09-07-2011 Space Project Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
September 7th, 2011
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Wellness & Sports Education Center Phase I: This project entails the
programming, design and construction of a Student Wellness and Sports Education
Center (Est. 116,000 GSF). Phase I in roughly 65,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
RFQ for Design
Complete
Consultant Selection
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Const. Documents
Complete
Construction
January 2011 – MAY 2012.
Changes from last month:
Construction GMP is on target
at $16.4 Million. Project is on
schedule for May 2012. No
changes this month.
2.
Programming for Buildings 50, 3 and 4: This project entails the programming, of three
buildings for backfilling and restacking once the Biology Department moves to the new
Biological Sciences Building in 2012.
Tentative Schedule:
Consultant Selection
Complete
Programming
March 2011
Changes from last month:
No changes this month.
3.
Science and Humanities Building (Biological Sciences): It is anticipated that the
building will be roughly 118,000 GSF on three levels. The building will be located
adjacent to the Social Sciences Building (51).
Tentative Schedule:
Consultant Selection
Complete
Programming
Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Const. Documents
March 2010
Select CM
Complete
Construction
August 2010 to February 2012
Changes from last month:
No Changes from Last Month.
Project is on schedule.
Zak Ovadia
1
4.
COE&HS Building with DRC, VCS, VCL and OCT:
Project to build a 2 story addition to the College of Education & Human Services of
approximately 15,000 GSF.
Tentative Schedule:
Consultant Selection
Complete
Programming
underway
Program Verification underway
Schematic Design
underway
Design Development August 2010
Const. Documents
September 2010
Select CM
October 2010
Construction
January 2011 to October 1st
Changes from last month:
No changes from last month.
Project on schedule.
5.
Science & Engineering Building Remedial Work:
Corrective measures to mitigate building envelope deficiencies.
Tentative Schedule:
Consultant Selection
Complete
Programming
N/A
Program Verification N/A
Schematic Design
TBD
Design Development TBD
Const. Documents
September 2010
Select CM
Complete
Construction
Dec. 2010 – Dec. 2011
Changes from last month:
No Changes from last month.
6.
Northeast Connector Roar and Lot 34 Upgrade:
Design and Build a new road connecting the Loop Road to the Round-about at Lot 18 and
paving of Lot 34 behind the Arena...
Tentative Schedule:
Consultant Selection
Complete
Programming
N/A
Program Verification N/A
Schematic Design
June 2011
Design Development July 2011
Const. Documents
September 2011
Select CM
TBD
Construction
October 2011 to August, 2012
Changes from last month:
No change from last month..
7.
Sanctuary and Meditation Center: Design and Construction of sanctuary building of
approximately 3,500 square feet to serve as a venue for group meditation or events.
Tentative Schedule:
Programming
Complete
Conceptual Permitting Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
Complete
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
No change from last month.
Zak Ovadia
2
8.
New Food Service Facility and General Purpose Building: Design and Construction
of a replacement food service facility to replace Osprey Café. Preliminary needs call for
a three or four-story building.
Tentative Schedule:
Programming
August 2010
Conceptual Permitting TBD
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification Completed
Schematic Design
February, 2011
Design Development March 2011 – April 2011
Select CM
Complete
Construction Docs.
May 2011 – August 2011
Demolition
May 2011
Construction
July 2011 to August 2012
Changes from last month:
Work on Boardwalk
complete. Project Substantial
Completion scheduled for
August 2012.
Completed Projects:





Zak Ovadia
Campus-wide Master Planning
New Fine Arts Buildings and Art Gallery
JJ Daniel Hall Renovations