MPR – May 2014 NATIONAL HIGHWAY AUTHORITY OF INDIA (MINISTRY OF ROAD TRANSPORT & HIGHWAYS) Rehabilitation, Strengthening and Four Laning of Srinagar to Banihal Section from Km 187.000 to 189.350 (Banihal Bypass) and Km 220.700 to 286.110 of NH 1-A in the State of Jammu & Kashmir (Package No. NHDP–Phase-II/BOT/I/J&K). Monthly Progress Report for the Month of May’2014 Employer : National Highways Authority of India Independent Consultant : Nicholas O’ Dwyer & Company Ltd – SA Infrastructure Pvt .Ltd in association with VKS Infratech Management Pvt. Ltd. (Placed in the month of March 2012). Concessionaire : Srinagar Banihal Expressway Limited. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 1 MPR – May 2014 TITLE: MPR May’ 2014 (Chainage –187+000 to 189+350, 220+700 to 286+110) INDEPENDENT ENGINEER: Nicholas O’ Dwyer & Company Ltd – SA Infrastructure Pvt .Ltd in association with VKS Infratech Management Pvt. Ltd. (Placed in the month of March 2012). CONCESSIONAIRE: Srinagar Banihal Expressway Limited .- SPV CONTRACTOR: RAMKY INFRASTRUCTURE LIMITED Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 2 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project NH-1A Monthly Report Index May – 2014 Sr. No 01 02 03 04 05 06 07 08 09 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 DESCRIPTION Cover Sheet Title Index Description of Project Project Alignment Organization Chart SPV & PMC Organization Chart EPC Mobilization Report Logistics Material Resource Report Methodology Statement & Source Approval Letters Status of Change or Variations Status of Stretches Approvals and Permits Status of Road & Structure Works Progress of Roads Works & Structures Works (S-Curve) Major Correspondences from SBEL Site Progress Photographs Annexure – I (Strip Plan) + IPC Status Annexure – II (Land Acquisition Strip Chart) Annexure – III (Land Acquisition Status) Annexure – IV (Strip Chart Highway) Annexure –V (Structure Status) Annexure – VI( QA QC Report) + (Weather Report) Annexure – VII(Mobilization of Man Power & Mobilization of Equipments ) Annexure – VIII(Drawing Status ) Annexure – IX(Targets V/S Achieved ) +Achievements PAGE 1 3 3 4 11 14 15 16 17 31 33 33 34 37 38 40 41 43 - Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 3 MPR – May 2014 1. 1.0 DESCRIPTION OF THE PROJECT: INTRODUCTION: This is the Progress Report for the month of May’ 2014 being submitted by the Concessionaire’s office which reflects the on-site progress and Executive summary of general information about the project is furnished hereunder. 1.1 Description of the Project The contract package Srinagar Banihal Road Project involves four laning and strengthening of the Existing National Highway NH- 1A between Srinagar and Banihal – Km 187+000 to 189+350 & 220+700 to 286+110. 1.2. Executive Summary: In the 67.76 km stretch of the road project SBEL has constructed 5 no’s of Camps namely Camp-I (Banihal) at chainage 188+000 Km, Camp-II (Vessu) at chainage 234+200 km, Camp-III (Samthan) at chainage 249+800Km , Camp-IV (Lethpora) at chainage 270+900 Km and Camp-V (Lasjan) at chainage 282+500 Km. Apart from the camps mentioned above SBEL has also constructed a Steel Yard at chainage 252+980 Km, as shown in the attached Logistic Plan. At these camps SBEL has operated with 2 no’s of Hot mix Plants, 5 no’s of Batching Plants, 4 no’s of Crushers and 3 no’s of Wet mix Plants. All the crushers are functional; also 3 numbers of Batching Plants are functional. Other than plants, Office buildings, Lab, Staff Quarters, Labour Hutments, Security Sheds, Workshops and Cement Stores etc have also been constructed in all the camps. Pre-Cast yard has also been established at the Samthan Camp and functional, where pre-casting of 230 cells of Box Culverts are completed In Structure Works, SBEL has completed works on 80 no’s culverts on both Sides. Apart from the above mentioned completed culverts, work on 55 no’s culverts are in progress. Work is also being executed on 6 no’s of VUP’s, 4 no’s PUP’s, 5 no’s Major Bridges and 4 no’s Minor Bridges and 1 no Fly-over. The detailed progress is elaborated in tabular form of physical program chart. In Highway Works SBEL has executed 39.5 lac Cum of earthwork. Other than earthwork SBEL has also executed approximately 1.92 lac Cum of GSB work, 1.43 lac Cum of WMM and 35000 Cum of DBM. The detailed progress is elaborated in tabular form of physical program chart. Apart from the permanent work Concessionaire has done the maintenance of Existing road in the month of April & May 2014 from Panth Chowk, Srinagar up to Qazugund Starting Chainage i.e 220+700. Including the Banihal Bye Pass i.e from Ch. 187+000 to 189+350. Concessionaire had executed the test of PFVD (Prefabricated Vertical Drain) at external laboratory for ground improvement where the high embankment exists and the test report of the same had submitted vide their office letter number RIL/SBEL/IE/NH-1A/2013/354 dated 22nd Jan 2013 & RIL/SBEL/IE/NH-1A/2013/371 dated 02nd Feb 2013 The agency Tech Feb had already execute the work. The Concessionaire has requested vide their office letter number RIL/SBEL/IE/NH-1A/11-12/88 dated 17th Aug 2012, RIL/SBEL/IE/NH-1A/11-12/57 dated 12th July 2012 & RIL/SBEL/IE/NH1A/11-12/76 dated 08th Aug 2012 to approve Shyam Steel for their permanent work against which the approval is still pending. The Concessionaire has requested vide their office letter number RIL/SBEL/IE/NH-1A/12-13/386 dated 21st Feb 2013 to approve TCI Max Cement for their permanent work against which the approval is still pending. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 4 MPR – May 2014 The Concessionaire has given proposal of via duct for Banihal Section from Km 187+000 to 189+350 vide their office letter number RIL/SBEL/IE/NH-1A/12-13/388 dated 25th Feb 2013 against which the approval is still pending. The Concessionaire had also submitted 3 (Three) sets of video recording for quarter ending 1st Oct. 2012 to 31st Dec 2012. vide their office letter number RIL/SBEL/NH-1A/12-13/340 dated 20th Feb 2013. The Concessionaire has mobilised additional manpower and resources to expedite the progress of work and the same has been communicated vide their office letter number RIL/SBEL/IE/NH1A/2013/393 dated 26th Feb 2013. The concessionaire has been executing the work of PFVD in section – III over the new alignment. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH1-A/2013/347 dated 2nd March 2013 regarding the non availability of 100% land as per Article 10 and clause 37.2.1 (a) becomes default of Authority as per Concession Agreement which got Material Adverse effect on the Concessionaires. The Concessionaire intimated to authority vide their office letter number RIL/SBEL/NH1-A/2013/353 dated 8th March 2013 regarding the month wise stretches made available by the client and the status of land Acquisition as on 28.02.2013. The Concessionaire once again intimated to authority vide their office letters number RIL/SBEL/NH1-A/2013/356 dated 11th March 2013 and RIL/SBEL/NH-1A/2013/358 dated 16th March 2013 regarding the achievement of mile stone- I and status of land acquisition. The Concessionaire intimated to authority vide their office letters number RIL/SBEL/NH1A/2013/359 & 360 dated 16th March 2013 regarding the Force Majeure (Curfew in Valley of Kashmir) due to militant attack and death of Army Jawans on 13th March 2013 and subsequent curfew in the valley and strike called by Hurriyat Conference on 13th March 2013. The Concessionaire intimated to authority vide their office letters number RIL/SBEL/NH1A/2013/362 dated 19th March 2013 regarding the Force Majeure (Sabotage at Samthan Camp) located at Km 249+700 mentioned that stone pelting on 6th March 2013 by unknown mob of around 30-35 people and consequences due to which 75 of our staff including 25 Engineers left the place and the progress of the work effected badly. The Concessionaire intimated to authority vide their office letters number RIL/SBEL/NH1A/2013/363 dated 19th March 2013 regarding the Force Majeure (Curfew in Kashmir) against the death of boy belongs to Baramullah district. Under the prevailing circumstances even the internet services were barred and SBEL was forced to stop the work. The Concessionaire intimated to authority vide their office letters number RIL/SBEL/NH1A/2013/372 dated 31st March 2013 regarding the Force Majeure (Strike called by MMM demanding the body of Afzal Guru) against the Afzal Guru’s body on 28th March 2013. Under the prevailing circumstances even the internet services were barred and SBEL was forced to stop the work. The Concessionaire intimated to Authority vide their office letter number RIL/SBEL/NH-1A/2013/373 dated 30th March 2013 regarding the additional structures required which are missing from schedule ‘B’ of Concession Agreement. The Concessionaire intimated to I.E vide their office letter number RIL/SBEL/I.E/NH-1A/2013/429 dated 1st June 2013 regarding the Month wise working stretches available and status of land acquisition as on 31.03.13. