Texas Mechanic’s Lien & Payment Bond Claims Issues Presented By: Jason C. Spencer Telephone: (512) 900-3032 jspencer@andrewsmyers.com www.andrewsmyers.com Contractors Ice Bucket Challenge ?!? Ice Bucket Challenge https:// INTRODUCTION I. Chapter 53 of the Texas Property Code – private projects II. Chapter 2253 of the Texas Government Code (f/k/a “The MacGregor Act”) Texas = very complicated lien and bond law Deadlines are strictly enforced If you miss a deadline, your claim will not be valid and your right to payment will be unnecessarily limited. Property Code = “original contractor” Government Code = “prime contractor.” When in doubt, send each form to everyone above you in the contracting chain, as well as any surety providing a payment bond. CMRRR, facsimile, etc. - - - proof of SENDING th 15 , th 15 , th 15 !!! PART ONE: NON-RESIDENTIAL LIEN CLAIMS “COMMERCIAL” OVERVIEW Contractors and suppliers of all tiers are provided lien rights on non-residential projects under Chapter 53 of the Texas Property Code. The lien provides an additional layer of protection against non-payment for contracting parties by giving them recourse against the owner of the property. When properly perfected, a contractor may force the sale of the property to satisfy its claim for unpaid labor and/or materials. The steps that must be taken to perfect a lien claim are complex. To simplify this process, we have broken down these steps into four primary sections: (1) (2) (3) (4) Gathering Information, Early Notices, Notices of Unpaid Account, and Perfecting the Claim. The benefit of a lien claim cannot be overstated Direct recourse against the improved property Superior to other creditors of the owner with respect to the improvements Distinction: private payment bond vs. indemnity bond (“bond around”) vs. public payment bond SECTION ONE: GATHERING INFORMATION FORM 1.1: REQUEST FOR INFORMATION TO OWNER [Date] Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Re: Request for Information to Owner regarding: [Project Description] Our company is providing labor and/or materials to improve the above-referenced project. It is our understanding that you are the owner of the real property and improvements at the project. If this is incorrect, please advise us immediately. In accordance with the Texas Property Code, please furnish us with the following information: (1) a description of the real property being improved legally sufficient to identify it; (2) whether there is a surety bond and, if so, the name and last known address of the surety and a copy of the bond; and (3) whether there are any prior recorded liens or security interests on the real property being improved and, if so, the name and address of any person having a lien or security interest. Pursuant to the Texas Property Code, you are requested to provide this information no later than 10 days following receipt of this request. Sincerely, [Claimant] FORM 1.2: SUBCONTRACTORS REQUEST FOR INFORMATION TO ORIGINAL CONTRACTOR [Date] Via Certified Mail No. [Number] Return Receipt Requested [Original Contractor’s Name and Address] Re: Request for Information to Original Contractor regarding: [Project Description] Our company is providing labor and/or materials to improve the above-referenced project. It is our understanding that you are the original contractor for the construction of these improvements at the project. If this is incorrect, please advise us immediately. In accordance with the Texas Property Code, please furnish us with the following information: (1) the name and last known address of the person to whom you have furnished labor and/or materials for the project; and (2) whether you have furnished or have been furnished a payment bond for any of the work on the project and, if so, the name and last known address of the surety(s) and a copy of the bond(s). Pursuant to the Texas Property Code, you are requested to provide this information not later than 10 days following receipt of this request. Sincerely, [Claimant] FORM 1.3: ORIGINAL CONTRACTORS RESPONSE TO REQUEST FOR INFORMATION [Date] Via Certified Mail No. [Number] Return Receipt Requested [Claimant’s Name and Address] Re: [Claimant’s] Request for Information regarding: [Project Description] Receipt of your letter dated [Date] requesting information regarding the above-referenced project is acknowledged. The name and address of the person to whom the undersigned has furnished labor and/or materials for the project is: [Owner’s Name and Address]. [Alternate 1] The undersigned has not furnished and no other party has furnished to us a payment bond for any of the work on the above-referenced project. [Alternate 2] We have furnished or otherwise been furnished with a payment bond(s) for the above-referenced project. A copy of the bond(s) is enclosed. The name and last known address of the surety(s) is: [Surety’s