Via Certified Mail No. [Number] Return Receipt Requested

advertisement
Texas Mechanic’s Lien &
Payment Bond Claims
Issues
Presented By:
Jason C. Spencer
Telephone: (512) 900-3032
jspencer@andrewsmyers.com
www.andrewsmyers.com
Contractors Ice Bucket Challenge ?!?
Ice Bucket Challenge
https://
INTRODUCTION
I.
Chapter 53 of the Texas Property Code – private projects
II.
Chapter 2253 of the Texas Government Code (f/k/a “The MacGregor Act”)
Texas = very complicated lien and bond law
Deadlines are strictly enforced
If you miss a deadline, your claim will not be valid and your right to payment will be
unnecessarily limited.
Property Code = “original contractor”
Government Code = “prime contractor.”
When in doubt, send each form to everyone above you in the contracting chain, as well as any
surety providing a payment bond.
 CMRRR, facsimile, etc. - - - proof of SENDING
th
15 ,
th
15 ,
th
15
!!!
PART ONE:
NON-RESIDENTIAL LIEN CLAIMS
“COMMERCIAL”
OVERVIEW
Contractors and suppliers of all tiers are provided lien rights on non-residential projects under
Chapter 53 of the Texas Property Code. The lien provides an additional layer of protection against
non-payment for contracting parties by giving them recourse against the owner of the property. When
properly perfected, a contractor may force the sale of the property to satisfy its claim for unpaid labor
and/or materials.
The steps that must be taken to perfect a lien claim are complex. To simplify this process, we have
broken down these steps into four primary sections:
(1)
(2)
(3)
(4)

Gathering Information,
Early Notices,
Notices of Unpaid Account, and
Perfecting the Claim.
The benefit of a lien claim cannot be overstated
Direct recourse against the improved property
Superior to other creditors of the owner with respect to the improvements
Distinction: private payment bond vs. indemnity bond (“bond around”) vs. public payment bond
SECTION ONE: GATHERING INFORMATION
FORM 1.1:
REQUEST FOR INFORMATION TO OWNER
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Re:
Request for Information to Owner regarding:
[Project Description]
Our company is providing labor and/or materials to improve the above-referenced project. It is our
understanding that you are the owner of the real property and improvements at the project. If this is incorrect,
please advise us immediately.
In accordance with the Texas Property Code, please furnish us with the following information:
(1) a description of the real property being improved legally sufficient to identify it;
(2) whether there is a surety bond and, if so, the name and last known address of the surety and a copy of the
bond; and
(3) whether there are any prior recorded liens or security interests on the real property being improved and, if so,
the name and address of any person having a lien or security interest.
Pursuant to the Texas Property Code, you are requested to provide this information no later than 10
days following receipt of this request.
Sincerely,
[Claimant]
FORM 1.2:
SUBCONTRACTORS REQUEST FOR INFORMATION TO ORIGINAL CONTRACTOR
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Original Contractor’s Name and Address]
Re:
Request for Information to Original Contractor regarding:
[Project Description]
Our company is providing labor and/or materials to improve the above-referenced project. It is our
understanding that you are the original contractor for the construction of these improvements at the project. If
this is incorrect, please advise us immediately. In accordance with the Texas Property Code, please furnish
us with the following information:
(1) the name and last known address of the person to whom you have furnished labor and/or materials for the
project; and
(2) whether you have furnished or have been furnished a payment bond for any of the work on the project and, if
so, the name and last known address of the surety(s) and a copy of the bond(s).
Pursuant to the Texas Property Code, you are requested to provide this information not later than 10
days following receipt of this request.
Sincerely,
[Claimant]
FORM 1.3:
ORIGINAL CONTRACTORS RESPONSE TO REQUEST FOR INFORMATION
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Claimant’s Name and Address]
Re:
[Claimant’s] Request for Information regarding:
[Project Description]
Receipt of your letter dated [Date] requesting information regarding the above-referenced project is
acknowledged. The name and address of the person to whom the undersigned has furnished labor and/or
materials for the project is: [Owner’s Name and Address].
[Alternate 1] The undersigned has not furnished and no other party has furnished to us a payment bond for any of
the work on the above-referenced project.
[Alternate 2] We have furnished or otherwise been furnished with a payment bond(s) for the above-referenced
project. A copy of the bond(s) is enclosed. The name and last known address of the surety(s) is: [Surety’s Name
and Address].