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 5 MPR – May 2014 The Concessionaire intimated to I.E vide their office letter number RIL/SBEL/I.E/NH-1A/2013/432 dated 1st June 2013 regarding the Force Majeure (Sabotage at Samthan Camp & Curfew in Kashmir Valley). The Concessionaire intimated to I.E vide their office letter number RIL/SBEL/I.E/NH-1A/2013/451 dated 9th June 2013 regarding the Submission of Sub Soil Investigation reports of 58 Location for High Embankment. The Concessionaire intimated to Authority vide their office letter number RIL/SBEL/NH-1A/2013/378 dated 6th June 2013, RIL/SBEL/NH-1A/2013/386 dated 13th June 2013 & RIL/SBEL/NH1A/2013/393 dated 30th June 2013 regarding the Entry Tax Exemption for the equipments bringing for this project. The Concessionaire intimated to Authority vide their office letter number RIL/SBEL/NH-1A/2013/380 dated 8th June 2013 regarding the Land Acquisition status both for Pulwama & Anantnag District. RIL/SBEL/NH-1A/2013/297 dated 29th June 2013 regarding the Land Acquisition status for Banihal District. The Concessionaire intimated to Authority vide their office letter number RIL/SBEL/NH-1A/2013/381 dated 8th June 2013 regarding the work stopped by the Land Owner at Banihal because the compensation against the land and structures not yet received by the land owners. The Concessionaire intimated to Authority vide their office letter number RIL/SBEL/NH-1A/2013/385 dated 10th June 2013 regarding the Project Milestones and shifting of appointed date under clause 47.10 of Concession Agreement. The Concessionaire intimated to Authority vide their office letter number RIL/SBEL/NH-1A/2013/382 dated 09th June 2013 & RIL/SBEL/NH-1A/2013/388 dated 13th June 2013 regarding the Quarry on Strike. The Concessionaire intimated to I.E vide their office letter number RIL/SBEL/I.E/NH-1A/2013/457 dated 16th June 2013 regarding the 03 (Three) sets of Video Recording for Quarter 01.01.2013 to 31.03.2013. The Concessionaire intimated to I.E vide their office letter number RIL/SBEL/I.E/NH-1A/2013/459 dated 20th June 2013 regarding the Selection for type of Well/Pile foundation. The Concessionaire intimated to I.E vide their office letter number RIL/SBEL/I.E/NH-1A/2013/472 dated 25th June 2013 regarding the Submission of method statement for Mackintosh Probe Test. The Concessionaire intimated to Authority vide their office letter number RIL/SBEL/NH-1A/2013/394 dated 25th June 2013 regarding the stoppage of work by villagers of Bumthan & Jadur villages between Km 236+500 to 237+500 (Force Majeure). The Concessionaire intimated to I.E vide their office letter number RIL/SBEL/NH-1A/2013/473 dated 27th June 2013 regarding the Snow Fall Accumulation Depth. The Concessionaire submitted mix design of DBM – Grading II Zewan Quarry vide their office letter number RIL/SBEL/NH-1A/2013/542 dated 29th June 2013. The Concessionaire submitted the details of machineries & equipments deployed at site against which the entry tax exemption got obtained vide their office letter number RIL/SBEL/NH-1A/1314/429 dated 01st June 2013. The Concessionaire submitted month wise land acquisition details to Authority vide their office letter number RIL/SBEL/NH-1A/2013/434 dated 01st June 2013. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 6 MPR – May 2014 The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/441 dated 09th June 2013 regarding the Force Majeure at Banihal Section. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/442 dated 09th June 2013 regarding the Force Majeure at Lasjan Camp. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/443 dated 09th June 2013 regarding the Force Majeure (243+900 to 244+100, Qazigund). The Concessionaire informed Authority regarding the status of land acquisition at Banihal vide their office letter number RIL/SBEL/NH-1A/2013/446 dated 13th June 2013. The Concessionaire informed Authority regarding the disbursement of compensation and Land Acquisition issues at Banihal Bye Pass (Km 187+000 to 189+350) vide their office letter number RIL/SBEL/NH-1A/2013/449 dated 16th June 2013. The Concessionaire informed Authority regarding the additional land required for Weigh Bridge for Toll Plaza vide their office letter number RIL/SBEL/NH-1A/2013/454 dated 23rd June 2013. The Concessionaire informed Authority regarding the dismantling and shifting of Police Lines shed at Km272+820 with in toe vide their office letter number RIL/SBEL/NH-1A/2013/458 dated 26th June 2013. The Concessionaire informed Authority regarding the dismal progress on National Highways (Four Lanning) Project in District Pulwama, where in a land made available in bits and pieces to Concessionaire vide their office letter number RIL/SBEL/NH-1A/2013/460 dated 26th June 2013. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/462 dated 30th June 2013 regarding the Force Majeure due to stoppage of works on the Highway for Security reason during the visit of Hon’ble Prime Minister to Kashmir Valley on 25 th & 26th June 2013. The Concessionaire intimated Independent Engineer vide their office letter number RIL/SBEL/NH1A/2013/547 & 570 dated 1st June 2013 & 13th June 2013 regarding the Construction of Project Highway “Banihal Section” Ch. 187+000 to 189+350. The Concessionaire Submitted Mix designs of DBM- Grade – I Zewan Quarry vide their office letter number RIL/SBEL/NH-1A/2013/565 dated 12th June 2013. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/572 dated 15th June 2013 regarding the Force Majeure due to unseasonal rain fall. The Concessionaire Submitted test results of Granular Sub Base material (Navayuga Tunnel Muck/Qazigund Screening Plant vide their office letter number RIL/SBEL/NH-1A/2013/580 dated 16th June 2013. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/601 dated 26th June 2013 regarding the Force Majeure due to unseasonal rain fall. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/602 dated 26th June 2013 regarding the Project Mile stone - I. The Concessionaire informed Authority regarding the non availability of land acquisition at Major Structures vide their office letter number RIL/SBEL/NH-1A/2013/603 dated 26th June 2013. The Concessionaire Submitted mix designs for all grades of concrete being used in our project with Vikram Premium & ACC OPC – 43 grades vide their office letter number RIL/SBEL/NH1A/2013/630 dated 3rd July 2013 & RIL/SBEL/NH-1A/2013/631 dated 3rd July 2013 respectively. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 7 MPR – May 2014 The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/632 dated 6th July 2013 regarding the review of designs. The Concessionaire informed Authority regarding the work could not get done on 9th & 10th July 2013 because of unseasonal rain fall vide their office letter number RIL/SBEL/NH-1A/2013/635 dated 10th July 2013. The Concessionaire Submitted the TCI Max Cement test report vide their office letter number RIL/SBEL/NH-1A/2013/638 dated 13th July 2013. The Concessionaire Submitted the Petrography test report from Zewan Quarry and Navayuga Tunnel rock vide their office letter number RIL/SBEL/NH-1A/2013/640 dated 13th July 2013. The Concessionaire Submitted the inclusion of material in RC list vide their office letter number RIL/SBEL/NH-1A/2013/647 dated 18th July 2013. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/649 dated 22nd July 2013 regarding the Force Majeure due to Curfew in the Valley on 22nd July 2013. The Concessionaire Submitted approval letters to the authority regarding the use of Shyam Steel vide their office letter number RIL/SBEL/NH-1A/2013/466 dated 07th July 2013. The Concessionaire intimated the authority regarding the additional Hume Pipes Culverts to be provided for Irrigation purpose vide their office letter number RIL/SBEL/NH-1A/2013/467 dated 08th July 2013. The Concessionaire intimated the authority regarding the stoppage of work by the villagers from Ch. 258+700 to 259+200 on want of reduction in Embankment height vide their office letter number RIL/SBEL/NH-1A/2013/470 dated 13th July 2013. The Concessionaire intimated the authority regarding the non availability of land for launching of Girders on both sides of the Abutments of MJB @ 277+076 vide their office letter number RIL/SBEL/NH-1A/2013/473 dated 15th July 2013. The Concessionaire intimated the authority regarding the stoppage of work by the villagers at Ch 260+080, 260+210, 277+489 & 279+026 vide their office letter number RIL/SBEL/NH-1A/2013/477 dated 16th July 2013. The Concessionaire intimated the authority regarding the assessment for cutting of Chinar trees vide their office letter number RIL/SBEL/NH-1A/2013/486 dated 31st July 2013. The Concessionaire intimated authority regarding the construction of additional structure under change of scope vide their office letter number RIL/SBEL/NH-1A/2013/488, 500 & 505 dated 03rd Aug 2013, 24th Aug 2013 & 28th Aug 2013 respectively. The Concessionaire submitted time extension intimated vide their office letter number RIL/SBEL/NH-1A/2013/495 dated 22nd Aug 2013. The Concessionaire requested Authority regarding the additional land required for shifting of Graveyard from Ch. 271 + 600 to 272+000 vide their office letter number RIL/SBEL/NH1A/2013/501 dated 25th Aug 2013. The Concessionaire requested Authority regarding the additional land required for construction of Trumpet portion for Fly over vide their office letter number RIL/SBEL/NH-1A/2013/498 dated 24th Aug 2013. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 8 MPR – May 2014 The Concessionaire replied Authority regarding the Non Achievement of Project Milestone vide their office letter number RIL/SBEL/NH-1A/2013/498 dated 24th Aug 2013. The Concessionaire submitted design and drawing for ROB @ 243+012 vide their office letter number RIL/SBEL/NH-1A/2013/506 dated 28th Aug 2013. The Concessionaire requested possessions of land @ 277+076 vide their office letter number RIL/SBEL/NH-1A/2013/507 dated 29th Aug 2013. The Concessionaire submitted source approvals of TCI Max Cement vide their office letter number RIL/SBEL/NH-1A/2013/685 & 713 dated 03rd Aug 2013 & 29th Aug 2013. The Concessionaire submitted replies of inspection report of Independent Engineer vide their office letter number RIL/SBEL/NH-1A/2013/688 dated 04th Aug 2013. The Concessionaire submitted video recordings for quarter ending June 2013 vide their office letter number RIL/SBEL/NH-1A/2013/689 dated 31st July 2013. The Concessionaire submitted details regarding the increase in cost of Toll Tax in the state of Jammu & Kashmir vide their office letter number RIL/SBEL/NH-1A/2013/692 dated 12th Aug 2013. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/NH-1A/2013/696 dated 16th Aug 2013 regarding the Force Majeure due to Unseasonal rain fall, High security and strike in Valley from 13th to 16th Aug 2013. The Concessionaire proposed Authority vide their office letter number RIL/SBEL/NH-1A/2013/705 dated 22nd Aug 2013 regarding the use of Evotherm Warm Mix Technology in Bituminous Works. The Concessionaire applied entry tax exemption for equipments vide their office letter number RIL/SBEL/NH-1A/2013/700 dated 21st Aug 2013. The Concessionaire submitted corrective action report for NCPN 27, 32 & 51 vide their office letter number RIL/SBEL/NH-1A/2013/712 dated 27th Aug 2013. The Concessionaire submitted test and inspection report on composite Girders for Major Bridge @ 277+076 are being manufactured by M/s Lloyd Corporation Ltd. vides their office letter number RIL/SBEL/IE/NH-1A/2013/727 dated 05th Sept 2013. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/IE/NH1A/2013/732 dated 10th Sept 2013 regarding the Force Majeure due to Kashmir shuts against Shopian Killings and Zublin Mehta Concert. The Concessionaire submitted Geo-Technical Reports on High Embankment vides their office letter number RIL/SBEL/IE/NH-1A/2013/735 dated 12th Sept 2013. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/IE/NH1A/2013/736 dated 14th Sept 2013 regarding the Force Majeure due to Curfew against Shopian Killings. The Concessionaire intimated Authority vide their office letter number RIL/SBEL/IE/NH1A/2013/755 dated 28th Sept 2013 regarding the Force Majeure due to non supply of cement because of strike called by truck union in Srinagar and attack by militants in Jammu region. The Concessionaire submitted request for Extension of time vides their office letter number RIL/SBEL/NH-1A/2013/531 dated 28th Sept 2013 for 18 months. A cumulative 15 working days lost in the month of Sept 2013 due to disturbance in Kahmir valley because of Zublin Mehta concert, Shopian killings, non supply of cement and attack by militant in Jammu region. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 9 MPR – May 2014 The Concessionaire requested Authorities for considering the composite girder in physical progress vide their office letter number RIL/SBEL/IE/NH-1A/2013/764 & 786 dated 05th Oct 2013 & 19th Oct 2013 respectively. The Concessionaire clarified the observation made on force majeure due to non supply of cement vide their office letter number RIL/SBEL/IE/NH-1A/2013/772 dated 08th Oct 2013. The Concessionaire submitted land acquisition status as on 30th Sept 2013 vides their office letter number RIL/SBEL/NH-1A/2013/787 dated 19th Oct 2013 & RIL/SBEL/NH-1A/2013/540 dated 9th Oct 2013. The Concessionaire requested Authority regarding the lifting of river bed material from Rambiyara Nalla vide their office letter number RIL/SBEL/NH-1A/2013/537 dated 06th Oct 2013. The Concessionaire submitted the Company profile of M/s Teracom to Authority regarding the shifting of utilities vide letter number RIL/SBEL/NH-1A/2013/555 dated 02nd Nov 2013. Concessionaire also requested the approval of escalation clause. The Concessionaire requested for extension of time Authority vides letter number RIL/SBEL/NH1A/2013/556 & 841 dated 02nd Nov 2013 & 20th Nov 2013 respectively. Concessionaire also mentioned that Authority fail to provide the encumbrance free land and as a result the delayed in progress after mobilising more than sufficient resources at site. The Concessionaire intimated Authority regarding the substitute structure (Siphon near Lethpora) vides letter number RIL/SBEL/NH-1A/2013/557 dated 09th Nov 2013. Concessionaire also submitted the minutes of meeting held with the Deputy Commissioner, Pulwama regarding the Siphon vide their letter number RIL/SBEL/NH-1A/2013/562 dated 19th Nov 2013. The Concessionaire intimated Authority regarding the arrangements of snow clearance has done vide letter number RIL/SBEL/NH-1A/2013/558 dated 11th Nov 2013. The Concessionaire intimated Authority regarding the non availability of land at Banihal Section (Ch. 187+000 to 189+350) vide letter number RIL/SBEL/NH-1A/2013/559 dated 11th Nov 2013. Concessionaire also mentioned that Authority failed to provide the encumbrance free land and as a result Concessionaire forced to stop the work after mobilising resources at site. The Concessionaire replied Authority regarding the Claim for damage under clause 12.4.2 of Concession arrangement vide letter number RIL/SBEL/NH-1A/2013/560 dated 12th Nov 2013. The Concessionaire requested Authority regarding the reimbursement of amount spent due to frequent damages of PHE lines at different locations at Sampora Junction, Kadalbal and HP Gas storage and Awantipora junction vide letter number RIL/SBEL/NH-1A/2013/561 & 563 dated 16th Nov 2013 & 19th Nov 2013 respectively. The Concessionaire submitted alternate proposal for ROB @ 243+018 vide letter number RIL/SBEL/NH-1A/2013/566 dated 21st Nov 2013. The Concessionaire submitted source approval of water for Lasjan, Samthan & Vessu Camp vide letter number RIL/SBEL/NH-1A/2013/814 dated 06th Nov 2013. The Concessionaire submitted errection methodology of composite girders vide letter number RIL/SBEL/NH-1A/2013/815 dated 11th Nov 2013. The Concessionaire submitted company profile of M/s Kashmir Steel Rolling Mills vide letter number RIL/SBEL/NH-1A/2013/819 dated 11th Nov 2013 for source approval. The Concessionaire submitted design and drawing for bearing details of Major Bridge @ Ch. 264+625, 268+065, 277+076 & 252+848 vide letter number RIL/SBEL/NH-1A/2013/820 dated 12th Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 10 MPR – May 2014 Nov 2013, RIL/SBEL/NH-1A/2013/821 dated 12th Nov 2013, RIL/SBEL/NH-1A/2013/822 dated 12th Nov 2013 & RIL/SBEL/NH-1A/2013/823 dated 12th Nov 2013 respectively for source approval. The Concessionaire submitted company profile of M/s Steel Auto Industries (SAI) vide letter number RIL/SBEL/NH-1A/2013/824 dated 12th Nov 2013 for source approval. The Concessionaire submitted Vertical Pile Load Test @ Km 245+890, Minor Bridge vide letter number RIL/SBEL/NH-1A/2013/825 dated 12th Nov 2013 for source approval. The Concessionaire submitted reconstruction of existing culverts under change of scope vide letter number RIL/SBEL/NH-1A/2013/830 dated 16th Nov 2013. The Concessionaire submitted design of retaining wall of various heights vide letter number RIL/SBEL/NH-1A/2013/831 dated 17th Nov 2013. The Concessionaire submitted method statement for conducting routine vertical load test on routine piles at Fly Over @ Km 286+116 vide letter number RIL/SBEL/NH-1A/2013/831 dated 17th Nov 2013. The Concessionaire submitted plan & profile of graveyards vide letter number RIL/SBEL/NH1A/2013/845 dated 24th Nov 2013. The Concessionaire requested to Client regarding the cutting down of trees at Lasjan vide letter number RIL/SBEL/NH-1A/2013/569 dated 04th Dec 2013. The Concessionaire requested Client to intervene in the matter of royalty with the geological and mining department vide letter number RIL/SBEL/NH-1A/2013/570 & 577 dated 05th & 15th Dec 2013 respectively. The Concessionaire requested for Extension of time under clause 12.4.2 of Concession agreement vide letter number RIL/SBEL/NH-1A/2013/578 dated 16th Dec 2013. The Concessionaire intimated authority regarding the stoppage of work by the villagers vide letter number RIL/SBEL/NH-1A/2013/579 dated 17th Dec 2013. The Concessionaire intimated authority vide letter number RIL/SBEL/NH-1A/2013/580 dated 17th Dec 2013 regarding the land to be made available on the right hand side of Fly over so that the piling work can be taken up. The Concessionaire intimated authority vide letter number RIL/SBEL/NH-1A/2013/581 dated 17th Dec 2013 regarding the stoppage of work of PUP @ Ch. 280+658 by the villagers. The demand of villagers is to increase the height and letter from the Chief Planning Commission is submitted and the decision from your end is pending. The Concessionaire submitted report on joint visit of site with the supervision consultant and the Client vide letter number RIL/SBEL/NH-1A/2013/582 dated 22nd Dec 2013. The Concessionaire intimated authority regarding the construction of additional structures vide letter number RIL/SBEL/NH-1A/2013/583 dated 19th Dec 2013. The Concessionaire submitted vertical pile load test report for VUP @ 224+780 vide letter number RIL/SBEL/NH-1A/2013/863 dated 21st Dec 2013. The Concessionaire submitted third party test report of VG 10 Bitumen from HPCL vide letter number RIL/SBEL/NH-1A/2013/864 dated 17th Dec 2013. The Concessionaire submitted proposal of cast – in situ culverts to pre cast culverts vide letter number RIL/SBEL/NH-1A/2013/869 dated 21st Dec 2013. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 11 MPR – May 2014 The Concessionaire requested Client for vender approval of POT/PTFE bearings and expansion joint vide letter number RIL/SBEL/NH-1A/2013/876 dated 24th Dec 2013. The Concessionaire requested for approval of Elastomeric bearings for various structures vides letter number RIL/SBEL/NH-1A/2013/879 & 900 dated 2nd Jan 2014 & 23rd Jan 2014 respectively. The Concessionaire submitted compliance of the comments on report submission of vertical pile load test for MNB @ 245+890 vides letter number RIL/SBEL/NH-1A/2014/881 dated 4th Jan 2014. The Concessionaire submitted summary of PDA test report and correlation done vide letter number RIL/SBEL/NH-1A/2014/885 dated 6th Jan 2014. The Concessionaire intimated Authority regarding the progress affected due to heavy Snowfall & low temperature vide letter number RIL/SBEL/NH-1A/2014/889 dated 9th Jan 2014. The Concessionaire submitted video recording (3 sets) for quarter Oct 2013 to Dec 2013 vide letter number RIL/SBEL/NH-1A/2014/890 dated 9th Jan 2014. The Concessionaire submitted PDA test report for MJB @ 222+144 (P2 & P1 (LHS)), 245+890 (A2, P4 (LHS)) & 250+309 (A2, P17 (LHS)) vide letter number RIL/SBEL/NH-1A/2014/892 dated 11th Jan 2014. The Concessionaire submitted report on safety week observed from 11th Jan 2014 to 17th Jan 2014 vide letter number RIL/SBEL/NH-1A/2014/894 dated 13th Jan 2014. The Concessionaire submitted report on safety week observed from 11th Jan 2014 to 17th Jan 2014 vide letter number RIL/SBEL/NH-1A/2014/894 dated 13th Jan 2014. The Concessionaire submitted revised plan and profile of ROB at Km 243+012 vide letter number RIL/SBEL/NH-1A/2014/595 dated 10th Jan 2014. The Concessionaire submitted extension of Performance Bank Guarantee vide letter number RIL/SBEL/NH-1A/2014/597 dated 16th Jan 2014. The Concessionaire submitted revised GAD of ROB at Km 243+012 vide letter number RIL/SBEL/NH-1A/2014/598 dated 21st Jan 2014. The Concessionaire submitted report on safety week observed from 11th to 17th Jan 2014 vide letter number RIL/SBEL/NH-1A/2014/599 dated 21st Jan 2014. The Concessionaire intimated Authority regarding the Vehicle stranding near Chanderkut & Udhampur vide letter number RIL/SBEL/NH-1A/2014/600 dated 21st Jan 2014. The Concessionaire submitted report on Vertical and Lateral Pile load test vide letter number RIL/SBEL/NH-1A/2014/904 dated 2nd Feb 2014. The Concessionaire submitted SSI report for Major & Minor Bridges vide letter number RIL/SBEL/NH-1A/2014/906 dated 8th Feb 2014. The Concessionaire requested I.E regarding the Force Majeure from 9th Feb 2014 to 11th Feb 2014 because of complete shutdown in the valley called by Hurriyat Conference on the first death Anniversary of Mohd. Maqbool Bhatt vide letter number RIL/SBEL/NH-1A/2014/908 dated 12th Feb 2014. The Concessionaire submitted Co-relation report between PDA & Static load test report vide letter number RIL/SBEL/NH-1A/2014/908 dated 12th Feb 2014. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 12 MPR – May 2014 The Concessionaire submitted observation on Environmental management plan vide letter number RIL/SBEL/NH-1A/2014/910 dated 13th Feb 2014. The Concessionaire submitted factory visit report on SHYAM Steel Industries Ltd. vide letter number RIL/SBEL/NH-1A/2014/911 dated 15th Feb 2014. The Concessionaire submitted factory visit report on SRMB SRIJAN Ltd. Regarding the supply of reinforcement steel for approval vide letter number RIL/SBEL/NH-1A/2014/911 dated 15th Feb 2014. The Concessionaire submitted extension of Performance Bank Guarantee vide letter number RIL/SBEL/NH-1A/2014/605 dated 13th Feb 2014. The Concessionaire submitted reports on Routine & Vertical Pile load test of Fly over vide letter number RIL/SBEL/NH-1A/2014/913, 914 & 915 dated 15th Feb 2014. The Concessionaire submitted details of Pile load tests conducted at various structures vide letter number RIL/SBEL/NH-1A/2014/916 dated 16th Feb 2014. The Concessionaire intimated Authority for Schedule “B” to be followed up for Design of Road Pavement vide letter number RIL/SBEL/NH-1A/2014/606 dated 13th Feb 2014. The Concessionaire requested for uses of TCI Max Cement above M30 grade concrete vide letter number RIL/SBEL/NH-1A/2014/607 dated 18th Feb 2014. The Concessionaire intimated Authority regarding the safety implication at site by putting more sign boards according to the specification of CA and also put blinkers at diversion vide letter number RIL/SBEL/NH-1A/2014/612 dated 23rd Feb 2014. The Concessionaire submitted Escrow account statement for the period of 01.12.2013 to 31.12.2013 under clause 31.2&31.3 of Article 31 of CA vide letter number RIL/SBEL/NH1A/2014/614 dated 24th Feb 2014. The Concessionaire submitted variation in scope of structure work for Srinagar Project RIL/SBEL/NH-1A/2014/621 dated 03rd March 2014. The Concessionaire intimated Authority regarding the Work stopped by the Villagers @ MJB 252+848 (Jammu Side) vide RIL/SBEL/NH-1A/2014/622 dated 08th March 2014. The Concessionaire submitted Escrow account statement for the period of 01.01.2014 to 28.02.2014 under clause 31.2&31.3 of Article 31 of CA vide letter number RIL/SBEL/NH1A/2014/625 dated 13th March 2014. The Concessionaire requested Authority regarding the additional land required for Toll Plaza vide RIL/SBEL/NH-1A/2014/626 dated 13th March 2014. The Concessionaire intimated Authority regarding the change in authorisation from Mr. C S Sastry to Mr. Ayaz Jawad Hussain vide RIL/SBEL/NH-1A/2014/627 dated 14th March 2014. The Concessionaire replied Authority regarding the suspension of construction work of structures like Major & Minor Bridges/Flyover/VUPs vide RIL/SBEL/NH-1A/2014/628 dated 17th March 2014. The Concessionaire intimated Authority regarding the closure of Main Gate by Local Villagers vide RIL/SBEL/NH-1A/2014/629 dated 17th March 2014. The Concessionaire requested Authority regarding the shifting of 33 KVA electric line as per DPR vides RIL/SBEL/NH-1A/2014/632 dated 26th March 2014. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 13 MPR – May 2014 The Concessionaire submitted PDA tests and Correlation approach for minor Bridges vide RIL/SBEL/NH-1A/2014/924 dated 3rd March 2014. The Concessionaire intimated Authority vide RIL/SBEL/IE/NH-1A/2014/932 dated 20th March 2014 regarding the Force Majeure due to heavy snowfall and curfew in Valley of Kashmir. The Concessionaire submitted test reports of POT/PTFE bearing for Major Bridges at Location Km 252+848, 264+625, 268+065 & 277+076 vide RIL/SBEL/I.E/NH-1A/2014/938 dated 22nd March 2014. The Concessionaire submitted video recording for the quarter ending March 2014 i.e from 1st Jan 2014 to March 2014 vide RIL/SBEL/I.E/NH-1A/2014/964 dated 25th April 2014. The Concessionaire submitted revised plan & profile of Km 225 to Km 226 & 227 vide RIL/SBEL/I.E/NH-1A/2014/961 dated 24th April 2014. The Concessionaire submitted detailed drawing for super structure & deck slab of MNB @ 261+026 vide RIL/SBEL/I.E/NH-1A/2014/960 dated 24th April 2014. The Concessionaire submitted revised drawing for Elastomeric bearing for VUP @ 224+780, MNB @ 239+856, MNB @ 245+890, MNB @ 250+309, MNB @ 261+026 & Fly over @ 286+110 vide RIL/SBEL/I.E/NH-1A/2014/959 dated 24th April 2014. The Concessionaire submitted drawing for deck slab details of Fly over @ Ch 287+466 vide RIL/SBEL/I.E/NH-1A/2014/952 dated 12th April 2014. The Concessionaire submitted revised plan & profile at various locations from Ch. 222+600 to 275+600 vide RIL/SBEL/I.E/NH-1A/2014/950 dated 12th April 2014. The Concessionaire intimated Client regarding the severe climatic condition in the valley and resulting poor progress of work for entire month vide RIL/SBEL/I.E/NH-1A/2014/942 dated 1st April 2014. The Concessionaire submitted estimate & drawing for shifting of electrical utility along the National Highway in Banihal Section vide RIL/SBEL/I.E/NH-1A/2014/649 dated 28th April 2014. The Concessionaire submitted the action taken report to Client regarding the meeting convened by Chief Secretary of J&K on 19th April 2014 vide RIL/SBEL/I.E/NH-1A/2014/646 dated 25th April 2014. The Concessionaire submitted compliance on Critical issues & Maintenance of Existing Road vide RIL/SBEL/I.E/NH-1A/2014/645 dated 25th April 2014. The Concessionaire submitted compliance on Maintenance of Existing Highway & Safety issues vide RIL/SBEL/I.E/NH-1A/2014/643 dated 22nd April 2014. The Concessionaire submitted escrow account statement for the month of March 2014 under clause 31.2 & 31.3 of article 31 of CA vides RIL/SBEL/I.E/NH-1A/2014/638 dated 10th April 2014. The Concessionaire submitted revised GAD of ROB @ 243+012 with single span of 45m vide RIL/SBEL/I.E/NH-1A/2014/637 dated 02nd April 2014. The Concessionaire requested Authority to provide land for construction of service road from Ch. 224+400 to 225+300 vide RIL/SBEL/I.E/NH-1A/2014/636 dated 01st April 2014. The Concessionaire submitted source approval of SRMB Srijan Reinforcement steel vide RIL/SBEL/I.E/NH-1A/2014/967 dated 04th May 2014. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 14 MPR – May 2014 The Concessionaire submitted pile integrity test reports for fly over 286 vide RIL/SBEL/I.E/NH1A/2014/968 dated 04th May 2014. The Concessionaire intimated to authority vide their office letters number RIL/SBEL/IE/NH1A/2014/971 dated 05th May 2014 regarding the Force Majeure (Curfew in Valley of Kashmir) due to death of Youth in CRPF firing at Nawakadal from 01st May 2014 to 3rd May 2014 resulting all our works have come to stand still. The Concessionaire submitted recheck test reports of Embankment, GSB & WMM layers for quality audit of NHAI vide RIL/SBEL/I.E/NH-1A/2014/974 dated 08th May 2014. The Concessionaire submitted High Embankment designs with additional SSI reports vide RIL/SBEL/I.E/NH-1A/2014/975 dated 10th May 2014. The Concessionaire requested approval of Speedway Petro Infra Pvt. Ltd. For CRMB vide RIL/SBEL/I.E/NH-1A/2014/978 dated 12th May 2014. The Concessionaire submitted elastomeric bearing for Minor Bridges & RIL/SBEL/I.E/NH-1A/2014/981 dated 29th May 2014. Flyover vide The Concessionaire submitted design & drawing of PSC superstructure, elastomeric bearing with pedestal for Minor Bridges vide RIL/SBEL/I.E/NH-1A/2014/982 dated 29th May 2014. The Concessionaire intimated Authority regarding the maintenance of existing road from Pantha Chowk up to Qazigund including Banihal Section vide RIL/SBEL/I.E/NH-1A/2014/650 & 662 dated 01st & 15th May 2014 respectively. The Concessionaire submitted Contractor All Risk insurance Policy vide to Authority vide RIL/SBEL/NH-1A/2014/652 dated 05th May 2014. The Concessionaire intimated to Authority regarding the stoppage of work by local Villagers between Ch. 262+600 to 264+700 vide RIL/SBEL/NH-1A/2014/653 dated 05th May 2014. The Concessionaire submitted variation/change of scope for additional structures to Authority vide RIL/SBEL/NH-1A/2014/654 dated 06th May 2014. The Concessionaire submitted Escrow account statement to Authority for the month of April 2014 under clause 31.2 & 31.3 of Article 31 of Concession agreement vide RIL/SBEL/NH-1A/2014/659 dated 10th May 2014. The Concessionaire deposited the welfare cess of workers under (RE & CS) Act 1969 vide RIL/SBEL/NH-1A/2014/660 dated 10th May 2014. The Concessionaire intimated Authority regarding the restoration of irrigation bund which was cut while the execution of pile work at MJB 277 vide RIL/SBEL/NH-1A/2014/663 dated 20th May 2014. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 15 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 16 MPR – May 2014 1.2.1 Contractual Details: (Total Project) Length of the Proposed Road Fly-Over / Grade Separator Railway Over Bridge Major Bridge Minor Bridge Box & Slab Culverts Pipe Culverts Vehicular Underpasses Pedestrian / Cattle Underpass Truck Lay Bay Bus Lay Bay Service Road Toll Plaza Si. No. Description 67.76 Km. 01 Nos. ( Total Length 347.46 m) 01 Nos. 8 Nos. 7 Nos. 197 Nos. 04 Nos. 10 Nos. 8 Nos. 02 Nos. 17 Nos. 4.8 Km. (Approx.) 1 No. Unit Total Quantity 1 Clearing & Grubbing Hector 2 3 4 Excavation Earthwork in Embankment Sub grade/Shoulder Cum Cum Cum 383,300 5,609,798 971,639 5 6 7 GSB WMM DBM Cum Cum Cum 3,826,51.5 329,719.5 135,279.7 Cum 61,046.24 8 BC 1.3 Important Features : 1 2 3 4 5 6 7 : : : : : : : : : : : : : Total Project Length Contract Value Date of Letter of Acceptance Concession Agreement Signed Appointed Date Appointment of IE Appointment of Safety Consultant 400.5 67.76 Km Rs. 1101 Crores. (As per Financial Closure) 27-06-2011 28-12-2010 27-06-2011 26-03-2012 Not Yet Appointed. Financial Progress Table: Physical Progress up to May-14. (As per new work program) Achieved Financial Progress Scheduled Financial (Rs.) Progress till 31st May 2014 Up to Last month This Month Up to This Month 815,82,73,037 476,86,70,980 52,81,000 477,39,51,980 Fall/slippage +/(Rs.) 338,43,21,057 Table: Physical Progress in % Progress in % (of Total Project Cost ) Cumulative up to end of May- 2014 Planned 69.43 Actual 30.36 Shortfall 39.07% Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 17 MPR – May 2014 1.4 Milestone: Contract Value - 1175.00 (As per Concession Agreement) Project Mile Stone(MS) Days from Expended Appointment Cost Date Percentage Financial Package Remarks MS-I 180 117.50 10% Construction of Project Highway Commenced MS-II 450 411.25 35% Commenced Construction of all Bridges MS-III 750 822.50 70% Commenced Construction of all Project Facilities Four Laning 1095 - - As per Schedule 'G' of Concession Agreement 2.0 Project Length Division: Project Km 187+000 to Km 189+350 & 220+700 to 286+110 Section I From Km 187+000 to Km 189+350 Section II From Km 220+700 to Km 252+800 Section III From Km 252+800 to Km 286+110 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 18 MPR – May 2014 ORGANISATION CHART SPV Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 19 MPR – May 2014 ORGANISATION CHART EPC Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 20 MPR – May 2014 MOBILISATION REPORT Mobilisation for the various items of Road Work & Structure Work completed and furnished below. The Batching plant and allied machinery for Concrete, GSB & WMM and DBM plant are completed. The major site operations in progress are as follows. Structure Works: Construction of Box culverts & Pipe under progress. Construction of Minor and all Major Bridges in progress. Construction of Fly-Over in Progress. Construction of VUP & PUP under progress. Pre-Cast concrete works under progress. Reinforcement (HYSD) works under progress for Structures. Composite Girder for Major Bridges stocked at site. Road Works: Excavation for Road Work is under progress. Construction of Embankment under progress. PFVD work is under progress. Laying of Sub-Grade under progress. Laying of GSB under progress. Laying of WMM under progress. Maintenance works of Existing Carriage Way under progress. Kerb laying in Progress. DBM Laying in progress Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 21 MPR – May 2014 LOGISTIC : Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 22 MPR – May 2014 Lab Equipment Status Mobilized at Section – II (Ch. 220+700 to Ch. 252+800) Srinagar Banihal Road Project LAB -1 NAME OF LAB EQUIPMENTS Sr. No. SOIL 1 Hot Oven (0 – 250 C) 60 X 60 X 60 cm, S.S.CHAMBER, With Digital temp. controller and forced air circulation 2 Max. Dry Density Mould (2250 cc) with rammer 4.89 kg √ 3 Max. Dry Density Mould (1000 cc) with rammer 4.89 kg √ 4 CBR Testing Machine set - With Proving ring, dial gauge & plunger √ 5 CBR Mould set (2250 cc) with perforated plate √ 6 Surcharge weight 147mm dia. 2.5 kg wt. (Annular) √ 7 Surcharge weight 147mm dia. 2.5 kg wt. (slotted) √ 8 Spacer disc 148mm dia, 47.5mm height with handle √ 9 Tripod stand for holding dial gauge (set) √ 10 Cassagrande Apparatus Hand operated √ 11 Cone Penetro meter. As per IS:2720 √ 12 Sand equivalent apparatus (Automatic) 13 Proving Ring Cap. 50 kn. √ 14 Proving Ring Cap. , 30 kn. √ 15 Proving Ring Cap. √ 16 Nuclear Density Gauge 17 RADIATION SURVEY METER 18 Sand Pouring Cylinder (20 Cm)with Tray and Calibrating Container √ 19 Sand Pouring Cylinder (15 Cm)with Tray and Calibrating Container √ 20 Sand Pouring Cylinder (10 Cm)with Tray and Calibrating Container √ 21 Rapid moisture meters Deluxe quality √ 22 Hydrometer - Soil (0.75 to 1.0 & 1.0 to 1.3 gm/cc density range) each 23 Tray different size(60*30 CM) √ 24 Steel/Aluminium Container (Approx 100 ml.150 & 200.0 ml vol.) per group 60 nos. in each lab √ 25 kn. √* CONCRETE 25 Mortar cube Vibrating Machine-With Crompton Motor 26 Cube Moulds Vibrating Table of 1m X 1m √ 27 Vicate Apparatus √ 28 Soundness apparatus (Le-Chatelier mould-set of 6) √ 29 Slump test Apparatus √ 30 Lab Concrete Trial Mixer 31 Cube Testing Machine (2000 KN) Cap -Digital (Cap. 1 cu. Feet) √ √ Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 23 MPR – May 2014 32 Specific gravity bottle (1000 ml/ 100 ml/50ml)Cap √ 33 Concrete Cube Moulds (15X15X 15 cm) - Weight 9.5 kg √ 34 Cement test Mould size 7.07 *7.07 * 7.07 cm √ 35 Mortar Cube Mould of size 5cm X 5cm X 5cm 36 Le- chatelier flask for cement specific gravity test √ AGGREGATE 37 Sieve Shaker- for 20cm and 45 cm dia sieves-Combined √ 38 Aggregate Impact Value Apparatus √ 39 Flakiness Gauge √ 40 Elongation Gauge √ 41 Pycnometer (1000 ML) 42 Wire Basket for density 43 Los Angeles abrasion Test Apparatus 44 Crushing Value Apparatus 45 Riffle Box of (40mm and 20mm ) √ 46 10% fines value testing apparatus set √ 47 SCOOP √ √ √* BITUMEN/BITUMINOUS MIXES 51 Modified Marshall stability apparatus (Complete set) √ 52 Modified Marshall Rammer 150mm dia (Automatic) EIE MAKE √ 53 Modified Marshall Rammer for 150mm dia (10.2 kg wt.)(Manual) √ 54 Modified Marshall compaction Pedestal for 150mm dia 55 Modified Marshall Mould 150mm Ø √ 56 Standard Marshall Stability Apparatus √ 57 Standard Marshall compaction Apparatus for 100mm dia (Automatic) √ 58 Standard Marshall compaction Pedestal for 100mm dia (Manual) 59 Marshall Rammer 100 mm Ø (4.9kg ) √ 60 Marshall Moulds sets of 100mm dia, with base plate and collar √ 61 Water bath - DIGITAL FOR 6 MARSHAL MOULDS(24*16*12") √ 62 Water bath - DIGITAL FOR 12 MARSHAL MOULDS(48*32*24") √ 63 Bitumen Penetration Apparatus-Automatic with timer √ 64 Centrifugal Bitumen Extractor- Motorized √ 65 Bitumen Mixer 66 Vacuum Pump with filter flask and rubber tubing √ 67 Specific gravity bottles of 50ml capacity set √ 68 Softening Point Apparatus – DIGITAL √ 69 Kinematic Viscometer - With U Tube Viscometers √ 70 Saybolt Viscometer (Aimil make only) √* √* Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 24 MPR – May 2014 71 Flash & Fire point Apparatus √ 72 Ductility Apparatus √ 73 Core cutting machine - with water pump & silent DG Set √ 74 Diamond core bit of 100mm dia with barrel (100 × 200) √ 75 Diamond core bit of 150mm dia with barrel (150 × 200) √ 76 Straight edge 3 METER WITH MEASURING WEDGE √ 77 Bump indicator Apparatus 78 Hydraulic De-mould Extractor (100mm Dia) 79 Conical flask of 2lit capacity (with made of side neck suction arrangement) 80 Thin Film OVEN 81 Beaker 600 ml (Borosil make) √ √ GENERAL 82 Hot Oven (0 – 250 C) 60 X 90 X 60 cm, S.S.CHAMBER, With Digital temp. controller and forced air circulation √ 83 Micrometer 0-25mm (Deflection gauge) √ 84 Vernier Caliper-300mm (Digital) √ 85 Hot Plate-20cm dia √ 86 Electronic Weighing Balance (50 Kg),5gm √ 87 Electronic Weighing Balance (30 Kg) , 1gm √ 88 Electronic Weighing Balance (20 Kg) 1 gm √ 89 Electronic Weighing Balance (15 Kg) 1 gm √ 90 Electronic Weighing Balance (6 Kg) , 0.5gm √ 91 Electronic Weighing Balance (600G) , 0.01gm √ 92 Platform Balance of 300kg capacity with 50gm accuracy(p2 & P3 200KG)(P-4 - 150 kg) 93 Pan balance of 50kg capacity √ 94 Pan balance of 30kg capacity with 2gm accuracy √ 95 Pan balance of 10kg capacity with 1gm accuracy √ 96 Pan balance of 5kg capacity 0.5gm accuracy √ 97 Standard Weights(50 Kg) √ 98 Standard Weights(20 Kg) √ 99 Standard Weights(10 Kg) √ 100 Standard Weights(05 Kg) √ 101 Standard Weights(02 Kg) √ 102 Standard Weights(01 Kg) √ 103 Standard Weights(500 G) √ 104 Standard Weights(200 G) √ 105 Standard Weights(100 G) √ 106 Standard Weights(50 G) √ Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 25 MPR – May 2014 107 Brass wt. Box √ 108 Standard Weights(0-200 G) √ 109 Standard Weights(10 G) √ 110 Standard Weights(5 G) √ 111 Cylinder for checking of DLBD 50 lit. Cap √ 112 Volume measuring container of 20lit capacity √ 113 Volume measuring container of 15lit capacity √ 114 Volume measuring container of 10lit capacity √ 115 Volume measuring container of 3lit capacity √ 116 Sample trays of 1m X 0.6m √ 117 Sample trays of 0.6m X 0.6m √ 118 Sample trays of 0.45m X 0.45m √ 119 Conical flask of 2lit capacity 120 Conical flask of 1lit capacity √ 121 measuring jars of 1000ml capacity(Borosil) √ 122 measuring jars of 1000ml capacity( Plastic) √ 123 measuring jars of 500ml capacity (Borosil) √ 124 measuring jars of 500ml capacity(Plastic) √ 125 measuring jars of 250ml capacity (Glass) √ 126 measuring jars of 250ml capacity (Plastic) √ 127 measuring jars of 100ml capacity (glass) √ 128 measuring jars of 50ml capacity (glass) √ 129 Stop watch DIGITAL √ 130 Glass thermometers of 250oc- Yellow back German Glass √* 131 Glass thermometers of 100 c Yellow back German Glass √ 132 Glass thermometers of 50oc Yellow back German Glass √ 133 Dial gauge thermometers of 300oc √ 134 Spirit level √ 135 Pippet glass of 25ml √ 136 Rain gauge - Non recording type, Fibre Glass body √ 137 DIGITAL HYGRO METER √ 138 Steel scale 1.0 meter √ 139 DIGITAL THERMOMETER √ o IS SIEVES G.I. Sieves (400 mm Dia.) 140 90 mm √* 141 80 mm √* Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 26 MPR – May 2014 142 75 mm √* 143 63 mm √* 144 53 mm √* 145 45 mm √* 146 40 mm √* 147 37.5 mm √* 148 31.5 mm √* 149 26.5 mm √* 150 25 mm √* 151 22.4 mm √* 152 20 mm √* 153 19 mm √* 154 16 mm √* 155 14mm √* 156 13.2 mm √* 157 12.5 mm √* 158 11.2 mm √* 159 10 mm √* 160 9.5 mm √* 161 6.3 mm √* 162 5.6 mm √* 163 4.75mm √* 164 2.36mm √* 165 1.18mm √* 166 pan & lid √* G.I. Sieves (300 mm Dia.) 167 90 mm √* 168 80 mm √* 169 75 mm √* 170 63 mm √* 171 53 mm √* 172 45 mm √* 173 40 mm √* 174 37.5 mm √* 175 31.5 mm √* 176 26.5 mm √* 177 25 mm √* 178 22.4 mm √* Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 27 MPR – May 2014 179 20 mm √* 180 19 mm √* 181 16 mm √* 182 14mm √* 183 13.2 mm √* 184 12.5 mm √* 185 11.2 mm √* 186 10 mm √* 187 9.5 mm √* 188 6.3 mm √* 189 5.6 mm √* 190 4.75mm √* 191 2.36mm √* 192 1.18mm √* 193 pan & lid √* Brass Sieves (200 mm Dia.) √* 194 19mm √* 195 13.2mm √* 196 12.5mm √* 197 10.mm √* 198 9.5mm √* 199 5.6mm √* 200 4.75mm √* 201 3.35mm √* 202 2.8mm √* 203 2.36mm √* 204 2.0mm √* 205 2.12mm √* 206 1.70mm √* 207 1.4mm √* 208 1.18mm √* 209 1.00mm √* 210 .850mm √* 211 .710mm √* 212 0. 600mm √* 213 0. 425mm √* 214 0. 300mm √* 215 .180mm √* Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 28 MPR – May 2014 216 0. 150mm √* 217 0. 090mm √* 218 0.075mm √* 219 .053mm √* 220 0. 045mm √* 221 Filter paper 100 mm & 150 mm dia.(pkd) (each) √ 222 Mixture machine (small) √ 223 Measuring tape (30m) √ 224 Permeability test machine √ Lab Equipment Status Mobilized at Section –Section - III (Ch. 252+800 to 286+110) Srinagar - Banihal Road Project LAB -2 LAB -3 NAME OF LAB EQUIPMENTS Sr. No. SOIL 1 CBR Testing Machine with Proving ring set √ √ 2 Nuclear Density Gauge (5804&3780 at mordu) √ √ 3 Max. Dry Density Mould (1000 cc) with 4.89kg rammer √ √ 4 Max. Dry Density Mould (2250 cc) with 4.89kg rammer √ √ √ √ √ √ √ √ √ √ √ √ 5 6 7 8 CBR Mould set (2250 cc) With perforated plate, 01 annular weight (2.5kg) of slot hole and 01 annular weight(2.5kg) of center hole. Sand Replacement apparatus (20 Cm) with tray and calibrating cylinder Sand Replacement apparatus (15 Cm) with tray and calibrating cylinder Sand Replacement apparatus (10 Cm) with tray and calibrating cylinder 9 Hot Oven ( 0 – 250 C) 10 Hot Oven ( 0 – 150 C) √ √ 11 Rapid moisture meters with calcium carbide √ √ 12 Cassagrande Apparatus √ √ 13 Cone Penetration Test √ √ 14 Hydrometer 1.00 to 1.500 √* √* 15 Hydrometer 0.950 to 1.000 √ √ 16 Hydrometer 0.750 to 1.100 √ √ 17 C and Phy value apparatus √* √* 18 Spatula √ √ 19 Glass rod √* √* CONCRETE √ √ Mortar cube Vibrating Machine √ √ 20 200lit Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 29 MPR – May 2014 21 Cube Moulds Vibrating Table of 1m X 1m √ √ 22 Vicate Apparatus √ √ 23 Soundness apparatus √ √ 24 Flexural Beam Mould (70X15X15 cm) √ √ 25 Flexural Beam Mould Vibrating Table √ √ 26 Slump test Apparatus with tamping rod √ √ 27 Mortar Cube Mould of size 7.06cm X7.06cm X 7.06cm √ √ 28 Mortar Cube Mould of size 5cm X5cm X 5cm √ √ 29 Lab Concrete Trial Mixer √ √ 30 Cube Testing Machine (2000 KN) Cap √ √ 31 Cube Testing Machine (500 KN) Cap √ √ 32 Flexural Testing Machine ( 100 KN) Cap √ √ 33 Pycnometer (50ML ) √ √ 34 Concrete Cube Moulds (15X15X 15 cm) √ √ 35 Concrete Cylinder Moulds √ √ 36 Vibrating Hammer for DLC √ √ 37 Air Entrainment meter √ √ 38 Wheel Barrow √ √ 39 Grouting cube mould (10cmX10cmX10cm) √ √ 40 Compaction factor √ √ 41 Flow table √ √ AGGREGATE 42 Sieve Shaker √ √ 43 Aggregate Impact Value Apparatus √ √ 44 Flakiness Gauge √ √ 45 Elongation Gauge √ √ 46 Pycnometer (1000 ML) √ √ 47 Wire Basket for density √ √ 48 Los Angeles abrasion Test Apparatus √ √ 49 Crushing Value Apparatus √ √ 50 Riffle Box of (40mm) √ √ 51 Riffle Box of (20mm ) √ √ 52 10% fines value testing apparatus set √ √ 53 Permeability test app √ √ BITUMEN/BITUMINOUS MIXES 54 Marshall Stability Apparatus set with 25 KN Pro. √ √ 55 Marshall Holder √ √ 56 Bitumen Penetration Apparatus √ √ Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 30 MPR – May 2014 57 Mould for Bitumen Penetration test √ √ 58 Centrifugal Bitumen Extractor, electrical operated √ √ 59 Centrifugal Bitumen Extractor, Hand operated √* √* 60 Watman filter paper 24" dia for Bitumen Extractor (100/packet) √ √ 61 Marshall Moulds sets of 100mm dia √ √ 62 Marshall Moulds sets of 150mm dia √ √ 63 Max. Spe Gra. Appa. √ √ 64 GMM bottle 1000ml √ √ 65 GMM bottle 500ml √ √ 66 Marshall compaction Pedestal for 100mm dia √ √ 67 Marshall rammers of 100mm dia √ √ 68 Marshall rammers of 150mm dia √ √ 69 Automatic compactor of 100mm dia for marshall moulds √ √ 70 Automatic compactor of 150mm dia for marshall moulds √ √ 71 Water bath(6 mould - 24X24X36) √ √ 72 Specific gravity bottles of 50ml capacity set √ √ 73 Softening Point Apparatus √ √ 74 Ductility Apparatus √ √ 75 Kinematic Viscometer with U tube √ √ 76 Tar viscometer √ √ 77 Core cutting machine,100mmdia &150mm dia √ √ 78 Diamond core bit of 100mm dia with barrel √ √ 79 Diamond core bit of 150mm dia with barrel √* √* 80 Straight edge √* √* 81 Bump integrator Apparatus √* √* 82 Marshel mould extractor 100mm / 150 mm √ √ 83 Elastic recovery mould in set √ √ 84 Max. Spe Gra. bottle - 5000ml √* √* 85 Max. Spe Gra. bottle - 2000ml √* √* 86 Gas stove √ √ 87 LPG Gas cylinder-19kg √ √ 88 Benzene √* √* 89 Thin film oven √ √ 90 Asphalt mixer √ √ 91 Vacuum pump for GMM test √ √ 92 Flash point apparatus √ √ √ √ GENERAL 93 Venire Calliper -Digital Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 31 MPR – May 2014 94 Hot Plate 95 Platform Electronic Weighing Balance (125Kg),10gm √ √ 96 Electronic Weighing Balance (40 Kg),2gm √ √ 97 Electronic Weighing Balance (60 Kg),1gm √ √ 98 Electronic Weighing Balance (30 Kg),1gm √ √ 99 Electronic Weighing Balance (12 Kg) , 1gm √ √ 100 Electronic Weighing Balance (3 Kg), √ √ 101 Electronic Weighing Balance (20 Kg) , 1gm √ √ 102 Electronic Weighing Balance (15 Kg) √* √* 103 Electronic Weighing Balance (10 Kg) , 0.5gm √ √ 104 Electronic Weighing Balance (6 Kg) , 0.1gm √ √ 105 Electronic Weighing Balance (600G) , 0.2gm √ √ 106 Tribul beam balance of 25kg capacity with 2gm accuracy √* √* 107 Pan balance of 5kg capacity 0.5gm accuracy √* √* 108 Pan balance of 30kg capacity √ √ 109 Pan balance of 25kg capacity √ √ 110 Pan balance of 20kg capacity √ √ 111 Standard Weights(20 Kg) √ √ 112 Standard Weights(10 Kg) √ √ 113 Standard Weights(05 Kg) √ √ 114 Standard Weights(02 Kg) √ √ 115 Standard Weights(01 Kg) √ √ 116 Standard Weights(500 G) √ √ 117 Standard Weights(200 G) √ √ 118 Standard Weights(100 G) √ √ 119 Standard Weights(50 G) √ √ 120 Standard Weights(20 G) √ √ 121 Standard Weights(10 G) √ √ 122 Standard Weights(5 G) √ √ 123 Digital Thermometer- 50 to 280 √ √ 124 Infra red Thermometer - 0 to 250 √ √ 125 Thermometer Glass Range - 0 to 360 √ √ 126 Thermometer Glass Range - 10 to 110 √ √ 127 Volume measuring container of 50lit capacity √ √ 128 Volume measuring container of 20lit capacity √ √ 129 Volume measuring container of 15lit capacity √ √ 130 Volume measuring container of 10lit capacity √ √ 131 Volume measuring container of 3lit capacity √ √ Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 32 MPR – May 2014 132 Sample trays of 1m X 1m √ √ 133 Sample trays of 0.6m X 0.6m √ √ 134 Sample trays of 0.45m X 0.45m √ √ 135 Sampling containers of 500gm capacity (Moisture container) √ √ 136 Sampling containers of 100gm capacity √* √* 137 Glass measuring jars of 500ml capacity 100mm dia √ √ 138 Glass measuring jars of 1000ml capacity 100mm dia √ √ 139 Glass measuring jars of 250ml capacity 40mm dia √ √ 140 Glass measuring jars of 100ml capacity 20mm dia √ √ 141 Glass measuring jars of 50ml capacity √ √ 142 Glass beaker 1000ml capacity √ √ 143 Glass beaker 500ml capacity √ √ 144 Stop watch √ √ 145 Glass thermometers of 250oc(300 c) √* √* 146 Glass thermometers of 100oc √* √* 147 Dial gauge thermometers of 300oc √* √* 148 Spirit level √ √ 149 Pipette glass of 25ml √ √ 150 Rain gauge √ √ 151 Spatula √ √ 152 PVC jar - 1 lit √ √ 153 PVC jar - 2 lit √ √ 154 PVC jar - 500ml √ √ 155 PVC bucket - 20 lit √ √ 156 Hygrometer √ √ 157 Steel trowel for cement test √ √ 158 Pick axe √* √* 159 Shovel √* √* 160 mortar pan √* √* 161 Gas stove √* √* 162 Rubber hammer √ √ 163 Wooden hammer √* √* 164 Proving ring - 50 KN √ √ 165 Proving ring - 25 KN √ √ 166 Steel tape 3 mtr √ √ 167 Steel scale 1mtr √ √ 168 Steel scale 300 mm √ √ 169 Water testing kit √ √ Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 33 MPR – May 2014 170 Steel Hammer 2 kg √ √ 171 Steel Hammer 1 kg √ √ 172 Gas cylinder-05 kg with mounted burner √* √* 173 Chisel steel, 300mm long √* √* 174 Spanner 10/11, 14/15, 17/18, 20/21 both open & close √ √ 175 Steel scoop 2 kg √ √ IS SIEVES G.I Sieves (450 mm Dia) : 176 100 mm √* √* 177 75 mm √* √* 178 63 mm √* √* 179 53 mm √ √ 180 45 mm √ √ 181 37.5 mm √ √ 182 26.5 mm √* √* 183 25.0 mm √* √* 184 22.4 mm √* √* 185 20 .0 mm √* √* 186 19. 