Current Design and
Implementation
Challenges of Road
Projects on the
Coastland
Ron Rahaman
Chief Roads and Bridges Officer
Ministry of Public Works
Works Services Group
Project Life Cycle
Project
Starting the Project
Manager
Conceptualized
Project
Team
Organising & Preparing
Feasibility,
Planning &
Stakeholders
Consultant
Design
Carrying out the works
Construct
Sponsor
Closing the project
Contractor
Test & Turnover
DESIGN PHASE
Design Phase (Feasibility Study and Tendering)
• Report submissions
– Preliminary Assessment Report
• Highlights the problems, challenges & deficiencies with
its current usage
– Environmental and Social Impact Assessment
Report
• Continuous engagement of stakeholders
• Compliance with the regulations of the EPA
Design Phase (Feasibility Study and Tendering)
– Project Selection Report
• Appropriate remedy to address problems, taking into
account stakeholders need, appropriate standards and
guidelines, sound engineering principles of safety,
economic benefits verses cost of implementation
– Draft and Final Design Report
• Comprehensive reports, including drawings, bills of
quantities
– Pre-bidder Conference
Design Challenges
• Inadequate record Keeping
• Loss of institutional Knowledge
• Missing road survey plans / road reserve /
acquisition
• Culture of People / poor enforcement
• Inter agency coordination
• Underground utilities / structures
Design Challenges
• Site Conditions – Swamp, water
• Budget Constraints – availability, most
economic (design / supervision / construct)
• Weight Control
• Competitive pricing – Tendering stage
• Attracting new contractors – Tendering stage
• Contractor overload – Tendering stage
implementation PHASE
Construction Stage
• Reports
– Project Design Review
• Review of design
– Review Report of Contractor QA/QC plan
• Review contractor’s submission
– Monthly Progress Reports
• Captures progress of works, issues, etc
Construction Stage
– Work Program
• To be used by the contractor to plan & execute the
works
• Initial program (First 3 months)
• Accepted Programme (entire work)
• Updated Programme (t least on monthly basis)
– Method Statement
• Same time with programme
• General description of the arrangements and methods
of construction and temporary works design
• The statement should be fully cross-reference to the
activities in the programme
Implementation Challenges
On site
• Encroachment on road reserve
– Fences
– Structures
Implementation Challenges
On site
• Utility Corridor
– no corridor
– Inadequate planning leads to poor usage
Implementation Challenges
On site
• Limited road reserve
– Compromise road geometry
– By passes
Implementation Challenges
On site
• Change in elevation
– modification to entrances
– Drainage issues
Implementation Challenges
On site
• Geological conditions
– Poor soil
– Buried structures
Implementation Challenges
Environment
• Time lapse between design and
implementation
• Change in market prices
• Shortage of construction material
• Culture
Implementation Challenges
Contractor
•
•
•
•
•
•
•
•
•
Frequent down time
Inadequate human resources
Equipment fleet
Poor planning / lack of planning tools
Procurement of materials
Quality / time Control
Use of Mobilization Advances
Traffic / Safety Management
Social Engagement
Recommendations
• Materials Management Unit (Government
level)
• Government roster with upcoming work
projects in all areas
• Better contractor register – Database
• Procurement / Evaluation Criteria
• Improved Public Relations
• Multi stakeholders Committee throughout the
project cycle
Recommendations
• Common spatial database for utilities
• Review and enforcement of weight control
• Establishment of equipment pool – renting of
specialised equipment
• Value Engineering