If you do not have a direct contractual relationship with the undersigned, we are entitled to actual
costs, not to exceed $25.00, incurred in complying with your request. Our actual costs exceed this amount;
therefore, please remit $25.00 as reimbursement for our costs of compliance.
Sincerely,
[Original Contractor]
SECTION TWO: SUBCONTRACTORS EARLY NOTICES
FORM 2.1:
SUBCONTRACTORS NOTICE OF RETAINAGE AGREEMENT
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Original Contractor’s Name and Address]
Re:
AMENDED BY HB 1390 Eff. Sept. 1,
2011 = 30th day after your work or prime
contract is completed, terminated or
abandoned
Notice of Retainage Agreement regarding:
Project: [Project Description]
Our company has entered into a contract with [Name of Party Contracted With] on the abovereferenced construction project. It is our understanding that you are the owner of the project and/or
original contractor of improvements thereon. If this is incorrect, please advise us immediately.
The agreement between our company and [Name of Party Contracted With] calls for us to
furnish the following labor and/or materials to the project: [General Description of Work]. In
accordance with the Texas Property Code, please be advised that this contract includes a “Contractual
Retainage Agreement” as defined therein. The contract requires retainage to be withheld as follows:
[Retainage as stated in your contract, e.g. 10% from each draw]. The retainage is due [Retainage due
date as stated in your contract, e.g. 30 days from completion]. Copies of the applicable portions of our
contract are enclosed for your review.
Sincerely,
[Claimant]
Enclosure
FORM 2.2:
SUBCONTRACTOR OR SUPPLIERS NOTICE OF SPECIALLY FABRICATED MATERIALS
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Original Contractor’s Name and Address]
Re:
15th day of the 2nd month after your
specialty order is received
Notice of Specially Fabricated Materials regarding:
Project: [Project Description]
Our company is providing labor and/or materials to the above-referenced project. It is our
understanding that you are the owner of the project and/or the original contractor of improvements
thereon. If this is incorrect, please advise us immediately.
In accordance with the Texas Property Code, please be advised that we have received and
accepted an order from [Name of Party Placing Order] for specially fabricated items to be incorporated
into the project. The price agreed upon for said items is [Dollar Amount]. A copy of the order is enclosed
for your reference.
Sincerely,
[Claimant]
Enclosure
SECTION THREE: NOTICES OF UNPAID DRAWS
FORM 3.1:
SUBCONTRACTORS NOTICE TO ORIGINAL CONTRACTOR OF UNPAID ACCOUNT
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Original Contractor’s Name and Address]
Re:
Notice to Original Contractor of Unpaid Account regarding:
[Project Description]
This form must be sent to the
original contractor no later than the
Dear [Original Contractor]:
fifteenth day of the second month
Our company has furnished labor and/or materials to the above-referenced project under a
following each month in which you
contract with [Name of Party Contracted With]. It is our understanding that you are the original contractor
on the project and that [Name
of Party Contracted
With] is operating
underbut
a contract with you or another
provided
labor
and/or
materials
one of your subcontractors. If this incorrect, please advise us immediately.
were not paid for them.
In accordance with the Texas Property Code, please be advised that we are owed [Dollar
Amount] under our contract with [Name of Party Contracted With] for labor and/or materials furnished to
the project that are generally described as follows: [General Description of Work Performed]. This labor
and/or materials was provided during the months of [Months and Year Work was Performed]. Enclosed
please find a copy of our invoice(s) for this work.
On a recurring basis—you must
send this notice for each month that
you were not paid.
Sincerely,
[Claimant]
Enclosure(s)
cc:
Via Certified Mail No. [Number]
Return Receipt Requested
[Name and Address of Party Contracted With]
FORM 3.2:
SUBCONTRACTORS NOTICE TO OWNER OF UNPAID ACCOUNT
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
This form
must be sent to the OWNER no later
Notice to Owner of Unpaid Account regarding:
[Project
Description]day of the third month
than the
fifteenth
following
each month
inmaterials
which
you
providedproject under a contract with
Our
company has furnished
labor and/or
to the
above-referenced
[Name of Party Contracted With]. It is our understanding that you are the owner of the real property on which the
labor and/or materials but were not paid for
improvements have been made. If this is incorrect, please advise us immediately.
them.