Name and Address]. If you do not have a direct contractual relationship with the undersigned, we are entitled to actual costs, not to exceed $25.00, incurred in complying with your request. Our actual costs exceed this amount; therefore, please remit $25.00 as reimbursement for our costs of compliance. Sincerely, [Original Contractor] SECTION TWO: SUBCONTRACTORS EARLY NOTICES FORM 2.1: SUBCONTRACTORS NOTICE OF RETAINAGE AGREEMENT [Date] Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Original Contractor’s Name and Address] Re: AMENDED BY HB 1390 Eff. Sept. 1, 2011 = 30th day after your work or prime contract is completed, terminated or abandoned Notice of Retainage Agreement regarding: Project: [Project Description] Our company has entered into a contract with [Name of Party Contracted With] on the abovereferenced construction project. It is our understanding that you are the owner of the project and/or original contractor of improvements thereon. If this is incorrect, please advise us immediately. The agreement between our company and [Name of Party Contracted With] calls for us to furnish the following labor and/or materials to the project: [General Description of Work]. In accordance with the Texas Property Code, please be advised that this contract includes a “Contractual Retainage Agreement” as defined therein. The contract requires retainage to be withheld as follows: [Retainage as stated in your contract, e.g. 10% from each draw]. The retainage is due [Retainage due date as stated in your contract, e.g. 30 days from completion]. Copies of the applicable portions of our contract are enclosed for your review. Sincerely, [Claimant] Enclosure FORM 2.2: SUBCONTRACTOR OR SUPPLIERS NOTICE OF SPECIALLY FABRICATED MATERIALS [Date] Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Original Contractor’s Name and Address] Re: 15th day of the 2nd month after your specialty order is received Notice of Specially Fabricated Materials regarding: Project: [Project Description] Our company is providing labor and/or materials to the above-referenced project. It is our understanding that you are the owner of the project and/or the original contractor of improvements thereon. If this is incorrect, please advise us immediately. In accordance with the Texas Property Code, please be advised that we have received and accepted an order from [Name of Party Placing Order] for specially fabricated items to be incorporated into the project. The price agreed upon for said items is [Dollar Amount]. A copy of the order is enclosed for your reference. Sincerely, [Claimant] Enclosure SECTION THREE: NOTICES OF UNPAID DRAWS FORM 3.1: SUBCONTRACTORS NOTICE TO ORIGINAL CONTRACTOR OF UNPAID ACCOUNT [Date] Via Certified Mail No. [Number] Return Receipt Requested [Original Contractor’s Name and Address] Re: Notice to Original Contractor of Unpaid Account regarding: [Project Description] This form must be sent to the original contractor no later than the Dear [Original Contractor]: fifteenth day of the second month Our company has furnished labor and/or materials to the above-referenced project under a following each month in which you contract with [Name of Party Contracted With]. It is our understanding that you are the original contractor on the project and that [Name of Party Contracted With] is operating underbut a contract with you or another provided labor and/or materials one of your subcontractors. If this incorrect, please advise us immediately. were not paid for them. In accordance with the Texas Property Code, please be advised that we are owed [Dollar Amount] under our contract with [Name of Party Contracted With] for labor and/or materials furnished to the project that are generally described as follows: [General Description of Work Performed]. This labor and/or materials was provided during the months of [Months and Year Work was Performed]. Enclosed please find a copy of our invoice(s) for this work. On a recurring basis—you must send this notice for each month that you were not paid. Sincerely, [Claimant] Enclosure(s) cc: Via Certified Mail No. [Number] Return Receipt Requested [Name and Address of Party Contracted With] FORM 3.2: SUBCONTRACTORS NOTICE TO OWNER OF UNPAID ACCOUNT [Date] Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] This form must be sent to the OWNER no later Notice to Owner of Unpaid Account regarding: [Project Description]day of the third month than the fifteenth following each month inmaterials which you providedproject under a contract with Our company has furnished labor and/or to the above-referenced [Name of Party Contracted With]. It is our understanding that you are the owner of the real property on which the labor and/or materials but were not paid for improvements have been made. If this is incorrect, please advise us immediately. them. Re: In accordance with the Texas