Identifying a project in trouble & replanning

advertisement
Identifying a project in
trouble & replanning
MPUG 111208
Moritz Farbstein
Senior Consultant
12 November 2008
3/24/2016 6:26 PM
1
Quality
Senior Policy
• Deliver what you promise.
–
Corollary: Do not promise what you know you cannot deliver.
Quality - The degree to which a product or service meets the requirements;
conformance to requirements.
Quality Plan - Initial quality considerations should include:
Quality Goals
Quality Objectives
Quality Organization
Quality Roles
Quality Responsibilities
Quality Resources
Quality Key Events
Quality Reviews
Quality Activities
Quality Processes
Quality Standards
Quality Procedures
Quality Tools
Quality Measurement
Periodically audit the Project and the Project Plan to the Quality Plan.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 2
Conformance to Requirements
• Many project failures can be attributed to problems with
Requirements (unspecified, unclear, changing, etc.)
• Good requirements do not come from a tool, or from a
customer interview. They come from a repeatable set of
processes which take the project from the early idea stage
through to the creation of an agreed-upon project and
product scope between the customer and the developer.
• And continuing throughout the Software Development Life
Cycle, requirements should be traced to ensure that
conformance occurs in all aspects of Design, Development,
Test, Documentation, User Acceptance, Maintenance.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 3
The Triple Constraint
• A project manager faces a complex challenge essential to success:
delivering the agreed-on project product or services within the time and
cost constraints. Meeting the time constraints, not exceeding the cost
constraints, and delivering what was promised are all essential
requirements of project success.
• The three requirements are grouped as a single function because they
are interdependent. A change in one affects the others, and all three must
be satisfied simultaneously for the project to succeed.
• Balancing the three requirements related to Delivery, Time, and Cost is
sometimes called managing the Triple Constraint.
• Delivery, time, and cost requirements take the form of project
Performance and Quality specifications (often called “Scope”), the
project Schedule, and the project Budget.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 4
The “Game” of Project Management –
Goal: Win-Win-Win on all Points
THE GAME
HOW IT’S
PLAYED
HOW IT’S
SCORED
Scope
Control
Client
Schedule
Budget
Plan
Identifying a project in trouble & replanning
Manage
Staff
Mgmt
3/24/2016 6:26 PM MPUG 111208 5
Manage to the Triple Constraint
To manage to the triple constraint, you must:
• Define the project’s purpose, scope, approach, constraints, work
products, priorities, and so forth.
• Create a plan that correctly interprets the project definition, is credible,
realizable, and in sufficient detail to monitor & measure effectively.
• Monitor the project’s performance against the plan.
• You must define the measurements you use for controlling the project.
Without these measurements, you have no way of knowing where the
project is currently headed, how far off course it is, or what action to take
to get it back on course.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 6
Project Purpose and Priorities
• During project execution, all project team members should know the
priorities attached to each element of the triple constraint - delivery
(scope), time (schedule), cost (budget).
• Two aspects are critical:
– “What is the compelling event that caused the client to request this work?” (i.e.
goal, purpose, objective)
– “What priority is placed on delivery, time, and cost by the client?”
• Every project decision is considered in the light of its consistency with,
and impact upon, those priorities.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 7
Quality of a Project Plan
• The Quality of a Project Plan is the degree to
which the plan enables management to the
Triple Constraint.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 8
What is a “Troubled Project?”
• A situation will escalate to troubled status when one of
the major stakeholders (customer, supplier, sponsor, etc.)
can no longer tolerate the situation—in other words,
when the variance trends have exceeded acceptable
levels of tolerance.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 9
When is a Project in Trouble?
• When one or more of the Triple Constraints are
– Out of control (possibly a subjective measure)
– Showing an adverse variance from expected performance
– Outside the limits set in the Quality Plan (an objective measure if it exists)
• How does one judge when a project is in trouble?
– “Judgment” is measured by the ability to evaluate relative importances.
– The basic process of this analysis is to gather information about delivery
(scope), time (schedule), cost (budget) and evaluate the relative importances of
the data thus found. It may not matter that the project is out of scope, over
schedule or over budget – only by comparing this information with project
priorities, management directions, project objectives, risks, issues, contractual
rewards & penalties, and so forth can a valid judgment be derived and an
agreement reached.
