Northside Piers – Brooklyn, NY Structural System Redesign Jeremiah Ergas AE 482 – 5th Year Senior Thesis Structural Option April 15th, 2008 Faculty Consultant: Dr. Ali Memari Presentation Outline Intro Intro Building Overview Redesign Goals Slab Design Shear Wall Design Construction Management Conclusions Acknowledgements Questions??? Presentation Outline Intro Building Background – Location Northside Piers - 4 North 5th Street, Brooklyn, NY Manhattan Overview Building Building Background North East United States Redesign Goals Slab Design Shear Wall Design Construction Management Conclusions Acknowledgements Questions??? Presentation Outline Building Background - Architecture Intro - 29 Story Condominium Tower Overview Building Building Background - 176 units Redesign Goals - Two typical floor plans (7500SF and 6200SF) Slab Design Shear Wall Design Construction Management Conclusions Acknowledgements Questions??? - Glass Cladding System that allows for floor to ceiling views - No drop ceiling over living spaces Presentation Outline Building Background – Structural System Intro Overview Building Building Background Redesign Goals Slab Design Shear Wall Design Construction Management Conclusions Acknowledgements Questions??? - Flat plate two-way mild reinforced slab - Irregular Column Scheme - Shear Walls around central core with additional wall Presentation Outline Redesign Goals Intro Building Overview Redesign Goals Redesign Goals Redesign Goals Slab Design Shear Wall Design - Make structure more cost effective - Meet or improve serviceability of structure Structural Elements Studied - Floor Slab System - Mild reinforced vs. Post-Tensioned? - Shear Wall System - More optimal layout? Construction Management Other Disciplines Considered Conclusions Acknowledgements Questions??? - Construction Management - Acoustics - Mechanical Exhaust Risers Slab Design - Introduction Presentation Outline Intro Slab Redesign Goals Building Overview Make slab more cost effective - Meet or improve serviceability of structure Why Post-Tensioned System? Redesign Goals SlabDesign Design Slab - 26th–Roof Shear Wall Design - No room for beams - Tendons improve slab efficiency - Tendons reduce deflections Design Method Construction Management Conclusions 3rd–25th Floor - RAM Concept with Post-Tensioned spreadsheets - Must meet ACI318-05 Design Loads (Floor) Acknowledgements Questions??? Design Loads (Balconies) - 40psf Live - 60psf Live - 30psf Super - 15psf Super Presentation Outline Slab Design – Current System 3rd–25th Floor Typical Slab Intro 26th-Roof Typical Slab Building Overview Redesign Goals SlabDesign Design Slab 26th–Roof Shear Wall Design Construction Management 3rd–25th Floor Conclusions Acknowledgements - 8” Slabs with #5’s @ 12” o/c on Top and Bottom going both ways Questions??? - Additional bars added as shown on plan Presentation Outline Slab Design – Current System 3rd–25th Floor Long-Term Deflection Intro 26th-Roof Long-Term Deflection Building Overview Redesign Goals SlabDesign Design Slab 26th–Roof Shear Wall Design Construction Management Conclusions 3rd–25th Floor Maximum Long-Term Deflection: 0.67” Maximum Long-Term Deflection: 0.74” Acknowledgements ACI318 Limit (30’ Span): L/480 = 0.75” Questions??? Slab Design – Post-Tensioned System Presentation Outline Intro Building Overview 3rd–25th Floor Tendon Plans Column Shifted 26th-Roof Tendon Plans Column Added Redesign Goals SlabDesign Design Slab 26th–Roof Shear Wall Design Construction Management 3rd–25th Floor Conclusions Acknowledgements Questions??? Maximum Long-Term Deflection: 0.48” Maximum Long-Term Deflection: 0.49” Slab Design – Post-Tensioned System Presentation Outline Intro Tendon Stress Building Overview - 35% Banded tendon Load-Balancing Percentage - 40% Uniform tendon Load-Balancing Percentage Redesign Goals SlabDesign Design Slab - Maximum P/A of 320psi 26th–Roof Design Details Shear Wall Design Construction Management Conclusions Acknowledgements Questions??? 3rd–25th Floor - 7” Slabs - ½” Unbonded Tendons - Typical Profile heights of 5.75” and 1.25” - Typically #4 bars @ 24”o/c at bottom, both ways -Top reinforcing at columns and walls Slab Design – Comparisons/Conclusions Presentation Outline Serviceability Comparison Intro - Maximum Long-Term Deflections reduced by about 30% Building Overview - Both slabs meet the IBC requirement for a 2-hr fire rating - The difference in Sound Transmission Level is almost imperceptible (57-56) Redesign Goals Cost Comparison SlabDesign Design Slab 26th–Roof Shear Wall Design Construction Management 3rd–25th Floor Conclusions Acknowledgements - $36,000 will be saved if the story height is decreased by 1” Questions??? Shear Wall Design - Introduction Presentation Outline Intro Shearwall Redesign Goals Building Overview Redesign Goals Make shear walls more cost effective - Meet or improve serviceability of structure Design Method Slab Design Shear