Property Code, please be advised that we are owed [Dollar Amount] under our contract with [Name of Party Contracted With] for labor and/or materials that are generally described as follows: [General Description of Work Performed]. This labor and/or materials was provided during the months of [Months and Year Work was Performed]. Enclosed please find a copy of our invoice(s) for this work. This claim has accrued under Section 53.053 of the Texas Property Code and is past due under the terms of the above-referenced contract. Demand is hereby made for payment of this amount under Section 53.083 of the Texas Property Code. Under the Texas Property Code, we must provide you with the following notice: IF THIS ACCOUNT REMAINS UNPAID, YOU WILL BE PERSONALLY LIABLE OR YOUR PROPERTY SUBJECTED TO A LIEN UNLESS YOU WITHHOLD PAYMENT FROM YOUR ORIGINAL CONTRACTOR FOR THE PAYMENT OF THE CLAIM OR UNLESS THE CLAIM IS OTHERWISE PAID OR SETTLED. Sincerely, [Claimant] Enclosure(s) cc: Via Certified Mail No. [Number] Return Receipt Requested [Original Contractor’s Name and Address] On a recurring basis—you must send this notice for each month that you were not paid. SECTION FOUR: THE LIEN AFFIDAVIT Lien must actually be filed in order to have a right to any money from the owner. It is filed in the real property records of the County Clerk’s office where the project is located. Original contractors must file the lien affidavit no later than the fifteenth day of the fourth month following: (1) (2) (3) written termination of your contract, abandonment of your contract, or completion of your work. Subcontractors that want their lien to attach to the retained funds so that they are paid from the retained fund in preference to the general contractor must file the lien affidavit within 30 days of completion of the project. Filing your lien affidavit is not the last step. A copy of the lien affidavit must be sent to the owner no later than the fifth (calendar) day following the day of filing with the County Clerk. FORM 4.1: ORIGINAL CONTRACTOR AFFIDAVIT OF MECHANIC’S LIEN STATE OF TEXAS COUNTY OF [COUNTY] § § § AFFIDAVIT OF MECHANIC’S LIEN BEFORE ME, Notary Public and in for the State of Texas, on this day personally appeared [Name], who upon his oath, deposed and stated the following: 1. My name is [Name]. I am the [Title] of [Claimant] (“Claimant”). I am over 18 years of age, have personal knowledge of the facts set forth below and am competent and authorized to make this Affidavit on Claimant’s behalf as the sworn statement of its claim. 2. Claimant furnished labor and/or materials for the improvement of real property located at [Address of Project] and more particularly described in the real property records of [County of Project], Texas as: [Legal Description]. 3. Claimant furnished labor and materials under a contract with: [Name and Address of Owner]. 4. The name and last known address of the original contractor for such improvements is: [Original Contractor’s Name and Address]. 5. The name and last known address of the owner or reputed owner of the land and improvements thereon is: [Owner’s Name and Address]. 6. The labor, materials, and/or work furnished by Claimant are generally described as follows: [General Description]. Claimant is hereby asserting a claim for work performed and/or materials furnished in the following months: [Months and Year Work was Performed]. FORM 4.1: ORIGINAL CONTRACTOR AFFIDAVIT OF MECHANIC’S LIEN (Cont.) 7. After allowing all just credits, offsets, and payments, the amount of [Dollar Amount] remains unpaid and is due and owing to Claimant. 8. Claimant’s name and address are as follows: [Name and Mail Address]. [Include Physical Address if Different]. 9. Claimant claims a lien against all the above described land and improvements thereon in the amount shown above pursuant to Chapter 53 of the Property Code of the State of Texas, and makes this sworn statement of claim in support thereof. 10. Claimant also claims a constitutional lien on such property pursuant to the provisions of Article 16, Section 37 of the Texas Constitution to the extent that Claimant is deemed an original contractor. 11. One (1) copy of this Affidavit is being sent by Certified Mail, Return Receipt Requested and First Class Mail to the Owner at all addresses described above. By: [Name], [Title] and Authorized Representative of Claimant STATE OF TEXAS COUNTY OF _____________ § § SUBSCRIBED AND SWORN TO BEFORE ME, by [Name], [Title] and Authorized Representative of Claimant on this _____ day of _______________ , 20___ to certify which witness my hand and official seal of office. _____________ Notary Public – State of Texas After Recordation Please Return to: [Claimant’s Name and Address] FORM 4.2: SUBCONTRACTOR AFFIDAVIT OF MECHANIC’S LIEN STATE OF TEXAS COUNTY OF [COUNTY] § § § AFFIDAVIT OF MECHANIC’S LIEN BEFORE ME, Notary Public and in for the State of Texas, on this day personally appeared [Name], who upon his oath, deposed and stated the following: 1. My name is [Name]. I am the [Title] of [Claimant] (“Claimant”). I am over 18 years of age, have personal knowledge of the facts set forth below and am competent and authorized to make this Affidavit on Claimant’s behalf as the sworn statement of its claim. 