pre-ch3-4

advertisement

IT 2123 - Pre-Quiz Chapters 3 & 4

Multiple Choice

Identify the choice that best completes the statement or answers the question.

____ 1. JWD Consulting’s core business goal is first presented in the ____ section of the business case. a. Critical Assumption and Constraints b. Current Situation and Problem/Opportunity Statement c. Introduction/Background d. Business Objective

____ 2. ____ processes include defining and authorizing a project or project phase. a. Monitoring and controlling c. Executing b. Planning d. Initiating

____ 3. The Project Communications Management knowledge area maps to the ____ process group through the activity of information distribution. a. initiating b. monitoring and controlling c. executing d. planning

____ 4. ____ processes include devising and maintaining a workable scheme to ensure that the project addresses the organization’s needs. a. Monitoring and controlling b. Initiating c. Planning d. Executing

____ 5. An organization may initiate information technology projects for several reasons, but the most important reason is to support ____. a. financial security b. technological advances c. shareholders d. business objectives

____ 6. Research shows that ____ is the number one reason cited for why organizations invest in information technology projects. a. supporting explicit business objectives b. supporting implicit business objectives c. keeping abreast of technological advances d. providing financial incentives

____ 7. Which of the following processes is a closing process? a. Integrated change control c. Risk response planning b. Contract closure d. Develop project team

____ 8. ____ involves working with stakeholders to create the document that formally authorizes a project. a. Developing the project charter b. Directing and managing project execution c. Developing the preliminary project scope statement d. Developing the project management plan

____ 9. In a weighted scoring model, the sum of all of the criteria’s weights must total ____ percent. a. 25 b. 50 c. 100 d. 150

____ 10. The main desired features of JWD’s new intranet are first listed in the ____ section of the business case. a. Analysis of Options and Recommendation b. Current Situation and Problem/Opportunity Statement c. Budget Estimate and Financial Analysis d. Preliminary Project Requirements

____ 11. JWD’s team contract contains the following point: “Work together to create the project schedule and enter actuals into our enterprise-wide project management system by 4 p.m. every Friday.” Which section of the team contract does this point appear in? a. Meeting Guidelines b. Communication c. Participation d. Problem Solving

____ 12. Most systems analysts begin their careers as ____. a. database administrators c. project manager b. CEOs d. programmers

____ 13. The Project Integration Management knowledge area maps to the ____ process group through the activities of developing project charters and developing preliminary project scope statements. a. monitoring and controlling b. planning c. initiating d. executing

____ 14. A(n) ____ is a document used to coordinate all project planning documents and help guide a project’s execution and control. a. contact b. project management plan c. scope statement d. statement of work

____ 15. ____ analysis is used to aid in strategic planning. a. “SWOT” c. “TWET” b. “SWAT” d. “SWEET”

____ 16. A(n) ____ is a document that describes the products or services to be created by the project team. a. project charter c. contract b. statement of work d. business case

____ 17. ____ analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time. a. Payback b. Net present value c. Cash flow d. Cost of capital

____ 18. ____ involves determining long-term objectives by analyzing the strengths and weaknesses of an organization, studying opportunities and threats in the business environment, predicting future trends, and projecting the need for new products and services. a. Project initiation c. Strategic initiation b. Project planning d. Strategic planning

____ 19. A(n) ____ is a document that formally recognizes the existence of a project and provides direction on the project’s objectives and management. a. net present value analysis b. balanced scorecard c. project charter d. business case

____ 20. Administrative activities are often involved in ____, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project. a. monitoring and controlling processes b. executing processes c. closing processes d. initiating processes

____ 21. The Project Procurement Management knowledge area maps to the ____ process group through the activities of requesting seller responses and selecting sellers. a. planning b. executing c. initiating d. monitoring and controlling

____ 22. The outputs of which process include approved and rejected change requests, approved corrective and preventive actions, approved and validated defect repair, deliverables, and updates to the project management plan and project scope statement? a. Close the project b. Monitor and control the project work c. Develop the project management plan d. Perform integrated change control

____ 23. On large projects, many project managers say that ____ percent of the job is communicating and managing changes. a. 50 b. 70 c. 90 d. 100

____ 24. A payback early in Year ____ is normally considered very good. a. 1 c. 3 b. 2 d. 4

____ 25. The majority of time on a project is usually spent on ____, as is most of the project’s budget. a. planning c. closing b. execution d. monitoring and controlling

____ 26. ____ are new requirements imposed by management, government, or some external influence. a. Commands c. Directives b. Opportunities d. Problems

____ 27. One method for selecting projects based on ____ is to determine whether they first meet three important criteria: need, funding, and will. a. using a weighted scoring model b. categorizing information technology projects c. broad organizational needs d. implementing a balanced scorecard

____ 28. Project sponsors are usually most interested in ____. a. Final products, services, or results c. Organizational process asset updates b. Administrative closure procedures d. Contract closure procedures

____ 29. The Project Time Management knowledge area maps to the ____ process group through the activity of schedule control. a. monitoring and controlling b. initiating c. planning d. executing

____ 30. The Project Procurement Management knowledge area maps to the ____ process group through the activity of contract administration. a. monitoring and controlling b. planning c. initiating d. executing

____ 31. JWD’s project ____ will include the preliminary budget and schedule information for the project. a. statement c. charter b. declaration d. contract

____ 32. Usually, the project manager and key team members are selected during the ____ process group, a. planning c. monitoring and controlling b. initiating d. executing

____ 33. JWD’s team contract contains the following point: “Only use constructive criticism and focus on solving problems, not blaming people.” Which section of the team contract does this point appear in? a. Meeting Guidelines b. Communication c. Participation d. Problem Solving

Essay

34. What is a weighted scoring model? How is it created? (Pg 130)

35. Describe the process of initiating a project and the issues involved. (Pg 80)

36. What are the methods for categorizing Information Technology projects? (Pg 123)

Download