Design ShearWall Wall Design - ETABS with shear wall spreadsheets - Must meet ACI318-05 Lateral Loads 3rd–25th Floor Construction Management Conclusions - Wind Loads were found from a wind tunnel test - Wind produced base moments almost twice that of seismic Serviceability Issues Acknowledgements Questions??? - Original Shear Walls Viewed from South West - Story Drift must be less than L/600 - Building acceleration must be less than 15 milli-g Shear Wall Design – Current Layout Presentation Outline Intro Original Shear Walls Original Shear Walls Viewed From South West Viewed From North East Original Shear Walls Plan Building Overview Redesign Goals Slab Design Shear Design ShearWall Wall Design 3rd–25th Floor Construction Management Design Information 8ksi concrete below 14th floor Conclusions 6ksi concrete above 14th floor Serviceability Total deflection: 3.80” (H/1004) Acknowledgements Questions??? Original Shear Walls Viewed from South West - Torsional deflection: 2.82 milli-rad - Max story drift: H/759 Shear Wall Design – Considered Layouts Presentation Outline Modified Original Intro Additional Wall Building Overview Redesign Goals Slab Design Shear Design ShearWall Wall Design 3rd–25th Floor Construction Management Conclusions Acknowledgements Questions??? Original Shear Walls Viewed from South West Shortened Wall Core Only Opposite Wall Only Shear Wall Design – Considered Layouts Presentation Outline Intro Building Overview Redesign Goals Slab Design Shear Design ShearWall Wall Design 3rd–25th Floor Construction Management Conclusions Acknowledgements Questions??? Original Shear Walls Viewed from South West Shear Wall Design – Alternate Layout Presentation Outline Original Shear Walls Original Shear Walls Intro Viewed From North East Viewed From South West Building Overview Original Shear Walls Plan Redesign Goals Slab Design Shear Design ShearWall Wall Design 3rd–25th Floor Construction Management Conclusions Serviceability Total deflection: 3.81” (H/1002) Acknowledgements Questions??? Original Shear Walls Viewed from South West Torsional deflection: 2.49 milli-rad Shear Wall Design – Comparison/Conclusions Presentation Outline Serviceability Comparison Intro - New layout reduced torsional deflections by 12% Building Overview - Both layouts have equivalent total deflections and story drifts Redesign Goals Cost Comparison Slab Design Shear Design ShearWall Wall Design 3rd–25th Floor Construction Management Conclusions Acknowledgements Questions??? Original Shear Walls Viewed from South West Presentation Outline Intro Building Overview Redesign Goals Slab Design Shear Wall Design Construction Management Construction Management Conclusions Acknowledgements Questions??? Construction Management – Schedule Comparison Schedule Comparison Presentation Outline Intro Building Overview Redesign Goals Slab Design Shear Wall Design Construction Management Construction Management Conclusions Acknowledgements Questions??? Construction Management – Schedule Comparison Schedule Comparison Presentation Outline Intro Building Overview Redesign Goals Slab Design Shear Wall Design Construction Management Construction Management Conclusions Acknowledgements Questions??? Construction Management – Construction Issues Typical Floor Plan (Ground-11th Floor) Overall Conclusions Presentation Outline Intro Building Overview Serviceability Exceeded? More Cost Effective? Redesign Goals Slab Design Shear Wall Design Construction Management Conclusions Overall Conclusions Acknowledgements Questions??? Post-Tensioned Slab New Shear Wall Layout 30% less long term deflection 20% Cheaper 12% less torsional deflection 5% Cheaper Acknowledgements Presentation Outline Intro Thanks to: Building Overview McLaren Engineering Toll Brother’s Inc. Redesign Goals FxFowle Architects Dr. Ali Memari Slab Design Shear Wall Design The entire AE Department Faculty and Staff All of the practitioners who participated in the discussion boards All my friends and family Construction Management The Class of 2008 Conclusions Acknowledgements Acknowledgements Questions??? Presentation Outline Intro Building Overview Redesign Goals Slab Design Shear Wall Design Construction Management Conclusions Acknowledgements Questions??? Any Questions??? Presentation Outline Intro Existing Ceiling Link Beam Height: 7’-9” Reduction due to thinner slab: 1” Reduction for shear walls: 3” Potential New Ceiling Link Beam Height: 7’-5” Building Overview Redesign Goals Slab Design Shear Wall Design New York City Limit: Construction Management Conclusions Acknowledgements Questions??? 7’-0” (Gives 5” for finishes) Presentation Outline Intro Building Overview Redesign Goals Slab Design Shear Wall Design Construction Management Conclusions Acknowledgements Questions??? Presentation Outline Intro Building Overview Redesign Goals Slab Design Shear Wall Design Construction Management Conclusions Acknowledgements Questions???