2. Claimant furnished labor and/or materials for the improvement of real property located at [Address of Project] and more particularly described in the real property records of [County of Project], Texas as: [Legal Description]. 3. Claimant furnished labor and materials under a contract with: [Name and Address of Party Contracted With]. 4. The name and last known address of the original contractor for such improvements is: [Original Contractor’s Name and Address]. 5. The name and last known address of the owner or reputed owner of the land and improvements thereon is: [Owner’s Name and Address]. 6. The labor, materials, and/or work furnished by Claimant are generally described as follows: [General Description]. Claimant is hereby asserting a claim for work performed and/or materials furnished in the following months: [Months and Year Work was Performed]. 7. After allowing all just credits, offsets, and payments, the amount of [Dollar Amount] remains unpaid and is due and owing to Claimant. 8. Claimant’s name and address are as follows: [Name and Mail Address]. [Include Physical Address if Different]. 9. Notice of claim was sent to the Owner and the Original Contractor at all addresses listed above as follows: FORM 4.2: SUBCONTRACTOR AFFIDAVIT OF MECHANIC’S LIEN (Cont.) Notice was sent on [Date] to [Owner] via Certified Mail No. [Number], Return Receipt Requested and first Class Mail. Notice was sent on [Date] to [Original Contractor] via Certified Mail No. [Number], Return Receipt Requested and First Class Mail. 10. 11. Claimant claims a lien against all the above described land and improvements thereon in the amount shown above pursuant to Chapter 53 of the Property Code of the State of Texas, and makes this sworn statement of claim in support thereof. One (1) copy of this Affidavit is being sent by Certified Mail, Return Receipt Requested and First Class Mail to the Owner and the Original Contractor at all respective addresses described above. By: [Name], [Title] and Authorized Representative of Claimant STATE OF TEXAS COUNTY OF _____________ § § SUBSCRIBED AND SWORN TO BEFORE ME, by [Name], [Title] and Authorized Representative of Claimant on this _____ day of _______________ , 20___ to certify which witness my hand and official seal of office. ________________ Notary Public – State of Texas After Recordation Please Return to: [Claimant’s Name and Address] FORM 4.3: NOTICE OF MECHANIC’S LIEN FILING [Date] Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Original Contractor’s Name and Address] Re: Lien Affidavit of [Claimant’s Name] regarding: [Project Description] Enclosed is a copy of our mechanic’s lien which we are filing with the county clerk. Demand is hereby made for the immediate payment of the amount claimed in the affidavit. In addition to this principal sum, interest may be accruing on this debt at the applicable statutory rate. You are hereby advised that if this account remains unpaid, your property may be subject to foreclosure for satisfaction of the lien. We will be pleased to release the same upon receipt of the balance due and owing. Please contact us immediately so that this matter can be resolved without formal legal action. Sincerely, [Claimant] Enclosure SUMMARY OF PERFECTION PROCEDURES: NON-RESIDENTIAL LIEN CLAIMS TABLE OF NOTICE DEADLINES: NON-RESIDENTIAL LIEN CLAIMS PART TWO: PUBLIC WORK PAYMENT BOND CLAIMS Public projects More streamlined procedure * 1 Year Statute of limitations plus 60-day pre-suit notice Prime (“Original”) Contractors may not avail themselves of a payment bond claim. * Personal guaranties FORM 1.1: SUBCONTRACTORS REQUEST FOR INFORMATION TO PRIME CONTRACTOR [Date] Via Certified Mail No. [Number] Return Receipt Requested [Prime Contractor’s Name and Address] Re: Request for Information to Prime Contractor regarding: [Project Description] Our company is providing labor and/or materials to improve the above-referenced project under a contract with [Name of Party Contracted With]. In accordance with the Texas Government Code, we hereby request that you provide the following information: 1. The name and last known address of the governmental entity with whom you have contracted to provide public work for the project; and 2. A copy of the payment and performance bonds for the project, including bonds furnished by or to you. As required by the Texas Government Code, please provide this information within 10 days of receipt of this request. If our contract