0 mm √* √* 187 18.0 mm √* √* 188 13.2 mm √* √* 189 12.5 mm √* √* 190 11.2 mm √ √ 191 9.5 mm √* √* 192 6.3 mm √* √* 193 4.75mm √* √* 194 Pan √ √ 195 Lid √* √* G.I Sieves (300 mm Dia) : 196 90 mm √ √ 197 75 mm √* √* 198 63 mm √* √* 199 53 mm √ √ 200 45 mm √* √* 201 40 mm √* √* 202 37.5 mm √ √ 203 31.5 mm √* √* 204 26.5 mm √ √ Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 34 MPR – May 2014 205 25 mm √ √ 206 22.4 mm √* √* 207 20 mm √* √* 208 19 mm √* √* 209 16 mm √ √ 210 14 mm √* √* 211 13.2 mm √* √* 212 12.5 mm √ √ 213 11.2 mm √* √* 214 10 mm √* √* 215 9.5 mm √* √* 216 6.3 mm √* √* 217 5.6 mm √* √* 218 4.75mm √* √* 219 Pan √* √* 220 Lid √* √* Brass Sieves (200 mm Dia) : 221 10.0mm √ √ 222 4.75mm √ √ 223 3.35 mm √* √* 224 2.8 mm √* √* 225 2.36mm √ √ 226 2.00 mm √ √ 227 1.80mm √* √* 228 1.18mm √ √ 229 1.00mm √ √ 230 0. 710mm √ √ 231 0. 600mm √ √ 232 0. 425mm √ √ 233 0. 300mm √ √ 234 0. 150mm √ √ 235 0. 090mm √ √ 236 0. 075mm √ √ 237 0. 045mm √ √ 238 Pan √ √ 239 Lid √ √ Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 35 MPR – May 2014 5.0 STATUS OF MATERIAL RESOURCES: Borrow areas approved details are as follows: Package A Borrow Areas for Earth Work: RAMKY INFRASTRUCTURE LIMITED QUALITY MANAGEMENT SYSTEM Monthly Progress Report SRINAGAR BANIHAL ROAD PROJECT May-14 For Section – II (220+700 to 252+800): Barrow Areas for Earth Work: List of Borrow Areas 23 Chainages Side Offset from NH (in Km) Status of Tests 227+700 LHS 6.7KM APPROVED 13 222+140 RHS 4.500KM APPROVED 15A 224+800 LHS 8.500KM APPROVED Emb/ sub grade 15B 229+100 LHS 4.500KM APPROVED 5 Emb/ sub grade 27 229+100 LHS 10KM APPROVED 6 Emb/ sub grade 07 229+300 LHS 3.100KM APPROVED 7 Emb/ sub grade 02 229+300 LHS 5.200KM APPROVED 8 Emb/ sub grade 18 230+600 LHS 0.200KM APPROVED 9 Emb/ sub grade 26 232+200 RHS 1.2KM APPROVED 10 Emb/ sub grade 08 232+800 LHS 1.500KM APPROVED 11 Emb/ sub grade 17 233+600 RHS 0.100KM APPROVED 12 Emb/ sub grade 14 246+200 LHS 13.000KM APPROVED 13 Emb/ sub grade 25 247+000 RHS 7.800KM APPROVED 14 Emb/ sub grade 1 247+650 LHS 7.200KM APPROVED 15 Emb/ sub grade 11 247+660 LHS 7.000KM APPROVED 16 Emb/ sub grade 21 250+800 LHS 1.3KM APPROVED 17 Emb/ sub grade 22A 251+400 RHS 3.00KM APPROVED 18 Emb/ sub grade 31 232+700 LHS 0.500 KM APPROVED 19 Emb/ sub grade 32 232+700 LHS 0.500 KM APPROVED 20 Emb/ sub grade 33 247+645 LHS 5.500 KM APPROVED 21 Emb/ sub grade 34 240+070 LHS 12.5 KM APPROVED 22 Emb/ sub grade 35 240+070 LHS 18.5 KM APPROVED Sr. No. Description 1 2 Emb/ sub grade Emb/ sub grade 3 Emb/ sub grade 4 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 36 MPR – May 2014 GSB Sr. No. 1 Description List of Borrow Areas Chainage Side Offset from NH 1 232+800 LHS 3.8 KM 2 233+100 RHS 1.5KM 3 236+040 LHS 12KM Submitted Submitted 4 239+000 LHS 4KM Submitted Package 1 Approval Status Submitted Section – III (252+800 to 286+110): Borrow Areas for Earth work: Approved Borrow area details are as follows: Sr. No. Description List of Borrow Areas Chainages Side Offset from NH (in Km) Approval Status 1 Emb/ sub grade 6 253+000 LHS 2.5KM Approved 2 Emb/ sub grade 12 253+000 RHS 4KM Approved 3 Emb/ sub grade 5 253+000 RHS 8KM Approved 4 Emb/ sub grade 22 256+800 RHS 3KM Approved 5 Emb/ sub grade 20 259+900 RHS 2.KM Approved 6 Emb/ sub grade 24 260+900 RHS 2.5KM Approved 7 Emb/ sub grade 10 267+300 RHS 9.4KM Approved 8 Emb/ sub grade 16 270+700 RHS .5KM Approved 9 Emb/ sub grade 19 278+450 LHS 14.5KM Approved 10 Emb/ sub grade 9 280+700 RHS 6KM Approved 11 Emb/ sub grade 3 281+000 LHS 13.2KM Approved 12 Emb/ sub grade 28 268+000 RHS 1KM Approved 13 Emb/ sub grade 4 281+000 RHS 18km Approved 14 Emb/ sub grade 30 275+600 RHS 1.5 KM Approved Borrow Areas for GSB Sr. No. Description List of Borrow Areas Chainages Side Offset from NH Approval Status 1 GSB 6 269+600 RHS 4 Submitted 2 GSB 5 286+110 RHS 3.5 Submitted Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 37 MPR – May 2014 10.0 METHODOLOGY STATEMENT’S The Source Approval and Method Statements submitted up to Month of March’14 are following below: Sr. No. LETTER NO. DATE DESCRIPTION 1 RIL/SBEL/SPV/NH-1A/12-13/63 05.02.13 Test Pile at P2 major bridge (268+065) 2 RIL/SBEL/SPV/NH-1A/12-13/49 07.01.13 Construction of Major Bridge 3 RIL/SBEL/SPV/NH-1A/12-13/47 03.01.12 Lateral Pile load Test 277+070 A1 TEST PILE 4 RIL/SBEL/SPV/NH-1A/23 14.12.12 Construction of Box Culvert/Pipe culvert 5 RIL/SBEL/IE/NH-1A/11-12/36 09.12.12 Construction of Minor Bridge 6 RIL/SBEL/SPV/NH-1A/11-12/07 22.11.12 Plate load test 7 RIL/SBEL/SPV/NH-1A/11-12/19 12.11.12 Pile Integrity test 8 RIL/SBEL/SPV/NH-1A/09 23.10.12 Lateral pile load Test 9 RIL/SBEL/SPV/NH-1A/07 22.10.12 Plate load test 10 RIL/SBEL/IE/NH-1A/11-12/04 21.10.12 Rock fill in Embankment 11 RIL/SBEL/IE/NH-1A/11-12/01 18.10.12 Pile load test RIL/SBEL/IE/NH-1A/11-12/30 26.06.12 GSB methodology 13 RIL/SBEL/IE/11-12/12 28.05.12 Filter media (GSB & Dust) 14 RIL/SBEL/NH-1A/11-12/04 10.05.12 Construction methodology (QAP) 15 RIL/SBEL/NH-1A/11-12/07 14.03.12 Filter media (10mm & Sand) 16 RIL/SBEL/NH-1A/10-11/47 02.12.11 PQP (PD NH-1A) 17 RIL/SBEL/SPV/NH-1A/12-13/100 12.03.13 18 RIL/SBEL/SPV/NH-1A/12-13/104 13.03.13 12 Methodology for Installation of PVD drains in High Embankment Design Methodology for A1 Test Pile at Km:261+026 11.0 STATUS OF CHANGES FOR VARIATIONS: So far no variation is coming under this project. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 38 MPR – May 2014 12.0 STATUS OF STRETCHES Status of Land Acquired-- SRINAGAR – BANIHAL (Km. 187+000 To Km. 189+350 & Km. 220+700 To 286+110) District Length in Km Land Acquired Land Acquired Hindrance free Land Acquired with Hindrance Balance to be Acquired Chainage Sr. No. From To 1 187+000 189+350 RAMBAN 2.35 2.35 0 2.35 0 2 220+700 257+600 ANANTNAG 36.90 35.80 32.2 3.6 1.1 3 257+600 280+000 PULWAMA 22.40 18.3 16.9 1.4 4.1 4 280+000 284+400 BUDGAM 4.40 4.40 4.40 0 0 5 284+400 286+110 SRINAGAR 1.71 1 0 1 .71 67.76 61.85 53.5 8.35 5.91 Total Utility Relocated: The Present status of Utility relocation is given below Utility Relocation / Removal of Encroachments / Tree cutting Table 1 : Details and status of utilities, encroachments and trees- District: Anantnag Utility / encroachment Utilities: Electrical Ser Unit Quantity Removed Balance Status 1 HT tower No 8 0 0 Estimates approved 2 LT poles No 635 497 138 LT poles shifting work at Anantnag Dist in Progress Transformers Telephone 4 cable (OFC) Utilities: Public health Water 5 pipeline 6 Hand pumps Encroachments No 36 3 33 Km 20.4 0 0 Km 16 No 11 3 Estimates approval awaited from NHAI, HQ. No's Removed Balance 7 Residential buildings No 251 211 40 8 Shops No 855 712 143 9 Mosque No 12 1 11 No No 1 3 0 1 1 2 10 FCI go downs 11 CRPF camps Trees 12 Social forestry No Not in Scope 1942 Cut 1942 Compensation not paid fully for all structures/buildings. Dismantling in progress where payment made. Matter lies with Authorities. Both NHAI and Administration has to take quick decision and shift the same. Balance 0 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 39 MPR – May 2014 13 Under public(80% Compensation to be made for land) No 21946 21126 820 14 15 Walnut Chinar No No 1094 32 787 17 307 15 1. Upon the compensation made for land, land owners will cut all the trees which are under public. 2. For Chinar trees & walnut trees, Divisional Commissioner has to give permission and later auction to be done. 3. Unless compensation made for land / building / encroachment cannot be removed. 4. Authorities have to take action for shifting of Mosque, Go down and CRPF camps. Details and status of utilities, encroachments and trees - District: Pulwama Ser Utility / encroachment Unit Status Quantity Utilities: Electrical Removed Balance 1 HT tower No 1 0 1 2 LT poles No 385 97 288 3 Transformers No 25 1 24 4 Telephone cable (OFC) km 13.72 Not in Scope Utilities: Public health 5 6 Water pipeline Hand pumps km No 6.00 Estimates approval waited from NHAI, HQ. 10 Encroachments 7 Residential buildings No 139 48 91 8 Shops No 376 356 20 Matter lies with Authorities. Both NHAI and Administration has to take quick decision and shift the same. 9 Mosque No 6 10 FCI go downs No 1 1 Nil 11 CRPF camps No 1 1 Nil Trees 12 Social forestry Under public(80% 13 payment to made for land) Compensation not paid fully for all structures/buildings. Dismantling in progress where payment made. No 794 Cut 794 Balance 0 No 14073 12885 1188 14 Walnut No 157 47 110 15 Chinar No 58 17 41 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 40 MPR – May 2014 1. Upon the compensation made for land, land owners will cut all the trees which are under public. 