adequate soil survey & exploration should be done for deciding the alignment for freight corridor to avoid troublesome spots, unstable hill slopes, swampy & soft soils, peat lands, etc. • Ground improvement and slope stabilization measures etc. may be planned in advance for troublesome spots. • Adequate thickness of blanket with or without geogrids based on soil type, axle load, speed, GMT to be provided. • Side slopes of embankment/cuttings should be designed with realistic soil parameters and drainage conditions using standard methods of slope stability analysis/ software rather than adopting thumb rules. 17 GENERAL DESIGN CONSIDERATIONS Contd… It is desirable to increase formation width of BG embankment for proposed DFC say upto 8.5 m for ballast side slope of 2 H:1 V and cess width of 120 cm against existing 6.85 m width & ballast slope of 1 H:1 V and cess width of 90 cm. Drainage Improvement • Water is the enemy of soil and poor drainage is most of the time the main cause of trouble in formation. • Adequate cross-slope should be provided at the subgrade top • In cuttings, adequate catch water drains and side drains should be planned. 18 GE CONSIDERATIONS IN CONSTRUCTION OF DFC Construction Material: • Unsuitable soils such as CH, MH, organic soils etc. should not be used in construction of embankment. • If bank has to be constructed with cohesive subgrade, sandwich construction (provision of intermediate sand layers ) may be adopted. • If suitable blanket material is not available naturally, mechanized production of blanket material should be planned. Details of mechanical production given in RDSO document GE: IRS-2, July 2005. 19 GE CONSIDERATIONS IN CONSTRUCTION OF DFC • • • • • Construction Machinery: Manual methods of construction cannot achieve the desired quality and progress of earthwork. Modern construction equipments viz. vibratory rollers, earthmover, motor graders, scraper, dumpers, mobile water sprinklers, etc. should be deployed. For construction of formation over soft soil, methods such as stage construction, pre - loading, sand drains, prefabricated vertical PVC drains may be used for expediting consolidation. For monitoring quality of construction, a well equipped & properly manned GE laboratory should be established in field. It would be desirable to have separate staff for quality control from those involved in construction. 20 GE CONSIDERATIONS IN CONSTRUCTION OF DFC • Rate of earthwork paid in railways is generally much less vis-a-vis other organizations such as NHAI, CPWD etc. while rate of blanket material is comparatively higher. • It is very difficult to achieve desirable quality of earthwork at low rate of earthwork. • Detailed realistic analysis of earthwork commensurate with the desired quality of earthwork including quality control set up etc. is required to be done. 21 CONSIDERATIONS FOR DFC ON EXISTING TRACK • Before introduction of higher axle load, it is necessary to investigate the condition of existing formation and rehabilitate & strengthen weak formation. • Methods of rehabilitation tried in past such as lime treatment, ballast piling, cement grouting, vinyl drains, open cross drains filled with coarse grained material, sall balli/ sleeper/ rail piling, layer of laterite block, polyethylene etc. have not shown the desired improvement. • Provision of blanket in full width of formation is proven solution for rehabilitating weak formation the world over. Geo-grid can also be provided to reduce the thickness of blanket. • General drainage arrangement of embankment/cuttings should be improved by providing cross drains, side drains, catch water drains etc. 22 CONSIDERATIONS FOR DFC ON EXISTING TRACK • Various methods for provision of blanket on existing track are detailed in RDSO report No. GE-39, March2003. These are: - With Aluminium Alloy Girder - Track Dismantling Method - With manually operated portals - With CC crib & rail clusters (SE Railway Method) - With rail Clusters (Eastern Railway Method) - Lifting of track with deep screening - Fully mechanized methods – Formation Rehabilitation Train • Choice of method depends on several factors like extent of problem, projected traffic, axle loads, availability of traffic blocks, accessibility of site, availability of labour and material etc. • Formation rehabilitation train is commonly being used 23 in foreign railways. It requires long block (about 8 hrs). CONCLUSIONS • To meet growing need of freight traffic, it is imperative to construct dedicated freight corridors. • These freight corridors must be designed for heavy axle load, higher speed & high GMT keeping in view of future traffic demands. • Construction of freight corridors will require use of modern machineries, strict quality control in execution of earthwork & blanketing and proper drainage. • Ground improvement in case of soft subsoil will have to be ensured for construction of new dedicated freight corridors. • Existing track, if planned to be used as dedicated freight corridor, will require to be investigated & strengthened by providing adequate thickness of blanket by any 24 suggested methods. 25