• There may be legitimate reasons to cancel a project; this alternative
should not be overlooked.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 10
When is a Project in Trouble? (reactive)
When is it Predicted to Be in Trouble? (proactive)
Some Triple Constraint Considerations
• Delivery / Scope (includes Quality and Performance)
– Missed deliverable or predicted miss on deliverable
– Scope creep
– Change Management non-existent or out of control
– The quality of what was delivered was not what was expected
– Defects are high, there is a backlog of open defects
– A named risk actually occurs (a risk may impact Delivery, Time, &/or Cost)
– Issues are not being identified and addressed
– Low morale, lack of teamwork
• “Morale” = “Production” – morale drops when production drops and morale increases
when production increases
– No clear direction exists for where the project is headed or when it will get there
– Escalation of issues is not working
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 11
When is a Project in Trouble? (reactive)
When is it Predicted to Be in Trouble? (proactive)
Some Triple Constraint Considerations
• Time / Schedule
– Schedule variance; Schedule Performance Index
– Missed milestone or predicted miss on milestone
– Resource over-allocation; resource flow variance metric
– Unrealistic commitments
– Too much (involuntary) overtime
– Finish Dates keep pushing out
– Frequent and extensive replanning
– The amount of work left to do on a task is more than the assigned resources
can accomplish before the expected Finish Date
• Cost / Budget
– Cost variance; Cost Performance Index
– Over budget or predicted overage on budget
– External changes (contracts, management decisions, vendor changes)
– Change Requests directly impact the Budget (e.g. hardware requests)
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 12
When is a Project in Trouble?
Additional Considerations
• Talk with the (previous) project manager.
• Talk with the project team, including the executive sponsor.
• Is the team competent enough in running a project to know where they
really are?
• If the team knows what they are doing then do they actually believe the
project is on track?
• Is there an agreed project purpose and project plan? Has it changed?
• Are the key dates achievable and consistent?
• Are external inputs into the plan on target?
• Does the high-level structure of the plan appear logical?
• Is the resourcing realistic?
• Are there any unrealistic constraints on dates?
• Do the Project Manager or team members have other responsibilities
besides this project?
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 13
Death by Meeting
• Another indicator of a project in trouble – endless and/or nonproductive
meetings.
• Death by Meeting: A Leadership Fable...About Solving the Most Painful
Problem in Business
by Patrick M. Lencioni
Copyright 2004, Published by Jossey-Bass, a Wily imprint, San Francisco, ISBN:
978-0-7879-6805-2
• Does it really need a meeting, or can you just get an answer over the
phone?
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 14
Check and Re-Check Your Focus
Periodically ask these questions. If your answer to one or more of
them is “No,” there is a high risk that the project is in trouble.
• Is the agreed-to project scope still the basis of work?
• Am I maintaining a correspondence between what is happening on the
project and what the three constituencies (client, staff, and management)
expect and need?
– Am I keeping expectations in balance?
– Am I meeting management expectations?
• Does the Project Plan correspond to the work being done by the project
team?
• Does the Project Management Plan still represent the path to success?
• Are issues outstanding beyond their agreed-to resolution date, are risks
not mitigated or avoided, or do changes remain outstanding (either not
agreed upon and incorporated in the plan, or under discussion)?
• Do the project reports provide an accurate, succinct account of the
project, and are they a basis for informed decisions and actions?
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 15
Project Management Tips
• The closer one is to the project, the shorter the period of time used to
report and manage. For example, a line manager might be gathering
data, reporting and managing hourly or daily; a local executive may be
reviewing the project weekly; a remote executive may be reviewing the
project monthly or quarterly.
• When MS Project is used as the source of all project planning
information, MS Excel can be used to capture metrics. Excel can
consolidate data from Project and build a Dashboard.
• It helps if all projects and all project managers use the same naming
conventions, formats and templates.
• The people doing the work must be actively involved in scheduling it.
• Do not focus solely on problems - Recognise team members for jobs well
done and celebrate successes.
• Whenever new information crosses your path, think “Who else needs to
know this?” and make sure they do.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 16
Project Management Tips
• Run the Project Plan through the formal Approval Process.
• Use a formal process & automated tool for Requirements that can
produce a Requirements Traceability Matrix (Req->Design->Code->Test).
• Hold a post mortem to solicit input for lessons learned.
• Insist that people do their own jobs. When they don’t, keep telling them
until they do.
• Choose your battles.
• Do not bring “problems” to Management and ask them to solve them; only
bring them “solutions” to which they can say either “yes” or “no” or take
some recommended action.
• Management must CARE about the people doing the work. The opposite
of caring is slavery.
• Enforce the correct and appropriate process and methodology, but don’t
allow it to stop the work. This will always be something that must
continually be balanced. Build process and methodology training into the
project plan if at all possible.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 17
Project Management Tips
• Action Items must always have the Name of who will do it and the Date
for when it is due. Review AI’s regularly and get them Done.