2. For Chinar trees & walnut trees, Divisional Commissioner has to give permission and later auction to be done. 3. Unless compensation made for land / building / encroachment cannot be removed. 4. Authorities has to take action for shifting of Mosque, Go down and CRPF camps. Details and status of utilities, encroachments and trees - District: Budgam Utility / encroachment Ser Utilities: Electrical Unit Quantity 1 HT tower No Nil 2 LT poles No 1 3 Transformers No Nil 4 Telephone cable (OFC) km Nil Status Estimates approved Not in Scope Utilities: Public health 5 Water pipeline km Nil 6 Hand pumps No Nil Nil Encroachments 7 Residential buildings No Nil 8 Shops No Nil 9 Mosque No Nil 10 FCI go downs No Nil 11 CRPF camps No Nil 12 Social forestry No Nil 13 Under public No 600 14 Walnut No Nil 15 Chinar No Nil Trees Compensation not paid.( Under process) Details and status of utilities, encroachments and trees - District: Srinagar Ser Utility / encroachment Utilities: Electrical Unit Quantity 1 HT tower No Nil 2 LT poles No 4 3 Transformers No Nil 4 Telephone cable (OFC) Km Nil Status Estimates approved Not in Scope Utilities: Public health Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 41 MPR – May 2014 6 Hand pumps Encroachments 7 Residential buildings No 4 Crossings Nil No 18 8 9 10 11 Trees No No No No Nil Nil Nil Nil 5 Water pipeline No Shops Mosque FCI go downs CRPF camps Estimates approved Dismantling completed. Cut 12 Social forestry No Nil Nil Balance Nil 13 Under public No 800 800 Nil 14 Walnut No 10 10 Nil 15 Chinar No Nil Nil Nil Approvals and Permits Description Ser Status (a) Permission of the State Government for extraction of boulders from quarry Permission from state Geology & Mining department has been obtained. (b) Permission of Village Panchayat and Pollution Control Board for installation of crushers Permission from SIDCO and Pollution control board for the consent of establishment has been obtained. (c) License for use of explosives Not required. (d) Permission of the State Government for drawing water from river/reservoir The State Government has no objection if we pay usage charges as per tariff. (e) License from Inspector of Factories/ competent authority for setting up Batching Plant Obtained. (f) Clearance of Pollution Control Board for setting up Batching Plant Permission from PCB has been obtained. (g) Clearance of Village Panchayat and Pollution Control Board for Asphalt Plant Permission from PCB has been obtained. (h) Agreement copies for the borrow areas Permission of Village Panchayat and State Government were already obtained. Permission from for borrow earth consent authorities obtained. (i) Permission of State Government for cutting of trees Obtained from all departments for cutting of Trees, except Chinar Trees (j) Any other permits or clearances applicable Laws Sales Tax Registration obtained. (k) Applicable permits in relation to environmental protection and conservation. Obtained by NHAI. (l) Sewage lines & Water Mains : Permission from local municipalities and development authorities Obtained from all departments for shifting. Note: - Copes of all NOC`s submitted to IE Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 42 MPR – May 2014 14.0 STATUS OF CD WORKS & ROAD WORKS AS ON 31.05.2014: Status of Highway – Up to May 2014 Sr. No. 1 2 3 4 5 6 Item C&G Description New Carriageway & Existing Road KM Service Road KM New Carriageway & Embankment Existing Road Top Sub grade Top GSB Top WMM Top DBM Top Unit KM Service Road KM New Carriageway & Existing Road KM Service Road KM New Carriageway & Existing Road KM Service Road KM New Carriageway & Existing Road KM Service Road KM New Carriageway & Existing Road KM Service Road KM Total Scope Work Executed Achieved 67.76 40.8 60.20% 67.76 36.30 53.56% 67.76 21.33 31.45% 67.76 13.69 22.23% 67.76 13.25 19.55% 67.76 8.175 12.06% Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 43 MPR – May 2014 13.1 Structure status Status of Structures - Up to May 2014 Total Scope Structure Started Structure Completed Sr. No. Type of Structure Unit 1 Culverts No's 201 113 80 2 Minor Bridge No's 7 4 0 3 P.U.P. No's 8 5 3 4 V.U.P. No's 10 6 1 5 Major Bridge No's 8 5 0 6 Fly Over No's 1 1 0 7 ROB No's 1 0 0 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 44 MPR – May 2014 15.1 S-Curve: Attached as per Annexure – IV attached. Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 45 MPR – May 2014 16.0 MAJOR CORRESPONDENCE FROM SBEL in May 2014 Date Letter Number 04th May 2014. RIL/SBEL/I.E/NH1A/2014/966 RIL/SBEL/I.E/NH1A/2014/967 RIL/SBEL/I.E/NH1A/2014/968 RIL/SBEL/I.E/NH1A/2014/969 RIL/SBEL/I.E/NH1A/2014/971 RIL/SBEL/I.E/NH1A/2014/972 RIL/SBEL/I.E/NH1A/2014/973 RIL/SBEL/I.E/NH1A/2014/974 RIL/SBEL/I.E/NH1A/2014/976 RIL/SBEL/I.E/NH1A/2014/977 RIL/SBEL/I.E/NH1A/2014/979 RIL/SBEL/I.E/NH1A/2014/980 04th May 2014 04th May 2014 05th May 2014 05th May 2014 06th May 2014 06th May 2014 08th May 2014 10th May 2014 11th May 2014 17th May 2014 20th May 2014 29th May 2014 RIL/SBEL/I.E/NH1A/2014/982 31st May 2014 RIL/SBEL/I.E/NH1A/2014/985 RIL/SBEL/NH1A/2013/650 RIL/SBEL/NH1A/2013/651 RIL/SBEL/NH1A/2013/652 RIL/SBEL/NH1A/2013/654 RIL/SBEL/NH1A/2013/657 RIL/SBEL/NH1A/2013/659 RIL/SBEL/NH1A/2013/663 RIL/SBEL/NH1A/2013/671 01st May 2014 03rd May 2014 05th May 2014 06th May 2014 08th May 2014 10th May 2014 20th May 2014 23rd May 2014 Subject Clarification on NCR no. 129 Regarding Source Approval for SRMB Srijan Reinforcement Steel Submission of Pile Integrity Test Reports-286 Fly-Over Regarding Closing of NCPN 127 Force Majeure (Curfew in Valley of Kashmir Submission of Drawings for MNB at KM 261+026 Submission of Drawings for Fly-Over at 287+466 Submission of recheck test reports of Embankment, GSB & WMM Layers-NHAI Quality Audit Submission of Drawings for Minor Bridges at KM 261+026 & 239+586 Inspection Report of Independent Engineer Regarding Approval of M/s Shiva Bitumen Standard Deviation of Concrete Cubes compressive strength-Lasjan Batching Plant Submission of Design & Drawing of PSC Superstructure, Elastomeric Bearing with Pedestal along with compliance for MNB at 220+809 Corrective Action Report for NCPN No. 135 Maintenance of Existing Highway & Safety Issues Damages of Houses Falling within ROW while executing the Work Contractor’s All Risk Insurance Policy Variation- Change of Scope Damage of Existing Highway near Sempora Submission of Escrow Account Statement for the Month of April 2014 Cutting of Existing Irrigation Bund for casting of Piles at MJB 277+076 P1 Location Maintenance of Existing Highway Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 46 MPR – May 2014 Percentage of Remarks Establishment Office/Camp 100% Main Office/Camp Established at Ch 270 + 900 and at Ch 234+000. 100% Office/Camp Established at Ch 249 + 800. 100% Office/Camp Established at Ch 282+500 100% SPV office, Residential Qtr work Complete at Ch 270+900. 1. Operational at km 270+900 camp. Lab 100% 2. Operational at km 282+500 camp. 3. Operational at km 234+000 camp Crusher 100% Production started (Spalls Extracted 621345MT, Crushed Aggregate Stocked 429139MT) 1. Batching Plant No. – 1(CP-30) at km 270+900, Batching Plant No.– 2(CP-45) at KM 249+800 is in operation. Batching Plant No. – 3 (CP-30) at km 282+500 is in operation. Plants Plant, Batching Plant No –4 foundation work in progress at km (Batching WMM & 234+000 HMP) 2. WMM Plant No - 1 Established at Km 282+500 & No.-2 Established at Km 249+800, WMM Plant No. –3 proposed at km 234+000 3. Hot MIX Plant No – 1 At Km 282+500 is in operation& , No.-2 At Km 234+000 is in operation. 1. Quarry & Crusher operation started from 9th September’12 and crushing is in progress at Lassipora village. 2. Quarry & Crusher crushing is in progress at km 222+400 Quarry 100% 3. Quarry & Crusher operation started from and crushing is in progress at Lasjan village CH 282+500. 4. Mobile crusher at Ch 270 is working. 5 Mobile Crusher is working at Ch.227 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 47 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 48 MPR – May 2014 Awantipora Town (Ch. 264+000) Barsoo (Ch 268+000) Galandar (Ch. 274+500) Pampore (Ch. 277+080) Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 49 MPR – May 2014 Vessu near Green Tunnel (Ch. 251+000) Vessu Town (Ch. 249+000) Qazigund Town (Ch. 223+000) Qazigund Town (Ch. 222+100) Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 50 MPR – May 2014 Safety Implication at Site Safety Implication at Site Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 51 MPR – May 2014 Progress of Pier @ MJB 285+848 Maintenance of Existing Road in Progress Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 52 MPR – May 2014 Existing Road Maintenance Staging in Progress at MJB 277+070 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 53 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 54 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 55 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 56 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 57 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 58 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 59 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 60 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 61 MPR – May 2014 Srinagar Banihal Expressway Limited. Srinagar Banihal Road Project 62