is not directly with you, we will pay your actual cost of providing this information, not to exceed $25, upon request. Sincerely, [Claimant] By: __________________________________ Title: _________________________________ FORM 1.2: SUBCONTRACTORS REQUEST FOR INFORMATION TO OWNER [Date] Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Re: Request for Information to Owner regarding: [Project Description] Our company has provided labor and/or materials to improve the above-referenced project under a contract with [Name of Party Contracted With]. We have not been paid in full for this labor and/or materials. In accordance with the Texas Government Code, we hereby request certified copies of: 1. The payment bond provided by [Prime Contractor] for construction of the improvements; and 2. The public work contract for which the bond was given. We will pay your reasonable fee for the actual cost of preparation of the copies upon request. Sincerely, [Claimant] By: __________________________________ Title: _________________________________ FORM 1.2: SUBCONTRACTORS REQUEST FOR INFORMATION TO OWNER (Cont.) STATE OF TEXAS COUNTY OF __________ § § Affiant, upon oath and after being duly sworn, states that he has read the above application and facts contained therein and that such statements are true and correct. Subscribed and sworn on this the _____ day of _______________ , 20___. _______________________________________ Notary Public in and for the State of Texas FORM 1.3: REQUEST FOR INFORMATION TO SUBCONTRACTOR [Date] Via Certified Mail No. [Number] Return Receipt Requested [Subcontractor’s Name and Address] Re: Request for Information to Subcontractor regarding: [Project Description] It is our understanding that you are a subcontractor on the above-referenced public work project. In accordance with the Texas Government Code, we hereby request that you provide the following information: 1. 2. 3. 4. The name and last known address of each person from whom you have purchased labor and/or material for the project; The name and last known address of each person to whom you have provided labor and/or material for the project; A statement of whether you have furnished a payment bond for the project; and If a payment bond has been provided, the name and last known address of the surety on the bond and copy of that bond. As required by the Texas Government Code, please provide this information within 10 days of receipt of this request. If our contract is not directly with you, we will pay your actual cost of providing this information, not to exceed $25, upon request. Sincerely, By: __________________________________ Title: _________________________________ [Claimant] SECTION TWO: EARLY NOTICES FORM 2.1: SUBCONTRACTORS NOTICE OF RETAINAGE AGREEMENT [Date] Via Certified Mail No. [Number] Return Receipt Requested [Prime Contractor’s Name and Address] Re: Notice of Retainage Agreement regarding: [Project Description] SECOND TIER (or lower) ONLY: Our company has entered into a contract with [Name of Party Contracted With] on the abovereferenced construction project. This agreement requires us to furnish the following labor and/or materials to the project: [General Description of Work]. This form must be sent no later than In accordance with the Texas Government Code, please be advised that this contract includes a the fifteenth day of the second month “retainage” provision as defined therein. The contact requires retainage to be withheld as follows: [Retainage as stated in your contract,when e.g. 10% from each draw]. The retainage first is due [Retainage due as following the claimant stated in your contract, e.g. 30 days from completion]. The total sum anticipated to be retained under this contract is [Dollar Amount]. Copies of the and/or applicable portions of our contract are enclosed for your provides labor materials to the review. Sincerely, project. [Claimant] By: __________________________________ Title: _________________________________ Enclosure cc: Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Name and Address of Party Contracted With] FORM 2.2: SUBCONTRACTORS OR SUPPLIERS NOTICE OF SPECIALLY FABRICATED MATERIALS [Date] Via Certified Mail No. [Number] Return Receipt Requested [Prime Contractor’s Name and Address] Re: SECOND (or Notice of SpeciallyTIER Fabricated Materials [Project Description] ONLY: lower) Our company is providing labor and/or materials to the above-referenced project. In accordance with the Texas Government Code, please be advised that we have received and accepted an order from [Name of Party Contracted With] for specially fabricated items to be incorporated into the project. These items are generally described as: [General Description of Items] [or] [as described on the attached order]. The price agreed upon for said items is [Dollar Amount]. A copy of the order is enclosed for your