Re:
In accordance with the Texas Property Code, please be advised that we are owed [Dollar Amount] under
our contract with [Name of Party Contracted With] for labor and/or materials that are generally described as follows:
[General Description of Work Performed]. This labor and/or materials was provided during the months of [Months
and Year Work was Performed]. Enclosed please find a copy of our invoice(s) for this work. This claim has accrued
under Section 53.053 of the Texas Property Code and is past due under the terms of the above-referenced
contract. Demand is hereby made for payment of this amount under Section 53.083 of the Texas Property
Code.
Under the Texas Property Code, we must provide you with the following notice: IF THIS
ACCOUNT REMAINS UNPAID, YOU WILL BE PERSONALLY LIABLE OR YOUR PROPERTY SUBJECTED
TO A LIEN UNLESS YOU WITHHOLD PAYMENT FROM YOUR ORIGINAL CONTRACTOR FOR THE
PAYMENT OF THE CLAIM OR UNLESS THE CLAIM IS OTHERWISE PAID OR SETTLED.
Sincerely,
[Claimant]
Enclosure(s)
cc:
Via Certified Mail No. [Number]
Return Receipt Requested
[Original Contractor’s Name and Address]
On a recurring basis—you must send this notice
for each month that you were not paid.
SECTION FOUR: THE LIEN AFFIDAVIT
Lien must actually be filed in order to have a right to any money from the
owner.
It is filed in the real property records of the County Clerk’s office where the
project is located.
Original contractors must file the lien affidavit no later than the fifteenth day
of the fourth month following:
(1)
(2)
(3)
written termination of your contract,
abandonment of your contract, or
completion of your work.
Subcontractors that want their lien to attach to the retained funds so
that they are paid from the retained fund in preference to the general
contractor must file the lien affidavit within 30 days of completion of
the project.
Filing your lien affidavit is not
the last step. A copy of the lien
affidavit must be sent to the owner
no later than the fifth (calendar)
day following the day of filing with
the County Clerk.
FORM 4.1:
ORIGINAL CONTRACTOR AFFIDAVIT OF MECHANIC’S LIEN
STATE OF TEXAS
COUNTY OF [COUNTY]
§
§
§
AFFIDAVIT OF MECHANIC’S LIEN
BEFORE ME, Notary Public and in for the State of Texas, on this day personally appeared
[Name], who upon his oath, deposed and stated the following:
1.
My name is [Name]. I am the [Title] of [Claimant] (“Claimant”). I am over 18 years of
age, have personal knowledge of the facts set forth below and am competent and
authorized to make this Affidavit on Claimant’s behalf as the sworn statement of its
claim.
2.
Claimant furnished labor and/or materials for the improvement of real property
located at [Address of Project] and more particularly described in the real property
records of [County of Project], Texas as: [Legal Description].
3.
Claimant furnished labor and materials under a contract with: [Name and Address
of Owner].
4.
The name and last known address of the original contractor for such improvements
is: [Original Contractor’s Name and Address].
5.
The name and last known address of the owner or reputed owner of the land and
improvements thereon is: [Owner’s Name and Address].
6.
The labor, materials, and/or work furnished by Claimant are generally described as
follows: [General Description]. Claimant is hereby asserting a claim for work
performed and/or materials furnished in the following months: [Months and Year
Work was Performed].
FORM 4.1:
ORIGINAL CONTRACTOR AFFIDAVIT OF MECHANIC’S LIEN (Cont.)
7.
After allowing all just credits, offsets, and payments, the amount of [Dollar Amount] remains
unpaid and is due and owing to Claimant.
8.
Claimant’s name and address are as follows: [Name and Mail Address]. [Include Physical
Address if Different].
9.
Claimant claims a lien against all the above described land and improvements thereon in the
amount shown above pursuant to Chapter 53 of the Property Code of the State of Texas, and
makes this sworn statement of claim in support thereof.
10.
Claimant also claims a constitutional lien on such property pursuant to the provisions of
Article 16, Section 37 of the Texas Constitution to the extent that Claimant is deemed an
original contractor.
11.
One (1) copy of this Affidavit is being sent by Certified Mail, Return Receipt Requested and
First Class Mail to the Owner at all addresses described above.
By:
[Name], [Title] and
Authorized Representative of Claimant
STATE OF TEXAS
COUNTY OF _____________
§
§
SUBSCRIBED AND SWORN TO BEFORE ME, by [Name], [Title] and Authorized Representative of
Claimant on this _____ day of _______________ , 20___ to certify which witness my hand and official seal of office.
