Presentation 6 (Chapter 4: Conflict & Negotiation)

Project Management: A
Managerial Approach
Chapter 6 – Conflict and
Negotiation
Overview
•
•
•
•
•
Operational Definitions
Negotiation
Facilitating PM
Partnering
Conflict
© 2006 John Wiley and Sons, Inc.
2
The Nature of Negotiation - Concepts
Concepts
• (Goal) conflicts: Occur when an individual or group pursues
goals different from those of other individuals or groups.
• Negotiation: The process through which two or more parties
seek an acceptable rate of exchange for items they own or
control.
• Objective of negotiation: To reduce or resolve conflict.
• “Reduce” means no further action against another party is
contemplated. “Resolve” means all parties are satisfied to a
point below the level of frustration.
© 2006 John Wiley and Sons, Inc.
3
Facilitating the Integration of Activities
• Lateral Relations allow decisions to be made
horizontally across lines of authority
• Because each area has its own goals, integrating
activities of two or more units is certain to
produce conflicts
• These conflicts may be resolved by negotiating a
solution, if one exists, that produces gains (or
minimizes losses) for all parties
© 2006 John Wiley and Sons, Inc.
4
Negotiating a Resolution
• Approaching intraproject conflicts with a desire to
win a victory over the other parties is inappropriate
• The project manager should remember that he will
be negotiating with project stakeholders many times
in the future
• The proper objective should be to optimize the
outcome in terms of overall organizational goals
© 2006 John Wiley and Sons, Inc.
5
Partnering, Chartering, and Change
• Three situations commonly arise during projects
that require the highest level of negotiating skill
the project manager can muster:
– The use of subcontractors
– The use of input from two or more functional units to
design and develop the project’s mission
– The management of changes ordered in the project’s
deliverables and/or priorities after the project is
underway
© 2006 John Wiley and Sons, Inc.
6
Sources of Conflicts: (1) Partnering
• In recent years there has been a steady growth in the
frequency of outsourcing parts of projects
• There are many reasons for this trend:
–
–
–
–
–
–
Avoidance of litigation
Diversification of technical risk
Avoidance of capital investment
Reducing political risk on multinational projects
Shortening the duration of the project
Pooling of complimentary knowledge
© 2006 John Wiley and Sons, Inc.
7
Sources of Conflicts: (1) Partnering
• Generally, relations between the organization
carrying out a project and a subcontractor working
on the project are at best characterized as
adversarial
• Conflicting interests tend to lead both parties to
work in an atmosphere of mutual suspicion and
antagonism
• To reduce this conflict, a process for building
partnered projects can be used
© 2006 John Wiley and Sons, Inc.
8
Process for Building Partnered Projects
• 1. The parent firm must make a commitment to
partnering, select subcontractors who will do the
same, and develop a “charter”
• 2. Both parties must implement the partnering
process with agreement on:
•
•
•
•
Joint evaluation of the project’s progress
A method for resolving problems or disagreements
Acceptance of a goal for continuous improvement
Support for the process of partnering from senior management of both
parties
• 3. Both parties commit to a joint review of “project
execution” when the project is completed
© 2006 John Wiley and Sons, Inc.
9
Sources of Conflicts: (2) Chartering
• A project charter is a written agreement between the project
manager, senior management, and the functional managers
who are committing resources to the project. The charter also
often includes the client.
• The charter may take many different forms
• Typically it details the project deliverables, often including the
project’s schedule and budget
• Most projects do not have charters
– Which is one reason for observing that most projects are not
completed on specification, on time, and on budget
© 2006 John Wiley and Sons, Inc.
10
Sources of Conflicts: (2) Chartering
Chartering
(use of input from two or more functional units to
carry out project’s mission)
A written agreement between the PM, senior
management and the functional departments for a
commitment to
i. meet design intent,
ii. complete contract without need for litigation,
iii. finish project on schedule, and
iv.keep the cost growth to a percentage.
© 2006 John Wiley and Sons, Inc.