• Look, Don’t Listen! If they really knew what was actually wrong they
would already have fixed it.
• It may not be just “one” problem and “one” solution. It may be more than
one problem and more than one solution.
• The work to recover a troubled project is a project all by itself. The rescue
project has a sponsor, an approval, a start, an end, resources,
deliverables, schedule, cost, etc. A recovery project must be run with
much tighter control than the original project, or risk a second failure.
• Verify that all work reported as "done" is in fact completed. (“Not Dones,”
“Half Dones,” “Backlogs”)
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 18
Being “Reasonable”
• You succeed when you are unreasonable. You neither give nor accept
excuses. You insist on success.
• Reasonableness is “faulty explanations.” When you agree with faulty
explanations, you are too reasonable. If you agree with faulty
explanations, you agree to fail. Excuses, justifications and
reasonableness produce nothing.
• The most important thing you must be unreasonable about is Down
Statistics. Example: the testing schedule calls for completing 50 tests per
day. Yesterday only 40 tests were completed. Today, being unreasonable,
you must demand that 60 tests are completed. The alternative is to go
over schedule; how much contingency is built in?
• Finally, if you are reasonable, your project will likely fail; there are too
many things that can go wrong, and only one way to go right (i.e. follow
the project plan and meet the milestones,) because, if your plan is like
most plans, it is predicated on everything happening on schedule. Murphy
says that your schedule will use up all built-in contingency time before all
the contingencies have occurred.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 19
Cycle of Action
• Create [Start]
• Survive [Change]
• Destroy [Stop]
Control is defined as the ability to start, change and stop something.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 20
The Project Life Cycle
• Initiate
• Plan
• Execute
• Monitor and Control
• Close-Down
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 21
The Weekly Control Cycle
The weekly control cycle is the basic foundation for project control
activities. Prioritize your week around completing these tasks:
• First, start in control with a sound plan
• Then, on a weekly basis:
– Collect and review project data
– Post actuals and calculate variances
– Evaluate status (using all available information)
– Control risks, issues and changes
– Focus on taking corrective action on variances, issues and problems
– Manage acceptance of deliverables
– Update the master plan as appropriate, or re-plan
– Provide a status report with quantified status of delivery, schedule and budget
– Meet regularly with the team
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 22
Project Office and Program Management Office
• Establish a Project Office and/or a Program Management Office.
– A project office (PO) is a team that is brought in on a large project or multiproject program to assist the project director and management team with project
startup, control, and monitoring activities.
– A program management office (PMO) is a governance body for managing a
program. Typical program management office responsibilities are to supervise
and coordinate across multiple projects:
• Project planning
• Measurement, monitoring, tracking, reporting
• Resolve, or raise and elevate, issues and risks that affect more than one project
• Change Management
• Quality Control (e.g. adherence to Policy and Standards)
• Manage achitecture interdependencies
– When a program management office scope expands to the enterprise level, it is
often referred to as an enterprise program management office (EPMO). The
purpose of an EPMO is to provide a strategic perspective to align with the
business goals.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 23
CSC M5 Offering Addresses The Following Management Disciplines
• PMO: IT or Business Management
Offices ranging from department-level
to enterprise level.
PMO
Management
Portfolio
Management
Demand
Management
CSC M5
Complex
Program
Management
Project
Recovery
Management
• Portfolio: Management techniques
and tools for selecting the “right”
project, application, or infrastructure
investments.
• Demand: Management techniques and
tools for managing day-to-day
application and infrastructure service
requests.
• Complex Program: Experienced
practitioners available to manage the
organizations most difficult initiatives.
• Project Recovery: Swat team
services designed to rescue troubled
projects and to establish controls for
preventing future runaway projects.
Can be implemented individually or collectively
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 24
Replanning
Just the same as planning, only doing it again
• Investigate where the project stands and where it is headed.
• Assess and re-plan the project if it has gotten off track.
– Review all outstanding tasks and requirements, then sort them into these
categories:
• 1. Must have
• 2. Nice to have
• 3. Cannot do yet
• Reset everyone's expectations.
• After resetting project goals and expectations, focus on delivery. Get
something that can be completed actually completed. Project work should
not stop during replanning, although it may be reprioritized, and
temporarily suspended in extreme cases.
• Publicize the fact that something got done. Here is where Project
Management crosses with Public Relations – don’t let everyone think that
“all is lost” when it is not.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 25
Replanning
Just the same as planning, only doing it again
• Plan is revised, if required, for changes of scope, budget, schedule, risks,
adverse performance variances, and so forth. Plan revision should be
assessed with approved change requests.