_____________
Notary Public – State of Texas
After Recordation Please Return to:
[Claimant’s Name and Address]
FORM 4.2:
SUBCONTRACTOR AFFIDAVIT OF MECHANIC’S LIEN
STATE OF TEXAS
COUNTY OF [COUNTY]
§
§
§
AFFIDAVIT OF MECHANIC’S LIEN
BEFORE ME, Notary Public and in for the State of Texas, on this day personally appeared
[Name], who upon his oath, deposed and stated the following:
1.
My name is [Name]. I am the [Title] of [Claimant] (“Claimant”). I am over 18 years of
age, have personal knowledge of the facts set forth below and am competent and
authorized to make this Affidavit on Claimant’s behalf as the sworn statement of its
claim.
2.
Claimant furnished labor and/or materials for the improvement of real property
located at [Address of Project] and more particularly described in the real property
records of [County of Project], Texas as: [Legal Description].
3.
Claimant furnished labor and materials under a contract with: [Name and Address
of Party Contracted With].
4.
The name and last known address of the original contractor for such improvements
is: [Original Contractor’s Name and Address].
5.
The name and last known address of the owner or reputed owner of the land and
improvements thereon is: [Owner’s Name and Address].
6.
The labor, materials, and/or work furnished by Claimant are generally described as
follows: [General Description]. Claimant is hereby asserting a claim for work
performed and/or materials furnished in the following months: [Months and Year
Work was Performed].
7.
After allowing all just credits, offsets, and payments, the amount of [Dollar Amount]
remains unpaid and is due and owing to Claimant.
8.
Claimant’s name and address are as follows: [Name and Mail Address]. [Include
Physical Address if Different].
9.
Notice of claim was sent to the Owner and the Original Contractor at all addresses
listed above as follows:
FORM 4.2:
SUBCONTRACTOR AFFIDAVIT OF MECHANIC’S LIEN (Cont.)
Notice was sent on [Date] to [Owner] via Certified Mail No. [Number], Return Receipt
Requested and first Class Mail.
Notice was sent on [Date] to [Original Contractor] via Certified Mail No.
[Number], Return Receipt Requested and First Class Mail.
10.
11.
Claimant claims a lien against all the above described land and improvements
thereon in the amount shown above pursuant to Chapter 53 of the Property Code of
the State of Texas, and makes this sworn statement of claim in support thereof.
One (1) copy of this Affidavit is being sent by Certified Mail, Return Receipt
Requested and First Class Mail to the Owner and the Original Contractor at all
respective addresses described above.
By:
[Name], [Title] and
Authorized Representative of Claimant
STATE OF TEXAS
COUNTY OF _____________
§
§
SUBSCRIBED AND SWORN TO BEFORE ME, by [Name], [Title] and Authorized Representative
of Claimant on this _____ day of _______________ , 20___ to certify which witness my hand and official
seal of office.
________________
Notary Public – State of Texas
After Recordation Please Return to:
[Claimant’s Name and Address]
FORM 4.3:
NOTICE OF MECHANIC’S LIEN FILING
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Original Contractor’s Name and Address]
Re:
Lien Affidavit of [Claimant’s Name] regarding:
[Project Description]
Enclosed is a copy of our mechanic’s lien which we are filing with the county clerk. Demand is hereby
made for the immediate payment of the amount claimed in the affidavit. In addition to this principal sum, interest
may be accruing on this debt at the applicable statutory rate.
You are hereby advised that if this account remains unpaid, your property may be subject to
foreclosure for satisfaction of the lien. We will be pleased to release the same upon receipt of the balance due
and owing. Please contact us immediately so that this matter can be resolved without formal legal action.
Sincerely,
[Claimant]
Enclosure
SUMMARY OF PERFECTION PROCEDURES: NON-RESIDENTIAL LIEN CLAIMS
TABLE OF NOTICE DEADLINES: NON-RESIDENTIAL LIEN CLAIMS
PART TWO:
PUBLIC WORK PAYMENT BOND CLAIMS
Public projects
More streamlined procedure
* 1 Year Statute of limitations plus 60-day pre-suit notice
Prime (“Original”) Contractors may not avail themselves of a payment
bond claim.
* Personal guaranties
FORM 1.1:
SUBCONTRACTORS REQUEST FOR INFORMATION TO PRIME CONTRACTOR
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Prime Contractor’s Name and Address]
Re:
Request for Information to Prime Contractor regarding:
[Project Description]
Our company is providing labor and/or materials to improve the above-referenced project under a
contract with [Name of Party Contracted With].