reference. This form must be sent no later than the fifteenth day of the second month following when the Sincerely, claimant received the order for [Claimant] specially fabricated materials. By: __________________________________ Title: _________________________________ Enclosure cc: Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Name and Address of Party Contracted With] SECTION THREE: SUBCONTRACTORS NOTICES OF UNPAID DRAWS FORM 3.1: SUBCONTRACTORS NOTICE TO PRIME CONTRACTOR OF UNPAID ACCOUNT [Date] Via Certified Mail No. [Number] Return Receipt Requested [Prime Contractor’s Name and Address] Re: Notice to Prime Contractor of Unpaid Account regarding: SECOND TIER (or lower) ONLY: [Project Description] Our company has provided labor and/or materials to the above-referenced project under a written contract with [Name of Party Contracted With], on which you are the prime contractor. This form must be sent no later than In accordance with the Texas Government Code, please be advised that we are owed [Dollar the fifteenth day of the second Amount] under this contract for labor and/or materials furnished to the project that are generally described as: [General Description of Work]. Enclosed please find a copy of our invoice(s) for this work. month following each month the If this claim is not promptly paid, we will proceed to perfect our claim against you and your surety. This notice is sent so that you may have an opportunity to see that his amount is paid in full prior to our taking claimant provided the labor and such action. Sincerely, materials. [Claimant] By: __________________________________ Title: _________________________________ Enclosure cc: Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Name and Address of Party Contracted With] FORM 3.2: SUBCONTRACTORS NOTICE TO PRIME AND SURETY OF UNPAID ACCOUNT [Date] Via Certified Mail No. [Number] Return Receipt Requested [Surety’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Prime Contractor’s Name and Address] ANY TIER: Notice to Surety and Prime Contractor of Unpaid Account regarding: This form must be sent no later than [Project Description] the fifteenth day of the third month Our company has furnished labor and/or materials to the above-referenced project under a written contract with [Name of Party Contracted With]. following each month the claimant In accordance with the Texas Government Code, please be advised that we are owed [Dollar provided the labor and materials. Amount] under this contract for labor and/or materials that are generally described as follows: [General Re: Description of Work Performed]. Enclosed please find a copy of our invoice(s) for this work. The following Sworn Statement of Account is provided as required by the Texas Government Code: SWORN STATEMENT OF ACCOUNT Before me, the undersigned authority, on this day personally appeared [Name of Claimant’s Representative], who, after being by me duly sworn did depose and state: 1. My Name is [Name] and I am the [Title] of [Claimant] and am over the age of 18 and authorized to make this affidavit and the statements contained herein. FORM 3.2: SUBCONTRACTORS NOTICE TO PRIME AND SURETY OF UNPAID ACCOUNT (Cont.) 2. [Claimant] has an outstanding and unpaid claim in the amount of [Dollar Amount] for labor and/or materials provided during the months of [Months and Year] under contact with [Name of Party Contracted With]. 3. This amount is just and correct and all lawful offsets, payments and credits known to the undersigned have been allowed. 4. [If applicable:] This amount includes contractual retainage in the amount of [Dollar Amount] which is now due or will become due on or about [Due Date]. 5. The invoices attached hereto are true and correct copies of the original invoices on which the above- described claim is based. By: ___________________________________ [Name of Claimant’s Representative], [Title] and Authorized Representative of [Claimant] STATE OF TEXAS COUNTY OF __________ § § Affiant, upon oath and after being duly sworn, states that he has read the above application and facts contained therein and that such statements are true and correct. Subscribed and sworn on this the _____ day of _______________ , 20___. _______________________________________ Notary Public in and for the State of Texas FORM 3.3: SUBCONTRACTORS NOTICE OF UNPAID RETAINAGE [Date] Via Certified Mail No. [Number] Return Receipt Requested [Surety’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Prime Contractor’s Name and Address] ANY TIER: This mustRetainage be sent to the prime Notice ofform Claim for Unpaid regarding: [Project Description] contractor and surety no later than the Our company has provided labor and/or materials to the above-referenced project under a day after date of final written contract with 90th [Name of Party Contracted With]. the completion of the