– Re-Assessment can be triggered by events such as Change Requests, delays
in starting the project, scope changes, start of a life-cycle phase, extending the
detailed plan, contractual changes, cost or budget changes, missed milestones,
risk occurrence, risk mitigation failure, adverse variances of Earned Value
metrics, failure of a Proof of Concept, periodic required re-assessments or
audits, major resource changes, etc.
– In other words, replanning is not done only to handle a project in trouble, but
also for any significant events that may affect the Triple Constraint.
• A project in trouble enough to revise the project plan should be managed
by the change control process.
• Develop several alternatives from which management can choose.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 26
Alternatives
• Reduce scope
• Phased releases & reorganization of deliverables
• Add resources
• Work overtime
• Pay overtime and/or bonuses
• Reward success, penalize failure
• Purchase and use tools
• Improve and/or enforce processes
• Improve team dynamics (i.e. communication)
• Cancel part or all of the project
• Revise the business case (increase the budget, change the scope, etc…)
• Heroics may work this time, but are heroics repeatable, and at what cost?
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 27
How to Present Alternatives to Management
• Use a form such as:
– Situation
• Name the situation, problem, issue, etc. and why it is such.
– Data
• Present ALL the information that management would need to make a “Yes or No”
decision. This would be all the pro’s and con’s of the situation and of the various solution
alternatives, the Triple Constraint data, the priorities, the contractual commitments;
whatever information is needed on which to base a decision on how to proceed. Use the
Triple Constraint model to describe how things must change.
– Solution
• Recommend a solution to which Management can say either “Yes” or “No.”
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 28
Replanning
• Work Breakdown Structure (WBS)
– Tasks, deliverables, resource assignments
• Dependencies
– Task predecessors & successors, critical path, priorities
• Schedule
– Milestones, timeboxes, put vacations & holidays into the Calendar
• Organization
– Roles, responsibilities, accountabilities, reporting relationships
• Staffing
– Number & type of personnel broken down by role and by time period
• Budget
– Time-phased budget baseline
• Payment Schedule – Sponsors, vendors, subcontractors
• Acquisition Management - Solution selection and contractor oversight
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 29
Earned Value Management
• With a complex project, obtaining a single view of cost and schedule is
virtually impossible without a metric that combines the impacts of cost,
schedule, and work performed to the current date. The Earned Value
technique is such a metric, and it provides a single view of cost and
schedule over time.
• Earned Value is a technique used to compare work planned with work
performed. Each product is given a budget and a completion date. When
it is agreed that the product is complete, its value (planned cost of work to
complete it) is earned.
• Earned Value, then, is the budget (planned cost) for a completed piece of
work. [It can also be measured as the work (labor hours) to complete.]
• The Earned Value is compared to the Actual Cost of completing the work.
If the budget is exceeded, the result is an unfavorable cost variance to
the amount of overrun. If the work takes longer than planned to complete,
an unfavorable schedule variance occurs, measured by the value of the
work not yet performed.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 30
Sample of Earned Value
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 31
Example (MS Project 2007)
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 32
Example (MS Project 2007)
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 33
Example
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 34
Example
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 35
Example (CSC)
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 36
Example (CSC)
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 37
Example (CSC)
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 38
SharePoint Server 2007 Dashboard Web Parts
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 39
SharePoint Web Parts
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 40
Project Server 2007 Reports
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 41
Calculate the Burn Rate
• The Burn Rate shows how much effort is needed going forward to finish
on time, expressed as a percentage of remaining planned hours:
Burn Rate = [EAC – ACWP] / [BAC – BCWS]
(in labor hours)
• EAC (Estimate at Complete) less ACWP (Actual Hours to Date) [Actual
Cost of Work Performed] equals the number of actual hours needed to
finish the project. EAC is calculated as ACWP divided by the Cost
Performance Index. In the denominator, BAC (Budget at Complete) less
BCWS (planned hours to date) [Budgeted Cost of Work Scheduled]
equals the remaining number of budgeted hours, i.e., the remaining
planned staffing. When this ratio is greater than 1.0, it means that
planned staffing is insufficient to get all work done before delivery date.
• Cost Performance Index (CPI) is the ratio of the earned value (EV) to the
actual cost (AC). CPI = EV ÷ AC. A value equal to or greater than one
indicates a favorable condition and a value less than one indicates an
unfavorable condition.