11
Sources of Conflicts: (3) Scope Change
Scope change (management of changes, after
the project is underway)
Sources for change:
i. technological uncertainty,
ii. change in the environment in which the
project/product is to be used, and
iii. other needs for change identified when the
project is under way.
© 2006 John Wiley and Sons, Inc.
12
Categories of Conflicts
• Goals: (Different goals & expectations)
– Groups working on the project may have different goals
and expectations
• Authority
– There is considerable uncertainty about who has the
authority to make decisions
• Interpersonal (conflicts)
– There are interpersonal conflicts between people who are
parties-at-interest in the project
© 2006 John Wiley and Sons, Inc.
13
Parties at Interest
- Project team
- Client
- Functional Management
- Senior management
© 2006 John Wiley and Sons, Inc.
14
Types of Conflicts
·
·
·
·
·
·
·
Over schedules
Over priorities
Over labor
Over tech. opinions
Over procedures
Over costs
Over personality
© 2006 John Wiley and Sons, Inc.
15
Issues/Types of likely conflicts during a Project
Project Formation Stage
Four fundamental issues:
– Technical objectives must be clear enough to allow detailed planning
• The breakdown structure
– The organizational structure of the project must be established to an
extent sufficient for the action plan, WBS, responsibility chart, and
network activity diagram to be prepared
• Top management support
– Commitment of resources to the project must be forthcoming from
senior management and functional managers
• Project’s level of priority
– The priority of the project relative to the priorities of the parent
organization’s other projects, must be set and communicated
• Organizational Structure
– (Who will do what…)
© 2006 John Wiley and Sons, Inc.
16
Issues/Types of likely conflicts during a Project
Project Buildup Stage
•
•
•
•
Project priorities
Schedules
Administrative procedures
Technical issues (between the project &
functional managers)
© 2006 John Wiley and Sons, Inc.
17
Issues/Types of likely conflicts during a Project
Main Program Stage
Schedules & resource redistribution
– (when something got delayed and additional
resources are needed to catch up.)
– Perceived Competition for Scarce Resources
© 2006 John Wiley and Sons, Inc.
18
Issues/Types of likely conflicts during a Project
Phase-out Stage (Implementation to Delivery Transition)
• Schedules and recovery from Schedule Slippage
(to meet the due date)
•
•
•
•
Personality clashes
Resource distribution and Cost Overruns
Lack of Documentation (Change Orders)
Anxiety
– Potential for Litigation
– About Team Dissolution / What’s Next?
• Redistribution of Remaining Resources
– Rewards and Recognition
© 2006 John Wiley and Sons, Inc.
19
Issues/Types of likely conflicts during a Project
• Figure 6.1 to see the intensity of each conflict type at
different stages
• Table 6.1 to see project conflicts by categories and
parties.
• If the above issues are not well defined or worked
out, conflicts are more likely to occur, and with
higher intensity.
© 2006 John Wiley and Sons, Inc.
20
PLC and Conflict Intensity
© 2006 John Wiley and Sons, Inc.
21
Project Conflict Categories
© 2006 John Wiley and Sons, Inc.
22
Three main requirements of project negotiation
• Conflicts must be settled without irreparable
harm to the project’s objectives
• The methods must foster honesty between
negotiators
• The solution must satisfy not only the needs of
the negotiating parties but also other parties to
the conflict, including their parent
organizations.
© 2006 John Wiley and Sons, Inc.
23
Principled Negotiation
A process of reaching agreement by following
the four guidelines:
• Separate the people from the problem
• Focus on interests not positions
• Invent options for mutual gain
• Insist on using objective criteria
© 2006 John Wiley and Sons, Inc.
24
Copyright 2006 John Wiley & Sons, Inc.
All rights reserved. Reproduction or translation of this work beyond that permitted in section 117
of the 1976 United States Copyright Act without express permission of the copyright owner is
unlawful. Request for further information should be addressed to the Permissions Department,
John Wiley & Sons, Inc. The Publisher assumes no responsibility for errors, omissions, or
damages caused by the use of these programs or from the use of the information herein.
© 2006 John Wiley and Sons, Inc.
25