In accordance with the Texas Government Code, we hereby request that you provide the following
information:
1.
The name and last known address of the governmental entity with whom you have contracted
to provide
public work for the project; and
2.
A copy of the payment and performance bonds for the project, including bonds furnished by or
to you.
As required by the Texas Government Code, please provide this information within 10 days of receipt
of this request. If our contract is not directly with you, we will pay your actual cost of providing this
information, not to exceed $25, upon request.
Sincerely,
[Claimant]
By: __________________________________
Title: _________________________________
FORM 1.2:
SUBCONTRACTORS REQUEST FOR INFORMATION TO OWNER
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Re:
Request for Information to Owner regarding:
[Project Description]
Our company has provided labor and/or materials to improve the above-referenced project under a
contract with [Name of Party Contracted With]. We have not been paid in full for this labor and/or
materials.
In accordance with the Texas Government Code, we hereby request certified copies of:
1.
The payment bond provided by [Prime Contractor] for construction of the improvements; and
2.
The public work contract for which the bond was given.
We will pay your reasonable fee for the actual cost of preparation of the copies upon request.
Sincerely,
[Claimant]
By: __________________________________
Title: _________________________________
FORM 1.2:
SUBCONTRACTORS REQUEST FOR INFORMATION TO OWNER (Cont.)
STATE OF TEXAS
COUNTY OF __________
§
§
Affiant, upon oath and after being duly sworn, states that he has read the above application
and facts contained therein and that such statements are true and correct.
Subscribed and sworn on this the _____ day of _______________ , 20___.
_______________________________________
Notary Public in and for the State of Texas
FORM 1.3:
REQUEST FOR INFORMATION TO SUBCONTRACTOR
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Subcontractor’s Name and Address]
Re:
Request for Information to Subcontractor regarding:
[Project Description]
It is our understanding that you are a subcontractor on the above-referenced public work project. In
accordance with the Texas Government Code, we hereby request that you provide the following
information:
1.
2.
3.
4.
The name and last known address of each person from whom you have purchased labor
and/or material for the project;
The name and last known address of each person to whom you have provided labor and/or
material for the project;
A statement of whether you have furnished a payment bond for the project; and
If a payment bond has been provided, the name and last known address of the surety on the
bond and copy of that bond.
As required by the Texas Government Code, please provide this information within 10 days of receipt
of this request. If our contract is not directly with you, we will pay your actual cost of providing this
information, not to exceed $25, upon request.
Sincerely,
By: __________________________________
Title: _________________________________
[Claimant]
SECTION TWO: EARLY NOTICES
FORM 2.1:
SUBCONTRACTORS NOTICE OF RETAINAGE AGREEMENT
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Prime Contractor’s Name and Address]
Re:
Notice of Retainage Agreement regarding:
[Project Description]
SECOND TIER (or lower) ONLY:
Our company has entered into a contract with [Name of Party Contracted With] on the abovereferenced construction project. This agreement requires us to furnish the following labor and/or
materials to the project: [General Description of Work].
This form must be sent no later than
In accordance
with the Texas Government
Code,
please
be advised
that this contract includes a
the
fifteenth
day
of
the
second
month
“retainage” provision as defined therein. The contact requires retainage to be withheld as follows:
[Retainage as stated
in your contract,when
e.g. 10% from
each draw].
The retainage first
is due [Retainage due as
following
the
claimant
stated in your contract, e.g. 30 days from completion]. The total sum anticipated to be retained under this
contract is [Dollar
Amount]. Copies
of the and/or
applicable portions
of our contract
are enclosed for your
provides
labor
materials
to
the
review.
Sincerely,
project.
[Claimant]
By: __________________________________
Title: _________________________________
Enclosure
cc:
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Name and Address of Party Contracted With]
FORM 2.2:
SUBCONTRACTORS OR SUPPLIERS NOTICE OF SPECIALLY FABRICATED MATERIALS
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Prime Contractor’s Name and Address]
Re:
SECOND
(or
Notice of SpeciallyTIER
Fabricated Materials
[Project Description]
ONLY:
lower)
Our company is providing labor and/or materials to the above-referenced project. In
accordance with the Texas Government Code, please be advised that we have received and accepted an
order from [Name of Party Contracted With] for specially fabricated items to be incorporated into the
project. These items are generally described as: [General Description of Items] [or] [as described on the
attached order]. The price agreed upon for said items is [Dollar Amount]. A copy of the order is enclosed
for your reference.
