IENG 471 - Lecture 03 Product & Process Design 3/23/2016 IENG 471 Facilities Planning 1 Agenda Assignments Product Design Process Design Routing Sheets Operations Process Charts Precedence Diagram Data for Facilities Planning Design Reverse Engineering Indented Bills of Material (BOM) Project Evaluation & Review Technique (PERT) Questions & Issues 3/23/2016 IENG 471 Facilities Planning 2 Product Design Must meet the needs of the customer QFD Must be communicated (internally) Product Drawings (Assembly, Detail) Parts List Part Structure 3/23/2016 Indented BOM covers both the parts list and part structure IENG 471 Facilities Planning 3 Indented Bill of Materials A “BOM” is a document that: Lists all parts in an assembly Shows the quantity of all components Allows for the roll-up of costs Shows the sequence of assembly 3/23/2016 Each indentation shows the components of the sub-assembly IENG 471 Facilities Planning 4 Example: Manual Juicer 3/23/2016 IENG 471 Facilities Planning 5 Example: Manual Juicer 3/23/2016 IENG 471 Facilities Planning 6 Example: Manual Juicer Function of the product: Obtain seed-free juice from produce Principle(s) of operation: Lever (Class 2) to provide pressure Grating to stop seeds Gravity to drain the juice 3/23/2016 IENG 471 Facilities Planning 7 Example: Manual Juicer Materials of construction: Aluminum (sandcast) body Rubber feet Cost of the artifact: $ 0.32 in aluminum $ 0.04 in rubber $ ??? in labor, shipping, packaging, etc. 3/23/2016 IENG 471 Facilities Planning 8 Example: Manual Juicer Indented BOM & Cost Roll-up: (1) Juicer Assembly $ 0.36 (1) Body Sub Assembly $ 0.18 (1) Body Casting $ 0.14 (4) Rubber Feet $ 0.01 These are the $ 0.05 These are the (1) Strainer Casting number of child number of required to $ 0.10 (1) Lever Casting parts child parts make ONE of the required to parent part (1) Hinge Pin $ 0.03 make ONE of the parent part Total # of Rubber Feet to make (1) Juicer Assembly: (1) (1) (4) = 4 3/23/2016 IENG 471 Facilities Planning 9 BOM Example in Excel Quantity Description 1 Juicer Assembly Cost $0.36 . . . 1 Body Sub-Assembly . $0.18 . . . 1 Body Casting . . $0.14 . . 4 Rubber Feet . . $0.01 . 1 Strainer Casting . $0.05 . . 1 . 1 Lever Casting . . $0.10 $0.03 . 3/23/2016 Hinge Pin IENG 471 Facilities Planning . 10 Process Design Steps in Process Identification 1. 2. 3. 4. 5. 6. 3/23/2016 Define elemental operations Identify alternative process(es) for each operation Analyze alternative processes for each operation Standardize processes for each operation Evaluate alternative processes for overall production Select processes for overall production IENG 471 Facilities Planning 11 Routing Example ROUTING PART NAME: Shaft, Vise PART NUMBER: MATERIAL: PREPARED BY: DATE: DRAWING NUMBER: GT CODE: LABOR RATE: TOTAL COST: Brass Process Parameters Op. No. Speed Operation Description ft/min Feed rpm 1 Cut material from bar 150 2 Face 1st end of shaft 150 900 3 Face 2nd end of shaft 150 4 Turn diameter to length, rough 5 ipr Estimated Depth ipm in. Machine Labor Setup hrs. hrs Cost Remarks band saw 0.10 0.10 Leave extra for machining 0.005 lathe 0.20 0.05 take minimal needed for cleanup 900 0.005 lathe 0.20 0.05 cut to length per print 150 900 0.015 lathe 0.20 0.05 leave .03 for finish cut Turn diameter to length, finish 150 900 0.005 lathe 0.10 6 Cut groove 150 900 0.005 lathe 0.20 0.05 7 Chamfer end of shaft 150 900 0.005 lathe 0.10 0.05 8 Turn diameter to length, rough 150 900 0.015 lathe 0.20 0.05 9 Turn diameter to length, finish 150 900 0.005 lathe 0.10 10 Chamfer end of shaft 150 900 0.005 lathe 0.10 0.05 11 Center drill end of shaft 150 900 0.010 lathe 0.10 0.10 12 Drill hole in end 150 900 0.010 lathe 0.10 0.05 drill extra deep 13 Tap hole lathe 0.10 0.10 hand tap, lots of oil 14 Center drill for cross hole 200 1200 0.006 mill 0.10 0.10 15 Drill cross hole 200 1200 0.006 mill 0.10 0.05 16 Chamfer cross hole 100 600 0.005 mill 0.05 0.05 3/23/2016 IENG 471 Facilities Planning leave .03 for finish cut both sides 12 Operation Process Chart Circles represent operations Number in circle represents standard operation Prefix in circle identifies: Circles are annotated with operation description Boxes represent inspections Subassemblies (SA) – child levels Assemblies (A) – parent level in this view Number in box represents standard operation Boxes are annotated with inspection description Arcs (lines) represent component(s) Arcs are annotated with part number & description for introduced components 3/23/2016 (See Figure 2.12 in text, p. 44) IENG 471 Facilities Planning 13 Example: Manual Juicer Operations-Process Chart Body Casting Rubber Feet Strainer Casting Lever Casting Hinge Pin 4001 4021 4002 4003 4004 Trim, 0101 sand, inspect Trim, 0102 inspect Trim, 0101 sand, inspect Trim, 0101 sand, inspect Trim, 0101 sand, inspect A1 SA1 I1 Plastic Bag A2 4031 Note: lines merge / diverge only at operations! 