• In MS Project, set Standard and Overtime Rates for all Resources to 1 in
order to get EV metrics in hours instead of $’s.
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 42
References
• Earned Value Management
– http://evm.nasa.gov/
– https://acc.dau.mil/evm
– http://www.microsoft.com/office/showcase/earnedvalue/default.mspx
– http://office.microsoft.com/en-us/project/HP010342581033.aspx
– http://office.microsoft.com/en-us/project/HA010211791033.aspx
– http://office.microsoft.com/enau/project/HA101567921033.aspx?pid=CH100666601033
– http://www.projectperfect.com.au/info_earned_value_management.php
– http://www.dekkerltd.com/
– http://www.deltek.com/products/wInsight/
– http://www.deltek.com/products/cobra/default.asp
– http://lmrsolutionsgov.wordpress.com/2008/03/05/applying-earned-valueanalysis-to-your-project/
– http://www.decisionedge.com/DecisionEdge-EarnedValueManager.html
– http://www.quantumpm.com/earnedvaluemanager.aspx
– http://articles.techrepublic.com.com/5100-10878_11-5030576.html
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 43
References
• Enterprise Project Management
– http://office.microsoft.com/en-au/epmsolution/FX101935291033.aspx
• Managing Costs
– http://office.microsoft.com/en-us/project/CH100666641033.aspx
– http://office.microsoft.com/en-us/project/HA012231941033.aspx
• Creating a Budget
– http://office.microsoft.com/en-us/project/HA101632951033.aspx
• Microsoft Project Most Valuable Professional Page
– http://project.mvps.org/
• Microsoft Project 2003 Add-in: Create PowerPoint from Project
– http://www.microsoft.com/downloads/details.aspx?FamilyID=5a4d6d5b069a-401c-9de1-440546836b85&DisplayLang=en
• Microsoft Excel Services (dashboards, SharePoint, Project Server)
– http://msdn.microsoft.com/en-us/library/cc539928.aspx
• SharePoint Web Parts dashboard generation with Project Server 2007
– Go to “Business Intelligence” on the Project Server 2007 SharePoint Help Menu
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 44
References
• Create a visual report in Microsoft Project 2007 (export data to Excel or
Visio) [Report->Visual Reports…]
– Enter “Create a visual report” in the Help search box
• Status Stoplights with Microsoft Project
– http://www.projectperfect.com.au/info_stoplights_in_microsoft_project.php
• Microsoft Project 2003 Analyze Timescaled Data Wizard
– http://articles.techrepublic.com.com/5100-10878_11-5030581.html
– http://office.microsoft.com/en-us/project/HP430079291033.aspx
• Microsoft Project 2003 Reports in Access
– http://www.projectperfect.com.au/info_msp_reports.php
• Microsoft Project 2007 Save to Excel Pivot Table (or other formats)
– Enter “Export wizard” in the Help search box
– http://safari.ibmpressbooks.com/9780735623057/ch12lev1sec5#ch12lev1sec5
• Quality Management - The Deming Cycle
– http://en.wikipedia.org/wiki/Shewhart_cycle
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 45
References
• Dashboards
– http://www.enterprise-dashboard.com/
– http://msdn.microsoft.com/en-us/library/aa164875(office.10).aspx
– http://www.spmn.com/pcpanel.html
– http://store.bamboosolutions.com/ps-102-2-bamboo-project-managementsuite.aspx
– http://www.decisionedge.com/landing_microsoft_earnedvalue.html
– http://mcpmag.com/features/article.asp?EditorialsID=2405
– http://www.jedox.com/en/enterprise-spreadsheet-server/excel-olap-server/paloserver.html
– http://processdash.sourceforge.net/
– http://www.epmsolutions.net/services/server_reporting.html?gclid=CNquqoK2m
JUCFQOeFQod7kz9gQ
– http://www.decisionedge.com/microsoft_decisioncharts_msolanding.html
– http://dashboardspy.wordpress.com/
– http://www.projectlink.co.za/systems_project_dashboard.aspx
– http://www-03.ibm.com/press/us/en/pressrelease/24194.wss
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 46
References
• Business Analysis and Project Requirements
– Determining Project Requirements, Hans Jonasson, Auerbach Publications ©
2008
– Guide to the Business Analysis Body of Knowledge, International Institute of
Business Analysis, www.theiiba.org
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 47
MPUG 111208
Identifying a project in trouble &
replanning
Moritz Farbstein
Senior Consultant
MFarbstein@CSC.com
Identifying a project in trouble & replanning
3/24/2016 6:26 PM MPUG 111208 48