This form must be sent no later
than the fifteenth day of the
second month following
when the
Sincerely,
claimant received the
order for
[Claimant]
specially fabricated materials.
By: __________________________________
Title: _________________________________
Enclosure
cc:
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Name and Address of Party Contracted With]
SECTION THREE:
SUBCONTRACTORS NOTICES OF UNPAID DRAWS
FORM 3.1:
SUBCONTRACTORS NOTICE TO PRIME CONTRACTOR OF UNPAID ACCOUNT
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Prime Contractor’s Name and Address]
Re:
Notice to Prime Contractor of Unpaid Account regarding:
SECOND
TIER (or lower) ONLY:
[Project Description]
Our company has provided labor and/or materials to the above-referenced project under a
written contract with [Name of Party Contracted With], on which you are the prime contractor.
This form must be sent no later than
In accordance with the Texas Government Code, please be advised that we are owed [Dollar
the fifteenth day of the second
Amount] under this contract for labor and/or materials furnished to the project that are generally
described as: [General Description of Work]. Enclosed please find a copy of our invoice(s) for this work.
month following each month the
If this claim is not promptly paid, we will proceed to perfect our claim against you and your surety. This
notice is sent so that you may have an opportunity to see that his amount is paid in full prior to our taking
claimant provided the labor and
such action.
Sincerely,
materials.
[Claimant]
By: __________________________________
Title: _________________________________
Enclosure
cc:
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Name and Address of Party Contracted With]
FORM 3.2:
SUBCONTRACTORS NOTICE TO PRIME AND SURETY OF UNPAID ACCOUNT
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Surety’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Prime Contractor’s Name and Address]
ANY TIER:
Notice to Surety and Prime Contractor of Unpaid Account regarding:
This
form must be sent no later than
[Project Description]
the fifteenth day of the third month
Our company has furnished labor and/or materials to the above-referenced project under a
written contract with [Name of Party Contracted With].
following each month the claimant
In accordance with the Texas Government Code, please be advised that we are owed [Dollar
provided the labor and materials.
Amount] under this contract for labor and/or materials that are generally described as follows: [General
Re:
Description of Work Performed]. Enclosed please find a copy of our invoice(s) for this work.
The following Sworn Statement of Account is provided as required by the Texas Government
Code:
SWORN STATEMENT OF ACCOUNT
Before me, the undersigned authority, on this day personally appeared [Name of Claimant’s
Representative], who, after being by me duly sworn did depose and state:
1. My Name is [Name] and I am the [Title] of [Claimant] and am over the age of 18 and
authorized to make this affidavit and the statements contained herein.
FORM 3.2:
SUBCONTRACTORS NOTICE TO PRIME AND SURETY OF UNPAID ACCOUNT (Cont.)
2. [Claimant] has an outstanding and unpaid claim in the amount of [Dollar Amount] for labor
and/or materials provided during the months of [Months and Year] under contact with [Name of Party
Contracted With].
3. This amount is just and correct and all lawful offsets, payments and credits known to the
undersigned have been allowed.
4. [If applicable:] This amount includes contractual retainage in the amount of [Dollar Amount]
which is now due or will become due on or about [Due Date].
5. The invoices attached hereto are true and correct copies of the original invoices on which
the above- described claim is based.
By: ___________________________________
[Name of Claimant’s Representative],
[Title] and Authorized Representative of [Claimant]
STATE OF TEXAS
COUNTY OF __________
§
§
Affiant, upon oath and after being duly sworn, states that he has read the above application
and facts contained therein and that such statements are true and correct.
Subscribed and sworn on this the _____ day of _______________ , 20___.
_______________________________________
Notary Public in and for the State of Texas
FORM 3.3:
SUBCONTRACTORS NOTICE OF UNPAID RETAINAGE
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Surety’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Prime Contractor’s Name and Address]
ANY TIER:
This
mustRetainage
be sent
to the prime
Notice ofform
Claim for Unpaid
regarding:
[Project Description]
contractor and surety no later than the
Our company has provided labor and/or materials to the above-referenced project under a
day
after
date of final
written contract with 90th
[Name of Party
Contracted
With]. the
completion
of the Code,
entire
—thenot
In accordance
with the Texas Government
pleaseproject
be advised that
total contract price
for this labor and/or materials provided is [Dollar Amount]. We have been paid the total amount of [Dollar
final ofcompletion
of your
scope
of work.