3/23/2016 IENG 471 Facilities Planning 14 Standard OPC Symbols 3/23/2016 IENG 471 Facilities Planning 15 Process Design Result The result of the process design can be a precedence diagram: Take the OPC and turn it on its’ side. Connect the component arcs with a single operation (START), and you have a Precedence Diagram The precedence diagram can be converted to a PERT chart for SCHEDULE DESIGN 3/23/2016 IENG 471 Facilities Planning 16 Example: Manual Juicer Precedence Diagram 0101 4004 4003 0100 4002 0101 0101 A1 I1 A2 4021 0102 SA1 4001 0101 4031 3/23/2016 IENG 471 Facilities Planning 17 PERT: Scheduling Terminology Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete Event - The result of completing one or more activities. An identifiable end state occurring at a particular time. Events use no resources. Network - The combination of all activities and events define the project and the activity precedence relationships Meredith, J. R. & Mantel, S. J. (2006) 3/23/2016 IENG 471 Facilities Planning 18 PERT: Scheduling Terminology Path - The series of connected activities (or intermediate events) between any two events in a network Critical - Activities, events, or paths which, if delayed, will delay the completion of the project. A project’s critical path is understood to mean that sequence of critical activities that connect the project’s start event to its finish event Meredith, J. R. & Mantel, S. J. (2006) 3/23/2016 IENG 471 Facilities Planning 19 PERT: Activity-on-Node Network Fundamentals J, K, & L can all begin at the same time, if you wish (they need not occur simultaneously) M but J A B C K A is preceded by nothing B is preceded by A C is preceded by B L (1) (3) All (J, K, L) must be completed before M can begin Y Y and Z are preceded by X X Z Z Y and Z can begin at the same time, if you wish Y AA AA is preceded by X and Y Z is preceded by X and Y X (2) 3/23/2016 (4) IENG 471 Facilities Planning Meredith, J. R. & Mantel, S. J. (2006) 20 PERT: Activity on Node Notation Early Start (ES) Early Finish (EF) Activity Late Start (LS) 3/23/2016 Duration (D) Late Finish (LF) IENG 471 Facilities Planning 21 PERT: Calculating ES and EF Forward Pass Through Network: Move left to right, covering each simultaneous activity in order ES = maximum of EF for all immediate predecessor activities (0 for START activity) EF = ES + Duration Critical Time = EF of the END activity 3/23/2016 IENG 471 Facilities Planning 22 PERT: Calculating LS and LF Backward Pass Through Network: Move right to left, covering each simultaneous activity in order LF = minimum of LS for all immediate successor activities (Critical Time for END activity) LS = LF – Duration Slack (Float) Time: 3/23/2016 LS – ES Note: Slack = 0 for Critical Activities IENG 471 Facilities Planning 23 PERT: Critical Path Example 1 4 4 5 B 3 3 0 1 F 1 6 6 1 G 1 7 7 8 4 8 1 1 4 1 3 2 9 9 H 1 8 4 D 2 3/23/2016 6 C 3 A 1 0 5 11 Z 2 9 9 11 8 E 4 4 4 8 Critical Time = 11 sec Slack D = 1 sec Slack B, F, G = 2 sec Critical Path = A, C, E, H, Z IENG 471 Facilities Planning 24 PERT: Critical Path Management CP are those activities where ES = LS Any delay in these activities will delay production! Wrong to say that these activities are the most important, though: 3/23/2016 Frequently, activities with slack are put off until too late if not monitored! Other paths may be near-critical, and will also delay the project if not monitored! IENG 471 Facilities Planning 25 Tying Critical Path to Facilities Critical Path is connected to Makespan If this were a repetitive operation environment: Makespan is the total time for a single, physical unit to go through all operations In manufacturing, it’s the time difference between the start and finish of a sequence of jobs or tasks Skorin-Kapov, J. & A. J. Vakharia In health care, it is the duration of a patient’s medical experience for the treatment of a medical episode Quick exercise Suppose that you had to schedule personnel to make a mass-produced product 3/23/2016 What would you do to perform operations on the CP? What might you do with non-CP operations? IENG 471 Facilities Planning 26 Questions & Issues HW 2: Hands on assignment to develop: BOM Operations Process Chart Precedence Diagram PERT Chart Team exercise Team members must each contribute a document 4 people per team (5 people, if necessary) Other tools are in MIL Lab (IER 310) 3/23/2016 Semi-randomly assigned members Leave the tools there, but OK to take the product parts IENG 471 Facilities Planning 27