2023-08-30T23:07:52+03:00[Europe/Moscow] en true <p><strong>P-4</strong></p>, <p><strong>P-6</strong></p>, <p><strong>P-7</strong></p>, <p><strong>P-8</strong></p>, <p><strong>P-9</strong></p>, <p><strong>P-10</strong></p>, <p><strong>P-11</strong></p>, <p><strong>P-12</strong></p>, <p><strong>P-13</strong></p>, <p><strong>P-14</strong></p> flashcards
Permissives

Permissives

  • P-4

    Reactor Trip

    Both Reactor Trip and bypass breaker open

    •Turbine Trip

    •FWIS if low TAVG (564°F)

    •Blocks automatic SIS

    •Arms steam dumps

    •Allows reset of SIS @ 60 seconds

  • P-6

    Source Range trip block

    1/2 IR > 10-10 amps

    Allows blocking the SR high flux trip

  • P-7

    Low power trip block

    P-10 or P-13 > 10% power

    Enables the following Reactor Trips:

    •Low PZR Pressure

    •High PZR Water Level

    •RCS loop low flow (2 loops)

    •RCP Bus Undervoltage

    •RCP Bus Underfrequency

  • P-8

    Single RCS low flow block

    2/4 PR < 48% power

    No Reactor Trip on Single RCS low flow

  • P-9

    Turbine Low Power

    2/4 PR > 49% power

    Enables Reactor Trip on turbine trip

  • P-10

    Nuclear at-power

    2/4 PR > 10% power

    Allows blocking of:

    •IR high Reactor trip (25%)

    •PR low setpoint Reactor Trip (25%)

    •C-1 rod stop (20%)

  • P-11

    Pressurizer low pressure

    2/3 PZR Pressure < 1970#

    Allows blocking of low PZR pressure SIS

    Allows blocking of low MS pressure SIS

    •Toggles MSIS to rate setpoint

  • P-12

    Lo-Lo TAVG

    2/4 TAVG < 550°F

    Closes all Steam Dumps

  • P-13

    Turbine at-power

    Turbine >10% power

    Feeds P-7

  • P-14

    Hi-Hi SG level

    2/4 SG level > 78%

    Turbine trip, Trips both MFPs & FWIS