Amount], leaving a balance
[Dollar Amount]. This
amount due
and owing
is for retainage withheld
Re:
during the course of the project. Enclosed please find a copy of our invoice(s) for this work.
Sincerely,
[Claimant]
By: __________________________________
Title: _________________________________
Enclosure
cc:
Via Certified Mail No. [Number]
Return Receipt Requested
[Owner’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Name and Address of Party Contracted With]
FORM 3.4:
PRIME CONTRACTOR OR SURETY REQUEST FOR INFORMATION ON BOND CLAIM
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Claimant’s Name and Address]
Re:
Request for Information on Bond Claim regarding:
[Project Description]
This letter acknowledges receipt of your payment bond claim on the above-referenced project on
[Date]. In accordance with the Texas Government Code, please provide the following information
regarding your claim:
1.
Copies of any applicable written agreements or purchase orders under which you have
provided labor and/or materials to the project;
2.
Copies of any statements or payment requests showing the amount claimed and the work
performed for which the claim is made; and
3.
The estimated amount due for each calendar month in which you have performed work or
provided labor.
The Texas Government Code requires that you provide this information within 30 days of receipt of
this request.
Sincerely,
[Surety or Prime Contractor]
FORM 3.5:
SUBCONTRACTORS RESPONSE TO REQUEST FOR INFORMATION ON BOND CLAIM
[Date]
Via Certified Mail No. [Number]
Return Receipt Requested
[Surety’s Name and Address]
Via Certified Mail No. [Number]
Return Receipt Requested
[Prime Contractor’s Name and Address]
Re:
Response to [Surety or Prime Contractor]’s Request for Information on Bond Claim
regarding:
[Project Description]
Receipt of your letter dated [Date] requesting information regarding our payment bond claim on
above-referenced project is acknowledged. In response to your request we have included the
following information:
1.
2.
A copy of the contract with [Name of Party Contracted With] under which we have provided
labor and/or materials to the project; and
Copies of all invoices showing the amount claimed and the work performed on which our
claim is based.
The estimated amount due for each calendar month in which we performed work on the project is as
follows: [Description of each month work performed and the amount owed for each month].
Sincerely,
[Claimant]
By: __________________________________
Title: _________________________________
Enclosure
SUMMARY OF PROCEDURES: PUBLIC WORK PAYMENT BOND CLAIMS
Notices Due in 2nd Month
Notices Due in 3rd Month
Other Requirements
First-Tier Subcontractor
(Direct contractual
relationship with prime
contractor)
None
Notice of Claim:
sent to surety and prime
contractor by 15th day of 3rd
month following each month
in which work was performed
for which payment was not
received
File suit:
against surety in no less than
61 days, but within 1 year of
date Notice of Unpaid
Account is mailed to surety
Second-Tier Subcontractor
(Direct contractual
relationship with first-tier
subcontractor)
Notice of Claim:
sent to prime contractor by
15th day of 2nd month
following each month in
which work was performed
for which payment was not
received
Notice of Claim:
sent to surety, 1st tier
subcontractor and prime
contractor by 15th day of 3rd
month following each month
in which work was performed
for which payment was not
received
File suit:
against surety in no less than
61 days, but within 1 year of
date Notice of Unpaid
Account is mailed to surety
Type of Claimant
TABLE OF NOTICE DEADLINES: PUBLIC WORK PAYMENT BOND CLAIMS
First Tier Subcontractor
(Direct contractual relationship with
prime contractor)
Second Tier Subcontractor
(Direct contractual relationship with first-tier subcontractor)
Month Work Furnished
Notice of Unpaid Accounts:
to surety and prime contractor
Notice of Unpaid Accounts:
to prime contractor
Notice of Unpaid Accounts:
to surety and prime contractor
January
April 15
March 15
April 15
February
May 15
April 15
May 15
March
June 15
May 15
June 15
April
July 15
June 15
July 15
May
August 15
July 15
August 15
June
September 15
August 15
September 15
July
October 15
September 15
October 15
August
November 15
October 15
November 15
September
December 15
November 15
December 15
October
January 15
December 15
January 15
November
February 15
January 15
February 15
December
March 15
February 15
March 15
Statutory Releases
Discussion
Presented by
Jason C. Spencer
Shareholder, Andrews Myers
512.900.3032
jspencer@andrewsmyers.com