Code, entire —thenot In accordance with the Texas Government pleaseproject be advised that total contract price for this labor and/or materials provided is [Dollar Amount]. We have been paid the total amount of [Dollar final ofcompletion of your scope of work. Amount], leaving a balance [Dollar Amount]. This amount due and owing is for retainage withheld Re: during the course of the project. Enclosed please find a copy of our invoice(s) for this work. Sincerely, [Claimant] By: __________________________________ Title: _________________________________ Enclosure cc: Via Certified Mail No. [Number] Return Receipt Requested [Owner’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Name and Address of Party Contracted With] FORM 3.4: PRIME CONTRACTOR OR SURETY REQUEST FOR INFORMATION ON BOND CLAIM [Date] Via Certified Mail No. [Number] Return Receipt Requested [Claimant’s Name and Address] Re: Request for Information on Bond Claim regarding: [Project Description] This letter acknowledges receipt of your payment bond claim on the above-referenced project on [Date]. In accordance with the Texas Government Code, please provide the following information regarding your claim: 1. Copies of any applicable written agreements or purchase orders under which you have provided labor and/or materials to the project; 2. Copies of any statements or payment requests showing the amount claimed and the work performed for which the claim is made; and 3. The estimated amount due for each calendar month in which you have performed work or provided labor. The Texas Government Code requires that you provide this information within 30 days of receipt of this request. Sincerely, [Surety or Prime Contractor] FORM 3.5: SUBCONTRACTORS RESPONSE TO REQUEST FOR INFORMATION ON BOND CLAIM [Date] Via Certified Mail No. [Number] Return Receipt Requested [Surety’s Name and Address] Via Certified Mail No. [Number] Return Receipt Requested [Prime Contractor’s Name and Address] Re: Response to [Surety or Prime Contractor]’s Request for Information on Bond Claim regarding: [Project Description] Receipt of your letter dated [Date] requesting information regarding our payment bond claim on above-referenced project is acknowledged. In response to your request we have included the following information: 1. 2. A copy of the contract with [Name of Party Contracted With] under which we have provided labor and/or materials to the project; and Copies of all invoices showing the amount claimed and the work performed on which our claim is based. The estimated amount due for each calendar month in which we performed work on the project is as follows: [Description of each month work performed and the amount owed for each month]. Sincerely, [Claimant] By: __________________________________ Title: _________________________________ Enclosure SUMMARY OF PROCEDURES: PUBLIC WORK PAYMENT BOND CLAIMS Notices Due in 2nd Month Notices Due in 3rd Month Other Requirements First-Tier Subcontractor (Direct contractual relationship with prime contractor) None Notice of Claim: sent to surety and prime contractor by 15th day of 3rd month following each month in which work was performed for which payment was not received File suit: against surety in no less than 61 days, but within 1 year of date Notice of Unpaid Account is mailed to surety Second-Tier Subcontractor (Direct contractual relationship with first-tier subcontractor) Notice of Claim: sent to prime contractor by 15th day of 2nd month following each month in which work was performed for which payment was not received Notice of Claim: sent to surety, 1st tier subcontractor and prime contractor by 15th day of 3rd month following each month in which work was performed for which payment was not received File suit: against surety in no less than 61 days, but within 1 year of date Notice of Unpaid Account is mailed to surety Type of Claimant TABLE OF NOTICE DEADLINES: PUBLIC WORK PAYMENT BOND CLAIMS First Tier Subcontractor (Direct contractual relationship with prime contractor) Second Tier Subcontractor (Direct contractual relationship with first-tier subcontractor) Month Work Furnished Notice of Unpaid Accounts: to surety and prime contractor Notice of Unpaid Accounts: to prime contractor Notice of Unpaid Accounts: to surety and prime contractor January April 15 March 15 April 15 February May 15 April 15 May 15 March June 15 May 15 June 15 April July 15 June 15 July 15 May August 15 July 15 August 15 June September 15 August 15 September 15 July October 15 September 15 October 15 August November 15 October 15 November 15 September December 15 November 15 December 15 October January 15 December 15 January 15 November February 15 January 15 February 15 December March 15 February 15 March 15 Statutory Releases Discussion Presented by Jason C. Spencer Shareholder, Andrews Myers 512.900.3032 jspencer@andrewsmyers.com